Joint structure between steel girder and precast deck Download PDF

Info

Publication number
JP7692807B2
JP7692807B2 JP2021192410A JP2021192410A JP7692807B2 JP 7692807 B2 JP7692807 B2 JP 7692807B2 JP 2021192410 A JP2021192410 A JP 2021192410A JP 2021192410 A JP2021192410 A JP 2021192410A JP 7692807 B2 JP7692807 B2 JP 7692807B2
Authority
JP
Japan
Prior art keywords
steel
joint structure
steel girder
precast deck
girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2021192410A
Other languages
Japanese (ja)
Other versions
JP2023079021A (en
Inventor
明夫 正司
俊也 井隼
博 渡瀬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Oriental Shiraishi Corp
Original Assignee
Oriental Shiraishi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Oriental Shiraishi Corp filed Critical Oriental Shiraishi Corp
Priority to JP2021192410A priority Critical patent/JP7692807B2/en
Publication of JP2023079021A publication Critical patent/JP2023079021A/en
Application granted granted Critical
Publication of JP7692807B2 publication Critical patent/JP7692807B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

本発明は、鋼桁とプレキャスト床版との接合構造に関する。 The present invention relates to a joint structure between a steel girder and a precast deck.

従来、鋼桁とプレキャスト床版との接合は、鋼桁の上フランジにずれ止めとしてスタッドジベルを溶殖して、上下に貫通する箱抜き孔を有したプレキャスト床版を鋼桁の上フランジを載置し、溶殖したスタッドジベルを箱抜き孔に収容する。そして、箱抜き孔に無収縮モルタル等の充填材を充填して硬化させ、鋼桁とプレキャスト床版と一体化させて合成桁としている。 Conventionally, steel girders and precast decks are joined by welding stud dowels to the upper flange of the steel girder as a slip stopper, placing a precast deck with a box-punched hole that penetrates from top to bottom on the upper flange of the steel girder, and fitting the welded stud dowels into the box-punched hole. The box-punched hole is then filled with a filler such as non-shrink mortar and allowed to harden, integrating the steel girder with the precast deck to form a composite girder.

しかし、大きなせん断力が作用する支点付近においては、ずれ止めに必要なスタッドの数が多くなり、プレキャスト床版の配筋が制限されるだけでなく、後打ち施工となるため耐久性上での弱点となっていた。また、充填材を硬化させる養生時間が必要なため、工期が長期化する要因となっているという問題もあった。このため、プレキャスト床版に箱抜き孔を設けずに鋼桁と一体的に接合する方法が切望されていた。 However, near the supports where large shear forces act, a large number of studs are required to prevent slippage, which not only limits the reinforcement of the precast deck, but also weakens its durability because it requires post-cast construction. There is also the problem that the filling material requires time to harden, which lengthens the construction period. For this reason, there was a strong demand for a method to join the precast deck to the steel girders as a single unit without creating box-punched holes.

このような問題を解決するべく、例えば、特許文献1には、プレキャスト床版にボルトと螺合するインサートを埋設し、鋼桁の上フランジに貫通孔を穿設し、鋼桁の上フランジとプレキャスト床版のインサートとをボルトで螺合して接合する鋼桁とプレキャスト床版との接合構造が開示されている(特許文献1の明細書の段落[0012]~[0027]、図面の図1等参照)。 To solve these problems, for example, Patent Document 1 discloses a joint structure between a steel girder and a precast deck in which an insert that screws into a bolt is embedded in the precast deck, a through hole is drilled in the upper flange of the steel girder, and the upper flange of the steel girder and the insert in the precast deck are joined by screwing the bolt together (see paragraphs [0012] to [0027] of the specification of Patent Document 1 and Figure 1 of the drawings, etc.).

しかし、特許文献1に記載の鋼桁とプレキャスト床版との接合構造は、充填材の硬化時間が必要ないため短期間で施工が可能であるが、鋼桁の上フランジに貫通孔を設けるため、断面欠損になり、構造上の弱点となるという問題があった。 However, the joint structure between the steel girder and the precast deck described in Patent Document 1 can be constructed in a short period of time because no time is required for the filler to harden, but there is a problem in that through holes must be provided in the upper flange of the steel girder, resulting in cross-sectional defects and structural weaknesses.

また、特許文献2には、スタッドジベル11を有するずれ止め部と、プレキャスト床版3の下面3aに埋設されたインサートナット7と、インサートナット7に取付けられたボルト9と、これらのスタッドジベル11とボルト9とを埋込むように硬化させる充填材15と、を備える鋼桁とプレキャスト床版との接合構造が開示されている(特許文献2の明細書の段落[0017]~[0032]、図面の図5等参照)。 Patent Document 2 also discloses a joint structure between a steel girder and a precast deck, which includes a slip prevention section having a stud dowel 11, an insert nut 7 embedded in the underside 3a of the precast deck 3, a bolt 9 attached to the insert nut 7, and a filler 15 that hardens to embed the stud dowel 11 and the bolt 9 (see paragraphs [0017] to [0032] of the specification of Patent Document 2, Figure 5 of the drawings, etc.).

しかし、特許文献2に記載の鋼桁とプレキャスト床版との接合構造は、せん断力には対抗できるものの、橋軸直角方向等の曲げモーメントには対抗できないという問題があった。 However, the joint structure between the steel girder and the precast deck described in Patent Document 2 had the problem that although it could withstand shear forces, it could not withstand bending moments perpendicular to the bridge axis.

特開2015-86595号公報JP 2015-86595 A 特開2021-1457号公報JP 2021-1457 A

そこで、本発明は、前述した問題に鑑みて案出されたものであり、その目的とするところは、短期間で施工が可能で、鋼桁に断面欠損が無く、橋軸方向せん断力にも橋軸直角方向曲げモーメントにも対抗することができる鋼桁とプレキャスト床版との接合構造を提供することにある。 The present invention was devised in consideration of the above-mentioned problems, and its purpose is to provide a joint structure between a steel girder and a precast deck that can be constructed in a short period of time, has no cross-sectional defects in the steel girder, and can withstand both shear forces in the bridge axis direction and bending moments perpendicular to the bridge axis.

請求項1に係る鋼桁とプレキャスト床版との接合構造は、鋼桁と、この鋼桁上に載置されたプレキャスト床版と、を接合する鋼桁とプレキャスト床版との接合構造であって、前記鋼桁の上フランジの上面の両縁には、この上フランジに溶殖されたスタッドボルトで底面部と立上り部とを有する断面L字状の一対の鋼製治具が取り付けられ、前記プレキャスト床版の下面には、少なくとも左右及び下方の三方を囲む囲繞部を有するずれ止め鋼材が突設され、前記一対の鋼製治具の間には、連結ボルトが挿通されて前記立上り部に止め付けられ、前記連結ボルトが前記ずれ止め鋼材の前記囲繞部に挿通されることで、前記鋼桁と前記プレキャスト床版とが接合されていることを特徴とする。 The joint structure between a steel girder and a precast deck according to claim 1 is a joint structure between a steel girder and a precast deck placed on the steel girder, characterized in that a pair of steel jigs with an L-shaped cross section having a bottom part and a rising part are attached to both edges of the upper surface of the upper flange of the steel girder by stud bolts fused to the upper flange, a shear-stop steel material having an enclosing part surrounding at least three sides, the left and right and the bottom, is protruded from the underside of the precast deck, a connecting bolt is inserted between the pair of steel jigs and fastened to the rising part, and the connecting bolt is inserted into the enclosing part of the shear-stop steel material to join the steel girder and the precast deck.

請求項2に係る鋼桁とプレキャスト床版との接合構造は、請求項1に係る鋼桁とプレキャスト床版との接合構造において、前記囲繞部は、側面視U字状の棒鋼又は穴開き鋼板からなることを特徴とする。 The joint structure between a steel girder and a precast deck according to claim 2 is the joint structure between a steel girder and a precast deck according to claim 1, characterized in that the surrounding portion is made of a U-shaped steel bar or a perforated steel plate when viewed from the side.

請求項3に係る鋼桁とプレキャスト床版との接合構造は、請求項1又は2に係る鋼桁とプレキャスト床版との接合構造において、前記一対の鋼製治具は、前記立上り部が外側となるように前記鋼桁の前記上フランジの両縁に取り付けられ、前記一対の鋼製治具の間には、充填材が充填されていることを特徴とする。 The joint structure between a steel girder and a precast deck according to claim 3 is the joint structure between a steel girder and a precast deck according to claim 1 or 2, characterized in that the pair of steel jigs are attached to both edges of the upper flange of the steel girder so that the rising portion is on the outside, and a filler material is filled between the pair of steel jigs.

請求項4に係る鋼桁とプレキャスト床版との接合構造は、請求項1又は2に係る鋼桁とプレキャスト床版との接合構造において、前記一対の鋼製治具は、前記立上り部が内側となるように前記鋼桁の前記上フランジの両縁に取り付けられ、前記連結ボルト及び前記スタッドボルトは、充填材の内部に埋設されていることを特徴とする。 The joint structure between a steel girder and a precast deck according to claim 4 is characterized in that in the joint structure between a steel girder and a precast deck according to claim 1 or 2, the pair of steel jigs are attached to both edges of the upper flange of the steel girder so that the rising portion is on the inside, and the connecting bolt and the stud bolt are embedded inside the filling material.

請求項1~4に係る発明によれば、プレキャスト床版に上下に貫通する貫通孔が無いため、プレキャスト床版に構造上の弱点部を無くすことができるたけでなく、充填材が硬化するまでの間もプレキャスト床版上での作業が可能となり、結果的に短時間で施工が可能となる。また、請求項1~4に係る発明によれば、鋼桁にも貫通孔を設ける必要がないため、鋼桁の断面欠損を無くすことができ、構造上安全な構造とすることができる。その上、請求項1~4に係る発明によれば、連結ボルトが側面視U字状のずれ止め鋼材に挿通されることで、鋼桁とプレキャスト床版とが接合されているので、橋軸直角方向のせん断力だけでなく、橋軸方向せん断力にも橋軸直角方向曲げモーメントにも対抗することができ、耐震上強固な接合構造とすることができる。 According to the inventions of claims 1 to 4, since there are no through holes that penetrate vertically in the precast deck, not only can the precast deck have no structural weak points, but also work can be done on the precast deck while the filling material is hardening, resulting in a short construction time. In addition, according to the inventions of claims 1 to 4, since there is no need to provide through holes in the steel girders, cross-sectional defects in the steel girders can be eliminated, resulting in a safe structure. Furthermore, according to the inventions of claims 1 to 4, the steel girders and the precast deck are joined by inserting the connecting bolts into the shear-stop steel material that is U-shaped in side view, so that it can withstand not only shear forces perpendicular to the bridge axis, but also shear forces in the bridge axis direction and bending moments perpendicular to the bridge axis, resulting in a joint structure that is strong in terms of earthquake resistance.

特に、請求項2に係る発明によれば、囲繞部が側面視U字状の棒鋼又は穴開き鋼板からなるので、連結ボルトを囲繞部で確実に取り囲んでせん断力及び曲げモーメントを伝達し、これらの応力に対抗することができる。 In particular, according to the invention of claim 2, the surrounding portion is made of a U-shaped steel bar or a perforated steel plate when viewed from the side, so that the connecting bolt is securely surrounded by the surrounding portion, transmitting shear forces and bending moments and resisting these stresses.

特に、請求項3に係る発明によれば、鋼製治具が部分的に充填材の型枠を兼用できるので、型枠の設置作業を一部省略することができるため、さらに短時間での施工が可能となる。 In particular, according to the invention of claim 3, the steel jig can partially serve as a formwork for the filling material, so that the installation work for the formwork can be partially omitted, making it possible to complete construction in an even shorter time.

特に、請求項4に係る発明によれば、連結ボルト及びスタッドボルトは、充填材の内部に埋設されているので、スタッドボルトや鋼製治具に防錆処理やこれらの部材をステンレス材とする必要がなく、部材単価を下げて安価に施工することが可能となる。 In particular, according to the invention of claim 4, the connecting bolts and stud bolts are embedded inside the filler, so there is no need to apply anti-rust treatment to the stud bolts and steel jigs or to use stainless steel for these components, which reduces the unit price of the components and makes it possible to carry out the work inexpensively.

図1は、本発明の第1実施形態に係る鋼桁とプレキャスト床版との接合構造の構成を示す橋梁を橋軸直角方向に沿って切断した鉛直断面図である。FIG. 1 is a vertical cross-sectional view of a bridge cut perpendicular to the bridge axis, showing the configuration of a joint structure between a steel girder and a precast deck according to a first embodiment of the present invention. 図2は、同上の鋼桁とプレキャスト床版との接合構造を示す図1のA-A線断面図である。FIG. 2 is a cross-sectional view taken along line AA in FIG. 1, showing the joint structure between the steel girder and the precast deck. 図3は、同上の鋼桁とプレキャスト床版との接合構造を示す図1のB-B線断面図である。FIG. 3 is a cross-sectional view taken along line B-B in FIG. 1, showing the joint structure between the steel girder and the precast deck. 図4は、本発明の第2実施形態に係る鋼桁とプレキャスト床版との接合構造の構成を示す橋梁を橋軸直角方向に沿って切断した鉛直断面図である。FIG. 4 is a vertical cross-sectional view of a bridge cut along a direction perpendicular to the bridge axis, showing the configuration of a joint structure between a steel girder and a precast deck according to a second embodiment of the present invention. 図5は、本発明の第3実施形態に係る鋼桁とプレキャスト床版との接合構造を示す図であり、左半分が図1のA-A線断面図に相当する図であり、右半分が図1のB-B線断面図に相当する図である。FIG. 5 is a diagram showing a joint structure between a steel girder and a precast deck in accordance with a third embodiment of the present invention, in which the left half corresponds to the cross-sectional view along line A-A in FIG. 1, and the right half corresponds to the cross-sectional view along line B-B in FIG. 1.

以下、本発明に係る連続桁となる鋼桁とプレキャスト床版との接合構造の一実施形態について、図面を参照しながら詳細に説明する。 Below, we will explain in detail one embodiment of the joint structure between a steel girder that serves as a continuous girder and a precast deck slab according to the present invention, with reference to the drawings.

[第1実施形態]
図1~図3を用いて、本発明の第1実施形態に係る鋼桁とプレキャスト床版との接合構造について説明する。図1は、本発明の第1実施形態に係る鋼桁とプレキャスト床版との接合構造1の構成を示す橋梁を橋軸直角方向Yに沿って切断した鉛直断面図である。また、図2は、鋼桁とプレキャスト床版との接合構造1を示す図1のA-A線断面図であり、図3は、鋼桁とプレキャスト床版との接合構造1を示す図1のB-B線断面図である。なお、図中のXは、橋軸方向Xであり、図中のYは、橋軸直角方向Yであり、図中のZは、上下方向Zである。但し、図2,図3の充填材は、見易くするために省略している。
[First embodiment]
The joint structure between a steel girder and a precast deck according to the first embodiment of the present invention will be described with reference to Figures 1 to 3. Figure 1 is a vertical cross-sectional view of a bridge cut along the direction Y perpendicular to the bridge axis, showing the configuration of the joint structure 1 between a steel girder and a precast deck according to the first embodiment of the present invention. Figure 2 is a cross-sectional view of line A-A in Figure 1 showing the joint structure 1 between a steel girder and a precast deck, and Figure 3 is a cross-sectional view of line B-B in Figure 1 showing the joint structure 1 between a steel girder and a precast deck. Note that X in the figures is the bridge axis direction X, Y in the figures is the direction Y perpendicular to the bridge axis, and Z in the figures is the up-down direction Z. However, the filler material in Figures 2 and 3 is omitted for ease of viewing.

第1実施形態に係る鋼桁とプレキャスト床版との接合構造1(以下単に接合構造1ともいう。)は、鋼桁2と、この鋼桁2上に載置されたプレキャスト床版3と、を接合する鋼桁とプレキャスト床版との接合構造である。 The joint structure 1 between a steel girder and a precast deck in the first embodiment (hereinafter also simply referred to as joint structure 1) is a joint structure between a steel girder and a precast deck that joins a steel girder 2 and a precast deck 3 placed on the steel girder 2.

(鋼桁)
鋼桁2は、I形鋼からなり、上フランジ20と下フランジ21とこれらを繋ぐウェブ22とを備えている。
(steel girder)
The steel girder 2 is made of an I-beam and has an upper flange 20, a lower flange 21 and a web 22 connecting them.

(スタッドボルト)
また、この鋼桁2の上フランジ20の上面2aの両縁沿いには、スタッドボルト4が溶殖されている。このスタッドボルト4は、棒状の鋼材からなり、棒状の一端(上端)にねじ部40が形成されてナット41を螺合可能に構成され、他端(下端)の基端部42がアークスタッド溶接されるいわゆるねじ付きスタッドである。このスタッドボルト4を介して、上フランジ20の上面の両縁沿いに一対の鋼製治具5,5が取り付けられている。
(Stud bolt)
Stud bolts 4 are welded along both edges of the upper surface 2a of the upper flange 20 of the steel girder 2. The stud bolts 4 are made of rod-shaped steel material, and are so-called threaded studs, with a threaded portion 40 formed at one end (upper end) of the rod so that a nut 41 can be screwed onto them, and a base end 42 at the other end (lower end) being arc stud welded. A pair of steel jigs 5, 5 are attached along both edges of the upper surface of the upper flange 20 via the stud bolts 4.

(プレキャスト床版)
プレキャスト床版3は、予め工場等でコンクリートが打設されて製造された鉄筋コンクリート製の平面視矩形の版状のプレキャスト床版であり、異形棒鋼からなる側面視U字状のずれ止め鋼材30が下面3aから下方に向け突設されている。勿論、このずれ止め鋼材30は、下面3aから突出している部分が橋軸直角方向Yに沿って見た側面視U字状となっており、プレキャスト床版3のコンクリート内部に有効に定着されている。なお、ずれ止め鋼材30の側面視U字状の部分が、後述の連結ボルト6を取り囲む囲繞部となっている。
(Precast floor slab)
The precast deck 3 is a rectangular precast deck made of reinforced concrete that has been manufactured in advance by pouring concrete in a factory or the like, and has a U-shaped anti-slip steel member 30 made of deformed steel bars that protrudes downward from the bottom surface 3a. Of course, the part of the anti-slip steel member 30 that protrudes from the bottom surface 3a is U-shaped when viewed from the side when viewed along the direction Y perpendicular to the bridge axis, and is effectively fixed inside the concrete of the precast deck 3. The U-shaped part of the anti-slip steel member 30 when viewed from the side serves as a surrounding part that surrounds the connecting bolt 6 described below.

(鋼製治具)
鋼製治具5は、断面L字状の鋼材であり、鋼桁2の上フランジ20の上面2aに設置される底面部50と、この底面部50に直交して立ち上がると立上り部51と、を備えている。また、立上り部51には、連結ボルト6を挿通するボルト孔(図示せず)が穿設されている。そして、図1に示すように、本実施形態に係る接合構造1では、立上り部51が外側(橋軸である鋼桁2のウェブ22中心線から離れる側)となるように、即ち、一対の鋼製治具5,5のそれぞれの底面部50が互いに対向する内向きに、鋼桁2の上フランジ20の両縁に沿って取り付けられている。
(Steel jig)
The steel jig 5 is a steel material having an L-shaped cross section, and includes a bottom surface portion 50 that is installed on the upper surface 2a of the upper flange 20 of the steel girder 2, and a rising portion 51 that rises perpendicular to the bottom surface portion 50. The rising portion 51 is provided with a bolt hole (not shown) through which a connecting bolt 6 is inserted. As shown in FIG. 1, in the joint structure 1 according to this embodiment, the bottom surface portions 50 of the pair of steel jigs 5, 5 are attached along both edges of the upper flange 20 of the steel girder 2 so that the rising portion 51 is on the outer side (the side away from the center line of the web 22 of the steel girder 2, which is the bridge axis), that is, facing inward and facing each other.

(連結ボルト)
連結ボルト6は、図1に示すように、鋼材からなる全ねじボルトであり、両端にナット60が螺着され、一対の鋼製治具5のそれぞれのボルト孔にボルト接合されて止め付けられている。勿論、連結ボルト6は、全ねじボルトに限られず、一端にボルト頭があるボルトタイプや両端にねじ部が形成されたねじ付き棒鋼であっても構わない。但し、本実施形態に係る連結ボルト6は、ナット60やボルト端部が充填材から露出することになるため、防錆上、ステンレス製であることが好ましい。
(Connecting bolt)
1, the connecting bolt 6 is a fully threaded bolt made of steel, with nuts 60 screwed onto both ends, and is bolted and fixed into the respective bolt holes of the pair of steel jigs 5. Of course, the connecting bolt 6 is not limited to a fully threaded bolt, and may be a bolt type having a bolt head at one end or a threaded steel bar having threads formed at both ends. However, since the nuts 60 and bolt ends of the connecting bolt 6 according to this embodiment are exposed from the filler, it is preferable that the connecting bolt 6 be made of stainless steel from the viewpoint of rust prevention.

連結ボルト6は、底面部50が鋼桁2の上フランジ20の上面2aにスタッドボルト4で固定された一対の鋼製治具5の立上り部51の間にボルト接合されて設置されている。これにより、連結ボルト6が側面視U字状のずれ止め鋼材に挿通された上、後述の充填材7でこれらの隙間が充填されて固められることにより、鋼桁2とプレキャスト床版3とが有効に接合されることなる。 The connecting bolts 6 are bolted and installed between the rising parts 51 of a pair of steel jigs 5 whose bottom parts 50 are fixed by stud bolts 4 to the upper surface 2a of the upper flange 20 of the steel girder 2. As a result, the connecting bolts 6 are inserted into the U-shaped anti-slip steel material in side view, and the gaps are filled and solidified with the filler material 7 described below, effectively joining the steel girder 2 and the precast deck 3.

このため、接合構造1は、図1の矢印で示す橋軸直角方向Yに沿った曲げモーメントに対抗することができるとともに、図2,図3の矢印で示す橋軸方向Xに沿ったせん断力にも対抗することができる。 As a result, the joint structure 1 can withstand bending moments along the direction perpendicular to the bridge axis Y, as indicated by the arrows in Figure 1, and can also withstand shear forces along the bridge axis direction X, as indicated by the arrows in Figures 2 and 3.

(充填材)
また、図1に示すように、鋼桁2とプレキャスト床版3との上下の隙間の一対の鋼製治具5の間には、無収縮モルタルなどの経時硬化材からなる充填材7が充填されて、スタッドボルト4、鋼製治具5、連結ボルト6との各部材の隙間が埋められて固められている。
(filling material)
As shown in FIG. 1 , a filler 7 made of a time-hardening material such as non-shrink mortar is filled between a pair of steel jigs 5 in the upper and lower gaps between the steel girder 2 and the precast deck 3, filling and hardening the gaps between the stud bolts 4, the steel jigs 5, and the connecting bolts 6.

つまり、前述のように、鋼桁2の上フランジ20の上面2aにスタッドボルト4が溶殖されて、鋼製治具5が設置された後、図3に示す鋼製治具5と鋼製治具5との間に、図示しない木製や樹脂製などの仮設の型枠を設置して、充填材7を充填する。その後、鋼製治具5及びプレキャスト床版3のずれ止め鋼材30に連結ボルト6が挿通されて、鋼桁2とプレキャスト床版3とが有効に接合される。この充填材7は、各部材の隙間が埋めてプレキャスト床版3の荷重を均等に鋼桁2に伝達する機能を有している。 In other words, as described above, the stud bolts 4 are welded to the upper surface 2a of the upper flange 20 of the steel girder 2, the steel jig 5 is installed, and then a temporary wooden or plastic formwork (not shown) is installed between the steel jigs 5 shown in FIG. 3 and filled with the filler 7. After that, the connecting bolts 6 are inserted through the steel jig 5 and the anti-slip steel material 30 of the precast deck 3, effectively joining the steel girder 2 and the precast deck 3. This filler 7 has the function of filling the gaps between the various members and evenly transferring the load of the precast deck 3 to the steel girder 2.

以上説明した第1実施形態に係る接合構造1によれば、プレキャスト床版3に上下に貫通する貫通孔が無いため、プレキャスト床版3に構造上の弱点部を無くすことができるたけでなく、充填材7が硬化するまでの間もプレキャスト床版3上での作業が可能となり、結果的に短時間で施工が可能となる。また、接合構造1によれば、鋼桁2にも貫通孔を設ける必要がないため、鋼桁2の断面欠損を無くすことができ、構造上安全な構造とすることができる。 According to the joint structure 1 of the first embodiment described above, since there are no through holes that penetrate vertically through the precast deck 3, not only can structural weak points in the precast deck 3 be eliminated, but work can be done on the precast deck 3 even while the filling material 7 is hardening, resulting in construction being completed in a short time. In addition, since there is no need to provide through holes in the steel girders 2 according to the joint structure 1, cross-sectional defects in the steel girders 2 can be eliminated, resulting in a structurally safe structure.

その上、接合構造1によれば、連結ボルト6が側面視U字状のずれ止め鋼材30に挿通されることで、鋼桁2とプレキャスト床版3とが接合されているので、橋軸直角方向Yに沿ったせん断力だけでなく、図2,3の矢印で示す橋軸方向Xに沿ったせん断力にも図1の矢印で示す橋軸直角方向Yの曲げモーメントにも対抗することができ、耐震上強固な接合構造とすることができる。 Furthermore, according to the joint structure 1, the steel girder 2 and the precast deck 3 are joined by inserting the connecting bolt 6 into the U-shaped anti-slip steel material 30 that is shaped in a side view, so that it can withstand not only the shear force along the direction perpendicular to the bridge axis Y, but also the shear force along the bridge axis direction X as shown by the arrows in Figures 2 and 3, and the bending moment along the direction perpendicular to the bridge axis Y as shown by the arrow in Figure 1, resulting in a joint structure that is strong in terms of earthquake resistance.

それに加え、接合構造1によれば、鋼製治具5が部分的に充填材7の型枠を兼用できるので、型枠の設置作業を一部省略することができるため、さらに短時間での施工が可能となる。 In addition, with the joint structure 1, the steel jig 5 can partially serve as the formwork for the filling material 7, so some of the work of setting up the formwork can be omitted, making it possible to complete the construction in an even shorter time.

[第2実施形態]
次に、図4を用いて、本発明の第2実施形態に係る鋼桁とプレキャスト床版との接合構造1’について説明する。図4は、本発明の第2実施形態に係る鋼桁とプレキャスト床版との接合構造1’の構成を示す橋梁を橋軸直角方向Yに沿って切断した鉛直断面図である。
[Second embodiment]
Next, a joint structure 1' between a steel girder and a precast deck according to a second embodiment of the present invention will be described with reference to Fig. 4. Fig. 4 is a vertical cross-sectional view of a bridge cut along the direction perpendicular to the bridge axis Y, showing the configuration of the joint structure 1' between a steel girder and a precast deck according to the second embodiment of the present invention.

第2実施形態に係る鋼桁とプレキャスト床版との接合構造1’(以下単に接合構造1’ともいう。)が、前述の接合構造1と相違する点は、主に、一対の鋼製治具5,5の立上り部51が内側となるように取り付けられている点であり、同一構成は、同一符号を付し、詳細な説明を省略する。 The second embodiment of the joint structure 1' between a steel girder and a precast deck (hereinafter also referred to as joint structure 1') differs from the previously described joint structure 1 mainly in that the rising portions 51 of a pair of steel jigs 5, 5 are attached so as to face inward. The same components are given the same reference numerals and detailed descriptions are omitted.

(鋼製治具)
鋼製治具5は、前述の接合構造1と同一の断面L字状の鋼材であるが、図4に示すように、本実施形態に係る接合構造1では、立上り部51が内側(橋軸である鋼桁2のウェブ22中心線に近い側)となるように、即ち、一対の鋼製治具5,5のそれぞれの底面部50が互いに対向する外向きに、鋼桁2の上フランジ20の両縁に沿って取り付けられている。
(Steel jig)
The steel jig 5 is a steel material with the same L-shaped cross section as the previously described joint structure 1, but as shown in Figure 4, in the joint structure 1 according to this embodiment, the steel jig 5 is attached along both edges of the upper flange 20 of the steel girder 2 so that the rising portion 51 is on the inside (the side closer to the center line of the web 22 of the steel girder 2, which is the bridge axis), i.e., the bottom portions 50 of the pair of steel jigs 5, 5 are attached facing outward and opposite each other.

(連結ボルト)
連結ボルト6’は、図4に示すように、連結ボルト6と同様に鋼材からなる全ねじボルトであり、両端に前述のナット60が螺着され、一対の鋼製治具5のそれぞれのボルト孔にボルト接合されて止め付けられている。しかし、接合構造1’では、一対の鋼製治具5,5の取付向きが、前述の接合構造1と相違して、同一幅の鋼桁2の縁沿いに底面部50が互いに対向する外向きに取り付けられているため、立上り部51の間隔が接合構造1より短くなっている。このため、連結ボルト6’の長さは、連結ボルト6の長さより短くなっている。勿論、連結ボルト6’も、全ねじボルトに限られず、一端にボルト頭があるボルトタイプや両端にねじ部が形成されたねじ付き棒鋼であっても構わない。
(Connecting bolt)
As shown in Fig. 4, the connecting bolt 6' is a fully threaded bolt made of steel like the connecting bolt 6, and has the aforementioned nuts 60 screwed to both ends and is bolted to the respective bolt holes of the pair of steel jigs 5. However, in the joint structure 1', the mounting orientation of the pair of steel jigs 5, 5 is different from that of the above-mentioned joint structure 1, and the bottom surface parts 50 are mounted facing outward along the edge of the steel girder 2 of the same width, so that the distance between the rising parts 51 is shorter than that of the joint structure 1. For this reason, the length of the connecting bolt 6' is shorter than that of the connecting bolt 6. Of course, the connecting bolt 6' is not limited to a fully threaded bolt, and may be a bolt type having a bolt head at one end or a threaded steel bar having threads formed at both ends.

一方、本実施形態に係る連結ボルト6’は、ナット60やボルト端部が充填材7から露出されておらず、充填材7の内部に埋設されている。このため、連結ボルト6’は、防錆上ステンレス製とする必要性は低くなっている。 On the other hand, in the connecting bolt 6' according to this embodiment, the nut 60 and the bolt end are not exposed from the filler 7, but are embedded inside the filler 7. Therefore, there is less need for the connecting bolt 6' to be made of stainless steel for rust prevention purposes.

(充填材)
接合構造1’の充填材7も、接合構造1と同様に、無収縮モルタルなどの経時硬化材からなる充填材である。但し、接合構造1’では、鋼製治具5の取付向きが底面部50が互いに対向する外向きに取り付けられているため、通常通り、型枠設置して充填材7を充填する必要がある。
(filling material)
The filler 7 of the joint structure 1' is also a filler made of a time-hardening material such as non-shrink mortar, similar to the joint structure 1. However, in the joint structure 1', the steel jigs 5 are attached so that the bottom parts 50 face outward, so that it is necessary to install a formwork and fill the filler 7 as usual.

以上説明した第2実施形態に係る鋼桁とプレキャスト床版との接合構造1’によれば、前記作用効果に加え、連結ボルト6’及びスタッドボルト4は、充填材7の内部に埋設されているので、スタッドボルト4や鋼製治具5に防錆処理やこれらの部材をステンレス材とする必要がなく、部材単価を下げて安価に施工することが可能となる。 In addition to the above-described effects, the joint structure 1' between the steel girder and the precast deck according to the second embodiment has the following advantages: the connecting bolts 6' and the stud bolts 4 are embedded inside the filling material 7, so there is no need to apply rust-proofing treatment to the stud bolts 4 and the steel jigs 5 or to use stainless steel for these components, which reduces the unit price of the components and makes it possible to carry out construction at low cost.

[第3実施形態]
次に、図5を用いて、本発明の第3実施形態に係る鋼桁とプレキャスト床版との接合構造1”について説明する。図5は、本発明の第3実施形態に係る鋼桁とプレキャスト床版との接合構造1”を示す図であり、左半分が図1のA-A線断面図に相当する図であり、右半分が図1のB-B線断面図に相当する図である。なお、符号が重なるため一点鎖線の円内にずれ止め鋼材のみを示している。
[Third embodiment]
Next, using Figure 5, we will explain the joint structure 1" between a steel girder and a precast deck in accordance with the third embodiment of the present invention. Figure 5 is a diagram showing the joint structure 1" between a steel girder and a precast deck in accordance with the third embodiment of the present invention, where the left half corresponds to the cross-sectional view along line A-A in Figure 1, and the right half corresponds to the cross-sectional view along line B-B in Figure 1. Note that since the symbols overlap, only the shear-stop steel material is shown within the dotted circle.

第3実施形態に係る鋼桁とプレキャスト床版との接合構造1”(以下単に接合構造1”ともいう。)が、前述の接合構造1と相違する点は、主にずれ止め鋼材の形状が異なる点であり、同一構成は、同一符号を付し、詳細な説明を省略する。 The third embodiment of the joint structure 1" between a steel girder and a precast deck (hereinafter also referred to as joint structure 1") differs from the previously described joint structure 1 mainly in the shape of the anti-slip steel material. The same components are given the same reference numerals and detailed descriptions are omitted.

本実施形態に係る接合構造1”のずれ止め鋼材30”は、図5に示すように、プレキャスト床版3の下面3aから突設された矩形の穴開き鋼板であり、前述の鋼製治具5に対応する。このずれ止め鋼材30”は、左右一対の側辺部30a”と、下辺部30b”及び上辺部30c”とを備えた連結ボルト6の左右及び上下の四方を囲む囲繞部を有する構成となっており、連結ボルト6を囲むことでせん断力及び曲げモーメントを伝達し、これらの応力に対抗する機能を有している。 As shown in FIG. 5, the anti-slip steel material 30" of the joint structure 1" according to this embodiment is a rectangular perforated steel plate protruding from the underside 3a of the precast deck 3, and corresponds to the steel jig 5 described above. This anti-slip steel material 30" has a pair of left and right side portions 30a" and a bottom portion 30b" and top portion 30c" and is configured with surrounding portions that surround the connecting bolt 6 on all four sides, left and right and above and below. By surrounding the connecting bolt 6, it transmits shear forces and bending moments and has the function of resisting these stresses.

但し、本発明に係るずれ止め鋼材は、連結ボルト6の周囲を少なくとも左右及び下方の三方を囲む囲繞部を有していればよい。つまり、図5に示す上辺部30c”が、プレキャスト床版3の下面3aから突出しておらず、破線で示すずれ止め鋼材30”の埋設部30d”と一体になっていてもよい。周囲の充填材7を介してプレキャスト床版3の下面3aに当接するため、上辺部30c”が無くても応力を連結ボルト6及び鋼製治具を介して鋼桁2に伝達できるからである。 However, the anti-slip steel material according to the present invention only needs to have a surrounding portion that surrounds the connecting bolt 6 on at least three sides, the left, right, and bottom. In other words, the upper edge portion 30c" shown in FIG. 5 does not need to protrude from the underside 3a of the precast deck 3, and may be integrated with the embedded portion 30d" of the anti-slip steel material 30" shown by the dashed line. This is because the upper edge portion 30c" abuts against the underside 3a of the precast deck 3 via the surrounding filler material 7, and therefore stress can be transmitted to the steel girder 2 via the connecting bolt 6 and the steel jig even without the upper edge portion 30c".

また、第3実施形態に係る接合構造1”のずれ止め鋼材30”として、矩形の穴が形成された鋼板を例示して説明したが、本発明に係るずれ止め鋼材は、円形の穴が形成されて鋼板であっても構わない。要するに、本発明に係るずれ止め鋼材は、引張力等を伝達可能なように鋼板又は鋼材により、連結ボルト6の周囲を少なくとも左右及び下方の三方を囲む囲繞部を有していればよい。 Although a steel plate with a rectangular hole has been described as the anti-slip steel material 30" of the joint structure 1" according to the third embodiment, the anti-slip steel material according to the present invention may be a steel plate with a circular hole. In short, the anti-slip steel material according to the present invention may have a surrounding portion that surrounds the connecting bolt 6 on at least three sides (left, right, and bottom) using a steel plate or material so that tensile force, etc. can be transmitted.

第3実施形態に係る接合構造1”によれば、接合構造1と同様に、前記作用効果を奏するとともに、連結ボルト6がずれ止め鋼材30”の左右一対の側辺部30a”と、下辺部30b”及び上辺部30c”とからなる囲繞部に挿通されることで、鋼桁2とプレキャスト床版3とが接合されている。このため、接合構造1”は、橋軸直角方向Yに沿ったせん断力だけでなく、図5の矢印で示す橋軸方向Xに沿ったせん断力にも図1の矢印で示す橋軸直角方向Yの曲げモーメントにも対抗することができ、耐震上強固な構造とすることができる。 The joint structure 1" according to the third embodiment has the same effect as the joint structure 1, and the steel girder 2 and the precast deck 3 are joined by inserting the connecting bolt 6 into the surrounding portion consisting of a pair of left and right side edges 30a" and a lower edge 30b" and an upper edge 30c" of the anti-slip steel material 30". Therefore, the joint structure 1" can withstand not only the shear force along the direction perpendicular to the bridge axis Y, but also the shear force along the bridge axis direction X shown by the arrow in Figure 5 and the bending moment along the direction perpendicular to the bridge axis Y shown by the arrow in Figure 1, making it a strong earthquake-resistant structure.

以上、本発明の実施形態に係る鋼桁とプレキャスト床版との接合構造1~1”について詳細に説明したが、前述した又は図示した実施形態は、いずれも本発明を実施するにあたって具体化した一実施形態を示したものに過ぎない。よって、これらによって本発明の技術的範囲が限定的に解釈されてはならないものである。 The above provides a detailed explanation of the joint structure 1-1" between a steel girder and a precast deck according to an embodiment of the present invention. However, the above-mentioned and illustrated embodiments are merely examples of embodiments that are embodied in the practice of the present invention. Therefore, the technical scope of the present invention should not be interpreted in a limiting manner based on these.

1,1’:鋼桁とプレキャスト床版との接合構造
2:鋼桁
2a:上面
20:上フランジ
21:下フランジ
22:ウェブ
3:プレキャスト床版
3a:下面
30,30”:ずれ止め鋼材
30a”:側辺部
30b”:下辺部
30c”:上辺部
30d”:埋設部
4:スタッドボルト
40:ねじ部
41:ナット
42:基端部
5:鋼製治具
51:底面部
52:立上り部
6,6:連結ボルト
60:ナット
7:充填材
1, 1': Joint structure between steel girder and precast deck 2: Steel girder 2a: Top surface 20: Top flange 21: Bottom flange 22: Web 3: Precast deck 3a: Bottom surface 30, 30": Anti-slip steel material 30a": Side edge portion 30b": Bottom edge portion 30c": Top edge portion 30d": Embedded portion 4: Stud bolt 40: Threaded portion 41: Nut 42: Base end portion 5: Steel jig 51: Bottom surface portion 52: Rising portion 6, 6: Connecting bolt 60: Nut 7: Filler

Claims (4)

鋼桁と、この鋼桁上に載置されたプレキャスト床版と、を接合する鋼桁とプレキャスト床版との接合構造であって、
前記鋼桁の上フランジの上面の両縁には、この上フランジに溶殖されたスタッドボルトで底面部と立上り部とを有する断面L字状の一対の鋼製治具が取り付けられ、
前記プレキャスト床版の下面には、少なくとも左右及び下方の三方を囲む囲繞部を有するずれ止め鋼材が突設され、
前記一対の鋼製治具の間には、連結ボルトが挿通されて前記立上り部に止め付けられ、
前記連結ボルトが前記ずれ止め鋼材の前記囲繞部に挿通されることで、前記鋼桁と前記プレキャスト床版とが接合されていること
を特徴とする鋼桁とプレキャスト床版との接合構造。
A joint structure between a steel girder and a precast deck placed on the steel girder,
A pair of steel jigs having an L-shaped cross section and a bottom portion and a rising portion are attached to both edges of the upper surface of the upper flange of the steel girder by stud bolts fused to the upper flange,
A shear-stop steel member having a surrounding portion surrounding at least the left, right, and bottom three sides is protruded from the underside of the precast floor slab,
A connecting bolt is inserted between the pair of steel jigs and fastened to the rising portion,
A joint structure between a steel girder and a precast deck, characterized in that the steel girder and the precast deck are joined by inserting the connecting bolt into the surrounding portion of the anti-slip steel material.
前記囲繞部は、側面視U字状の棒鋼又は穴開き鋼板からなること
を特徴とする請求項1に記載の鋼桁とプレキャスト床版との接合構造。
The joint structure between a steel girder and a precast deck according to claim 1, characterized in that the surrounding portion is made of a U-shaped steel bar or a perforated steel plate when viewed from the side.
前記一対の鋼製治具は、前記立上り部が外側となるように前記鋼桁の前記上フランジの両縁に取り付けられ、
前記一対の鋼製治具の間には、充填材が充填されていること
を特徴とする請求項1又は2に記載の鋼桁とプレキャスト床版との接合構造。
The pair of steel jigs are attached to both edges of the upper flange of the steel girder so that the rising portion is on the outside,
3. The joint structure between a steel girder and a precast deck according to claim 1 or 2, characterized in that a filler is filled between the pair of steel jigs.
前記一対の鋼製治具は、前記立上り部が内側となるように前記鋼桁の前記上フランジの両縁に取り付けられ、
前記連結ボルト及び前記スタッドボルトは、充填材の内部に埋設されていること
を特徴とする請求項1又は2に記載の鋼桁とプレキャスト床版との接合構造。
The pair of steel jigs are attached to both edges of the upper flange of the steel girder so that the rising portion is on the inside,
3. The joint structure between a steel girder and a precast deck according to claim 1 or 2, wherein the connecting bolts and the stud bolts are embedded inside a filler material.
JP2021192410A 2021-11-26 2021-11-26 Joint structure between steel girder and precast deck Active JP7692807B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2021192410A JP7692807B2 (en) 2021-11-26 2021-11-26 Joint structure between steel girder and precast deck

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2021192410A JP7692807B2 (en) 2021-11-26 2021-11-26 Joint structure between steel girder and precast deck

Publications (2)

Publication Number Publication Date
JP2023079021A JP2023079021A (en) 2023-06-07
JP7692807B2 true JP7692807B2 (en) 2025-06-16

Family

ID=86646140

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2021192410A Active JP7692807B2 (en) 2021-11-26 2021-11-26 Joint structure between steel girder and precast deck

Country Status (1)

Country Link
JP (1) JP7692807B2 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013185398A (en) 2012-03-09 2013-09-19 Yokogawa Sumikin Bridge Corp Floor slab structure using sandwich type composite floor slab panel
JP2021001457A (en) 2019-06-20 2021-01-07 鹿島建設株式会社 Joint structure and joining method

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2941632B2 (en) * 1994-01-28 1999-08-25 三菱重工業株式会社 Joint structure between floor slab and steel girder in precast concrete slab composite girder bridge
US6857156B1 (en) * 2000-04-05 2005-02-22 Stanley J. Grossman Modular bridge structure construction and repair system

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013185398A (en) 2012-03-09 2013-09-19 Yokogawa Sumikin Bridge Corp Floor slab structure using sandwich type composite floor slab panel
JP2021001457A (en) 2019-06-20 2021-01-07 鹿島建設株式会社 Joint structure and joining method

Also Published As

Publication number Publication date
JP2023079021A (en) 2023-06-07

Similar Documents

Publication Publication Date Title
JP7430155B2 (en) Method for constructing a connection structure between precast structural members and time-cured materials
KR100609184B1 (en) Precast Concrete Beam-Column Connection Structure
JP2017101442A (en) Joining structure and joining method
JP5508070B2 (en) Joining structure and joining method of steel member and concrete member
JP7692807B2 (en) Joint structure between steel girder and precast deck
KR102349866B1 (en) Connecting hardware for dry method and a structure for joining a pc girder to a pc column using the connecting hardware and construction method of the joining structure
JPH10331436A (en) Seismic retrofitting of columns and beams in existing structures
KR20210005806A (en) Joining method of steel members using double anchor plate with wedge-shaped concave-convex section in the construction of steel structure or steel-reinforced concrete composite structure
JP2750556B2 (en) Manufacturing method of prestressed concrete girder
KR200201561Y1 (en) Head reinforcement structure of steel pipe pile
JP2001295478A (en) Connecting method for src constructed existing skeleton and repairing member
KR100622935B1 (en) Horizontal extension joint structure and joining method using the same
JP3771177B2 (en) Joining structure of reinforced concrete column and steel column, and joining method thereof
JP5255543B2 (en) Mixed girder joint structure
JP2009280958A (en) Steel plate concrete structure and construction method for steel plate concrete structure
JP4233105B2 (en) Seismic reinforcement method for existing pillars
JP5282721B2 (en) Rigid floor structure and method
JP2001107373A (en) Joint structure of steel column base with foundation concrete
JP2000017731A (en) Joint structure between concrete member and steel pipe member
JP7034229B2 (en) How to build a connected structure of precast structural member and cast-in-place cured material of repaired part of cross-section repair
JP7385064B2 (en) Precast concrete plate fittings
KR200362688Y1 (en) Anchor structure for pier
JP7849188B2 (en) Strut connection structure
JP2004092248A (en) Joint metal of anchor bar, joint structure using the same and joining method used for the same
JP5525884B2 (en) Reinforcement joint structure and method for constructing the joint structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20240904

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20250415

TRDD Decision of grant or rejection written
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20250528

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20250603

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20250604

R150 Certificate of patent or registration of utility model

Ref document number: 7692807

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150