JP7768170B2 - Method for preventing jamming in hot rolling of steel plate, hot rolling method using the same, and method for manufacturing steel plate - Google Patents
Method for preventing jamming in hot rolling of steel plate, hot rolling method using the same, and method for manufacturing steel plateInfo
- Publication number
- JP7768170B2 JP7768170B2 JP2023048205A JP2023048205A JP7768170B2 JP 7768170 B2 JP7768170 B2 JP 7768170B2 JP 2023048205 A JP2023048205 A JP 2023048205A JP 2023048205 A JP2023048205 A JP 2023048205A JP 7768170 B2 JP7768170 B2 JP 7768170B2
- Authority
- JP
- Japan
- Prior art keywords
- torque
- rolling
- steel plate
- pass
- hot rolling
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Control Of Metal Rolling (AREA)
Description
本発明は、鋼板の熱間圧延における噛み止めの防止方法、特にトルク制約値の自動補正による噛み止めの防止方法、この噛み止め防止方法を用いる熱間圧延方法及び鋼板の製造方法に関する。 The present invention relates to a method for preventing jamming during hot rolling of steel plate, in particular a method for preventing jamming by automatically correcting torque constraint values, and a hot rolling method and steel plate manufacturing method that use this jamming prevention method.
従来、厚板圧延機に代表される四重圧延機を用いた熱間圧延では、圧延能率最大化を目的として、圧延スケジュールが計算される。この計算では、各パスの予測温度や設定板厚を用いて、設備制約の最大荷重や最大トルク(以下、「トルク制約値」ともいう)を超えない範囲内で、各パスで最大の圧下量をとるよう計算されている(例えば、特許文献1参照)。 Conventionally, in hot rolling using a four-high rolling mill, such as a plate rolling mill, a rolling schedule is calculated with the aim of maximizing rolling efficiency. This calculation uses the predicted temperature and set plate thickness for each pass to achieve the maximum reduction amount for each pass without exceeding the maximum load and maximum torque (hereinafter also referred to as "torque constraint values") imposed by the equipment (see, for example, Patent Document 1).
したがって、実績の鋼板温度が予測した鋼板温度よりも低い場合、実績の変形抵抗が予測した変形抵抗よりも高くなる。その結果、ワークロールを回転させる主機モータの上限トルクに比べて、鋼板を圧下しながら送り出すのに必要なトルクが不足し、鋼板が圧延機内で停止してしまうことがある。これを「噛み止め」と呼ぶ。 Therefore, if the actual steel plate temperature is lower than the predicted steel plate temperature, the actual deformation resistance will be higher than the predicted deformation resistance. As a result, the torque required to feed the steel plate while compressing it will be insufficient compared to the upper limit torque of the main motor that rotates the work rolls, and the steel plate may stop inside the rolling mill. This is called "sticking."
そこで、従来、圧延作業員(以下、「オペレータ」ともいう)が圧延開始前及び圧延中にトルク制約値を減じる補正値を手動で入力して圧延スケジュールを再計算する「マイナストルク補正」とよばれる操作を行って、噛み止めを防止していた。 Therefore, in the past, rolling workers (hereinafter also referred to as "operators") would perform an operation called "minus torque correction," in which they manually input a correction value that subtracts from the torque constraint value before and during rolling, and recalculate the rolling schedule to prevent jamming.
前述したマイナストルク補正の操作は、オペレータがスラブ単重や1パス目の荷重外れのトン数、スラブ外観の色から判断するスラブの加熱の程度等の状況に基づき、補正の要否を判断し、必要な場合は補正値を決定している。この操作は手動で行うので、オペレータの技量差に影響される。 The negative torque correction mentioned above is performed by the operator, who determines whether correction is necessary based on factors such as the slab unit weight, the tonnage at which the load was removed on the first pass, and the degree of heating of the slab as judged from the external color of the slab, and if necessary, determines the correction value. Because this operation is performed manually, it is subject to differences in operator skill.
圧延トルクが当初の予測より外れ、その結果噛み止めが発生するリスクがあるとオペレータが判断し、例えばトルク制約値を-10%補正した場合には、圧延スケジュール計算における最大トルク値も-10%補正されて再計算され、最大圧下量が小さくなる。したがって、実際に発生するトルクは当初の最大トルク値の場合よりも小さくなるので、主機モータの上限を超えるトルクが作用しなくなる。その結果、この-10%補正によって、圧延途中の噛み止めトラブルを抑止できるが、各パスの圧下量が小さくなるので、圧延パスの合計数は増加してしまう。 If the rolling torque deviates from the initial prediction, and the operator determines that there is a risk of jamming as a result, and corrects the torque constraint value by, for example, -10%, the maximum torque value in the rolling schedule calculation will also be corrected by -10% and recalculated, reducing the maximum reduction amount. Therefore, the actually generated torque will be smaller than in the case of the initial maximum torque value, and torque that exceeds the upper limit of the main motor will no longer be applied. As a result, this -10% correction can prevent jamming problems during rolling, but because the reduction amount for each pass is smaller, the total number of rolling passes will increase.
このように、オペレータによるマイナストルク補正が、過剰である場合、圧延パス数が必要以上に増加して圧延能率が悪化し、逆にこの補正が不足である場合、噛み止めが発生する。 As such, if the operator applies excessive negative torque correction, the number of rolling passes increases more than necessary, reducing rolling efficiency; conversely, if this correction is insufficient, jamming occurs.
噛み止めが発生するとワークロールと高温の鋼板が長時間接触することによりワークロールにクラックが発生し、ワークロールの研削量が通常の10倍以上に増えることでワークロール原単位が悪化する。また、噛み止めが発生した鋼板は圧延続行が不可能と判断され、そのままスクラップとなり歩留が悪化する。また、圧延が停止すると圧延ラインのダウンタイムが発生する。 When jamming occurs, prolonged contact between the work roll and the hot steel plate causes cracks to form in the work roll, and the amount of work roll grinding increases by more than 10 times the normal amount, worsening the work roll consumption rate. Furthermore, steel plates with jamming are deemed unable to continue rolling and are scrapped, resulting in a decrease in yield. Furthermore, stopping rolling causes downtime for the rolling line.
本発明は、前述の諸々の課題を解決し、オペレータの手動によるマイナストルク補正ではなく、適切なトルク補正値を自動で計算する熱間圧延における噛み止めの防止方法を提供することを目的とする。 The present invention aims to solve the aforementioned problems and provide a method for preventing jamming in hot rolling by automatically calculating an appropriate torque correction value rather than manually performing negative torque correction by an operator.
また、本発明の他の目的は、前記噛み止めの防止方法を用いる鋼板の熱間圧延方法及び鋼板の製造方法を提供することにある。 Another object of the present invention is to provide a hot rolling method for steel plate and a method for manufacturing steel plate that use the above-mentioned method for preventing jamming.
本発明者らは、前述の課題を解決するために鋭意検討した。その結果、熱間圧延の前段のパスでのトルク外れ率を用いて後段のパスでの噛み止め発生の有無を予測した。この予測結果に基づき、後段のパスに対しトルク制約値を自動で補正して再度圧延スケジュール計算をすることが噛み止めの防止に対して有効との知見を得、本発明をなした。 The inventors conducted extensive research to solve the aforementioned problems. As a result, they used the torque deviation rate in the preceding passes of hot rolling to predict whether jamming would occur in the following passes. Based on these prediction results, they discovered that automatically correcting the torque constraint value for the following passes and recalculating the rolling schedule is effective in preventing jamming, leading to the creation of the present invention.
すなわち、本発明は、以下のとおりである。
[1] トルク制約値を用いて計算した圧延スケジュールに基づき圧延を行う鋼板の熱間圧延における噛み止めの防止方法であって、
前段のパス毎に圧延トルクを計算し、トルク外れ率を計算し、該計算の結果に基づいて後段の各パスに対しトルク制約値の補正を行い、補正されたトルク制約値を使用して圧延スケジュールの再計算をすることを特徴とする鋼板の熱間圧延における噛み止めの防止方法。
[2] 前記[1]において、前記前段のパスが、圧延開始から1~5パス目であることを特徴とする鋼板の熱間圧延における噛み止めの防止方法。
[3] 前記[1]又は[2]において、前記トルク外れ率は下記式(1)で計算し、下記式(2)の成立下で下記式(3)及び式(4)にてトルク制約値を補正することを特徴とする鋼板の熱間圧延における噛み止めの防止方法。
トルク外れ率=(実績トルク-予測トルク)/予測トルク ‥‥(1)
予測トルク×(1+トルク外れ率)>閾値 ‥‥(2)
トルク補正値=-{予測トルク×(1+トルク外れ率)-閾値}/補正前のトルク制約値 ‥‥(3)
補正後のトルク制約値=補正前のトルク制約値×(1+トルク補正値) ‥‥(4)
[4] 鋼板の熱間圧延方法において、前記[1]~[3]のいずれか一つに記載された噛み止めの防止方法を用いることを特徴とする鋼板の熱間圧延方法。
[5] 鋼板の製造方法において、前記[4]に記載された熱間圧延方法を用いることを特徴とする鋼板の製造方法。
That is, the present invention is as follows.
[1] A method for preventing jamming in hot rolling of a steel plate, the method comprising:
A method for preventing jamming in hot rolling of steel plate, characterized by calculating a rolling torque for each pass in the previous stage, calculating a torque deviation rate, correcting a torque constraint value for each pass in the subsequent stage based on the results of the calculation, and recalculating a rolling schedule using the corrected torque constraint value.
[2] The method for preventing jamming in hot rolling of a steel plate according to [1], wherein the preceding pass is one to five passes from the start of rolling.
[3] In the above [1] or [2], the torque deviation rate is calculated by the following formula (1), and the torque constraint value is corrected by the following formulas (3) and (4) under the condition that the following formula (2) is established.
Torque deviation rate = (actual torque - predicted torque) / predicted torque (1)
Predicted torque × (1 + torque deviation rate) > threshold (2)
Torque correction value = - {predicted torque x (1 + torque deviation rate) - threshold} / torque constraint value before correction (3)
Corrected torque constraint value = Pre-corrected torque constraint value × (1 + Torque correction value) (4)
[4] A method for hot rolling a steel plate, characterized in that the method for preventing jamming described in any one of [1] to [3] above is used.
[5] A method for producing a steel sheet, characterized in that the hot rolling method described in [4] above is used.
本発明に係る熱間圧延の噛み止め防止方法によれば、従来のオペレータの経験と勘に頼った手動操作によらず、適切なトルクの補正値を自動で計算して圧延スケジュールを再計算し圧延に適用することで、無用な圧延パス数の増加を防ぎつつ、噛み止めを防止できる。また、本発明に係る熱間圧延方法及び鋼板の製造方法によれば、圧延能率向上の効果とともに、ワークロール原単位の改善、歩留改善の効果が得られる。 The hot rolling jam prevention method of the present invention automatically calculates an appropriate torque correction value, recalculates the rolling schedule, and applies it to rolling, rather than relying on manual operations that rely on the experience and intuition of conventional operators. This prevents jamming while preventing an unnecessary increase in the number of rolling passes. Furthermore, the hot rolling method and steel plate manufacturing method of the present invention not only improve rolling efficiency, but also improve the work roll consumption rate and yield.
以下、本発明に係る鋼板の熱間圧延における噛み止め防止方法の実施形態について図1に示すフロー図を参照し説明する。このフロー図に沿った作業はプロセスコンピュータが実行する。
本発明ではまず、圧延スケジュール計算をする(ステップ100)。
An embodiment of a method for preventing jamming in hot rolling of a steel plate according to the present invention will be described below with reference to the flow chart shown in Figure 1. Operations according to this flow chart are executed by a process computer.
In the present invention, first, a rolling schedule is calculated (step 100).
[圧延スケジュール計算]
この計算では、各パスの予測温度や目標板厚を用いて、設備制約の最大荷重や最大トルクを超えない範囲で各パスで最大の圧下量が算出され、また、圧延トルク(以下、単に「トルク」ともいう)も算出される。
トルクの計算には下記式(5)が用いられる。
To=α×{RD×(入側板厚-出側板厚)}×0.5×(最大荷重) ‥‥(5)
ここで、Toはトルクであり、予測トルクともいう。RDは偏平ロール径で、RD=C×(上ワークロール径)/2、Cはロール偏平係数である。αはトルクアーム係数で、α=0.5+0.17×(出側板厚/RD)×0.5×{1-(入側板厚-出側板厚)/入側板厚}である。なお、単位は、トルク[t・m]、RD、入側板厚、出側板厚[mm]、最大荷重[t]である。
[Rolling schedule calculation]
In this calculation, the predicted temperature and target plate thickness for each pass are used to calculate the maximum reduction amount for each pass within a range that does not exceed the maximum load and maximum torque of the equipment constraints, and the rolling torque (hereinafter also simply referred to as "torque") is also calculated.
The torque is calculated using the following equation (5).
To=α×{RD×(Inlet side plate thickness - Outlet side plate thickness)}×0.5×(Maximum load) ‥‥(5)
Here, To is torque, also called predicted torque. RD is the flattening roll diameter, RD = C × (upper work roll diameter) / 2, and C is the roll flattening coefficient. α is the torque arm coefficient, α = 0.5 + 0.17 × (exit thickness / RD) × 0.5 × {1 - (entry thickness - exit thickness) / entry thickness}. The units are torque [t m], RD, entry thickness, exit thickness [mm], and maximum load [t].
[トルク制約値]
設備制約の最大トルク値であるトルク制約値の初期設定値は、通常圧延材と制御圧延材に対し、プロセスコンピュータ内で個別に定数が充当される。この定数は例えば、通常圧延材に対し300~400t・m、制御圧延材に対し300~400t・mが挙げられる。
圧延スケジュール計算の後、圧延を開始する(ステップ110)。圧延の開始後、パス順番、荷重及びトルクの実績を取得する(ステップ120)。実績パス順番が最終パスかの当否を判定し(ステップ130)、「当」(Y)ならば圧延終了し(ステップ190)、「否」(N)ならば前段パスかの当否を判定する(ステップ140)。
Torque Constraint Value
The initial setting of the torque constraint value, which is the maximum torque value of the equipment constraint, is assigned a constant value in the process computer for normal rolled material and controlled rolled material, for example, 300 to 400 t m for normal rolled material and 300 to 400 t m for controlled rolled material.
After the rolling schedule is calculated, rolling is started (step 110). After the start of rolling, the pass order, load, and torque results are acquired (step 120). It is determined whether the actual pass order is the final pass (step 130). If the result is "yes" (Y), rolling is terminated (step 190). If the result is "no" (N), it is determined whether the previous pass is correct (step 140).
[前段のパス]
ステップ140の「前段のパス」とは、圧延開始から順に区分される「調整パス」、「幅出しパス」及び「仕上げパス」のうち調整パス又は幅出しパスに含まれる少なくとも1つのパスを意味する。前記調整パスは、圧下量制約で各パスの圧下量が決定されるパスである。前記幅出しパスは、トルク値の制約で各パスの圧下量が決定されるパスであり、前記仕上げパスは、荷重制約・形状線の制約によって各パスの圧下量が決定されるパスである。
前記前段のパスは、圧延開始から1~5パス目とするのが好ましい。これにより、噛み止め及び無用なパス数増加を防止する効果がより十分なものとなる。
[Previous path]
The "previous pass" in step 140 refers to at least one pass included in the adjustment pass or the width setting pass among the "adjustment pass,""width setting pass," and "finishing pass" which are classified in order from the start of rolling. The adjustment pass is a pass in which the reduction amount of each pass is determined by the reduction amount constraint. The width setting pass is a pass in which the reduction amount of each pass is determined by the torque value constraint, and the finishing pass is a pass in which the reduction amount of each pass is determined by the load constraint and the shape line constraint.
The preceding passes are preferably the first to fifth passes from the start of rolling, which provides a more sufficient effect of preventing jamming and unnecessary increase in the number of passes.
前段のパスを1~5パス目とするのが好適な理由を以下に述べる。噛み止めは経験上、主に幅出し圧延時に発生する。幅出し圧延時は、圧延中に最もワークロールと鋼板の接触面積が大きく圧延時のトルクが大きくなりやすいためである。幅出し圧延は、通常、3パス目から開始し、6~8パス目で終了する。したがって、前記前段のパスを6パス目以降とした場合、補正の時機を失して噛み止めの発生防止が困難である。
ステップ140の前段のパスかの当否判定が「否」(N)ならば、パス順番を1つ増してステップ120へ飛び、「当」(Y)ならばトルク外れ率を計算する(ステップ150)。
The reason why the first to fifth passes are preferable as the first pass is as follows. Experience has shown that jamming occurs mainly during width setting rolling. This is because, during width setting rolling, the contact area between the work roll and the steel sheet is the largest during rolling, and the torque during rolling is likely to be large. Width setting rolling usually starts from the third pass and ends between the sixth and eighth passes. Therefore, if the first pass is set to the sixth pass or later, the opportunity for correction will be missed, making it difficult to prevent jamming from occurring.
If the pass determination in the previous step of step 140 is "No" (N), the pass order is incremented by one and the process jumps to step 120, and if it is "Yes" (Y), the torque deviation rate is calculated (step 150).
[トルク外れ率]
ステップ150におけるトルク外れ率は、例えば下記式(1)で計算する。
トルク外れ率=(実績トルク-予測トルク)/予測トルク ‥‥(1)
ここで、実績トルクは、式(5)の最大荷重に実績荷重を代入して求められる。予定荷重は、各パスの予測温度と変形抵抗から計算される。
[Torque deviation rate]
The torque deviation rate in step 150 is calculated, for example, by the following formula (1).
Torque deviation rate = (actual torque - predicted torque) / predicted torque (1)
Here, the actual torque is obtained by substituting the actual load for the maximum load in equation (5). The expected load is calculated from the predicted temperature and deformation resistance of each pass.
[トルク制約値の補正の要否]
前記トルク外れ率の計算結果に基づいて後段のパスでのトルク制約値の補正の要否を判定し(ステップ160)、「否」(N)ならば、パス順番を1つ増してステップ120へ飛ぶ。
前記「後段のパス」とは、前段のパスよりも後の少なくとも1つのパスを意味する。
前記補正の要否判定には、例えば下記式(2)を用いる。
予測トルク×(1+トルク外れ率)>閾値 ‥‥(2)
式(2)における予測トルクは、後段のパスでのものである。式(2)の左辺は、前段のパスでのトルク外れ率が、後段のパスでも維持されるとして、後段のパスで推定されるトルクである。この推定は、過去の圧延操業実績の解析結果から裏付けられた。
[Whether or not correction of torque constraint value is necessary]
Based on the calculation result of the torque deviation rate, it is determined whether or not the torque constraint value needs to be corrected in the subsequent pass (step 160). If the answer is "No" (N), the pass order is incremented by one and the process jumps to step 120.
The "subsequent path" means at least one path subsequent to the preceding path.
The necessity of correction is determined using, for example, the following equation (2).
Predicted torque × (1 + torque deviation rate) > threshold (2)
The predicted torque in equation (2) is that for the subsequent pass. The left side of equation (2) is the torque estimated for the subsequent pass, assuming that the torque deviation rate for the previous pass is maintained for the subsequent pass. This estimation was supported by the results of analysis of past rolling operation results.
前記推定されるトルクが高いと、噛み止めのリスクが大きい。そこで、前記推定されるトルクと比較する閾値を設定し、前記推定されるトルクが閾値超のとき、噛み止めのリスクが高いとして、トルク制約値の補正「要」と判定する。 When the estimated torque is high, the risk of jamming is high. Therefore, a threshold value is set for comparison with the estimated torque, and when the estimated torque exceeds the threshold value, it is determined that the risk of jamming is high and that correction of the torque constraint value is required.
[閾値]
前記閾値は、圧延材種が、スラブ長:4~5m、スラブ抽出温度:1050~1150℃及び鋼種:N11LXR(日本海事協会NK規格、40A、40D、40E相当)の場合の例として370t・mが挙げられる。この例の閾値は次のようにして決定した。すなわち、過去の圧延操業実績の解析から最大計算トルク区分に対するパス数の分布と、噛み止めが発生したことがある範囲とを求め、図4を得た。図4から、最大計算トルクが370t・m以下では噛み止めが発生していないことがわかる。よって、この例における閾値は370t・mとした。
[Threshold]
An example of the threshold value is 370 t·m when the rolling material type is N11LXR (equivalent to Nippon Kaiji Kyokai NK standard 40A, 40D, or 40E) with a slab length of 4 to 5 m, a slab extraction temperature of 1050 to 1150°C, and a steel type of N11LXR. The threshold value for this example was determined as follows. That is, the distribution of the number of passes for each maximum calculated torque category and the range in which jamming has occurred were determined from an analysis of past rolling operation results, and Figure 4 was obtained. From Figure 4, it can be seen that jamming does not occur when the maximum calculated torque is 370 t·m or less. Therefore, the threshold value for this example was set to 370 t·m.
なお、図4の例では、スラブ長:4~5m、スラブ抽出温度:1050~1150℃及び鋼種:N11LXRの条件の場合である。これらの条件の少なくともいずれか1つがこの例の範囲から外れると、370t・mとは異なる閾値が適正となる場合がある。そのように条件が異なる場合の適正な閾値の全体は、300~400t・mの範囲である。したがって、閾値は、スラブ長、スラブ抽出温度及び鋼種の内の少なくともいずれか1つの関数として設定することが好ましい。 The example in Figure 4 is for the following conditions: slab length: 4-5 m, slab extraction temperature: 1050-1150°C, and steel type: N11LXR. If at least one of these conditions falls outside the range of this example, a threshold value other than 370 t·m may be appropriate. When conditions differ in this way, the overall appropriate threshold value is in the range of 300-400 t·m. Therefore, it is preferable to set the threshold value as a function of at least one of slab length, slab extraction temperature, and steel type.
例えば、鋼種ごとに、複数に区分したスラブ長及びスラブ抽出温度と対応する閾値との関係をテーブルの形式で準備しておき、このテーブルから、実際の圧延材の鋼種、スラブ長及びスラブ抽出温度に対応する閾値を選定するようにしてもよい。 For example, the relationship between multiple slab lengths and slab extraction temperatures and corresponding threshold values for each steel type can be prepared in the form of a table, and the threshold value corresponding to the actual steel type, slab length, and slab extraction temperature of the rolled material can be selected from this table.
[トルク制約値の補正]
トルク制約値の補正の要否が[要](Y)ならば、後段のパスに用いるトルク制約値を補正する(ステップ170)。これには、例えば下記式(3)及び(4)を用いる。
トルク補正値=-{予測トルク×(1+トルク外れ率)-閾値}/補正前のトルク制約値 ‥‥(3)
補正後のトルク制約値=補正前のトルク制約値×(1+トルク補正値) ‥‥(4)
ここで、式(3)における「補正前のトルク制約値」は、前述のように、通常圧延材に対し300~400t・m、制御圧延材に対し300~400t・mが挙げられる。
[Torque Constraint Value Correction]
If the torque constraint value correction is necessary (Y), the torque constraint value used in the subsequent pass is corrected (step 170). For this, for example, the following equations (3) and (4) are used.
Torque correction value = - {predicted torque x (1 + torque deviation rate) - threshold} / torque constraint value before correction (3)
Corrected torque constraint value = Pre-corrected torque constraint value × (1 + Torque correction value) (4)
Here, the "torque constraint value before correction" in equation (3) is, as mentioned above, 300 to 400 t·m for normal rolled material and 300 to 400 t·m for controlled rolled material.
[圧延スケジュール再計算]
そして、式(4)で得られた補正後のトルク制約値を用いて、圧延スケジュール再計算を行う(ステップ180)。
圧延スケジュール再計算後は、パス順番を1つ増してステップ120へ飛ぶ。よって、後段のパスでは、再計算後の圧延スケジュールに基づいて圧延が継続される。
[Rolling schedule recalculation]
Then, the rolling schedule is recalculated using the corrected torque constraint value obtained by equation (4) (step 180).
After the rolling schedule is recalculated, the pass order is incremented by one and the process jumps to step 120. Therefore, in the subsequent passes, rolling continues based on the recalculated rolling schedule.
本発明の熱間圧延方法は、本発明の噛み止めの防止方法を用いたものであり、これにより、噛み止めの発生を防止でき、その結果、圧延能率が向上し、ワークロール原単位が向上する。 The hot rolling method of the present invention uses the method for preventing jamming of the present invention, which prevents jamming from occurring, resulting in improved rolling efficiency and improved work roll consumption.
また、本発明の鋼板の製造方法は、本発明の熱間圧延方法を用いたものであり、これにより、噛み止めによる鋼板のスクラップ化が防止でき、その結果、鋼板の製品歩留りが向上する。 In addition, the steel plate manufacturing method of the present invention uses the hot rolling method of the present invention, which prevents steel plates from being scrapped due to jamming, thereby improving the product yield of steel plates.
[実施例1]
実施例1では、鋼種:N11LXR、スラブ寸法:245mm×1904mm×2680mm、圧延命令寸法:10.2mm×4151mm×40600mm、スラブ抽出温度:1120℃の場合の例である。
[Example 1]
Example 1 is an example in which the steel type is N11LXR, the slab dimensions are 245 mm x 1904 mm x 2680 mm, the rolling order dimensions are 10.2 mm x 4151 mm x 40600 mm, and the slab extraction temperature is 1120°C.
前段のパスは1~5パス目とした。鋼板は通常圧延材で、トルク制約値の初期設定値は326t・mとした。トルク外れ率の計算には前記式(1)を用い、トルク制約値の補正の要否判定には前記式(2)を用い、閾値は370t・mとした。トルク補正値の計算には前記式(3)を用い、補正後のトルク制約値の計算には前記式(4)を用いた。 The first pass was set to passes 1 to 5. The steel plate was a conventionally rolled material, and the initial setting for the torque constraint value was set to 326 t·m. The torque deviation rate was calculated using formula (1), and the threshold value was set to 370 t·m to determine whether correction to the torque constraint value was necessary using formula (2). The torque correction value was calculated using formula (3), and the corrected torque constraint value was calculated using formula (4).
圧延開始後、3パス目でトルク制約値の補正「要」となったので、トルク補正値の計算、トルク制約値の補正、圧延スケジュール再計算を順次実行し、第4パス以降は、再計算後の圧延スケジュールに基づいて圧延を行った。 After rolling began, it was determined that correction of the torque constraint value was "necessary" on the third pass, so the torque correction value was calculated, the torque constraint value was corrected, and the rolling schedule was recalculated in that order, and from the fourth pass onwards, rolling was carried out based on the recalculated rolling schedule.
このときの、当初予定荷重、予定荷重及び実績荷重の推移を図3に示す。ここで、横軸の板厚は圧延開始からの各パスの出側板厚である。また、当初予定荷重とは、当初の圧延スケジュール計算での予測荷重であり、再スケ後予定荷重とは圧延スケジュール再計算での予測荷重である。なお、この例では、当初、全14パスで、1及び2パス目が前記調整パス、3~7パス目が前記幅出しパス、8~14パス目が前記仕上げパスであったが、再スケ後は、前記15パスで、3~8パス目が前記幅出しパス、9~15パス目が前記仕上げパスとなった。 Figure 3 shows the changes in the initial planned load, planned load, and actual load at this time. Here, the plate thickness on the horizontal axis is the delivery plate thickness for each pass from the start of rolling. The initial planned load is the predicted load in the initial rolling schedule calculation, and the planned load after rescheduling is the predicted load in the recalculated rolling schedule. In this example, initially, of the 14 passes, the first and second passes were the adjustment passes, the third to seventh passes were the width setting passes, and the eighth to fourteenth passes were the finishing passes. However, after rescheduling, of the 15 passes, the third to eighth passes were the width setting passes, and the ninth to fifteenth passes were the finishing passes.
図3に示されるとおり、実施例1では、3パス目で実績荷重が当初予定荷重より高く外れ、この成り行きでは4パス目以降で圧延時の荷重がさらに増大し、トルク不足となって噛み止めが発生するリスクが高いと自動で判定した。そこで、前述のとおりトルク外れ率を用いてトルク制約値を自動で補正して圧延スケジュール再計算を行い、4パス目以降は再計算後の圧延スケジュールに基づき圧延し、噛み止めを防止できた。 As shown in Figure 3, in Example 1, the actual load in the third pass deviated higher than the initially planned load, and if this continued, the load during rolling would increase further from the fourth pass onwards, resulting in a high risk of torque shortage and jamming. Therefore, as described above, the torque constraint value was automatically corrected using the torque deviation rate, and the rolling schedule was recalculated. From the fourth pass onwards, rolling was carried out based on the recalculated rolling schedule, preventing jamming.
[実施例2]
実施例2では、通常圧延材で仕上げ板厚が20~30mmの範囲の鋼板を対象とした。従来は、オペレータが前述のマイナストルク補正を行っていた。実施例2と従来とで、トルク補正値及びパス数を比較した。圧延本数は、実施例2が1箇月分の合計で2000本、従来が3箇月分の合計で6000本である。トルク補正値、圧延パス数とも、圧延本数の全域にわたる合計を圧延本数で除した平均値で示した。その結果を図5に示す。
[Example 2]
In Example 2, steel plates of normally rolled material with a finished thickness in the range of 20 to 30 mm were targeted. Conventionally, the operator performed the above-mentioned negative torque correction. The torque correction values and number of passes were compared between Example 2 and the conventional method. The number of rolled pieces was 2,000 pieces in total for one month in Example 2, and 6,000 pieces in total for three months in the conventional method. Both the torque correction value and the number of rolling passes were shown as average values obtained by dividing the total across the entire range of the number of rolled pieces by the number of rolled pieces. The results are shown in Figure 5.
図5に示すとおり、実施例2では、トルク補正値が従来より5.5ポイント増加し、パス数が従来より0.7パス減少した。これにより、圧延能率が約22t/h改善した。 As shown in Figure 5, in Example 2, the torque correction value increased by 5.5 points and the number of passes decreased by 0.7 passes compared to the conventional method. This resulted in an improvement in rolling efficiency of approximately 22 t/h.
また、従来では、ワークロールのクラック発生頻度が最大で約6回/月であったのに対し、実施例2では1回/月未満と格段に低減した(図示せず)。 In addition, whereas the frequency of cracks occurring in the work rolls in the conventional method was a maximum of approximately six times per month, in Example 2 this was significantly reduced to less than one time per month (not shown).
100、110、120、130、140、150、160、170、180、190 ステップ 100, 110, 120, 130, 140, 150, 160, 170, 180, 190 steps
Claims (4)
前段のパス毎に圧延トルクを計算し、トルク外れ率を計算し、該計算の結果に基づいて後段の各パスに対しトルク制約値の補正を行い、補正されたトルク制約値を使用して圧延スケジュールの再計算をするにあたり、
前記トルク外れ率は下記式(1)で計算し、下記式(2)の成立下で下記式(3)及び式(4)にてトルク制約値を補正することを特徴とする鋼板の熱間圧延における噛み止めの防止方法。
トルク外れ率=(実績トルク-予測トルク)/予測トルク ‥‥(1)
予測トルク×(1+トルク外れ率)>閾値 ‥‥(2)
トルク補正値=-{予測トルク×(1+トルク外れ率)-閾値}/補正前のトルク制約値 ‥‥(3)
補正後のトルク制約値=補正前のトルク制約値×(1+トルク補正値) ‥‥(4) A method for preventing jamming in hot rolling of a steel plate, the method comprising:
Calculating the rolling torque for each pass in the preceding stage, calculating the torque deviation rate, correcting the torque constraint value for each pass in the subsequent stage based on the calculation results, and recalculating the rolling schedule using the corrected torque constraint value,
A method for preventing jamming in hot rolling of a steel plate, characterized in that the torque deviation rate is calculated by the following formula (1), and the torque constraint value is corrected by the following formulas (3) and (4) when the following formula (2) is satisfied.
Torque deviation rate = (actual torque - predicted torque) / predicted torque (1)
Predicted torque × (1 + torque deviation rate) > threshold (2)
Torque correction value = - {predicted torque x (1 + torque deviation rate) - threshold} / torque constraint value before correction (3)
Corrected torque constraint value = Pre-corrected torque constraint value × (1 + Torque correction value) (4)
A method for producing a steel sheet, comprising using the hot rolling method according to claim 3 .
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2023048205A JP7768170B2 (en) | 2023-03-24 | 2023-03-24 | Method for preventing jamming in hot rolling of steel plate, hot rolling method using the same, and method for manufacturing steel plate |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2023048205A JP7768170B2 (en) | 2023-03-24 | 2023-03-24 | Method for preventing jamming in hot rolling of steel plate, hot rolling method using the same, and method for manufacturing steel plate |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2024136901A JP2024136901A (en) | 2024-10-04 |
| JP7768170B2 true JP7768170B2 (en) | 2025-11-12 |
Family
ID=92911336
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2023048205A Active JP7768170B2 (en) | 2023-03-24 | 2023-03-24 | Method for preventing jamming in hot rolling of steel plate, hot rolling method using the same, and method for manufacturing steel plate |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP7768170B2 (en) |
Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2001259719A (en) | 2000-03-21 | 2001-09-25 | Nkk Corp | Rolling mill setting calculation method |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS623815A (en) * | 1985-06-27 | 1987-01-09 | Kawasaki Steel Corp | Method for predicting spindle torque of rolling mill |
| JPH10137825A (en) * | 1996-11-07 | 1998-05-26 | Toshiba Corp | Path schedule determination device |
-
2023
- 2023-03-24 JP JP2023048205A patent/JP7768170B2/en active Active
Patent Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2001259719A (en) | 2000-03-21 | 2001-09-25 | Nkk Corp | Rolling mill setting calculation method |
Also Published As
| Publication number | Publication date |
|---|---|
| JP2024136901A (en) | 2024-10-04 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| EP3928885B1 (en) | Rolling load predicting method, rolling load predicting device, and rolling control method | |
| EP2465620B1 (en) | Method for cooling hot-rolled steel strip | |
| KR101242841B1 (en) | Method and apparatus for roughing mill of thick steel sheet | |
| EP4035787B1 (en) | Method for rolling super austenitic stainless steel | |
| CN111389928B (en) | Method for producing ultrathin and ultra-wide limit specification nuclear power steel by wide and thick plate rolling mill | |
| KR20130099091A (en) | Method for producing steel strips by continuous rolling or semi-continuous rolling | |
| JP2025129388A (en) | Calculation method for thickness schedule of tandem rolling mill | |
| JP7768170B2 (en) | Method for preventing jamming in hot rolling of steel plate, hot rolling method using the same, and method for manufacturing steel plate | |
| CN113617850A (en) | Control method for improving surface quality of hot-rolled mild steel | |
| JP7141995B2 (en) | Hot-rolled steel sheet manufacturing method and hot-rolled steel sheet manufacturing system | |
| JP6354722B2 (en) | Trimming material trimming method and trimming apparatus | |
| JP4311058B2 (en) | Thick steel plate rolling method | |
| JP4701762B2 (en) | Hot rolled steel sheet rolling method | |
| JP5854177B1 (en) | Hot rolling method for high carbon steel | |
| JP2019072757A (en) | Leveling setting method of rolling mill, leveling setting device of rolling mill and manufacturing method of steel plate | |
| CN119426378B (en) | Rolling width control method based on continuous optimization of side pressure strategy | |
| JP3661691B2 (en) | Continuous casting method of high carbon special steel | |
| JP3156568B2 (en) | Cold rolling method | |
| JP2006051512A (en) | Method for controlling material width in hot rolling and method for producing hot rolled metal sheet | |
| JP3845345B2 (en) | Hot slab width reduction method | |
| EP4537951A1 (en) | Cold rolling equipment, steel plate manufacturing equipment, cold rolling method, and steel plate manufacturing method | |
| JP5152791B2 (en) | Method for producing Cr-Ni type stainless steel strip capable of preventing occurrence of ear cracks in hot rolling | |
| CN119566071A (en) | A method for preventing edge quality defects of hot-rolled strip steel | |
| JPH06102202B2 (en) | Rolling method for U-shaped steel sheet pile | |
| CN117772786A (en) | A method for hot rolling deformation and re-rolling of furnace billets |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20241031 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20250725 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20250729 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20250911 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20250930 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20251013 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 7768170 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |