JP7744261B2 - Deck replacement method and boom-reversal deck erection machine - Google Patents
Deck replacement method and boom-reversal deck erection machineInfo
- Publication number
- JP7744261B2 JP7744261B2 JP2022023101A JP2022023101A JP7744261B2 JP 7744261 B2 JP7744261 B2 JP 7744261B2 JP 2022023101 A JP2022023101 A JP 2022023101A JP 2022023101 A JP2022023101 A JP 2022023101A JP 7744261 B2 JP7744261 B2 JP 7744261B2
- Authority
- JP
- Japan
- Prior art keywords
- deck
- boom
- existing
- new
- replacement area
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Description
本発明は、新設床版の架設時の補強あるいは床版場所打ち部の床版打設による工程遅延がなく、簡易に既設床版を連続して撤去することができる床版取替工法及びブーム反転式床版架設機に関する。 This invention relates to a deck replacement method and boom-reversing deck erection machine that allows for the easy and continuous removal of existing decks without delays due to reinforcement during the erection of new decks or due to the casting of cast-in-place sections of the deck.
橋梁の床版取替工事では、橋面上から既設床版の撤去及び新設床版の架設を行う場合、幅員に制限があり、クレーンなどの旋回時に幅員方向に作業範囲を広げる作業機械は用いることができないことから、床版取替専用の架設機を用いて実施する場合が多い。 When replacing bridge decks, there are width restrictions when removing the existing deck from the bridge surface and erecting a new deck. This means that machines such as cranes that can expand their working area in the width direction when rotating cannot be used, so the work is often carried out using erection machines specifically designed for deck replacement.
この床版取替専用の架設機としては、例えば図14に示すように、4つの柱301を有する門型床版架設機300が知られている。この門型床版架設機300は、床版取替領域E1の両側の新設床版102上及び既設床版104上に柱301を設置する。柱301の上端には、橋軸方向に延びて吊り部302を橋軸方向に案内する橋部を有する。吊り部302は、旋回機構303を介して橋部に連結される。既設床版101の撤去は、吊り部302を用いて既設床版101を吊り上げ(A101)、中間位置P100まで既設床版104側に移動し(A102)、中間位置P100において旋回機構303により90度回転し(A103)、その後、さらに既設床版104側に移動させた(A104)後、待機しているトレーラ202の荷台に吊り下げる(A105)。その後、既設床版101が積み込まれたトレーラ202は、トラクタ201により、搬出方向A106に運搬される。なお、新設床版の架設は、既設床版101の撤去手順の逆順に行われる。 As an example of an erection machine dedicated to this type of deck replacement, a portal deck erection machine 300 with four pillars 301 is known, as shown in Figure 14. This portal deck erection machine 300 installs the pillars 301 on the new deck 102 and the existing deck 104 on both sides of the deck replacement area E1. The upper end of the pillar 301 has a bridge section that extends in the bridge axis direction and guides the suspension section 302 in the bridge axis direction. The suspension section 302 is connected to the bridge section via a swivel mechanism 303. To remove the existing deck 101, the existing deck 101 is lifted using the lifting part 302 (A101), moved to the intermediate position P100 toward the existing deck 104 (A102), rotated 90 degrees by the swivel mechanism 303 at the intermediate position P100 (A103), and then moved further toward the existing deck 104 (A104), after which it is suspended from the loading platform of the waiting trailer 202 (A105). The trailer 202 loaded with the existing deck 101 is then transported by the tractor 201 in the removal direction A106. Note that the installation of the new deck is performed in the reverse order of the procedure for removing the existing deck 101.
ところで、従来の門型床版架設機は、床版取替領域の両側になる新設床版上と既設床版上に柱を設置するため、床版吊り上げ時は、新設床版に架設機の反力が作用することから、新設床版下にモルタルを打設して架設機の反力を鋼桁に伝達する。この場合、無収縮モルタルを打設して新設床版を固定するため、無収縮モルタルの初期強度が発現するまで、次の床版取替サイクルの作業に移ることができず、無収縮モルタルの硬化時間を考慮した工程管理が必要になる。 Conventional portal-type deck erection machines install columns on the new and existing decks, which are on either side of the deck replacement area. Therefore, when the deck is lifted, the reaction force of the erection machine acts on the new deck. Therefore, mortar is poured under the new deck to transmit the reaction force of the erection machine to the steel girders. In this case, because the new deck is fixed in place by pouring non-shrinkage mortar, work cannot proceed to the next deck replacement cycle until the non-shrinkage mortar has developed its initial strength. Therefore, process management must take into account the hardening time of the non-shrinkage mortar.
一方、床版場所打ち部の既設床版を撤去する場合、門型床版架設機は、床版取替領域の両側に柱を設置するため、床版撤去後、床版場所打ち部の床版打設が完了し、初期強度が発現するまで待機する必要があり、作業工程が遅延してしまう。この工程遅延を防止するため、床版場所打ち部を通過してプレキャスト床版のみの取替を行い、床版場所打ち部の既設床版の撤去作業を別の施工機械を用いて行うことが考えられるが、この場合、追加の工事費用がかかってしまう。 On the other hand, when removing the existing deck slab in the cast-in-place deck section, the portal deck erection machine installs columns on both sides of the deck replacement area, so after removing the deck, it is necessary to wait until the deck slab in the cast-in-place deck section has been poured and its initial strength has been achieved, delaying the work process. To prevent this process delay, it is possible to pass through the cast-in-place deck section and replace only the precast deck slab, and then use a separate construction machine to remove the existing deck slab in the cast-in-place deck section, but this would incur additional construction costs.
本発明は、上記に鑑みてなされたものであって、新設床版の架設時のモルタル強度発現を考慮した工程管理が必要なく、簡易に既設床版を連続して撤去することができる床版取替工法及びブーム反転式床版架設機を提供することを目的とする。 The present invention was made in consideration of the above, and aims to provide a deck replacement method and boom-reversal deck erection machine that can easily and continuously remove existing decks without the need for process management that takes into account the development of mortar strength when erecting new decks.
上述した課題を解決し、目的を達成するために、本発明は、既設床版を順次撤去するとともに新設床版を順次架設する床版取替領域における床版取替工法であって、前記床版取替領域外の既設床版側に配置され、幅員方向に少なくとも床版幅を超える間隔をもって平行配置されて橋軸方向に同期して反転可能かつ伸縮可能なブームを有し、該ブームの先端がブームトップビームによって連結され、該ブームトップビームに吊り下げられて旋回機構をもつ吊り部を有したブーム反転式床版架設機を備え、前記床版取替領域における既設床版の撤去時は、前記床版取替領域側に前記ブームを向け、前記吊り部に撤去すべき既設床版を吊るし、その後、該既設床版を前記旋回機構により90度旋回して既設床版の長手方向を前記橋軸方向に向け、この状態で前記ブームを反転して、吊り下げた既設床版を前記床版取替領域外の搬入搬出領域に移動させ、前記床版取替領域における新設床版の架設時は、前記搬入搬出領域に前記ブームを向け、長手方向が前記橋軸方向に向いた新設床版を前記吊り部に吊るし、その後、前記ブームを前記床版取替領域側に反転させて、吊り下げた新設床版を前記床版取替領域に移動し、その後、吊り下げた新設床版を前記旋回機構により90度旋回して新設床版の長手方向を幅員方向に向け、この状態で前記新設床版を架設することを特徴とする。 In order to solve the above-mentioned problems and achieve the objectives, the present invention provides a deck replacement method in a deck replacement area in which existing decks are sequentially removed and new decks are sequentially erected. The method comprises a boom-reversal deck erection machine that is positioned on the existing deck side outside the deck replacement area, is arranged in parallel in the bridge width direction with a gap that exceeds at least the deck width, and has booms that are reversible and extendable synchronously in the bridge axis direction, the ends of the booms are connected by a boom top beam, and is suspended from the boom top beam and has a lifting section with a swivel mechanism. When removing the existing deck in the deck replacement area, the boom is directed toward the deck replacement area, and the existing deck to be removed is suspended from the lifting section. The existing deck is then rotated 90 degrees by the rotating mechanism so that its longitudinal direction is aligned with the bridge axis. In this state, the boom is reversed and the suspended existing deck is moved to a loading/unloading area outside the deck replacement area. When erecting the new deck in the deck replacement area, the boom is directed toward the loading/unloading area and the new deck, with its longitudinal direction aligned with the bridge axis, is hung from the hanging section. The boom is then reversed toward the deck replacement area and the suspended new deck is moved to the deck replacement area. The suspended new deck is then rotated 90 degrees by the rotating mechanism so that its longitudinal direction is aligned with the bridge width direction, and the new deck is erected in this state.
また、本発明は、上記の発明において、前記搬入搬出領域には、前記既設床版を搬送し、あるいは前記新設床版を搬入するトレーラが配置されることを特徴とする。 Furthermore, in the above invention, the present invention is characterized in that a trailer is placed in the loading/unloading area to transport the existing deck slab or to load the new deck slab.
また、本発明は、上記の発明において、前記ブームは、同期して伸縮し、前記吊り部の位置を調整することを特徴とする。 In the above invention, the present invention is also characterized in that the booms extend and retract synchronously to adjust the position of the hanging part.
また、本発明は、既設床版を順次撤去するとともに新設床版を順次架設する床版取替領域における床版取替に用いるブーム反転式床版架設機であって、前記床版取替領域外の既設床版側に配置され、幅員方向に少なくとも床版幅を超える間隔をもって平行配置されて橋軸方向に同期して反転可能かつ伸縮可能なブームを有し、該ブームの先端がブームトップビームによって連結され、該ブームトップビームに吊り下げられて旋回機構をもつ吊り部を有し、前記床版取替領域における既設床版の撤去時は、前記床版取替領域側に前記ブームを向け、前記吊り部に撤去すべき既設床版を吊るし、その後、該既設床版を前記旋回機構により90度旋回して既設床版の長手方向を前記橋軸方向に向け、この状態で前記ブームを反転して、吊り下げた既設床版を前記床版取替領域外の搬入搬出領域に移動させ、 前記床版取替領域における新設床版の架設時は、前記搬入搬出領域に前記ブームを向け、長手方向が前記橋軸方向に向いた新設床版を前記吊り部に吊るし、その後、前記ブームを前記床版取替領域側に反転させて、吊り下げた新設床版を前記床版取替領域に移動し、その後、吊り下げた新設床版を前記旋回機構により90度旋回して新設床版の長手方向を幅員方向に向け、この状態で前記新設床版を架設することを特徴とする。 The present invention also provides a boom-reversing deck erection machine used for deck replacement in a deck replacement area, where existing decks are sequentially removed and new decks are sequentially erected. The machine has booms that are positioned on the side of the existing deck outside the deck replacement area, are arranged in parallel in the width direction with a gap that at least exceeds the deck width, and are reversible and extendable in sync in the bridge axis direction, and the ends of the booms are connected by a boom top beam and have a hanging section that is suspended from the boom top beam and has a swivel mechanism. When removing the existing deck in the deck replacement area, the boom is directed toward the deck replacement area and the existing deck to be removed is hung from the hanging section. The existing deck is then rotated 90 degrees by the swivel mechanism so that the longitudinal direction of the existing deck is aligned in the bridge axis direction, and in this state the boom is reversed to move the suspended existing deck to a loading/unloading area outside the deck replacement area. When erecting a new deck in the deck replacement area, the boom is directed toward the carry-in/carry-out area, and the new deck with its longitudinal direction oriented in the bridge axis direction is hung from the hanging section. The boom is then inverted toward the deck replacement area, and the suspended new deck is moved to the deck replacement area. The suspended new deck is then rotated 90 degrees by the rotation mechanism so that the longitudinal direction of the new deck is oriented in the width direction, and the new deck is erected in this state.
また、本発明は、上記の発明において、前記床版取替領域外の既設床版側に、前記既設床版を搬送し、あるいは前記新設床版を搬入するトレーラが配置される搬入搬出領域を形成することを特徴とする。 Furthermore, in the above invention, the present invention is characterized in that a loading/unloading area is formed on the existing deck side outside the deck replacement area, where a trailer is positioned to transport the existing deck or to bring in the new deck.
また、本発明は、上記の発明において、前記ブームは、同期して伸縮し、前記吊り部の位置を調整することを特徴とする。 In the above invention, the present invention is also characterized in that the booms extend and retract synchronously to adjust the position of the hanging part.
本発明によれば、新設床版の架設時のモルタル強度発現を考慮した工程管理が必要なく、簡易に既設床版を連続して撤去することができる。 According to this invention, there is no need for process management that takes into account the development of mortar strength during the erection of new deck slabs, and existing deck slabs can be easily and continuously removed.
以下、添付図面を参照して本発明を実施するための形態について説明する。図1は、本実施の形態であるブーム反転式床版架設機1による既設床版の撤去作業を説明する概要側面図である。また、図2は、図1に示したブーム反転式床版架設機1の概要平面図である。さらに、図3は、図1に示したブーム反転式床版架設機1の概要正面図である。また、図4は、図1に示したブーム反転式床版架設機1の斜視図である。さらに、図5は、図1に示したブーム反転式床版架設機1による床版取替作業工程を説明する説明図である。 The following describes an embodiment of the present invention with reference to the accompanying drawings. Figure 1 is a schematic side view illustrating the removal of an existing deck using a boom reversal type deck erection machine 1 according to this embodiment. Figure 2 is a schematic plan view of the boom reversal type deck erection machine 1 shown in Figure 1. Figure 3 is a schematic front view of the boom reversal type deck erection machine 1 shown in Figure 1. Figure 4 is a perspective view of the boom reversal type deck erection machine 1 shown in Figure 1. Figure 5 is an explanatory diagram illustrating the deck replacement work process using the boom reversal type deck erection machine 1 shown in Figure 1.
図1~図4においては、既設床版101を順次撤去するとともに新設床版102を順次架設する床版取替領域E1の一端側であって床版取替領域E1外の既設床版領域E2に配置される。ブーム反転式床版架設機1は、幅員方向(±X方向)に、少なくとも、橋軸方向(±Y方向)に分割された床版の床版幅を超える間隔をもって配置され、橋軸方向(±Y方向)に同期して反転可能かつ伸縮可能な2つのテレスコープ式ブーム11を有する。テレスコープ式ブーム11は、それぞれ架設機本体2の軸C1,C2を中心に回動する。各テレスコープ式ブーム11の先端側は、ブームトップビーム13により連結されている。テレスコープ式ブーム11はそれぞれブーム折り畳み用シリンダ11aによって回動されるとともに、ブーム反転用シリンダ11bによって伸縮される。 In Figures 1 to 4, the boom-reversing deck erection machine 1 is located at one end of the deck replacement area E1, where the existing deck slabs 101 are sequentially removed and new deck slabs 102 are sequentially installed, in the existing deck area E2 outside the deck replacement area E1. The boom-reversing deck erection machine 1 is positioned in the width direction (±X direction) at a distance that exceeds at least the deck width of the deck divided in the bridge axis direction (±Y direction), and has two telescopic booms 11 that can be reversed and extended in sync in the bridge axis direction (±Y direction). The telescopic booms 11 each rotate around axes C1 and C2 of the erection machine main body 2. The tips of each telescopic boom 11 are connected by a boom top beam 13. The telescopic booms 11 are rotated by boom folding cylinders 11a and extended by boom reversing cylinders 11b.
ブームトップビーム13には、吊り部12が吊り下げられる。吊り部12は、旋回機構15を有する幅方向移動機構14がブームトップビーム13に連結し、床版昇降装置17が旋回吊り天秤16を介して旋回機構15に連結する。幅方向移動機構14は、床版架設時あるいは床版撤去時に床版の幅方向の位置を微調整する。旋回機構15は、床版架設時あるいは床版撤去時に鉛直軸(Z軸)まわりに床版を旋回する。床版昇降装置17は、床版の吊り位置を昇降する。なお、幅方向移動機構14、旋回機構15、床版昇降装置17は、電動モータによって駆動される。 A hoisting unit 12 is suspended from the boom top beam 13. A width-direction movement mechanism 14 having a swivel mechanism 15 is connected to the boom top beam 13 for the hoisting unit 12, and a deck lifting device 17 is connected to the swivel mechanism 15 via a swivel lifting balance 16. The width-direction movement mechanism 14 fine-tunes the widthwise position of the deck when erecting or removing the deck. The swivel mechanism 15 rotates the deck around the vertical axis (Z-axis) when erecting or removing the deck. The deck lifting device 17 raises and lowers the suspended position of the deck. The width-direction movement mechanism 14, swivel mechanism 15, and deck lifting device 17 are driven by electric motors.
架設機本体2の-Y方向には、各軸C1,C2から-Y方向に延びてテレスコープ式ブーム11を支持するメインビーム2bを有する。なお、メインビーム2bのーY方向端部には、カウンタウエイトが配置される。メインビーム2bは、下部にタイヤ2aを有し、油圧モータにより、ブーム反転式床版架設機1の自走を可能にしている。なお、ブーム反転式床版架設機1の自走は、タイヤ2aに限らず、レール上を移動するレール式であってもよい。メインビーム2bは、複数の連結ビーム3によって連結される。連結ビーム3の上には、トレーラ202の走行用の鉄板が設置され、スロープを介して、トレーラ202が搬入搬出領域Eに進入可能としている。また、架設機本体2は、例えば、アウトリガーなどにより、縦断勾配や横断勾配に対応して架設機本体2の水平を維持する機能を有する。なお、各部の油圧機構の駆動及び制御を行うエンジン式の油圧ユニットや、電動モータの電力供給を行う発電ユニットは、架設機本体2の-Y方向に外部配置されて接続される。 In the -Y direction of the construction machine main body 2, there is a main beam 2b that extends from each axis C1, C2 in the -Y direction and supports the telescopic boom 11. A counterweight is placed at the -Y end of the main beam 2b. The main beam 2b has tires 2a at its bottom, allowing the boom-reversal deck slab erection machine 1 to propel itself using a hydraulic motor. The boom-reversal deck slab erection machine 1 can also propel itself using rails, rather than tires 2a. The main beam 2b is connected by multiple connecting beams 3. A steel plate for the trailer 202 to travel on is installed on the connecting beams 3, allowing the trailer 202 to enter the loading/unloading area E via a slope. The construction machine main body 2 also has the function of maintaining the construction machine main body 2 level in response to longitudinal and transverse gradients, for example, using outriggers. The engine-driven hydraulic unit that drives and controls the hydraulic mechanisms of each section and the power generation unit that supplies power to the electric motor are externally located and connected to the construction machine main body 2 in the -Y direction.
自走によって、現在の既設床版領域E2側であって現在の床版取替領域E1に隣接する領域を次の床版取替領域として作業を行う場合、ブーム反転式床版架設機1は、自走によって-Y方向に移動する。なお、この際、ブーム反転式床版架設機1は、テレスコープ式ブーム11を-Y方向に反転して折り畳んだ状態で自走することが好ましい。トレーラ202は、トラクタ201に連結されて牽引される。また、ブーム反転式床版架設機1の制御は、リモートで行ってもよいし、移動作業に影響しない場所に運転席を設けてもよい。なお、床版取替領域E1の-Y方向に隣接した架設済領域E3には、取替により既に架設された架設済新設床版103が配置される。 When working to move to the next deck replacement area adjacent to the current deck replacement area E1 on the side of the current existing deck area E2, the boom reversal deck erection machine 1 moves in the -Y direction by self-propelled movement. At this time, the boom reversal deck erection machine 1 preferably self-propels with the telescopic boom 11 inverted in the -Y direction and folded. The trailer 202 is connected to the tractor 201 and towed. The boom reversal deck erection machine 1 may be controlled remotely, or the driver's seat may be located in a location that does not affect the movement work. A new deck 103 that has already been installed by replacement is placed in the installed area E3 adjacent to the deck replacement area E1 in the -Y direction.
<床版取替作業工程>
次に、図5~図9を参照して床版取替作業工程について説明する。まず、図5に示すように、ブーム反転式床版架設機1を、既設床版領域E2の床版取替領域E1側に展開して配置する。そして、図6に示すように、トレーラ202を搬入搬出領域Eに進入させる。その後、図7に示すように、剥離された既設床版101を吊り部12に吊り下げ、テレスコープ式ブーム11を反転及び伸縮させてトレーラ202の荷台に運ぶ。この際、既設床版101は、吊り下げられた後、旋回機構15により90度旋回されて、既設床版101の長手方向が橋軸方向に向けられる。そして、旋回された既設床版101は、そのままの姿勢が維持され、テレスコープ式ブーム11間に位置してトレーラ202の荷台に載置される。トレーラ202は、2枚の既設床版101が載置されると、搬入搬出領域Eから退出して運搬される。
<Deck replacement work process>
Next, the deck replacement work process will be described with reference to Figures 5 to 9. First, as shown in Figure 5, the boom-reversing deck erection machine 1 is deployed and positioned on the deck replacement area E1 side of the existing deck area E2. Then, as shown in Figure 6, the trailer 202 is moved into the loading/unloading area E. After that, as shown in Figure 7, the peeled existing deck 101 is hung from the hoisting section 12, and the telescopic boom 11 is inverted and extended to carry it to the bed of the trailer 202. At this time, after being hung, the existing deck 101 is rotated 90 degrees by the swivel mechanism 15 so that the longitudinal direction of the existing deck 101 is oriented in the bridge axis direction. Then, the rotated existing deck 101 is maintained in its current position and placed between the telescopic booms 11 on the bed of the trailer 202. Once the two existing deck slabs 101 are loaded onto the trailer 202, the trailer 202 leaves the loading/unloading area E and is transported.
なお、テレスコープ式ブーム11の伸縮は、必要に応じて行われる。例えば、既設床版101がブーム反転式床版架設機1から遠い位置にある場合や、既設床版101を載置すべきトレーラ202の荷台位置が遠い場合などに行われる。テレスコープ式ブーム11の先端位置は、床版取替領域E1での吊りをカバーできるとともに、搬入搬出領域Eでの吊りをカバーできるように、伸縮調整される。搬入搬出領域Eでは、トレーラ202に床版2枚を載せる場合があり、テレスコープ式ブーム11の作業半径は予め床版2枚を載せることができる範囲に調整されている。 The telescopic boom 11 is extended and retracted as needed. For example, this is done when the existing deck slab 101 is located far from the boom reversal deck erection machine 1, or when the loading platform of the trailer 202 on which the existing deck slab 101 is to be placed is far away. The tip position of the telescopic boom 11 is adjusted and retracted so that it can cover lifting in the deck slab replacement area E1 as well as in the loading and unloading area E. In the loading and unloading area E, two decks may be loaded on the trailer 202, and the working radius of the telescopic boom 11 is adjusted in advance to a range that allows two decks to be loaded.
具体的に、図1に示すように、搬入搬出領域Eへの既設床版101の配置位置が架設機本体2に近い場合、ブーム先端は、軌道L1を描いて矢印A1に示すように既設床版101を移動する。また、搬入搬出領域Eへの既設床版101の配置位置が既設床版領域E2から遠い場合、ブーム先端は、軌道L1,L2を描いて矢印A2に示すように既設床版101を移動する。さらに、床版取替領域E1内の既設床版101が架設機本体2から遠い位置にある場合、ブーム先端は、軌道L3を描いて+Y方向に延びる。 Specifically, as shown in Figure 1, if the position of the existing deck slab 101 in the loading/unloading area E is close to the erection machine main body 2, the boom tip moves along trajectory L1 and over the existing deck slab 101 as indicated by arrow A1. Also, if the position of the existing deck slab 101 in the loading/unloading area E is far from the existing deck slab area E2, the boom tip moves along trajectories L1 and L2 and over the existing deck slab 101 as indicated by arrow A2. Furthermore, if the existing deck slab 101 in the deck replacement area E1 is far from the erection machine main body 2, the boom tip extends in the +Y direction along trajectory L3.
その後、床版取替領域E1における新設床版102の架設を行う。まず、図8に示すように、搬入搬出領域Eに新設床版102を載せたトレーラ203を進入させる。そして、既設床版101の撤去工程の逆順に、新設床版102をトレーラ203から床版取替領域E1に移動する。具体的には、搬入搬出領域Eにテレスコープ式ブーム11を向け、長手方向が橋軸方向に向いた新設床版102を吊り部12に吊るし、その後、テレスコープ式ブーム11を床版取替領域E1側に反転させて、吊り下げた新設床版102を床版取替領域E1に移動し、その後、吊り下げた新設床版102を旋回機構15により90度旋回して新設床版102の長手方向を幅員方向に向け、この状態で新設床版102を主桁100上に架設する。トレーラ203に載せられた2枚の新設床版102の架設が終了すると、トレーラ203は、搬入搬出領域Eから退出する。 Then, the new deck 102 is erected in the deck replacement area E1. First, as shown in Figure 8, a trailer 203 carrying the new deck 102 enters the loading/unloading area E. Then, the new deck 102 is moved from the trailer 203 to the deck replacement area E1 in the reverse order of the removal process of the existing deck 101. Specifically, the telescopic boom 11 is directed toward the loading/unloading area E, and the new deck slab 102, with its longitudinal direction oriented in the bridge axis direction, is hung from the suspender 12. The telescopic boom 11 is then inverted toward the deck replacement area E1, and the suspended new deck slab 102 is moved to the deck replacement area E1. The suspended new deck slab 102 is then rotated 90 degrees by the rotating mechanism 15 so that its longitudinal direction is oriented in the width direction, and in this state the new deck slab 102 is erected on the main girder 100. When the erection of the two new deck slabs 102 loaded on the trailer 203 is complete, the trailer 203 exits the loading/unloading area E.
その後、図9に示すように、テレスコープ式ブーム11を反転して折り畳んだブーム反転式床版架設機1を、次の床版取替領域E1´から既設床版領域E2に自走で移動する。その後、図5に示すように、ブーム反転式床版架設機1を展開し、上記の作業手順を繰り返す。 Then, as shown in Figure 9, the boom reversal type deck erection machine 1, with the telescopic boom 11 inverted and folded, moves under its own power from the next deck replacement area E1' to the existing deck area E2. Then, as shown in Figure 5, the boom reversal type deck erection machine 1 is unfolded, and the above work procedure is repeated.
<ブーム反転式床版架設機の展開>
次に、図10~図13を参照して、ブーム反転式床版架設機1の展開の概要について説明する。図10に示すように、ブーム反転式床版架設機1は、複数の連結ビーム3がメインビーム2b間に折り畳まれた状態でトレーラ204に載せられて運搬される。このとき、メインビーム2b間の間隔は、トレーラ204の荷台の幅以下となっている。トレーラ204が搬入搬出領域Eに進入した後、図11に示すように、連結ビーム3は、拡幅シリンダ20によって幅方向(±X方向)に広げられて配列される。これに伴って、メインビーム2b及びこれに連結するテレスコープ式ブーム11も幅方向に広がる。この結果、メインビーム2b及びテレスコープ式ブーム11は、トレーラ204の荷台の幅を超えて荷台の外部に移動する。ここで、四隅に配置されたアウトリガーとしてのシリンダジャッキ21を鉛直下方に伸ばすことによって、ブーム反転式床版架設機1と、トレーラ204の荷台との間に隙間が生じる。この状態で、トレーラ204は、-X方向に移動でき、トレーラ204は搬入搬出領域Eから退出する。
<Deployment of boom-reversing deck erection machines>
Next, an overview of the deployment of the boom reversal type deck erection machine 1 will be described with reference to Figures 10 to 13. As shown in Figure 10, the boom reversal type deck erection machine 1 is transported on a trailer 204 with multiple connecting beams 3 folded between the main beams 2b. At this time, the spacing between the main beams 2b is equal to or less than the width of the trailer 204 bed. After the trailer 204 enters the loading/unloading area E, as shown in Figure 11, the connecting beams 3 are widened in the width direction (±X direction) by the widening cylinders 20. Accordingly, the main beams 2b and the telescopic boom 11 connected thereto also widen in the width direction. As a result, the main beams 2b and the telescopic boom 11 move outside the bed beyond the width of the trailer 204 bed. Here, by extending the cylinder jacks 21 serving as outriggers arranged at the four corners vertically downward, a gap is created between the boom reversal type deck erection machine 1 and the bed of the trailer 204. In this state, the trailer 204 can move in the −X direction, and the trailer 204 leaves the loading/unloading area E.
トレーラ204の退出後、図12に示すように、シリンダジャッキ21を鉛直上方に伸ばしてブーム反転式床版架設機1を既設床版101上に配置する。その後、連結ビーム3上には、鉄板311が配置され、連結ビーム3の前後(±Y方向)端にスロープ312が配置されて、剥離された既設床版101を載せるトレーラ205が搬入搬出領域Eへの出入がしやすいようにする。なお、このとき、カウンタウエイト30が架設機本体2の各メインビーム2bの後方(-Y方向)に配置される。 After the trailer 204 has withdrawn, as shown in Figure 12, the cylinder jack 21 is extended vertically upward to place the boom-reversal deck erection machine 1 on the existing deck 101. Then, steel plates 311 are placed on the connecting beam 3, and slopes 312 are placed at the front and rear (±Y direction) ends of the connecting beam 3 to facilitate the trailer 205 carrying the peeled existing deck 101 entering and exiting the loading/unloading area E. At this time, the counterweight 30 is positioned behind each main beam 2b of the erection machine body 2 (-Y direction).
ここで、図13に示すように、既設床版101は縦断勾配や横断勾配などの傾斜面Sがあるため、シリンダジャッキ21をアウトリガーとして調整してブーム反転式床版架設機1の水平面Hを維持する。これにより、既設床版101及び新設床版102の移動を安定して行うことができる。 As shown in Figure 13, the existing deck 101 has an inclined surface S, such as a longitudinal gradient or a transverse gradient, so the cylinder jack 21 is adjusted as an outrigger to maintain the horizontal plane H of the boom-reversal deck erection machine 1. This allows for stable movement of the existing deck 101 and the new deck 102.
本実施の形態では、ブーム反転式床版架設機1を、床版取替領域E1の一方側、すなわち既設床版領域E2側に配置して、既設床版101及び新設床版102の移動をテレスコープ式ブーム11の反転により行っているため、新設床版102の架設時のモルタル強度発現を考慮した工程管理が必要なく、また、床版場所打ち部の床版打設による工程遅延もなく、簡易に既設床版101を連続して撤去することができるとともに、新設床版102を連続して架設することができる。 In this embodiment, the boom-reversing deck erection machine 1 is positioned on one side of the deck replacement area E1, i.e., on the side of the existing deck area E2, and the existing deck 101 and new deck 102 are moved by reversing the telescopic boom 11. This eliminates the need for process management that takes into account the development of mortar strength when erecting the new deck 102, and eliminates process delays due to deck casting in the cast-in-place section of the deck. This allows the existing deck 101 to be easily removed in succession, and the new deck 102 to be erected in succession.
なお、本実施の形態では、4枚/日の床版取替が可能なブーム長を有し、従来の3枚/日の床版取替に比して作業効率を2倍に高めることができる。また、ブーム反転式床版架設機1は、重心が低く、床版移動時の安定性が高い。 In this embodiment, the boom length allows for four deck slabs to be replaced per day, doubling work efficiency compared to the conventional rate of three deck slabs per day. Furthermore, the boom-reversal deck erection machine 1 has a low center of gravity, providing high stability when moving deck slabs.
また、上記の実施の形態で図示した各構成は機能概略的なものであり、必ずしも物理的に図示の構成をされていることを要しない。すなわち、各装置及び構成要素の分散・統合の形態は図示のものに限られず、その全部又は一部を各種の使用状況などに応じて、任意の単位で機能的又は物理的に分散・統合して構成することができる。 Furthermore, the components illustrated in the above embodiments are merely functional schematics and do not necessarily have to be physically configured as shown. In other words, the distribution and integration of each device and component is not limited to that shown, and all or part of them can be functionally or physically distributed and integrated in any unit depending on various usage conditions, etc.
1 ブーム反転式床版架設機
2 架設機本体
2a タイヤ
2b メインビーム
3 連結ビーム
11 テレスコープ式ブーム
11a ブーム折り畳み用シリンダ
11b ブーム反転用シリンダ
12 吊り部
13 ブームトップビーム
14 幅方向移動機構
15 旋回機構
16 旋回吊り天秤
17 床版昇降装置
20 拡幅シリンダ
21 シリンダジャッキ
30 カウンタウエイト
100 主桁
101 既設床版
102 新設床版
103 架設済新設床版
201 トラクタ
202,203,204,205 トレーラ
311 鉄板
312 スロープ
A1、A2 矢印
E 搬入搬出領域
E1 床版取替領域
E2 既設床版領域
E3 架設済領域
H 水平面
L1~L3 軌道
S 勾配面
DESCRIPTION OF SYMBOLS 1 Boom-reversing deck erection machine 2 Erection machine body 2a Tire 2b Main beam 3 Connecting beam 11 Telescopic boom 11a Boom folding cylinder 11b Boom reversing cylinder 12 Lifting section 13 Boom top beam 14 Width direction movement mechanism 15 Swivel mechanism 16 Swivel lifting balance 17 Deck slab lifting device 20 Widening cylinder 21 Cylinder jack 30 Counterweight 100 Main girder 101 Existing deck 102 New deck slab 103 Erected new deck slab 201 Tractor 202, 203, 204, 205 Trailer 311 Iron plate 312 Slope A1, A2 Arrows E Loading/unloading area E1 Deck slab replacement area E2 Existing deck area E3 Installed area H Horizontal plane L1 to L3 Track S Inclined surface
Claims (6)
前記床版取替領域外の既設床版側に配置され、幅員方向に少なくとも床版幅を超える間隔をもって平行配置されて橋軸方向に同期して反転可能かつ伸縮可能なブームを有し、該ブームの先端がブームトップビームによって連結され、該ブームトップビームに吊り下げられて旋回機構をもつ吊り部を有したブーム反転式床版架設機を備え、
前記床版取替領域における既設床版の撤去時は、前記床版取替領域側に前記ブームを向け、前記吊り部に撤去すべき既設床版を吊るし、その後、該既設床版を前記旋回機構により90度旋回して既設床版の長手方向を前記橋軸方向に向け、この状態で前記ブームを反転して、吊り下げた既設床版を前記床版取替領域外の搬入搬出領域に移動させ、
前記床版取替領域における新設床版の架設時は、前記搬入搬出領域に前記ブームを向け、長手方向が前記橋軸方向に向いた新設床版を前記吊り部に吊るし、その後、前記ブームを前記床版取替領域側に反転させて、吊り下げた新設床版を前記床版取替領域に移動し、その後、吊り下げた新設床版を前記旋回機構により90度旋回して新設床版の長手方向を幅員方向に向け、この状態で前記新設床版を架設することを特徴とする床版取替工法。 A slab replacement method in a slab replacement area in which existing slabs are sequentially removed and new slabs are sequentially erected,
A boom-reversing deck erection machine is provided, which is arranged on the existing deck side outside the deck replacement area, has booms arranged in parallel in the width direction with an interval that exceeds at least the deck width, and is reversible and extendable synchronously in the bridge axis direction, and the tips of the booms are connected by a boom top beam, and has a hanging part that is suspended from the boom top beam and has a swivel mechanism,
When removing the existing deck in the deck replacement area, the boom is directed toward the deck replacement area, and the existing deck to be removed is hung from the hanging section. The existing deck is then rotated 90 degrees by the rotating mechanism so that the longitudinal direction of the existing deck is oriented in the direction of the bridge axis. In this state, the boom is reversed, and the suspended existing deck is moved to a loading/unloading area outside the deck replacement area.
When erecting a new deck in the deck replacement area, the boom is directed toward the loading/unloading area, and the new deck with its longitudinal direction facing the bridge axis direction is hung from the hanging section, then the boom is flipped toward the deck replacement area and the hung new deck is moved to the deck replacement area, and then the hung new deck is rotated 90 degrees by the rotating mechanism so that the longitudinal direction of the new deck is facing the width direction, and the new deck is erected in this state.This deck replacement method is characterized by the following.
前記床版取替領域外の既設床版側に配置され、幅員方向に少なくとも床版幅を超える間隔をもって平行配置されて橋軸方向に同期して反転可能かつ伸縮可能なブームを有し、該ブームの先端がブームトップビームによって連結され、該ブームトップビームに吊り下げられて旋回機構をもつ吊り部を有し、
前記床版取替領域における既設床版の撤去時は、前記床版取替領域側に前記ブームを向け、前記吊り部に撤去すべき既設床版を吊るし、その後、該既設床版を前記旋回機構により90度旋回して既設床版の長手方向を前記橋軸方向に向け、この状態で前記ブームを反転して、吊り下げた既設床版を前記床版取替領域外の搬入搬出領域に移動させ、
前記床版取替領域における新設床版の架設時は、前記搬入搬出領域に前記ブームを向け、長手方向が前記橋軸方向に向いた新設床版を前記吊り部に吊るし、その後、前記ブームを前記床版取替領域側に反転させて、吊り下げた新設床版を前記床版取替領域に移動し、その後、吊り下げた新設床版を前記旋回機構により90度旋回して新設床版の長手方向を幅員方向に向け、この状態で前記新設床版を架設することを特徴とするブーム反転式床版架設機。 A boom-reversing deck erection machine used for deck replacement in a deck replacement area in which existing decks are sequentially removed and new decks are sequentially erected,
The bridge has booms that are arranged on the existing deck side outside the deck replacement area, arranged in parallel in the width direction with an interval that exceeds at least the deck width, and are reversible and extendable in synchronization with the bridge axis direction, the tips of the booms are connected by a boom top beam, and a hanging part that is suspended from the boom top beam and has a swivel mechanism,
When removing the existing deck in the deck replacement area, the boom is directed toward the deck replacement area, and the existing deck to be removed is hung from the hanging section. The existing deck is then rotated 90 degrees by the rotating mechanism so that the longitudinal direction of the existing deck is oriented in the direction of the bridge axis. In this state, the boom is reversed, and the suspended existing deck is moved to a loading/unloading area outside the deck replacement area.
When erecting a new deck in the deck replacement area, the boom is directed toward the loading/unloading area, and the new deck with its longitudinal direction oriented in the bridge axis direction is hung from the hanging section, and then the boom is inverted toward the deck replacement area to move the hung new deck to the deck replacement area, and then the hung new deck is rotated 90 degrees by the rotating mechanism so that the longitudinal direction of the new deck is oriented in the width direction, and the new deck is erected in this state.This is a boom-reversal type deck erection machine.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2022023101A JP7744261B2 (en) | 2022-02-17 | 2022-02-17 | Deck replacement method and boom-reversal deck erection machine |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2022023101A JP7744261B2 (en) | 2022-02-17 | 2022-02-17 | Deck replacement method and boom-reversal deck erection machine |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2023119948A JP2023119948A (en) | 2023-08-29 |
| JP7744261B2 true JP7744261B2 (en) | 2025-09-25 |
Family
ID=87778341
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2022023101A Active JP7744261B2 (en) | 2022-02-17 | 2022-02-17 | Deck replacement method and boom-reversal deck erection machine |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP7744261B2 (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP7467751B1 (en) | 2023-10-19 | 2024-04-15 | 大成建設株式会社 | Construction equipment and assembly method for construction equipment |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2008050907A (en) | 2006-08-28 | 2008-03-06 | Yokogawa Bridge Holdings Corp | Bridge girder construction method and bridge girder construction device used for it |
| JP2009191458A (en) | 2008-02-12 | 2009-08-27 | Jfe Engineering Corp | Bridge erection device, floor slab erection method, and bridge erection method |
| JP2021143522A (en) | 2020-03-12 | 2021-09-24 | 岐阜工業株式会社 | Slab erection device |
-
2022
- 2022-02-17 JP JP2022023101A patent/JP7744261B2/en active Active
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2008050907A (en) | 2006-08-28 | 2008-03-06 | Yokogawa Bridge Holdings Corp | Bridge girder construction method and bridge girder construction device used for it |
| JP2009191458A (en) | 2008-02-12 | 2009-08-27 | Jfe Engineering Corp | Bridge erection device, floor slab erection method, and bridge erection method |
| JP2021143522A (en) | 2020-03-12 | 2021-09-24 | 岐阜工業株式会社 | Slab erection device |
Also Published As
| Publication number | Publication date |
|---|---|
| JP2023119948A (en) | 2023-08-29 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP7570481B2 (en) | Method for moving heavy objects using a heavy object moving device and a heavy object moving device | |
| CN115637658B (en) | Cantilever casting walking machine | |
| US5549176A (en) | Bridge construction machinery and method for constructing bridges | |
| JP5184248B2 (en) | Construction method of level crossing | |
| CN115613478B (en) | Continuous beam cantilever pouring method | |
| JP5890060B1 (en) | Bridge dismantling method using erection girder | |
| CN113882286A (en) | Bridge dismantling and building all-in-one machine and spanning method thereof, bridge dismantling method and new building method | |
| JP5484983B2 (en) | Method for assembling and dismantling bridge moving work device | |
| JP7744261B2 (en) | Deck replacement method and boom-reversal deck erection machine | |
| JP4489872B2 (en) | Bridge erection method and apparatus | |
| JP7630038B2 (en) | Deck replacement method | |
| JP3356048B2 (en) | Construction method of elevated structure using building girder | |
| JP2023074170A (en) | Floor slab replacement method and construction machine used therefor | |
| CN213653212U (en) | Self-propelled cast-in-place box girder integrated bridge construction machine | |
| JPS6041165B2 (en) | Equipment for cantilevering bridge structures made of reinforced concrete or prestressed concrete into sections. | |
| CN108130864A (en) | The whole bridge transport of overall assembled bridge sets up equipment and construction method | |
| JP7330411B2 (en) | Floor slab moving method and floor slab moving device | |
| JP2768281B2 (en) | Bridge construction method | |
| JP6627177B2 (en) | Construction method of vehicle-mounted lifter and pier | |
| JP3247138B2 (en) | Concrete construction equipment for dam construction | |
| CN114016422B (en) | Steel girder erection method | |
| JP2020122359A (en) | Floor slab erection system, additional floor slab installation method, and floor slab removing method | |
| CN118208240A (en) | A method for turning over and lowering a pressure steel pipe shaft | |
| CN114657895A (en) | A kind of prefabricated bridge integrated construction platform and construction method | |
| JP2026004047A (en) | Deck replacement construction system and deck replacement construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20241212 |
|
| TRDD | Decision of grant or rejection written | ||
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20250820 |
|
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20250826 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20250911 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 7744261 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |