JP7712066B2 - How to build an underground structure - Google Patents
How to build an underground structureInfo
- Publication number
- JP7712066B2 JP7712066B2 JP2020115176A JP2020115176A JP7712066B2 JP 7712066 B2 JP7712066 B2 JP 7712066B2 JP 2020115176 A JP2020115176 A JP 2020115176A JP 2020115176 A JP2020115176 A JP 2020115176A JP 7712066 B2 JP7712066 B2 JP 7712066B2
- Authority
- JP
- Japan
- Prior art keywords
- side walls
- constructing
- underground structure
- walls
- formwork
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Description
本発明は、地下構造物の構築方法およびこれに用いる支保工構造に関する。 The present invention relates to a method for constructing underground structures and a support structure used therefor.
道路等の下方の地盤に地下構造物を構築する方法として、地表から地盤を掘削し、その掘削部に地下構造物を構築する開削工法がある。開削工法では、地盤の掘削予定箇所の両側で土留め壁を設置し、土留め壁の間で地盤の掘削を行う。この際、土留め壁の間に切梁を設けることにより、土留め壁に作用する地盤の側圧を切梁により支持させる。 One method for constructing underground structures in the ground beneath roads and other structures is the open cut method, in which the ground is excavated from the surface and an underground structure is constructed in the excavated portion. With the open cut method, retaining walls are installed on both sides of the planned excavation point in the ground, and the ground is excavated between the retaining walls. At this time, struts are installed between the retaining walls so that the lateral pressure of the ground acting on the retaining walls can be supported by the struts.
この状態で、地下構造物の底版や側壁が掘削部で下から順に構築される。切梁は地下構造物の構築に伴って撤去されるが、地盤の側圧が問題となる場合には、構築済みの側壁の間に盛替え梁を設置し、土留め壁等を介して側壁に作用する地盤の側圧を、盛替え梁により支持させる(例えば、特許文献1参照)。 In this state, the base plate and side walls of the underground structure are constructed in the excavation section from the bottom up. The struts are removed as the underground structure is constructed, but if lateral pressure from the ground becomes a problem, replacement beams are installed between the already constructed side walls, and the lateral pressure from the ground acting on the side walls via retaining walls, etc. is supported by the replacement beams (see, for example, Patent Document 1).
盛替え梁を用いる場合には、地下構造物の側壁に仮設のアンカーを打ち込んでブラケットを取り付け、ブラケット上に腹起しを設置し、盛替え梁の先端を腹起しに固定する。しかし、このような作業には手間がかかる。また側壁にアンカーを打ち込むための孔を形成すると、地下構造物の品質と美観を損なうという問題もある。 When using replacement beams, temporary anchors are driven into the side wall of the underground structure, a bracket is attached, a wale is placed on the bracket, and the tip of the replacement beam is fixed to the wale. However, this type of work is time-consuming. In addition, forming holes in the side wall to drive anchors into can cause problems such as a loss of quality and aesthetics of the underground structure.
本発明は上記の問題に鑑みてなされたものであり、その目的は、地下構造物を容易に構築できる地下構造物の構築方法等を提供することである。 The present invention was made in consideration of the above problems, and its purpose is to provide a method for constructing an underground structure that allows for easy construction of an underground structure.
前述した目的を達成するための本発明は、地盤の掘削予定箇所の両側に一対の土留め壁を構築して一対の前記土留め壁の間の地盤を掘削し、前記土留め壁に作用する地盤の側圧を一対の前記土留め壁の間に架け渡した切梁によって支持させる工程(a)と、前記切梁を撤去し、一対の前記土留め壁の間の掘削部に、トンネルである地下構造物の躯体本体の両側の側壁を、一対の前記土留め壁に沿った位置で、高さ方向に下から上へと順に前記躯体本体の底版上に構築する工程(b)と、両側の前記側壁の間で、前記側壁の上方の部分である地下構造物の躯体本体の頂版の高さまで設けられた、鉛直材の高さ方向の途中に水平材を接続した構成を有する型枠支保工で頂版構築時の型枠を支持し、当該型枠を用いてコンクリートにより頂版を構築する工程(c)と、を有し、前記工程(b)において、両側の前記側壁の間で、前記型枠支保工の前記水平材の上に、水平方向の仮設梁を鉛直面において両側の前記側壁を結ぶ方向に載置して、前記仮設梁を前記型枠支保工により鉛直方向に支持し、前記仮設梁の一方の前記側壁側の先端に、前記側壁の延伸方向に延びる当接部材を固定した後、前記仮設梁の長手方向の途中に設けた伸縮部材を伸長させることで、前記当接部材を一方の前記側壁の構築済みの部分の頭部に当接させ、他方の前記側壁の構築済みの部分または両側の前記側壁の間に構築される隔壁の構築済みの部分に反力を取って前記仮設梁に軸力を導入し、一方の前記側壁の構築済みの部分に前記土留め壁を介して作用する地盤の側圧を前記仮設梁により支持し、前記型枠支保工を用いて前記頂版の構築を行った後、前記型枠支保工を、前記トンネルの次の施工区間へと、前記底版上で前記トンネルの延伸方向に移動させ、当該施工区間の前記側壁に作用する地盤の側圧を前記仮設梁により支持することを特徴とする地下構造物の構築方法である。 In order to achieve the above-mentioned object, the present invention includes a step (a) of constructing a pair of earth retaining walls on both sides of a planned excavation location of the ground, excavating the ground between the pair of earth retaining walls, and supporting the lateral pressure of the ground acting on the earth retaining walls by a strut spanning between the pair of earth retaining walls; a step (b) of removing the struts and constructing side walls on both sides of a main body of a skeleton of an underground structure, which is a tunnel , on the bottom slab of the main body of the skeleton in order from bottom to top in the height direction at positions along the pair of earth retaining walls in the excavation portion between the pair of earth retaining walls; and a step (c) of supporting a formwork for constructing the top slab with a formwork support having a configuration in which a horizontal member is connected midway in the height direction of a vertical member, the formwork being provided between the side walls on both sides up to the height of the top slab of the main body of the skeleton of the underground structure, which is the upper part of the side walls, and constructing the top slab with concrete using the formwork, and in the step (b), a horizontal temporary beam is provided on the horizontal member of the formwork support between the side walls on both sides. a contact member extending in the extension direction of the side walls is fixed to a tip end of one of the side walls of the temporary beam, and an expansion member provided midway in the longitudinal direction of the temporary beam is extended to bring the contact member into contact with a head of a constructed portion of one of the side walls, and an axial force is introduced into the temporary beam by taking a reaction force against the constructed portion of the other side wall or a constructed portion of a partition wall constructed between the side walls on both sides, the lateral pressure of the ground acting on the constructed portion of one of the side walls via the retaining wall is supported by the temporary beam , the top slab is constructed using the formwork shoring, and then the formwork shoring is moved on the bottom slab in the extension direction of the tunnel to a next construction section of the tunnel, and the lateral pressure of the ground acting on the side walls of the construction section is supported by the temporary beam .
本発明では、地下構造物の側壁の延伸方向に延びる当接部材を先端に取付けた仮設梁により、地下構造物の側壁に作用する地盤の側圧を支持する。仮設梁は型枠支保工に載置され、当接部材は仮設梁の先端に固定されるので、側壁にブラケット等を取付けることなく仮設梁と当接部材を設置することができ、地下構造物の構築が容易になり、品質や美観を損なうこともない。 In this invention, the lateral pressure of the ground acting on the side walls of the underground structure is supported by a temporary beam with an abutment member attached to its tip, which extends in the extension direction of the side walls of the underground structure. The temporary beam is placed on the formwork support and the abutment member is fixed to the tip of the temporary beam, so that the temporary beam and the abutment member can be installed without attaching a bracket or the like to the side walls, making it easier to build the underground structure and without compromising the quality or aesthetics.
前記仮設梁は、長手方向に分割可能であることが望ましい。
これにより、仮設梁を分割した各部分を型枠支保工に格納し、仮設梁を型枠支保工上で容易に解体し、組立てることができる。
It is desirable that the temporary beam be separable in the longitudinal direction.
This allows each divided part of the temporary beam to be stored in the formwork support, and the temporary beam can be easily dismantled and reassembled on the formwork support.
前記仮設梁は、前記側壁の延伸方向に間隔を空けて複数設けられ、前記当接部材は、前記仮設梁ごとに設けられることが望ましい。
当接部材は、仮設梁ごとに設ける短尺のものとすることで、仮設梁格納時に型枠支保工に過大な偏荷重がかからず、型枠支保工の転倒が防止される。
It is desirable that a plurality of the temporary beams are provided at intervals in the extension direction of the side wall, and the abutment member is provided for each of the temporary beams.
By using short abutment members for each temporary beam, excessive unbalanced load is not placed on the formwork support when the temporary beams are stored, preventing the formwork support from collapsing.
本発明では、前記型枠支保工を用いて前記頂版の構築を行った後、前記型枠支保工を前記地下構造物の次の施工区間に移動させ、当該施工区間の前記側壁に作用する地盤の側圧を前記仮設梁により支持することにより、仮設梁と当接部材、および型枠支保工を一括して次の施工区間に移動させ、転用することができる。 In the present invention, after the top plate is constructed using the formwork support, the formwork support is moved to the next construction section of the underground structure and the lateral pressure of the ground acting on the side walls of that construction section is supported by the temporary beams, so that the temporary beams, abutment members and formwork support can be moved together to the next construction section and reused.
本発明によれば、地下構造物を容易に構築できる地下構造物の構築方法等を提供することができる。 The present invention provides a method for constructing an underground structure that allows for easy construction of an underground structure.
以下、図面に基づいて本発明の好適な実施形態について詳細に説明する。 The following describes in detail a preferred embodiment of the present invention with reference to the drawings.
本実施形態では、道路等の下方の地盤を開削し、地下構造物としてコンクリートによるトンネルを構築する例について説明する。ここではまず図1(a)に示すように、地盤1の掘削予定箇所の両側に一対の土留め壁2を構築し、土留め壁2の間の地盤1に中間杭3を打設する。土留め壁2は例えばソイルセメント壁体であるが、これに限らず既知の種々の壁体を用いることができる。 In this embodiment, an example will be described in which the ground beneath a road or the like is excavated, and a concrete tunnel is constructed as an underground structure. First, as shown in FIG. 1(a), a pair of retaining walls 2 are constructed on both sides of the planned excavation location of the ground 1, and intermediate piles 3 are driven into the ground 1 between the retaining walls 2. The retaining walls 2 are, for example, soil cement walls, but are not limited to this and various known wall structures can be used.
また、土留め壁2の間の地盤1を浅く掘削し、両土留め壁2の内側に上段の腹起し4を設置する。腹起し4には例えばH形鋼等の鋼材が用いられる。腹起し4は土留め壁2の内側に固定したブラケット21上に設置され、土留め壁2の延伸方向(図1(a)の紙面法線方向に対応する)に沿って配置される。 The ground 1 between the retaining walls 2 is shallowly excavated, and the upper wales 4 are installed inside both retaining walls 2. Steel materials such as H-shaped steel are used for the wales 4. The wales 4 are installed on brackets 21 fixed to the inside of the retaining walls 2, and are positioned along the extension direction of the retaining walls 2 (corresponding to the direction normal to the paper surface in Figure 1(a)).
さらに、両土留め壁2の頂部の間には受桁6が架け渡され、受桁6上に覆工板7が設置される。覆工板7は、掘削部15上の交通を確保するために設けられる。 Furthermore, a support girder 6 is placed between the tops of both retaining walls 2, and a lining plate 7 is installed on the support girder 6. The lining plate 7 is provided to ensure access over the excavation section 15.
本実施形態では受桁6の下面に反力受け部材17が固定されており、反力受け部材17と腹起し4がジャッキ18を介して連結される。これにより、土留め壁2に作用する地盤1の側圧を反力受け部材17を介して受桁6に伝達でき、受桁6が当該側圧を支持する上段の切梁として機能する。受桁6には例えばH形鋼等の鋼材が用いられる。 In this embodiment, a reaction force receiving member 17 is fixed to the underside of the support girder 6, and the reaction force receiving member 17 and the rib 4 are connected via a jack 18. This allows the lateral pressure of the ground 1 acting on the retaining wall 2 to be transmitted to the support girder 6 via the reaction force receiving member 17, and the support girder 6 functions as an upper strut that supports the lateral pressure. For example, steel such as H-shaped steel is used for the support girder 6.
その後、図1(b)に示すように、土留め壁2の間の地盤1の掘削を進め、両土留め壁2の内側で下段の腹起し4を前記と同様に設ける。そして、下段の腹起し4の間に切梁5を設置する。切梁5には例えばH形鋼等の鋼材が用いられる。 After that, as shown in FIG. 1(b), excavation of the ground 1 between the retaining walls 2 is continued, and the lower wale 4 is installed inside both retaining walls 2 in the same manner as described above. Then, struts 5 are installed between the lower wale 4. For the struts 5, steel materials such as H-shaped steel are used.
次に、両土留め壁2の間の掘削部15の底面に、図2(a)に示すようにトンネルの底版8を構築する。底版8のコンクリートが十分に硬化した後、下段の腹起し4、切梁5等を撤去する。 Next, the tunnel base slab 8 is constructed on the bottom of the excavation 15 between the two retaining walls 2, as shown in Figure 2(a). After the concrete of the base slab 8 has sufficiently hardened, the lower wale 4, strut 5, etc. are removed.
その後、図2(b)に示すように、底版8の両側の両土留め壁2に沿った位置で、トンネルの側壁9を底版8上に構築する。また両側壁9の間で、底版8上にトンネルの隔壁10を構築する。 Then, as shown in FIG. 2(b), the tunnel side walls 9 are constructed on the bottom slab 8 at positions along the two retaining walls 2 on both sides of the bottom slab 8. In addition, the tunnel bulkheads 10 are constructed on the bottom slab 8 between the two side walls 9.
本実施形態では、これらの壁体の上方の部分であるトンネルの頂版を構築するため、図3(a)に示すように掘削部15の底版8上に型枠支保工11を組み立てる。型枠支保工11は、頂版構築時の型枠(不図示)を支持するためのものであり、各側壁9と隔壁10の間で、中間杭3の位置を避けてその両側に分割して設けられる。 In this embodiment, to construct the top slab of the tunnel, which is the upper part of these walls, formwork supports 11 are assembled on the bottom slab 8 of the excavation section 15 as shown in FIG. 3(a). The formwork supports 11 are for supporting the formwork (not shown) when constructing the top slab, and are installed separately on both sides between each side wall 9 and the bulkhead 10, avoiding the position of the intermediate piles 3.
また、中間杭3の両側の型枠支保工11、11に跨って配置されるように、各側壁9と隔壁10の間でトンネル幅方向(図3(a)の左右方向に対応する)の盛替え梁12(仮設梁)を組み立てる。 In addition, replacement beams 12 (temporary beams) are assembled in the tunnel width direction (corresponding to the left and right direction in Figure 3(a)) between each side wall 9 and the partition wall 10 so that they are positioned across the formwork supports 11, 11 on both sides of the intermediate pile 3.
盛替え梁12にはH形鋼等の鋼材が用いられ、その長手方向は分割部121にて分割可能である。盛替え梁12は分割部121で分割した各部分を連結して構成され、盛替え梁12の長手方向の途中にはジャッキ122が設けられる。ジャッキ122は盛替え梁12の長手方向に伸縮する伸縮部材である。盛替え梁12は、分割部121で分割した状態で型枠支保工11内に搬入され、型枠支保工11上で組み立てられる。 The replacement beam 12 is made of steel material such as H-shaped steel, and can be divided in the longitudinal direction at the dividing section 121. The replacement beam 12 is constructed by connecting each part divided at the dividing section 121, and a jack 122 is provided midway along the longitudinal direction of the replacement beam 12. The jack 122 is an expandable member that expands and contracts in the longitudinal direction of the replacement beam 12. The replacement beam 12 is transported into the formwork support 11 in a state divided at the dividing section 121, and assembled on the formwork support 11.
本実施形態では、図3(b)に示すように、盛替え梁12の両端に、側壁9と隔壁10に当接させる当接部材13を固定する。 In this embodiment, as shown in FIG. 3(b), abutment members 13 that abut against the side walls 9 and the partition walls 10 are fixed to both ends of the replacement beam 12.
側壁9と隔壁10のコンクリートが十分に硬化したら、ジャッキ122を伸長させ、両端の当接部材13を側壁9と隔壁10にそれぞれ当接させて盛替え梁12に軸力を導入する。 When the concrete in the side walls 9 and bulkheads 10 has sufficiently hardened, the jacks 122 are extended, and the abutment members 13 at both ends are brought into contact with the side walls 9 and bulkheads 10, respectively, to introduce axial force into the replacement beams 12.
図4は、図3(b)の線A-Aによる水平断面を示す図である。図4に示すように、当接部材13は側壁9の延伸方向(図4の上下方向に対応する)に延びる短尺の部材であり、例えばH形鋼等の鋼材が用いられる。盛替え梁12は、側壁9の延伸方向に間隔を空けて複数設けられ、各盛替え梁12の先端に、当接部材13の中央部が固定される。 Figure 4 is a diagram showing a horizontal cross section along line A-A in Figure 3(b). As shown in Figure 4, the abutment member 13 is a short member extending in the extension direction of the side wall 9 (corresponding to the up-down direction in Figure 4), and is made of steel such as an H-shaped steel. A plurality of replacement beams 12 are provided at intervals in the extension direction of the side wall 9, and the center of the abutment member 13 is fixed to the tip of each replacement beam 12.
これにより、I字状の盛替え梁12と当接部材13を型枠支保工11に載置した支保工構造が形成される。地盤1の側圧は土留め壁2を介して側壁9に作用し、盛替え梁12はこの側圧を支持する切梁として機能する。盛替え梁12は型枠支保工11に載置され、盛替え梁12の自重は型枠支保工11によって支持される。 This forms a support structure in which the I-shaped replacement beam 12 and the abutment member 13 are placed on the formwork support 11. The lateral pressure of the ground 1 acts on the side wall 9 via the retaining wall 2, and the replacement beam 12 functions as a strut that supports this lateral pressure. The replacement beam 12 is placed on the formwork support 11, and the weight of the replacement beam 12 is supported by the formwork support 11.
その後、覆工板7と受桁6、および上段の腹起し4とジャッキ18等を撤去し、盛替え梁12により地盤1の側圧を支持しつつ、図5(a)に示すように型枠支保工11を用いてトンネルの頂版14を構築する。 Then, the lining plate 7, the support beam 6, the upper wale 4, the jacks 18, etc. are removed, and the top slab 14 of the tunnel is constructed using the formwork support 11 as shown in Figure 5 (a) while the lateral pressure of the ground 1 is supported by the replacement beam 12.
頂版14のコンクリートが十分に硬化した後、ジャッキ122を収縮させて盛替え梁12の軸力を解除する。また、盛替え梁12を分割部121の位置で分割し型枠支保工11上に載置して、型枠支保工11を底版8と側壁9の構築が完了した次の施工区間(図4の符号B参照)に移動させる。そして、図5(b)に示すように、頂版14上の地盤1を埋め戻す。 After the concrete of the top slab 14 has sufficiently hardened, the jack 122 is contracted to release the axial force of the replacement beam 12. The replacement beam 12 is then divided at the dividing section 121 and placed on the formwork support 11, which is then moved to the next construction section (see symbol B in Figure 4) where construction of the bottom slab 8 and side walls 9 has been completed. Then, as shown in Figure 5 (b), the ground 1 on the top slab 14 is backfilled.
トンネルは、複数の施工区間に区画して施工され、次の施工区間でも、図2~図5で説明した各工程が時間差をおいて実施される。そのため、底版8上で型枠支保工11を移動させれば、次の施工区間での型枠支保工11の設置が完了し、盛替え梁12と当接部材13を次の施工区間での施工に転用でき、当該施工区間の側壁9に作用する地盤1の側圧を盛替え梁12によって支持させることができる。 The tunnel is constructed by dividing it into multiple construction sections, and in the next construction section, each process described in Figures 2 to 5 is carried out with a time lag. Therefore, by moving the formwork support 11 on the base slab 8, the installation of the formwork support 11 in the next construction section is completed, and the replacement beam 12 and the abutment member 13 can be reused for construction in the next construction section, and the lateral pressure of the ground 1 acting on the side wall 9 of that construction section can be supported by the replacement beam 12.
このように、本実施形態では、トンネルの側壁9の延伸方向に延びる当接部材13を先端に取付けた盛替え梁12により、側壁9に作用する地盤1の側圧を支持する。盛替え梁12は型枠支保工11に載置され、当接部材13は盛替え梁12の先端に固定されるので、側壁9にブラケット等を取付けることなく盛替え梁12と当接部材13を設置することができ、トンネルの構築が容易になり、品質や美観を損なうこともない。 In this way, in this embodiment, the lateral pressure of the ground 1 acting on the side wall 9 is supported by the replacement beam 12, which has an abutment member 13 attached to its tip, extending in the extension direction of the tunnel side wall 9. The replacement beam 12 is placed on the formwork support 11, and the abutment member 13 is fixed to the tip of the replacement beam 12, so that the replacement beam 12 and the abutment member 13 can be installed without attaching a bracket or the like to the side wall 9, making it easier to construct the tunnel and without compromising the quality or aesthetics.
また本実施形態では、盛替え梁12が分割部121で分割可能であるため、分割された盛替え梁12の各部分を型枠支保工11に格納し、盛替え梁12を型枠支保工11上で容易に解体し、組立てることができる。 In addition, in this embodiment, since the replacement beam 12 can be divided at the dividing section 121, each part of the divided replacement beam 12 can be stored in the formwork support 11, and the replacement beam 12 can be easily disassembled and assembled on the formwork support 11.
盛替え梁12の使用後は、型枠支保工11を次の施工区間に移動させることで、盛替え梁12と当接部材13、および型枠支保工11を一括して次の施工区間に移動させ、転用することができる。事前に盛替え梁12を型枠支保工11上で分割しておくことで、型枠支保工11の移動時に盛替え梁12が中間杭3と干渉することもない。 After the replacement beam 12 is used, the formwork support 11 can be moved to the next construction section, and the replacement beam 12, abutment member 13, and formwork support 11 can be moved together to the next construction section and reused. By dividing the replacement beam 12 on the formwork support 11 in advance, the replacement beam 12 will not interfere with the intermediate pile 3 when the formwork support 11 is moved.
また本実施形態では、当接部材13を盛替え梁12ごとに設ける短尺のものとしている。仮に当接部材13を長尺のものとして各盛替え梁12の先端を1本の当接部材13に連結するような構成とすると、盛替え梁12の格納時に中間杭3の両側の型枠支保工11、11で当接部材13側に大きな偏荷重が発生し、型枠支保工11が転倒する恐れも考えられる。しかし本実施形態では、当接部材13を短尺とすることで、盛替え梁12の格納時にこのような大きな偏荷重が発生するのを抑制できる。 In addition, in this embodiment, the abutment members 13 are short and provided for each replacement beam 12. If the abutment members 13 were long and the tip of each replacement beam 12 was connected to a single abutment member 13, a large unbalanced load would be generated on the abutment member 13 side of the formwork supports 11, 11 on both sides of the intermediate pile 3 when the replacement beam 12 was stored, and there is a risk that the formwork supports 11 would tip over. However, in this embodiment, by making the abutment members 13 short, it is possible to prevent such a large unbalanced load from occurring when the replacement beam 12 is stored.
しかしながら、本発明が上記の実施形態に限ることはない。例えば上記の実施形態では受桁6を上段の切梁として機能させたが、これは必須ではなく、受桁6の下方に上段の切梁を別途設置してもよい。 However, the present invention is not limited to the above embodiment. For example, in the above embodiment, the support girder 6 functions as an upper strut, but this is not essential, and an upper strut may be installed separately below the support girder 6.
また、図6において図4と同様の水平断面で示すように、中間杭3が省略されることもあり、この場合は各側壁9と隔壁10の間で中間杭3の位置を避けて型枠支保工11を分割配置する必要がない。また当接部材13aを長尺のものとし、1本の当接部材13aに複数本の盛替え梁12aを接続することができる。盛替え梁12aには前記の分割部121が設けられず、盛替え梁12aの使用後は、ジャッキ122を収縮させて型枠支保工11を次の施工区間Bへ移動させることで、一体の盛替え梁12aと当接部材13aが型枠支保工11とともに移動する。 Also, as shown in FIG. 6 in a horizontal cross section similar to that of FIG. 4, the intermediate piles 3 may be omitted, in which case there is no need to divide and arrange the formwork support 11 between each side wall 9 and the partition wall 10 to avoid the position of the intermediate piles 3. Also, the abutment members 13a may be long, and multiple replacement beams 12a may be connected to one abutment member 13a. The replacement beams 12a do not have the above-mentioned division section 121, and after the replacement beams 12a are used, the jacks 122 are contracted to move the formwork support 11 to the next construction section B, and the integrated replacement beams 12a and abutment members 13a move together with the formwork support 11.
その他、トンネルの断面は図5(a)等に示したものに限らない。例えば図7に示すように隔壁10を有しないものであってもよいし、2つ以上の隔壁10を有してもよい。支保工の構成も特に限定されず、盛替え梁の先端の当接部材が、地盤1の側圧が作用するトンネルの側壁9に当接し、側壁9に作用する地盤1の側圧が盛替え梁によって支持されればよい。例えば図7の例では、盛替え梁12の両端の当接部材13が、側圧の作用するトンネル両側の側壁9のそれぞれに当接する。 In addition, the cross section of the tunnel is not limited to that shown in FIG. 5(a) etc. For example, as shown in FIG. 7, it may have no bulkhead 10, or it may have two or more bulkheads 10. The configuration of the support is also not particularly limited, as long as the abutment member at the tip of the replacement beam abuts against the side wall 9 of the tunnel on which the lateral pressure of the ground 1 acts, and the lateral pressure of the ground 1 acting on the side wall 9 is supported by the replacement beam. For example, in the example of FIG. 7, the abutment members 13 at both ends of the replacement beam 12 abut against each of the side walls 9 on both sides of the tunnel on which the lateral pressure acts.
また、側壁9は図5(a)等に示すように土留め壁2に接するものに限らない。例えば特許文献1に示されるように、側壁9を土留め壁2から間隔を空けて設け、地盤1の側圧を側壁9に伝達するため土留め壁2と側壁9の間にコンクリート等を設ける場合もある。 Furthermore, the side wall 9 is not limited to being in contact with the retaining wall 2 as shown in FIG. 5(a) etc. For example, as shown in Patent Document 1, the side wall 9 may be provided at a distance from the retaining wall 2, and concrete or the like may be provided between the retaining wall 2 and the side wall 9 to transmit the lateral pressure of the ground 1 to the side wall 9.
また本実施形態の手法を用いて構築する地下構造物もトンネルに限ることはなく、その他の地下構造物を構築する際も同様の手法を適用することができる。 Furthermore, the underground structures constructed using the method of this embodiment are not limited to tunnels, and the same method can be applied when constructing other underground structures.
以上、添付図面を参照しながら、本発明に係る好適な実施形態について説明したが、本発明はかかる例に限定されない。当業者であれば、本願で開示した技術的思想の範疇内において、各種の変更例又は修正例に想到し得ることは明らかであり、それらについても当然に本発明の技術的範囲に属するものと了解される。 The above describes preferred embodiments of the present invention with reference to the attached drawings, but the present invention is not limited to these examples. It is clear that a person skilled in the art can come up with various modified or revised examples within the scope of the technical ideas disclosed in this application, and it is understood that these also naturally fall within the technical scope of the present invention.
1:地盤
2:土留め壁
3:中間杭
4:腹起し
5:切梁
6:受桁
7:覆工板
8:底版
9:側壁
10:隔壁
11:型枠支保工
12、12a:盛替え梁
13、13a:当接部材
14:頂版
15:掘削部
17:反力受け部材
18、122:ジャッキ
21:ブラケット
121:分割部
1: Ground 2: Retaining wall 3: Intermediate pile 4: Wale 5: Beam 6: Support girder 7: Covering plate 8: Bottom slab 9: Side wall 10: Partition wall 11: Formwork support 12, 12a: Relay beam 13, 13a: Abutment member 14: Top slab 15: Excavation section 17: Reaction receiving member 18, 122: Jack 21: Bracket 121: Division section
Claims (3)
前記切梁を撤去し、一対の前記土留め壁の間の掘削部に、トンネルである地下構造物の躯体本体の両側の側壁を、一対の前記土留め壁に沿った位置で、高さ方向に下から上へと順に前記躯体本体の底版上に構築する工程(b)と、
両側の前記側壁の間で、前記側壁の上方の部分である地下構造物の躯体本体の頂版の高さまで設けられた、鉛直材の高さ方向の途中に水平材を接続した構成を有する型枠支保工で頂版構築時の型枠を支持し、当該型枠を用いてコンクリートにより頂版を構築する工程(c)と、
を有し、
前記工程(b)において、
両側の前記側壁の間で、前記型枠支保工の前記水平材の上に、水平方向の仮設梁を鉛直面において両側の前記側壁を結ぶ方向に載置して、前記仮設梁を前記型枠支保工により鉛直方向に支持し、
前記仮設梁の一方の前記側壁側の先端に、前記側壁の延伸方向に延びる当接部材を固定した後、前記仮設梁の長手方向の途中に設けた伸縮部材を伸長させることで、前記当接部材を一方の前記側壁の構築済みの部分の頭部に当接させ、他方の前記側壁の構築済みの部分または両側の前記側壁の間に構築される隔壁の構築済みの部分に反力を取って前記仮設梁に軸力を導入し、一方の前記側壁の構築済みの部分に前記土留め壁を介して作用する地盤の側圧を前記仮設梁により支持し、
前記型枠支保工を用いて前記頂版の構築を行った後、前記型枠支保工を、前記トンネルの次の施工区間へと、前記底版上で前記トンネルの延伸方向に移動させ、当該施工区間の前記側壁に作用する地盤の側圧を前記仮設梁により支持することを特徴とする地下構造物の構築方法。 (a) constructing a pair of retaining walls on both sides of a planned excavation location of the ground, excavating the ground between the pair of retaining walls, and supporting the lateral pressure of the ground acting on the retaining walls with a strut bridge spanning the pair of retaining walls;
(b) removing the struts and constructing side walls on both sides of the main body of the underground structure, which is a tunnel , in the excavation between the pair of earth retaining walls, in a height direction from bottom to top on the bottom slab of the main body of the underground structure, in a position along the pair of earth retaining walls;
A step (c) of supporting the formwork for constructing the top plate with a formwork support having a configuration in which a horizontal member is connected to the middle of the vertical member in the height direction, the formwork being provided between the side walls on both sides up to the height of the top plate of the main body of the underground structure, which is the upper part of the side walls, and constructing the top plate with concrete using the formwork;
having
In the step (b),
Between the side walls on both sides, a horizontal temporary beam is placed on the horizontal member of the formwork support in a direction connecting the side walls on both sides in a vertical plane, and the temporary beam is supported in the vertical direction by the formwork support;
abutment members extending in the extension direction of the side walls are fixed to the tip of one of the side walls of the temporary beam, and an expandable member provided midway in the longitudinal direction of the temporary beam is extended to bring the abutment members into contact with the head of the constructed portion of one of the side walls, and an axial force is introduced into the temporary beam by taking a reaction force from the constructed portion of the other side wall or the constructed portion of the partition wall constructed between the side walls on both sides, and the lateral pressure of the ground acting on the constructed portion of one of the side walls via the retaining wall is supported by the temporary beam ;
A method for constructing an underground structure, characterized in that after constructing the top slab using the formwork support, the formwork support is moved on the bottom slab in the extension direction of the tunnel to the next construction section of the tunnel, and the lateral pressure of the ground acting on the side walls of that construction section is supported by the temporary beams .
前記当接部材は、前記仮設梁ごとに設けられることを特徴とする請求項2記載の地下構造物の構築方法。 The temporary beams are provided at intervals in the extension direction of the side wall,
3. The method for constructing an underground structure according to claim 2, wherein the abutment member is provided for each of the temporary beams.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2020115176A JP7712066B2 (en) | 2020-07-02 | 2020-07-02 | How to build an underground structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2020115176A JP7712066B2 (en) | 2020-07-02 | 2020-07-02 | How to build an underground structure |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2022012971A JP2022012971A (en) | 2022-01-18 |
| JP7712066B2 true JP7712066B2 (en) | 2025-07-23 |
Family
ID=80169376
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2020115176A Active JP7712066B2 (en) | 2020-07-02 | 2020-07-02 | How to build an underground structure |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP7712066B2 (en) |
Family Cites Families (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS6088725A (en) * | 1983-10-20 | 1985-05-18 | Osaka Gas Co Ltd | Sheathing work of excavated trench |
| JPS61221497A (en) * | 1985-03-26 | 1986-10-01 | 五洋建設株式会社 | Construction of arch shaped tunnel and slide type scaffold truck used therein |
| JPH0344817Y2 (en) * | 1986-04-08 | 1991-09-20 | ||
| JPH04119557U (en) * | 1991-04-12 | 1992-10-26 | 日綜産業株式会社 | formwork equipment |
| JP3188342B2 (en) * | 1993-03-18 | 2001-07-16 | 株式会社鴻池組 | Tunnel construction method |
| JP5513867B2 (en) * | 2009-12-14 | 2014-06-04 | 戸田建設株式会社 | Construction method of underground structure, underground structure, and precast concrete member therefor |
| JP5465086B2 (en) * | 2010-05-25 | 2014-04-09 | 大成建設株式会社 | Construction method of underground structure |
| JP7072483B2 (en) * | 2018-10-09 | 2022-05-20 | 大成建設株式会社 | How to build a skeleton |
-
2020
- 2020-07-02 JP JP2020115176A patent/JP7712066B2/en active Active
Also Published As
| Publication number | Publication date |
|---|---|
| JP2022012971A (en) | 2022-01-18 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR101111594B1 (en) | Underground construction method through ground structure | |
| JP5055249B2 (en) | Multiple tunnel construction method and multiple tunnel structure | |
| JP4853429B2 (en) | Support structure of lining board, method of supporting lining board | |
| CN110499779B (en) | Construction method of air duct structure sharing side wall with subway station | |
| KR101803353B1 (en) | Structure for underground vertical extension in the building | |
| CN205242436U (en) | Supplementary soleplate traded interim bearing structure who props during system was gone along with sb. to guard him to underground complex | |
| JP6543176B2 (en) | Building method | |
| JP4226954B2 (en) | Underpinning method and viaduct | |
| JP5634931B2 (en) | Construction method of underground structure | |
| KR102231331B1 (en) | Removal apparatus of steel reinforcing member for tunnel portal area and construction method therefor | |
| JP3850785B2 (en) | Caisson laying method using main foundation pile | |
| JP2017218805A (en) | Construction method of underground structure | |
| KR101011969B1 (en) | Construction method of precast box structure using sliding means | |
| JP7712066B2 (en) | How to build an underground structure | |
| KR20190066754A (en) | Formwork structure supported by column unit | |
| JP2004027609A (en) | Construction method of underground structure and underground structure | |
| CN110904977A (en) | Municipal foundation pit supporting system and construction method thereof | |
| JPH11140892A (en) | Method for excavating ground and method for constructing underground structure using the same | |
| JP6228836B2 (en) | Reverse winding method | |
| JP7437336B2 (en) | Temporary cofferdam method, temporary cofferdam structure | |
| JP2016223084A (en) | Construction method of underground structure in reverse driving method | |
| JP6543177B2 (en) | Building method | |
| JP6938198B2 (en) | Construction method | |
| CN212452772U (en) | Auxiliary enclosure structure of parallel station main body | |
| KR20060029348A (en) | Underground tunnel structure construction method and steel pipe applied thereto and steel pipe structure using the same, and underground tunnel structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20221223 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20231004 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20231010 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20231205 |
|
| A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20240206 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20240415 |
|
| A911 | Transfer to examiner for re-examination before appeal (zenchi) |
Free format text: JAPANESE INTERMEDIATE CODE: A911 Effective date: 20240419 |
|
| A912 | Re-examination (zenchi) completed and case transferred to appeal board |
Free format text: JAPANESE INTERMEDIATE CODE: A912 Effective date: 20240510 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20250710 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 7712066 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |