Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JP7684089B2 - Secondary battery management device, secondary battery management method, and program - Google Patents
[go: Go Back, main page]

JP7684089B2 - Secondary battery management device, secondary battery management method, and program - Google Patents

Secondary battery management device, secondary battery management method, and program Download PDF

Info

Publication number
JP7684089B2
JP7684089B2 JP2021080900A JP2021080900A JP7684089B2 JP 7684089 B2 JP7684089 B2 JP 7684089B2 JP 2021080900 A JP2021080900 A JP 2021080900A JP 2021080900 A JP2021080900 A JP 2021080900A JP 7684089 B2 JP7684089 B2 JP 7684089B2
Authority
JP
Japan
Prior art keywords
secondary battery
soc
charging
battery
deterioration
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2021080900A
Other languages
Japanese (ja)
Other versions
JP2022174885A (en
Inventor
修子 山内
亮平 中尾
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Priority to JP2021080900A priority Critical patent/JP7684089B2/en
Publication of JP2022174885A publication Critical patent/JP2022174885A/en
Application granted granted Critical
Publication of JP7684089B2 publication Critical patent/JP7684089B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Tests Of Electric Status Of Batteries (AREA)
  • Charge And Discharge Circuits For Batteries Or The Like (AREA)
  • Secondary Cells (AREA)
  • Electric Propulsion And Braking For Vehicles (AREA)

Description

本発明は、二次電池管理装置、二次電池管理方法およびプログラムに関する。 The present invention relates to a secondary battery management device, a secondary battery management method, and a program.

環境問題が大きくクローズアップされてきており、地球温暖化を防止するために、あらゆる場面で炭酸ガスの排出削減が求められている。このような背景から、炭酸ガスの大きな排出源の一つであるガソリンエンジンを使用した自動車については、ハイブリッド電気自動車や電気自動車等への代替が進められている。電気自動車やハイブリッド電気自動車の動力用電源となる車載の電池は、その性能が走行性能に影響するため、近年では高性能で軽量のリチウムイオン電池が使用されており、走行用バッテリの価格は高く、電気自動車の価格も同じクラスのガソリン車よりも高額である。ユーザー側からは長期に運用できることが望まれており、メーカー側からは最適な電池量でコストを抑制したいという要求がある。
一般に二次電池は充放電に伴い容量が減少する。特に、正極材料がLiCoO2,LiMnxNiyCo(1-x-y)O2(x+y>1)などの含リチウムイオン遷移金属酸化物で、負極が黒鉛や非晶質炭素材料の組合せのリチウム二次電池においては満充電状態で劣化が進行しやすいことが知られている。
Environmental issues have been receiving a lot of attention, and in order to prevent global warming, it is necessary to reduce carbon dioxide emissions in all situations. Against this background, automobiles using gasoline engines, which are one of the major sources of carbon dioxide emissions, are being replaced by hybrid electric vehicles and electric vehicles. The performance of the on-board batteries that serve as the power source for electric vehicles and hybrid electric vehicles affects their driving performance, so in recent years, high-performance, lightweight lithium-ion batteries have been used, and the price of driving batteries is high, and the price of electric vehicles is higher than that of gasoline-powered vehicles in the same class. Users want long-term operation, and manufacturers want to keep costs down with an optimal battery capacity.
In general, the capacity of secondary batteries decreases with charging and discharging. In particular, it is known that the capacity of lithium secondary batteries that use a combination of a positive electrode material containing lithium ions, such as LiCoO2 or LiMnxNiyCo (1-xy) O2 (x+y>1), and a negative electrode material such as graphite or amorphous carbon material, is prone to deterioration even when fully charged.

本技術分野の背景技術として、下記特許文献1の要約には、「電気自動車の電池の電池残量を検出する電池残量検出部15bと、次回の電気自動車を利用するトリップの出発時刻及び当該トリップにおける必要消費電力を次回トリップ情報として検出する次回トリップ情報検出部15eと、前記電池残量と前記次回トリップ情報とに基づき、次回トリップ出発時刻までに前記必要消費電力を充電する充電速度及び充電量を決定して充電する充電制御部15cとを備えている。」と記載されている。 As background technology in this technical field, the abstract of the following Patent Document 1 states that "the electric vehicle includes a battery remaining capacity detection unit 15b that detects the remaining battery capacity of the battery, a next trip information detection unit 15e that detects the departure time of the next trip using the electric vehicle and the required power consumption for the trip as next trip information, and a charge control unit 15c that determines the charging speed and charging amount to charge the required power consumption by the departure time of the next trip based on the remaining battery capacity and the next trip information."

特許文献1記載の電気自動車の充電制御装置には、搭載している電池を毎回満充電まで充電する場合に劣化が進行することを予防する観点で、共同利用する複数の電気自動車を次回トリップまでの間に充電する際に、電池劣化に与える影響度合いである電池劣化コストを加味して充電制御を行っている。電池の残量と検出した次回トリップ出発時刻および必要消費電力とに基づき、次回トリップ出発時刻までに必要消費電力を充電する充電速度および充電量を決定して充電することにより、充電速度および充電量を最適化した複数車両の充電制御を行っている。 The electric vehicle charging control device described in Patent Document 1 controls charging by taking into account battery degradation cost, which is the degree of impact on battery degradation, when charging multiple shared electric vehicles until the next trip, with the aim of preventing deterioration that would occur if the onboard battery is charged to full charge every time. Based on the remaining battery charge and the detected departure time and required power consumption for the next trip, the charging speed and charge amount that will charge the required power consumption by the departure time of the next trip are determined, and charging is performed to control charging of multiple vehicles with optimized charging speed and charge amount.

特開2013-90360号公報JP 2013-90360 A

近年、ネット通販市場が拡大し、配送、配達などの物流量が増加しており、配送効率の向上が求められているとともに背景技術に示したように炭酸ガスの排出削減も求められている。このような背景から、配達や配送用の車両についても電気自動車やプラグインハイブリッド車など大型の二次電池を動力とする車両が増加していくと考えられる。配達や配送向けの電気自動車やプラグインハイブリッド電気自動車の動力用電源には大型で大容量二次電池が必要となる。電気自動車の場合、大型車になると必要なエネルギー量も増し、電池重量が増加するため、積載量と電池コストのトレードオフの問題が発生する。車体の重量やバッテリの性能が走行に影響し、物流コスト低減と環境対応のため、車載の電池は、最適な電池量で効率的にオペレーションすることが重要となる。 In recent years, the online shopping market has expanded, and the volume of goods being shipped and delivered has increased. This calls for improved delivery efficiency, as well as a reduction in carbon dioxide emissions, as described in the background art. Against this background, it is expected that the number of vehicles powered by large secondary batteries, such as electric vehicles and plug-in hybrid vehicles, will increase for delivery and delivery vehicles. Electric vehicles and plug-in hybrid electric vehicles for delivery and delivery require large, high-capacity secondary batteries as their power source. For electric vehicles, the amount of energy required increases as the vehicle becomes larger, and the battery weight increases, creating a trade-off between payload and battery cost. The weight of the vehicle body and the performance of the battery affect driving, and in order to reduce logistics costs and be environmentally friendly, it is important that on-board batteries are operated efficiently with optimal battery capacity.

しかし、リチウムイオン電池等の二次電池は、充放電を繰り返す度に劣化が進行し、容量が減少するとともに内部抵抗が上昇する。これにより、二次電池の出力の変動が生じる。二次電池における劣化進行の程度は、現在までに二次電池が使用された環境や方法など、二次電池の使用履歴によって異なる。 However, secondary batteries such as lithium-ion batteries deteriorate with each charge and discharge cycle, reducing capacity and increasing internal resistance. This causes fluctuations in the output of the secondary battery. The degree of deterioration of a secondary battery varies depending on the usage history of the secondary battery, such as the environment and method in which it has been used up to now.

上述のように、特許文献1の内容を適用した技術においては、電気自動車の充電時間を高速化できる。しかし、考慮されていることは、主として急速充電による劣化影響である。このため、電気自動車がこれから配送走行する際の電池の使い方については考慮しないため、電池の劣化が加速される可能性を避けることができない。 As mentioned above, the technology that applies the contents of Patent Document 1 can speed up the charging time of electric vehicles. However, what is mainly taken into consideration is the degradation effect caused by rapid charging. For this reason, no consideration is given to how the battery will be used when the electric vehicle travels on its delivery journey, and the possibility of accelerated battery degradation cannot be avoided.

例えば、配達、配送トラックに関しては、日中の稼働停車・駐車時は、直射日光や、路面の照り返しを必ずしも避けることができる環境にあるとは言い難く、特に夏期は高温になるため、SOC(state of charge;充電率または充電状態)が高い状態で保持されるほど劣化が加速されることになる。二次電池の特性は温度に大きく影響され、特に、容量、抵抗などの特性が変化する。図1を参照して、その内容を説明する。 For example, when it comes to delivery and distribution trucks, they are not necessarily in an environment where they can avoid direct sunlight or glare from the road surface when they are operating, stopped, or parked during the day, and temperatures can get particularly high in the summer, so the higher the SOC (state of charge) is maintained, the faster the degradation will be. The characteristics of secondary batteries are greatly affected by temperature, and in particular, characteristics such as capacity and resistance change. The details will be explained with reference to Figure 1.

図1は、二次電池(例えばリチウムイオン電池)の各種特性例を示す図である。
まず、グラフG2は、二次電池の温度に対する、内部抵抗の抵抗値比率DCRを示すグラフである。グラフG2において横軸は二次電池の温度であり、縦軸は、抵抗値比率DCRである。ここで、抵抗値比率DCRとは、25℃における抵抗値を「1」として、各温度における比率を表すものである。低温になるほど抵抗が高く出力が小さくなる。
FIG. 1 is a diagram showing examples of various characteristics of a secondary battery (for example, a lithium ion battery).
First, graph G2 is a graph showing the resistance value ratio DCR of the internal resistance versus the temperature of the secondary battery. In graph G2, the horizontal axis is the temperature of the secondary battery, and the vertical axis is the resistance value ratio DCR. Here, the resistance value ratio DCR represents the ratio at each temperature, with the resistance value at 25°C being "1". The lower the temperature, the higher the resistance and the smaller the output.

また、グラフG4は、二次電池のSOCと温度に対する容量維持率を示すグラフである。グラフG4において、横軸は二次電池のSOCであり、縦軸は二次電池を所定期間保存したときの容量維持率である。また、特性G4-25、G4-50、G4-65、G4-80は、それぞれ電池温度が25℃、50℃、65℃および80℃における特性である。グラフG4に示すように、SOCが高く電池温度が高くなるほど容量維持率が低下する。 Graph G4 is a graph showing the capacity retention rate versus the SOC and temperature of the secondary battery. In graph G4, the horizontal axis is the SOC of the secondary battery, and the vertical axis is the capacity retention rate when the secondary battery is stored for a specified period of time. Characteristics G4-25, G4-50, G4-65, and G4-80 are characteristics at battery temperatures of 25°C, 50°C, 65°C, and 80°C, respectively. As shown in graph G4, the higher the SOC and the higher the battery temperature, the lower the capacity retention rate.

また、グラフG6は、二次電池を様々な温度で6ヵ月保存した場合における、内部抵抗の抵抗上昇率を示す図である。図示のように、温度が高くなるほど、抵抗上昇率が高くなり、劣化が大きくなる。また、グラフG8は、二次電池を様々なSOCにおいて、25℃で190日間保存した場合の抵抗上昇率を示す図である。図示のように、SOCが高くなるほど、抵抗上昇率が高くなり、劣化が大きくなる。ここに示した例は一例であり、電池材料の種類、仕様によりその劣化特性は異なり、使い方によって劣化が変動する。 Graph G6 shows the rate of increase in internal resistance when a secondary battery is stored for six months at various temperatures. As shown, the higher the temperature, the higher the rate of increase in resistance and the greater the degradation. Graph G8 shows the rate of increase in resistance when a secondary battery is stored for 190 days at 25°C at various SOCs. As shown, the higher the SOC, the higher the rate of increase in resistance and the greater the degradation. The example shown here is just one example, and the degradation characteristics differ depending on the type and specifications of the battery material, and degradation varies depending on how it is used.

前述したように特許文献1において、考慮に入っているのは急速充電による劣化影響である。電気自動車が充電後に走行する際の電池の使い方については考慮していないため、走行時の状態によって電池の劣化が加速される可能性を避けることができない。そこで、配送・配達用で電池を動力源に使用する車両において、二次電池モジュールの劣化度反映し、短時間で充電を効率よくかつ電池を効果的に活用する配送・配達システムと連携した最適充電ナビゲーションシステムを提供できれば好ましい。
この発明は上述した事情に鑑みてなされたものであり、走行時の状態を反映して二次電池の劣化速度を抑制しかつ安定な走行を可能にする二次電池管理装置、二次電池管理方法およびプログラムを提供することを目的とする。
As mentioned above, Patent Document 1 takes into consideration the degradation effect due to rapid charging. It does not take into consideration how the battery is used when the electric vehicle runs after charging, so it is impossible to avoid the possibility that the battery degradation will be accelerated depending on the driving conditions. Therefore, it would be preferable to provide an optimal charging navigation system that reflects the degree of degradation of the secondary battery module in vehicles that use batteries as a power source for delivery and distribution, and that is linked to a delivery and distribution system that efficiently charges in a short time and effectively utilizes the battery.
The present invention has been made in consideration of the above-mentioned circumstances, and aims to provide a secondary battery management device, a secondary battery management method, and a program that reflect the state during driving to suppress the rate of deterioration of the secondary battery and enable stable driving.

上記課題を解決するため本発明の二次電池管理装置は、二次電池によって駆動される移動体の移動日時または移動時外気温と、移動経路と、に対応して所要電力量を記憶する電力量データベースに基づいて、前記移動体が指定された移動予定経路を移動するために要すると予測される予測電力量を算出する電力量算出部と、前記二次電池の使用状態と劣化状態との相関関係を示すデータとともに前記二次電池の過去の使用状態を記録した電池劣化データベースを参照し、前記二次電池の劣化状態に応じて、前記予測電力量を確保できる前記二次電池の使用SOC領域または使用電圧領域を算出し、算出した前記使用SOC領域または前記使用電圧領域に基づいて、充電完了状態における前記二次電池の電圧またはSOCである走行開始条件を決定する走行開始状態決定部と、を備えることを特徴とする。 In order to solve the above problem, the secondary battery management device of the present invention is characterized in that it comprises: an electric energy calculation unit that calculates a predicted amount of electric energy that is predicted to be required for a mobile body powered by a secondary battery to move along a specified planned travel route based on an electric energy database that stores required electric energy corresponding to the travel date and time or outside air temperature during travel and the travel route of the mobile body; and a driving start state determination unit that refers to a battery degradation database that records the past usage state of the secondary battery along with data indicating the correlation between the usage state and degradation state of the secondary battery, calculates a usage SOC range or usage voltage range of the secondary battery in which the predicted amount of electric energy can be secured according to the degradation state of the secondary battery, and determines a driving start condition, which is the voltage or SOC of the secondary battery in a fully charged state, based on the calculated usage SOC range or usage voltage range.

具体的には、二次電池によって駆動される移動体の移動日時または移動時外気温と、移動経路と、に対応して所要電力量を記憶する電力量データベースに基づいて、前記移動体が指定された移動予定経路を移動するために要すると予測される予測電力量を算出する電力量算出部と、前記二次電池の劣化状態を記録し、または、前記二次電池の使用状態と前記劣化状態との相関関係を示すデータとともに前記二次電池の過去の使用状態を記録した電池劣化データベースを参照し、前記劣化状態に応じて、前記予測電力量を確保できる前記二次電池の使用SOC領域または使用電圧領域を算出し、算出した前記使用SOC領域または前記使用電圧領域に基づいて、走行開始時の二次電池の推奨電圧または推奨SOCを決定し、充電完了状態における前記二次電池の電圧またはSOCである走行開始条件を決定する走行開始状態決定部と、を備えることを特徴とする。
後述する好適な実施形態においては、配送・配達用で電池を動力源に使用する車両において、二次電池モジュールの劣化度を反映し効率よく充電し、かつ、電池を有効活用する。さらに、好適な実施形態では、配送・配達システムと連携した最適充電ナビゲーションシステムを提供する。そのため、好適な実施形態による二次電池管理装置においては、予め蓄積された配達、配送時の走行ルート走行履歴と、当該車両における二次電池の現在の劣化状態と、環境温度と、配送予定ルートと、荷重と、に基づいて必要と考えられる予測電力量を算出する。
Specifically, the device is characterized by comprising: an electric energy calculation unit that calculates a predicted amount of electric energy that is predicted to be required for a mobile body powered by a secondary battery to move along a specified planned travel route based on an electric energy database that stores required electric energy corresponding to the travel date and time or the outside air temperature during travel and the travel route; and a travel start state determination unit that records the deterioration state of the secondary battery, or refers to a battery deterioration database that records the past usage state of the secondary battery together with data indicating the correlation between the usage state of the secondary battery and the deterioration state, calculates a usage SOC range or usage voltage range of the secondary battery in which the predicted amount of electric energy can be secured according to the deterioration state, determines a recommended voltage or recommended SOC of the secondary battery at the start of travel based on the calculated usage SOC range or usage voltage range, and determines a travel start condition, which is the voltage or SOC of the secondary battery in a fully charged state.
In a preferred embodiment described later, in a vehicle for delivery and distribution that uses a battery as a power source, charging is performed efficiently while reflecting the degree of deterioration of the secondary battery module, and the battery is utilized effectively. Furthermore, in a preferred embodiment, an optimal charging navigation system linked to a delivery and distribution system is provided. For this reason, the secondary battery management device according to the preferred embodiment calculates a predicted amount of power required based on previously accumulated driving route driving history during delivery and distribution, the current deterioration state of the secondary battery in the vehicle, the environmental temperature, the planned delivery route, and the load.

そして、好適な実施形態においては、予測電力量と、配送予定ルートと、配送予定ルートでの停車時間と、電池温度または気温と、に基づいて、少なくとも2つ以上の異なるSOC領域の中から、実際に適用する使用SOC領域を選択し、走行開始時または充電完了時のSOCである走行開始充電率SOCsを決定する。 In a preferred embodiment, an SOC range to be actually applied is selected from at least two or more different SOC ranges based on the predicted power amount, the planned delivery route, the stopping time on the planned delivery route, and the battery temperature or air temperature, and a starting charging rate SOCs, which is the SOC at the start of driving or when charging is completed, is determined.

本発明によれば、走行に必要な電力を適切に決定し車両稼働時の充電による待ち時間を短くし、二次電池の充電状態を適切に決定でき、電池が劣化しにくい条件で使用することで必要電池量の最適化や車両のコストパフォーマンスを上げることができる。 The present invention appropriately determines the amount of power required for driving, shortens the waiting time for charging while the vehicle is in operation, and appropriately determines the state of charge of the secondary battery. By using the battery under conditions that are less likely to deteriorate, it is possible to optimize the required battery capacity and improve the cost performance of the vehicle.

二次電池の各種特性例を示す図である。5A to 5C are diagrams illustrating examples of various characteristics of a secondary battery. 好適な第1実施形態による二次電池管理システムのブロック図である。1 is a block diagram of a secondary battery management system according to a first preferred embodiment; 好適な第2実施形態による二次電池管理システムのブロック図である。FIG. 11 is a block diagram of a secondary battery management system according to a second preferred embodiment. 二次電池のSOCと電圧の関係を示すSOC領域選択の説明図である。FIG. 4 is an explanatory diagram of SOC region selection showing the relationship between the SOC and voltage of a secondary battery. 好適な第3実施形態における時系列データの構造を示す図である。FIG. 13 is a diagram showing a structure of time-series data in the third preferred embodiment. 好適な第4実施形態による二次電池管理システムのブロック図である。FIG. 13 is a block diagram of a secondary battery management system according to a fourth preferred embodiment. 第4実施形態の二次電池管理装置によって実行される走行開始充電率算出プログラムのフローチャートである。13 is a flowchart of a travel start charging rate calculation program executed by a secondary battery management device of a fourth embodiment. 好適な第5実施形態による充電ナビゲーションシステムのブロック図である。FIG. 13 is a block diagram of a charging navigation system according to a fifth preferred embodiment. 第5実施形態における車両BMSの二次電池モジュール劣化度検出法を示すブロック図である。FIG. 13 is a block diagram showing a method for detecting a deterioration level of a secondary battery module of a vehicle BMS in a fifth embodiment. 第5実施形態の電力量データベースに含まれる電力量補正データの模式図である。FIG. 13 is a schematic diagram of power amount correction data included in a power amount database according to the fifth embodiment. 好適な第6実施形態の電力量データベースに含まれる走行実績データの模式図である。FIG. 13 is a schematic diagram of driving record data included in an electric power amount database according to a sixth embodiment. 好適な第7実施形態による二次電池劣化度検出システムのブロック図である。FIG. 13 is a block diagram of a secondary battery deterioration detection system according to a seventh preferred embodiment. 第7実施形態のサーバー機で実行される劣化検出ルーチンのフローチャートである。23 is a flowchart of a deterioration detection routine executed in a server machine according to the seventh embodiment. 二次電池の各種特性を示す図である。FIG. 4 is a diagram showing various characteristics of a secondary battery. 好適な第8実施形態による、車両内電池管理システムのブロック図である。FIG. 13 is a block diagram of an in-vehicle battery management system according to an eighth preferred embodiment. 好適な第9実施形態による、二次電池管理システムのブロック図である。FIG. 13 is a block diagram of a secondary battery management system according to a ninth preferred embodiment. 車両が検出する二次電池の電池電圧、充放電電流およびSOCの経時的変化の一例を示す図である。5 is a diagram showing an example of changes over time in the battery voltage, charge/discharge current, and SOC of a secondary battery detected by a vehicle; 好適な第10実施形態による、二次電池管理システムのブロック図である。FIG. 23 is a block diagram of a secondary battery management system according to a tenth preferred embodiment.

二次電池の保管等においては、二次電池が滞在するSOCをなるべく低く抑えることが好ましい。
そこで、後述する好適な実施形態においては、配送・配達用で電池を動力源に使用する車両において、二次電池モジュールの劣化度反映し、短時間で効率よく充電し、かつ、電池を有効活用する。さらに、好適な実施形態では、配送・配達システムと連携した最適充電ナビゲーションシステムを提供する。そのため、好適な実施形態による二次電池管理装置においては、予め蓄積された配達、配送時の走行ルート走行履歴と、当該車両における二次電池の現在の劣化状態と、環境温度と、配送予定ルートと、荷重と、に基づいて必要と考えられる予測電力量を算出する。
During storage of a secondary battery, it is preferable to keep the SOC at which the secondary battery remains as low as possible.
Therefore, in a preferred embodiment described below, in a vehicle for delivery and distribution that uses a battery as a power source, the degree of deterioration of the secondary battery module is reflected, charging is performed efficiently in a short time, and the battery is effectively utilized. Furthermore, in a preferred embodiment, an optimal charging navigation system linked to a delivery and distribution system is provided. Therefore, in the secondary battery management device according to the preferred embodiment, a predicted amount of power required is calculated based on the previously accumulated driving route driving history during delivery and distribution, the current deterioration state of the secondary battery in the vehicle, the environmental temperature, the planned delivery route, and the load.

そして、好適な実施形態においては、予測電力量と、配送予定ルートと、配送予定ルートでの停車時間と、電池温度または気温と、に基づいて、少なくとも2つ以上の異なるSOC領域の中から、実際に適用する使用SOC領域を選択し、走行開始時または充電完了時のSOCである走行開始充電率SOCsを決定する。
このように、好適な実施形態によれば、劣化が最も少ない領域で走行量(予測電力量)を確保し、かつ短時間充電が可能で、予測電力量を適切に管理でき、電池を効率的に使用でき、電池の搭載量を必要最小限にでき、そのコストパフォーマンスを向上させることができる。
In a preferred embodiment, an SOC range to be actually applied is selected from at least two or more different SOC ranges based on the predicted power amount, the planned delivery route, the stopping time along the planned delivery route, and the battery temperature or air temperature, and a starting charging rate SOCs, which is the SOC at the start of driving or the completion of charging, is determined.
Thus, according to a preferred embodiment, it is possible to ensure the travel distance (predicted power amount) in the area with the least deterioration, charge in a short time, appropriately manage the predicted power amount, use the battery efficiently, reduce the amount of battery installed to the minimum necessary, and improve cost performance.

[第1実施形態]
図2は、好適な第1実施形態による二次電池管理システムS1のブロック図である。
二次電池管理システムS1は、二次電池管理装置100A(コンピュータ)と、電力量データベース142と、電池劣化データベース144と、を備えている。
二次電池管理装置100Aは、CPU(Central Processing Unit)、RAM(Random Access Memory)、ROM(Read Only Memory)、HDD(Hard Disk Drive)等、一般的なコンピュータとしてのハードウエアを備えており、SSDまたはHDDには、OS(Operating System)、アプリケーションプログラム、各種データ等が格納されている。OSおよびアプリケーションプログラムは、RAMに展開され、CPUによって実行される。図2において、二次電池管理装置100Aの内部は、アプリケーションプログラム等によって実現される機能を、ブロックとして示している。
[First embodiment]
FIG. 2 is a block diagram of a secondary battery management system S1 according to the first preferred embodiment.
The secondary battery management system S1 includes a secondary battery management device 100A (computer), an electric energy database 142, and a battery deterioration database 144.
The secondary battery management device 100A includes hardware as a general computer, such as a central processing unit (CPU), random access memory (RAM), read only memory (ROM), and hard disk drive (HDD), and the SSD or HDD stores an operating system (OS), application programs, various data, and the like. The OS and application programs are deployed in the RAM and executed by the CPU. In FIG. 2, the inside of the secondary battery management device 100A shows functions realized by application programs, etc., as blocks.

すなわち、二次電池管理装置100Aは、電力量算出部112(電力量算出手段、電力量算出過程)と、走行開始状態決定部114(充電条件決定手段、充電条件決定過程)と、を備えている。二次電池管理装置100Aは、車両に動力源として搭載される二次電池(図示せず)を管理する。ここで、二次電池管理装置100Aは、車両に搭載されたコンピュータであってもよく、車両とは別体のコンピュータであってもよい。 That is, the secondary battery management device 100A includes an electric power calculation unit 112 (electric power calculation means, electric power calculation process) and a running start state determination unit 114 (charging condition determination means, charging condition determination process). The secondary battery management device 100A manages a secondary battery (not shown) that is installed in the vehicle as a power source. Here, the secondary battery management device 100A may be a computer installed in the vehicle, or may be a computer separate from the vehicle.

車両は、様々な移動経路に沿って荷物等の配送を行う。電力量データベース142は、車両の使用履歴を示す履歴情報と、標準的な所要電力量と、を対応付けて記憶する。ここで、履歴情報は、少なくとも移動日時または移動時の外気温と、移動経路を示すルート情報と、を含んでいる。電力量算出部112は、例えばユーザによって移動予定経路を特定する予定ルート情報Rt(移動予定経路)が入力されると、電力量データベース142に基づいて、その移動予定経路を走行するために車両が要すると予測される予測電力量W1,W2を算出する。ここで、予測電力量W1は、予定ルート情報Rtに基づいて算出した予測電力量であり、予測電力量W2は二次電池の劣化状態等に基づいて予測電力量W1を補正した結果である。 The vehicle delivers luggage and the like along various travel routes. The power amount database 142 stores history information indicating the usage history of the vehicle in association with the standard required power amount. Here, the history information includes at least the travel date and time or the outside temperature at the time of travel, and route information indicating the travel route. For example, when the user inputs planned route information Rt (planned travel route) specifying the planned travel route, the power amount calculation unit 112 calculates the predicted power amounts W1 and W2 that are predicted to be required by the vehicle to travel the planned travel route based on the power amount database 142. Here, the predicted power amount W1 is the predicted power amount calculated based on the planned route information Rt, and the predicted power amount W2 is the result of correcting the predicted power amount W1 based on the deterioration state of the secondary battery, etc.

電池劣化データベース144は、電池の使用条件とバッテリの容量、抵抗の変化を推定できる相関データを含んで構成される。但し、現状の劣化状態に代えて、過去の使用状態(例えば環境温度の推移、出力した電力量等)と、劣化影響データとを記憶してもよい。ここで、劣化影響データは、二次電池の使用条件と劣化状態との相関関係を記述したデータである。走行開始状態決定部114は、電池劣化データベース144に基づいて、予測電力量W2を確保できる二次電池の使用電圧領域または使用SOC領域を算出する。 The battery degradation database 144 is configured to include correlation data that can estimate the battery usage conditions and changes in the battery capacity and resistance. However, instead of the current degradation state, past usage states (e.g., changes in ambient temperature, amount of power output, etc.) and degradation impact data may be stored. Here, the degradation impact data is data that describes the correlation between the usage conditions and degradation state of the secondary battery. The running start state determination unit 114 calculates the usage voltage region or usage SOC region of the secondary battery that can secure the predicted power amount W2 based on the battery degradation database 144.

ここで、使用電圧領域とは、車両が予定ルート情報Rtで示される移動予定経路を走行する場合における、二次電池の放電開始時の電圧から放電終了時の電圧に至るまでの領域である。また、使用SOC領域は、放電開始時のSOCから放電終了時のSOCに至るまでの領域である。走行開始状態決定部114は、電池の劣化が加速されないように、使用する電圧領域を決定することが好ましい。 The operating voltage range is the range from the voltage at the start of discharging the secondary battery to the voltage at the end of discharging when the vehicle travels along the planned travel route indicated by the planned route information Rt. The operating SOC range is the range from the SOC at the start of discharging to the SOC at the end of discharging. It is preferable that the travel start state determination unit 114 determines the voltage range to be used so as not to accelerate battery deterioration.

走行開始状態決定部114は、電池劣化データベース144を参照し、稼働に適切な使用電圧領域を算出する。そして、その使用電圧領域に基づいて、充電完了条件として、充電完了状態における二次電池の電圧である走行開始電圧Vs(走行開始条件)、または、充電完了状態における二次電池のSOCである走行開始充電率SOCs(走行開始条件)を決定し、出力する。 The driving start state determination unit 114 refers to the battery degradation database 144 and calculates the operating voltage range appropriate for operation. Then, based on the operating voltage range, it determines and outputs the driving start voltage Vs (driving start condition), which is the voltage of the secondary battery in the charging complete state, or the driving start charging rate SOCs (driving start condition), which is the SOC of the secondary battery in the charging complete state, as the charging complete condition.

ここで、実際の走行開始電圧Vsは、上述した使用電圧領域の上限値、もしくはその上限値に対して若干の余裕を加算した電圧であってもよい。同様に、走行開始充電率SOCsは、使用電圧領域の上限値に対応するSOCであってもよく、その上限値に対して若干の余裕を加算した電圧に対応するSOCであってもよい。以下、Vsおよび/またはSOCsを総称して、「走行開始条件(SOCs,Vs)」と称することがある。 Here, the actual running start voltage Vs may be the upper limit of the operating voltage range described above, or a voltage obtained by adding a small margin to that upper limit. Similarly, the running start charge rate SOCs may be an SOC corresponding to the upper limit of the operating voltage range, or an SOC corresponding to a voltage obtained by adding a small margin to that upper limit. Hereinafter, Vs and/or SOCs may be collectively referred to as the "running start condition (SOCs, Vs)."

車両のECUは、走行開始状態決定部114が出力した走行開始条件(SOCs,Vs)を認識すると、当該走行開始条件(SOCs,Vs)を充電装置(図示せず)に設定する。これにより、充電装置は、二次電池に対する充電を開始する。そして、二次電池のSOCまたは出力電圧が走行開始条件(SOCs,Vs)に達すると、充電装置は充電動作を終了する。
但し、二次電池11のSOCまたは電池電圧が走行開始条件(SOCs,Vs)以上である場合、車両は充電操作をスキップして走行を開始することが可能である。
When the vehicle ECU recognizes the driving start condition (SOCs, Vs) output by the driving start state determination unit 114, it sets the driving start condition (SOCs, Vs) in the charging device (not shown). As a result, the charging device starts charging the secondary battery. Then, when the SOC or output voltage of the secondary battery reaches the driving start condition (SOCs, Vs), the charging device ends the charging operation.
However, when the SOC or battery voltage of the secondary battery 11 is equal to or higher than the running start condition (SOCs, Vs), the vehicle can skip the charging operation and start running.

[第2実施形態]
図3は、好適な第2実施形態による二次電池管理システムS2のブロック図である。なお、以下の説明において、上述した第1実施形態の各部に対応する部分には同一の符号を付し、その説明を省略する場合がある。
二次電池管理システムS2は、充電装置200と、二次電池管理装置100B(コンピュータ)と、電力量データベース142と、電池劣化データベース144と、を備えている。
[Second embodiment]
3 is a block diagram of a secondary battery management system S2 according to a preferred second embodiment. In the following description, parts corresponding to those in the first embodiment are given the same reference numerals, and the description thereof may be omitted.
The secondary battery management system S2 includes a charging device 200, a secondary battery management device 100B (computer), an electric energy database 142, and a battery deterioration database 144.

二次電池管理装置100Bのハードウエア構成は、第1実施形態の二次電池管理装置100Aと同様である。そして、二次電池管理装置100Bは、二次電池管理装置100Aと同様に、電力量算出部112と、走行開始状態決定部114と、を備えている。さらに、二次電池管理装置100Bは、データベース更新部118と、解析部120と、を備えている。 The hardware configuration of the secondary battery management device 100B is the same as that of the secondary battery management device 100A of the first embodiment. And, like the secondary battery management device 100A, the secondary battery management device 100B includes an electric energy calculation unit 112 and a running start state determination unit 114. Furthermore, the secondary battery management device 100B includes a database update unit 118 and an analysis unit 120.

また、本実施形態は複数の車両10(移動体)を管理するものである。但し、図3には1台の車両10のみを図示する。各車両10には、動力源としての二次電池11と、データ処理部12が設けられている。データ処理部12は、所定のサンプリング周期で、車両10の位置情報、二次電池11の状態(電圧、電流等)を計測し、その結果を時系列データD10として一定量蓄積し出力する。そして、データ処理部12は、時系列データD10を、無線または有線で、二次電池管理装置100Bの解析部120に送信する。送信タイミングはリアルタイムでもよいが、通信の負荷や、蓄積できるデータ量に応じで、好適なタイミングで送信する。例えば、1回の走行における、駐車時、走行停止後や、スタータ起動時のタイミングで送信する。 This embodiment also manages multiple vehicles 10 (mobiles). However, FIG. 3 illustrates only one vehicle 10. Each vehicle 10 is provided with a secondary battery 11 as a power source and a data processing unit 12. The data processing unit 12 measures the position information of the vehicle 10 and the state of the secondary battery 11 (voltage, current, etc.) at a predetermined sampling period, and accumulates and outputs a certain amount of the results as time-series data D10. The data processing unit 12 then transmits the time-series data D10 to the analysis unit 120 of the secondary battery management device 100B wirelessly or via a wired connection. The transmission timing may be real-time, but transmission is performed at an appropriate timing depending on the communication load and the amount of data that can be accumulated. For example, transmission is performed when parking, after stopping, or when the starter is started during one run.

また、解析部120は、複数の車両10から受信した時系列データD10を解析し、その内容に基づいて、電力量データベース142および電池劣化データベース144に蓄積するデータを生成する。データベース更新部118は、解析部120が生成したデータに基づいて、電力量データベース142と、電池劣化データベース144と、を更新する。 The analysis unit 120 also analyzes the time series data D10 received from multiple vehicles 10, and generates data to be stored in the power amount database 142 and the battery deterioration database 144 based on the contents of the data. The database update unit 118 updates the power amount database 142 and the battery deterioration database 144 based on the data generated by the analysis unit 120.

本実施形態における電力量データベース142も、第1実施形態のものと同様に、履歴情報と、標準的な所要電力量と、を対応付けて記憶する。また、本実施形態における履歴情報は、移動日時と、移動時外気温と、配送ルート等のルート情報と、車両10の位置情報と、使用時間と、車両10の車量と、車両10の荷重と、車両10を特定する車両IDと、運転者を特定する運転者IDと、を含んでいる。 In the present embodiment, the power database 142 stores history information and standard required power amounts in association with each other, similar to the first embodiment. The history information in this embodiment also includes the travel date and time, the outside air temperature during travel, route information such as a delivery route, location information of the vehicle 10, the usage time, the volume of the vehicle 10, the load of the vehicle 10, a vehicle ID that identifies the vehicle 10, and a driver ID that identifies the driver.

車両10の所要電力量は、車両10の車重や荷重によって、同一のルートであっても変わり、電費も変動する。従って、車重や荷重と所要電力量との関係を蓄積して利用することで、予測電力量W1,W2をより正確に見積もることができる。また、車両10の車重および荷重は、トラックスケールと連動して記憶することが好ましい。さらに、車重および荷重は、車種データと、搭載荷物の各重量和およびドライバーの体重等から、計算による合算で求めた値でもよい。電力量算出部112は、この電力量データベース142を参照することで、これから車両10が走行するための予測電力量W1を算出する。 The amount of power required by the vehicle 10 varies depending on the weight and load of the vehicle 10, even for the same route, and the power consumption also varies. Therefore, by accumulating and using the relationship between the vehicle weight and load and the amount of power required, the predicted power amounts W1 and W2 can be estimated more accurately. It is also preferable to store the weight and load of the vehicle 10 in conjunction with a truck scale. Furthermore, the vehicle weight and load may be values calculated by adding up the vehicle type data, the sum of the weights of the loaded luggage, the weight of the driver, etc. The power amount calculation unit 112 refers to this power amount database 142 to calculate the predicted amount of power W1 for the vehicle 10 to travel from now on.

さらに、電力量算出部112は、車載BMSまたは充電器で検出された劣化度SOHに基づいて、二次電池11の劣化状態を取得し、現在の二次電池11の劣化状態と、想定温度Tassと、に基づいて予測電力量W1を補正し、補正結果を予測電力量W2として出力する。ここで、想定温度Tassとは、例えば二次電池11に装着した温度センサ(図示せず)から取得した温度であってもよく、天気予報等で予報された、配送時間帯における気温であってもよい。 Furthermore, the power calculation unit 112 acquires the degradation state of the secondary battery 11 based on the degradation level SOH detected by the in-vehicle BMS or the charger, corrects the predicted power amount W1 based on the current degradation state of the secondary battery 11 and the assumed temperature Tass, and outputs the correction result as the predicted power amount W2. Here, the assumed temperature Tass may be, for example, a temperature acquired from a temperature sensor (not shown) attached to the secondary battery 11, or may be the air temperature during the delivery time period predicted by a weather forecast or the like.

また、走行開始状態決定部114は、電池劣化データベース144に対して、教師あり学習によって学習処理を行った人工知能によって、使用条件から充電完了条件、すなわち走行開始条件(SOCs,Vs)を決定することが好ましい。 In addition, it is preferable that the driving start state determination unit 114 determines the charging completion condition, i.e., the driving start condition (SOCs, Vs), from the usage conditions using artificial intelligence that performs learning processing using supervised learning on the battery deterioration database 144.

ここで、走行開始状態決定部114は、二次電池11の劣化条件と、最適な走行開始条件(SOCs,Vs)との関係をマップ(テーブル)形式のデータとして記憶し、このマップ形式のデータを参照して走行開始条件(SOCs,Vs)を決定してもよい。また、二次電池11の使用条件と、最適な走行開始条件(SOCs,Vs)との関係をマップ形式で記憶してもよい。さらに、電池の使用条件と、電力量と、最適な走行開始条件(SOCs,Vs)との関係をマップ形式で記憶してもよい。 Here, the driving start state determination unit 114 may store the relationship between the deterioration conditions of the secondary battery 11 and the optimal driving start conditions (SOCs, Vs) as data in a map (table) format, and determine the driving start conditions (SOCs, Vs) by referring to this map-format data. Also, the relationship between the usage conditions of the secondary battery 11 and the optimal driving start conditions (SOCs, Vs) may be stored in map format. Furthermore, the relationship between the battery usage conditions, the amount of power, and the optimal driving start conditions (SOCs, Vs) may be stored in map format.

充電制御部124は、上述した走行開始条件(SOCs,Vs)と、デューティ比Dtrと、に基づいて充電要求(出力・時間その他の情報)を決定し、決定した充電要求により充電装置200を制御する。走行開始状態決定部114の機能は第1実施形態のものと同様であるが、本実施形態の走行開始状態決定部114は、対象とする二次電池11の環境温度の想定値である想定温度Tassを受信する。 The charging control unit 124 determines a charging request (output, time, and other information) based on the above-mentioned driving start conditions (SOCs, Vs) and the duty ratio Dtr, and controls the charging device 200 based on the determined charging request. The function of the driving start state determination unit 114 is similar to that of the first embodiment, but the driving start state determination unit 114 of this embodiment receives an expected temperature Tass, which is an expected value of the environmental temperature of the target secondary battery 11.

そして、走行開始状態決定部114は、想定温度Tassが高くなるほど、同一の予測電力量W2に対する走行開始条件(SOCs,Vs)が低くなるように、SOCsまたはVsを設定する。ここで、走行開始状態決定部114は、二次電池11の劣化条件と、走行開始条件(SOCs,Vs)との関係を、二次元のマップ(テーブル)として記憶してもよい。また、走行開始状態決定部114は、二次電池11の使用条件と、最適な走行開始電圧Vsとの関係をマップで実装してもよい。さらに、走行開始状態決定部114は、二次電池11の使用条件と、予測電力量W2と、最適な走行開始電圧Vsとの関係をマップ化して実装してもよい。 Then, the running start state determination unit 114 sets the SOCs or Vs so that the running start condition (SOCs, Vs) for the same predicted power amount W2 becomes lower as the assumed temperature Tass becomes higher. Here, the running start state determination unit 114 may store the relationship between the deterioration condition of the secondary battery 11 and the running start condition (SOCs, Vs) as a two-dimensional map (table). In addition, the running start state determination unit 114 may implement the relationship between the usage condition of the secondary battery 11 and the optimal running start voltage Vs in a map. Furthermore, the running start state determination unit 114 may implement the relationship between the usage condition of the secondary battery 11, the predicted power amount W2, and the optimal running start voltage Vs in a map.

ここで、走行開始状態決定部114の動作についてさらに詳細を説明する。図4を参照して、二次電池11の現在のSOCを参照して、使用SOC領域を決定する動作の一例を説明する。
図4は、二次電池11のSOCと電圧の関係を示す図である。
図4の横軸はSOCであり、左端が100%であり、右端が0%である。二次電池11の開回路電圧OCVおよび所定電流を流した際の閉回路電圧CCVは、図示のように、SOCが低下するほど低下する。ハッチングを付した領域EA1,EA2は、上述した予測電力量W2を確保できる電圧領域(またはSOC領域)の例であり、これらは使用電圧領域または使用SOC領域の候補になる。
Here, a more detailed description will be given of the operation of the running start state determination unit 114. An example of an operation for determining a usable SOC range by referring to the current SOC of the secondary battery 11 will be described with reference to Fig. 4 .
FIG. 4 is a diagram showing the relationship between the SOC and the voltage of the secondary battery 11. As shown in FIG.
The horizontal axis in Fig. 4 is SOC, with the left end being 100% and the right end being 0%. As shown in the figure, the open circuit voltage OCV of the secondary battery 11 and the closed circuit voltage CCV when a predetermined current flows decrease as the SOC decreases. The hatched areas EA1 and EA2 are examples of voltage areas (or SOC areas) in which the above-mentioned predicted power amount W2 can be secured, and these are candidates for the operating voltage area or operating SOC area.

なお、図示のもの以外にも、使用電圧領域または使用SOC領域の候補になり得る様々な電圧領域またはSOC領域を考えることができる。低電圧側の領域EA1のSOCは、下限値SOC1L~上限値SOC1Hの範囲であり、両者の差分(SOC1H-SOC1L)をSOC幅ΔSOC1と呼ぶ。同様に、高圧側の領域EA2のSOCは、下限値SOC2L~上限値SOC2Hの範囲であり、両者の差分(SOC2H-SOC2L)をSOC幅ΔSOC2と呼ぶ。 Note that in addition to those shown in the figure, various voltage ranges or SOC ranges can be considered as candidates for the operating voltage range or operating SOC range. The SOC in the low-voltage side range EA1 ranges from the lower limit value SOC1L to the upper limit value SOC1H, and the difference between the two (SOC1H-SOC1L) is called the SOC range ΔSOC1. Similarly, the SOC in the high-voltage side range EA2 ranges from the lower limit value SOC2L to the upper limit value SOC2H, and the difference between the two (SOC2H-SOC2L) is called the SOC range ΔSOC2.

図4に示す上限値SOC1H,SOC2Hは、上述した走行開始充電率SOCsの候補値になる。ところで、先に図1のグラフG6,G8に示したように、リチウムイオン電池の劣化速度は、保管温度が高くなるほど速くなり、保管時のSOCが高いほど速くなる傾向がある。そこで、走行開始状態決定部114は、これらの劣化特性を踏まえて、運行時の気温を勘案し、なるべく二次電池11が劣化しにくい使用SOC領域を設定し、その使用SOC領域の上限値(例えばSOC1H,SOC2H)を走行開始充電率SOCsとして出力する。または、これに代えて、走行開始状態決定部114は、使用SOC領域の上限値に対応する開回路電圧OCVを、走行開始電圧Vsとして出力してもよい。 The upper limit values SOC1H and SOC2H shown in FIG. 4 are candidate values for the above-mentioned running start charging rate SOCs. Incidentally, as previously shown in graphs G6 and G8 in FIG. 1, the rate of deterioration of lithium-ion batteries tends to be faster as the storage temperature increases and as the SOC during storage increases. Therefore, the running start state determination unit 114 takes into account these deterioration characteristics and the temperature during operation, sets a usage SOC range in which the secondary battery 11 is as unlikely to deteriorate as possible, and outputs the upper limit value (e.g., SOC1H, SOC2H) of the usage SOC range as the running start charging rate SOCs. Alternatively, the running start state determination unit 114 may output the open circuit voltage OCV corresponding to the upper limit value of the usage SOC range as the running start voltage Vs.

これにより、必要な予測電力量W2を確保し、かつ、劣化を抑制しつつ二次電池11を運用することができる。さらに、二次電池11を常に満充電にする場合と比較して充電時間も短くでき、効率的に車両10を運用することが可能になる。例えば、夏期は気温も高く輻射熱や廃熱により二次電池11が高温になりやすく、二次電池11の劣化が進行しやすくなる。そこで、夏期においては、使用SOC領域を低SOC側(例えば図4の領域EA1)に設定し、充電時間を短縮すること好ましい。この場合は、走行開始充電率SOCsとして、上限値SOC1Hが選択される。 This allows the secondary battery 11 to be operated while ensuring the necessary predicted power amount W2 and suppressing deterioration. Furthermore, the charging time can be shortened compared to when the secondary battery 11 is always fully charged, making it possible to operate the vehicle 10 efficiently. For example, in summer, the temperature is high and the secondary battery 11 is likely to become hot due to radiant heat and waste heat, which makes it easier for deterioration of the secondary battery 11 to progress. Therefore, in summer, it is preferable to set the SOC region to be used on the low SOC side (for example, region EA1 in Figure 4) and shorten the charging time. In this case, the upper limit value SOC1H is selected as the driving start charging rate SOCs.

逆に、気温が低い冬期においては、図1のグラフG2に示したように、抵抗値比率DCRが大きくなるため、開回路電圧OCVに対して放電時の閉回路電圧CCVが低くなりやすい。これにより、実際のSOCと比較して実際利用できる電池容量が小さくなる(一般に温度特性、レート特性の依存性が高い)。一方、グラフG6に示したように、20℃以下の低い温度では劣化の進行速度は遅くなる。従って、冬期においては、電力量の確保を優先し、使用SOC領域を高SOC側(例えば図4の領域EA2)に設定することが好ましい。この場合は、走行開始充電率SOCsとして、上限値SOC2Hを選択する。 Conversely, in winter when temperatures are low, as shown in graph G2 of FIG. 1, the resistance ratio DCR increases, so the closed circuit voltage CCV during discharge tends to be lower than the open circuit voltage OCV. This results in a smaller battery capacity that can actually be used compared to the actual SOC (which is generally highly dependent on temperature and rate characteristics). On the other hand, as shown in graph G6, the rate of deterioration slows down at low temperatures below 20°C. Therefore, in winter, it is preferable to prioritize securing the amount of power and set the SOC region to the high SOC side (for example, region EA2 in FIG. 4). In this case, the upper limit value SOC2H is selected as the driving start charging rate SOCs.

二次電池、特にリチウムイオン電池の劣化状態は、使用したSOCの範囲、使用温度、通電電流、稼働電圧範囲等により劣化の進行速度が異なる。このため、走行開始状態決定部114は、これらの関係を式または、マップでデータベース化したものから、最適な使用SOC領域を選択する。 The rate at which the deterioration of a secondary battery, particularly a lithium-ion battery, progresses varies depending on the range of SOC used, the temperature at which it is used, the current flowing through it, the operating voltage range, etc. For this reason, the driving start state determination unit 114 selects the optimal SOC range to be used from a database of these relationships in the form of an equation or map.

[第3実施形態]
次に、好適な第3実施形態について説明する。なお、以下の説明において、上述した他の実施形態の各部に対応する部分には同一の符号を付し、その説明を省略する場合がある。
図5は、第3実施形態における時系列データD10の構造を示す図である。第3実施形態の構成は第2実施形態のもの(図3)と同様であるが、各車両10のデータ処理部12が出力する時系列データD10は、図5に示すように構成されている。
[Third embodiment]
Next, a preferred third embodiment will be described. In the following description, the same reference numerals are used to designate parts corresponding to those in the other embodiments described above, and the description thereof may be omitted.
Fig. 5 is a diagram showing the structure of the time series data D10 in the third embodiment. The configuration of the third embodiment is similar to that of the second embodiment (Fig. 3), but the time series data D10 output by the data processing unit 12 of each vehicle 10 is configured as shown in Fig. 5.

図5における各行は、時系列データD10のレコードであり、データベース更新部118(図3参照)は、例えば、車両10の走行時に所定のサンプリング周期毎に一つのレコードを作成する。また、各レコードには、日付D11、時刻D12、車両経度D13、車両緯度D14、電池温度D15、電池電圧D16、電池電流D17および電力量D18が含まれている。 Each row in FIG. 5 is a record of the time series data D10, and the database update unit 118 (see FIG. 3) creates one record for each predetermined sampling period while the vehicle 10 is traveling. Each record also includes the date D11, the time D12, the vehicle longitude D13, the vehicle latitude D14, the battery temperature D15, the battery voltage D16, the battery current D17, and the amount of power D18.

日付D11および時刻D12とは、サンプリングタイミングの日付および時刻である。また、車両経度D13および車両緯度D14は、サンプリングタイミングにおける車両10の経度および緯度である。電池温度D15、電池電圧D16、電池電流D17は、サンプリングタイミングにおける二次電池11の温度、出力電圧および出力電流である。また、電力量D18は、二次電池11が最後に充電された後、該サンプリングタイミングまでに二次電池11から出力された電力量である。 The date D11 and time D12 are the date and time of the sampling timing. The vehicle longitude D13 and vehicle latitude D14 are the longitude and latitude of the vehicle 10 at the sampling timing. The battery temperature D15, battery voltage D16, and battery current D17 are the temperature, output voltage, and output current of the secondary battery 11 at the sampling timing. The amount of power D18 is the amount of power output from the secondary battery 11 up to the sampling timing after the secondary battery 11 was last charged.

各車両10のデータ処理部12は、サンプリングタイミング毎に、リアルタイムで時系列データD10を解析部120に無線で送信する。これにより、解析部120は、電力量データベース142および電池劣化データベース144に蓄積するデータをリアルタイムで生成する。そして、データベース更新部118は、解析部120が生成したデータに基づいて、電力量データベース142と、電池劣化データベース144と、をリアルタイムに更新する。 The data processing unit 12 of each vehicle 10 wirelessly transmits the time series data D10 to the analysis unit 120 in real time at each sampling timing. As a result, the analysis unit 120 generates data to be stored in the power amount database 142 and the battery deterioration database 144 in real time. The database update unit 118 then updates the power amount database 142 and the battery deterioration database 144 in real time based on the data generated by the analysis unit 120.

但し、各車両10のデータ処理部12は、必ずしも時系列データD10をリアルタイムで解析部120に送信する必要はない。例えば、データ処理部12は、二次電池11の充電完了後に時系列データD10の蓄積を開始し、その後に当該車両10が充電のために再び充電装置200に接続された際に、蓄積した時系列データD10を解析部120に供給してもよい。この場合、データベース更新部118は、車両10が充電装置200に接続されている期間中に電力量データベース142および電池劣化データベース144を更新することになる。 However, the data processing unit 12 of each vehicle 10 does not necessarily need to transmit the time series data D10 to the analysis unit 120 in real time. For example, the data processing unit 12 may start accumulating the time series data D10 after charging of the secondary battery 11 is completed, and then supply the accumulated time series data D10 to the analysis unit 120 when the vehicle 10 is again connected to the charging device 200 for charging. In this case, the database update unit 118 updates the power amount database 142 and the battery deterioration database 144 while the vehicle 10 is connected to the charging device 200.

また、解析部120は、時系列データD10に基づいて、時間とSOCの関係をSOCの階級幅毎に時間を蓄積する。そして、時系列データにおいて所定時間以上、SOCが略一定である所定範囲に滞在している時間を検出する。ここで検出した時間はSOCが変動しない、すなわち電池の使用量が少ない、例えば「駐停車期間」である。車両10は、駐停車期間においても、補機等に電力を供給するため、SOCは若干変動するが、ほぼ一定であると考えることができる。この駐停車時間におけるSOCを休止区間滞在SOCと呼ぶ。解析部120は、滞在時間とともに、この時の休止区間滞在SOCも抽出する。例えば、図5の時刻t14~t20の区間Tr10においては、車両経度D13および車両緯度D14は一定値(L13およびLo13)になっている。そこで、解析部120は、当該期間Tr10を駐停車区間として同定する。 The analysis unit 120 also accumulates the time for each SOC class width for the relationship between time and SOC based on the time series data D10. Then, it detects the time in the time series data during which the SOC remains in a predetermined range where it is approximately constant for a predetermined time or more. The detected time is, for example, a "parking period" during which the SOC does not fluctuate, i.e., the battery usage is low. Even during the parking period, the vehicle 10 supplies power to auxiliary equipment, etc., so the SOC fluctuates slightly, but it can be considered to be approximately constant. The SOC during this parking period is called the pause section stay SOC. The analysis unit 120 extracts the pause section stay SOC at this time along with the stay time. For example, in the section Tr10 from time t14 to t20 in FIG. 5, the vehicle longitude D13 and vehicle latitude D14 are constant values (L13 and Lo13). Therefore, the analysis unit 120 identifies the period Tr10 as the parking section.

走行開始状態決定部114は、二次電池11の想定温度Tassを受信する機能と、受信した想定温度Tassが許容される劣化挙動の閾値の温度よりも高い場合に、二次電池11の休止区間滞在SOCが低くなるように、走行開始条件(SOCs,Vs)を決定する機能と、を備えると一層好ましい。 It is more preferable that the driving start state determination unit 114 has a function of receiving the assumed temperature Tass of the secondary battery 11, and a function of determining the driving start conditions (SOCs, Vs) so that the rest section stay SOC of the secondary battery 11 is low when the received assumed temperature Tass is higher than the threshold temperature of the acceptable deterioration behavior.

また、解析部120は、車両10の走行期間と、滞在期間とを分析したパターンに基づいて、走行時における標準電力量と温度の関係を算出する。さらに、解析部120は、配送ルート等のルート情報を複数の部分経路に分割し、各々の部分経路における電池電流D17の平均値、SOCの変動幅(ΔSOC)、中心SOC(部分経路におけるSOCの中央値)等の関係を解析する。 The analysis unit 120 also calculates the relationship between the standard amount of power and temperature during driving based on the pattern obtained by analyzing the driving period and stay period of the vehicle 10. Furthermore, the analysis unit 120 divides route information such as a delivery route into multiple partial routes, and analyzes the relationship between the average battery current D17, the SOC fluctuation range (ΔSOC), the central SOC (the median SOC of the partial routes), etc. for each partial route.

そして、解析部120は、その解析結果を、「詳細経路走行データベース」として、データベース更新部118を介して電力量データベース142に記憶させる。そして、走行開始状態決定部114は、この詳細経路走行データベースと、電池電圧D16との関係に基づいて、分割した部分経路における二次電池11の劣化状態を予測する。これにより、走行開始状態決定部114は、劣化状態の予測値において、劣化が抑制されるような使用SOC領域を決定することができる。 The analysis unit 120 then stores the analysis results as a "detailed route travel database" in the power amount database 142 via the database update unit 118. The travel start state determination unit 114 then predicts the degradation state of the secondary battery 11 in the divided partial route based on the relationship between this detailed route travel database and the battery voltage D16. This allows the travel start state determination unit 114 to determine a usable SOC range in which degradation is suppressed in the predicted value of the degradation state.

また、解析部120は、電力量データベース142に必要なデータも抽出し、抽出したデータに基づいて、データベース更新部118を介して電力量データベース142を更新する。
また、ルート情報は、ナビゲーションシステム(図示せず)によって推奨された、時間優先、距離最短ルートと連動させると好ましい。さらに、該ナビゲーションシステムは、一方通行など交通規制を反映して、効率的な配達順を時間帯毎に考慮した一筆書きルートを提案できるものが好ましく、ルート情報は、この一筆書きルートと連動させると好ましい。これにより、配送時の典型的な予測電力量Wrecを算出することができる。
The analysis unit 120 also extracts data necessary for the power amount database 142, and updates the power amount database 142 via the database update unit 118 based on the extracted data.
In addition, the route information is preferably linked to a time-prioritized, shortest distance route recommended by a navigation system (not shown). Furthermore, the navigation system is preferably capable of proposing a one-stroke route that reflects traffic regulations such as one-way streets and takes into account efficient delivery orders for each time period, and the route information is preferably linked to this one-stroke route. This makes it possible to calculate a typical predicted energy Wrec during delivery.

ルート配送の履歴が蓄積されてゆくことにより、電力量データベース142が充実し、これによって典型的なルートにおける予測電力量W2の算出精度がより向上する。
この履歴蓄積時に、解析部120は、容量に関する劣化度SOHQ(劣化状態)や、抵抗に関する劣化度SOHR(劣化状態)を算出し、これら算出結果を電池劣化データベース144に記録する。但し、劣化度SOHQ,SOHRは、車両内部のBMSや二次電池管理装置100Aで算出するのみならず、充電装置200によって算出してもよい。例えば、充電装置200が二次電池11に対して充電する際の二次電池11の電圧、電流、温度等に基づいて劣化度SOHQ,SOHRを検出してもよい。
As the route delivery history is accumulated, the power amount database 142 is enriched, thereby improving the accuracy of calculation of the predicted power amount W2 for a typical route.
During this history accumulation, the analysis unit 120 calculates the degree of deterioration SOHQ (deterioration state) related to the capacity and the degree of deterioration SOHR (deterioration state) related to the resistance, and records these calculation results in the battery deterioration database 144. However, the degrees of deterioration SOHQ and SOHR may be calculated not only by the BMS inside the vehicle or the secondary battery management device 100A, but also by the charging device 200. For example, the degrees of deterioration SOHQ and SOHR may be detected based on the voltage, current, temperature, etc. of the secondary battery 11 when the charging device 200 charges the secondary battery 11.

電池劣化データベース144は、二次電池11の使用条件と、二次電池11の内部抵抗と、容量の変化を推定できる相関データと、を記憶している。また、上述したように、二次電池11の使用条件は、少なくとも温度、電流、使用電圧範囲、使用SOC領域、使用電気量および休止比率のうち複数を含んでいる。ここで、劣化計算単位は時系列、1日単位、サイクル単位、回数単位の何れを採用してもよい。 The battery deterioration database 144 stores the usage conditions of the secondary battery 11, the internal resistance of the secondary battery 11, and correlation data that can estimate changes in capacity. As described above, the usage conditions of the secondary battery 11 include at least two or more of the temperature, current, usage voltage range, usage SOC range, amount of electricity used, and rest ratio. Here, the deterioration calculation unit may be any of a time series, daily unit, cycle unit, or number of times unit.

さらに、車両10における二次電池11のSOC・温度の滞在時間の分析ログを利用すると、二次電池11の稼働領域について、劣化係数に重み係数γを乗算して劣化度を算出でき、簡易な方式で劣化を考慮できる。本実施形態における劣化推定は、上述の方式のみならず、二次電池11のSOCの使用範囲と温度と劣化との相関データを使用するものが適用できる。 Furthermore, by using the analysis log of the SOC and temperature residence time of the secondary battery 11 in the vehicle 10, the deterioration degree can be calculated for the operating range of the secondary battery 11 by multiplying the deterioration coefficient by a weighting coefficient γ, and deterioration can be taken into account in a simple manner. In this embodiment, the deterioration estimation can be performed not only by the above-mentioned method, but also by using correlation data between the operating range of the SOC of the secondary battery 11, the temperature, and deterioration.

また、走行開始状態決定部114は、二次電池11の走行開始充電率SOCsを、予測電力量W2と、現在のSOCと、に基づいて、次のように決定するとよい。まず、現在の二次電池11の劣化を反映した放電曲線において、出力下限値のSOC(例えば10%)から、SOCの高い側に向かって予測電力量W2が確保できる上限のSOC値を算出する。このSOCをSOCreqと呼ぶ。 The running start state determination unit 114 may determine the running start charging rate SOCs of the secondary battery 11 based on the predicted power amount W2 and the current SOC as follows. First, in a discharge curve reflecting the current deterioration of the secondary battery 11, the upper limit SOC value at which the predicted power amount W2 can be secured is calculated from the SOC of the output lower limit value (e.g., 10%) toward the higher SOC side. This SOC is called SOCreq.

次に、走行開始状態決定部114は、現状のSOCであるSOCpreから予測電力量W2を出力した場合の下限のSOCを計算し、計算したSOCが前出の出力下限値のSOCよりも高い場合には、現状のSOCであるSOCpreを走行開始充電率SOCsにするとよい。一方、現状のSOCから計算したSOCが出力下限値のSOC以下になる場合は、SOCreqを走行開始充電率SOCsにするとよい。 Next, the running start state determination unit 114 calculates the lower limit SOC when the predicted power amount W2 is output from the current SOC, SOCpre , and if the calculated SOC is higher than the above-mentioned output lower limit SOC, it may set the current SOC, SOCpre , as the running start charging rate SOCs. On the other hand, if the SOC calculated from the current SOC is equal to or lower than the output lower limit SOC, it may set the running start charging rate SOCs to SOCreq.

[第4実施形態]
図6は、好適な第4実施形態による二次電池管理システムS4のブロック図である。なお、以下の説明において、上述した他の実施形態の各部に対応する部分には同一の符号を付し、その説明を省略する場合がある。
二次電池管理システムS4は、充電装置200と、二次電池管理装置100D(コンピュータ)と、電力量データベース142と、電池劣化データベース144と、運行スケジュール立案部146と、を備えている。
[Fourth embodiment]
6 is a block diagram of a secondary battery management system S4 according to a preferred fourth embodiment. In the following description, the same reference numerals are used to designate parts corresponding to the parts of the other embodiments described above, and the description thereof may be omitted.
The secondary battery management system S4 includes a charging device 200, a secondary battery management device 100D (computer), an electric energy database 142, a battery deterioration database 144, and an operation schedule planning unit 146.

ここで、運行スケジュール立案部146は、複数の車両10が配達すべき荷物の重量、寸法、配達先の位置等に応じて、各々の車両10の運行スケジュールを立案するものである。また、二次電池管理装置100Dは、第2実施形態の二次電池管理装置100B(図3参照)と同様の構成を備え、さらに充電スケジュール立案部122を備えている。充電スケジュール立案部122は、運行スケジュール立案部146が出力した運行スケジュールに基づいて、各々の車両10の充電スケジュール、すなわち充電開始時刻や充電終了時刻等を立案する。 The operation schedule planning unit 146 plans operation schedules for each vehicle 10 according to the weight, dimensions, and delivery destination locations of the packages to be delivered by the multiple vehicles 10. The secondary battery management device 100D has a configuration similar to that of the secondary battery management device 100B of the second embodiment (see FIG. 3), and further includes a charging schedule planning unit 122. The charging schedule planning unit 122 plans a charging schedule for each vehicle 10, i.e., charging start times, charging end times, etc., based on the operation schedule output by the operation schedule planning unit 146.

本実施形態における二次電池管理装置100Dは、デューティ比決定部116を有していてもよい。デューティ比決定部116は、充電完了までの中で通電状態が占める割合であるデューティ比Dtrを決定するものである。ここで、通電状態とは、二次電池11に電流を供給する状態である。また、二次電池11に電流を供給しない、または閾値電流より小さな電流を供給する状態を休止状態とする。 The secondary battery management device 100D in this embodiment may have a duty ratio determination unit 116. The duty ratio determination unit 116 determines the duty ratio Dtr, which is the proportion of the current-carrying state until charging is completed. Here, the current-carrying state is a state in which a current is supplied to the secondary battery 11. In addition, a state in which no current is supplied to the secondary battery 11, or a state in which a current smaller than the threshold current is supplied, is a pause state.

そして、デューティ比決定部116は、電池劣化データベース144に基づいて二次電池11の劣化状態を判定し、二次電池11の劣化が進行するほどデューティ比Dtrを下げる機能を有している。充電制御部124は、上述した走行開始条件(SOCs,Vs)と、デューティ比Dtrと、に基づいて充電装置200の完了時間を制御する。充電後の休止時間を電池の劣化度に合わせてコントロールすることで、より電池の劣化を抑制することが可能になる。なお、二次電池管理装置100Dはデューティ比決定部116がない構成も可能である。 The duty ratio determination unit 116 has a function of determining the degradation state of the secondary battery 11 based on the battery degradation database 144, and lowering the duty ratio Dtr as the degradation of the secondary battery 11 progresses. The charging control unit 124 controls the completion time of the charging device 200 based on the above-mentioned running start conditions (SOCs, Vs) and the duty ratio Dtr. By controlling the rest time after charging according to the degree of battery degradation, it is possible to further suppress battery degradation. Note that the secondary battery management device 100D can also be configured without the duty ratio determination unit 116.

本実施形態は、特に商用のラスト1マイルの配達システムにおいて、車両10として電気自動車を採用する場合に適用して好適な実施形態である。運行スケジュール立案部146は、配達エリアにおける、時間帯別の全戸配達最適標準ルートRS(t)を設定する。ここで、tは配達開始時刻または配達時間帯である。 This embodiment is particularly suitable for use in commercial last-mile delivery systems where an electric vehicle is used as the vehicle 10. The operation schedule planning unit 146 sets an optimal standard route RS(t) for home-to-home delivery by time period in the delivery area. Here, t is the delivery start time or delivery time period.

充電装置200が、営業所のみに配置されている場合、電力量算出部112は、配送または物流システムと連携し、運行スケジュール立案部146は、時間帯毎の配達荷物を仕分け、配送エリアのルート毎に必要な予測電力量W1を電力量データベース142に基づいて算出する。ここで、予測電力量W1も配達開始時刻tの関数であるため、以下「予測電力量W1(t)」と呼ぶことがある。 When the charging device 200 is installed only at the business office, the power calculation unit 112 cooperates with the delivery or logistics system, and the operation schedule planning unit 146 sorts the delivery packages by time period and calculates the predicted amount of power W1 required for each route in the delivery area based on the power database 142. Here, the predicted amount of power W1 is also a function of the delivery start time t, so hereinafter it may be referred to as "predicted amount of power W1(t)".

さらに、電力量算出部112は、車両10における荷重、二次電池11の現在の劣化度、気温、想定温度Tass、天候等の条件に基づいて、予測電力量W1(t)を補正して、予測電力量W2(t)を決定する。走行開始状態決定部114は、決定された予測電力量W2(t)と、想定温度Tassと、に基づいて、使用SOC領域(例えば図4の領域EA1,EA2)を決定し、走行開始条件(SOCs,Vs)を決定する。 The power calculation unit 112 further corrects the predicted power amount W1(t) based on conditions such as the load on the vehicle 10, the current deterioration level of the secondary battery 11, the air temperature, the assumed temperature Tass, and weather, to determine the predicted power amount W2(t). The running start state determination unit 114 determines the use SOC region (e.g., regions EA1 and EA2 in FIG. 4) based on the determined predicted power amount W2(t) and the assumed temperature Tass, and determines the running start condition (SOCs, Vs).

その際、走行開始状態決定部114は、電池劣化データベース144を参照し、予測電力量W2が確保でき、かつ、使用時の最低SOCがSOC下限値(例えば10%)を下回らないように上限のSOC値を決定する。そして、走行開始状態決定部114は、その計算結果に基づいて、走行開始条件(SOCs,Vs)を出力する。その際、現在の二次電池11の電圧が走行開始電圧Vsよりも高い場合は充電を行うことなく、配達を開始する。一方、現在の二次電池11の電圧が走行開始電圧Vsよりも低い場合は、充電装置200によって二次電池11に対する充電を行うとよい。こうすることで全体の充電時間を節約し短縮することができる。 At this time, the driving start state determination unit 114 refers to the battery deterioration database 144 and determines an upper SOC value so that the predicted power amount W2 can be secured and the minimum SOC during use does not fall below the SOC lower limit value (e.g. 10%). Then, the driving start state determination unit 114 outputs the driving start condition (SOCs, Vs) based on the calculation result. At this time, if the current voltage of the secondary battery 11 is higher than the driving start voltage Vs, delivery is started without charging. On the other hand, if the current voltage of the secondary battery 11 is lower than the driving start voltage Vs, it is recommended that the secondary battery 11 be charged by the charging device 200. This can save and shorten the overall charging time.

多量の荷物を配達するために要する電力量は、フル充電した1台の車両10で配達する場合と、複数台の車両10が時間帯を分割しつつ配達する場合と、で異なる。一般的には、荷物が多量である場合には、複数の車両10で時間帯を分割しつつ配達した場合のほうが、車両10の充電時間を短くすることができ、かつ、二次電池11の劣化も抑制できる。そこで、運行スケジュール立案部146は、到着時間指定がない荷物を、配達ルートで分散するよう機械学習を利用したデータ選択システムを使用する。 The amount of electricity required to deliver a large amount of luggage differs between when a single fully charged vehicle 10 is used to deliver the luggage and when multiple vehicles 10 deliver the luggage over separate time periods. In general, when there is a large amount of luggage, when multiple vehicles 10 deliver the luggage over separate time periods, the charging time of the vehicle 10 can be shortened and deterioration of the secondary battery 11 can be suppressed. Therefore, the operation schedule planning unit 146 uses a data selection system that utilizes machine learning to distribute luggage without a specified arrival time along the delivery route.

そして、充電スケジュール立案部122は、各車両が営業所に(充電装置200の近傍に)駐車している時間帯に二次電池11を充電するように、充電スケジュールをコントロールしている。これにより、二次電池管理システムS4においては、顧客満足度を低下させず、かつ効率的に荷物を配送することができる。さらに、二次電池管理システムS4によれば、電動車両である車両10の電池劣化も抑制でき、電池の搭載量の余分を少なくすることが可能になる。 The charging schedule planning unit 122 controls the charging schedule so that the secondary battery 11 is charged during the time period when each vehicle is parked at the office (near the charging device 200). This allows the secondary battery management system S4 to deliver packages efficiently without reducing customer satisfaction. Furthermore, the secondary battery management system S4 can also suppress battery deterioration in the vehicle 10, which is an electric vehicle, making it possible to reduce excess battery capacity.

図7は、第4実施形態の二次電池管理装置100Dによって実行される走行開始充電率算出プログラムのフローチャートである。
図7のステップS11において、電力量算出部112は、移動予定経路の予定ルート情報Rtと、車両10の車重と、車両10の荷重と、配達時の想定温度Tassと、を受信する。そして、電力量算出部112は、受信した情報に基づいて電力量データベース142にアクセスし、予測電力量W1を取得する。なお、上述したように、電力量データベース142は、移動日時、移動時外気温等を有する履歴情報と、標準的な所要電力量と、を対応付けて記憶している。
FIG. 7 is a flowchart of a start-of-travel charging rate calculation program executed by the secondary-battery management unit 100D of the fourth embodiment.
7, the power amount calculation unit 112 receives planned route information Rt of the planned travel route, the vehicle weight of the vehicle 10, the load of the vehicle 10, and the estimated temperature Tass at the time of delivery. Then, the power amount calculation unit 112 accesses the power amount database 142 based on the received information to obtain the predicted power amount W1. As described above, the power amount database 142 stores history information including the travel date and time, the outside air temperature at the time of travel, etc., in association with the standard required power amount.

次に、ステップS12において、電力量算出部112は、想定温度Tassを取得し、これと同時に二次電池11の現在の劣化情報(劣化度SOHQ,SOHR等)を取得する。そして、取得した情報と電池劣化データベース144とに基づいて、必要に応じて予測電力量W1を補正することにより、予測電力量W2を算出する。 Next, in step S12, the power calculation unit 112 acquires the assumed temperature Tass and, at the same time, acquires the current deterioration information (deterioration levels SOHQ, SOHR, etc.) of the secondary battery 11. Then, based on the acquired information and the battery deterioration database 144, the predicted power amount W1 is corrected as necessary to calculate the predicted power amount W2.

予測電力量W2は、例えば、補正式「W2=α×W1+βd」に基づいて求めることができる。ここで、αは補正係数、βdは補機電力マージン等である。また、これに代えて、例えば補正式「W2=α×W1×βdd」に基づいて、予測電力量W1に対して、倍数で補正して予測電力量W2を算出してもよい。ここで、βddは倍数による補機電力マージン等である。さらに、予測電力量W1に対して固定値を増減して予測電力量W2を算出してもよい。 The predicted power amount W2 can be calculated, for example, based on the correction formula "W2 = α x W1 + βd". Here, α is a correction coefficient, and βd is an auxiliary power margin, etc. Alternatively, the predicted power amount W2 may be calculated by correcting the predicted power amount W1 by a multiple, for example, based on the correction formula "W2 = α x W1 x βdd". Here, βdd is an auxiliary power margin, etc., based on a multiple. Furthermore, the predicted power amount W2 may be calculated by increasing or decreasing a fixed value with respect to the predicted power amount W1.

次に、ステップS13において、走行開始状態決定部114は、二次電池11の現状のSOCにおいて予測電力量W2を出力可能であるか否かを判定する。すなわち、現在のSOCを最大SOCとしたときに、SOC下限値(例えば10%)に至るまでのSOC領域で予測電力量W2が取得できるか否かを判定する。そして、予測電力量W2が出力可能な場合は「Yes」と判定され、処理はステップS18に進む。ステップS18においては、現在のSOCを走行開始充電率SOCsとして出力する。一方、二次電池11の現在のSOCでは予測電力量W2を出力できない場合、ステップS13において「No」と判定され、処理はステップS14に進む。 Next, in step S13, the driving start state determination unit 114 determines whether the predicted power amount W2 can be output with the current SOC of the secondary battery 11. That is, when the current SOC is set to the maximum SOC, it determines whether the predicted power amount W2 can be obtained in the SOC range up to the SOC lower limit value (e.g., 10%). If the predicted power amount W2 can be output, it is determined as "Yes" and the process proceeds to step S18. In step S18, the current SOC is output as the driving start charging rate SOCs. On the other hand, if the predicted power amount W2 cannot be output with the current SOC of the secondary battery 11, it is determined as "No" in step S13 and the process proceeds to step S14.

ステップS14において、走行開始状態決定部114は、SOC下限値を最小値として予測電力量W2を取得できるSOC領域、すなわちSOC領域EA01(図示せず)を算出する。次に、処理がステップS15に進むと、走行開始状態決定部114は、劣化が少ない領域であるSOC50%を中心にして、予測電力量W2を取得できるSOC領域、すなわちSOC領域EA02(図示せず)を算出する。 In step S14, the driving start state determination unit 114 calculates the SOC region in which the predicted power amount W2 can be obtained with the SOC lower limit value as the minimum value, i.e., SOC region EA01 (not shown). Next, when the process proceeds to step S15, the driving start state determination unit 114 calculates the SOC region in which the predicted power amount W2 can be obtained, i.e., SOC region EA02 (not shown), centered around SOC 50%, which is a region with little degradation.

次に、処理がステップS16に進むと、走行開始状態決定部114は、SOC上限値(例えば100%)を最大値として予測電力量W2を取得できるSOC領域、すなわちSOC領域EA03(図示せず)を算出する。次に、処理がステップS17に進むと、走行開始状態決定部114は、電池劣化データベース144を参照し、SOC領域EA01,EA02,EA03のうち、二次電池11の劣化が最小であると予測されるものを、使用SOC領域として選択する。次に、処理がステップS19に進むと、走行開始状態決定部114は、使用SOC領域の最大値を走行開始充電率SOCsとして出力する。 Next, when the process proceeds to step S16, the driving start state determination unit 114 calculates the SOC region in which the predicted power amount W2 can be obtained with the SOC upper limit value (e.g., 100%) as the maximum value, that is, the SOC region EA03 (not shown). Next, when the process proceeds to step S17, the driving start state determination unit 114 refers to the battery deterioration database 144 and selects, as the use SOC region, one of the SOC regions EA01, EA02, and EA03 in which the deterioration of the secondary battery 11 is predicted to be the smallest. Next, when the process proceeds to step S19, the driving start state determination unit 114 outputs the maximum value of the use SOC region as the driving start charging rate SOCs.

上述した例では、3つのSOC領域EA01,EA02,EA03を算出し、その中から使用SOC領域を決定することにより走行開始条件(SOCs,Vs)を決定したが、走行開始条件(SOCs,Vs)の決定方法はこれに限定されるわけではない。例えば、走行開始充電率SOCsの候補となる複数のSOCを予め決定しておき、それぞれについて、予測電力量W2を確保できるSOC領域を計算し、計算した各々のSOC領域について電池劣化データベース144を参照することにより、使用SOC領域を決定してもよい。なお、計算した複数のSOC領域のうち、劣化度が等しいものがあれば、走行可能区間が最も長くなる高SOC側のSOC領域を選択することが好ましい。 In the above example, the driving start conditions (SOCs, Vs) are determined by calculating three SOC ranges EA01, EA02, and EA03 and determining the usable SOC range from among them, but the method of determining the driving start conditions (SOCs, Vs) is not limited to this. For example, multiple SOCs that are candidates for the driving start charge rate SOCs may be determined in advance, and for each of them, the SOC range in which the predicted power amount W2 can be secured may be calculated, and the usable SOC range may be determined by referring to the battery deterioration database 144 for each calculated SOC range. Note that if there are multiple calculated SOC ranges with the same degree of deterioration, it is preferable to select the SOC range on the higher SOC side that provides the longest driving range.

[第5実施形態]
図8は、好適な第5実施形態による充電ナビゲーションシステムS5のブロック図である。なお、以下の説明において、上述した他の実施形態の各部に対応する部分には同一の符号を付し、その説明を省略する場合がある。
充電ナビゲーションシステムS5は、二次電池管理装置100E(コンピュータ)と、車両10と、を備えている。また、充電ナビゲーションシステムS5は、天気予報システム131と、配達ナビケーションシステム132と、トラックスケールシステム133と、に接続されている。
[Fifth embodiment]
8 is a block diagram of a charging navigation system S5 according to a preferred fifth embodiment. In the following description, the same reference numerals are used to designate parts corresponding to those in the other embodiments described above, and the description thereof may be omitted.
The charging navigation system S5 includes a secondary battery management device 100E (computer) and a vehicle 10. The charging navigation system S5 is also connected to a weather forecast system 131, a delivery navigation system 132, and a truck scale system 133.

ここで、天気予報システム131は、現状の気温、天候および将来の気温、天候等の天気予報を配信するものである。また、配達ナビケーションシステム132は、運送すべき複数の荷物の搬送先、重量、寸法等に基づいて、各車両10に積載する荷物および搬送ルートを決定するものである。また、トラックスケールシステム133は、各車両10の車両IDと、車重、荷重とを記憶、管理するものである。 Here, the weather forecast system 131 distributes weather forecasts such as the current temperature and weather, as well as future temperature and weather. The delivery navigation system 132 determines the luggage to be loaded onto each vehicle 10 and the transportation route based on the destination, weight, dimensions, etc. of the multiple luggage to be transported. The truck scale system 133 stores and manages the vehicle ID, vehicle weight, and load of each vehicle 10.

車両10は、動力源としての二次電池11と、データ処理部12と、車両BMS(Battery Management System)16と、運行履歴記録部18と、を備えている。車両BMS16は、二次電池11の状態を検知するものである。運行履歴記録部18は、車両10の運行履歴を記録するものである。運行履歴記録部18は、車両BMS16の内部に配置されていてもよい。 The vehicle 10 includes a secondary battery 11 as a power source, a data processing unit 12, a vehicle BMS (Battery Management System) 16, and an operation history recording unit 18. The vehicle BMS 16 detects the state of the secondary battery 11. The operation history recording unit 18 records the operation history of the vehicle 10. The operation history recording unit 18 may be disposed inside the vehicle BMS 16.

図9は、第5実施形態における車両BMS16の電池劣化検出部のブロック図である。車両BMS16は、SOH演算部16aを備えている。SOH演算部16aは、二次電池11の電圧、電流および温度に基づいて、劣化度SOHを演算する。なお、劣化度SOHは、上述した劣化度SOHQ,SOHR等を総称したものである。 Figure 9 is a block diagram of the battery deterioration detection unit of the vehicle BMS 16 in the fifth embodiment. The vehicle BMS 16 is equipped with a SOH calculation unit 16a. The SOH calculation unit 16a calculates the deterioration level SOH based on the voltage, current, and temperature of the secondary battery 11. Note that the deterioration level SOH is a general term for the deterioration levels SOHQ, SOHR, etc. described above.

図8に戻り、二次電池管理装置100Eのハードウエア構成は、第1実施形態の二次電池管理装置100Aと同様である。二次電池管理装置100Eは、電池稼働領域判定選択部103と、配達予定車両条件入力部104と、予測電力量計算部105(電力量算出部)と、電力量データベース142と、を備えている。また、電池稼働領域判定選択部103は、予測電力量補正部106(電力量算出部)と、走行開始状態決定部114と、データ解析部109と、電池劣化データベース144と、を備えている。 Returning to FIG. 8, the hardware configuration of the secondary battery management device 100E is the same as that of the secondary battery management device 100A of the first embodiment. The secondary battery management device 100E includes a battery operating range determination and selection unit 103, a delivery schedule vehicle condition input unit 104, a predicted power amount calculation unit 105 (power amount calculation unit), and a power amount database 142. The battery operating range determination and selection unit 103 also includes a predicted power amount correction unit 106 (power amount calculation unit), a running start state determination unit 114, a data analysis unit 109, and a battery deterioration database 144.

二次電池管理装置100E内の配達予定車両条件入力部104は、車両BMS16から、データ処理部12を介して、電池の劣化度SOHQ,SOHRと、セル温度Tcellと、現在の車両のSOCと、を取得する。また、配達予定車両条件入力部104は、天気予報システム131から気温等の環境温度Taと、天気の情報とを取得し、物流会社等が利用している配達ナビケーションシステム132から配送・配達の予定経路の予定ルート情報Rtを取得する。さらに、配達予定車両条件入力部104は、物流会社が有するトラックスケールシステム133から車両IDと、車重と、荷重とを連動して取得する。 The scheduled delivery vehicle condition input unit 104 in the secondary battery management device 100E acquires the battery deterioration levels SOHQ, SOHR, cell temperature Tcell, and the current vehicle SOC from the vehicle BMS 16 via the data processing unit 12. The scheduled delivery vehicle condition input unit 104 also acquires the ambient temperature Ta, such as air temperature, and weather information from the weather forecast system 131, and acquires planned route information Rt of the planned route for shipping and delivery from a delivery navigation system 132 used by logistics companies, etc. Furthermore, the scheduled delivery vehicle condition input unit 104 acquires the vehicle ID, vehicle weight, and load in conjunction with each other from a truck scale system 133 owned by the logistics company.

予測電力量計算部105は、電力量データベース142を参照するために、必要な参照条件を抽出し、予測電力量W1を計算する。電池稼働領域判定選択部103は、予測電力量W1に対して、今回の走行条件と参照条件との差分がある場合、予測電力量補正部106において予測電力量W1を補正し、予測電力量W2を求める。上述したように、予測電力量W2は、例えば、「W2=α×W1+βd」、「W2=α×W1×βdd」に基づいて、算出してもよく、予測電力量W1に対して固定値を増減して予測電力量W2を算出してもよい。以下、図10を参照し、予測電力量W1を倍数で補正して予測電力量W2を求める例について説明する。 The predicted power calculation unit 105 extracts the necessary reference conditions to refer to the power database 142 and calculates the predicted power amount W1. If there is a difference between the current driving conditions and the reference conditions for the predicted power amount W1, the battery operating range determination and selection unit 103 corrects the predicted power amount W1 in the predicted power amount correction unit 106 to obtain the predicted power amount W2. As described above, the predicted power amount W2 may be calculated based on, for example, "W2 = α x W1 + βd" or "W2 = α x W1 x βdd", or the predicted power amount W2 may be calculated by increasing or decreasing a fixed value for the predicted power amount W1. Below, with reference to FIG. 10, an example of calculating the predicted power amount W2 by correcting the predicted power amount W1 by a multiple will be described.

図10は、第5実施形態の電力量データベース142に含まれる電力量補正データD30の模式図である。図10における各行は、電力量補正データD30のレコードであり、各レコードには、ルートD31、電力量D32、冬期係数D33、夏期係数D34、および積み荷50%,80%に対する荷重係数D35,D36が含まれている。電力量D32は、20℃の劣化していない二次電池11を適用し、荷重が100%である場合の、各ルートD31を走行する電力量である。 Figure 10 is a schematic diagram of the power amount correction data D30 included in the power amount database 142 of the fifth embodiment. Each row in Figure 10 is a record of the power amount correction data D30, and each record includes a route D31, power amount D32, winter coefficient D33, summer coefficient D34, and load coefficients D35 and D36 for loads of 50% and 80%. The power amount D32 is the amount of power required to travel each route D31 when an undegraded secondary battery 11 at 20°C is used and the load is 100%.

冬期係数D33は冬期に電力量D32に乗算すべき係数であり、夏期係数D34は夏期に電力量D32に乗算すべき係数である。また、荷重係数D35およびD36は、それぞれ荷重が50%および80%であるときに電力量D32に乗算すべき係数である。車両10がルートAとルートBとを通る場合、予測電力量W1は、両者の電力量D32の和、すなわち「W1=Wa1+Wa2」として求めることができる。走行予定条件が、夏期で、積み荷の量が50%であり、かつ、劣化していない二次電池11を適用する場合は、予測電力量W1に対して、各々の夏期係数D34および荷重係数D35を適用し、「W2=Wa1×α1×β1+Wa2×α1×β2」として予測電力量W2を求めることができる。 The winter coefficient D33 is a coefficient by which the amount of power D32 should be multiplied in winter, and the summer coefficient D34 is a coefficient by which the amount of power D32 should be multiplied in summer. The load coefficients D35 and D36 are coefficients by which the amount of power D32 should be multiplied when the load is 50% and 80%, respectively. When the vehicle 10 travels along route A and route B, the predicted amount of power W1 can be calculated as the sum of the amounts of power D32 of both routes, that is, "W1 = Wa1 + Wa2". When the planned travel conditions are summer, the amount of cargo is 50%, and an undegraded secondary battery 11 is used, the predicted amount of power W2 can be calculated by applying the respective summer coefficients D34 and load coefficients D35 to the predicted amount of power W1, and calculating "W2 = Wa1 x α1 x β1 + Wa2 x α1 x β2".

また、図8において、予測電力量補正部106は、電池劣化データベース144も参照し、予測電力量W2を決定する。走行開始状態決定部114は、第1~第4実施形態のものと同様に、二次電池11の劣化情報と、電池温度と、現在のSOCを使用して、電池の使用SOC領域を算出する。すなわち、走行開始状態決定部114は、予測電力量W2が確保でき、充電時間が短く、かつ、使用時に二次電池11の劣化が小さくなるように、使用SOC領域を算出する。 In FIG. 8, the predicted power amount correction unit 106 also references the battery deterioration database 144 to determine the predicted power amount W2. As in the first to fourth embodiments, the driving start state determination unit 114 calculates the battery's usable SOC range using the deterioration information of the secondary battery 11, the battery temperature, and the current SOC. That is, the driving start state determination unit 114 calculates the usable SOC range so that the predicted power amount W2 can be secured, the charging time is short, and deterioration of the secondary battery 11 during use is small.

そして、走行開始状態決定部114は、使用SOC領域の最大値を走行開始充電率SOCsとして、車両10と、充電装置200(図3参照)とに通知する。充電装置200は、現在SOC値が走行開始充電率SOCsを上回る場合は充電せず、現在SOCが走行開始充電率SOCsに満たない場合は走行開始充電率SOCsまで充電する。 Then, the driving start state determination unit 114 notifies the vehicle 10 and the charging device 200 (see FIG. 3) of the maximum value of the use SOC region as the driving start charging rate SOCs. The charging device 200 does not charge if the current SOC value exceeds the driving start charging rate SOCs, and charges up to the driving start charging rate SOCs if the current SOC is less than the driving start charging rate SOCs.

車両10の運行履歴記録部18は、走行日時、走行時刻、位置情報、電池電圧、電池電流、電池温度、使用電力等を時系列に取得して蓄積し、蓄積結果を、無線または有線の通信により、データ処理部12を介して二次電池管理装置100Eに通信する。そして、電池稼働領域判定選択部103は通信されたデータを蓄積する。データ解析部109は、電力量データベース142用のデータを作成し、電力量データベース142に追加する。また、データ解析部109は、劣化度SOHQ,SOHR、運転条件等、電池劣化データベース144に蓄積する項目を分析抽出し、その結果を電池劣化データベース144に追加する。 The vehicle 10's operation history recording unit 18 acquires and stores the driving date and time, driving time, location information, battery voltage, battery current, battery temperature, power usage, etc. in chronological order, and communicates the stored results to the secondary battery management device 100E via the data processing unit 12 by wireless or wired communication. The battery operating range determination and selection unit 103 then stores the communicated data. The data analysis unit 109 creates data for the power amount database 142 and adds it to the power amount database 142. The data analysis unit 109 also analyzes and extracts items to be stored in the battery deterioration database 144, such as the deterioration levels SOHQ, SOHR, and driving conditions, and adds the results to the battery deterioration database 144.

これにより、車両10の走行毎に、各種データがさらに蓄積され、より適切に予測電力量W2を選択できるようになる。以上のように、必要な予測電力量W2に応じた電力量のみを二次電池11に充電して走行でき、かつ、劣化抑制領域を使用することで、二次電池11の劣化を抑制しながら、効率的な配達、配送が可能となる。また、効率的な電池利用が可能となり、従来の搭載電池量よりもマージンを小さくでき、適正な電池量の車両とすることができ、コストパフォーマンスの向上を図ることができる。 As a result, various data are further accumulated each time the vehicle 10 travels, making it possible to select a more appropriate predicted power amount W2. As described above, the vehicle can travel by charging only the amount of power corresponding to the required predicted power amount W2 into the secondary battery 11, and by using the degradation suppression area, efficient delivery and distribution is possible while suppressing deterioration of the secondary battery 11. Furthermore, efficient battery utilization is possible, the margin can be made smaller than with conventional on-board battery amounts, and a vehicle with an appropriate battery amount can be produced, thereby improving cost performance.

[第6実施形態]
次に、好適な第6実施形態について説明する。なお、以下の説明において、上述した他の実施形態の各部に対応する部分には同一の符号を付し、その説明を省略する場合がある。また、第6実施形態の構成は、第5実施形態のもの(図8参照)と同様であるため、図示を省略する。
Sixth Embodiment
Next, a preferred sixth embodiment will be described. In the following description, the same reference numerals are used to designate parts corresponding to the parts of the other embodiments described above, and the description thereof may be omitted. Also, the configuration of the sixth embodiment is the same as that of the fifth embodiment (see FIG. 8), and therefore illustration thereof will be omitted.

一般的に、電池は大電流での充放電が連続で継続すると、劣化が加速される傾向がある。これを抑制するために、本実施形態においては、二次電池11の劣化と、電池の休止時間比率の関係を予め取得している。そして、電池劣化データベース144には、二次電池11が通電しない休止時間Tr(図示せず)と、二次電池11が通電する通電時間Tc(図示せず)についての情報が蓄積される。この蓄積情報を利用して、休止時間Trが長い場所は、ルートの後半で低SOC側になるようにルートを組むと好ましい。これにより、二次電池11が高SOCで保持されることによる劣化を抑制できる。 Generally, when a battery is continuously charged and discharged at a large current, deterioration tends to accelerate. To prevent this, in this embodiment, the relationship between deterioration of the secondary battery 11 and the battery's downtime ratio is acquired in advance. Then, the battery deterioration database 144 stores information on the downtime Tr (not shown) during which the secondary battery 11 is not energized and the energization time Tc (not shown) during which the secondary battery 11 is energized. Using this accumulated information, it is preferable to create a route such that the locations with long downtime Tr are on the low SOC side in the latter half of the route. This makes it possible to prevent deterioration caused by the secondary battery 11 being maintained at a high SOC.

また、一般的に二次電池11を急速充電すると、電流が大きいために発熱量が増加し内部温度が上昇するなど劣化が進みやすくなる。そのため急速充電後、配送前に二次電池11を使用しない休止時間をある程度設けることが好ましい。二次電池11の通電比率Rdutyは、「Rduty=tc/(tc+tr)」によって求めることができる。この通電比率Rdutyが劣化を促進する閾値Rdth以下になるように、電流値と劣化を促進する通電比率の閾値Rdthとのマップを作成しておくとよい。そして、このマップを参照して、走行開始充電率SOCsの設定後に、推奨配達開始時刻をディスプレイ(図示せず)に表示し、充電後の休止時間終了後に配達開始となるようにスケジューリングするとよい。また、充電機への充電指令の充電終了までの充電時間が充電完了電圧に達してから休止時間を経た後の総時間とし、充電完了時間に休止時間を含むようにすると、充電完了と同時に配達を開始することができる。本実施形態を適用することで、さらに電池の劣化を抑制し、効率的に配達、配送することが可能になる。 In addition, when the secondary battery 11 is generally charged quickly, the amount of heat generated increases due to the large current, causing the internal temperature to rise and the battery to deteriorate. Therefore, it is preferable to provide a certain amount of downtime during which the secondary battery 11 is not used before delivery after the rapid charge. The current duty of the secondary battery 11 can be calculated by "Rduty = tc/(tc + tr)". It is preferable to create a map of the current value and the threshold value Rdth of the current duty that accelerates deterioration so that the current duty is equal to or less than the threshold value Rdth that accelerates deterioration. Then, after setting the running start charging rate SOCs by referring to this map, the recommended delivery start time is displayed on a display (not shown), and the delivery can be scheduled to start after the end of the downtime after charging. In addition, if the charging time until the end of charging of the charge command to the charger is set to the total time from the time the charging completion voltage is reached through the downtime, and the downtime is included in the charging completion time, delivery can be started at the same time as the charging completion. By applying this embodiment, it is possible to further suppress battery deterioration and to efficiently deliver and distribute the goods.

上述したように、走行開始状態決定部114は、二次電池11の劣化条件と、最適な走行開始条件(SOCs,Vs)との関係をマップ(テーブル)形式のデータとして記憶し、このマップ形式のデータを参照して走行開始条件(SOCs,Vs)を決定してもよい。また、二次電池11の使用条件と、最適な走行開始条件(SOCs,Vs)との関係をマップ形式で記憶してもよい。さらに、電池の使用条件と、電力量と、最適な走行開始条件(SOCs,Vs)との関係をマップ形式で記憶してもよい。このように、各種パラメータの関係をマップ化して実装することにより、実装時のデータ量を削減し、演算量を低減することが可能になり、システムストレージに余裕を持たせて高速に演算することが可能になる。すなわち、走行開始充電率SOCsをより早く算出でき、安価な装置でのシステム構築が可能になる。 As described above, the running start state determination unit 114 may store the relationship between the deterioration conditions of the secondary battery 11 and the optimal running start conditions (SOCs, Vs) as data in a map (table) format, and may determine the running start conditions (SOCs, Vs) by referring to this map-format data. Also, the relationship between the usage conditions of the secondary battery 11 and the optimal running start conditions (SOCs, Vs) may be stored in a map format. Furthermore, the relationship between the usage conditions of the battery, the amount of power, and the optimal running start conditions (SOCs, Vs) may be stored in a map format. In this way, by mapping and implementing the relationship between various parameters, it is possible to reduce the amount of data and the amount of calculation during implementation, and it is possible to perform calculations at high speed with a margin in the system storage. In other words, the running start charge rate SOCs can be calculated more quickly, and it is possible to build a system with an inexpensive device.

さらに、電池稼働領域判定選択部103は、電力量データベース142を、リアルタイムに更新してもよい。すなわち、車両10からの通信により、時系列の緯度、経度、二次電池11のSOC、電池電圧、電池電流、電力量、電池温度、環境温度を運転者IDまたは車両IDとともに記録するとよい。そして、車両10の積み荷重量と、配達完了記録とを参照して、電力量データベース142において重量変化と必要電力量との関係を記述した重量変化対応データベースを構築するとよい。作成した重量変化対応データベースから、学習用のデータを抽出し、抽出データを教師あり学習を用いて、予測電力量W2を出力することができる。または、重量変化対応データベースから、指定項目のユークリッド距離またはマハラノビス距離が小さい条件を選択することで、予測電力量W2を出力することができる。 Furthermore, the battery operating range determination and selection unit 103 may update the power amount database 142 in real time. That is, by communication from the vehicle 10, the time series latitude, longitude, SOC of the secondary battery 11, battery voltage, battery current, power amount, battery temperature, and environmental temperature may be recorded together with the driver ID or vehicle ID. Then, by referring to the load weight of the vehicle 10 and the delivery completion record, a weight change correspondence database that describes the relationship between weight change and required power amount in the power amount database 142 may be constructed. From the created weight change correspondence database, data for learning may be extracted, and the extracted data may be subjected to supervised learning to output the predicted power amount W2. Alternatively, the predicted power amount W2 may be output by selecting a condition in which the Euclidean distance or Mahalanobis distance of the specified item is small from the weight change correspondence database.

図11は、本実施形態の電力量データベース142に含まれる走行実績データD40の模式図である。図11における各行は、走行実績データD40のレコードであり、各レコードは、レコード番号D42と、ルート条件パラメータ部D44と、劣化情報部D46と、必要電力量部D48と、を含んでいる。 Figure 11 is a schematic diagram of driving history data D40 included in the power amount database 142 of this embodiment. Each row in Figure 11 is a record of the driving history data D40, and each record includes a record number D42, a route condition parameter section D44, a deterioration information section D46, and a required power amount section D48.

レコード番号D42は、当該レコードを特定する数値であり、「1」~「N」の範囲で一意に定められる数値である。また、ルート条件パラメータ部D44は、m個の特徴パラメータk1~kmを有している。ここで、特徴パラメータk1~kmは、当該レコードにおける走行日時、車両ID、運転者ID、気温、配送ルート、荷重、車重、位置情報(エリア)を含み、さらに電池温度、天候、配送時間帯情報を含んでいてもよい。劣化情報部D46は、当該レコードの取得時における劣化度SOHQ,SOHRを含んでいる。また、必要電力量部D48は、各レコードに係る走行において車両10が消費した消費電力量Wc1~Wcnである。これら消費電力量Wc1~Wcnが相関解析や学習処理を行う際の目的変数になる。 The record number D42 is a number that identifies the record and is a unique number in the range of "1" to "N". The route condition parameter section D44 has m feature parameters k1 to km. Here, the feature parameters k1 to km include the driving date and time, vehicle ID, driver ID, temperature, delivery route, load, vehicle weight, and location information (area) in the record, and may also include battery temperature, weather, and delivery time zone information. The deterioration information section D46 includes the deterioration levels SOHQ and SOHR at the time the record was obtained. The required power section D48 is the power consumption amounts Wc1 to Wcn consumed by the vehicle 10 during the driving related to each record. These power consumption amounts Wc1 to Wcn become the objective variables when performing correlation analysis and learning processing.

本実施形態において、二次電池管理装置100Eは、この走行実績データD40に基づいて、予定走行ルートでの予測電力量W2を算出する。まず、配達予定車両条件入力部104は、配達予定の予定ルート情報Rt、気温、天気、車両ID,運転者ID、荷重、車重、車両10の位置情報、二次電池11の電池劣化度を受信する。予測電力量計算部105は、配達予定車両条件入力部104に入力された項目について、走行実績データD40の平均値で各値を除して、規格化し項目毎に入力条件との差分を計算する。さらにその差分を項目毎の重み係数をかけて足し合わせ、その平方根を計算する。具体的には、下式(1)で示す演算を実行する。 In this embodiment, the secondary battery management device 100E calculates the predicted power amount W2 for the planned driving route based on this driving performance data D40. First, the delivery schedule vehicle condition input unit 104 receives planned delivery route information Rt, temperature, weather, vehicle ID, driver ID, load, vehicle weight, vehicle 10 position information, and the battery deterioration level of the secondary battery 11. For the items input to the delivery schedule vehicle condition input unit 104, the predicted power amount calculation unit 105 divides each value by the average value of the driving performance data D40, standardizes, and calculates the difference from the input conditions for each item. Furthermore, the difference is multiplied by the weighting coefficient for each item, added, and the square root is calculated. Specifically, the calculation shown in the following formula (1) is performed.

Figure 0007684089000001
Figure 0007684089000001

式(1)において、z1は入力された項目の値を規格化した値であり、zは走行実績データD40の当該項目の値を規格化した値である。また、dは最小二乗誤差である。予測電力量計算部105は、この最小二乗誤差dが最も0に近い、すなわちユークリッド距離が近い条件の走行実績情報を検索し、検索した走行実績情報における電力を予測電力量W1として算出する。また、予測電力量計算部105は、最小二乗誤差dが所定の閾値未満の場合に、予測電力量W1を出力してもよい。 In formula (1), z1 is a value obtained by normalizing the value of the input item, and z is a value obtained by normalizing the value of the item in the driving performance data D40. Furthermore, d is the least square error. The predicted power amount calculation unit 105 searches for driving performance information for which this least square error d is closest to 0, i.e., the Euclidean distance is closest, and calculates the power in the searched driving performance information as the predicted power amount W1. Furthermore, the predicted power amount calculation unit 105 may output the predicted power amount W1 when the least square error d is less than a predetermined threshold value.

予測電力量補正部106は、得られた予測電力量W1と、選択された走行実績情報と、に対して、最も距離が離れている情報を選択する。そして、予測電力量補正部106は、差分に関係する項目について、図10に示した電力量補正データD30から係数を選択し、予測電力量W1を補正することによって予測電力量W2を算出する。また、走行開始状態決定部114は、電池使用時のパラメータから推定される劣化度が小さくなるSOC領域を選択し、走行開始充電率SOCsを決定する。 The predicted power amount correction unit 106 selects the information with the greatest distance between the obtained predicted power amount W1 and the selected driving performance information. The predicted power amount correction unit 106 then selects a coefficient from the power amount correction data D30 shown in FIG. 10 for the item related to the difference, and calculates the predicted power amount W2 by correcting the predicted power amount W1. The driving start state determination unit 114 also selects an SOC region in which the degree of deterioration estimated from the parameters when the battery is in use is small, and determines the driving start charging rate SOCs.

さらに、走行開始充電率SOCsと現在SOC値の差が、通常の充電電流で充電時間として許容される閾値Ctime_th(図示せず)で充電できる電力量よりも大きい場合、電池稼働領域判定選択部103は、充電装置200(図3参照)に対して、急速充電を指令し、これによって充電時間を短縮する。これにより、二次電池管理装置100Eは、ルート走行に支障が出ないように充電スケジュールを制定できるため、効率よく荷物を配達・配送することが可能になる。 Furthermore, if the difference between the charging rate SOCs at the start of driving and the current SOC value is greater than the amount of power that can be charged at the threshold Ctime_th (not shown) that is the allowable charging time with a normal charging current, the battery operating range determination and selection unit 103 commands the charging device 200 (see FIG. 3) to perform rapid charging, thereby shortening the charging time. This allows the secondary battery management device 100E to establish a charging schedule that does not interfere with route driving, making it possible to deliver and distribute packages efficiently.

[第7実施形態]
図12は、好適な第7実施形態による二次電池劣化度検出システムS7のブロック図である。なお、以下の説明において、上述した他の実施形態の各部に対応する部分には同一の符号を付し、その説明を省略する場合がある。
二次電池劣化度検出システムS7は、充電装置200と、サーバー機210と、を備えている。また、本実施形態において対象とする車両10は、第5実施形態(図8参照)のものと同様に、二次電池11と、車両BMS16と、を備えている。この二次電池11が、劣化検出の対象になる。
[Seventh embodiment]
12 is a block diagram of a secondary battery deterioration detection system S7 according to a preferred seventh embodiment. In the following description, the same reference numerals are used to designate parts corresponding to the parts of the other embodiments described above, and the description thereof may be omitted.
The secondary battery deterioration level detection system S7 includes a charging device 200 and a server machine 210. The vehicle 10 that is the subject of this embodiment includes, similarly to the vehicle 10 in the fifth embodiment (see FIG. 8 ), a secondary battery 11 and a vehicle BMS 16. This secondary battery 11 is the subject of deterioration detection.

充電装置200は、充電する際に充電ケーブル内の通信プロトコルから得られる充電状態(SOC)、出力電流I、出力電圧V等の情報を、サーバー機210に対して、無線または有線の通信によって送信できるように構成されている。
サーバー機210は、二次電池11の劣化診断装置であり、そのハードウエア構成は、第1実施形態の二次電池管理装置100A(図2参照)のものと同様である。
The charging device 200 is configured to transmit information such as the state of charge (SOC), output current I, output voltage V, etc. obtained from the communication protocol in the charging cable during charging to the server machine 210 via wireless or wired communication.
The server machine 210 is a deterioration diagnosis device for the secondary battery 11, and its hardware configuration is similar to that of the secondary-battery management device 100A of the first embodiment (see FIG. 2).

図12において、サーバー機210の内部は、アプリケーションプログラム等によって実現される機能を、ブロックとして示している。すなわち、サーバー機210は、抵抗・容量演算部212と、劣化検出部214と、を備えている。抵抗・容量演算部212、劣化検出部214は、互いに連携し、情報を共有可能になっている。なお、サーバー機210は充電装置200の外部にあってもよいし、充電装置200にサーバー機210の一部または全部を内蔵してもよい。 In FIG. 12, the inside of the server machine 210 shows functions realized by application programs and the like as blocks. That is, the server machine 210 has a resistance/capacity calculation unit 212 and a deterioration detection unit 214. The resistance/capacity calculation unit 212 and the deterioration detection unit 214 cooperate with each other and are capable of sharing information. Note that the server machine 210 may be external to the charging device 200, or part or all of the server machine 210 may be built into the charging device 200.

車両10を充電装置200に接続すると、走行開始充電率SOCsまで二次電池11が充電される。この際、充電装置200は、車両10から二次電池11のSOC、出力電流I、出力電圧V等の情報を取得する。充電装置200は、取得された充電情報を抵抗・容量演算部212に送信する。抵抗・容量演算部212は、取得した情報から二次電池の現在の容量および抵抗の値を演算し、劣化検出部214では初期値と比較して劣化度SOHQ,SOHRを算出する。 When the vehicle 10 is connected to the charging device 200, the secondary battery 11 is charged up to the charging rate SOCs at the start of driving. At this time, the charging device 200 acquires information such as the SOC, output current I, and output voltage V of the secondary battery 11 from the vehicle 10. The charging device 200 transmits the acquired charging information to the resistance and capacity calculation unit 212. The resistance and capacity calculation unit 212 calculates the current capacity and resistance values of the secondary battery from the acquired information, and the deterioration detection unit 214 compares these with the initial values to calculate the deterioration levels SOHQ and SOHR.

劣化検出部214は、端末220に劣化度の情報を送信することができる。また、1台のサーバー機210に複数の車両10の情報を蓄積することができる。これにより、実測の劣化データベースの充実させることができる。そして、データベースから同車種の劣化情報を参照し、電池の劣化傾向をさらに正確に予測することが可能になる。 The deterioration detection unit 214 can transmit information on the deterioration level to the terminal 220. Also, information on multiple vehicles 10 can be stored in a single server machine 210. This allows the actual deterioration database to be enriched. Then, by referencing the deterioration information of the same vehicle model from the database, it becomes possible to more accurately predict the deterioration tendency of the battery.

図13は、サーバー機210で実行される劣化検出ルーチンのフローチャートである。
まず、ステップS31において、抵抗・容量演算部212は、充電装置200から、電圧、電流および充電時間を取得する。ここで、「充電時間」とは、充電開始以降の経過時間である。次に、ステップS32において、抵抗・容量演算部212は、予め学習によって取得した充電カーブに基づいて、充電時間に対する電池温度を推定する。
FIG. 13 is a flowchart of a deterioration detection routine executed by the server machine 210. As shown in FIG.
First, in step S31, the resistance/capacity calculation unit 212 acquires the voltage, current, and charging time from the charging device 200. Here, the "charging time" is the time elapsed since the start of charging. Next, in step S32, the resistance/capacity calculation unit 212 estimates the battery temperature with respect to the charging time based on the charging curve acquired in advance by learning.

次に、処理がステップS33に進むと、抵抗・容量演算部212は、取得した電圧値と充電時間と電流値と充電率SOCとに基づいて、図14のグラフG11,G12(詳細は後述する)に示すような、SOCと電圧との関係を取得する。次に、処理がステップS34に進むと、抵抗・容量演算部212は、抵抗・容量演算部212が記憶しているデータベースに基づいて、この二次電池11のSOCと開回路電圧OCVとの関係を検索する。 Next, when the process proceeds to step S33, the resistance/capacity calculation unit 212 obtains the relationship between SOC and voltage as shown in graphs G11 and G12 in FIG. 14 (details will be described later) based on the obtained voltage value, charging time, current value, and charging rate SOC. Next, when the process proceeds to step S34, the resistance/capacity calculation unit 212 searches for the relationship between the SOC and the open circuit voltage OCV of this secondary battery 11 based on the database stored in the resistance/capacity calculation unit 212.

次に、処理がステップS35に進むと、抵抗・容量演算部212は、図14のグラフG12に示すように、同一のSOCにおける充電電圧Vと、開回路電圧OCVとの差分を充電電流Iで除算することにより、暫定抵抗値R0を算出する。ここで、暫定抵抗値R0は、二次電池11の内部抵抗である抵抗値Rの暫定値である。 Next, when the process proceeds to step S35, the resistance/capacity calculation unit 212 calculates a provisional resistance value R0 by dividing the difference between the charging voltage V and the open circuit voltage OCV at the same SOC by the charging current I, as shown in graph G12 in FIG. 14. Here, the provisional resistance value R0 is a provisional value of the resistance value R, which is the internal resistance of the secondary battery 11.

ここで、抵抗・容量演算部212は、SOCと電池温度と抵抗値Rとの相関関係のデータベースを記憶している。次に、処理がステップS36に進むと、抵抗・容量演算部212は、この相関関係のデータベースと、ステップS32において推定した電池温度に基づく温度係数と、に基づいて暫定抵抗値R0を補正し、暫定抵抗値R1を算出する。 Here, the resistance/capacity calculation unit 212 stores a database of correlations between SOC, battery temperature, and resistance value R. Next, when the process proceeds to step S36, the resistance/capacity calculation unit 212 corrects the provisional resistance value R0 based on this database of correlations and a temperature coefficient based on the battery temperature estimated in step S32, and calculates a provisional resistance value R1.

次に、処理がステップS37に進むと、抵抗・容量演算部212は、充電電流Iと充電時間とに基づいて、暫定容量値Q0を算出する。ここで、暫定容量値Q0は、二次電池11の現在の容量値Qの暫定値である。また、抵抗・容量演算部212は、暫定容量値Q0と、暫定抵抗値R1と、に対して補正を行い、容量値Qと抵抗値Rとを算出する。具体的には、カタログ表示仕様における測定温度等、基準の温度、電流および時刻条件での取得値に換算して容量値Qと抵抗値Rとを取得する。 Next, when the process proceeds to step S37, the resistance/capacity calculation unit 212 calculates a provisional capacity value Q0 based on the charging current I and the charging time. Here, the provisional capacity value Q0 is a provisional value of the current capacity value Q of the secondary battery 11. The resistance/capacity calculation unit 212 also performs corrections to the provisional capacity value Q0 and the provisional resistance value R1 to calculate the capacity value Q and the resistance value R. Specifically, the capacity value Q and the resistance value R are obtained by converting them into values obtained under standard temperature, current and time conditions such as the measurement temperature in the catalog display specifications.

次に、処理がステップS38に進むと、劣化検出部214は、取得した容量値Qおよび抵抗値Rと、未使用時の二次電池11における容量値Qおよび抵抗値Rとの比を求め、これによって劣化度SOHQ,SOHRを算出する。すなわち、サーバー機210は、これら劣化度SOHQ,SOHRを二次電池11の劣化情報として出力する。 Next, when the process proceeds to step S38, the deterioration detection unit 214 obtains the ratio between the acquired capacity value Q and resistance value R and the capacity value Q and resistance value R of the secondary battery 11 when it is not in use, and calculates the deterioration levels SOHQ and SOHR from this. In other words, the server machine 210 outputs these deterioration levels SOHQ and SOHR as deterioration information of the secondary battery 11.

ここで、二次電池11の劣化情報についてさらに説明する。
二次電池11の劣化状態は、電池の内部抵抗(以下単に「抵抗」ともいう)を用いて演算したSOHRおよび/または電池の満充電容量を用いて演算したSOHQである。SOHRは、電池の内部抵抗に基づいて求めた劣化度あり、電池の劣化に伴い上昇する電池の内部抵抗の上昇率を表し、次式(2)で定義される。

SOHR=100×R1(SOC,T)/R0(SOC,T) …(2)
Here, the deterioration information of the secondary battery 11 will be further described.
The deterioration state of the secondary battery 11 is the SOHR calculated using the internal resistance (hereinafter also simply referred to as "resistance") of the battery and/or the SOHQ calculated using the full charge capacity of the battery. The SOHR is the degree of deterioration calculated based on the internal resistance of the battery, and represents the rate of increase in the internal resistance of the battery that increases with battery deterioration, and is defined by the following formula (2).

SOHR=100×R1(SOC,T)/R0(SOC,T)...(2)

式(2)において、R1(SOC,T)は、現在(劣化後)の二次電池11の内部抵抗[Ω]を表す。R0(SOC,T)は、新品時の二次電池11の内部抵抗[Ω]を表す。
容量を用いて演算するSOHQは、現在容量を初期容量で除したものである。上記式(1)のSOHRは、百分率で表しているが、初期に対する現在の比率であれば必ずしも百分率に限られない。
ここで、図14のグラフG11,G12を用いて、劣化による劣化度診断の算出方法の例を示す。
In formula (2), R1(SOC, T) represents the current (deteriorated) internal resistance [Ω] of the secondary battery 11. R0(SOC, T) represents the internal resistance [Ω] of the secondary battery 11 when it is new.
The SOHQ calculated using the capacity is the current capacity divided by the initial capacity. Although the SOHR in the above formula (1) is expressed as a percentage, it is not necessarily limited to a percentage as long as it is the ratio of the current capacity to the initial capacity.
Here, an example of a method for calculating the deterioration degree diagnosis due to deterioration will be shown using graphs G11 and G12 in FIG.

図14は、二次電池11の電圧特性を示す図である。
まず、図14のグラフG11は、充電時の電圧・充電時間特性の一例を示す。グラフG11において横軸は充電開始後の経過時間であり、縦軸は二次電池11の電圧である。図中の特性G110は開回路電圧OCVまたは低レートでの充電電圧でほぼOCVとみなすことができる電圧曲線である。特性G112は急速充電時の電圧変化である。急速充電開始時の開回路電圧(OCV)をOCViniとする。経過時間tendまでの充電時間で、電気量Qchが充電される。何れの特性においても、充電時間の経過に伴って開回路電圧OCVは上昇する。但し、急速充電の特性G112によれば、比較的短い経過時間tendが経過するまでに、二次電池11には、満充電に相当する電気量Qchが供給される。
FIG. 14 is a diagram showing the voltage characteristics of the secondary battery 11. As shown in FIG.
First, the graph G11 in FIG. 14 shows an example of the voltage-charging time characteristic during charging. In the graph G11, the horizontal axis is the elapsed time after the start of charging, and the vertical axis is the voltage of the secondary battery 11. The characteristic G110 in the figure is a voltage curve that can be regarded as an open circuit voltage OCV or a charging voltage at a low rate, and can be considered to be almost the OCV. The characteristic G112 shows the voltage change during rapid charging. The open circuit voltage (OCV) at the start of rapid charging is OCV ini . The amount of electricity Qch is charged during the charging time until the elapsed time tend. In either characteristic, the open circuit voltage OCV increases as the charging time elapses. However, according to the rapid charging characteristic G112, the amount of electricity Qch equivalent to full charging is supplied to the secondary battery 11 before a relatively short elapsed time tend has elapsed.

また、図14のグラフG12は、二次電池11のSOCと電圧との関係を示す。グラフG12において特性G120はSOCと開回路電圧OCVとの関係を示し、特性G122はSOCと充電電圧Vcとの関係を示す。G122は、グラフG11の電圧曲線G112をSOCに対応して示したものである。G112の充電開始時の開回路電圧OCViniを、SOCとOCVの関係からSOCに換算し、相当するSOC値をSOCiniを求める。SOCiniから充電したグラフG11の電気量QchをSOCに換算して、SOCendが求められる。ここで、充電電圧Vcとは、所定の充電電流を二次電池11に供給している際に二次電池11に現れる電圧である。図示のように、同一のSOC値に対して、充電電圧Vcは開回路電圧OCVよりも高くなる。両者の差を電圧差分ΔV(socx)と呼ぶ。電圧差分ΔV(socx)は、主として二次電池11の内部抵抗における電圧降下である。二次電池11のSOCをSOCiniからSOCendまで充電したとき、充電される電気量Qchは、グラフG11に示した電気量Qchに等しい。 Graph G12 in FIG. 14 shows the relationship between the SOC and the voltage of the secondary battery 11. In the graph G12, characteristic G120 shows the relationship between the SOC and the open circuit voltage OCV, and characteristic G122 shows the relationship between the SOC and the charging voltage Vc. G122 shows the voltage curve G112 of the graph G11 corresponding to the SOC. The open circuit voltage OCV ini at the start of charging of G112 is converted to SOC from the relationship between SOC and OCV, and the corresponding SOC value is obtained as SOC ini . The amount of electricity Qch of the graph G11 charged from the SOC ini is converted to SOC to obtain SOCend. Here, the charging voltage Vc is the voltage that appears at the secondary battery 11 when a predetermined charging current is supplied to the secondary battery 11. As shown in the figure, for the same SOC value, the charging voltage Vc is higher than the open circuit voltage OCV. The difference between the two is called the voltage difference ΔV (socx). The voltage difference ΔV (socx) is mainly a voltage drop across the internal resistance of the secondary battery 11. When the SOC of the secondary battery 11 is charged from SOCini to SOCend, the charged amount of electricity Qch is equal to the amount of electricity Qch shown in graph G11.

抵抗・容量演算部212(図13参照)は、車両10に関する情報に基づいて、車両10に適用されている二次電池11の仕様を、抵抗・容量演算部212の内部のデータベースから取得することができる。その仕様の中に、特性G120に相当するOCV曲線が含まれている。そこで、抵抗・容量演算部212は、充電開始時の開回路電圧OCVと、特性G120とに基づいて、充電開始時のSOCであるSOCiniを取得する。 The resistance/capacity calculation unit 212 (see FIG. 13) can obtain the specifications of the secondary battery 11 applied to the vehicle 10 from a database inside the resistance/capacity calculation unit 212 based on information about the vehicle 10. The specifications include an OCV curve corresponding to the characteristic G120. Therefore, the resistance/capacity calculation unit 212 obtains SOCini, which is the SOC at the start of charging, based on the open circuit voltage OCV at the start of charging and the characteristic G120.

また、抵抗・容量演算部212は、同一のSOCにおいて、充電電圧Vcと開回路電圧OCVとを計測し、両者に基づいて電圧差分ΔV(socx)を算出する。さらに、抵抗・容量演算部212は、この電圧差分ΔV(socx)を充電電流Iで除算し、二次電池11の内部抵抗の抵抗値Rを取得する。特に、二次電池11に通電した直後は、SOCが変動する前であり、反応抵抗の影響が少ないため、その際に抵抗値Rを取得することが好ましい。二次電池11がリチウムイオン電池である場合、上述のように算出される抵抗値Rは、SOCに対して依存性があることが知られている。 Furthermore, the resistance/capacity calculation unit 212 measures the charging voltage Vc and the open circuit voltage OCV at the same SOC, and calculates the voltage difference ΔV (socx) based on both. Furthermore, the resistance/capacity calculation unit 212 divides this voltage difference ΔV (socx) by the charging current I to obtain the resistance value R of the internal resistance of the secondary battery 11. In particular, it is preferable to obtain the resistance value R immediately after current is applied to the secondary battery 11, before the SOC fluctuates and because there is little effect from reaction resistance. When the secondary battery 11 is a lithium ion battery, it is known that the resistance value R calculated as described above depends on the SOC.

従って、抵抗値RとSOCとの関係は、関数またはテーブルとして表すことができる。
例えば、二次電池11に対して、あるSOCa(図示せず)から他のSOCb(図示せず)まで充電した場合は、それぞれの抵抗値Rを引き当てて、補正演算を行うとよい。二次電池11に対する充放電終了時の電圧および電流をそれぞれVlast、Ilastとし、充放電終了時から所定時間後に検出される電池の開回路電圧をOCVとすると、抵抗曲線における抵抗値Rは、次式(3)で求められる。

R=(|OCV-Vlast|)/Ilast …(3)
Therefore, the relationship between the resistance value R and the SOC can be expressed as a function or a table.
For example, when the secondary battery 11 is charged from a certain SOCa (not shown) to another SOCb (not shown), a correction calculation may be performed by subtracting the respective resistance values R. If the voltage and current at the end of charging and discharging the secondary battery 11 are Vlast and Ilast, respectively, and the open circuit voltage of the battery detected a predetermined time after the end of charging and discharging is OCV, the resistance value R in the resistance curve can be calculated by the following formula (3).

R=(|OCV-Vlast|)/Ilast...(3)

また、充電電流Iが一定である場合には、電池の閉回路電圧をCCVとすると、抵抗値Rは、次式(4)によっても求めることができる。

R=(OCV-CCV)/I …(4)
Furthermore, when the charging current I is constant, and the closed circuit voltage of the battery is CCV, the resistance value R can also be calculated by the following equation (4):

R=(OCV-CCV)/I...(4)

また、抵抗値Rは、他の方法によっても求めることができる。例えば、あるSOCにおける電流値xと、閉回路電圧CCVと、に基づいて、線形近似式「CCV=Hx+J」を求めることができる。抵抗値Rは、この近似式における係数Hに基づいて求めることができる。ここで、定数Jが開回路電圧OCVに等しい場合は、係数Hは、抵抗値Rに等しいと考えることができる。 The resistance value R can also be calculated by other methods. For example, a linear approximation equation "CCV = Hx + J" can be calculated based on the current value x at a certain SOC and the closed circuit voltage CCV. The resistance value R can be calculated based on the coefficient H in this approximation equation. Here, if the constant J is equal to the open circuit voltage OCV, the coefficient H can be considered to be equal to the resistance value R.

また、容量値Qは、充電開始時のSOCであるSOCiniと、充電終了時のSOCであるSOCendとの差、すなわちSOCの変動幅と、電気量Qchと、に基づいて、次の式(5)で求めることができる。

Q=Qch/(SOCend-SOCini)×100 …(5)
In addition, the capacitance value Q can be calculated based on the difference between SOCini, which is the SOC at the start of charging, and SOCend, which is the SOC at the end of charging, i.e., the fluctuation range of the SOC, and the amount of electricity Qch, using the following equation (5).

Q=Qch/(SOCend-SOCini)×100...(5)

[第8実施形態]
図15は、好適な第8実施形態による、車両の電池システムの例である。なお、以下の説明において、上述した他の実施形態の各部に対応する部分には同一の符号を付し、その説明を省略する場合がある。
車両電池システムS8は、車両10の内部に実装され、測定値検出部22と、電池制御部24と、負荷制御部26と、上位制御部28と、を備えている。
Eighth embodiment
15 is an example of a vehicle battery system according to a preferred embodiment 8. In the following description, parts corresponding to those in the other embodiments described above are given the same reference numerals, and the description thereof may be omitted.
The vehicle battery system S8 is implemented inside the vehicle 10, and includes a measurement value detection unit 22, a battery control unit 24, a load control unit 26, and a higher-level control unit 28.

また、二次電池11は、各々が正極および負極を有する複数の単電池11a,11b等を、直列に接続して構成されている。二次電池11は、不図示の負荷装置と接続されており、負荷装置に対して電力を供給する。測定値検出部22は、二次電池11の状態に関する様々な情報、例えば、二次電池11の総電流、総電圧、環境温度、最高温度、平均温度、最低温度や、単電池11a,11bのそれぞれの温度、電圧等のデータを検出する。測定値検出部22で検出されたデータは、電池制御部24に入力される。なお、測定値検出部22は、単電池11a,11bのそれぞれの種類または型式等、換言すれば、単電池11a,11bの個別の特徴についても検出することが好ましい。 The secondary battery 11 is configured by connecting a plurality of single cells 11a, 11b, etc., each having a positive electrode and a negative electrode, in series. The secondary battery 11 is connected to a load device (not shown) and supplies power to the load device. The measurement value detection unit 22 detects various information related to the state of the secondary battery 11, such as the total current, total voltage, environmental temperature, maximum temperature, average temperature, and minimum temperature of the secondary battery 11, and the temperature and voltage of each of the single cells 11a, 11b. The data detected by the measurement value detection unit 22 is input to the battery control unit 24. It is preferable that the measurement value detection unit 22 also detects the type or model of each of the single cells 11a, 11b, in other words, the individual characteristics of the single cells 11a, 11b.

電池制御部24は、測定値検出部22から入力されたデータに基づいて、現在の二次電池11の充電状態(SOC等)を計算するとともに、異常状態の検知、入出力可能な電力の計算、温度コントロール指令の生成等の処理を実行する。電池制御部24から出力される各信号は、負荷制御部26および上位制御部28に供給される。上位制御部28は、供給された信号に基づいて、負荷制御部26に対して、制御指令を出力する。この制御指令は、例えば、負荷装置が消費できる最大電力や最大電力量等を指定するものである。負荷制御部26は、これら上位制御部28から入力された制御指令と、電池制御部24から入力された情報とに基づいて、負荷装置の制御を実行する。 The battery control unit 24 calculates the current state of charge (SOC, etc.) of the secondary battery 11 based on the data input from the measurement value detection unit 22, and performs processes such as detecting abnormal states, calculating the power that can be input and output, and generating a temperature control command. Each signal output from the battery control unit 24 is supplied to the load control unit 26 and the upper control unit 28. The upper control unit 28 outputs a control command to the load control unit 26 based on the supplied signal. This control command specifies, for example, the maximum power or maximum amount of power that can be consumed by the load device. The load control unit 26 controls the load device based on the control commands input from the upper control unit 28 and the information input from the battery control unit 24.

[第9実施形態]
図16は、好適な第9実施形態による、二次電池管理システムS9のブロック図である。なお、以下の説明において、上述した他の実施形態の各部に対応する部分には同一の符号を付し、その説明を省略する場合がある。
二次電池管理システムS9は、検出部30と、電池稼働領域判定選択部40と、を供えている。
[Ninth embodiment]
16 is a block diagram of a secondary battery management system S9 according to a preferred ninth embodiment. In the following description, the same reference numerals are used to designate parts corresponding to the parts of the other embodiments described above, and the description thereof may be omitted.
The secondary battery management system S9 includes a detection unit 30 and a battery operating range determination and selection unit 40.

電池稼働領域判定選択部40のハードウエア構成は、第1実施形態の二次電池管理装置100A(図2参照)のものと同様である。図16において、電池稼働領域判定選択部40の内部は、アプリケーションプログラム等によって実現される機能を、ブロックとして示している。
すなわち、電池稼働領域判定選択部40は、データ蓄積部41と、データ選択部42と、劣化算出部43と、運転パラメータ算出部45と、劣化予測部46と、走行開始状態決定部114と、を備えている。
The hardware configuration of the battery operating range determination and selection unit 40 is similar to that of the secondary battery management device 100A (see FIG. 2) of the first embodiment. In FIG. 16, the inside of the battery operating range determination and selection unit 40 is shown as a block, with functions realized by application programs and the like.
That is, the battery operating range determination and selection unit 40 includes a data accumulation unit 41 , a data selection unit 42 , a deterioration calculation unit 43 , a driving parameter calculation unit 45 , a deterioration prediction unit 46 , and a driving start state determination unit 114 .

検出部30は、二次電池11(図15参照)の電圧、電流、温度等のデータを、日時等の時間情報とともに検出し、検出結果を電池稼働領域判定選択部40に出力する。この際、充電装置200(図12参照)に通知されて演算されたSOCの情報も、電池稼働領域判定選択部40に入力する。走行開始状態決定部114の機能は、第5実施形態(図8参照)のものと同様である。データ選択部42は、検出部30または車両10(図3参照)内の測定値検出部22(図15参照)によって取得されたデータ(電池温度・走行履歴に関係するデータを含む)および検出部30から出力されたデータのうち、予め設定した条件に合致するものを選択し、データ蓄積部41に出力する。 The detection unit 30 detects data such as the voltage, current, and temperature of the secondary battery 11 (see FIG. 15) together with time information such as date and time, and outputs the detection result to the battery operating range determination and selection unit 40. At this time, the SOC information notified to the charging device 200 (see FIG. 12) and calculated is also input to the battery operating range determination and selection unit 40. The function of the running start state determination unit 114 is the same as that of the fifth embodiment (see FIG. 8). The data selection unit 42 selects data (including data related to battery temperature and running history) acquired by the detection unit 30 or the measurement value detection unit 22 (see FIG. 15) in the vehicle 10 (see FIG. 3) and data output from the detection unit 30 that meets preset conditions, and outputs the data to the data storage unit 41.

なお、電池温度および走行履歴は、図15に示した測定値検出部22での測定値を、図示せぬOBD(On-board diagnostics)端子または任意の端末を経由して取得するとよい。データ蓄積部41は、SOC-OCVデータ蓄積部41aと、SOC-Rデータ蓄積部41bと、運転パラメータデータ蓄積部41cと、データベース44と、を備えている。 The battery temperature and driving history may be obtained by acquiring the measured values from the measurement value detection unit 22 shown in FIG. 15 via an OBD (On-board diagnostics) terminal (not shown) or any other terminal. The data storage unit 41 includes an SOC-OCV data storage unit 41a, an SOC-R data storage unit 41b, an operating parameter data storage unit 41c, and a database 44.

データ選択部42は、一定期間または一定回数毎に、条件に合致したSOCに対する二次電池11(図15参照)の開回路電圧を取得し、SOC-OCVデータ蓄積部41aに蓄積する。同様に、データ選択部42は、当該SOCに対する二次電池11の抵抗値のデータを取得し、SOC-Rデータ蓄積部41bに蓄積する。さらに、データ選択部42は、運転パラメータデータ蓄積部41cに対して、測定値検出部22(図15参照)から出力されたデータに基づいて、二次電池11の使用時間に応じた使用履歴データとして短時間例えば、数分間の電流、通電時間、SOC変動等のデータを取得して蓄積する。 The data selection unit 42 acquires the open circuit voltage of the secondary battery 11 (see FIG. 15) for an SOC that meets the conditions at regular intervals or regular counts, and stores the voltage in the SOC-OCV data storage unit 41a. Similarly, the data selection unit 42 acquires data on the resistance value of the secondary battery 11 for that SOC, and stores the data in the SOC-R data storage unit 41b. Furthermore, the data selection unit 42 acquires and stores data on the current, current flow time, SOC fluctuations, etc. for a short period of time, for example, several minutes, as usage history data corresponding to the usage time of the secondary battery 11, based on the data output from the measurement value detection unit 22 (see FIG. 15), in the operating parameter data storage unit 41c.

データベース44には、劣化推定に使用する各種データが備えられる。これらは、例えば、劣化を推定する予測式、パラメータの初期値、パラメータの変化量等である。劣化算出部43は、データベース44、SOC-OCVデータ蓄積部41a、SOC-Rデータ蓄積部41bのデータを使用して、二次電池11の内部状態である容量や抵抗値を演算し、二次電池11の劣化状態を算出する。ここで、SOC-OCVデータ蓄積部41aおよびSOC-Rデータ蓄積部41bは、二次電池11の初期データも予め蓄積している。 The database 44 contains various data used for estimating deterioration. These include, for example, a prediction formula for estimating deterioration, initial parameter values, and parameter change amounts. The deterioration calculation unit 43 uses data from the database 44, the SOC-OCV data accumulation unit 41a, and the SOC-R data accumulation unit 41b to calculate the capacity and resistance values, which are the internal state of the secondary battery 11, and calculates the deterioration state of the secondary battery 11. Here, the SOC-OCV data accumulation unit 41a and the SOC-R data accumulation unit 41b also accumulate initial data for the secondary battery 11 in advance.

劣化算出部43は、二次電池11の現在の劣化状態を推定し、その結果を上位制御部28(図15参照)および劣化予測部46に出力する。劣化予測部46は、運転パラメータ算出部45で算出したパラメータを用いて、時系列の劣化予測を行い、その結果を劣化予測データとして出力する。走行開始状態決定部114は、使用SOC領域を決定し、走行開始条件(SOCs,Vs)を出力する。 The deterioration calculation unit 43 estimates the current deterioration state of the secondary battery 11 and outputs the result to the upper control unit 28 (see FIG. 15) and the deterioration prediction unit 46. The deterioration prediction unit 46 performs a time-series deterioration prediction using the parameters calculated by the operating parameter calculation unit 45 and outputs the result as deterioration prediction data. The running start state determination unit 114 determines the usable SOC region and outputs the running start condition (SOCs, Vs).

ここで、運転パラメータ算出部45の動作について詳細に説明する。
運転パラメータ算出部45は、データ選択部42で選択したデータから、データ蓄積部41内の運転パラメータデータ蓄積部41cに蓄積された使用履歴データに基づいて、二次電池11の運転条件に関する様々な運転パラメータを算出する。二次電池11の運転パラメータは、例えば、電力量、休止時間比率、移動距離、稼働時の稼働中心SOC、稼働電圧範囲、稼働上限電圧、稼働下限電圧、平均電流、最大・最小電流、電池温度、環境温度、発熱ファクタ、実効電流、稼働平均電気量、充電容量、放電容量、SOC変動幅、単位時間当たりの通電極性比率、単位時間当たりの休止時間比率などである。
Here, the operation of the operating parameter calculation unit 45 will be described in detail.
The operating parameter calculation unit 45 calculates various operating parameters related to the operating conditions of the secondary battery 11 from the data selected by the data selection unit 42, based on the usage history data accumulated in the operating parameter data accumulation unit 41c in the data accumulation unit 41. The operating parameters of the secondary battery 11 include, for example, the amount of power, the downtime ratio, the travel distance, the operating center SOC during operation, the operating voltage range, the upper operating voltage limit, the lower operating voltage limit, the average current, the maximum and minimum currents, the battery temperature, the environmental temperature, the heat generation factor, the effective current, the operating average amount of electricity, the charge capacity, the discharge capacity, the SOC fluctuation range, the conductive ratio per unit time, and the downtime ratio per unit time.

なお、運転パラメータは、これらに限定されない。運転パラメータ算出部45は、様々な運転条件から導き出せるパラメータを二次電池11の運転パラメータとして使用することができる。また、データ選択部42は、測定値検出部22で検出した所定範囲のデータを、データ蓄積部41に蓄積するデータであって二次電池11の使用に関するパラメータを算出するためのデータとして選択する。 Note that the operating parameters are not limited to these. The operating parameter calculation unit 45 can use parameters that can be derived from various operating conditions as operating parameters for the secondary battery 11. Furthermore, the data selection unit 42 selects data within a predetermined range detected by the measurement value detection unit 22 as data to be stored in the data storage unit 41 and used to calculate parameters related to the use of the secondary battery 11.

電気自動車などの車両は、走行時の加減速に電池の入出力が伴う。減速時に電池に回生電流を受け入れ走行時、停車時に放電する。図17は、車両が検出する二次電池11の電池電圧V、充放電電流IおよびSOCの経時的変化の一例を示す図である。
グラフG21は二次電池11の電池電圧V、グラフG22は充放電電流I、グラフG23はSOCの変化を示す。充放電電流Iは、正値が充電電流であり、負値が放電電流である。以下、図17を参照して、データ選択部42が実行するデータ選択の一例を説明する。
Vehicles such as electric vehicles require input and output from a battery when accelerating or decelerating while traveling. The battery receives regenerative current during deceleration and discharges when traveling or stopped. Fig. 17 is a diagram showing an example of time-dependent changes in the battery voltage V, charge/discharge current I, and SOC of the secondary battery 11 detected by the vehicle.
Graph G21 indicates the battery voltage V of the secondary battery 11, graph G22 indicates the charge/discharge current I, and graph G23 indicates the change in SOC. With regard to the charge/discharge current I, a positive value is the charge current, and a negative value is the discharge current. Hereinafter, an example of data selection performed by the data selection unit 42 will be described with reference to FIG.

車両システムにおいては、センサの誤差、補機や、制御回路への通電により電池を走行用の電力として利用する場合に、休止時間があった場合でも完全に通電電流値の検出値が0に一致しない場合がある。電池の休止時間とみなせるある一定電流幅内の区間を休止時間とみなし、この一定電流幅の電流を電流値「0」と以下記載する。図17の時刻t0~t01の期間、二次電池11に放電電流が流れ、時刻t01において充放電電流Iは「0」になっている。そして、時刻tc1において、二次電池11には再び放電電流が流れ始めている。このように、時刻t0~tchの期間では、二次電池11は断続的に放電されている。また、時刻tch~t05の期間には、二次電池11は充電されて電圧が上昇している。 In a vehicle system, when a battery is used as a power source for driving, the detected current value may not completely match zero due to sensor errors and current supply to auxiliary equipment and control circuits even if there is a downtime. A section within a certain current width that can be considered as the downtime of the battery is considered to be the downtime, and the current of this certain current width is hereinafter described as a current value of "0". In the period from time t 0 to t 01 in FIG. 17, a discharge current flows to the secondary battery 11, and at time t 01 , the charge/discharge current I becomes "0". Then, at time t c1 , a discharge current starts to flow again to the secondary battery 11. In this way, the secondary battery 11 is intermittently discharged during the period from time t 0 to t ch . Furthermore, during the period from time t ch to t 05 , the secondary battery 11 is charged and the voltage rises.

そして、時刻t05~tcまで、充放電電流Iが0になっている(但し、計測器の誤差を除く)期間が続いている。当該期間は、所定の休止閾値期間Trthよりも長くなっている。このように、通電終了からの経過時間が休止閾値期間Trthを超えると、データ選択部42は、再び通電が始まる直前のタイミング(図示の例では時刻tcの直前)の電池電圧V(同、Vtp1)を開回路電圧OCVとして記録する。さらに、データ選択部42は、そのタイミングにおけるSOC(同、SOCtp1)も記録する。 Then, from time t 05 to t c , there is a period during which the charge/discharge current I is zero (excluding the measurement error). This period is longer than the predetermined pause threshold period Tr th . In this way, when the time elapsed since the end of energization exceeds the pause threshold period Tr th , the data selection unit 42 records the battery voltage V (V tp1 ) at the timing immediately before energization starts again (immediately before time t c in the illustrated example) as the open circuit voltage OCV. Furthermore, the data selection unit 42 also records the SOC (SOC tp1 ) at that timing.

同様に、時刻t06~tcpまで、充放電電流Iが0になっており、当該期間は、休止閾値期間Trthよりも長くなっている。そこで、データ選択部42は、再び通電が始まる直前のタイミングの電池電圧V(同、Vtp2)を開回路電圧OCVとして記録し、同タイミングにおけるSOC(同、SOCtp2)も記録する。このように、SOCと開回路電圧OCVとの関係を蓄積してゆくと、SOC-OCV特性を近似的に求めることができる。 Similarly, the charge/discharge current I is zero from time t 06 to time t cp , and this period is longer than the pause threshold period Tr th . Therefore, the data selection unit 42 records the battery voltage V (V tp2 ) at the timing immediately before the current flow starts again as the open circuit voltage OCV, and also records the SOC (SOC tp2 ) at the same timing. In this way, by accumulating the relationship between the SOC and the open circuit voltage OCV, the SOC-OCV characteristic can be approximately determined.

また、データ選択部42は、充放電電流Iの絶対値|I|が、急峻に(所定時間内に)0から所定の電流閾値Ij以上に変化するタイミングを検出する。図17の例では、時刻tcnが当該タイミングに相当する。データ選択部42は、検出したタイミング(時刻tcn)における電池電圧Vcnと、と充電状態SOCcnと、充放電電流Icnと、を記録する。さらに、データ選択部42は、二次電池11が閉回路状態になる直前の時刻tcn-1(図示せず)における電池電圧Vcn-1(図示せず)および充電状態SOCcn-1(図示せず)を記録する。 The data selection unit 42 also detects the timing at which the absolute value |I| of the charge/discharge current I changes sharply (within a predetermined time) from 0 to a predetermined current threshold value Ij or more. In the example of FIG. 17, the time t cn corresponds to this timing. The data selection unit 42 records the battery voltage V cn , the state of charge SOC cn , and the charge/discharge current I cn at the detected timing (time t cn ). Furthermore, the data selection unit 42 records the battery voltage V cn - 1 (not shown) and the state of charge SOC cn-1 (not shown) at time t cn-1 (not shown) immediately before the secondary battery 11 enters a closed circuit state.

そして、データ選択部42は、電池電圧Vcn,Vcn-1と、充電状態SOCcn,SOCcn-1と、充放電電流Icnと、に基づいて、一次近似により二次電池11の抵抗値Rを算出する。また、データ選択部42は、充放電電流Iの絶対値|I|が0に変化する通電終了時刻を検出する。図示の例では、時刻t01,t02,t03,t04,t05等がこれに該当する。これらを、以下、通電終了時刻t0xと総称する。 The data selection unit 42 then calculates the resistance value R of the secondary battery 11 by first-order approximation based on the battery voltages Vcn , Vcn -1 , the states of charge SOCcn , SOCcn -1 , and the charge/discharge current Icn . The data selection unit 42 also detects the current flow end time at which the absolute value |I| of the charge/discharge current I changes to 0. In the illustrated example, this corresponds to times t01 , t02 , t03 , t04 , t05 , etc. These are hereinafter collectively referred to as current flow end time t0x .

また、データ選択部42は、通電終了時刻t0xの後、二次電池11の通電が開始される時刻を特定する。図示の例では、時刻tc1,tc2,tc3等がこれに該当する。これらを、以下、通電開始時刻tcxと総称する。データ選択部42は、これら通電終了時刻t0xと、通電開始時刻tcxとにおける電池電圧VおよびSOCを、二次電池11の充放電前後における電圧およびSOCとしてそれぞれ記録する。 The data selection unit 42 also identifies the time when current supply to the secondary battery 11 starts after the current supply end time t 0x . In the illustrated example, these times correspond to t c1 , t c2 , t c3 , etc. These are hereinafter collectively referred to as current supply start time t cx . The data selection unit 42 records the battery voltage V and SOC at the current supply end time t 0x and the current supply start time t cx as the voltage and SOC before and after charging and discharging the secondary battery 11, respectively.

例えば、データ選択部42は、時刻t01,t02,t03におけるSOCを、充電状態SOCa,SOCb,SOCcとして記録し、同時刻における電池電圧V01,V02(図示せず),V03(図示せず)を開回路電圧として記録する。また、データ選択部42は、例えば時刻tc1,tc2,tc3における充電状態SOC、充放電電流I、電池電圧Vc1,Vc2(図示せず),Vc3(図示せず)を記録する。 For example, the data selection unit 42 records the SOC at times t01 , t02 , and t03 as states of charge SOCa, SOCb, and SOCc, and records the battery voltages V01 , V02 (not shown), and V03 (not shown) at the same times as open circuit voltages. The data selection unit 42 also records the state of charge SOC , charge/discharge current I, and battery voltages Vc1 , Vc2 (not shown), and Vc3 (not shown) at times tc1, tc2 , and tc3 , for example.

また、データ選択部42は、ある通電終了時刻t0xからその直後の通電開始時刻tcxまでの時間(例えば時刻t01~時刻tc1)を休止時間Tr(図示せず)として記録し、ある通電開始時刻tcxからその直後の通電終了時刻t0xまでの時間(例えば時刻tc1~時刻t02)を通電時間Tc(図示せず)として記録する。そして、データ選択部42は、各通電時間Tcにおける充放電電流Iの積算値を演算により求め、これによって容量値Q(図示せず)の時系列データを記録する。 The data selection unit 42 also records the time from a certain current flow end time t 0x to the immediately following current flow start time t cx (e.g., time t 01 to time t c1 ) as a down time Tr (not shown), and records the time from a certain current flow start time t cx to the immediately following current flow end time t 0x (e.g., time t c1 to time t 02 ) as a current flow time Tc (not shown).The data selection unit 42 then calculates an integrated value of the charge/discharge current I during each current flow time Tc, and records time-series data of the capacitance value Q (not shown) based on this.

また、データ選択部42は、各通電時間Tcにおける電池電圧Vおよび充放電電流Iに基づいて、入出力電力を計算し、入出力電力を積算することによって入出力電力量を計算し記録する。さらに、データ選択部42は、ある期間内における休止時間Trの合計値ΣTrと、通電時間Tcの合計値ΣTcとを求め、ΣTc/(ΣTc+ΣTr)を通電比率として抽出する。 The data selection unit 42 also calculates the input and output power based on the battery voltage V and the charge/discharge current I during each current-flow time Tc, and calculates and records the amount of input and output power by integrating the input and output power. Furthermore, the data selection unit 42 determines the total value ΣTr of the downtime Tr within a certain period and the total value ΣTc of the current-flow time Tc, and extracts ΣTc/(ΣTc+ΣTr) as the current-flow ratio.

また、データ選択部42は、ある期間において電流極性毎に充放電電流Iを積算し、その結果を各々の通電時間で除算することにより、平均充電電流および平均放電電流を算出し、電池温度とともに記録する。さらに、データ選択部42は、上述のように蓄積された充放電電流Iに基づいて、通電時に変化した電気量および通電時間も併せて記録する。 The data selection unit 42 also integrates the charge/discharge current I for each current polarity over a certain period of time, and divides the result by the current flow time to calculate the average charge current and average discharge current, which are then recorded together with the battery temperature. The data selection unit 42 also records the amount of electricity that changes during current flow and the current flow time based on the charge/discharge current I accumulated as described above.

図16において、運転パラメータ算出部45は、多岐にわたる運転パラメータを分析することができる。これらのパラメータは、特に図示しないが、例えば、開始電圧Vini、終了電圧Vlast、最大電圧Vmax、最低電圧Vmin、セル温度Tcell、環境温度Ta、充電容量Qc、放電容量Qd、単位時間当たりの電気量変動ΔQ、最大電流Imax、最小電流Imin、平均電流Iave、実効電流Ie、稼働中心電圧Vcenter、各電圧領域の滞在時間比率Ratet、単位時間当たりの通電極性比率tp、通電時間比率ts、休止時間比率tr、上下限SOC(SOCmax、SOCmin)、上下限電圧(Vmax、Vmin)、SOC変動幅ΔSOC、通電時間ttotalなどである。なお、通電極性比率tpは、一定の通電時間内に充電と放電の極性が何回変わったかを示す指標である。 16, the operating parameter calculation unit 45 can analyze a wide variety of operating parameters. These parameters are not specifically illustrated, but include, for example, the start voltage Vini, the end voltage Vlast, the maximum voltage Vmax, the minimum voltage Vmin, the cell temperature Tcell, the environmental temperature Ta, the charge capacity Qc, the discharge capacity Qd, the fluctuation in the amount of electricity ΔQ per unit time, the maximum current Imax, the minimum current Imin, the average current Iave, the effective current Ie, the operating center voltage Vcenter, the residence time ratio Ratet in each voltage region, the conductive polarity ratio tp per unit time, the current-carrying time ratio ts, the rest time ratio tr, the upper and lower SOC limits (SOCmax, SOCmin), the upper and lower voltage limits (Vmax, Vmin), the SOC fluctuation range ΔSOC, and the current-carrying time ttotal. The conductive polarity ratio tp is an index indicating how many times the polarity of charging and discharging has changed within a certain current-carrying time.

図17に示すように、二次電池11においては、充放電電流Iの変動に対してSOCも変動する。このときのSOCの最大値を最大SOCとし、SOCの最小値を最小SOCとし、両者の差からSOC変動幅ΔSOCが求められる。データ選択部42は、例えば充電が継続している部分の電気量ΔQcと、放電が継続している部分の電気量ΔQdとを電流波形から抽出する。そして、データ選択部42は、単位時間内でこれらの値を積算して平均値で除算することにより、単位時間当たりの電気量変動ΔQを算出する。 As shown in FIG. 17, in the secondary battery 11, the SOC also fluctuates in response to fluctuations in the charge/discharge current I. The maximum value of the SOC at this time is taken as the maximum SOC, the minimum value of the SOC is taken as the minimum SOC, and the SOC fluctuation range ΔSOC is calculated from the difference between the two. The data selection unit 42 extracts, for example, the amount of electricity ΔQc of the portion where charging is continuing and the amount of electricity ΔQd of the portion where discharging is continuing from the current waveform. The data selection unit 42 then calculates the amount of electricity fluctuation ΔQ per unit time by integrating these values within a unit time and dividing by the average value.

また、データ選択部42は、その他にも、発熱の指標として定義する発熱ファクタ積算値I2tや、電池温度の変化量ΔTなどを使用して、運転パラメータの分析を行うことができる。なお、運転パラメータの分析に用いるデータの数は、任意に決定することができる。 In addition, the data selection unit 42 can analyze the operating parameters using the heat generation factor integrated value I2t defined as an index of heat generation, the amount of change in battery temperature ΔT, etc. The number of data used in the analysis of the operating parameters can be determined arbitrarily.

また、運転パラメータ算出部45は、データ蓄積部41に蓄積されたデータの蓄積期間に対応して、数時間から数十日分の運転パラメータを分析し、これらパラメータを運転状態に相当するパターンに近似する。さらに、算出した二次電池11の劣化状態と、その時の運転パラメータとを時系列に履歴セットとして蓄積し、運転方法が変化したときの条件と容量および抵抗の変化を記録してもよい。これにより、同一の二次電池11の異常を容易に発見できる効果がある。 The operating parameter calculation unit 45 also analyzes operating parameters for several hours to several tens of days, corresponding to the accumulation period of data accumulated in the data accumulation unit 41, and approximates these parameters to a pattern corresponding to the operating state. Furthermore, the calculated deterioration state of the secondary battery 11 and the operating parameters at that time may be accumulated in chronological order as a history set, and the conditions and changes in capacity and resistance when the operating method is changed may be recorded. This has the effect of making it easy to discover abnormalities in the same secondary battery 11.

また、車両10の図示せぬOBD端子を介して二次電池11の使用時の温度データが出力されない場合も考えられる。このような場合、端末220(図12参照)に車両走行時および車両停止時の気温や電池温度を記録し、二次電池11の温度履歴として利用するとよい。
このように、本実施形態によれば、車両10の重量や、二次電池11の劣化状態に関する情報を適切に検出し、二次電池11の容量や抵抗等を取得でき、精度の高い劣化予測情報を利用することで、適切な走行開始条件(SOCs,Vs)を指定することが可能になる。
There may also be cases where temperature data during use of the secondary battery 11 is not output via an OBD terminal (not shown) of the vehicle 10. In such cases, it is advisable to record the air temperature and battery temperature while the vehicle is running and when the vehicle is stopped in the terminal 220 (see FIG. 12 ) and use the recorded data as the temperature history of the secondary battery 11.
In this way, according to this embodiment, it is possible to appropriately detect information relating to the weight of the vehicle 10 and the deterioration state of the secondary battery 11, and obtain the capacity, resistance, etc. of the secondary battery 11, and by using highly accurate deterioration prediction information, it is possible to specify appropriate driving start conditions (SOCs, Vs).

[第10実施形態]
図18は、好適な第10実施形態による二次電池管理システムS10のブロック図である。なお、以下の説明において、上述した他の実施形態の各部に対応する部分には同一の符号を付し、その説明を省略する場合がある。
二次電池管理システムS10は、充電装置200と、二次電池管理装置100F(コンピュータ)と、電力量データベース142と、電池劣化データベース144と、を備えている。
[Tenth embodiment]
18 is a block diagram of a secondary battery management system S10 according to a preferred embodiment 10. In the following description, parts corresponding to the parts of the other embodiments described above are given the same reference numerals, and the description thereof may be omitted.
The secondary battery management system S10 includes a charging device 200, a secondary battery management device 100F (computer), an electric energy database 142, and a battery deterioration database 144.

二次電池管理装置100Fのハードウエア構成は、第4実施形態の二次電池管理装置100D(図6参照)と同様である。そして、二次電池管理装置100Fは、二次電池管理装置100Dと同様に、電力量算出部112と、走行開始状態決定部114と、デューティ比決定部116と、データベース更新部118と、解析部120と、充電制御部124と、を備えている。これらの機能も第4実施形態のものと同様である。
本実施形態によれば、二次電池管理装置100F内の充電制御部124がデューティ比Dtrに基づいて充電装置200を制御するため、個々の車両10における構成を簡略化することができる。
The hardware configuration of the secondary battery management device 100F is similar to that of the secondary battery management device 100D of the fourth embodiment (see FIG. 6). Like the secondary battery management device 100D, the secondary battery management device 100F includes an electric energy calculation unit 112, a running start state determination unit 114, a duty ratio determination unit 116, a database update unit 118, an analysis unit 120, and a charge control unit 124. These functions are also similar to those of the fourth embodiment.
According to this embodiment, the charging control unit 124 in the secondary-battery management device 100F controls the charging device 200 based on the duty ratio Dtr, so that the configuration of each vehicle 10 can be simplified.

[実施形態の効果]
以上のように好適な実施形態による二次電池管理装置100A,100B,100D,100E,100Fは、二次電池11によって駆動される移動体(10)の移動日時または移動時外気温と、移動経路と、に対応して所要電力量を記憶する電力量データベース142に基づいて、移動体(10)が指定された移動予定経路(Rt)を移動するために要すると予測される予測電力量W2を算出する電力量算出部(105,106,112)と、二次電池11の劣化状態(SOHQ,SOHR)を記録し、または、二次電池11の使用状態と劣化状態(SOHQ,SOHR)との相関関係を示すデータとともに二次電池11の過去の使用状態を記録した電池劣化データベース144を参照し、劣化状態(SOHQ,SOHR)に応じて、予測電力量W2を確保できる二次電池11の使用SOC領域または使用電圧領域を算出し、算出した使用SOC領域または使用電圧領域に基づいて、充電完了状態における二次電池11の電圧またはSOCである走行開始条件(SOCs,Vs)を決定する走行開始状態決定部114と、を備える。これにより、二次電池11の劣化状態(SOHQ,SOHR)に基づいて、二次電池11の充電状態を適切に決定できる。
[Effects of the embodiment]
As described above, the secondary battery management devices 100A, 100B, 100D, 100E, and 100F according to the preferred embodiments include an electric energy calculation unit (105, 106, 112) that calculates a predicted amount of electric energy W2 that is predicted to be required for a moving body (10) to move along a designated planned moving route (Rt) based on an electric energy database 142 that stores a required amount of electric energy corresponding to the moving date and time or outside air temperature during moving of the moving body (10) driven by the secondary battery 11, and a state of deterioration (SOHQ, SOHR) of the secondary battery 11 or a secondary battery 12 that stores the state of deterioration (SOHQ, SOHR) of the secondary battery 11. and a running start state determination unit 114 that refers to a battery degradation database 144 that records the past usage states of the secondary battery 11 together with data showing the correlation between the usage state and the degradation state (SOHQ, SOHR) of the secondary battery 11, calculates a usage SOC region or usage voltage region of the secondary battery 11 that can secure a predicted power amount W2 according to the degradation state (SOHQ, SOHR), and determines a running start condition (SOCs, Vs) that is the voltage or SOC of the secondary battery 11 in a charged state based on the calculated usage SOC region or usage voltage region. This makes it possible to appropriately determine the charging state of the secondary battery 11 based on the degradation state (SOHQ, SOHR) of the secondary battery 11.

また、電力量データベース142は、移動日時または移動時外気温と、移動経路と、に加えて、移動体(10)の重量に対応して所要電力量を記憶するものであり、電力量算出部(105,106,112)は、移動体(10)の重量と、移動予定経路(Rt)とに基づいて予測電力量W2を算出すると一層好ましい。これにより、様々な重量を有する移動体(10)の様々な移動予定経路(Rt)に対応して、二次電池11充電状態を一層適切に決定できる。 The power database 142 also stores the required power amount corresponding to the weight of the moving body (10) in addition to the travel date and time or the outside air temperature during travel and the travel route, and it is more preferable that the power amount calculation unit (105, 106, 112) calculates the predicted power amount W2 based on the weight of the moving body (10) and the planned travel route (Rt). This makes it possible to more appropriately determine the charge state of the secondary battery 11 in accordance with various planned travel routes (Rt) of moving bodies (10) having various weights.

また、二次電池11は、通電状態と休止状態とを交互に繰り返しつつ充電されることが可能なものであり、電池劣化データベース144に基づいて、二次電池11の劣化が進行するほど通電状態のデューティ比を下げるようにデューティ比を決定するデューティ比決定部116をさらに備えると一層好ましい。これにより、二次電池11の劣化状態に応じて、デューティ比決定部116が適切なデューティ比を決定することができる。 The secondary battery 11 can be charged while alternately repeating a powered state and a resting state, and it is more preferable to further include a duty ratio determination unit 116 that determines the duty ratio based on the battery deterioration database 144 so that the duty ratio of the powered state is lowered as the deterioration of the secondary battery 11 progresses. This allows the duty ratio determination unit 116 to determine an appropriate duty ratio according to the deterioration state of the secondary battery 11.

また、走行開始状態決定部114は、劣化状態(SOHQ,SOHR)と、走行開始条件(SOCs,Vs)との関係をマップ形式のデータとして記憶し、マップ形式のデータを参照して走行開始条件(SOCs,Vs)を決定すると一層好ましい。これにより、実装時のデータ量を削減し、演算量を低減することが可能になり、システムストレージに余裕を持たせて高速に演算することが可能になる。 More preferably, the driving start state determination unit 114 stores the relationship between the deterioration state (SOHQ, SOHR) and the driving start condition (SOCs, Vs) as map-format data, and determines the driving start condition (SOCs, Vs) by referring to the map-format data. This makes it possible to reduce the amount of data and the amount of calculations during implementation, and allows for high-speed calculations with ample system storage.

また、電力量データベース142は、移動日時または移動時外気温と、移動経路と、移動体の重量と、に加えて、移動体の運転者を特定する運転者識別情報に対応して所要電力量を記憶するものであり、走行開始状態決定部114は、教師あり学習によって学習処理を行った人工知能によって走行開始条件を決定するものであり、移動体の移動状況に応じて電力量データベース142と、電池劣化データベース144と、をリアルタイムで更新するデータベース更新部118をさらに備えると一層好ましい。これにより、移動体(10)の実際の運用状態に応じて、電力量データベース142および電池劣化データベース144をリアルタイムに更新できる。 The power database 142 stores the required power amount corresponding to the travel date and time or the outside temperature during travel, the travel route, the weight of the mobile body, and the driver identification information that identifies the driver of the mobile body, and the travel start state determination unit 114 determines the travel start conditions using artificial intelligence that has performed learning processing through supervised learning, and it is even more preferable to further include a database update unit 118 that updates the power database 142 and the battery deterioration database 144 in real time according to the travel status of the mobile body. This allows the power database 142 and the battery deterioration database 144 to be updated in real time according to the actual operating status of the mobile body (10).

また、走行開始状態決定部114は、二次電池11の想定温度Tassを受信する機能と、受信した想定温度Tassが高くなるほど、二次電池11が所定時間以上滞在するSOCである滞在SOCが低くなるように、走行開始条件(SOCs,Vs)を決定する機能と、を備えると一層好ましい。これにより、想定温度Tassに対応した適切な走行開始条件(SOCs,Vs)を決定することができる。 Moreover, it is more preferable that the driving start state determination unit 114 has a function of receiving the assumed temperature Tass of the secondary battery 11, and a function of determining the driving start conditions (SOCs, Vs) such that the higher the received assumed temperature Tass, the lower the staying SOC, which is the SOC at which the secondary battery 11 stays for a predetermined time or more. This makes it possible to determine appropriate driving start conditions (SOCs, Vs) corresponding to the assumed temperature Tass.

また、二次電池管理装置100B,100Dのように、走行開始状態決定部114から供給された走行開始条件(SOCs,Vs)と、デューティ比決定部116が決定したデューティ比Dtrと、に基づいて、二次電池11を充電する充電装置200を制御する充電制御部124をさらに備えると一層好ましい。これにより、適切なデューティ比Dtrで二次電池11を充電することができる。 Moreover, like the secondary battery management devices 100B and 100D, it is even more preferable to further include a charging control unit 124 that controls the charging device 200 that charges the secondary battery 11 based on the driving start conditions (SOCs, Vs) supplied from the driving start state determination unit 114 and the duty ratio Dtr determined by the duty ratio determination unit 116. This allows the secondary battery 11 to be charged with an appropriate duty ratio Dtr.

また、二次電池管理装置100Dのように、移動体(10)の運行スケジュールを立案する運行スケジュール立案部146と通信し、移動体の充電スケジュールを立案する充電スケジュール立案部122をさらに備えると一層好ましい。これにより、移動体(10)の運行スケジュールに適合した充電スケジュールを立案することができる。 Moreover, like the secondary battery management device 100D, it is even more preferable to further include a charging schedule planning unit 122 that communicates with an operation schedule planning unit 146 that plans an operation schedule for the mobile body (10) and plans a charging schedule for the mobile body. This makes it possible to plan a charging schedule that is compatible with the operation schedule of the mobile body (10).

[変形例]
本発明は上述した実施形態に限定されるものではなく、種々の変形が可能である。上述した実施形態は本発明を理解しやすく説明するために例示したものであり、必ずしも説明した全ての構成を備えるものに限定されるものではない。また、ある実施形態の構成の一部を他の実施形態の構成に置き換えることが可能であり、ある実施形態の構成に他の実施形態の構成を加えることも可能である。また、各実施形態の構成の一部について削除し、もしくは他の構成の追加・置換をすることが可能である。また、図中に示した制御線や情報線は説明上必要と考えられるものを示しており、製品上で必要な全ての制御線や情報線を示しているとは限らない。実際には殆ど全ての構成が相互に接続されていると考えてもよい。上記実施形態に対して可能な変形は、例えば以下のようなものである。
[Modification]
The present invention is not limited to the above-mentioned embodiment, and various modifications are possible. The above-mentioned embodiment is exemplified to explain the present invention in an easy-to-understand manner, and is not necessarily limited to those having all the configurations described. In addition, it is possible to replace a part of the configuration of one embodiment with the configuration of another embodiment, and it is also possible to add the configuration of another embodiment to the configuration of one embodiment. In addition, it is possible to delete a part of the configuration of each embodiment, or to add or replace other configurations. In addition, the control lines and information lines shown in the figure show those that are considered necessary for explanation, and do not necessarily show all the control lines and information lines necessary on the product. In reality, it may be considered that almost all the configurations are connected to each other. Possible modifications of the above-mentioned embodiment are, for example, as follows.

(1)上述した車両10は、配送、配達トラックのみならず、ルートが確定している電気自動車バス、路面電池車両等にも適用でき、劣化を抑制しながら電池量の最適化や使用期間とコストのバランスを取り二次電池を有効に活用することが可能になる。さらに、本発明における移動体は、車両10に限られるものではなく、二次電池を動力源とする走行ロボット、飛行ロボット、飛翔体、船舶等も含まれる。 (1) The vehicle 10 described above can be applied not only to delivery trucks, but also to electric buses with fixed routes, road battery vehicles, etc., and makes it possible to effectively utilize secondary batteries by optimizing battery capacity while suppressing deterioration and balancing usage period and cost. Furthermore, the mobile body in the present invention is not limited to the vehicle 10, but also includes running robots, flying robots, flying objects, ships, etc. that use secondary batteries as a power source.

(2)上記実施形態における二次電池管理装置100A,100B,100D,100Eのハードウエアは一般的なコンピュータによって実現できるため、図7、図13に示したフローチャート、その他上述した各種処理を実行するプログラム等を記憶媒体に格納し、または伝送路を介して頒布してもよい。 (2) The hardware of the secondary battery management devices 100A, 100B, 100D, and 100E in the above embodiments can be realized by a general computer, so the flowcharts shown in Figures 7 and 13 and other programs that execute the various processes described above may be stored on a storage medium or distributed via a transmission path.

(3)図7、図13に示した処理、その他上述した各処理は、上記実施形態ではプログラムを用いたソフトウエア的な処理として説明したが、その一部または全部をASIC(Application Specific Integrated Circuit;特定用途向けIC)、あるいはFPGA(Field Programmable Gate Array)等を用いたハードウエア的な処理に置き換えてもよい。 (3) In the above embodiment, the processes shown in Figures 7 and 13 and the other processes described above are described as software processes using a program, but some or all of them may be replaced with hardware processes using an ASIC (Application Specific Integrated Circuit) or an FPGA (Field Programmable Gate Array), etc.

(4)上記実施形態において実行される各種処理は、図示せぬネットワーク経由でサーバコンピュータが実行してもよく、上記実施形態において記憶される各種データも該サーバコンピュータに記憶させるようにしてもよい。 (4) The various processes performed in the above embodiment may be executed by a server computer via a network (not shown), and the various data stored in the above embodiment may also be stored in the server computer.

10 車両(移動体)
11 二次電池
100A,100B,100D,100E 二次電池管理装置(コンピュータ)
105 予測電力量計算部(電力量算出部)
106 予測電力量補正部(電力量算出部)
112 電力量算出部(電力量算出手段、電力量算出過程)
114 走行開始状態決定部(充電条件決定手段、充電条件決定過程)
116 デューティ比決定部
118 データベース更新部
122 充電スケジュール立案部
124 充電制御部
142 電力量データベース
144 電池劣化データベース
146 運行スケジュール立案部
200 充電装置
Rt 予定ルート情報(移動予定経路)
Vs 走行開始電圧(走行開始条件)
Dtr デューティ比
SOCs 走行開始充電率(走行開始条件)
Tass 想定温度
W2 予測電力量
SOHQ,SOHR 劣化度(劣化状態)
10. Vehicles (moving objects)
11 Secondary batteries 100A, 100B, 100D, 100E Secondary battery management device (computer)
105 predicted power amount calculation unit (power amount calculation unit)
106 predicted power amount correction unit (power amount calculation unit)
112 Electric energy calculation unit (electric energy calculation means, electric energy calculation process)
114: Running start state determination unit (charging condition determination means, charging condition determination process)
116 Duty ratio determination unit 118 Database update unit 122 Charging schedule planning unit 124 Charging control unit 142 Power amount database 144 Battery deterioration database 146 Operation schedule planning unit 200 Charging device Rt Planned route information (planned travel route)
Vs Running start voltage (running start condition)
Dtr Duty ratio SOCs Charge rate at start of running (start condition of running)
Tass Estimated temperature W2 Estimated power consumption SOHQ, SOHR Degree of deterioration (deterioration state)

Claims (10)

二次電池によって駆動される移動体の移動日時または移動時外気温と、移動経路と、に対応して所要電力量を記憶する電力量データベースに基づいて、前記移動体が指定された移動予定経路を移動するために要すると予測される予測電力量を算出する電力量算出部と、
前記二次電池の使用状態と劣化状態との相関関係を示すデータとともに前記二次電池の過去の使用状態を記録した電池劣化データベースを参照し、前記二次電池の劣化状態に応じて、前記予測電力量を確保できる前記二次電池の使用SOC領域または使用電圧領域を算出し、算出した前記使用SOC領域または前記使用電圧領域に基づいて、充電完了状態における前記二次電池の電圧またはSOCである走行開始条件を決定する走行開始状態決定部と、を備える
ことを特徴とする二次電池管理装置。
an electric power calculation unit that calculates a predicted amount of electric power required for a moving body driven by a secondary battery to move along a designated planned movement route based on an electric power database that stores a required electric power amount corresponding to a movement date and time or an outside temperature during movement and a movement route of the moving body;
a battery degradation database that records the past usage states of the secondary battery along with data indicating the correlation between the usage state and degradation state of the secondary battery, calculates a usage SOC region or usage voltage region of the secondary battery in which the predicted amount of power can be secured according to the degradation state of the secondary battery, and determines a running start condition, which is the voltage or SOC of the secondary battery in a fully charged state, based on the calculated usage SOC region or usage voltage region.
前記電力量データベースは、前記移動日時または前記移動時外気温と、前記移動経路と、に加えて、前記移動体の重量に対応して前記所要電力量を記憶するものであり、
前記電力量算出部は、前記移動体の重量と、前記移動予定経路とに基づいて前記予測電力量を算出する
ことを特徴とする請求項1に記載の二次電池管理装置。
the power amount database stores the required power amount corresponding to the travel date and time or the outside air temperature during the travel, the travel route, and a weight of the moving object;
The secondary battery management device according to claim 1 , wherein the power amount calculation unit calculates the predicted power amount based on a weight of the moving object and the planned moving route.
前記二次電池は、通電状態と休止状態とを交互に繰り返しつつ充電されることが可能なものであり、
前記電池劣化データベースに基づいて、電池劣化と通電比率の情報を使用し、充電完了までの通電時間と通電後の休止時間の比率を決定するデューティ比決定部により充電後の休止時間を制御する
ことを特徴とする請求項2に記載の二次電池管理装置。
The secondary battery is capable of being charged while alternately repeating a power-on state and a power-off state,
The secondary battery management device according to claim 2, characterized in that the rest time after charging is controlled by a duty ratio determination unit that uses information on battery deterioration and current conduction ratio based on the battery deterioration database and determines the ratio of the current conduction time until charging is completed to the rest time after current conduction.
前記走行開始状態決定部は使用条件と、前記走行開始条件との関係をマップ形式のデータとして記憶し、前記マップ形式のデータを参照して前記走行開始条件を決定する
ことを特徴とする請求項1ないし3の何れか1項に記載の二次電池管理装置。
The secondary battery management device according to any one of claims 1 to 3 , characterized in that the driving start state determination unit stores the relationship between the usage conditions and the driving start conditions as map-format data, and determines the driving start conditions by referring to the map-format data.
前記電力量データベースは、前記移動日時または前記移動時外気温と、前記移動経路と、前記移動体の重量と、に加えて、前記移動体の運転者を特定する運転者識別情報に対応して前記所要電力量を記憶するものであり、
前記走行開始状態決定部は、教師あり学習によって学習処理を行った人工知能によって前記走行開始条件を決定するものであり、
前記移動体の移動状況に応じて前記電力量データベースと、前記電池劣化データベースと、をリアルタイムで更新するデータベース更新部をさらに備える
ことを特徴とする請求項3に記載の二次電池管理装置。
the power amount database stores the required power amount in association with the travel date and time or the outside air temperature during travel, the travel route, the weight of the mobile body, and driver identification information that identifies a driver of the mobile body;
The running start condition determination unit determines the running start condition by an artificial intelligence that has undergone a learning process by supervised learning,
4. The secondary battery management device according to claim 3, further comprising a database update unit that updates the power amount database and the battery deterioration database in real time according to a movement state of the mobile object.
前記走行開始状態決定部は、前記二次電池の想定温度を受信する機能と、受信した前記想定温度が高くなるほど、前記二次電池が所定時間以上滞在するSOCである滞在SOCが低くなるように、前記走行開始条件を決定する機能と、を備える
ことを特徴とする請求項1に記載の二次電池管理装置。
The secondary battery management device according to claim 1, characterized in that the driving start state determination unit has a function of receiving an estimated temperature of the secondary battery, and a function of determining the driving start condition so that the higher the received estimated temperature, the lower the staying SOC, which is the SOC at which the secondary battery stays for a predetermined time or more.
前記走行開始状態決定部から供給された前記走行開始条件と、前記デューティ比決定部が決定した前記比率と、に基づいて、前記二次電池を充電する充電装置を制御する充電制御部をさらに備える
ことを特徴とする請求項3に記載の二次電池管理装置。
The secondary battery management device according to claim 3, further comprising a charging control unit that controls a charging device that charges the secondary battery based on the driving start condition supplied from the driving start state determination unit and the ratio determined by the duty ratio determination unit.
前記移動体の運行スケジュールを立案する運行スケジュール立案部と通信し、前記移動体の充電スケジュールを立案する充電スケジュール立案部をさらに備える
ことを特徴とする請求項3に記載の二次電池管理装置。
The secondary battery management device according to claim 3 , further comprising a charging schedule planning unit that communicates with a driving schedule planning unit that plans a driving schedule for the mobile body and that plans a charging schedule for the mobile body.
二次電池によって駆動される移動体の移動日時または移動時外気温と、移動経路と、に対応して所要電力量を記憶する電力量データベースに基づいて、前記移動体が指定された移動予定経路を移動するために要すると予測される予測電力量を算出する電力量算出過程と、
前記二次電池の劣化状態を記録し、または、前記二次電池の使用状態と前記劣化状態との相関関係を示すデータとともに前記二次電池の過去の使用状態を記録した電池劣化データベースを参照し、前記劣化状態に応じて、前記予測電力量を確保できる前記二次電池の使用SOC領域または使用電圧領域を算出し、算出した前記使用SOC領域または前記使用電圧領域に基づいて、充電完了状態における前記二次電池の電圧またはSOCである走行開始条件を決定する充電条件決定過程と、を有する
ことを特徴とする二次電池管理方法。
an energy calculation step of calculating a predicted energy required for a moving body driven by a secondary battery to move along a designated planned moving route based on an energy database storing a required energy amount corresponding to a moving date and time or an outside air temperature during the moving and the moving route;
a charging condition determination process for recording the deterioration state of the secondary battery, or referring to a battery deterioration database in which the past usage states of the secondary battery are recorded together with data showing a correlation between the usage state of the secondary battery and the deterioration state, calculating a usage SOC region or usage voltage region of the secondary battery in which the predicted amount of power can be secured according to the deterioration state, and determining a driving start condition, which is the voltage or SOC of the secondary battery in a fully charged state, based on the calculated usage SOC region or usage voltage region.
コンピュータを、
二次電池によって駆動される移動体の移動日時または移動時外気温と、移動経路と、に対応して所要電力量を記憶する電力量データベースに基づいて、前記移動体が指定された移動予定経路を移動するために要すると予測される予測電力量を算出する電力量算出手段、
前記二次電池の劣化状態を記録し、または、前記二次電池の使用状態と前記劣化状態との相関関係を示すデータとともに前記二次電池の過去の使用状態を記録した電池劣化データベースを参照し、前記劣化状態に応じて、前記予測電力量を確保できる前記二次電池の使用SOC領域または使用電圧領域を算出し、算出した前記使用SOC領域または前記使用電圧領域に基づいて、充電完了状態における前記二次電池の電圧またはSOCである走行開始条件を決定する充電条件決定手段、
として機能させるためのプログラム。
Computer,
an electric power calculation means for calculating a predicted amount of electric power required for a moving body driven by a secondary battery to move along a designated planned moving route, based on an electric power database storing a required electric power amount corresponding to a moving date and time or an outside temperature during the moving and a moving route;
a charging condition determination means for recording a degradation state of the secondary battery, or for referring to a battery degradation database in which a past usage state of the secondary battery is recorded together with data showing a correlation between a usage state of the secondary battery and the degradation state, calculating a usage SOC region or usage voltage region of the secondary battery in which the predicted amount of power can be secured according to the degradation state, and determining a running start condition, which is the voltage or SOC of the secondary battery in a charging complete state, based on the calculated usage SOC region or usage voltage region;
A program to function as a
JP2021080900A 2021-05-12 2021-05-12 Secondary battery management device, secondary battery management method, and program Active JP7684089B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2021080900A JP7684089B2 (en) 2021-05-12 2021-05-12 Secondary battery management device, secondary battery management method, and program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2021080900A JP7684089B2 (en) 2021-05-12 2021-05-12 Secondary battery management device, secondary battery management method, and program

Publications (2)

Publication Number Publication Date
JP2022174885A JP2022174885A (en) 2022-11-25
JP7684089B2 true JP7684089B2 (en) 2025-05-27

Family

ID=84144845

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2021080900A Active JP7684089B2 (en) 2021-05-12 2021-05-12 Secondary battery management device, secondary battery management method, and program

Country Status (1)

Country Link
JP (1) JP7684089B2 (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102706438B1 (en) * 2021-12-10 2024-09-13 주식회사 엘지에너지솔루션 Charging protocol inspection apparatus and operating method of the same
JP2024115916A (en) * 2023-02-15 2024-08-27 プライムアースEvエナジー株式会社 Design method of non-aqueous electrolyte secondary battery, non-aqueous electrolyte secondary battery
WO2024189905A1 (en) * 2023-03-16 2024-09-19 株式会社 東芝 Storage cell diagnostic device, diagnostics system, and diagnostic method
CN116736150B (en) * 2023-08-16 2023-11-03 杭州高特电子设备股份有限公司 Battery abnormality detection method, battery system and computer program
JP7806773B2 (en) * 2023-09-21 2026-01-27 トヨタ自動車株式会社 Charging system and charging method
CN118362906B (en) * 2024-06-19 2024-10-29 中国第一汽车股份有限公司 Battery state parameter prediction method, device, electronic device and storage medium
CN118810540B (en) * 2024-09-20 2024-12-03 南通理工学院 Electric control method and system for new energy automobile

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5454537B2 (en) * 2011-09-22 2014-03-26 株式会社デンソー Electric vehicle charging control system
JP5803548B2 (en) * 2011-10-13 2015-11-04 日産自動車株式会社 Charge control device
JP2018064413A (en) * 2016-10-14 2018-04-19 東洋ゴム工業株式会社 Charge system for secondary battery and charge optimizing method

Also Published As

Publication number Publication date
JP2022174885A (en) 2022-11-25

Similar Documents

Publication Publication Date Title
JP7684089B2 (en) Secondary battery management device, secondary battery management method, and program
KR102928335B1 (en) Powering electric vehicles
JP7182476B2 (en) Remaining life diagnostic method and remaining life diagnostic system for secondary battery module
US20230406109A1 (en) Predictive model for estimating battery states
US11325494B2 (en) Systems, methods, and storage media for determining a target battery charging level for a drive route
JP7097336B2 (en) Secondary battery module temperature estimation method, deterioration state estimation method and life prediction method, secondary battery module temperature estimation device, deterioration state estimation device and life prediction device, and charging device
US20230139003A1 (en) Systems and methods for managing velocity profiles
EP3850551A1 (en) Systems and methods for managing energy storage systems
CN113325316A (en) Information calculation system and information calculation method
US11225169B2 (en) Management system with supervisory control for rechargeable energy storage device in electric vehicle
US20220041078A1 (en) Energy storage device evaluation device, computer program, energy storage device evaluation method, learning method and generation method
CN116373680A (en) Method and apparatus for operating powered equipment with replaceable equipment batteries and battery swap station with predictive dispatch
WO2023224874A1 (en) System and method for battery state of health characterization based on route segments
CN109919393A (en) A kind of charging load forecasting method of electric taxi
US20240013313A1 (en) Information processing device, insurance premium determination method, and system
Delprat et al. Reducing the computation effort of a hybrid vehicle predictive energy management strategy
KR20250063631A (en) Driving Energy Based SOH Diagnosis Method and System for Electric Vehicle Batteries
EP4390793A1 (en) A method and system for electrical energy storage maintenance on fleet level
Shiledar et al. Daily Operational Impacts on Battery Degradation in Heavy-Duty Electric Drayage Trucks
Borgosano et al. Predictive Modelling of Electric Vehicle Charging Sessions: an Empirical Validation of an Italy-France Route
Staudt et al. Applying Data Reduction Methods to Battery Degradation Prediction Models for Electric Vehicles
Klaproth et al. Long-term Monitoring of Electrical Bus Fleets for Usage Analysis and Operating Strategy Optimization
CN116848015A (en) Powering electric vehicles

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20240129

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20241211

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20250107

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20250129

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20250507

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20250515

R150 Certificate of patent or registration of utility model

Ref document number: 7684089

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150