JP7657261B2 - Truss and truss construction method - Google Patents
Truss and truss construction method Download PDFInfo
- Publication number
- JP7657261B2 JP7657261B2 JP2023119930A JP2023119930A JP7657261B2 JP 7657261 B2 JP7657261 B2 JP 7657261B2 JP 2023119930 A JP2023119930 A JP 2023119930A JP 2023119930 A JP2023119930 A JP 2023119930A JP 7657261 B2 JP7657261 B2 JP 7657261B2
- Authority
- JP
- Japan
- Prior art keywords
- truss
- chord
- diagonal
- crane
- diagonal member
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C3/00—Structural elongated elements designed for load-supporting
- E04C3/02—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Rod-Shaped Construction Members (AREA)
Description
本発明は、トラス構造施工の技術分野に関し、特にトラス及びトラス施工方法に関する。 The present invention relates to the technical field of truss structure construction, and in particular to trusses and truss construction methods.
トラス構造は建物で一般的に使用されている構造であり、トラスの複数の弦材が複数の三角形構造を形成できるため、トラスは良好な耐荷重性を有する。従来技術では、大型トラスの場合、施工者は通常、トラスの複数の弦材を所定の高さまで吊り上げ、その後、高所で弦材を組み立ててトラスを形成する。トラスの施工中、支保工を使用してトラス又はトラスの一部の弦材を支持する必要があり、従来技術では、大型トラスの施工には多くの支保工を使用する必要があり、その結果、トラスの施工効率が低くなり、トラスの施工コストが高くなる。 The truss structure is a commonly used structure in buildings, and the truss has good load-bearing capacity because the multiple chords of the truss can form multiple triangular structures. In the prior art, for a large truss, the builder usually hoists the multiple chords of the truss to a predetermined height, and then assembles the chords at a high altitude to form the truss. During the construction of the truss, shoring must be used to support the truss or some of the chords of the truss, and in the prior art, a large number of shoring must be used for the construction of a large truss, resulting in low truss construction efficiency and high truss construction costs.
本発明は少なくとも従来技術に存在する技術的問題の1つを解決することを目的とする。このため、本発明は、組立が容易であり、組立に必要な支保工が少なく、トラスの施工コストの削減及びトラスの施工効率の向上に有利であるトラスを提案する。 The present invention aims to solve at least one of the technical problems existing in the prior art. To this end, the present invention proposes a truss that is easy to assemble, requires less support work for assembly, and is advantageous in reducing the construction cost of the truss and improving the construction efficiency of the truss.
本発明はトラス施工方法をさらに提案する。 The present invention further proposes a truss construction method.
本発明の第1態様の実施例のトラスでは、横方向に設置され、対向する始端及び終端を有する下弦材と、垂直に設置され、底端が前記始端に接続される垂直材と、複数設置されるトラスモジュールであって、複数の前記トラスモジュールは前記下弦材の長手方向に配置され、各前記トラスモジュールは1つの上弦部及び1つの第1斜材を含み、前記上弦部は横方向に設置され、前記上弦部の一端は前記第1斜材の上端に接続され、上弦部と第1斜材との夾角は鋭角であり、異なるトラスモジュールにそれぞれ属する複数の前記上弦部は端部同士を順に接続して上弦材を形成し、前記上弦材は前記下弦材の上方に間隔をおいて設置され、前記上弦材の一端は前記垂直材の上端に接続され、前記第1斜材の底端は前記下弦材に接続されるトラスモジュールと、複数設置される第2斜材であって、前記第2斜材の上端は上弦部に接続され、前記始端から前記終端まで前記第1斜材と前記第2斜材は交互に設置され、前記第1斜材と前記第2斜材の傾斜方向は反対である第2斜材と、を含む。 In a truss according to an embodiment of the first aspect of the present invention, a lower chord member is installed laterally and has an opposing start and end, and a vertical member is installed vertically and has a bottom end connected to the start end, and a plurality of truss modules are installed, the plurality of truss modules are arranged in the longitudinal direction of the lower chord member, each of the truss modules includes one upper chord portion and one first diagonal member, the upper chord portion is installed laterally, one end of the upper chord portion is connected to the upper end of the first diagonal member, the included angle between the upper chord portion and the first diagonal member is an acute angle, and the different truss modules are arranged in the longitudinal direction of the lower chord member, each of the truss modules includes one upper chord portion and one first diagonal member, the upper chord portion is installed laterally, one end of the upper chord portion is connected to the upper end of the first diagonal member, and the included angle between the upper chord portion and the first diagonal member is an acute angle, and the different truss modules include a lower chord member and a lower diagonal member. The upper chords of the multiple upper chords, each belonging to a vertical member, are connected to each other in sequence at their ends to form an upper chord, the upper chord is installed above the lower chord at a distance, one end of the upper chord is connected to the upper end of the vertical member, and the bottom end of the first diagonal member is connected to the lower chord; and a truss module is installed in multiple second diagonal members, the top end of the second diagonal member is connected to the upper chord, the first diagonal member and the second diagonal member are installed alternately from the starting end to the ending end, and the inclination directions of the first diagonal member and the second diagonal member are opposite to each other.
本発明の第2態様の実施例のトラス施工方法では、前記下弦材を支保工の上部に取り付け、前記下弦材を横方向に設置するステップと、前記垂直材の底部を前記下弦材の始端と接続し、前記垂直材を垂直に設置するステップと、前記始端から前記終端までの方向において、下弦材に前記トラスモジュールと前記第2斜材を交互に取り付けるステップと、を含む。 The truss construction method according to the second embodiment of the present invention includes the steps of attaching the lower chord to the top of the support and installing the lower chord horizontally, connecting the bottom of the vertical member to the start end of the lower chord and installing the vertical member vertically, and attaching the truss modules and the second diagonal members alternately to the lower chord in the direction from the start end to the end end.
本発明のいくつかの実施例では、前記トラス施工方法は、前記トラスモジュールを前記下弦材に取り付ける前に、前記トラスモジュールを組み立てるステップをさらに含み、前記トラスモジュールを組み立てるステップは、支持フレームを使用して前記第1斜材を支持し、前記第1斜材を傾斜させて設置するステップと、前記上弦部を前記第1斜材の上方に吊り上げ、前記上弦部を横方向に設置するステップと、前記上弦部の一端を前記第1斜材の上端と接続するステップと、を含む。 In some embodiments of the present invention, the truss construction method further includes assembling the truss module before attaching the truss module to the lower chord, and assembling the truss module includes supporting the first diagonal member using a support frame and installing the first diagonal member at an angle, hoisting the upper chord above the first diagonal member and installing the upper chord laterally, and connecting one end of the upper chord to the upper end of the first diagonal member.
本発明のいくつかの実施例では、前記下弦材は端部同士が順に接続される複数の下弦部を含み、前記下弦材は前記下弦部に接続される第1連結部材をさらに含み、前記第1斜材と前記第2斜材はいずれも第1連結部材と接続可能であり、前記下弦材を前記支保工の上部に取り付けるステップは、複数の前記支保工を設置し、複数の前記支保工を水平方向に間隔をおいて配置するステップと、複数の前記支保工で下弦材を共同で支え、各前記第1連結部材を1つの前記支保工の上方にそれぞれ位置させるステップと、を含む。 In some embodiments of the present invention, the lower chord includes a plurality of lower chord sections whose ends are connected in sequence, the lower chord further includes a first connecting member connected to the lower chord sections, the first diagonal member and the second diagonal member are both connectable to the first connecting member, and the step of attaching the lower chord to the upper part of the shoring includes the steps of installing a plurality of the shorings and arranging the plurality of the shorings horizontally at intervals, and supporting the lower chord together with the plurality of the shorings and positioning each of the first connecting members above one of the shorings.
本発明のいくつかの実施例では、前記垂直材と接続するための前記トラスモジュールを前記下弦材に取り付けるステップは、クレーンを使用して前記トラスモジュールを所定の高さまで吊り上げるステップと、前記クレーンと前記トラスモジュールとの接続を維持しながら、前記第1斜材の底端を前記下弦材と溶接し、前記上弦部を前記垂直材の上端と溶接するステップと、前記クレーンと前記トラスモジュールとの接続を解除するステップと、を含む。 In some embodiments of the invention, the step of attaching the truss module to the lower chord for connection to the vertical member includes the steps of: hoisting the truss module to a predetermined height using a crane; welding the bottom end of the first diagonal member to the lower chord and welding the top chord to the top end of the vertical member while maintaining the connection between the crane and the truss module; and disconnecting the connection between the crane and the truss module.
本発明のいくつかの実施例では、前記垂直材と間隔をおいて設置される前記トラスモジュールを前記下弦材に取り付けるステップは、クレーンを使用して前記トラスモジュールを所定の高さまで吊り上げるステップと、前記クレーンと現在吊り上げられている前記トラスモジュールとの接続を維持しながら、現在前記クレーンにより吊り上げられている前記トラスモジュールを前記下弦材に取り付けられた前記トラスモジュールと溶接し、現在クレーンにより吊り上げられている前記トラスモジュールを前記下弦材と溶接するステップと、前記クレーンと現在前記クレーンに接続されている前記トラスモジュールとの接続を解除するステップと、を含む。 In some embodiments of the present invention, the step of attaching the truss module, which is spaced apart from the vertical members, to the lower chord includes the steps of: lifting the truss module to a predetermined height using a crane; while maintaining a connection between the crane and the currently lifted truss module, welding the truss module currently lifted by the crane to the truss module attached to the lower chord and welding the truss module currently lifted by the crane to the lower chord; and disconnecting the crane from the truss module currently connected to the crane.
本発明のいくつかの実施例では、前記第2斜材を前記下弦材に取り付けるステップは、クレーンを使用して前記第2斜材を所定の高さまで吊り上げるステップと、前記クレーンと前記第2斜材との接続を維持しながら、前記第2斜材の上端を前記上弦部と溶接し、前記第2斜材の底端を前記下弦材と溶接するステップと、前記クレーンと前記第2斜材との接続を解除するステップと、を含む。 In some embodiments of the present invention, the step of attaching the second diagonal member to the lower chord includes the steps of using a crane to hoist the second diagonal member to a predetermined height, welding the top end of the second diagonal member to the upper chord and welding the bottom end of the second diagonal member to the lower chord while maintaining the connection between the crane and the second diagonal member, and disconnecting the connection between the crane and the second diagonal member.
本発明のいくつかの実施例では、前記下弦材を前記支保工の上部に取り付けるステップは、前記支保工の上部に当て板を取り付けるステップと、前記下弦材を前記当て板の上方に配置するステップと、を含む。 In some embodiments of the present invention, the step of attaching the bottom chord to the top of the support includes the steps of attaching a backing plate to the top of the support and positioning the bottom chord above the backing plate.
本発明のトラス及びトラス施工方法は少なくとも以下の有益な効果を有する。トラスの上弦材は異なるトラスモジュールにそれぞれ属する複数の上弦部を互いに接続して形成されるため、トラスの組立中、トラスモジュールの第1斜材を下弦材と固定すると、トラスモジュールは下弦材に対して固定でき、上弦部も固定できる。下弦材に取り付けられるトラス数の増加に伴い、上弦材は徐々に成形される。従って、下弦材を支持するための支保工を除き、該トラスを組み立てる時、上弦材又は上弦部を支持するための支保工を別途設置する必要がなく、トラスの施工に必要な支保工の低減に有利であり、それによってトラスの施工容易性を向上させ、トラスの施工コストを削減する。 The truss and truss construction method of the present invention have at least the following beneficial effects: The upper chord of the truss is formed by connecting multiple upper chords belonging to different truss modules to each other, so that during the assembly of the truss, when the first diagonal member of the truss module is fixed to the lower chord, the truss module can be fixed to the lower chord and the upper chord can also be fixed. As the number of trusses attached to the lower chord increases, the upper chord is gradually formed. Therefore, except for the support for supporting the lower chord, there is no need to install a separate support for supporting the upper chord or the upper chord when assembling the truss, which is advantageous to reducing the support required for the construction of the truss, thereby improving the ease of construction of the truss and reducing the construction costs of the truss.
本発明の付加的な態様及び利点は、以下の説明において部分的に与えられ、一部は以下の説明から明らかになるか、又は本発明の実施を通じて把握される。 Additional aspects and advantages of the invention are set forth in part in the description that follows, and in part will be apparent from the description that follows, or may be learned through the practice of the invention.
以下、図面及び実施例を参照しながら本発明をさらに説明する。 The present invention will be further described below with reference to the drawings and examples.
以下、本発明の実施例を詳細に説明し、前記実施例は図面において例示されており、全明細書を通して、同じ又は類似する符号は同じ又は類似する素子、或いは同じ又は類似する機能を有する素子を示す。以下、図面を参照しながら説明される実施例は例示的なものであり、本発明を解釈するためのものに過ぎず、本発明を限定しないと理解すべきである。 The following describes in detail the embodiments of the present invention, which are illustrated in the drawings, and throughout the specification, the same or similar reference numerals refer to the same or similar elements, or elements having the same or similar functions. It should be understood that the embodiments described below with reference to the drawings are merely illustrative and are for the purpose of interpreting the present invention, and do not limit the present invention.
本発明の説明では、方位説明について、例えば上、下、前、後、左、右等で指示される方位又は位置関係は図示に基づく方位又は位置関係であり、本発明を簡単に説明し、且つ説明を簡素化するためのものに過ぎず、係る装置又は素子が必ず特定の方位を有したり、特定の方位で構成及び操作したりすることを指示又は暗示するわけではないことを理解する必要があり、従って、本発明を限定しないと理解すべきである。 In the description of the present invention, with regard to the orientation, for example, the orientation or positional relationship indicated by up, down, front, back, left, right, etc. is based on the illustration, and is merely for the purpose of easily explaining and simplifying the present invention, and it should be understood that it does not indicate or imply that the device or element in question necessarily has a specific orientation or is constructed and operated in a specific orientation, and therefore should not be understood to limit the present invention.
本発明の説明では、若干の意味は1つ以上であり、複数の意味は2つ以上であり、超え、未満、超過等は基準となる数を含まないと理解され、以上、以下、以内等は基準となる数を含むと理解される。第1、第2が言及される場合、技術的特徴を区分することを目的とするに過ぎず、相対重要性を指示又は暗示したり指示される技術的特徴の数を暗黙的に示したり指示される技術的特徴の順序関係を暗黙的に示したりしないことを理解すべきである。 In the description of this invention, some means one or more, plural means two or more, more than, less than, exceeding, etc. are understood to exclude the reference number, and more than, less than, within, etc. are understood to include the reference number. When first and second are mentioned, it should be understood that they are merely intended to distinguish technical features and do not indicate or imply relative importance, or imply the number of technical features indicated, or imply an ordering relationship of the technical features indicated.
本発明の説明では、特に明確な限定がない限り、設置、取り付け、接続等の用語は広義に理解されるべきであり、当業者は技術的解決手段の具体的な内容に応じて本発明における上記用語の具体的な意味を決定することができる。 In describing the present invention, unless otherwise specified, terms such as installation, mounting, connection, etc. should be understood in a broad sense, and a person skilled in the art can determine the specific meaning of the above terms in the present invention according to the specific content of the technical solution.
図1、及び図3~図8は本発明の一実施例におけるトラスを示す。トラスは下弦材103、トラスモジュール205、垂直材106及び第2斜材105を含む。トラスにおいて、トラスモジュール205は複数設置され、複数のトラスモジュール205は下弦材103の長手方向に配置され、図6に示すように、トラスモジュール205は第1斜材104及び上弦部206を含む。 Figures 1 and 3 to 8 show a truss in one embodiment of the present invention. The truss includes a lower chord 103, a truss module 205, a vertical member 106, and a second diagonal member 105. In the truss, a plurality of truss modules 205 are installed, and the plurality of truss modules 205 are arranged in the longitudinal direction of the lower chord 103. As shown in Figure 6, the truss module 205 includes a first diagonal member 104 and an upper chord 206.
図5と図6を比較してわかるように、トラスモジュール205は「7」字形であり、上弦部206は横方向に設置され、上弦部206の一端は第1斜材104の上端に接続され、上弦部206と第1斜材104との夾角は鋭角である。上弦部206の横方向設置とは、具体的には、上弦部206が水平に設置されることを指し、別のいくつかの実施例では、上弦部206は傾斜してもよく、上弦部206の横方向設置とは、上弦部206と水平面との夾角が20°未満であることを指す。本発明では、ほかの弦部又は弦材の横方向設置の定義は上弦部206の横方向設置の定義と同じであり、以下では重複説明を省略する。図1と図8を比較してわかるように、異なるトラスモジュール205にそれぞれ属する複数の上弦部206は端部同士を順に接続して上弦材102を形成する。 5 and 6, the truss module 205 is in the shape of a "7", the upper chord 206 is installed horizontally, one end of the upper chord 206 is connected to the upper end of the first diagonal member 104, and the included angle between the upper chord 206 and the first diagonal member 104 is an acute angle. The horizontal installation of the upper chord 206 specifically refers to the upper chord 206 being installed horizontally, and in some other embodiments, the upper chord 206 may be inclined, and the horizontal installation of the upper chord 206 refers to the included angle between the upper chord 206 and the horizontal plane being less than 20°. In the present invention, the definition of the horizontal installation of other chords or chord members is the same as the definition of the horizontal installation of the upper chord 206, and the overlapping description will be omitted below. As can be seen from the comparison of FIG. 1 and FIG. 8, the upper chords 206 belonging to different truss modules 205 are connected at their ends in sequence to form the upper chord member 102.
下弦材103は横方向に設置され、下弦材103は上弦材102の下方に間隔をおいて設置される。図5に示すように、下弦材103は端部同士が順に接続される複数の下弦部201を含み、また、下弦材103は端部連結部材207をさらに含み、端部連結部材207はそのうちの1つの下弦部201に接続され、下弦材103の一端に位置する。垂直材106の底端は下弦材103の一端に接続され、具体的には、垂直材106の底端は端部連結部材207に接続される。図5及び図6に示すように、垂直材106の上端は1番目のトラスモジュール205の上弦部206と接続することに用いられ、それによって垂直材106の上端と上弦材102の一端との接続を実現する。 The lower chord 103 is installed horizontally and is installed below the upper chord 102 at a distance. As shown in FIG. 5, the lower chord 103 includes a plurality of lower chords 201 whose ends are connected in sequence, and further includes an end connector 207, which is connected to one of the lower chords 201 and is located at one end of the lower chord 103. The bottom end of the vertical member 106 is connected to one end of the lower chord 103, specifically, the bottom end of the vertical member 106 is connected to the end connector 207. As shown in FIG. 5 and FIG. 6, the upper end of the vertical member 106 is used to connect to the upper chord 206 of the first truss module 205, thereby realizing the connection between the upper end of the vertical member 106 and one end of the upper chord 102.
図1に示すように、第1斜材104及び第2斜材105はいずれも上弦材102と下弦材103との間に位置し、第1斜材104の底端及び第2斜材105の底端はいずれも下弦材103に接続され、第2斜材105の上端及び第1斜材104の上端はいずれも上弦材102に接続される。そして、隣接する1つの第1斜材104と1つの第2斜材105の傾斜方向は反対である。本発明における第1斜材104と第2斜材105の傾斜方向が反対であることは、第1斜材104の上端が第1斜材104の底端の左側にあると、第2斜材105の上端が第2斜材105の底端の右側にあり、第1斜材104の上端が第1斜材104の底端の右側にあると、第2斜材105の上端が第2斜材105の底端の左側にあることを指す。 As shown in FIG. 1, the first diagonal member 104 and the second diagonal member 105 are both located between the upper chord member 102 and the lower chord member 103, the bottom end of the first diagonal member 104 and the bottom end of the second diagonal member 105 are both connected to the lower chord member 103, and the top end of the second diagonal member 105 and the top end of the first diagonal member 104 are both connected to the upper chord member 102. The inclination directions of one adjacent first diagonal member 104 and one adjacent second diagonal member 105 are opposite. In the present invention, the inclination directions of the first diagonal member 104 and the second diagonal member 105 are opposite to each other, meaning that when the upper end of the first diagonal member 104 is to the left of the bottom end of the first diagonal member 104, the upper end of the second diagonal member 105 is to the right of the bottom end of the second diagonal member 105, and when the upper end of the first diagonal member 104 is to the right of the bottom end of the first diagonal member 104, the upper end of the second diagonal member 105 is to the left of the bottom end of the second diagonal member 105.
下弦材103の垂直材106と接続するための端を始端(始端は図面における下弦材103の左端に対応する)と呼び、下弦材103の始端と対向する端を終端(終端は図面における下弦材103の右端に対応する)と呼ぶ場合、始端から終端までの方向において、第1斜材104と第2斜材105は交互に設置される(図8参照)。図8に示すように、第1斜材104と第2斜材105が交互に設置されることは、始端から終端まで、隣接する2つの第2斜材105の間に1つの第1斜材104が設置され、隣接する2つの第1斜材104の間に1つの第2斜材105が設置されることを意味する。 If the end of the lower chord 103 for connecting to the vertical member 106 is called the start end (the start end corresponds to the left end of the lower chord 103 in the drawing), and the end of the lower chord 103 opposite the start end is called the end end (the end end corresponds to the right end of the lower chord 103 in the drawing), the first diagonal member 104 and the second diagonal member 105 are installed alternately in the direction from the start end to the end end (see Figure 8). As shown in Figure 8, the first diagonal member 104 and the second diagonal member 105 are installed alternately, which means that one first diagonal member 104 is installed between two adjacent second diagonal members 105, and one second diagonal member 105 is installed between two adjacent first diagonal members 104, from the start end to the end end.
上記トラスに基づいて、本発明はトラス施工方法を提供し、図2に示すように、該施工方法は、
下弦材103を支保工101の上部に取り付け、下弦材103を横方向に設置するステップS10と、
垂直材106の底部を下弦材103の始端と接続し、垂直材106を垂直に設置するステップS20と、
始端から終端までの方向において、下弦材103にトラスモジュール205と第2斜材105を交互に取り付けるステップS30と、を含む。
Based on the above truss, the present invention provides a truss construction method, as shown in FIG. 2, the construction method includes:
Step S10 of attaching the lower chord 103 to the upper part of the support 101 and installing the lower chord 103 laterally;
Step S20: connecting the bottom of the vertical member 106 to the beginning of the lower chord member 103 and installing the vertical member 106 vertically;
The method includes a step S30 of alternately attaching the truss modules 205 and the second diagonal members 105 to the lower chord member 103 in a direction from the start end to the end end.
上記方法に係る支保工101は、荷重を支持するためのフレームとして理解でき、支保工101は建築分野で一般的に使用されている補助ツーリングであり、支保工101の構造については本発明では具体的に説明しない。図3~図8に示すように、トラスを支持するための支保工101は複数設置されてもよく、複数の支保工101は水平方向に間隔をおいて設置される。トラス組立を完了し、トラスと建物のほかの部分とを互いに固定した後、支保工101を撤去し、それによってトラスを片持ちトラスとする。 The shoring 101 in the above method can be understood as a frame for supporting a load, and the shoring 101 is an auxiliary tooling commonly used in the construction field, and the structure of the shoring 101 is not specifically described in the present invention. As shown in Figures 3 to 8, multiple shoring 101 for supporting the truss may be installed, and the multiple shoring 101 are installed at intervals in the horizontal direction. After completing the truss assembly and fixing the truss to other parts of the building, the shoring 101 is removed, thereby making the truss a cantilever truss.
上記方法は図3~図8と併せて理解することができる。図3は支保工101の模式図であり、下弦材103を支保工101の上部に取り付けた後(即ち、ステップS10を完了した後)、下弦材103と支保工101との相対位置は図4に示される(下弦材103は端部連結部材207及び複数の下弦部201を含む)。図4をもとに、垂直材106を下弦材103と接続した後(即ち、ステップS20を完了した後)、下弦材103、及び垂直材106の状態は図5に示される。以下、ステップS30におけるトラスモジュール205及び第2斜材105の取り付けを説明する。順に図5及び図6に参照されるように、垂直材106の取り付けを完了した後、施工者はまず1つのトラスモジュール205を下弦材103の上方に吊り上げ、その後、該トラスモジュール205の上弦部206を垂直材106の上端と接続し、トラスモジュール205の第1斜材104の底端を下弦材103と接続する。このようにして、トラスモジュール205と下弦材103、垂直材106が相対的に固定される。さらに順に図6及び図7に参照されるように、1番目のトラスモジュール205の取り付けを完了した後、施工者は1つの第2斜材105を下弦材103の上方に吊り上げ、次に、第2斜材105の底端を下弦材103と接続し、第2斜材105の上端をトラスモジュール205の上弦部206と接続する。 The above method can be understood in conjunction with Figures 3 to 8. Figure 3 is a schematic diagram of the support 101, and after the lower chord 103 is attached to the top of the support 101 (i.e., after completing step S10), the relative position of the lower chord 103 and the support 101 is shown in Figure 4 (the lower chord 103 includes an end connecting member 207 and multiple lower chord portions 201). Based on Figure 4, after the vertical member 106 is connected to the lower chord 103 (i.e., after completing step S20), the state of the lower chord 103 and the vertical member 106 is shown in Figure 5. The installation of the truss module 205 and the second diagonal member 105 in step S30 will be described below. 5 and 6, after completing the installation of the vertical member 106, the builder first lifts one truss module 205 above the lower chord member 103, then connects the upper chord portion 206 of the truss module 205 to the upper end of the vertical member 106, and connects the bottom end of the first diagonal member 104 of the truss module 205 to the lower chord member 103. In this way, the truss module 205, the lower chord member 103, and the vertical member 106 are fixed relative to each other. Further, as shown in FIG. 6 and FIG. 7, after completing the installation of the first truss module 205, the builder lifts one second diagonal member 105 above the lower chord member 103, then connects the bottom end of the second diagonal member 105 to the lower chord member 103, and connects the top end of the second diagonal member 105 to the upper chord portion 206 of the truss module 205.
1番目のトラスモジュール205及び1番目の第2斜材105の取り付けを完了した後、残りのトラスモジュール205及び第2斜材105を交互に取り付ける。複数のトラスモジュール205及び複数の第2斜材105を取り付けた後、トラスの状態は図8に示される。なお、図7及び図8に示すように、1番目のトラスモジュール205(垂直材106に接続されるトラスモジュール205)を除き、残りのトラスモジュール205は取り付け時に、垂直材106と接続されるのではなく、実際に前に取り付けられたトラスモジュール205と接続される。 After completing the installation of the first truss module 205 and the first second diagonal member 105, the remaining truss modules 205 and second diagonal members 105 are installed alternately. After the installation of the multiple truss modules 205 and multiple second diagonal members 105, the state of the truss is as shown in FIG. 8. Note that, as shown in FIG. 7 and FIG. 8, except for the first truss module 205 (the truss module 205 connected to the vertical member 106), the remaining truss modules 205 are not connected to the vertical member 106 when installed, but are actually connected to the previously installed truss module 205.
従来技術では、トラスを組み立てるために、通常、まず支保工101を使用して上弦材102及び下弦材103を支持し、その後、上弦材102と下弦材103との間に斜材を取り付ける必要がある。一方、本発明は、支保工101を使用して上弦材102を下弦材103の上方に支持するのではなく、トラスモジュール205の接合によって複数の上弦部206を組み立てて上弦材102を形成する。本発明の施工方法は、上弦材102を支持するための支保工101を省くことができ、それによって施工中に使用される支保工101の数を低減させ、さらにトラスの施工コストを削減し、トラスの施工効率を向上させる。 In the prior art, in order to assemble a truss, it is usually necessary to first use shoring 101 to support the upper chord 102 and the lower chord 103, and then attach diagonal members between the upper chord 102 and the lower chord 103. On the other hand, in the present invention, instead of using shoring 101 to support the upper chord 102 above the lower chord 103, the upper chord 102 is formed by assembling multiple upper chords 206 by joining truss modules 205. The construction method of the present invention can omit the shoring 101 for supporting the upper chord 102, thereby reducing the number of shoring 101 used during construction, further reducing the construction cost of the truss, and improving the construction efficiency of the truss.
以下、本発明の施工方法のほかの詳細を追加する。 Further details on the construction method of the present invention are added below.
図3に示すように、一実施例では、下弦材103は複数の下弦部201を含み、各下弦部201は1つの第1連結部材202を含む。第1連結部材202は第1溶接部203及び第2溶接部204を含み、第1溶接部203と第2溶接部204の底端は接続され、第1溶接部203の上端と第2溶接部204の上端は間隔をおいて設置され、それによって第1連結部材202を「V」字形にする。図8に示すように、第1溶接部203はトラスモジュール205の第1斜材104の底端と溶接することに用いられ、第2溶接部204は第2斜材105の底端と溶接することに用いられる。 3, in one embodiment, the lower chord 103 includes a plurality of lower chords 201, each of which includes a first connecting member 202. The first connecting member 202 includes a first weld 203 and a second weld 204, and the bottom ends of the first weld 203 and the second weld 204 are connected, and the top end of the first weld 203 and the top end of the second weld 204 are spaced apart, thereby making the first connecting member 202 "V" shaped. As shown in FIG. 8, the first weld 203 is used to weld to the bottom end of the first diagonal 104 of the truss module 205, and the second weld 204 is used to weld to the bottom end of the second diagonal 105.
下弦材103が複数の下弦部201を含む場合、一実施例では、上記言及されたステップS10における「下弦材103を支保工101の上部に取り付ける」は、具体的には、
複数の支保工101を設置し、複数の支保工101を水平方向に間隔をおいて配置する(図3参照)ステップS101と、
複数の支保工101で下弦材103を共同で支え、各第1連結部材202を1つの支保工101の上方にそれぞれ位置させる(図5参照)ステップS102と、を含む。
In the case where the lower chord 103 includes a plurality of lower chord portions 201, in one embodiment, the above-mentioned step S10 of “attaching the lower chord 103 to the upper portion of the support 101” specifically means:
Step S101: Installing a plurality of shoring structures 101 and arranging the plurality of shoring structures 101 at intervals in the horizontal direction (see FIG. 3 );
The method includes step S102 in which a plurality of supports 101 jointly support the lower chord 103 and each first connecting member 202 is positioned above one of the supports 101 (see FIG. 5).
第1連結部材202は第1斜材104と第2斜材105を接続することに用いられ、従って、第1連結部材202は下弦部201の受ける力の集中部である。第1連結部材202を1つの支保工101の上方にそれぞれ設置することは、支保工101が下弦部201の受ける力の集中点を支持できることを意味し、このようにして、支保工101が下弦材103を全体的に支持する効果を向上させ、トラス施工中の安全性を向上させることに有利である。 The first connecting member 202 is used to connect the first diagonal member 104 and the second diagonal member 105, and therefore the first connecting member 202 is the part where the force of the lower chord 201 is concentrated. Installing the first connecting member 202 above one shoring 101 means that the shoring 101 can support the point where the force of the lower chord 201 is concentrated, thus improving the effect of the shoring 101 in supporting the lower chord 103 as a whole, which is advantageous in improving safety during truss construction.
一実施例では、「下弦材103を支保工101の上部に取り付ける」は、まず、支保工101の上部に当て板(当て板は図示せず)を取り付け、その後、下弦材103を当て板の上方に配置するステップをさらに含む。支保工101の上部に当て板を取り付けることで、トラスの位置要件を満たすように下弦材103の標高を容易に調整できる。なお、施工者はさらに下弦材103の標高要件を満たすように当て板の厚さ又は当て板の数を調整することができる。 In one embodiment, "attaching the lower chord 103 to the top of the shoring 101" further includes the steps of first attaching a backing plate (backing plate not shown) to the top of the shoring 101, and then positioning the lower chord 103 above the backing plate. By attaching the backing plate to the top of the shoring 101, the elevation of the lower chord 103 can be easily adjusted to meet the positional requirements of the truss. Note that the builder can further adjust the thickness of the backing plate or the number of backing plates to meet the elevation requirements of the lower chord 103.
トラスモジュール205を下弦材103に取り付ける前に、まずトラスモジュール205を製造する必要がある。トラスモジュール205を組み立てるステップとステップS10、ステップS20の時間順について厳密な要件はなく、例えば、トラスモジュール205はステップS20の後に組み立てられてもよく、ステップS10の前に組み立てられてもよい。一実施例では、トラスモジュール205を組み立てるステップは具体的には、
支持フレーム303を使用して第1斜材104を支持し、第1斜材104を傾斜させて設置するステップS01と、
上弦部206を第1斜材104の上方に吊り上げ、上弦部206を横方向に設置するステップS02と、
上弦部206の一端を第1斜材104の上端と接続するステップS03と、を含む。
Before the truss module 205 is attached to the lower chord 103, the truss module 205 needs to be manufactured first. There is no strict requirement on the time sequence of the step of assembling the truss module 205 and steps S10 and S20, for example, the truss module 205 may be assembled after step S20 or before step S10. In one embodiment, the step of assembling the truss module 205 specifically includes:
Step S01 of supporting the first diagonal member 104 using the support frame 303 and installing the first diagonal member 104 at an incline;
Step S02 of lifting the upper chord portion 206 above the first diagonal member 104 and installing the upper chord portion 206 in a horizontal direction;
The step S03 includes connecting one end of the upper chord portion 206 to the upper end of the first diagonal member 104.
トラスモジュール205を組み立てるプロセスは図9~図11と併せて理解することができる。トラスモジュール205の組立中に使用される支持フレーム303は、下弦材103を支持するための支保工101とは異なる。支持フレーム303は第1斜材104を支持した後(ステップS01に対応する)、第1斜材104の状態は図9に示され、地面304は第1斜材104の底端に当接し、支持フレーム303は第1斜材104の側部に当接して第1斜材104を支持する。その後、施工者はクレーンを使用して上弦部206を第1斜材104の上方に吊り上げ(図10参照)、その後、上弦部206の一端を第1斜材104の上端と接続する(図11参照)ことができる。図面にはクレーン全体が示されず、クレーンのフック301のみが示され、フック301はロープ302を引っ掛け、ロープ302はさらにトラスモジュール205に接続され、フック301は上昇すると、トラスモジュール205を吊り上げることができる。ステップS03を実行する時、施工者は上弦部206と第1斜材104を仮接続し、後続でステップS30を実行する時、上弦部206と第1斜材104を溶接する。仮接続の手段は図11を参照でき、施工者は仮接続板306及び2つの手動式チェーンホイスト305を設置でき、手動式チェーンホイスト305は上弦部206及び第1斜材104を引っ張り、仮接続板306はボルトを介して上弦部206、第1斜材104に接続される。図12に示すように、トラスモジュールの組立を完了した後、施工者はクレーンを使用してトラスモジュール205全体を吊り上げてトラスモジュール205を支持フレーム303から分離することができる。トラスモジュール205を支持フレーム303から分離した後、トラスモジュール205は下弦材103の上方に吊り上げられる(図6参照)。 The process of assembling the truss module 205 can be understood in conjunction with Figures 9 to 11. The support frame 303 used during the assembly of the truss module 205 is different from the shoring 101 for supporting the lower chord 103. After the support frame 303 supports the first diagonal member 104 (corresponding to step S01), the state of the first diagonal member 104 is shown in Figure 9, where the ground 304 abuts against the bottom end of the first diagonal member 104, and the support frame 303 abuts against the side of the first diagonal member 104 to support the first diagonal member 104. Then, the builder can use a crane to hoist the upper chord 206 above the first diagonal member 104 (see Figure 10), and then connect one end of the upper chord 206 to the upper end of the first diagonal member 104 (see Figure 11). The drawing does not show the whole crane, but only the hook 301 of the crane, the hook 301 hooks the rope 302, the rope 302 is further connected to the truss module 205, the hook 301 can lift the truss module 205 when it rises. When performing step S03, the builder temporarily connects the upper chord 206 and the first diagonal member 104, and when performing step S30 subsequently, the upper chord 206 and the first diagonal member 104 are welded. The temporary connection means can be seen in FIG. 11, the builder can install a temporary connection plate 306 and two manual chain hoists 305, the manual chain hoists 305 pull the upper chord 206 and the first diagonal member 104, and the temporary connection plate 306 is connected to the upper chord 206 and the first diagonal member 104 through a bolt. As shown in FIG. 12, after completing the assembly of the truss module, the builder can use a crane to lift the entire truss module 205 and separate the truss module 205 from the support frame 303. After the truss module 205 is separated from the support frame 303, the truss module 205 is lifted above the lower chord 103 (see FIG. 6).
上弦材102が複数の上弦部206からなる場合、各上弦部206は第2連結部材208を含む。図10に示すように、第2連結部材208もV字形であり、第2連結部材208は第3溶接部209及び第4溶接部210を含む。第3溶接部209は第1斜材104の上端と溶接することに用いられ、第4溶接部210は第2斜材105の上端と溶接することに用いられる。 When the upper chord member 102 is composed of multiple upper chord portions 206, each upper chord portion 206 includes a second connecting member 208. As shown in FIG. 10, the second connecting member 208 is also V-shaped, and the second connecting member 208 includes a third weld portion 209 and a fourth weld portion 210. The third weld portion 209 is used to weld to the upper end of the first diagonal member 104, and the fourth weld portion 210 is used to weld to the upper end of the second diagonal member 105.
本発明では、異なる弦材又は弦部間の接続手段はいずれも溶接に設定されてもよい。一実施例では、垂直材106と接続するためのトラスモジュール205(図6~図8では、左から1番目のトラスモジュール205)を下弦材103に取り付けるステップは、
クレーンを使用してトラスモジュール205を所定の高さまで吊り上げるステップS301と、
クレーンとトラスモジュール205との接続を維持しながら、第1斜材104の底端を下弦材103と溶接し、上弦部206を垂直材106の上端と溶接するステップS302と、
クレーンとトラスモジュール205との接続を解除するステップS303と、によって実現され得る。
In the present invention, the connection means between different chords or chord sections may be set to be welding. In one embodiment, the step of attaching a truss module 205 (the first truss module 205 from the left in Figs. 6 to 8) to the lower chord 103 for connection with the vertical member 106 is as follows:
Step S301: hoisting the truss module 205 to a predetermined height using a crane;
Step S302: welding the bottom end of the first diagonal member 104 to the lower chord member 103 and welding the upper chord member 206 to the upper end of the vertical member 106 while maintaining the connection between the crane and the truss module 205;
This can be achieved by step S303 of disconnecting the crane from the truss module 205.
上記設置形態では、トラスモジュール205と下弦材103及び垂直材106との溶接中、クレーンはトラスモジュール205と接続し続け、クレーンはトラスモジュール205に対して一定の支持作用を発揮し、施工者は支保工101を別途使用してトラスモジュール205を支持する必要がない。 In the above installation configuration, while the truss module 205 is being welded to the lower chord 103 and the vertical members 106, the crane remains connected to the truss module 205, and the crane provides a certain level of support to the truss module 205, eliminating the need for the contractor to use separate supports 101 to support the truss module 205.
同様に、垂直材106と間隔をおいて設置されるトラスモジュール205を下弦材103に取り付けるステップは、
クレーンを使用してトラスモジュール205を所定の高さまで吊り上げるステップS304と、
クレーンと現在クレーンに接続されているトラスモジュール205との接続を維持しながら、現在クレーンにより吊り上げられているトラスモジュール205を下弦材103に取り付けられたトラスモジュール205と溶接し、現在クレーンにより吊り上げられているトラスモジュール205を下弦材103と溶接するステップS305と、
クレーンと現在クレーンに接続されているトラスモジュール205との接続を解除するステップS306と、によって実現され得る。
Similarly, the step of attaching the truss module 205 spaced apart from the upright member 106 to the bottom chord member 103 includes the steps of:
Step S304 of lifting the truss module 205 to a predetermined height using a crane;
Step S305: while maintaining the connection between the crane and the truss module 205 currently connected to the crane, welding the truss module 205 currently being lifted by the crane to the truss module 205 attached to the lower chord 103, and welding the truss module 205 currently being lifted by the crane to the lower chord 103;
and step S306 of disconnecting the crane from the truss module 205 currently connected to the crane.
同様に、第2斜材105を取り付けるステップは、
クレーンを使用して第2斜材105を所定の高さまで吊り上げるステップS307と、
クレーンと第2斜材105との接続を維持しながら第2斜材105の上端を上弦部206と溶接し、第2斜材105の底端を下弦材103と溶接するステップS308と、
クレーンと第2斜材105との接続を解除するステップS309と、によって実現され得る。
Similarly, the step of attaching the second diagonal member 105 includes:
Step S307 of hoisting the second diagonal member 105 to a predetermined height using a crane;
Step S308: welding the upper end of the second diagonal member 105 to the upper chord 206 while maintaining the connection between the crane and the second diagonal member 105, and welding the bottom end of the second diagonal member 105 to the lower chord 103;
This can be achieved by step S309 of disconnecting the crane from the second diagonal member 105.
ステップS307~ステップS309によって第2斜材105の取り付けを実現することで、クレーンは第2斜材105に対して一定の支持作用を発揮し、支保工101によって第2斜材105を支持する必要がないという利点を持つ。 By installing the second diagonal member 105 through steps S307 to S309, the crane can provide a certain level of support for the second diagonal member 105, and this has the advantage that there is no need to support the second diagonal member 105 with the shoring 101.
なお、本発明は「S10」、「S301」等の番号で施工方法の異なるステップを示すが、これらの番号は主に施工方法の説明を容易にするためのものであり、特に断らない限り、2つの番号の大きさは2つのステップの順序を厳密に限定しない。 In the present invention, different steps of the construction method are indicated by numbers such as "S10" and "S301", but these numbers are primarily intended to facilitate the explanation of the construction method, and unless otherwise specified, the size of the two numbers does not strictly limit the order of the two steps.
本発明の説明では、「1つの実施例」、「いくつかの実施例」、「例示的な実施例」、「例」、「具体例」、又は「いくつかの例」等の用語を参照する説明は、該実施例又は例と組み合わせて説明される具体的な特徴、構造、材料又は特性が本発明の少なくとも1つの実施例又は例に含まれることを意味する。本明細書では、上記用語についての例示的な表現は必ずしも同じ実施例又は例を指すわけではない。また、説明される具体的特徴、構造、材料又は特性はいずれか1つ又は複数の実施例又は例において適宜組み合わせることができる。 In describing the present invention, references to terms such as "one embodiment," "several embodiments," "exemplary embodiments," "examples," "specific examples," or "examples" mean that the specific feature, structure, material, or characteristic described in combination with the embodiment or example is included in at least one embodiment or example of the present invention. In this specification, exemplary references to the above terms do not necessarily refer to the same embodiment or example. Also, the specific features, structures, materials, or characteristics described may be combined in any one or more embodiments or examples, as appropriate.
101 支保工
102 上弦材
103 下弦材
104 第1斜材
105 第2斜材
106 垂直材
201 下弦部
202 第1連結部材
203 第1溶接部
204 第2溶接部
205 トラスモジュール
206 上弦部
207 端部連結部材
208 第2連結部材
209 第3溶接部
210 第4溶接部;
301 フック
302 ロープ
303 支持フレーム
304 地面
305 手動式チェーンホイスト
306 仮接続板
101 Support 102 Upper chord member 103 Lower chord member 104 First diagonal member 105 Second diagonal member 106 Vertical member 201 Lower chord portion 202 First connecting member 203 First welded portion 204 Second welded portion 205 Truss module 206 Upper chord portion 207 End connecting member 208 Second connecting member 209 Third welded portion 210 Fourth welded portion;
301 Hook 302 Rope 303 Support frame 304 Ground 305 Manual chain hoist 306 Temporary connection plate
Claims (7)
前記トラスは、
横方向に設置され、対向する始端及び終端を有する下弦材と、
垂直に設置され、底端が前記始端に接続される垂直材と、
複数設置されるトラスモジュールであって、複数の前記トラスモジュールは前記下弦材の長手方向に配置され、各前記トラスモジュールは1つの上弦部及び1つの第1斜材を含み、前記上弦部は横方向に設置され、前記上弦部の一端は前記第1斜材の上端に接続され、上弦部と第1斜材との夾角は鋭角であり、異なるトラスモジュールにそれぞれ属する複数の前記上弦部は端部同士を順に接続して上弦材を形成し、前記上弦材は前記下弦材の上方に間隔をおいて設置され、前記上弦材の一端は前記垂直材の上端に接続され、前記第1斜材の底端は前記下弦材に接続されるトラスモジュールと、
複数設置される第2斜材であって、前記第2斜材の上端は上弦部に接続され、前記始端から前記終端まで前記第1斜材と前記第2斜材は交互に設置され、前記第1斜材と前記第2斜材の傾斜方向は反対である第2斜材と、を含み、
前記トラス施工方法は、
前記下弦材を支保工の上部に取り付け、前記下弦材を横方向に設置するステップと、
前記垂直材の底部を前記始端と接続し、前記垂直材を垂直に設置するステップと、
前記始端から前記終端までの方向において、前記下弦材に前記トラスモジュールと前記第2斜材を交互に取り付けるステップと、を含むことを特徴とするトラス施工方法。 A truss construction method used to assemble a truss ,
The truss is
a transversely extending bottom chord having opposing beginning and end terminations;
A vertical member that is installed vertically and has a bottom end connected to the starting end;
a truss module including a plurality of truss modules arranged in the longitudinal direction of the lower chord, each of the truss modules including one upper chord and one first diagonal member, the upper chord being arranged in the horizontal direction, one end of the upper chord being connected to the upper end of the first diagonal member, and an included angle between the upper chord and the first diagonal member being an acute angle, the upper chords belonging to different truss modules being connected to each other at their ends in order to form an upper chord, the upper chord being arranged above the lower chord with a gap therebetween, one end of the upper chord being connected to the upper end of the vertical member, and the bottom end of the first diagonal member being connected to the lower chord;
A plurality of second diagonal members are installed, the upper ends of the second diagonal members are connected to the upper chord portion, the first diagonal members and the second diagonal members are installed alternately from the starting end to the terminal end, and the inclination directions of the first diagonal members and the second diagonal members are opposite to each other.
The truss construction method includes:
Attaching the bottom chord to an upper portion of the support and laterally positioning the bottom chord;
connecting a bottom of the upright to the starting end and vertically installing the upright;
A truss construction method comprising the steps of alternately attaching the truss modules and the second diagonal members to the lower chord in a direction from the starting end to the end end.
前記トラスモジュールを組み立てるステップは、
支持フレームを使用して前記第1斜材を支持し、前記第1斜材を傾斜させて設置するステップと、
前記上弦部を前記第1斜材の上方に吊り上げ、前記上弦部を横方向に設置するステップと、
前記上弦部の一端を前記第1斜材の上端と接続するステップと、を含むことを特徴とする請求項1に記載のトラス施工方法。 further comprising assembling the truss module prior to attaching the truss module to the bottom chord;
The step of assembling the truss module includes:
Supporting the first diagonal member using a support frame and installing the first diagonal member at an incline;
Lifting the upper chord above the first diagonal member and laterally installing the upper chord;
The truss construction method according to claim 1 , further comprising a step of connecting one end of the upper chord portion to the upper end of the first diagonal member.
前記下弦材を前記支保工の上部に取り付けるステップは、
複数の前記支保工を設置し、複数の前記支保工を水平方向に間隔をおいて配置するステップと、
複数の前記支保工で下弦材を共同で支え、各前記第1連結部材を1つの前記支保工の上方にそれぞれ位置させるステップと、を含むことを特徴とする請求項1に記載のトラス施工方法。 The lower chord includes a plurality of lower chords whose ends are connected in sequence, the lower chord further includes a first connecting member connected to the lower chord, and both the first diagonal member and the second diagonal member are connectable to the first connecting member;
The step of attaching the bottom chord to the top of the support includes:
Installing a plurality of the supports and spaced apart the supports horizontally;
The truss construction method according to claim 1 , further comprising a step of jointly supporting the lower chord with a plurality of said supports and positioning each of said first connecting members above one of said supports.
クレーンを使用して前記トラスモジュールを所定の高さまで吊り上げるステップと、
前記クレーンと前記トラスモジュールとの接続を維持しながら、前記第1斜材の底端を前記下弦材と溶接し、前記上弦部を前記垂直材の上端と溶接するステップと、
前記クレーンと前記トラスモジュールとの接続を解除するステップと、を含むことを特徴とする請求項1に記載のトラス施工方法。 The step of attaching the truss module to the bottom chord for connection to the upright member includes:
hoisting the truss module to a predetermined height using a crane;
while maintaining a connection between the crane and the truss module, welding the bottom end of the first diagonal member to the bottom chord and welding the top chord to the top end of the upright member;
The truss construction method according to claim 1 , further comprising the step of disconnecting the crane from the truss module.
クレーンを使用して前記トラスモジュールを所定の高さまで吊り上げるステップと、
前記クレーンと現在吊り上げられている前記トラスモジュールとの接続を維持しながら、現在前記クレーンにより吊り上げられている前記トラスモジュールを前記下弦材に取り付けられた前記トラスモジュールと溶接し、現在クレーンにより吊り上げられている前記トラスモジュールを前記下弦材と溶接するステップと、
前記クレーンと現在前記クレーンに接続されている前記トラスモジュールとの接続を解除するステップと、を含むことを特徴とする請求項1に記載のトラス施工方法。 The step of attaching the truss module spaced apart from the uprights to the bottom chords includes:
hoisting the truss module to a predetermined height using a crane;
while maintaining a connection between the crane and the currently lifted truss module, welding the truss module currently lifted by the crane to the truss module attached to the bottom chord and welding the truss module currently lifted by the crane to the bottom chord;
2. The truss construction method according to claim 1 , further comprising the step of: disconnecting the crane from the truss module currently connected to the crane.
クレーンを使用して前記第2斜材を所定の高さまで吊り上げるステップと、
前記クレーンと前記第2斜材との接続を維持しながら、前記第2斜材の上端を前記上弦部と溶接し、前記第2斜材の底端を前記下弦材と溶接するステップと、
前記クレーンと前記第2斜材との接続を解除するステップと、を含むことを特徴とする請求項1に記載のトラス施工方法。 The step of attaching the second diagonal member to the lower chord includes:
Lifting the second diagonal member to a predetermined height using a crane;
while maintaining a connection between the crane and the second diagonal, welding an upper end of the second diagonal to the upper chord and welding a bottom end of the second diagonal to the lower chord;
The truss construction method according to claim 1 , further comprising the step of disconnecting the crane from the second diagonal member.
前記支保工の上部に当て板を取り付けるステップと、
前記下弦材を前記当て板の上方に配置するステップと、を含むことを特徴とする請求項1に記載のトラス施工方法。 The step of attaching the bottom chord to the top of the support includes:
Attaching a backing plate to the upper part of the support;
The truss construction method according to claim 1 , further comprising the step of: placing the bottom chord above the backing plate.
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310404900.1A CN116480068B (en) | 2023-04-12 | 2023-04-12 | Truss and truss construction method |
| CN202310404900.1 | 2023-04-12 |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2024152549A JP2024152549A (en) | 2024-10-25 |
| JP7657261B2 true JP7657261B2 (en) | 2025-04-04 |
Family
ID=87220689
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2023119930A Active JP7657261B2 (en) | 2023-04-12 | 2023-07-24 | Truss and truss construction method |
Country Status (2)
| Country | Link |
|---|---|
| JP (1) | JP7657261B2 (en) |
| CN (1) | CN116480068B (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117051974B (en) * | 2023-08-18 | 2026-03-20 | 中国建筑第二工程局有限公司 | Construction methods for large-span cantilever platforms in super high-rise buildings and their hoisting. |
| CN117552527A (en) * | 2023-11-28 | 2024-02-13 | 中冶(上海)钢结构科技有限公司 | A method for installation of ultra-large-span truss rectangular cross-section web rods without supplementary gear |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2002167710A (en) | 2000-11-30 | 2002-06-11 | Nkk Corp | Steel pipe joint structure and pipe truss bridge construction method |
| US20190078330A1 (en) | 2017-09-13 | 2019-03-14 | Xtreme Structures & Fabrication, LLC | Modular truss |
| CN111794529A (en) | 2020-07-15 | 2020-10-20 | 沈阳科维润工程技术有限公司 | Modular construction hoisting method for arch type space pipe truss steel structure system |
| JP7116400B2 (en) | 2019-01-28 | 2022-08-10 | 三井住友建設株式会社 | truss girder |
Family Cites Families (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP3232486B2 (en) * | 1992-04-08 | 2001-11-26 | 清水建設株式会社 | Unit truss construction method |
| JPH06200563A (en) * | 1993-01-05 | 1994-07-19 | Toshiro Suzuki | Construction method for trussed structure |
| JP3658073B2 (en) * | 1996-01-24 | 2005-06-08 | 中央ビルト工業株式会社 | Construction method of long truss |
| CN202099719U (en) * | 2011-05-23 | 2012-01-04 | 江苏沪宁钢机股份有限公司 | Steel truss bridge |
| CN212641166U (en) * | 2020-03-27 | 2021-03-02 | 中铁十四局集团第三工程有限公司 | Vertical-rod-free triangular truss split type steel guide beam |
| CN113445740B (en) * | 2021-05-25 | 2022-09-16 | 中建钢构工程有限公司 | Truss construction method |
| CN115821767A (en) * | 2022-11-23 | 2023-03-21 | 中铁宝桥集团有限公司 | A method for manufacturing and constructing large sections of steel truss girders for suspension bridges |
| CN115772861B (en) * | 2022-12-05 | 2026-02-10 | 中铁二局集团有限公司 | A method for installing the main truss of a steel truss bridge |
-
2023
- 2023-04-12 CN CN202310404900.1A patent/CN116480068B/en active Active
- 2023-07-24 JP JP2023119930A patent/JP7657261B2/en active Active
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2002167710A (en) | 2000-11-30 | 2002-06-11 | Nkk Corp | Steel pipe joint structure and pipe truss bridge construction method |
| US20190078330A1 (en) | 2017-09-13 | 2019-03-14 | Xtreme Structures & Fabrication, LLC | Modular truss |
| JP7116400B2 (en) | 2019-01-28 | 2022-08-10 | 三井住友建設株式会社 | truss girder |
| CN111794529A (en) | 2020-07-15 | 2020-10-20 | 沈阳科维润工程技术有限公司 | Modular construction hoisting method for arch type space pipe truss steel structure system |
Also Published As
| Publication number | Publication date |
|---|---|
| CN116480068A (en) | 2023-07-25 |
| JP2024152549A (en) | 2024-10-25 |
| CN116480068B (en) | 2026-04-07 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP7657261B2 (en) | Truss and truss construction method | |
| AU2023210601A1 (en) | Cable-Supported Large-Span Structure And Construction Method Therefor | |
| CN112942661B (en) | Construction method of stay cable with flexible cable net boundary | |
| CN113756592A (en) | Lifting system of truss roof when height of upper lifting point is limited and construction method thereof | |
| CN115233807B (en) | Locally overhanging oversized steel structure corridor and construction method thereof | |
| CN113756501B (en) | Construction method of overhanging aluminum alloy roof | |
| CN114575509B (en) | Assembled building beam plate connecting structure and connecting method | |
| CN115787996A (en) | Overhung construction method and overhung frame for super-high building | |
| CN220336505U (en) | Temporary fixing structure of arched steel structure | |
| CN218375364U (en) | Steel truss promotes auxiliary stay structure | |
| CN109184032B (en) | Assembled shear wall vertical connection structure convenient to install and installation method | |
| CN118516916A (en) | Bridge tower beam skeleton integrated lifting construction method | |
| CN215828215U (en) | Self-balancing large-span net rack lifting structure | |
| CN216108083U (en) | Cable-stayed bridge cable tower end anchoring device | |
| JPH11269825A (en) | Bridge girder erection method and lifting device | |
| CN116556587A (en) | An inclined hanging steel structure and its installation method | |
| CN116122579A (en) | Hoisting method for bidirectional bending dome bracket | |
| CN113582040A (en) | Self-balancing large-span net rack lifting structure and lifting method | |
| JP3826352B2 (en) | Assembling the deck unit | |
| CN223753500U (en) | A lifting platform for hydraulic synchronous lifting of steel structures | |
| CN117228556B (en) | Climbing method of variable-section structural space self-elevating inner climbing tower crane | |
| CN215160345U (en) | Novel slant variable angle cable promotes device | |
| CN111764308A (en) | A light-weight assembled bridge bottom surface construction platform and its construction method | |
| KR102945020B1 (en) | Method for installing a truss structure using a temporary member | |
| CN220364263U (en) | Suspension type lifting construction system |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20230724 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20241001 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20241227 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20250311 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20250325 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 7657261 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |