JP7787657B2 - Power outage cause notification system, breaker, power outage cause notification method and program - Google Patents
[go: Go Back, main page]

JP7787657B2 - Power outage cause notification system, breaker, power outage cause notification method and program - Google Patents

Power outage cause notification system, breaker, power outage cause notification method and program

Info

Publication number
JP7787657B2
JP7787657B2 JP2021106080A JP2021106080A JP7787657B2 JP 7787657 B2 JP7787657 B2 JP 7787657B2 JP 2021106080 A JP2021106080 A JP 2021106080A JP 2021106080 A JP2021106080 A JP 2021106080A JP 7787657 B2 JP7787657 B2 JP 7787657B2
Authority
JP
Japan
Prior art keywords
power outage
cause
terminal
breaker
power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2021106080A
Other languages
Japanese (ja)
Other versions
JP2023004429A (en
Inventor
修平 田中
史迅 大垣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Panasonic Corp
Panasonic Holdings Corp
Original Assignee
Panasonic Corp
Matsushita Electric Industrial Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Panasonic Corp, Matsushita Electric Industrial Co Ltd filed Critical Panasonic Corp
Priority to JP2021106080A priority Critical patent/JP7787657B2/en
Publication of JP2023004429A publication Critical patent/JP2023004429A/en
Application granted granted Critical
Publication of JP7787657B2 publication Critical patent/JP7787657B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Emergency Alarm Devices (AREA)
  • Breakers (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Distribution Board (AREA)

Description

本開示は、停電原因通知システム、ブレーカ、停電原因通知方法及びプログラムに関し、より詳細には、停電の原因に関する情報を顧客に通知する停電原因通知システム、ブレーカ、停電原因通知方法及びプログラムに関する。 This disclosure relates to a power outage cause notification system, a breaker, a power outage cause notification method, and a program, and more specifically to a power outage cause notification system, a breaker, a power outage cause notification method, and a program that notify customers of information regarding the cause of a power outage.

特許文献1には、顧客端末に対し、発生した停電に関する停電情報をサーバ装置により通知する停電情報通知システムが記載されている。通知される停電情報には、停電時間及び停電原因が含まれる。 Patent Document 1 describes a power outage information notification system that uses a server device to notify customer terminals of power outage information related to power outages that have occurred. The notified power outage information includes the duration and cause of the outage.

特開2007-336692号公報Japanese Patent Application Laid-Open No. 2007-336692

しかし、停電には、電力系統に起因する広範囲の停電(以下、系統停電)と、個々の顧客宅のブレーカの動作に起因する宅内の停電(以下、宅内停電)とがある。特許文献1の停電原因通知システムは、系統停電について、停電原因等の情報を通知するものであり、宅内停電も含む停電の原因に関する原因情報を個々の顧客に通知することは行っていない。 However, there are two types of power outages: widespread power outages caused by the power grid (hereinafter referred to as grid power outages), and in-home power outages caused by the operation of breakers in individual customer homes (hereinafter referred to as in-home power outages). The power outage cause notification system in Patent Document 1 notifies information about the cause of power outages, including in-home power outages, for grid power outages, but does not notify individual customers of information about the cause of power outages, including in-home power outages.

本開示の目的は、個々の顧客に対して、宅内停電も含む停電の原因に関する原因情報を容易に通知できる、停電原因通知システム、ブレーカ、停電原因通知方法及びプログラムを提供することである。 The purpose of this disclosure is to provide a power outage cause notification system, breaker, power outage cause notification method, and program that can easily notify individual customers of information regarding the cause of a power outage, including in-home power outages.

本開示の一態様に係る停電原因通知システムは、ブレーカに付随して用いられる。前記ブレーカは、電力系統と顧客の宅内の負荷との間の電路に介在する。前記ブレーカは、停電の発生時に、前記顧客の端末と通信可能に接続される。前記停電原因通知システムは、前記停電の原因を前記ブレーカから前記端末を介して前記顧客に通知する。前記端末には、アプリケーションソフトウェアがインストールされている。前記アプリケーションソフトウェアは、少なくとも前記停電の原因を通知する。前記停電原因通知システムは、起動部と、取得部と、出力部と、電源部と、受付部と、を備える。前記起動部は、前記停電の発生時に、前記端末の前記アプリケーションソフトウェアを起動する。前記取得部は、前記停電の発生時に、停電情報を取得する。前記停電情報は、原因情報を少なくとも含む。前記原因情報は、前記停電が、系統停電か、宅内停電か、を示す。前記系統停電は、前記電力系統に起因する停電である。前記宅内停電は、前記ブレーカがトリップ状態となったことに起因する停電である。前記出力部は、前記取得部が取得した前記停電情報を、前記起動部が起動した前記アプリケーションソフトウェアに引き渡す。前記電源部は、前記系統停電の発生時に、少なくとも前記起動部、前記取得部及び前記出力部に電力を供給する。前記受付部は、前記ブレーカを前記端末と通信可能に接続するための接続操作を受け付ける。前記ブレーカは、前記接続操作に応じて前記端末と通信可能に接続される。
本開示の一態様に係る停電原因通知システムは、ブレーカに付随して用いられる。前記ブレーカは、電力系統と顧客の宅内の負荷との間の電路に介在する。前記ブレーカは、停電の発生時に、前記顧客の端末と通信可能に接続される。前記停電原因通知システムは、前記停電の原因を前記ブレーカから前記端末を介して前記顧客に通知する。前記端末には、アプリケーションソフトウェアがインストールされている。前記アプリケーションソフトウェアは、少なくとも前記停電の原因を通知する。前記停電原因通知システムは、起動部と、取得部と、出力部と、電源部と、を備える。前記起動部は、前記停電の発生時に、前記端末の前記アプリケーションソフトウェアを起動する。前記取得部は、前記停電の発生時に、停電情報を取得する。前記停電情報は、原因情報を少なくとも含む。前記原因情報は、前記停電が、系統停電か、宅内停電か、を示す。前記系統停電は、前記電力系統に起因する停電である。前記宅内停電は、前記ブレーカがトリップ状態となったことに起因する停電である。前記出力部は、前記取得部が取得した前記停電情報を、前記起動部が起動した前記アプリケーションソフトウェアに引き渡す。前記電源部は、前記系統停電の発生時に、少なくとも前記起動部、前記取得部及び前記出力部に電力を供給する。前記端末は、サーバと常時通信可能に接続される。前記サーバは、前記端末の前記アプリケーションソフトウェアを通じて前記顧客への情報提供を行う。前記ブレーカは、前記サーバと常時通信可能に接続される。前記サーバが前記起動部を備え、前記サーバの前記起動部は、前記ブレーカと前記サーバの間の接続が切断されたことに応じて、前記端末の前記アプリケーションソフトウェアを起動する。
A power outage cause notification system according to one aspect of the present disclosure is used in conjunction with a breaker. The breaker is located in an electric circuit between a power grid and a load in a customer's home. The breaker is communicably connected to a terminal of the customer when a power outage occurs. The power outage cause notification system notifies the customer of the cause of the power outage from the breaker via the terminal. Application software is installed on the terminal. The application software notifies the customer of at least the cause of the power outage. The power outage cause notification system includes a launching unit, an acquisition unit, an output unit , a power supply unit, and a reception unit . The launching unit launches the application software on the terminal when the power outage occurs. The acquisition unit acquires power outage information when the power outage occurs. The power outage information includes at least cause information. The cause information indicates whether the power outage is a grid power outage or a home power outage. The grid power outage is a power outage caused by the power grid. The home power outage is a power outage caused by the breaker being tripped. The output unit passes the power outage information acquired by the acquisition unit to the application software launched by the launching unit. The power supply unit supplies power to at least the startup unit, the acquisition unit, and the output unit when the grid power outage occurs. The reception unit receives a connection operation for connecting the breaker to the terminal so that the breaker can communicate with the terminal in response to the connection operation.
A power outage cause notification system according to one aspect of the present disclosure is used in conjunction with a breaker. The breaker is located in an electric circuit between a power grid and a load in a customer's home. The breaker is communicatively connected to a terminal of the customer when a power outage occurs. The power outage cause notification system notifies the customer of the cause of the power outage from the breaker via the terminal. Application software is installed on the terminal. The application software notifies the customer of at least the cause of the power outage. The power outage cause notification system includes a launching unit, an acquisition unit, an output unit, and a power supply unit. The launching unit launches the application software on the terminal when the power outage occurs. The acquisition unit acquires power outage information when the power outage occurs. The power outage information includes at least cause information. The cause information indicates whether the power outage is a grid power outage or a home power outage. The grid power outage is a power outage caused by the power grid. The home power outage is a power outage caused by the breaker being tripped. The output unit passes the power outage information acquired by the acquisition unit to the application software launched by the launching unit. The power supply unit supplies power to at least the startup unit, the acquisition unit, and the output unit when the grid power outage occurs. The terminal is connected to a server so as to be able to communicate at all times. The server provides information to the customer through the application software of the terminal. The breaker is connected to the server so as to be able to communicate at all times. The server includes the startup unit, and the startup unit of the server starts the application software of the terminal in response to the connection between the breaker and the server being cut off.

本開示の一態様に係るブレーカは、電力系統と顧客の宅内の負荷との間の電路に介在し、少なくとも停電の発生時に顧客の端末と通信可能に接続されて、前記停電の原因を前記顧客に前記端末を介して通知する。前記端末には、アプリケーションソフトウェアがインストールされている。前記アプリケーションソフトウェアは、少なくとも前記停電の原因を通知する。前記ブレーカは、起動部と、取得部と、出力部と、電源部と、受付部と、を備える。前記起動部は、前記停電の発生時に、前記端末の前記アプリケーションソフトウェアを起動する。前記取得部は、前記停電の発生時に、停電情報を取得する。前記停電情報は、原因情報を少なくとも含む。前記原因情報は、前記停電が、系統停電か、宅内停電か、を示す。前記系統停電は、前記電力系統に起因する停電である。前記宅内停電は、前記ブレーカ自身がトリップ状態となったことに起因する停電である。前記出力部は、前記取得部が取得した前記停電情報を、前記起動部が起動した前記アプリケーションソフトウェアに引き渡す。前記電源部は、前記系統停電の発生時に、少なくとも前記起動部、前記取得部及び前記出力部に電力を供給する。前記受付部は、前記ブレーカを前記端末と通信可能に接続するための接続操作を受け付ける。前記ブレーカは、前記接続操作に応じて前記端末と通信可能に接続される。
本開示の一態様に係るブレーカは、電力系統と顧客の宅内の負荷との間の電路に介在し、少なくとも停電の発生時に顧客の端末と通信可能に接続されて、前記停電の原因を前記顧客に前記端末を介して通知する。前記端末には、アプリケーションソフトウェアがインストールされている。前記アプリケーションソフトウェアは、少なくとも前記停電の原因を通知する。前記ブレーカは、起動部と、取得部と、出力部と、電源部と、を備える。前記起動部は、前記停電の発生時に、前記端末の前記アプリケーションソフトウェアを起動する。前記取得部は、前記停電の発生時に、停電情報を取得する。前記停電情報は、原因情報を少なくとも含む。前記原因情報は、前記停電が、系統停電か、宅内停電か、を示す。前記系統停電は、前記電力系統に起因する停電である。前記宅内停電は、前記ブレーカ自身がトリップ状態となったことに起因する停電である。前記出力部は、前記取得部が取得した前記停電情報を、前記起動部が起動した前記アプリケーションソフトウェアに引き渡す。前記電源部は、前記系統停電の発生時に、少なくとも前記起動部、前記取得部及び前記出力部に電力を供給する。前記端末は、サーバと常時通信可能に接続される。前記サーバは、前記端末の前記アプリケーションソフトウェアを通じて前記顧客への情報提供を行う。前記ブレーカは、前記サーバと常時通信可能に接続される。前記サーバが前記起動部を備え、前記サーバの前記起動部は、前記ブレーカと前記サーバの間の接続が切断されたことに応じて、前記端末の前記アプリケーションソフトウェアを起動する。
A breaker according to one aspect of the present disclosure is interposed in an electric circuit between a power grid and a load in a customer's home, and is communicatively connected to a customer's terminal at least when a power outage occurs, and notifies the customer of the cause of the power outage via the terminal. Application software is installed on the terminal. The application software notifies the customer of at least the cause of the power outage. The breaker includes a startup unit, an acquisition unit, an output unit , a power supply unit, and a reception unit . The startup unit starts the application software on the terminal when the power outage occurs. The acquisition unit acquires power outage information when the power outage occurs. The power outage information includes at least cause information. The cause information indicates whether the power outage is a grid power outage or a home power outage. The grid power outage is a power outage caused by the power grid. The home power outage is a power outage caused by the breaker itself being tripped. The output unit passes the power outage information acquired by the acquisition unit to the application software started by the startup unit. The power supply unit supplies power to at least the startup unit, the acquisition unit, and the output unit when the grid power outage occurs. The receiving unit receives a connection operation for connecting the breaker to the terminal so that the breaker can communicate with the terminal in response to the connection operation.
A breaker according to one aspect of the present disclosure is interposed in an electric circuit between a power grid and a load in a customer's home, and is communicatively connected to a customer's terminal at least when a power outage occurs, and notifies the customer of the cause of the power outage via the terminal. Application software is installed on the terminal. The application software notifies the customer of at least the cause of the power outage. The breaker includes a startup unit, an acquisition unit, an output unit, and a power supply unit. The startup unit starts the application software on the terminal when the power outage occurs. The acquisition unit acquires power outage information when the power outage occurs. The power outage information includes at least cause information. The cause information indicates whether the power outage is a grid power outage or a home power outage. The grid power outage is a power outage caused by the power grid. The home power outage is a power outage caused by the breaker itself being tripped. The output unit passes the power outage information acquired by the acquisition unit to the application software started by the startup unit. The power supply unit supplies power to at least the startup unit, the acquisition unit, and the output unit when the grid power outage occurs. The terminal is connected to a server so as to be able to communicate at all times. The server provides information to the customer through the application software of the terminal. The breaker is connected to the server so as to be able to communicate at all times. The server includes the startup unit, and the startup unit of the server starts the application software of the terminal in response to the connection between the breaker and the server being cut off.

本開示の一態様に係る停電原因通知方法は、停電原因通知システムの1以上のコンピュータによって実行される。前記停電原因通知システムは、ブレーカに付随して用いられる。前記ブレーカは、電力系統と顧客の宅内の負荷との間の電路に介在する。前記ブレーカは、少なくとも停電の発生時に前記顧客の端末と通信可能に接続される。前記停電原因通知方法は、前記停電の原因を前記ブレーカから前記端末を介して前記顧客に通知する停電原因通知方法である。前記端末には、アプリケーションソフトウェアがインストールされている。前記アプリケーションソフトウェアは、少なくとも前記停電の原因を通知する。前記停電原因通知システムは、電源部と、受付部と、を備える。前記電源部は、前記電力系統に起因する停電である系統停電の発生時に、少なくとも前記1以上のコンピュータに電力を供給する。前記受付部は、前記ブレーカを前記端末と通信可能に接続するための接続操作を受け付ける。前記停電原因通知方法は、起動ステップと、取得ステップと、出力ステップと、を含む。前記起動ステップでは、前記停電の発生時に、前記端末の前記アプリケーションソフトウェアを起動する。前記取得ステップでは、前記停電の発生時に、停電情報が取得される。前記停電情報は、原因情報を少なくとも含む。前記原因情報は、前記停電が、系統停電か、宅内停電か、を示す。前記系統停電は、前記電力系統に起因する停電である。前記宅内停電は、前記ブレーカがトリップ状態となったことに起因する停電である。前記出力ステップでは、前記取得ステップで取得された前記停電情報が、前記起動ステップで起動された前記アプリケーションソフトウェアに引き渡される。
本開示の一態様に係る停電原因通知方法は、停電原因通知システムの1以上のコンピュータによって実行される。前記停電原因通知システムは、ブレーカに付随して用いられる。前記ブレーカは、電力系統と顧客の宅内の負荷との間の電路に介在する。前記ブレーカは、少なくとも停電の発生時に前記顧客の端末と通信可能に接続される。前記停電原因通知方法は、前記停電の原因を前記ブレーカから前記端末を介して前記顧客に通知する停電原因通知方法である。前記端末には、アプリケーションソフトウェアがインストールされている。前記アプリケーションソフトウェアは、少なくとも前記停電の原因を通知する。前記停電原因通知システムは、電源部を備える。前記電源部は、前記電力系統に起因する停電である系統停電の発生時に、少なくとも前記1以上のコンピュータに電力を供給する。前記端末は、前記端末の前記アプリケーションソフトウェアを通じて前記顧客への情報提供を行うサーバと常時通信可能に接続される。前記ブレーカは、前記サーバと常時通信可能に接続される。前記停電原因通知方法は、起動ステップと、取得ステップと、出力ステップと、を含む。前記起動ステップでは、前記停電の発生時に、前記端末の前記アプリケーションソフトウェアを起動する。前記取得ステップでは、前記停電の発生時に、停電情報が取得される。前記停電情報は、原因情報を少なくとも含む。前記原因情報は、前記停電が、系統停電か、宅内停電か、を示す。前記系統停電は、前記電力系統に起因する停電である。前記宅内停電は、前記ブレーカがトリップ状態となったことに起因する停電である。前記出力ステップでは、前記取得ステップで取得された前記停電情報が、前記起動ステップで起動された前記アプリケーションソフトウェアに引き渡される。前記サーバが前記起動ステップを実行し、前記サーバの前記起動ステップでは、前記ブレーカと前記サーバの間の接続が切断されたことに応じて、前記端末の前記アプリケーションソフトウェアを起動する。
A power outage cause notification method according to one aspect of the present disclosure is executed by one or more computers of a power outage cause notification system. The power outage cause notification system is used in conjunction with a breaker. The breaker is located in an electric circuit between a power grid and a load in a customer's premises. The breaker is communicatively connected to a terminal of the customer at least when a power outage occurs. The power outage cause notification method notifies the customer of the cause of the power outage from the breaker via the terminal. Application software is installed on the terminal. The application software notifies at least the cause of the power outage. The power outage cause notification system includes a power supply unit and a reception unit. The power supply unit supplies power to at least the one or more computers when a grid power outage occurs, which is a power outage caused by the power grid. The reception unit receives a connection operation to communicatively connect the breaker to the terminal. The power outage cause notification method includes a startup step, an acquisition step, and an output step. In the startup step, the application software of the terminal is started when the power outage occurs. In the acquisition step, power outage information is acquired when the power outage occurs. The power outage information includes at least cause information. The cause information indicates whether the power outage is a grid power outage or a home power outage. The grid power outage is a power outage caused by the power grid. The home power outage is a power outage caused by the breaker being tripped. In the output step, the power outage information acquired in the acquisition step is passed to the application software started in the startup step.
A power outage cause notification method according to one aspect of the present disclosure is executed by one or more computers of a power outage cause notification system. The power outage cause notification system is used in conjunction with a breaker. The breaker is located in an electric circuit between a power grid and a load in a customer's premises. The breaker is communicatively connected to a terminal of the customer at least when a power outage occurs. The power outage cause notification method notifies the customer of the cause of the power outage from the breaker via the terminal. Application software is installed in the terminal. The application software notifies the customer of at least the cause of the power outage. The power outage cause notification system includes a power supply unit. The power supply unit supplies power to at least the one or more computers when a grid power outage occurs, which is a power outage caused by the power grid. The terminal is constantly connected to a server that provides information to the customer through the application software of the terminal so as to be able to communicate with the server. The breaker is constantly connected to the server so as to be able to communicate with the server. The power outage cause notification method includes a startup step, an acquisition step, and an output step. In the startup step, the application software of the terminal is started when the power outage occurs. In the acquisition step, power outage information is acquired when the power outage occurs. The power outage information includes at least cause information. The cause information indicates whether the power outage is a grid power outage or a home power outage. The grid power outage is a power outage caused by the power grid. The home power outage is a power outage caused by the breaker being tripped. In the output step, the power outage information acquired in the acquisition step is passed to the application software launched in the startup step. The server executes the startup step, and in the server startup step, the application software on the terminal is launched in response to the connection between the breaker and the server being disconnected.

本開示の一態様に係るプログラムは、前記停電原因通知方法を1以上のコンピュータに実行させるためのプログラムである。 A program according to one aspect of the present disclosure is a program for causing one or more computers to execute the power outage cause notification method.

本開示の停電原因通知システム、ブレーカ、停電原因通知方法及びプログラムは、個々の顧客に対して、宅内停電も含む停電の原因に関する原因情報を容易に通知できる、という効果がある。 The power outage cause notification system, breaker, power outage cause notification method, and program disclosed herein have the advantage of easily notifying individual customers of information regarding the cause of a power outage, including in-home power outages.

図1は、本開示の実施形態1に係る停電原因通知システムを含む電力供給システムのブロック図である。FIG. 1 is a block diagram of a power supply system including a power outage cause notification system according to a first embodiment of the present disclosure. 図2は、同上の停電原因通知システムを構成する主幹ブレーカのブロック図である。FIG. 2 is a block diagram of a main breaker constituting the power outage cause notification system. 図3は、同上の停電原因通知システムの動作を説明するフローチャートである。FIG. 3 is a flowchart illustrating the operation of the power outage cause notification system. 図4は、本開示の実施形態2に係る停電原因通知システムを含む電力供給システムのブロック図である。FIG. 4 is a block diagram of a power supply system including a power outage cause notification system according to a second embodiment of the present disclosure. 図5は、同上の停電原因通知システムを構成するサーバのブロック図である。FIG. 5 is a block diagram of a server constituting the power outage cause notification system. 図6は、停電原因通知システムを構成する主幹ブレーカのブロック図である。FIG. 6 is a block diagram of a main breaker that constitutes the power outage cause notification system. 図7は、同上のサーバの動作を説明するフローチャートである。FIG. 7 is a flowchart illustrating the operation of the server in the above embodiment. 図8は、同上の主幹ブレーカの動作を説明するフローチャートである。FIG. 8 is a flowchart illustrating the operation of the main breaker. 図9は、同上の停電原因通知システムによる停電情報の出力例を示す図である。FIG. 9 is a diagram showing an example of power outage information output by the power outage cause notification system. 図10は、同上の主幹ブレーカを含む分電盤の外観図である。FIG. 10 is an external view of a distribution board including the above-mentioned main breaker.

本開示は、以下の実施形態に限定されず、本開示の効果を奏することができれば、設計等に応じて種々の変更が可能である。 This disclosure is not limited to the following embodiments, and various modifications are possible depending on the design, etc., as long as the effects of this disclosure can be achieved.

(1)前提事項
最初に、図1~図10を適宜参照して、本開示の実施形態1,2に係る停電原因通知システムに共通の前提事項を説明する。
(1) Premise Conditions First, the premise conditions common to the power outage cause notification systems according to the first and second embodiments of the present disclosure will be described with reference to FIGS. 1 to 10 as appropriate.

図1,図4に示すように、本開示の実施形態1,2に係る停電原因通知システム1は、ブレーカに付随して用いられる。ブレーカは、電力系統201と顧客の宅内の負荷202との間の電路に介在する。 As shown in Figures 1 and 4, the power outage cause notification system 1 according to embodiments 1 and 2 of the present disclosure is used in conjunction with a breaker. The breaker is located in an electrical path between the power grid 201 and a load 202 in a customer's home.

なお、ブレーカに付随して用いられることは、ブレーカが停電原因通知システム1を構成する要素である場合と、停電原因通知システム1の外部の要素である(停電原因通知システム1の構成要素でない)場合とを含む。また、ブレーカが停電原因通知システム1を構成する要素であることは、停電原因通知システム1がブレーカ単独で構成される場合も含む。 Note that being used in conjunction with a breaker includes cases where the breaker is an element that constitutes the power outage cause notification system 1, and cases where it is an element external to the power outage cause notification system 1 (not a component of the power outage cause notification system 1). Furthermore, the breaker being an element that constitutes the power outage cause notification system 1 also includes cases where the power outage cause notification system 1 is composed of a breaker alone.

(1-1)ブレーカ
ブレーカは、例えば、図10に示すような分電盤100を構成する主幹ブレーカ10である。
(1-1) Breaker The breaker is, for example, a main breaker 10 constituting a distribution board 100 as shown in FIG.

なお、分電盤100は、例えば、図10に示すように、主幹ブレーカ10に加えて、複数の分岐ブレーカ50、及び計測ユニット15を有する。主幹ブレーカ10には、接点(後述)を開閉するスイッチ(ハンドルともいう)10Aが設けられ、分岐ブレーカ50にも同様のスイッチが設けられている。計測ユニット15は、接続操作(後述)を受け付ける接続キー15Aを有する。また、計測ユニット15は、計測結果等の情報を表示するディスプレイ15Bを有していてもよい。 As shown in FIG. 10, the distribution board 100 includes a main breaker 10, multiple branch breakers 50, and a measurement unit 15. The main breaker 10 is provided with a switch (also called a handle) 10A that opens and closes contacts (described below), and the branch breakers 50 are also provided with similar switches. The measurement unit 15 has a connection key 15A that accepts connection operations (described below). The measurement unit 15 may also have a display 15B that displays information such as measurement results.

主幹ブレーカ10は、過電流、漏電及び地震を検知する検知機能、過電流等を検知した場合に電路の電流を遮断する(トリップ状態となる)遮断機能、及び、少なくとも端末40と通信する通信機能、を有する。なお、トリップ状態とは、第1電路203a及び第2電路203b(いずれも後述)の間の接点が開放された状態である。 The master breaker 10 has a detection function for detecting overcurrents, electrical leakage, and earthquakes, a cutoff function for cutting off the current in the circuit (entering a tripped state) when an overcurrent or other condition is detected, and a communication function for communicating with at least the terminal 40. The tripped state refers to a state in which the contacts between the first circuit 203a and the second circuit 203b (both described below) are open.

主幹ブレーカ10は、第2電路203bで過電流又は漏電が発生した場合、又は地震が発生した場合に、トリップ状態となる。主幹ブレーカ10がトリップ状態となることで、負荷202へ電力の供給は停止される。 The main breaker 10 trips when an overcurrent or leakage current occurs in the second electrical circuit 203b, or when an earthquake occurs. When the main breaker 10 trips, the supply of power to the load 202 is stopped.

主幹ブレーカ10は、プロセッサ(CPU,MPU等)及びメモリ(半導体メモリ、SSD等)と、通信モジュールと(いずれも図示しない)を有する。メモリには、各種のデータ及びプログラムが格納され、プロセッサが当該各種のデータを用いて当該プログラムを実行することにより、上記検知機能及び上記遮断機能が実現される。なお、以下では、各種の機能を実現するプロセッサ及びメモリを「コンピュータ」と称する場合がある。 The main breaker 10 has a processor (CPU, MPU, etc.), memory (semiconductor memory, SSD, etc.), and a communication module (none of which are shown). The memory stores various data and programs, and the processor executes the programs using the various data to achieve the detection and shutdown functions. Note that, below, the processor and memory that achieve the various functions may be referred to as the "computer."

通信モジュールは、上記通信機能を実現する。主幹ブレーカ10と端末40との間の通信は、通常、近距離無線通信であり、主幹ブレーカ10の通信モジュールは、近距離無線の通信機能を少なくとも実現する。 The communication module realizes the above-mentioned communication functions. Communication between the master breaker 10 and the terminal 40 is usually short-range wireless communication, and the communication module of the master breaker 10 realizes at least the short-range wireless communication function.

なお、実施形態2では、計測ユニット15(後述)の通信モジュールが、近距離無線による通信、及び第2ネットワーク302を介した通信、の2種類の通信機能を有している。主幹ブレーカ10の通信モジュールは、計測ユニット15の通信モジュールと近距離無線通信を行うことにより、第2ネットワーク302を介した通信機能を更に実現する。 In embodiment 2, the communication module of the measurement unit 15 (described below) has two types of communication functions: short-range wireless communication and communication via the second network 302. The communication module of the main breaker 10 performs short-range wireless communication with the communication module of the measurement unit 15, thereby further realizing the communication function via the second network 302.

ただし、主幹ブレーカ10の通信モジュールは、第2ネットワーク302を介した通信機能を、計測ユニット15の通信モジュールを介すことなく単独で実現してもよい。また、主幹ブレーカ10の通信モジュールは、第1ネットワーク301(後述)を介した通信機能を、端末40の通信モジュールを介すことなく単独で実現してもよい。 However, the communication module of the main breaker 10 may independently realize the communication function via the second network 302 without going through the communication module of the measurement unit 15. Furthermore, the communication module of the main breaker 10 may independently realize the communication function via the first network 301 (described below) without going through the communication module of the terminal 40.

主幹ブレーカ10は、例えば、タッチパネルやキーボード等の入力デバイスを有していてもよい。また、主幹ブレーカ10は、ディスプレイやスピーカ等の出力デバイスを有していてもよい。 The main breaker 10 may have input devices such as a touch panel or keyboard. The main breaker 10 may also have output devices such as a display or speaker.

ただし、ブレーカは、例えば、分電盤100を構成する分岐ブレーカ50又はリミッタ(図示しない)でもよいし、分電盤100の構成要素でなくてもよい。つまり、ブレーカは、電力系統201と負荷202との間の電路(第1電路203a,第2電路203b)に介在し、過電流等の発生に応じて電路を遮断するものであれば、そのタイプは問わない。 However, the breaker may be, for example, a branch breaker 50 or a limiter (not shown) that constitutes the distribution board 100, or it may not be a component of the distribution board 100. In other words, the type of breaker is not important as long as it is interposed in the electrical circuit (first electrical circuit 203a, second electrical circuit 203b) between the power system 201 and the load 202 and cuts off the electrical circuit in response to the occurrence of an overcurrent or the like.

(1-2)負荷
負荷202は、電力系統201からの電力で動作する家庭用の電気機器である。負荷202は、例えば、情報家電等のIoT機器が好適である。このような負荷202は、第2ネットワーク302(後述)に接続可能である(実施形態2:図4参照)。ただし、負荷202は、第2ネットワーク302への接続機能を有さない電気機器でもよい(実施形態1:図1参照)。
(1-2) Load The load 202 is a household electrical appliance that operates on power from the power grid 201. The load 202 is preferably an IoT device such as an information appliance. Such a load 202 can be connected to a second network 302 (described later) (see FIG. 4 in the second embodiment). However, the load 202 may also be an electrical appliance that does not have a function for connecting to the second network 302 (see FIG. 1 in the first embodiment).

(1-3)電路
電路は、第1電路203a及び第2電路203bを含む。第1電路203aは、ブレーカ(主幹ブレーカ10)に対して電力系統201側(主幹ブレーカ10の一次側)の電路である。第2電路203bは、ブレーカ(主幹ブレーカ10)に対して負荷202側(主幹ブレーカ10の二次側)の電路である。
(1-3) Electrical Path The electrical paths include a first electrical path 203a and a second electrical path 203b. The first electrical path 203a is an electrical path on the power grid 201 side (the primary side of the main breaker 10) relative to the breaker (main breaker 10). The second electrical path 203b is an electrical path on the load 202 side (the secondary side of the main breaker 10) relative to the breaker (main breaker 10).

(1-4)端末
上記顧客は、端末(40)を利用可能である。利用とは、例えば、ディスプレイに表示又はスピーカから音声出力される情報の視聴、タッチパネル等の入力デバイスを介した情報の入力、等を行うことである。
(1-4) Terminal The customer can use the terminal (40). For example, using the terminal means viewing information displayed on a display or outputted as audio from a speaker, inputting information via an input device such as a touch panel, etc.

端末40は、例えば、スマートフォン等の携帯端末であるが、デスクトップPC(Personal Computer)等の据え置き型端末でもよい。携帯端末は、上記顧客によって携帯される。据え置き型端末は、上記顧客の宅内に設置される。 The terminal 40 may be, for example, a mobile terminal such as a smartphone, or a stationary terminal such as a desktop personal computer (PC). A mobile terminal is carried by the customer. A stationary terminal is installed in the customer's home.

端末40は、サーバ30(後述)と通信可能であることが好適である(実施形態2)。ただし、端末40は、サーバ30との通信機能を有さなくてもよいし、サーバ30が存在しなくても構わない(実施形態1)。 It is preferable that the terminal 40 be capable of communicating with the server 30 (described below) (Embodiment 2). However, the terminal 40 does not have to have the ability to communicate with the server 30, and the server 30 does not have to exist (Embodiment 1).

端末40は、プロセッサ及びメモリ(コンピュータ)と、通信モジュールと、タッチパネル等の入力デバイスと、ディスプレイ等の出力デバイスと、を有する。 The terminal 40 has a processor and memory (computer), a communication module, an input device such as a touch panel, and an output device such as a display.

なお、端末40とサーバ30との間の通信は、第1ネットワーク301(後述)を介した通信である。端末40の通信モジュールは、主幹ブレーカ10との間の上記近距離無線通信に加えて、このような第1ネットワーク301を介した通信機能を実現する(実施形態2)。 Note that communication between the terminal 40 and the server 30 is via a first network 301 (described below). The communication module of the terminal 40 realizes communication functionality via the first network 301 in addition to the short-range wireless communication with the main breaker 10 (Embodiment 2).

端末40は、例えば、スマートフォン等の携帯端末であるが、デスクトップPC等の据え置き型端末でもよい。携帯端末は、上記顧客によって携帯される。据え置き型端末は、上記顧客の宅内に設置される。 The terminal 40 is, for example, a mobile terminal such as a smartphone, but may also be a stationary terminal such as a desktop PC. A mobile terminal is carried by the customer. A stationary terminal is installed in the customer's home.

(1-5)サーバ
サーバ30は、端末40を介して顧客にサービスを提供する。サービスは、電力系統201の停電に関する停電情報の顧客への通知を含む。サービスの提供は、端末40にインストールされているアプリケーションソフトウェア(サービスアプリ)を通じて行われる。
(1-5) Server The server 30 provides services to customers via the terminal 40. The services include notifying customers of power outage information regarding a power outage in the power grid 201. The services are provided through application software (service app) installed on the terminal 40.

ただし、サーバ30は、本開示の停電原因通知システム1の実施に必須の要素ではない(実施形態1)。 However, the server 30 is not an essential element for implementing the power outage cause notification system 1 of the present disclosure (Embodiment 1).

(1-6)ネットワーク
サーバ30は、第1ネットワーク301を介して端末40と通信可能に接続される。第1ネットワーク301は、例えば、インターネットや通信回線網等の広域ネットワークである。
(1-6) Network The server 30 is communicably connected to the terminal 40 via a first network 301. The first network 301 is, for example, a wide area network such as the Internet or a communication line network.

一方、負荷202が接続されるネットワークは、第2ネットワーク302である。第2ネットワークは、例えば、宅内の電路を介して通信を行うPLC(Power Line Communications)ネットワークである。第2ネットワーク302は、ゲートウェイ(GW)303を介して第1ネットワーク301と通信可能に接続される(実施形態2)。 On the other hand, the network to which the load 202 is connected is the second network 302. The second network is, for example, a PLC (Power Line Communications) network that communicates via electrical lines within the home. The second network 302 is communicatively connected to the first network 301 via a gateway (GW) 303 (embodiment 2).

詳しくは、実施形態2では、サーバ30が接続された第1ネットワーク(インターネット)の通信プロトコルと、主幹ブレーカ10が接続された第2ネットワーク(PLCネットワーク)の通信プロトコルとが異なるため、第1ネットワーク・第2ネットワーク間に、当該2つのプロトコルの間のプロトコルを変換するゲートウェイ(GW)303が介在する。 In more detail, in embodiment 2, the communication protocol of the first network (Internet) to which the server 30 is connected is different from the communication protocol of the second network (PLC network) to which the main breaker 10 is connected, so a gateway (GW) 303 that converts between the two protocols is interposed between the first network and the second network.

なお、GW303は、このようなプロトコル変換に加えて、第2ネットワーク302に接続された各種のIoT機器に関連する処理も行ってもよい。関連する処理とは、例えば、各種のIoT機器に関する機器情報を収集してサーバ30に提供する処理などである。 In addition to this protocol conversion, GW303 may also perform processing related to various IoT devices connected to the second network 302. Examples of related processing include collecting device information about various IoT devices and providing the information to server 30.

ただし、第2ネットワーク302及びGW303は、本開示の停電原因通知システム1の実施に必須の要素ではない(実施形態1)。 However, the second network 302 and GW 303 are not essential elements for implementing the power outage cause notification system 1 of the present disclosure (embodiment 1).

(2)特徴事項
以下、実施形態1,2に共通の特徴事項、及び実施形態1,2の各々に固有の特徴事項を説明する。
(2) Characteristics The following describes characteristics common to the first and second embodiments, as well as characteristics unique to each of the first and second embodiments.

(2-1)ブレーカ
ブレーカ(主幹ブレーカ10)は、停電の発生時に、上記顧客の端末40と通信可能に接続される。
(2-1) Breaker The breaker (master breaker 10) is connected to the customer terminal 40 so as to be able to communicate with it in the event of a power outage.

主幹ブレーカ10と端末40との間の接続は、実施形態1では適時接続、実施形態2では常時接続である。また、実施形態1における適時とは、接続操作が受け付けられた時である。 The connection between the main breaker 10 and the terminal 40 is a timely connection in embodiment 1 and a constant connection in embodiment 2. Also, in embodiment 1, "timely" refers to when a connection operation is accepted.

すなわち、実施形態1では、ブレーカ(主幹ブレーカ10)は、例えば、停電の発生時に顧客が行う接続操作、に応じて端末40と接続される。接続操作に応じてブレーカ(主幹ブレーカ10)と端末40とが接続された後、停電原因通知システム1は、停電の原因をブレーカ(主幹ブレーカ10)から端末40を介して上記顧客に通知する。 That is, in embodiment 1, the breaker (main breaker 10) is connected to the terminal 40 in response to a connection operation performed by a customer, for example, when a power outage occurs. After the breaker (main breaker 10) and terminal 40 are connected in response to the connection operation, the power outage cause notification system 1 notifies the customer of the cause of the power outage from the breaker (main breaker 10) via the terminal 40.

実施形態2では、ブレーカ(主幹ブレーカ10)と端末40との間の接続は、常時接続である。 In embodiment 2, the connection between the breaker (main breaker 10) and the terminal 40 is a permanent connection.

なお、実施形態1,2における常時接続とは、接続された状態が継続することである。接続された状態が継続することは、例えば、接続された状態が、一定以上の期間に渡って途切れることなく継続することであるが、予め決められた閾値より短い期間、一時的に途切れてもよい。また、常時接続は、例えば、予め決められた閾値より短い周期で定期的に接続する場合や、予め決められた閾値を超えない時間間隔で不定期に接続する場合、なども含む。 Note that a constant connection in embodiments 1 and 2 refers to a continuous connection. A continuous connection means, for example, that the connection continues uninterrupted for a certain period of time or longer, but may also be temporarily interrupted for a period shorter than a predetermined threshold. A constant connection also includes, for example, a periodic connection at a cycle shorter than a predetermined threshold, or an irregular connection at time intervals that do not exceed a predetermined threshold.

また、実施形態1,2において、常時通信可能(後述)とは、機器間が常時接続されていて、通信可能な状態が継続することである。 In addition, in embodiments 1 and 2, "constant communication possible" (described below) means that the devices are constantly connected and continuously capable of communication.

(2-2)端末
端末40には、アプリケーションソフトウェア201がインストールされている。アプリケーションソフトウェア201(以下、アプリ401)は、端末40のコンピュータ、通信モジュール、入力デバイス及び出力デバイスを介して、少なくとも上記停電の原因を通知する通知機能を実現する。なお、インストールされていることは、アプリ401が、端末40のメモリに起動可能な状態で格納されていることである。
(2-2) Terminal Application software 201 is installed on the terminal 40. The application software 201 (hereinafter, app 401) realizes a notification function that notifies at least the cause of the power outage via the computer, communication module, input device, and output device of the terminal 40. Note that being installed means that the app 401 is stored in the memory of the terminal 40 in an activatable state.

実施形態1では、アプリ401は、停電原因の通知のための専用の通知アプリである。実施形態2では、アプリ401は、顧客へのサービス提供を行うサービスアプリに、停電原因の通知機能を追加したものである。 In embodiment 1, app 401 is a notification app dedicated to notifying users of the cause of a power outage. In embodiment 2, app 401 is a service app that provides services to customers, to which a power outage cause notification function has been added.

また、アプリ401は、停電の原因に応じた対処法も通知する。 The app 401 also notifies you of the corrective action to take depending on the cause of the power outage.

(2-3)停電原因通知システム
停電原因通知システム1は、起動部121と、取得部122と、出力部13とを備える。
(2-3) Power Outage Cause Notification System The power outage cause notification system 1 includes a startup unit 121, an acquisition unit 122, and an output unit 13.

起動部121は、停電の発生時に、端末40のアプリ401を起動する。 The startup unit 121 starts the app 401 on the terminal 40 when a power outage occurs.

実施形態1では、図2に示すように、主幹ブレーカ10が起動部121を備え、主幹ブレーカ10の起動部121が、端末40のアプリ401を起動する。 In embodiment 1, as shown in FIG. 2, the main breaker 10 includes a startup unit 121, which starts the app 401 on the terminal 40.

実施形態2では、図4に示すように、サーバ30が起動部121を備え、サーバ30の起動部121が、端末40のアプリ401を起動する。 In embodiment 2, as shown in FIG. 4, the server 30 includes a launch unit 121, which launches the app 401 on the terminal 40.

取得部122は、停電の発生時に、停電情報を取得する。停電情報とは、停電に関する情報である。停電情報は、原因情報を少なくとも含む。原因情報とは、停電の原因に関する情報である。 The acquisition unit 122 acquires power outage information when a power outage occurs. Power outage information is information related to the power outage. Power outage information includes at least cause information. Cause information is information related to the cause of the power outage.

原因情報は、例えば、第1原因情報である。第1原因情報は、発生した停電が、系統停電か、宅内停電か、を示す。系統停電とは、電力系統201に起因する停電である。宅内停電とは、ブレーカ(主幹ブレーカ10)がトリップ状態となったことに起因する停電である。 The cause information is, for example, first cause information. The first cause information indicates whether the power outage that occurred is a grid power outage or a home power outage. A grid power outage is a power outage caused by the power grid 201. A home power outage is a power outage caused by a breaker (main breaker 10) tripping.

または、原因情報は、第2原因情報でもよい。第2原因情報は、宅内停電の原因に関する情報である。宅内停電の原因は、前述したように、過電流、漏電及び地震のいずれかであり、第2原因情報は、宅内停電の原因が、過電流か、漏電か、地震か、を示す。 Alternatively, the cause information may be second cause information. The second cause information is information regarding the cause of the in-home power outage. As mentioned above, the cause of an in-home power outage is either an overcurrent, a ground fault, or an earthquake, and the second cause information indicates whether the cause of the in-home power outage is an overcurrent, a ground fault, or an earthquake.

なお、過電流には、例えば、過負荷による過電流と、短絡による過電流とがある。第2原因情報では、過電流は、過負荷による過電流と、短絡による過電流とに区別されてもよい。 Note that overcurrents include, for example, overcurrents caused by overloads and overcurrents caused by short circuits. In the second cause information, overcurrents may be distinguished into overcurrents caused by overloads and overcurrents caused by short circuits.

取得部122は、系統停電の発生時に、“系統停電”を示す第1原因情報を含む停電情報を取得する。なお、このような停電情報は、例えば“停電原因は、電力系統のトラブルです。”等のメッセージ(自然言語による文字列)であってもよい。 When a grid power outage occurs, the acquisition unit 122 acquires power outage information including first cause information indicating a "grid power outage." Note that such power outage information may be, for example, a message (a string of characters in natural language) such as "The cause of the power outage is a problem with the power grid."

また、取得部122は、宅内停電の発生時には、“宅内停電”を示す第1原因情報、並びに“過電流”,”漏電”及び“地震”のいずれかを示す第2原因情報、を含む停電情報を取得する。なお、このような停電情報は、例えば“停電原因は、宅内ブレーカの動作です。漏電の可能性があります。”等のメッセージであってもよい。 Furthermore, when a home power outage occurs, the acquisition unit 122 acquires power outage information including first cause information indicating a "home power outage" and second cause information indicating one of "overcurrent," "earthquake," and "earthquake." Note that such power outage information may be, for example, a message such as "The cause of the power outage is the operation of the home breaker. There is a possibility of a power leak."

取得部122は、例えば、計測ユニット15の計測結果を基に、停電が系統停電か宅内停電かを示す第1原因情報を取得する。また、取得部122は、停電が宅内停電の場合に、宅内停電の原因が過電流か漏電か地震かを示す第2原因情報を取得する。 The acquisition unit 122 acquires first cause information indicating whether the power outage is a grid power outage or a home power outage, for example, based on the measurement results of the measurement unit 15. Furthermore, if the power outage is a home power outage, the acquisition unit 122 acquires second cause information indicating whether the home power outage was caused by an overcurrent, a ground fault, or an earthquake.

詳しくは、実施形態1では、停電原因通知システム1は、監視部123を更に備える。監視部123は、計測ユニット15の計測結果を常時監視し、当該計測結果を基に、停電が系統停電か宅内停電かを判断する。そして、監視部123は、判断結果(“系統停電”又は“宅内停電”)を示す第1原因情報を取得して、取得部122に引き渡す。 More specifically, in embodiment 1, the power outage cause notification system 1 further includes a monitoring unit 123. The monitoring unit 123 constantly monitors the measurement results of the measurement unit 15 and determines whether the power outage is a grid power outage or a home power outage based on the measurement results. The monitoring unit 123 then acquires first cause information indicating the determination result ("grid power outage" or "home power outage") and passes it to the acquisition unit 122.

また、“宅内停電”を示す第1原因情報を取得した場合、第1監視部123は、上記計測結果を基に、宅内停電の原因が過電流か漏電か地震かの判断を行い、判断結果(“過電流”,“漏電”及び“地震”のいずれか)を示す第2原因情報を更に取得して、取得部122に引き渡す。 Furthermore, when first cause information indicating a "household power outage" is acquired, the first monitoring unit 123 determines whether the cause of the household power outage is an overcurrent, a ground fault, or an earthquake based on the measurement results, and further acquires second cause information indicating the determination result (either "overcurrent," "ground fault," or "earthquake") and passes it to the acquisition unit 122.

実施形態2では、停電原因通知システム1は、実施形態1の監視部123と同じ機能を有する第1監視部123と、第2監視部124とを備える。第2監視部124は、サーバ30から提供される系統停電情報を常時監視し、停電が系統停電か宅内停電かを判断する。そして、第2監視部124は、判断結果(“系統停電”又は“宅内停電”)を示す第1原因情報を取得して、取得部122に引き渡す。 In embodiment 2, the power outage cause notification system 1 includes a first monitoring unit 123 having the same functions as the monitoring unit 123 in embodiment 1, and a second monitoring unit 124. The second monitoring unit 124 constantly monitors grid power outage information provided by the server 30 and determines whether the power outage is a grid power outage or a home power outage. The second monitoring unit 124 then acquires first cause information indicating the determination result ("grid power outage" or "home power outage") and passes it to the acquisition unit 122.

ただし、実施形態2において、停電原因通知システム1は、第1監視部123及び計測ユニット15を備えず、第2監視部124のみを備えていてもよい(実施形態2の変形例)。 However, in embodiment 2, the power outage cause notification system 1 may not include the first monitoring unit 123 and the measurement unit 15, but may include only the second monitoring unit 124 (a modified example of embodiment 2).

取得部122は、対処情報を更に含む停電情報を取得してもよい。対処情報とは、停電の原因に応じた対処法に関する情報である。このような停電情報は、例えば、“停電原因は、宅内ブレーカの動作です。漏電の可能性があります。次の手順で対処して下さい。・・・”等のメッセージであってもよい。 The acquisition unit 122 may acquire power outage information that further includes response information. Response information is information regarding the response method depending on the cause of the power outage. Such power outage information may be, for example, a message such as, "The cause of the power outage is the operation of the in-house breaker. There is a possibility of a power leak. Please take action by following the procedure below..."

実施形態1,2では、例えば、主幹ブレーカ10のメモリに、原因情報と対処情報との対(対情報)の集合(対情報群)が格納されている。対情報群を構成する対情報は、例えば、“系統停電”を示す第1原因情報と第1対処情報との対(第1対情報)、“過電流”を示す第2原因情報と第2対処情報との対(第2対情報)、“漏電”を示す第2原因情報と第3対処情報との対(第3対情報)、及び“地震”を示す第2原因情報と第4対処情報との対(第4対情報)、などである。 In embodiments 1 and 2, for example, a collection (pair information group) of pairs (pair information) of cause information and response information is stored in the memory of the main breaker 10. The pair information constituting the pair information group includes, for example, a pair of first cause information and first response information indicating a "grid power outage" (first pair information), a pair of second cause information and second response information indicating an "overcurrent" (second pair information), a pair of second cause information and third response information indicating a "leakage current" (third pair information), and a pair of second cause information and fourth response information indicating an "earthquake" (fourth pair information).

第1対処情報は、例えば“電力系統の復電まで、そのままお待ちください。”であってもよい。第2対処情報は、例えば“一部の機器の電源を切った後、主幹ブレーカのスイッチを入れて下さい”であってもよい。第3対処情報は、例えば“以下の手順で対処して下さい。分岐ブレーカのスイッチを全て切る。主幹ブレーカのスイッチを入れる。分岐ブレーカのスイッチを順番に入れていき・・・”であってもよい。第4対処情報は、例えば“機器が倒れたり破損したりしていないことを確認後、主幹ブレーカのスイッチを入れて下さい”であってもよい。 The first action information may be, for example, "Please wait until power is restored to the power system." The second action information may be, for example, "After turning off the power to some of the equipment, switch on the main breaker." The third action information may be, for example, "Please take action in the following procedure. Switch off all branch breakers. Switch on the main breaker. Switch on the branch breakers in order...." The fourth action information may be, for example, "After making sure that no equipment has fallen or been damaged, switch on the main breaker."

なお、対情報群は、上記第2~第4対情報に代えて、例えば、“宅内停電”を示す第1原因情報と第5対処情報との対(第5対情報)を含んでいてもよい。第5対処情報は、例えば、“宅内の配線を点検してください。”であってもよい。 In addition, instead of the second to fourth paired information, the paired information group may include, for example, a pair (fifth paired information) of first cause information indicating "in-house power outage" and fifth response information. The fifth response information may be, for example, "Please check the wiring in your home."

取得部122は、上記のように原因情報を取得し、当該原因情報に対応する対処情報を上記メモリから更に取得し、当該取得した原因情報及び当該取得した対処情報を含む停電情報を取得する。 The acquisition unit 122 acquires the cause information as described above, further acquires the response information corresponding to the cause information from the memory, and acquires power outage information including the acquired cause information and the acquired response information.

原因情報及び対処情報を含む停電情報は、例えば“停電原因は、宅内のブレーカの動作です。漏電の可能性があります。以下の手順で対処して下さい。・・・”等のメッセージであってもよい。 Power outage information including cause information and response information may be a message such as, "The cause of the power outage is the operation of the breaker in your home. There may be a power leak. Please take action by following the steps below..."

なお、対情報群は、例えば、分電盤100の、主幹ブレーカ10以外の内器のメモリに格納されていてもよいし、分電盤100の外部(例えばサーバ30)のメモリに格納されていてもよい。対情報群が格納されるメモリは、主幹ブレーカ10のプロセッサがアクセス可能なメモリであれば、その所在は問わない。 The pair information group may be stored, for example, in the memory of an internal device other than the main breaker 10 of the distribution board 100, or in memory external to the distribution board 100 (for example, in the server 30). The location of the memory in which the pair information group is stored does not matter as long as it is memory accessible by the processor of the main breaker 10.

なお、取得部122が取得した各種の情報(第1原因情報、第2原因情報、対策情報、及びこれらを含む停電情報)は、主幹ブレーカ10のメモリに保持される。ただし、第1原因情報等の情報もまた、主幹ブレーカ10のプロセッサがアクセス可能なメモリであれば、どのメモリに保持されてもよい。 The various types of information acquired by the acquisition unit 122 (first cause information, second cause information, countermeasure information, and power outage information including these) are stored in the memory of the main breaker 10. However, information such as the first cause information may also be stored in any memory accessible to the processor of the main breaker 10.

実施形態2では、停電原因通知システム1は、第2監視部124を更に備える。 In embodiment 2, the power outage cause notification system 1 further includes a second monitoring unit 124.

第2監視部124は、サーバ30からブレーカ(主幹ブレーカ10)に提供される系統停電情報を(常時)監視し、系統停電情報を基に、停電が系統停電か宅内停電かを判断して、第1原因情報を取得する。 The second monitoring unit 124 (constantly) monitors the grid power outage information provided to the breaker (main breaker 10) from the server 30, and based on the grid power outage information, determines whether the power outage is a grid power outage or a home power outage, and obtains the first cause information.

詳しくは、第2監視部124は、停電発生時に、受付部11(後述)が系統停電情報を行け付けたか否かを判断し、受付部11が系統停電情報を行け付けた場合、停電が系統停電であると判断して、“系統停電”を示す第1原因情報を取得する。一方、停電の発生から予め決められた時間が経過しても、受付部11が系統停電情報を行け付けていない場合、第2監視部124は、停電が宅内停電であると判断して、“宅内停電”を示す第1原因情報を取得する。 In more detail, when a power outage occurs, the second monitoring unit 124 determines whether the reception unit 11 (described below) has received grid power outage information. If the reception unit 11 has received grid power outage information, the second monitoring unit 124 determines that the power outage is a grid power outage and acquires first cause information indicating a "grid power outage." On the other hand, if the reception unit 11 has not received grid power outage information even after a predetermined time has passed since the power outage occurred, the second monitoring unit 124 determines that the power outage is an in-house power outage and acquires first cause information indicating a "in-house power outage."

なお、実施形態2では、停電原因通知システム1は、第1監視部123及び計測ユニット15を備えず、第2監視部124のみを備えていてもよい(実施形態2の変形例1)。 In addition, in embodiment 2, the power outage cause notification system 1 may not include the first monitoring unit 123 and the measurement unit 15, but may include only the second monitoring unit 124 (variant 1 of embodiment 2).

こうして、系統停電時にサーバ30から提供される系統停電情報を常時監視することによっても、系統停電か宅内停電かを判断し、第1原因情報を取得できる。従って、サーバ30が存在しなくても、又は端末40とサーバ30との間が接続されていなくても、系統停電情報を停電情報に更に含めて端末40に提供できる。 In this way, by constantly monitoring the grid power outage information provided by server 30 during a grid power outage, it is possible to determine whether the power outage is a grid power outage or a home power outage and obtain first cause information. Therefore, even if server 30 does not exist or there is no connection between terminal 40 and server 30, grid power outage information can be further included in the power outage information and provided to terminal 40.

出力部13は、取得部122が取得した停電情報を、起動部121が起動したアプリ401に引き渡す。 The output unit 13 passes the power outage information acquired by the acquisition unit 122 to the app 401 launched by the launch unit 121.

アプリ401は、こうして主幹ブレーカ10から引き渡される停電情報を、端末40が有するディスプレイ等の出力デバイスを介して、上記顧客に通知する。 The app 401 notifies the customer of the power outage information thus received from the main breaker 10 via an output device such as a display on the terminal 40.

実施形態2の停電原因通知システム1は、受付部11を更に備える。 The power outage cause notification system 1 of embodiment 2 further includes a reception unit 11.

受付部11は、接続操作を受け付ける。接続操作とは、ブレーカ(主幹ブレーカ10)を端末40と通信可能に接続するための操作である。主幹ブレーカ10は、受付部11が受け付けた接続操作に応じて、端末40と通信可能に接続される。 The reception unit 11 receives a connection operation. The connection operation is an operation for connecting the breaker (main breaker 10) to the terminal 40 so that it can communicate with the breaker. In response to the connection operation received by the reception unit 11, the main breaker 10 is connected to the terminal 40 so that it can communicate with the breaker.

実施形態1の起動部121は、接続操作に応じて主幹ブレーカ10が端末40と接続された後、端末40のアプリ401を起動する。 In embodiment 1, the startup unit 121 starts the app 401 on the terminal 40 after the main breaker 10 is connected to the terminal 40 in response to a connection operation.

なお、受付部11は、切断操作も受け付けてもよい。切断操作とは、主幹ブレーカ10と端末40との間の接続を切断するための操作である。切断操作は、例えば、接続キー15Aの再押下でもよい。 The reception unit 11 may also receive a disconnection operation. A disconnection operation is an operation for severing the connection between the main breaker 10 and the terminal 40. The disconnection operation may be, for example, a re-press of the connection key 15A.

受付部11は、例えば、タッチパネルやキーボード等の入力デバイスを介して、接続操作等の操作を受け付ける。操作を受け付けるための入力デバイスは、例えば、主幹ブレーカ10に設けられるが、分電盤100内の、主幹ブレーカ以外の内器に設けられてもよい。または、入力デバイスは、分電盤100のフロントカバー(図示しない)等に設けられてもよいし、分電盤100とは別体(リモコン等:図示しない)でも構わない。 The reception unit 11 receives operations such as connection operations via an input device such as a touch panel or keyboard. The input device for receiving operations is provided, for example, in the main breaker 10, but may also be provided in an internal device other than the main breaker within the distribution board 100. Alternatively, the input device may be provided in the front cover (not shown) of the distribution board 100, or may be separate from the distribution board 100 (such as a remote control: not shown).

接続操作等の操作を受け付けるための入力デバイスは、例えば、計測ユニット15が有する接続キー15A(図10参照)である。接続操作は、接続キー15Aの押下であり、切断操作は、接続キー15Aの再押下でもよい。 The input device for accepting operations such as connection operations is, for example, the connection key 15A (see Figure 10) of the measurement unit 15. A connection operation is performed by pressing the connection key 15A, and a disconnection operation can be performed by pressing the connection key 15A again.

これによって、停電発生時に、顧客の判断で端末のアプリを起動できる。また、顧客が必要と判断した場合に限り、主幹ブレーカ10は端末40と通信を開始するので、通信量を抑制できる。さらに、電源部14がバッテリの場合、バッテリの消耗を防ぐことができる。 This allows the customer to launch the app on their device at their discretion in the event of a power outage. Furthermore, the main breaker 10 only starts communicating with the terminal 40 when the customer deems it necessary, which helps to reduce communication volume. Furthermore, if the power supply unit 14 is a battery, battery drain can be prevented.

実施形態2では、端末40は、サーバ30と常時通信可能に接続される。サーバ30は、端末40のアプリケーションソフトウェア201を通じて、上記顧客への情報提供を行う。提供される情報は、例えば、系統停電情報である。系統停電情報とは、系統停電に関する情報である。系統停電情報は、例えば、系統停電の原因、系統停電の範囲、復電の時刻、等に関する情報を含む。なお、系統停電情報は、電力系統201のサーバ(図示しない)から取得される。 In embodiment 2, the terminal 40 is connected to the server 30 so that it can communicate with the terminal 40 at all times. The server 30 provides information to the customer through the application software 201 of the terminal 40. The information provided is, for example, grid power outage information. The grid power outage information is information related to the grid power outage. The grid power outage information includes, for example, information related to the cause of the grid power outage, the extent of the grid power outage, the time of power restoration, etc. The grid power outage information is obtained from a server (not shown) of the power grid 201.

ただし、提供される情報は、系統停電情報以外の情報も含んでもよい。系統停電情報以外の情報とは、例えば、主幹ブレーカ10、及び主幹ブレーカ10以外のIoT機器、に関する機器情報である。機器情報は、例えば、GW303から取得される。 However, the information provided may also include information other than grid power outage information. Information other than grid power outage information is, for example, device information related to the master breaker 10 and IoT devices other than the master breaker 10. The device information is obtained, for example, from GW303.

詳しくは、GW303は、第2ネットワーク302に接続されている各種のIoT機器の機器情報を収集し、第2ネットワーク302を介してサーバ30に提供する。サーバ30は、GW303から提供された機器情報を、第1ネットワーク301を介して端末40のアプリ401に引き渡す。アプリ401は、サーバ30から引き渡された機器情報を、端末40が有するディスプレイ等の出力デバイスを介して、上記利用者に通知する。 In more detail, GW303 collects device information from various IoT devices connected to second network 302 and provides it to server 30 via second network 302. Server 30 passes the device information provided by GW303 to app 401 on terminal 40 via first network 301. App 401 notifies the user of the device information passed from server 30 via an output device such as a display on terminal 40.

実施形態2では、サーバ30が起動部121を備える。サーバ30の起動部121は、主幹ブレーカ10とサーバ30の間の接続が切断されたことに応じて、端末40のアプリ401を起動する。 In embodiment 2, the server 30 includes a startup unit 121. The startup unit 121 of the server 30 starts the app 401 of the terminal 40 in response to the disconnection of the connection between the main breaker 10 and the server 30.

なお、実施形態2では、系統停電中、主幹ブレーカ10は、電源部14からの電力で動作可能である一方、電源部14から電力供給を受けないGW303は、動作不能となる。このため、サーバ30の起動部121は、サーバ30とGW303との間の接続が切断されたことに応じて、端末40のアプリ401を起動する。 In the second embodiment, during a grid power outage, the main breaker 10 can operate using power from the power supply unit 14, but the GW 303, which does not receive power from the power supply unit 14, becomes inoperable. Therefore, the startup unit 121 of the server 30 starts the app 401 of the terminal 40 in response to the disconnection of the connection between the server 30 and the GW 303.

これにより、停電発生時に、主幹ブレーカ10(GW303)とサーバ30との間の接続が切れることを利用して、サーバ30が自動的に端末40のアプリ401を起動できる。 As a result, when a power outage occurs, the connection between the main breaker 10 (GW303) and the server 30 is cut off, allowing the server 30 to automatically start the app 401 on the terminal 40.

実施形態2では、主幹ブレーカ10は、端末40と常時通信可能に接続される。なお、系統停電中、主幹ブレーカ10の各部(11~13,121,123,124)は、電源部14からの電力で動作可能である。 In embodiment 2, the master breaker 10 is connected to the terminal 40 so that it can communicate with the terminal 40 at all times. During a power outage, each section of the master breaker 10 (11-13, 121, 123, 124) can operate using power from the power supply section 14.

サーバ30は、系統停電の発生時に、系統停電情報を少なくとも主幹ブレーカ10に提供する。なお、系統停電情報は、実施形態2では、端末のアプリ401を通じて上記顧客にも提供される。一方、実施形態1では、系統停電情報は、顧客にのみ提供され、主幹ブレーカ10には提供されない。 When a grid power outage occurs, the server 30 provides grid power outage information to at least the main breaker 10. In embodiment 2, the grid power outage information is also provided to the customer via the terminal app 401. In embodiment 1, on the other hand, the grid power outage information is provided only to the customer, not to the main breaker 10.

なお、実施形態1では、ブレーカ(主幹ブレーカ10)が、上記各部(121,122,13)を備える。ただし、上記各部(121,122,13)は、分電盤100内の、ブレーカ(主幹ブレーカ10)以外の内器(リミッタ等)、が備えていてもよい。 In embodiment 1, the breaker (main breaker 10) is equipped with the above-mentioned units (121, 122, 13). However, the above-mentioned units (121, 122, 13) may also be equipped with internal devices (such as limiters) other than the breaker (main breaker 10) within the distribution board 100.

または、上記各部(121,122,13)は、複数の機器に分散していてもよい。例えば、実施形態2では、サーバ30が起動部121を備え、ブレーカ(主幹ブレーカ10)は、起動部121以外の各部(121,13)を備える。 Alternatively, the above-mentioned units (121, 122, 13) may be distributed across multiple devices. For example, in embodiment 2, the server 30 includes the startup unit 121, and the breaker (master breaker 10) includes the units (121, 13) other than the startup unit 121.

ただし、上記各部(121,122,13)の所在は、実施形態1,2に限定されない。 However, the locations of the above-mentioned parts (121, 122, 13) are not limited to those in embodiments 1 and 2.

(2-4)計測ユニット
詳しくは、停電原因通知システム1は、計測ユニット15を更に備える。
(2-4) Measurement Unit More specifically, the power outage cause notification system 1 further includes a measurement unit 15 .

計測ユニット15は、第1電路203aに接続された電力計(図示しない)を少なくとも有する。実施形態1,2における計測ユニット15は、第2電路203bに接続された電流計(図示しない)、及び加速度計(図示しない)を更に有する。 The measurement unit 15 has at least a wattmeter (not shown) connected to the first electrical circuit 203a. In embodiments 1 and 2, the measurement unit 15 further has an ammeter (not shown) and an accelerometer (not shown) connected to the second electrical circuit 203b.

計測ユニット15は、第1電路203aの電力を上記電力計で少なくとも計測し、その計測結果である電力値を取得する。 The measurement unit 15 measures at least the power of the first electrical circuit 203a using the power meter and obtains the power value resulting from the measurement.

また、計測ユニット15は、第2電路203bの電流を上記電流計で計測し、その計測結果である電流値を取得する。 The measurement unit 15 also measures the current in the second electrical circuit 203b using the ammeter and obtains the current value resulting from the measurement.

さらに、計測ユニット15は、計測ユニット15自身の加速度を上記加速度計で計測し、その計測結果である加速度値を取得する。 Furthermore, the measurement unit 15 measures the acceleration of the measurement unit 15 itself using the accelerometer and obtains the acceleration value that is the measurement result.

なお、後述する第1監視部123は、計測ユニット15が計測した電流及び加速度を基に、宅内停電の原因が、過電流か、漏電か、地震か、を判断し、判断の結果を示す第2原因情報を更に取得する。 The first monitoring unit 123, which will be described later, determines whether the cause of the in-home power outage is an overcurrent, a ground fault, or an earthquake based on the current and acceleration measured by the measurement unit 15, and further obtains second cause information indicating the result of the determination.

これによって、宅内停電の原因が過電流か漏電か地震かを更に判断し、第2原因情報をも含む停電情報を迅速に提供できる。 This allows for further determination of whether the cause of the in-home power outage is an overcurrent, a power leak, or an earthquake, and allows for quick provision of power outage information that also includes information on the second cause.

なお、計測ユニット15は、実施形態1,2では、主幹ブレーカ10とは別体の専用ユニットであり、ブレーカ(主幹ブレーカ10)と常時通信可能に接続される。計測ユニット15と主幹ブレーカ10との間の接続は、実施形態1,2では近距離無線通信による接続であるが、有線接続でもよい。 In embodiments 1 and 2, the measurement unit 15 is a dedicated unit separate from the main breaker 10 and is connected to the breaker (main breaker 10) so that it can communicate with the breaker at all times. In embodiments 1 and 2, the connection between the measurement unit 15 and the main breaker 10 is via short-range wireless communication, but a wired connection is also possible.

ただし、計測ユニット15は、主幹ブレーカ10の構成要素であってもよい。例えば、少なくとも上記電力計が、主幹ブレーカ10に内蔵されていてもよい。また、上記電流計及び上記加速度計の少なくとも一方が、主幹ブレーカ10に更に内蔵されていてもよい。 However, the measurement unit 15 may also be a component of the main breaker 10. For example, at least the wattmeter may be built into the main breaker 10. Furthermore, at least one of the ammeter and the accelerometer may also be built into the main breaker 10.

または、計測ユニット15は、分電盤100内の、主幹ブレーカ10以外の内器(例えば、リミッタ)が備えていてもよいし、分電盤100の外部に設けられてもよい。計測ユニット15の計測結果を、主幹ブレーカ10の処理部12に引き渡すことが可能であれば、計測ユニット15の所在は問わない。 Alternatively, the measurement unit 15 may be provided in an internal device (e.g., a limiter) other than the main breaker 10 within the distribution board 100, or may be provided outside the distribution board 100. The location of the measurement unit 15 is not important as long as the measurement results of the measurement unit 15 can be transferred to the processing unit 12 of the main breaker 10.

(2-5)主幹ブレーカ
実施形態1,2の主幹ブレーカ10は、上記のような計測ユニット15の計測結果を基に、過電流、漏電、及び地震の各々の発生を検出し、トリップ状態となる。
(2-5) Main Breaker The main breaker 10 of the first and second embodiments detects the occurrence of an overcurrent, a ground fault, or an earthquake based on the measurement results of the measurement unit 15 as described above, and enters a trip state.

詳しくは、後述する処理部12が、計測ユニット15の計測結果を基に、過電流等が発生したか否かを判断する。そして、過電流等が発生したと判断した場合に、処理部12は、第1電路203a及び第2電路203bの間の接点を開閉する開閉機構(図示しない)、及び開閉機構を駆動する駆動回路(図示しない)、を介して接点を開放し、主幹ブレーカ10をトリップ状態に移行させてもよい。 More specifically, the processing unit 12, which will be described later, determines whether an overcurrent or the like has occurred based on the measurement results of the measurement unit 15. If it is determined that an overcurrent or the like has occurred, the processing unit 12 may open the contacts between the first electric circuit 203a and the second electric circuit 203b via a switching mechanism (not shown) that opens and closes the contacts, and a drive circuit (not shown) that drives the switching mechanism, thereby transitioning the main breaker 10 to a tripped state.

ただし、主幹ブレーカ10は、上記のような電子式のブレーカに限らず、バイメタルや電磁コイル等を利用してトリップ状態(スイッチ10Aがオフの状態)に移行する熱動式や電磁式のブレーカでもよい。この場合、主幹ブレーカ10には、スイッチ10Aのオン・オフを検知するセンサが設けられ、処理部12は、センサの検知結果を基に、トリップ状態か否かの判断を行う。 However, the main breaker 10 is not limited to the electronic type breaker described above; it may also be a thermal or electromagnetic breaker that uses a bimetal or electromagnetic coil to transition to a tripped state (switch 10A is off). In this case, the main breaker 10 is provided with a sensor that detects the on/off state of switch 10A, and the processing unit 12 determines whether or not the breaker is in a tripped state based on the sensor's detection results.

(2-6)バックアップ電源
停電原因通知システム1は、電源部14を更に備える。電源部14は、系統停電中、少なくとも取得部122、起動部121及び出力部13に、電力を供給する。実施形態1,2では、電源部14は、計測ユニット15、監視部(第1監視部123,第2監視部124)及び受付部11にも電力を供給する。
(2-6) Backup Power Supply The power outage cause notification system 1 further includes a power supply unit 14. During a grid power outage, the power supply unit 14 supplies power to at least the acquisition unit 122, the startup unit 121, and the output unit 13. In the first and second embodiments, the power supply unit 14 also supplies power to the measurement unit 15, the monitoring units (first monitoring unit 123, second monitoring unit 124), and the reception unit 11.

電源部14は、通常、バッテリである。バッテリは、例えば、使い切りであるが、充電式でもよい。実施形態1,2では、電源部14は、主幹ブレーカ10とは別体であり、分電盤100内に設けられる。ただし、電源部14は、主幹ブレーカ10に内蔵されていてもよいし、主幹ブレーカ10以外の内器に内蔵されていてもよい。 The power supply unit 14 is typically a battery. The battery may be, for example, disposable, but may also be rechargeable. In embodiments 1 and 2, the power supply unit 14 is separate from the main breaker 10 and is provided within the distribution board 100. However, the power supply unit 14 may also be built into the main breaker 10, or may be built into an internal device other than the main breaker 10.

または、電源部14は、例えば、少なくとも系統停電時に稼働する自家発電システムでもよい。 Alternatively, the power supply unit 14 may be, for example, a private power generation system that operates at least during a grid power outage.

(3)実施形態1
本開示の実施形態1に係る停電原因通知システム1は、例えば、図1に示すような電力供給システム2に用いられる。
(3) Embodiment 1
A power outage cause notification system 1 according to the first embodiment of the present disclosure is used in, for example, a power supply system 2 as shown in FIG. 1 .

(3-1)電力供給システム
図1の電力供給システム2は、電力系統201と、電力系統201から分電盤100を介して電力の供給を受ける負荷202と、を備える。分電盤100及び負荷202は、電力系統201を管理する電力会社の複数の顧客の各々、が住む住宅の内部(宅内)に配置される。以下で「顧客」とは、これら複数の顧客のうち一の顧客である。
(3-1) Power Supply System The power supply system 2 in Fig. 1 includes a power system 201 and loads 202 that receive power from the power system 201 via a distribution board 100. The distribution board 100 and the loads 202 are located inside (inside) the homes of multiple customers of the power company that manages the power system 201. Hereinafter, a "customer" refers to one of these multiple customers.

分電盤100は、主幹ブレーカ10と、2つ以上の分岐ブレーカ50とを備える。主幹ブレーカ10は、一次側が電力系統201と、二次側が2つ以上の分岐ブレーカ50の各々と、それぞれ接続される。分岐ブレーカ50には、1つ以上の負荷202が接続される。負荷202は、家電等の電気機器である。 The distribution board 100 comprises a main breaker 10 and two or more branch breakers 50. The main breaker 10 has its primary side connected to the power grid 201 and its secondary side connected to each of the two or more branch breakers 50. One or more loads 202 are connected to the branch breakers 50. The loads 202 are electrical devices such as home appliances.

また、主幹ブレーカ10は、顧客が利用可能な端末40と通信可能に接続される。端末40は、通常、宅内に位置するが、宅外に位置していてもよい。端末40は、例えば、スマートフォン等の携帯端末であるが、デスクトップPC等の固定端末でもよい。主幹ブレーカ10と端末40との間の通信は、例えば、Bluetooth(登録商標)、無線LAN(Local Area Network)等の近距離無線通信である。ただし、端末40が少なくとも宅内に位置する場合に主幹ブレーカ10と通信可能であれば、その方式は問わない。 The main breaker 10 is also connected to a terminal 40 that can be used by the customer so that it can communicate with it. The terminal 40 is typically located within the home, but may also be located outside the home. The terminal 40 is, for example, a mobile terminal such as a smartphone, but may also be a fixed terminal such as a desktop PC. Communication between the main breaker 10 and the terminal 40 is, for example, short-range wireless communication such as Bluetooth (registered trademark) or wireless LAN (Local Area Network). However, the communication method is not important as long as the terminal 40 can communicate with the main breaker 10 at least when located within the home.

なお、端末40は、実施形態2における端末40と同様、第1ネットワーク301を介してサーバ30と通信可能に接続されてもよい(実施形態1の変形例1)。 Note that, like the terminal 40 in embodiment 2, the terminal 40 may be communicably connected to the server 30 via the first network 301 (variant 1 of embodiment 1).

(3-2)停電原因通知システム
本実施形態の停電原因通知システム1は、図1に示すように、主幹ブレーカ10と、電源部14と、計測ユニット15と、端末40とを備える。
(3-2) Power Outage Cause Notification System As shown in FIG. 1, the power outage cause notification system 1 of this embodiment includes a main breaker 10, a power supply unit 14, a measurement unit 15, and a terminal 40.

また、主幹ブレーカ10は、図2に示すように、受付部11と、処理部12と、出力部13とを備える。さらに、処理部12は、起動部121と、取得部122と、監視部123とを備える。 As shown in FIG. 2, the main breaker 10 includes a reception unit 11, a processing unit 12, and an output unit 13. The processing unit 12 also includes a startup unit 121, an acquisition unit 122, and a monitoring unit 123.

主幹ブレーカ10を構成する各部(11~13及び121~123)は、通常、電力系統201からの電力で動作する。電源部14は、系統停電中に、主幹ブレーカ10を構成する各部(11~13及び121~123)が動作するための電力を供給する。 The components (11-13 and 121-123) that make up the main breaker 10 normally operate on power from the power grid 201. The power supply unit 14 supplies power for the components (11-13 and 121-123) that make up the main breaker 10 to operate during a grid power outage.

計測ユニット15は、主幹ブレーカ10と常時通信可能に接続される。計測ユニット15と主幹ブレーカ10との間の接続は、近距離無線通信による接続である。 The measurement unit 15 is connected to the main breaker 10 so that it can communicate at all times. The connection between the measurement unit 15 and the main breaker 10 is via short-range wireless communication.

計測ユニット15は、主幹ブレーカ10の一次側の電路203aの電力を電力計で計測する。また、計測ユニット15は、主幹ブレーカ10の二次側の電路203aの電流を電流計で計測する。さらに、計測ユニット15は、計測ユニット15自身の加速度を加速度計で計測する。そして、計測ユニット15は、当該3つの計測結果(電力値、電流値及び加速度値)を主幹ブレーカ10に引き渡す。 The measurement unit 15 measures the power of the circuit 203a on the primary side of the main breaker 10 using a wattmeter. The measurement unit 15 also measures the current of the circuit 203a on the secondary side of the main breaker 10 using an ammeter. Furthermore, the measurement unit 15 measures its own acceleration using an accelerometer. The measurement unit 15 then passes these three measurement results (power value, current value, and acceleration value) to the main breaker 10.

主幹ブレーカ10は、計測ユニット15の計測結果を基に、過電流、漏電、及び地震の各々の発生を検出し、トリップ状態となる。 Based on the measurement results of the measurement unit 15, the main breaker 10 detects the occurrence of overcurrent, leakage current, and earthquakes and enters a trip state.

端末40には、停電発生時に停電原因を通知するアプリケーションソフトウェア(アプリ)401がインストールされている。 Application software (app) 401 is installed on terminal 40, which notifies the user of the cause of a power outage when it occurs.

(3-2-1)主幹ブレーカ
主幹ブレーカ10を構成する受付部11は、各種の情報を受け付ける。各種の情報とは、例えば、接続操作、及び計測ユニット15の計測結果などである。
(3-2-1) Main Breaker The reception unit 11 included in the main breaker 10 receives various types of information, such as connection operations and measurement results from the measurement unit 15.

受付部11は、接続操作を受け付ける。接続操作は、停電の発生時に、顧客によって行われる。また、受付部11は、計測ユニット15の計測結果を受け付ける。 The reception unit 11 accepts connection operations. Connection operations are performed by customers when a power outage occurs. The reception unit 11 also accepts measurement results from the measurement unit 15.

処理部12は、各種の処理を行う。各種の処理とは、例えば、取得部122、起動部121及び監視部123の処理である。 The processing unit 12 performs various processes. These processes include, for example, the processes of the acquisition unit 122, the startup unit 121, and the monitoring unit 123.

また、処理部12は、図3のフローチャートで説明する各種の判断なども行う。 The processing unit 12 also performs various judgments as explained in the flowchart in Figure 3.

さらに、処理部12は、計測ユニット15の計測結果を基に、過電流等が発生したと判断した場合に、第1電路203a及び第2電路203bの間の接点を開閉する開閉機構(図示しない)、及び開閉機構を駆動する駆動回路(図示しない)、を介して接点を開放し、主幹ブレーカ10をトリップ状態に移行させる。 Furthermore, if the processing unit 12 determines, based on the measurement results of the measurement unit 15, that an overcurrent or the like has occurred, it opens the contacts between the first electric circuit 203a and the second electric circuit 203b via a switching mechanism (not shown) that opens and closes the contacts, and a drive circuit (not shown) that drives the switching mechanism, thereby transitioning the main breaker 10 to a tripped state.

出力部13は、各種の情報を出力する。各種の情報とは、例えば、停電情報、停電原因情報(第1停電原因情報、第2停電原因情報)、対処情報などである。 The output unit 13 outputs various types of information. Examples of such information include power outage information, power outage cause information (first power outage cause information, second power outage cause information), and response information.

なお、出力部13の出力は、通常、端末40のアプリ401への停電情報等の情報の引き渡しである。ただし、出力は、例えば、ディスプレイへの表示、スピーカからの音声出力、プリンタによるプリントアウト、他の装置への送信、記録媒体への記録などでもよい。なお、ディスプレイは、通常、端末40のディスプレイであるが、計測ユニット15のディスプレイ15B等でもよい。 The output of the output unit 13 is typically the transfer of information such as power outage information to the app 401 of the terminal 40. However, the output may also be, for example, a display on a display, audio output from a speaker, a printout by a printer, transmission to another device, or recording on a recording medium. The display is typically the display of the terminal 40, but may also be the display 15B of the measurement unit 15, etc.

処理部12は、受付部11が接続操作を受け付けた場合に、停電が発生したと判断する。接続操作が受け付けられていない場合は、停電は発生していないと判断される。 The processing unit 12 determines that a power outage has occurred if the reception unit 11 receives a connection operation. If the connection operation has not been received, it determines that a power outage has not occurred.

処理部12を構成する起動部121は、停電の発生時に、近距離無線通信により端末40のアプリ401を起動する。 The startup unit 121, which constitutes the processing unit 12, starts the app 401 on the terminal 40 via short-range wireless communication when a power outage occurs.

取得部122は、停電の発生時に、原因情報(第1原因情報、第2原因情報)及び対処情報を含む停電情報を、以下のように取得する。 When a power outage occurs, the acquisition unit 122 acquires power outage information including cause information (first cause information, second cause information) and response information as follows:

例えば、主幹ブレーカ10のメモリに、第1~第4対情報を含む対情報群が格納されている。 For example, a group of pair information including first to fourth pair information is stored in the memory of the main breaker 10.

監視部123が、計測ユニット15の計測結果を基に原因情報(第1原因情報、第2監視情報)を取得し、取得部122に引き渡す。取得部122は、監視部123から引き渡しを受けた原因情報に対応する対処情報を上記メモリから更に取得し、当該取得した原因情報及び当該取得した対処情報を含む停電情報を取得する。 The monitoring unit 123 acquires cause information (first cause information, second monitoring information) based on the measurement results of the measurement unit 15 and passes it to the acquisition unit 122. The acquisition unit 122 further acquires from the memory the response information corresponding to the cause information received from the monitoring unit 123, and acquires power outage information including the acquired cause information and the acquired response information.

詳しくは、監視部123は、計測ユニット15の計測結果を常時監視し、停電が系統停電か宅内停電かを判断して、判断結果を示す第1原因情報を取得する。例えば、停電が系統停電であると判断した場合、監視部123は、“系統停電”を示す第1原因情報を取得し、取得部122に引き渡す。 In more detail, the monitoring unit 123 constantly monitors the measurement results of the measurement unit 15, determines whether the power outage is a grid power outage or a home power outage, and acquires first cause information indicating the determination result. For example, if the power outage is determined to be a grid power outage, the monitoring unit 123 acquires first cause information indicating a "grid power outage" and passes it to the acquisition unit 122.

取得部122は、監視部123から引き渡された“系統停電”を示す第1原因情報に対応する第1対処情報を上記メモリから更に取得し、当該“系統停電”を示す第1原因情報及び当該取得した第1対処情報を含む停電情報を取得する。 The acquisition unit 122 further acquires from the memory first response information corresponding to the first cause information indicating a "grid power outage" delivered from the monitoring unit 123, and acquires power outage information including the first cause information indicating the "grid power outage" and the acquired first response information.

なお、ここで取得される停電情報は、例えば“停電が発生しました。停電原因は、電力系統のトラブルです。電力系統の復電まで、そのままお待ちください。”等のメッセージであってもよい。 The power outage information obtained here may be a message such as, "A power outage has occurred. The cause of the power outage is a problem with the power system. Please wait until power is restored to the power system."

一方、停電が宅内停電であると判断した場合、監視部123は、“宅内停電”を示す第1原因情報を取得する。また、監視部123は、計測結果を基に、宅内停電の原因が過電流か漏電か地震かを更に判断し、判断結果を示す第2停電情報を取得する。そして、第1監視部123は、“宅内停電”を示す第1原因情報、並びに“過電流”,“漏電”及び“地震”のいずれかを示す第2原因情報を、取得部122に引き渡す。 On the other hand, if the power outage is determined to be an in-house power outage, the monitoring unit 123 acquires first cause information indicating an "in-house power outage." The monitoring unit 123 then further determines, based on the measurement results, whether the cause of the in-house power outage is an overcurrent, a ground fault, or an earthquake, and acquires second power outage information indicating the determination result. The first monitoring unit 123 then passes the first cause information indicating an "in-house power outage" and the second cause information indicating either an "overcurrent," "ground fault," or "earthquake" to the acquisition unit 122.

取得部122は、監視部123から引き渡された第2原因情報(“過電流”,“漏電”及び“地震”のいずれか)に対応する対処情報(第2~第4対処情報のいずれか)を上記メモリから更に取得し、当該“宅内停電”を示す第1原因情報、及び当該取得した対処情報、を含む停電情報を取得する。 The acquisition unit 122 further acquires from the memory the response information (any of the second to fourth response information) corresponding to the second cause information (any of "overcurrent," "earthquake," or "earthquake") delivered from the monitoring unit 123, and acquires power outage information including the first cause information indicating the "in-home power outage" and the acquired response information.

例えば、監視部123から、“宅内停電”を示す第1原因情報、及び“漏電”を示す第2原因情報が引き渡された場合、取得部122は、当該“漏電”を示す第2原因情報に対応する第3対処情報をメモリから取得する。そして、監視部123は、当該引き渡された“宅内停電”を示す第1原因情報、当該取得した“漏電”を示す第2原因情報、及び当該取得した第3対処情報、を含む停電情報を取得する。 For example, if the monitoring unit 123 delivers first cause information indicating an "in-house power outage" and second cause information indicating a "power leakage," the acquisition unit 122 acquires from memory third response information corresponding to the second cause information indicating the "power leakage." The monitoring unit 123 then acquires power outage information including the delivered first cause information indicating the "in-house power outage," the acquired second cause information indicating the "power leakage," and the acquired third response information.

なお、ここで取得される停電情報は、例えば“停電が発生しました。停電原因は、宅内のブレーカの動作です。漏電の可能性があります。以下の手順で対処して下さい。分岐ブレーカのスイッチを全て切る。主幹ブレーカのスイッチを入れる。分岐ブレーカのスイッチを順番に入れていき・・・”等のメッセージであってもよい。 The power outage information obtained here may be a message such as, "A power outage has occurred. The cause of the power outage is the operation of a breaker in the house. There may be a power leak. Please take action by following the steps below. Turn off all branch breakers. Turn on the main breaker. Turn on the branch breakers in order..."

取得部122は、監視部123が取得した停電情報を出力部13に引き渡し、出力部13は、当該停電情報を更に端末40のアプリ401に引き渡す。アプリ401は、引き渡された停電情報を、端末40のディスプレイに表示する。これによって、端末40のディスプレイには、例えば、図9に示すような画面が表示される。 The acquisition unit 122 passes the power outage information acquired by the monitoring unit 123 to the output unit 13, and the output unit 13 further passes the power outage information to the app 401 of the terminal 40. The app 401 displays the passed power outage information on the display of the terminal 40. As a result, a screen such as that shown in FIG. 9 is displayed on the display of the terminal 40.

図9の画面には、停電情報“停電が発生しました。停電原因は、宅内のブレーカの動作です。漏電の可能性があります。以下の手順で対処して下さい。分岐ブレーカのスイッチを全て切る。主幹ブレーカのスイッチを入れる。分岐ブレーカのスイッチを順番に入れていき・・・”が含まれる。 The screen in Figure 9 includes the following information about the power outage: "A power outage has occurred. The cause of the power outage is the operation of a breaker in your home. There may be a power leak. Please take the following steps to resolve the issue. Switch off all branch breakers. Switch on the main breaker. Switch on the branch breakers in order..."

顧客は、このような停電情報を参照して、停電原因である漏電に対する適切な対処を行うことができる。 Customers can refer to this power outage information and take appropriate measures to address the power leakage that is causing the outage.

(3-2-2)停電原因通知システムの動作
本実施形態における停電原因通知システム1は、図4のフローチャートに従って動作する。
(3-2-2) Operation of Power Outage Cause Notification System The power outage cause notification system 1 in this embodiment operates according to the flowchart of FIG.

主幹ブレーカ10を構成する処理部12は、停電が発生したか否かを判断する(ステップS11)。 The processing unit 12 that constitutes the main breaker 10 determines whether a power outage has occurred (step S11).

この実施形態では、処理部12は、受付部11が起動操作を受け付けた場合に、停電が発生したと判断する。起動操作が受け付けられていない場合には、停電は発生していないと判断される。停電が発生したと判断された場合、処理はステップS12に進む。停電が発生していないと判断された場合、処理はステップS18に進む。 In this embodiment, the processing unit 12 determines that a power outage has occurred if the reception unit 11 receives a startup operation. If a startup operation has not been received, it determines that a power outage has not occurred. If it is determined that a power outage has occurred, the process proceeds to step S12. If it is determined that a power outage has not occurred, the process proceeds to step S18.

処理部12は、主幹ブレーカ10を端末40と通信可能に接続する(ステップS12)。詳しくは、ステップS11で受け付けられた起動操作に応じて、主幹ブレーカ10の通信モジュールが、端末40の通信モジュールとの間で、近距離無線による通信を開始する。 The processing unit 12 connects the master breaker 10 to the terminal 40 so that they can communicate with each other (step S12). Specifically, in response to the startup operation received in step S11, the communication module of the master breaker 10 starts short-range wireless communication with the communication module of the terminal 40.

主幹ブレーカ10の起動部121は、端末40のアプリ401を起動する(ステップS13)。詳しくは、起動部121は、アプリ401に対する起動命令を近距離無線で端末40に送信し、端末40が当該起動命令を受信してアプリ401を起動する。 The startup unit 121 of the main breaker 10 starts the app 401 of the terminal 40 (step S13). More specifically, the startup unit 121 transmits a startup command for the app 401 to the terminal 40 via short-range wireless communication, and the terminal 40 receives the startup command and starts the app 401.

取得部122は、原因情報を取得する(ステップS14)。詳しくは、取得部122は、計測ユニット15の計測結果を基に、第1原因情報を取得し、第1原因情報が“宅内停電”の場合は、第2原因情報を更に取得する。 The acquisition unit 122 acquires cause information (step S14). Specifically, the acquisition unit 122 acquires first cause information based on the measurement results of the measurement unit 15, and if the first cause information is "in-home power outage," it further acquires second cause information.

例えば、計測ユニット15の監視結果には、第1電路203aの電力値、第2電路203bの電流値、及び加速度値が含まれており、取得部122は、電力値が第1閾値以下(例えば、電力値=0)の場合、又は電流値が第2閾値以下(例えば、電流値=0)の場合に、停電が発生したと判断する。 For example, the monitoring results of the measurement unit 15 include the power value of the first electrical circuit 203a, the current value of the second electrical circuit 203b, and the acceleration value, and the acquisition unit 122 determines that a power outage has occurred when the power value is equal to or less than a first threshold value (e.g., power value = 0) or when the current value is equal to or less than a second threshold value (e.g., current value = 0).

停電が発生したと判断した場合、取得部122は、当該停電が系統停電か宅内停電かを更に判断する。詳しくは、電力値が第1閾値以下(例えば、電力値=0)である場合、取得部122は、系統停電が発生したと判断する。一方、電力値が第1閾値より大(例えば、電力値>0)であり、かつ電流値が第2閾値以下(例えば、電流値=0)の場合、取得部122は、宅内停電が発生したと判断する。そして、取得部122は、上記判断結果を基に、“系統停電”又は“宅内停電”を示す第1原因情報を取得する。 If it is determined that a power outage has occurred, the acquisition unit 122 further determines whether the power outage is a grid power outage or a home power outage. More specifically, if the power value is equal to or less than a first threshold (e.g., power value = 0), the acquisition unit 122 determines that a grid power outage has occurred. On the other hand, if the power value is greater than the first threshold (e.g., power value > 0) and the current value is equal to or less than a second threshold (e.g., current value = 0), the acquisition unit 122 determines that a home power outage has occurred. Then, based on the above determination result, the acquisition unit 122 acquires first cause information indicating a "grid power outage" or a "home power outage."

宅内停電が発生したと判断した場合、取得部122は、計測結果に含まれる電流値電流値及び加速度値を基に、当該宅内停電の原因が過電流か漏電か地震かを更に判断する。詳しくは、例えば、電流値が第3閾値を超える場合は、過電流と判断される。また、電流値には、第2電路203bでの行きと帰りの2つの電流値(L1相又はL2相の電力線の電流値、及び中性線の電流値)が含まれており、当該2つの電流値の差分が第4閾値を超える場合は、漏電と判断される。さらに、加速度値が第5閾値を超える場合は、地震と判断される。 If it is determined that a home power outage has occurred, the acquisition unit 122 further determines whether the cause of the home power outage is an overcurrent, a ground fault, or an earthquake, based on the current value and acceleration value included in the measurement results. In more detail, for example, if the current value exceeds the third threshold, it is determined to be an overcurrent. Furthermore, the current value includes two current values (the current value of the L1 phase or L2 phase power line, and the current value of the neutral line) for the outbound and return currents in the second electrical circuit 203b, and if the difference between these two current values exceeds the fourth threshold, it is determined to be a ground fault. Furthermore, if the acceleration value exceeds the fifth threshold, it is determined to be an earthquake.

そして、取得部122は、上記判断結果を基に、“過電流”、“漏電”及び“地震”のいずれかを示す第2原因情報を取得する。 Then, based on the above determination result, the acquisition unit 122 acquires second cause information indicating either "overcurrent," "electric leakage," or "earthquake."

次に、取得部122は、ステップS14で取得した原因情報に対応する対策情報を取得する(ステップS15)。詳しくは、メモリに、原因情報と対策情報との対の集合が格納されており、取得部122は、取得した原因情報と対になる対策情報をメモリから取得する。 Next, the acquisition unit 122 acquires countermeasure information corresponding to the cause information acquired in step S14 (step S15). More specifically, a set of pairs of cause information and countermeasure information is stored in memory, and the acquisition unit 122 acquires countermeasure information that pairs with the acquired cause information from memory.

取得部は121、ステップS14で取得した原因情報、及びステップS15で取得した対策情報、を含む停電情報を取得する(ステップS16)。 The acquisition unit 121 acquires power outage information including the cause information acquired in step S14 and the countermeasure information acquired in step S15 (step S16).

出力部13は、ステップS16で取得された停電情報を、端末40のアプリ401に引き渡す(ステップS17)。詳しくは、出力部13は、停電情報を近距離無線で端末40に送信し、端末40が当該停電情報を受信してアプリ401に引き渡す。その後、処理はステップS11に戻る。 The output unit 13 passes the power outage information acquired in step S16 to the app 401 of the terminal 40 (step S17). Specifically, the output unit 13 transmits the power outage information to the terminal 40 via short-range wireless communication, and the terminal 40 receives the power outage information and passes it to the app 401. Then, processing returns to step S11.

処理部12は、切断条件を満たすか否かを判断する(ステップS18)。切断条件とは、主幹ブレーカ10と端末40との間の接続を切断するための条件である。切断条件は、例えば、“切断操作が受け付けられたこと”、“何ら操作が受け付けられない無操作状態が、予め決められた時間以上継続したこと”等である。切断条件を満たす場合、処理はステップS19に進む。切断条件を満たさない場合、処理はステップS11に戻る。 The processing unit 12 determines whether the disconnection conditions are met (step S18). The disconnection conditions are conditions for severing the connection between the main breaker 10 and the terminal 40. Examples of disconnection conditions include "a disconnection operation has been accepted" or "a no-operation state in which no operation is accepted has continued for a predetermined period of time or longer." If the disconnection conditions are met, processing proceeds to step S19. If the disconnection conditions are not met, processing returns to step S11.

処理部12は、主幹ブレーカ10と端末40との間の接続を切断する(ステップS19)。詳しくは、例えば、切断操作の受け付けに応じて、主幹ブレーカ10の通信モジュールが、端末40の通信モジュールとの間の通信を終了する。その後、処理はステップS11に戻る。 The processing unit 12 disconnects the connection between the main breaker 10 and the terminal 40 (step S19). In more detail, for example, in response to receiving the disconnection operation, the communication module of the main breaker 10 terminates communication with the communication module of the terminal 40. Then, processing returns to step S11.

(3-3)実施形態1の変形例1
実施形態1の変形例1に係る停電原因通知システム1は、実施形態1の停電原因通知システム1において、端末40に、系統停電の発生時に系統停電情報を提供するサーバ30、との通信機能を持たせたものである。
(3-3) Modification 1 of the First Embodiment
The power outage cause notification system 1 according to variant 1 of embodiment 1 is the power outage cause notification system 1 of embodiment 1, in which the terminal 40 is provided with a communication function with a server 30 that provides grid power outage information when a grid power outage occurs.

この変形例では、実施形態1のものと同様の通知に加えて、系統停電が発生した場合に、サーバ30から提供される系統停電情報を、更に顧客に通知することができる。 In this variant, in addition to the same notifications as in embodiment 1, in the event of a grid power outage, customers can also be notified of grid power outage information provided by server 30.

(3-4)実施形態1の変形例2
実施形態1の変形例2に係る停電原因通知システム1は、実施形態1の停電原因通知システム1から、計測ユニット15及び監視部123を除いたものである。
(3-4) Modification 2 of Embodiment 1
The power outage cause notification system 1 according to the second modification of the first embodiment is the power outage cause notification system 1 of the first embodiment from which the measurement unit 15 and the monitoring unit 123 have been removed.

この変形例でも、停電が発生した場合に、サーバ30からの系統停電情報を基に、当該停電が系統停電か宅内停電かを判断し、その判断結果(“系統停電”又は“宅内停電”)を示す第1原因情報を顧客に通知することはできる。 Even in this variant, when a power outage occurs, it is possible to determine whether the power outage is a power grid power outage or a home power outage based on the power grid power outage information from server 30, and notify the customer of the first cause information indicating the determination result ("power grid power outage" or "home power outage").

(3-5)実施形態1の変形例3
実施形態1の変形例3に係る停電原因通知システム1は、実施形態1の停電原因通知システム1から、計測ユニット15及び監視部123並びに電源部14を除いたものである。
(3-5) Modification 3 of Embodiment 1
The power outage cause notification system 1 according to the third modification of the first embodiment is the power outage cause notification system 1 of the first embodiment, except that the measurement unit 15, the monitoring unit 123, and the power supply unit 14 are removed.

この変形例でも、宅内停電が発生した場合に、“宅内停電”を示す第1原因情報を顧客に通知することはできる。 Even with this variant, if a power outage occurs within the home, the customer can be notified of the first cause information indicating "power outage within the home."

(4)実施形態2
本開示の実施形態2に係る停電原因通知システム1は、例えば、図4に示すような電力供給システム2に用いられる。
(4) Embodiment 2
The power outage cause notification system 1 according to the second embodiment of the present disclosure is used in, for example, a power supply system 2 as shown in FIG. 4 .

(4-1)電力供給システム
図4の電力供給システム2は、図1の電力供給システム2において、第1ネットワーク301に接続されたサーバ30と、第1ネットワーク301及び第2ネットワーク302の各々に接続されたGW303とを更に備える。
(4-1) Power Supply System The power supply system 2 of FIG. 4 is the power supply system 2 of FIG. 1, and further includes a server 30 connected to the first network 301 and a GW 303 connected to each of the first network 301 and the second network 302.

負荷202は、第2ネットワーク302に接続されている。 The load 202 is connected to the second network 302.

(4-2)停電原因通知システム
本実施形態の停電原因通知システム1は、図4に示すように、主幹ブレーカ10と、電源部14と、計測ユニット15と、端末40とを備える。すなわち、本実施形態の停電原因通知システム1は、実施形態1の停電原因通知システム1(図1参照)と同様に構成される。
(4-2) Power Outage Cause Notification System As shown in Fig. 4, the power outage cause notification system 1 of this embodiment includes a main breaker 10, a power supply unit 14, a measurement unit 15, and a terminal 40. That is, the power outage cause notification system 1 of this embodiment is configured in the same manner as the power outage cause notification system 1 of the first embodiment (see Fig. 1).

ただし、本実施形態の停電原因通知システム1では、計測ユニット15が第2ネットワーク302に接続されている。また、サーバ30が起動部121を備えている。 However, in the power outage cause notification system 1 of this embodiment, the measurement unit 15 is connected to the second network 302. In addition, the server 30 is equipped with a startup unit 121.

主幹ブレーカ10は、計測ユニット15、第2ネットワーク302、GW303及び第1ネットワーク301を介して、サーバ30と通信可能に接続される。主幹ブレーカ10とサーバ30との間の接続は、常時接続である。 The main breaker 10 is communicatively connected to the server 30 via the measurement unit 15, the second network 302, the GW 303, and the first network 301. The connection between the main breaker 10 and the server 30 is always connected.

サーバ30は、系統停電の発生時に、第1ネットワーク301、GW303、第2ネットワーク302及び計測ユニット15を介して、系統停電情報を主幹ブレーカ10に提供する。また、サーバ30は、系統停電の発生時に、第1ネットワーク301、及び端末40のアプリ401を介して、顧客に系統停電情報を通知する。 When a grid power outage occurs, the server 30 provides grid power outage information to the main breaker 10 via the first network 301, GW 303, second network 302, and measurement unit 15. Furthermore, when a grid power outage occurs, the server 30 notifies the customer of the grid power outage information via the first network 301 and the app 401 on the terminal 40.

(4-2-1)サーバ
本実施形態のサーバ30は、図5に示すように、受付部31と、処理部32と、出力部33とを備える。処理部32は、起動部121を備える。
5, the server 30 of this embodiment includes a receiving unit 31, a processing unit 32, and an output unit 33. The processing unit 32 includes a starting unit 121.

受付部31は、各種の情報を受け付ける。各種の情報とは、例えば、系統停電情報である。受付部31は、例えば、系統停電の発生時に、電力会社のサーバ(図示しない)から提供される系統停電情報を受け付ける。 The reception unit 31 receives various types of information. Examples of such information include grid power outage information. For example, the reception unit 31 receives grid power outage information provided by a power company's server (not shown) when a grid power outage occurs.

処理部32は、各種の処理を行う。各種の処理とは、例えば、起動部121の処理である。また、処理部32は、図7のフローチャートで説明する各種の判断なども行う。各種の判断とは、例えば、サーバ30と主幹ブレーカ10との接続が切断されたか否かの判断、系統停電情報が取得されたか否かの判断などである。 The processing unit 32 performs various processes. For example, these processes are the processes of the startup unit 121. The processing unit 32 also performs various determinations, which are explained in the flowchart of FIG. 7. For example, these determinations include determining whether the connection between the server 30 and the main breaker 10 has been disconnected, and determining whether grid power outage information has been acquired.

処理部32を構成する起動部121は、サーバ30と主幹ブレーカ10(GW303)との接続が切断された場合に、第1ネットワーク301を介して端末40のアプリを起動する。 The startup unit 121, which constitutes the processing unit 32, starts the app on the terminal 40 via the first network 301 when the connection between the server 30 and the main breaker 10 (GW303) is disconnected.

出力部33は、各種の情報を出力する。各種の情報とは、例えば、系統停電情報である。 The output unit 33 outputs various information. Examples of such information include grid power outage information.

なお、出力部33の出力は、通常、主幹ブレーカ10への情報の送信、及び端末40のアプリ401への情報の引き渡しである。 The output of the output unit 33 typically involves sending information to the main breaker 10 and passing information to the app 401 on the terminal 40.

(4-2-2)主幹ブレーカ
本実施形態の主幹ブレーカ10は、図6に示すように、受付部11と、処理部12と、出力部13とを備える。処理部12は、取得部122と、第1監視部123と、第2監視部124とを備える。
6, the main breaker 10 of this embodiment includes a reception unit 11, a processing unit 12, and an output unit 13. The processing unit 12 includes an acquisition unit 122, a first monitoring unit 123, and a second monitoring unit 124.

すなわち、本実施形態の主幹フレーカ1は、実施形態1の主幹ブレーカ10において、起動部121に代えて、第1監視部123及び第2監視部124を備える。 In other words, the main breaker 1 of this embodiment is the main breaker 10 of embodiment 1, except that it is equipped with a first monitoring unit 123 and a second monitoring unit 124 instead of the starting unit 121.

受付部11は、計測ユニット15の計測結果、及びサーバ30からの系統停電情報を受け付ける。 The reception unit 11 receives the measurement results from the measurement unit 15 and grid power outage information from the server 30.

すなわち、本実施形態の受付部11は、実施形態1の受付部11において、顧客による接続操作に代えて、サーバ30からの系統停電情報を受け付ける。 In other words, the reception unit 11 of this embodiment receives grid power outage information from the server 30 instead of the connection operation by the customer, as in the reception unit 11 of embodiment 1.

処理部12は、例えば、取得部122、第1監視部123及び第2監視部124の処理を行う。 The processing unit 12 performs, for example, the processing of the acquisition unit 122, the first monitoring unit 123, and the second monitoring unit 124.

また、処理部12は、図8のフローチャートで説明する各種の判断なども行う。さらに、処理部12は、実施形態1の処理部12と同様、計測ユニット15の計測結果を基に、過電流等が発生したと判断した場合に、主幹ブレーカ10をトリップ状態に移行させる。 The processing unit 12 also performs various determinations, as explained in the flowchart of Figure 8. Furthermore, similar to the processing unit 12 in embodiment 1, if the processing unit 12 determines that an overcurrent or the like has occurred based on the measurement results of the measurement unit 15, it transitions the main breaker 10 to a trip state.

出力部13は、実施形態1の出力部13と同様、停電情報などの情報を出力する。 The output unit 13 outputs information such as power outage information, similar to the output unit 13 in embodiment 1.

処理部12を構成する第1監視部123は、実施形態1における監視部123と同じものである。 The first monitoring unit 123 that constitutes the processing unit 12 is the same as the monitoring unit 123 in embodiment 1.

第2監視部124は、サーバ30から提供される系統停電情報を常時監視し、停電が系統停電か宅内停電かを判断して、判断結果を示す第1原因情報を取得する。そして、第2監視部124は、取得した第1原因情報を取得部122に引き渡す。 The second monitoring unit 124 constantly monitors the grid power outage information provided by the server 30, determines whether the power outage is a grid power outage or a home power outage, and acquires first cause information indicating the determination result. The second monitoring unit 124 then passes the acquired first cause information to the acquisition unit 122.

取得部122は、実施形態1の取得部122と同様、停電の発生時に、原因情報(第1原因情報、第2原因情報)及び対処情報を含む停電情報を取得する。 Similar to the acquisition unit 122 in embodiment 1, when a power outage occurs, the acquisition unit 122 acquires power outage information including cause information (first cause information, second cause information) and response information.

ただし、本実施形態の取得部122は、第1監視部123又は第2監視部124が“系統停電”を示す第1原因情報を取得した場合に、当該“系統停電”を示す第1原因情報と、当該第1原因情報に対応する第1対処情報と、を含む停電情報を取得する。 However, in this embodiment, when the first monitoring unit 123 or the second monitoring unit 124 acquires first cause information indicating a "grid power outage," the acquisition unit 122 acquires power outage information including the first cause information indicating the "grid power outage" and first response information corresponding to the first cause information.

また、取得部122は、第1監視部123が“宅内停電”を示す第1原因情報と、第2原因情報(“過電流”,“漏電”及び“地震”のいずれか)と、を取得した場合に、当該“宅内停電”を示す第1原因情報と、当該第2原因情報と、当該第2原因情報に対応する対処情報(第2~第4原因情報のいずれか)と、を含む停電情報を取得する。 Furthermore, when the first monitoring unit 123 acquires first cause information indicating an "in-home power outage" and second cause information (any of "overcurrent," "earthquake," or "earthquake"), the acquisition unit 122 acquires power outage information including the first cause information indicating the "in-home power outage," the second cause information, and handling information corresponding to the second cause information (any of the second to fourth cause information).

(4-2-3)停電原因通知システムの動作
本実施形態では、サーバ30が、図7のフローチャートに従って動作する。なお、顧客の数が2以上の場合、図7のステップS31,S13,S32及びS33の処理が、2以上の顧客に対応する2以上の顧客識別子の各々について、順次又は並列に実行される。
(4-2-3) Operation of the Power Outage Cause Notification System In this embodiment, the server 30 operates according to the flowchart in Fig. 7. Note that, if the number of customers is two or more, the processes of steps S31, S13, S32, and S33 in Fig. 7 are executed sequentially or in parallel for each of two or more customer identifiers corresponding to two or more customers.

サーバ30を構成する処理部32は、主幹ブレーカ10(又はGW301)とサーバ30自身との間の接続が切断されたか否かを判断する(ステップS31)。 The processing unit 32 that constitutes the server 30 determines whether the connection between the main breaker 10 (or GW301) and the server 30 itself has been disconnected (step S31).

この実施形態では、主幹ブレーカ10(又はGW301)とサーバ30自身との間の接続が切断された場合に、停電が発生したと判断され、接続が切断されていない場合には、停電は発生していないと判断される。接続が切断された場合、処理はステップS13に進む。接続が切断されていない場合、処理はステップS33に進む。 In this embodiment, if the connection between the main breaker 10 (or GW301) and the server 30 itself is disconnected, it is determined that a power outage has occurred; if the connection is not disconnected, it is determined that a power outage has not occurred. If the connection is disconnected, processing proceeds to step S13. If the connection is not disconnected, processing proceeds to step S33.

サーバ30の起動部121は、端末40のアプリ401を起動する(ステップS13)。詳しくは、起動部121は、アプリ401に対する起動命令を第1ネットワーク301を介して端末40に送信し、端末40が当該起動命令を受信してアプリ401を起動する。その後、処理はステップS31に戻る。 The launch unit 121 of the server 30 launches the app 401 on the terminal 40 (step S13). Specifically, the launch unit 121 sends a launch command for the app 401 to the terminal 40 via the first network 301, and the terminal 40 receives the launch command and launches the app 401. Then, the process returns to step S31.

処理部32は、系統停電情報が取得されたか否かを判断する(ステップS32)。詳しくは、系統停電が発生すると、電力系統201のサーバ(図示しない)によって系統停電情報が取得され、電力系統201のサーバからサーバ30に当該系統停電情報が提供される。サーバ30の受付部31が当該系統停電情報を受け付けると、処理部32は、系統停電情報が取得されたと判断する。系統停電情報が受け付けられていなければ、処理部32は、系統停電情報は取得されていないと判断する。 The processing unit 32 determines whether grid power outage information has been acquired (step S32). More specifically, when a grid power outage occurs, the server (not shown) of the power grid 201 acquires the grid power outage information, and the server of the power grid 201 provides the grid power outage information to the server 30. When the reception unit 31 of the server 30 receives the grid power outage information, the processing unit 32 determines that the grid power outage information has been acquired. If the grid power outage information has not been received, the processing unit 32 determines that the grid power outage information has not been acquired.

系統停電情報が取得された場合、処理はステップS33に進む。系統停電情報が取得されていない場合、処理はステップS11に戻る。 If grid power outage information has been acquired, processing proceeds to step S33. If grid power outage information has not been acquired, processing returns to step S11.

出力部33は、ステップS32で取得された系統停電情報を端末40のアプリに引き渡す(ステップS33)。詳しくは、出力部33は、系統停電情報を第1ネットワーク301を介して端末40に送信し、端末40が当該系統停電情報を受信してアプリ401に引き渡す。その後、処理はステップS11に戻る。 The output unit 33 passes the grid power outage information acquired in step S32 to the app on the terminal 40 (step S33). Specifically, the output unit 33 transmits the grid power outage information to the terminal 40 via the first network 301, and the terminal 40 receives the grid power outage information and passes it to the app 401. Then, processing returns to step S11.

本実施形態の停電原因通知システム1は、図8のフローチャートに従って動作する。 The power outage cause notification system 1 of this embodiment operates according to the flowchart in Figure 8.

図8のフローチャートは、図3のフローチャートにおいて、5つのステップS11~S13,S18及びS19を、下記2つのステップS41及びS42に置き換えたもののである。 The flowchart in Figure 8 is the same as the flowchart in Figure 3, except that the five steps S11 to S13, S18, and S19 have been replaced with the following two steps S41 and S42.

なお、顧客の数が2以上の場合、2以上の顧客に対応する2以上の停電原因通知システム1の各々が、図8のステップS41,S42及びS14~S17の処理を実行する。 If there are two or more customers, each of the two or more power outage cause notification systems 1 corresponding to the two or more customers executes the processes of steps S41, S42, and S14 to S17 in FIG. 8.

主幹ブレーカ10を構成する処理部12は、計測ユニット15の計測結果及びサーバ30からの系統停電情報を監視する(ステップS41)。詳しくは、計測ユニット15の計測結果が、主幹ブレーカ10の処理部12に引き渡され、処理部12を構成する第1監視部123が、当該計測結果を監視する。また、サーバ30からの系統停電情報を受付部31が受け付け、処理部12を構成する第2監視部124が、当該系統停電情報を監視する。 The processing unit 12 constituting the main breaker 10 monitors the measurement results of the measurement unit 15 and the grid power outage information from the server 30 (step S41). Specifically, the measurement results of the measurement unit 15 are handed over to the processing unit 12 of the main breaker 10, and the first monitoring unit 123 constituting the processing unit 12 monitors the measurement results. In addition, the receiving unit 31 receives the grid power outage information from the server 30, and the second monitoring unit 124 constituting the processing unit 12 monitors the grid power outage information.

処理部12は、停電が発生したか否かを判断する(ステップS42)。この実施形態では、処理部12は、ステップS41の監視結果を基に、停電が発生したか否かを判断する。ここで処理部12が行う判断は、図3のステップS14で取得部122が行った判断と同様である。すなわち、処理部12は、監視結果に含まれる電力値が第1閾値以下の場合、又は監視結果に含まれる電流値が第2閾値以下の場合に、停電が発生したと判断する。その後、ステップS14に進む。 The processing unit 12 determines whether a power outage has occurred (step S42). In this embodiment, the processing unit 12 determines whether a power outage has occurred based on the monitoring results of step S41. The determination made by the processing unit 12 here is the same as the determination made by the acquisition unit 122 in step S14 of FIG. 3. That is, the processing unit 12 determines that a power outage has occurred if the power value included in the monitoring results is equal to or less than the first threshold value, or if the current value included in the monitoring results is equal to or less than the second threshold value. Then, the processing proceeds to step S14.

ステップS14~S17の処理は、実施形態1におけるものと同様であり、説明を省略する。 The processing in steps S14 to S17 is the same as in embodiment 1, so a detailed explanation will be omitted.

(4-3)実施形態2の変形例1
実施形態2の変形例1に係る停電原因通知システム1は、実施形態2の停電原因通知システム1から、計測ユニット15及び第1監視部123を除いたものである。
(4-3) Modification 1 of Embodiment 2
The power outage cause notification system 1 according to the first modification of the second embodiment is the power outage cause notification system 1 according to the second embodiment, except that the measurement unit 15 and the first monitoring unit 123 are removed.

この変形例でも、停電が発生した場合に、サーバ30からの系統停電情報を基に、当該停電が系統停電か宅内停電かを判断し、その判断結果(“系統停電”又は“宅内停電”)を示す第1原因情報を顧客に通知することはできる。 Even in this variant, when a power outage occurs, it is possible to determine whether the power outage is a power grid power outage or a home power outage based on the power grid power outage information from server 30, and notify the customer of the first cause information indicating the determination result ("power grid power outage" or "home power outage").

(4-4)実施形態2の変形例2
実施形態2の変形例2に係る停電原因通知システム1は、実施形態2の停電原因通知システム1から、電源部14を除いたものである。
(4-4) Modification 2 of Embodiment 2
The power outage cause notification system 1 according to the second modification of the second embodiment is the power outage cause notification system 1 of the second embodiment without the power supply unit 14 .

この変形例でも、宅内停電が発生した場合に、“宅内停電”を示す第1原因情報、及び宅内停電の原因に関する第2原因情報、を顧客に通知することはできる。 Even with this variant, if a power outage occurs within the home, the customer can be notified of first cause information indicating "power outage within the home" and second cause information regarding the cause of the power outage within the home.

(4-5)実施形態2の変形例3
実施形態2の変形例3に係る停電原因通知システム1は、実施形態2の停電原因通知システム1から、計測ユニット15及び第1監視部123並びに電源部14を除いたものである。
(4-5) Modification 3 of Embodiment 2
The power outage cause notification system 1 according to the third modification of the second embodiment is the power outage cause notification system 1 of the second embodiment, except that the measurement unit 15, the first monitoring unit 123, and the power supply unit 14 are removed.

この変形例でも、宅内停電が発生した場合に、“宅内停電”を示す第1原因情報を顧客に通知することはできる。 Even with this variant, if a power outage occurs within the home, the customer can be notified of the first cause information indicating "power outage within the home."

なお、上記実施形態1,2に係る停電原因通知システム1と同様の機能は、停電原因通知方法、(コンピュータ)プログラム、又はプログラムを記録した非一時的記録媒体等で具現化されてもよい。なお、停電原因通知方法は、上で説明した各種ステップのうち、少なくとも、ステップS13(起動ステップ)と、ステップS16(取得ステップ)と、ステップS17(出力ステップ)と、を含む方法である。また、プログラムは、停電原因通知方法を1以上のコンピュータに実行させるためのプログラムである。 Functions similar to those of the power outage cause notification system 1 according to the first and second embodiments may be embodied in a power outage cause notification method, a (computer) program, or a non-transitory recording medium on which a program is recorded. The power outage cause notification method is a method that includes at least step S13 (startup step), step S16 (acquisition step), and step S17 (output step) of the various steps described above. The program is a program for causing one or more computers to execute the power outage cause notification method.

(5)まとめ
第1の態様に係る停電原因通知システム(1)は、ブレーカ(主幹ブレーカ10)に付随して用いられる。ブレーカ(主幹ブレーカ10)は、電力系統(201)と顧客の宅内の負荷(202)との間の電路(第1電路203a,第2電路203b)に介在する。ブレーカ(主幹ブレーカ10)は、停電の発生時に、前記顧客の端末(40)と通信可能に接続される。停電原因通知システム(1)は、前記停電の原因を前記ブレーカ(10)から端末(40)を介して前記顧客に通知する。
(5) Summary The power outage cause notification system (1) according to the first aspect is used in association with a breaker (master breaker 10). The breaker (master breaker 10) is interposed in an electric circuit (first electric circuit 203a, second electric circuit 203b) between a power system (201) and a load (202) in a customer's premises. When a power outage occurs, the breaker (master breaker 10) is communicably connected to the customer's terminal (40). The power outage cause notification system (1) notifies the customer of the cause of the power outage from the breaker (10) via the terminal (40).

端末(40)には、アプリケーションソフトウェア(401)がインストールされている。アプリケーションソフトウェア(401)は、少なくとも前記停電の原因を通知する。 Application software (401) is installed on the terminal (40). The application software (401) notifies the user of at least the cause of the power outage.

停電原因通知システム(1)は、起動部(121)と、取得部(122)と、出力部(13)とを備える。起動部(121)は、前記停電の発生時に、端末(40)のアプリケーションソフトウェア(401)を起動する。取得部(122)は、前記停電の発生時に、停電情報を取得する。前記停電情報は、原因情報を少なくとも含む。原因情報は、前記停電が、系統停電か、宅内停電か、を示す。前記系統停電は、電力系統(201)に起因する停電である。前記宅内停電は、ブレーカ(主幹ブレーカ10)がトリップ状態となったことに起因する停電である。出力部(13)は、取得部(122)が取得した前記停電情報を、起動部(121)が起動した前記アプリケーションソフトウェア(401)に引き渡す。 The power outage cause notification system (1) comprises a startup unit (121), an acquisition unit (122), and an output unit (13). The startup unit (121) starts application software (401) of the terminal (40) when the power outage occurs. The acquisition unit (122) acquires power outage information when the power outage occurs. The power outage information includes at least cause information. The cause information indicates whether the power outage is a grid power outage or a home power outage. The grid power outage is a power outage caused by the power grid (201). The home power outage is a power outage caused by a breaker (main breaker 10) being tripped. The output unit (13) passes the power outage information acquired by the acquisition unit (122) to the application software (401) started by the startup unit (121).

この態様は、実施形態1及び2に対応する。この態様では、停電の発生時に、系統停電か宅内停電かを少なくとも示す停電原因情報を含む停電情報を取得し、顧客の端末の通知アプリを起動し、停電情報を通知アプリに引き渡す。 This aspect corresponds to embodiments 1 and 2. In this aspect, when a power outage occurs, power outage information is obtained, including information on the cause of the power outage that indicates at least whether it is a grid power outage or a power outage within the home, a notification app on the customer's device is launched, and the power outage information is passed to the notification app.

この態様によれば、個々の顧客に対して、宅内停電も含む停電の原因に関する原因情報を容易に通知できる。 This allows individual customers to easily be notified of information regarding the cause of power outages, including in-home power outages.

第2の態様に係る停電原因通知システム(1)では、第1の態様において、前記原因情報は第1原因情報である。取得部(122)は、前記宅内停電の発生時には、第2原因情報を含む停電情報を取得する。第2原因情報は、前記宅内停電の原因に関する情報である。 In the power outage cause notification system (1) according to the second aspect, in the first aspect, the cause information is first cause information. When the in-home power outage occurs, the acquisition unit (122) acquires power outage information including second cause information. The second cause information is information regarding the cause of the in-home power outage.

この態様は、実施形態1及び2に対応する。この態様では、宅内停電時には、ブレーカがトリップ状態となった原因も通知する。 This aspect corresponds to embodiments 1 and 2. In this aspect, when a power outage occurs within the home, the cause of the breaker tripping is also notified.

この態様によれば、停電が系統停電か宅内停電かを示す第1原因情報に加えて、宅内停電の原因が過電流か漏電か地震かを示す第2原因情報も通知できる。 According to this aspect, in addition to the first cause information indicating whether the power outage is a grid power outage or a home power outage, second cause information indicating whether the home power outage is caused by an overcurrent, a ground fault, or an earthquake can also be notified.

第3の態様に係る停電原因通知システム(1)では、第2の態様において、取得部(122)は、対処情報を更に含む停電情報を取得する。対処情報は、前記停電の原因に応じた対処法に関する情報である。 In the power outage cause notification system (1) according to the third aspect, in the second aspect, the acquisition unit (122) acquires power outage information that further includes response information. The response information is information regarding a response method according to the cause of the power outage.

この態様は、実施形態1及び2に対応する。この態様では、停電原因に応じた対処法も通知する。 This aspect corresponds to embodiments 1 and 2. In this aspect, the system also notifies the user of the corrective action to be taken depending on the cause of the power outage.

この態様によれば、個々の顧客に対して、原因情報に対応する対処情報を容易に通知できる。 This allows individual customers to easily be notified of the countermeasure information corresponding to the cause information.

第4の態様に係る停電原因通知システム(1)は、第2又は第3の態様において、電源部(14)を更に備える。電源部(14)は、前記系統停電の発生時に、少なくとも起動部(121)、取得部(122)及び出力部(13)に電力を供給する。 The power outage cause notification system (1) according to the fourth aspect is the second or third aspect, further including a power supply unit (14). The power supply unit (14) supplies power to at least the start-up unit (121), acquisition unit (122), and output unit (13) when the grid power outage occurs.

この態様は、実施形態1及び2に対応する。この態様では、バックアップ電源を有する。 This aspect corresponds to embodiments 1 and 2. This aspect has a backup power supply.

この態様によれば、電力系統の停電中でも通知を行える。 This allows notifications to be sent even during a power outage in the power grid.

第5の態様に係る停電原因通知システム(1)は、第4の態様において、受付部(11)を更に備える。受付部(11)は、接続操作を受け付ける。接続操作は、ブレーカ(主幹ブレーカ10)を端末(40)と通信可能に接続するための操作である。ブレーカ(主幹ブレーカ10)は、接続操作に応じて、端末(40)と通信可能に接続される。 The power outage cause notification system (1) according to the fifth aspect is the fourth aspect, and further includes a reception unit (11). The reception unit (11) receives a connection operation. The connection operation is an operation for connecting the breaker (main breaker 10) so that it can communicate with the terminal (40). In response to the connection operation, the breaker (main breaker 10) is connected so that it can communicate with the terminal (40).

この態様は、実施形態1に対応する。この態様では、ブレーカ・端末間は、通常、非接続であり、接続操作に応じて通信可能になる(適時接続)。なお、この態様では、サーバ(30)は必須でない。 This aspect corresponds to embodiment 1. In this aspect, the breaker and terminal are normally disconnected, and communication becomes possible depending on the connection operation (timely connection). Note that in this aspect, the server (30) is not required.

この態様によれば、停電発生時に、顧客の判断で端末のアプリを起動できる。また、顧客が必要と判断した場合に限り、ブレーカは端末と通信を開始するので、通信量を抑制できる。さらに、電源部(14)がバッテリの場合、バッテリの消耗を防ぐことができる。 According to this aspect, in the event of a power outage, the customer can decide to launch the app on the terminal. Furthermore, the breaker only starts communication with the terminal when the customer deems it necessary, which reduces communication volume. Furthermore, if the power supply unit (14) is a battery, battery drain can be prevented.

第6の態様に係る停電原因通知システム(1)では、第4の態様において、端末(40)は、サーバ(30)と常時通信可能に接続される。サーバ(30)は、端末(40)のアプリケーションソフトウェア(401)を通じて前記顧客への情報提供を行う。ブレーカ(主幹ブレーカ10)は、サーバ(30)と常時通信可能に接続され、サーバ(30)が起動部(121)を備える。サーバ(30)の起動部(121)は、ブレーカ(主幹ブレーカ10)とサーバ(30)の間の接続が切断されたことに応じて、端末(40)のアプリケーションソフトウェア(401)を起動する。 In the power outage cause notification system (1) according to the sixth aspect, in the fourth aspect, the terminal (40) is connected to the server (30) so that it can communicate with the terminal (40). The server (30) provides information to the customer through application software (401) on the terminal (40). The breaker (master breaker 10) is connected to the server (30) so that it can communicate with the server (30), and the server (30) has a startup unit (121). The startup unit (121) of the server (30) starts the application software (401) on the terminal (40) in response to the disconnection of the connection between the breaker (master breaker 10) and the server (30).

この態様は、実施形態2に対応する。この態様では、サーバ(30)が必須であり、ブレーカ・サーバ間及びブレーカ・端末間が共に常時接続される。ブレーカは、端末と(直に)常時通信可能に接続され、ブレーカは(ゲートウェイを介して)サーバと常時通信可能に接続され、ブレーカ(又はゲートウェイ)とサーバとの間の接続が切断されたことに応じて、サーバが端末の通知アプリを起動する。 This aspect corresponds to embodiment 2. In this aspect, a server (30) is required, and there is a constant connection between the breaker and the server, and between the breaker and the terminal. The breaker is connected to the terminal (directly) so that it can communicate at all times, and the breaker is connected to the server (via a gateway) so that it can communicate at all times, and in response to the connection between the breaker (or gateway) and the server being disconnected, the server launches a notification app on the terminal.

この態様によれば、停電発生時に、ブレーカ・サーバ間の接続が切れることを利用して、サーバが自動的に端末のアプリを起動できる。 In this case, when a power outage occurs, the server can automatically start the device's app by taking advantage of the fact that the connection between the breaker and the server is cut off.

第7の態様に係る停電原因通知システム(1)では、第5の態様において、端末(40)は、サーバ(30)と常時通信可能に接続される。サーバ(30)は、前記系統停電の発生時に端末(40)のアプリケーションソフトウェア(401)を通じて前記顧客に前記系統停電に関する系統停電情報を通知する。 In the seventh aspect of the power outage cause notification system (1), in the fifth aspect, the terminal (40) is connected to the server (30) so that it can communicate with the server at all times. When the power outage occurs, the server (30) notifies the customer of power outage information related to the power outage via the application software (401) of the terminal (40).

この態様は、実施形態1の変形例1に対応する。この態様では、端末(40)は、サーバ(30)との通信機能を有し、サーバ(30)は、系統停電の発生時に端末(40)への系統停電情報の提供を行う。 This aspect corresponds to Variation 1 of Embodiment 1. In this aspect, the terminal (40) has a communication function with the server (30), and the server (30) provides grid power outage information to the terminal (40) when a grid power outage occurs.

この態様によれば、宅内停電が発生した場合の第2原因情報の通知に加えて、系統停電が発生した場合にサーバ(30)から提供される系統停電情報を、更に顧客に通知することができる。 According to this embodiment, in addition to notifying the customer of the second cause information when a power outage occurs within the home, the customer can also be notified of grid power outage information provided by the server (30) when a grid power outage occurs.

第8の態様に係る停電原因通知システム(1)は、第5~第7のいずれかの態様において、計測ユニット(15)を更に備える。計測ユニット(15)は、第1電路(203a)の電力を少なくとも計測する。第1電路(203a)は、ブレーカ(主幹ブレーカ10)に対して電力系統(201)側の電路である。計測ユニット(15)は、ブレーカ(主幹ブレーカ10)と常時通信可能に接続される。停電原因通知システム(1)は、監視部(第1監視部123)を備える。監視部(第1監視部123)は、計測ユニット(15)の計測結果を常時監視し、前記計測結果を基に前記停電が前記系統停電か前記宅内停電かを判断して前記第1原因情報を取得する。 The power outage cause notification system (1) according to the eighth aspect is any one of the fifth to seventh aspects, and further includes a measurement unit (15). The measurement unit (15) measures at least the power of the first electric circuit (203a). The first electric circuit (203a) is an electric circuit on the power grid (201) side of the breaker (master breaker 10). The measurement unit (15) is connected to the breaker (master breaker 10) so that it can communicate with the breaker. The power outage cause notification system (1) includes a monitoring unit (first monitoring unit 123). The monitoring unit (first monitoring unit 123) constantly monitors the measurement results of the measurement unit (15), and based on the measurement results, determines whether the power outage is a grid power outage or a home power outage, and acquires the first cause information.

この態様は、実施形態1,2に対応する。この態様では、ブレーカ(10)の一次側の電力を少なくとも計測する計測ユニット(15)を備え、計測ユニット(15)はブレーカ(10)と、ブレーカ(10)は端末(40)と、それぞれ常時通信可能に接続され、ブレーカ(10)は、計測ユニット(15)の計測結果を常時監視して第1原因情報を取得する。 This aspect corresponds to embodiments 1 and 2. In this aspect, a measurement unit (15) is provided that measures at least the power on the primary side of the breaker (10), the measurement unit (15) is connected to the breaker (10), and the breaker (10) is connected to a terminal (40) so that they can communicate at all times, and the breaker (10) constantly monitors the measurement results of the measurement unit (15) to obtain first cause information.

この態様によれば、計測ユニット(15)の計測結果を常時監視することで、系統停電か宅内停電かを判断し、第1原因情報を取得できる。系統停電情報を常時監視する場合(第10の態様)と比べて、第1原因情報のより早い取得が可能であり、停電情報を迅速に提供できる。 According to this aspect, by constantly monitoring the measurement results of the measurement unit (15), it is possible to determine whether the power outage is a grid power outage or a home power outage and obtain first cause information. Compared to constantly monitoring grid power outage information (aspect 10), first cause information can be obtained more quickly, allowing power outage information to be provided more quickly.

第9の態様に係る停電原因通知システム(1)では、第8の態様において、計測ユニット(15)は、第2電路(203b)の電流、及び計測ユニット(15)自身の加速度、を更に計測する。第2電路(203b)は、ブレーカ(主幹ブレーカ10)に対して負荷(202)側の電路である。監視部(第1監視部123)は、前記電流及び前記加速度を基に、前記宅内停電の原因が、過電流か、漏電か、地震か、を判断し、前記判断の結果を示す第2原因情報を更に取得する。 In the power outage cause notification system (1) according to the ninth aspect, in the eighth aspect, the measurement unit (15) further measures the current of the second electric circuit (203b) and the acceleration of the measurement unit (15) itself. The second electric circuit (203b) is the electric circuit on the load (202) side of the breaker (main breaker 10). The monitoring unit (first monitoring unit 123) determines whether the cause of the in-home power outage is an overcurrent, a ground fault, or an earthquake based on the current and the acceleration, and further acquires second cause information indicating the result of the determination.

この態様は、実施形態1,2に対応する。この態様では、計測ユニット(15)は、第2電路(203b)の電流、及び加速度を更に計測し、ブレーカ(主幹ブレーカ10)は、計測結果を常時監視して第2原因情報を取得する。 This aspect corresponds to embodiments 1 and 2. In this aspect, the measurement unit (15) further measures the current and acceleration of the second electrical circuit (203b), and the breaker (main breaker 10) constantly monitors the measurement results to obtain second cause information.

この態様によれば、宅内停電の原因が過電流か漏電か地震かを更に判断し、第2原因情報をも含む停電情報を迅速に提供できる。 This aspect further determines whether the cause of the in-home power outage is an overcurrent, a power leak, or an earthquake, and allows for quick provision of power outage information that also includes information on the second cause.

第10の態様に係る停電原因通知システム(1)では、第6の態様において、ブレーカ(主幹ブレーカ10)は、端末(40)と常時通信可能に接続される。サーバ(30)は、前記系統停電の発生時に、前記系統停電に関する系統停電情報を少なくともブレーカ(主幹ブレーカ10)に提供する。停電原因通知システム(1)は、第2監視部(124)を更に備える。第2監視部(124)は、サーバ(30)から前記ブレーカに提供される前記系統停電情報を常時監視し、前記系統停電情報を基に前記停電が前記系統停電か前記宅内停電かを判断して前記第1原因情報を取得する。 In the power outage cause notification system (1) according to the tenth aspect, in the sixth aspect, the breaker (main breaker 10) is connected to a terminal (40) so that it can communicate with the terminal at all times. When the power outage occurs, the server (30) provides at least the breaker (main breaker 10) with power outage information relating to the power outage. The power outage cause notification system (1) further includes a second monitoring unit (124). The second monitoring unit (124) constantly monitors the power outage information provided to the breaker from the server (30), and determines whether the power outage is a power outage on the main breaker or a power outage within the home based on the power outage information, thereby acquiring the first cause information.

この態様は、実施形態2に対応する。この態様では、ブレーカ(主幹ブレーカ10)は、サーバからの系統停電情報を常時監視して第1原因情報を取得する。 This aspect corresponds to embodiment 2. In this aspect, the breaker (main breaker 10) constantly monitors grid power outage information from the server and acquires first cause information.

この態様によれば、系統停電情報を常時監視することで、系統停電か宅内停電かを判断し、第1原因情報を取得できる。 According to this aspect, by constantly monitoring grid power outage information, it is possible to determine whether the power outage is a grid power outage or a home power outage and obtain first cause information.

第11の態様に係るブレーカ(主幹ブレーカ10)は、電力系統(201)と顧客の宅内の負荷(202)との間の電路(第1電路203a,第2電路203b)に介在し、少なくとも停電の発生時に顧客の端末(40)と通信可能に接続されて、前記停電の原因を前記顧客に端末(40)を介して通知する。端末(40)には、アプリケーションソフトウェア(401)がインストールされている。アプリケーションソフトウェア(401)は、少なくとも前記停電の原因を通知する。ブレーカ(主幹ブレーカ10)は、起動部(121)と、取得部(122)と、出力部(13)とを備える。起動部(121)は、前記停電の発生時に、端末(40)のアプリケーションソフトウェア(401)を起動する。取得部(122)は、前記停電の発生時に、停電情報を取得する。停電情報は、原因情報を少なくとも含む。原因情報は、前記停電が、系統停電か、宅内停電か、を示す。前記系統停電は、電力系統(201)に起因する停電である。前記宅内停電は、ブレーカ(主幹ブレーカ10)自身がトリップ状態となったことに起因する停電である。出力部(13)は、取得部(122)が取得した停電情報を、起動部(121)が起動したアプリケーションソフトウェア(401)に引き渡す。 The breaker (main breaker 10) according to the eleventh aspect is interposed in an electric circuit (first electric circuit 203a, second electric circuit 203b) between the power system (201) and a load (202) in a customer's premises, and is communicatively connected to a customer's terminal (40) at least when a power outage occurs, and notifies the customer of the cause of the power outage via the terminal (40). Application software (401) is installed in the terminal (40). The application software (401) notifies the customer of at least the cause of the power outage. The breaker (main breaker 10) comprises a startup unit (121), an acquisition unit (122), and an output unit (13). The startup unit (121) starts the application software (401) of the terminal (40) when the power outage occurs. The acquisition unit (122) acquires power outage information when the power outage occurs. The power outage information includes at least cause information. The cause information indicates whether the power outage is a grid power outage or a home power outage. The grid power outage is a power outage caused by the power grid (201). The home power outage is a power outage caused by the breaker (main breaker 10) itself tripping. The output unit (13) passes the power outage information acquired by the acquisition unit (122) to the application software (401) launched by the startup unit (121).

この態様は、実施形態1,2に対応する。この態様では、停電の発生時に、系統停電か宅内停電かを少なくとも示す停電原因情報を含む停電情報を取得し、顧客の端末の通知アプリを起動し、停電情報を通知アプリに引き渡す。 This aspect corresponds to embodiments 1 and 2. In this aspect, when a power outage occurs, power outage information is obtained, including information on the cause of the power outage that indicates at least whether it is a grid power outage or a power outage within the home, a notification app on the customer's device is launched, and the power outage information is passed to the notification app.

この態様によれば、個々の顧客に対して、宅内停電も含む停電の原因に関する原因情報を容易に通知できる。 This allows individual customers to easily be notified of information regarding the cause of power outages, including in-home power outages.

第12の態様に係る停電原因通知方法は、停電原因通知システム(1)の1以上のコンピュータによって実行される。停電原因通知システム(1)は、ブレーカ(主幹ブレーカ10)に付随して用いられる。ブレーカ(10)は、電力系統(201)と顧客の宅内の負荷(202)との間の電路(第1電路203a,第2電路203b)に介在する。ブレーカ(10)は、少なくとも停電の発生時に前記顧客の端末(40)と通信可能に接続される。この停電原因通知方法は、前記停電の原因を前記ブレーカ(10)から前記端末(40)を介して前記顧客に通知する停電原因通知方法である。端末(40)には、少なくとも前記停電の原因を通知するアプリケーションソフトウェア(401)がインストールされている。この停電原因通知方法は、起動ステップ(S13)と、取得ステップ(S14)と、出力ステップ(S17)と、を含む。起動ステップ(S13)では、前記停電の発生時に、前記端末(40)の前記アプリケーションソフトウェア(401)を起動する。取得ステップ(S14)では、前記停電の発生時に、原因情報を少なくとも含む停電情報が取得される。原因情報は、前記停電が、系統停電か、宅内停電か、を示す。前記系統停電は、電力系統(201)に起因する停電である。前記宅内停電は、ブレーカ(主幹ブレーカ10)がトリップ状態となったことに起因する停電である。出力ステップ(S17)では、取得ステップ(S14)で取得された前記停電情報が、起動ステップ(S13)で起動された前記アプリケーションソフトウェア(401)に引き渡される。 The power outage cause notification method according to the twelfth aspect is executed by one or more computers of a power outage cause notification system (1). The power outage cause notification system (1) is used in conjunction with a breaker (main breaker 10). The breaker (10) is located in an electric circuit (first electric circuit 203a, second electric circuit 203b) between the power grid (201) and a load (202) in a customer's premises. The breaker (10) is connected to the customer's terminal (40) so that it can communicate with the customer at least when a power outage occurs. This power outage cause notification method notifies the customer of the cause of the power outage from the breaker (10) via the terminal (40). Application software (401) that notifies the customer of at least the cause of the power outage is installed in the terminal (40). This power outage cause notification method includes a startup step (S13), an acquisition step (S14), and an output step (S17). In the activation step (S13), the application software (401) of the terminal (40) is activated when the power outage occurs. In the acquisition step (S14), power outage information including at least cause information is acquired when the power outage occurs. The cause information indicates whether the power outage is a grid power outage or a home power outage. The grid power outage is a power outage caused by the power grid (201). The home power outage is a power outage caused by a breaker (main breaker 10) being tripped. In the output step (S17), the power outage information acquired in the acquisition step (S14) is passed to the application software (401) activated in the activation step (S13).

この態様は、実施形態1,2に対応する。この態様では、停電の発生時に、系統停電か宅内停電かを少なくとも示す停電原因情報を含む停電情報を取得し、顧客の端末の通知アプリを起動し、停電情報を通知アプリに引き渡す。 This aspect corresponds to embodiments 1 and 2. In this aspect, when a power outage occurs, power outage information is obtained, including information on the cause of the power outage that indicates at least whether it is a grid power outage or a power outage within the home, a notification app on the customer's device is launched, and the power outage information is passed to the notification app.

この態様によれば、個々の顧客に対して、宅内停電も含む停電の原因に関する原因情報を容易に通知できる。 This allows individual customers to easily be notified of information regarding the cause of power outages, including in-home power outages.

第13の態様に係るプログラムは、第12の態様に係る停電原因通知方法を1以上のコンピュータに実行させるためのプログラムである。 A program according to a thirteenth aspect is a program for causing one or more computers to execute the power outage cause notification method according to the twelfth aspect.

この態様は、実施形態1,2に対応する。この態様では、停電の発生時に、系統停電か宅内停電かを少なくとも示す停電原因情報を含む停電情報を取得し、顧客の端末の通知アプリを起動し、停電情報を通知アプリに引き渡す。 This aspect corresponds to embodiments 1 and 2. In this aspect, when a power outage occurs, power outage information is obtained, including information on the cause of the power outage that indicates at least whether it is a grid power outage or a power outage within the home, a notification app on the customer's device is launched, and the power outage information is passed to the notification app.

この態様によれば、個々の顧客に対して、宅内停電も含む停電の原因に関する原因情報を容易に通知できる。 This allows individual customers to easily be notified of information regarding the cause of power outages, including in-home power outages.

1 停電原因通知システム
10 主幹ブレーカ(ブレーカ)
100 分電盤
11 受付部
12 処理部
121 起動部
122 取得部
123 第1監視部(監視部)
124 第2監視部
13 出力部
14 電源部
15 計測ユニット
30 サーバ
40 端末
401 アプリケーションソフトウェア(アプリ)
2 電力供給システム
201 電力系統
202 負荷
203a 第1電路(電路)
203b 第2電路(電路)
1 Power outage cause notification system 10 Main breaker (breaker)
100 Distribution board 11 Reception unit 12 Processing unit 121 Startup unit 122 Acquisition unit 123 First monitoring unit (monitoring unit)
124 Second monitoring unit 13 Output unit 14 Power supply unit 15 Measurement unit 30 Server 40 Terminal 401 Application software (app)
2 Power supply system 201 Power system 202 Load 203a First electric circuit (electric circuit)
203b Second electrical circuit (electrical circuit)

Claims (13)

電力系統と顧客の宅内の負荷との間の電路に介在し、停電の発生時に前記顧客の端末と通信可能に接続されるブレーカ、に付随して用いられ、前記停電の原因を前記ブレーカから前記端末を介して前記顧客に通知する停電原因通知システムであって、
前記端末には、少なくとも前記停電の原因を通知するアプリケーションソフトウェアがインストールされており、
前記停電の発生時に、前記端末の前記アプリケーションソフトウェアを起動する起動部と、
前記停電の発生時に、前記停電が、前記電力系統に起因する停電である系統停電か、前記ブレーカがトリップ状態となったことに起因する停電である宅内停電か、を示す原因情報を少なくとも含む停電情報を取得する取得部と、
前記取得部が取得した前記停電情報を、前記起動部が起動した前記アプリケーションソフトウェアに引き渡す出力部と、
前記系統停電の発生時に、少なくとも前記起動部、前記取得部及び前記出力部に電力を供給する電源部と、
前記ブレーカを前記端末と通信可能に接続するための接続操作を受け付ける受付部と、を備え、
前記ブレーカは、前記接続操作に応じて前記端末と通信可能に接続される、
停電原因通知システム。
A power outage cause notification system that is used in conjunction with a breaker that is interposed in an electric circuit between a power system and a load in a customer's home and is connected to a terminal of the customer so as to be able to communicate with the customer when a power outage occurs, and that notifies the customer of the cause of the power outage from the breaker via the terminal,
application software that notifies the user of at least the cause of the power outage is installed on the terminal;
a startup unit that starts the application software of the terminal when the power outage occurs;
An acquisition unit that acquires power outage information including at least cause information indicating whether the power outage is a system power outage caused by the power system or an in-home power outage caused by the breaker being tripped when the power outage occurs;
An output unit that transfers the power outage information acquired by the acquisition unit to the application software started by the startup unit;
A power supply unit that supplies power to at least the startup unit, the acquisition unit, and the output unit when the grid power outage occurs;
a reception unit that receives a connection operation for connecting the breaker to the terminal so that the breaker can communicate with the terminal,
the breaker is communicably connected to the terminal in response to the connection operation;
Power outage cause notification system.
電力系統と顧客の宅内の負荷との間の電路に介在し、停電の発生時に前記顧客の端末と通信可能に接続されるブレーカ、に付随して用いられ、前記停電の原因を前記ブレーカから前記端末を介して前記顧客に通知する停電原因通知システムであって、
前記端末には、少なくとも前記停電の原因を通知するアプリケーションソフトウェアがインストールされており、
前記停電の発生時に、前記端末の前記アプリケーションソフトウェアを起動する起動部と、
前記停電の発生時に、前記停電が、前記電力系統に起因する停電である系統停電か、前記ブレーカがトリップ状態となったことに起因する停電である宅内停電か、を示す原因情報を少なくとも含む停電情報を取得する取得部と、
前記取得部が取得した前記停電情報を、前記起動部が起動した前記アプリケーションソフトウェアに引き渡す出力部と、
前記系統停電の発生時に、少なくとも前記起動部、前記取得部及び前記出力部に電力を供給する電源部と、を備え、
前記端末は、前記端末の前記アプリケーションソフトウェアを通じて前記顧客への情報提供を行うサーバと常時通信可能に接続され、
前記ブレーカは、前記サーバと常時通信可能に接続され、
前記サーバが前記起動部を備え、
前記サーバの前記起動部は、前記ブレーカと前記サーバの間の接続が切断されたことに応じて、前記端末の前記アプリケーションソフトウェアを起動する、
停電原因通知システム。
A power outage cause notification system that is used in conjunction with a breaker that is interposed in an electric circuit between a power system and a load in a customer's home and is connected to a terminal of the customer so as to be able to communicate with the customer when a power outage occurs, and that notifies the customer of the cause of the power outage from the breaker via the terminal,
application software that notifies the user of at least the cause of the power outage is installed on the terminal;
a startup unit that starts the application software of the terminal when the power outage occurs;
An acquisition unit that acquires power outage information including at least cause information indicating whether the power outage is a system power outage caused by the power system or an in-home power outage caused by the breaker being tripped when the power outage occurs;
An output unit that transfers the power outage information acquired by the acquisition unit to the application software started by the startup unit;
a power supply unit that supplies power to at least the startup unit, the acquisition unit, and the output unit when the grid power outage occurs;
the terminal is constantly connected to a server that provides information to the customer through the application software of the terminal so as to be able to communicate with the server;
the breaker is connected to the server so as to be able to communicate with the server at all times;
the server includes the launch unit,
the starting unit of the server starts the application software of the terminal in response to the disconnection of the connection between the breaker and the server;
Power outage cause notification system.
前記端末は、前記系統停電の発生時に前記端末の前記アプリケーションソフトウェアを通じて前記顧客に前記系統停電に関する系統停電情報を通知するサーバ、と常時通信可能に接続される、
請求項1に記載の停電原因通知システム。
The terminal is constantly connected to a server that notifies the customer of grid power outage information regarding the grid power outage through the application software of the terminal when the grid power outage occurs,
The power outage cause notification system according to claim 1.
前記ブレーカに対して前記電力系統側、の電路である第1電路の電力を少なくとも計測する計測ユニットを更に備え、
前記計測ユニットは、前記ブレーカと常時通信可能に接続され、
前記計測ユニットの計測結果を常時監視し、前記計測結果を基に前記停電が前記系統停電か前記宅内停電かを判断して前記原因情報を取得する監視部を更に備える、
請求項1~3のいずれか一項に記載の停電原因通知システム。
Further, a measurement unit is provided to measure at least the power of a first electric circuit which is an electric circuit on the power grid side with respect to the breaker,
the measurement unit is connected to the breaker so as to be able to communicate with it at all times;
The power supply unit further includes a monitoring unit that constantly monitors the measurement results of the measurement unit, determines whether the power outage is a grid power outage or a home power outage based on the measurement results, and acquires the cause information.
The power outage cause notification system according to any one of claims 1 to 3.
前記原因情報は第1原因情報であり、
前記計測ユニットは、前記ブレーカに対して前記負荷側、の電路である第2電路の電流、及び前記計測ユニット自身の加速度、を更に計測し、
前記監視部は、前記電流及び前記加速度を基に、前記宅内停電の原因が、過電流か、漏電か、地震か、を判断し、前記判断の結果を示す第2原因情報を更に取得する、
請求項4に記載の停電原因通知システム。
the cause information is first cause information,
The measurement unit further measures a current in a second electric circuit, which is an electric circuit on the load side of the breaker, and an acceleration of the measurement unit itself;
The monitoring unit determines whether the cause of the in-home power outage is an overcurrent, a ground fault, or an earthquake based on the current and the acceleration, and further acquires second cause information indicating the result of the determination.
The power outage cause notification system according to claim 4.
前記ブレーカは、前記端末と常時通信可能に接続され、
前記サーバは、前記系統停電の発生時に、前記系統停電に関する系統停電情報を少なくとも前記ブレーカに提供し、
前記サーバから前記ブレーカに提供される前記系統停電情報を常時監視し、前記系統停電情報を基に前記停電が前記系統停電か前記宅内停電かを判断して前記原因情報を取得する第2監視部を更に備える、
請求項2に記載の停電原因通知システム。
the breaker is connected to the terminal so as to be able to communicate with the terminal at all times;
The server provides grid power outage information regarding the grid power outage to at least the breaker when the grid power outage occurs;
A second monitoring unit constantly monitors the grid power outage information provided from the server to the breaker, determines whether the power outage is the grid power outage or the in-home power outage based on the grid power outage information, and acquires the cause information.
The power outage cause notification system according to claim 2.
前記原因情報は第1原因情報であり、
前記取得部は、前記宅内停電の発生時には、前記宅内停電の原因に関する第2原因情報、を更に含む前記停電情報を取得する、
請求項1~4及び6のいずれか一項に記載の停電原因通知システム。
the cause information is first cause information,
When the in-home power outage occurs, the acquisition unit acquires the power outage information further including second cause information related to a cause of the in-home power outage.
The power outage cause notification system according to any one of claims 1 to 4 and 6.
前記取得部は、前記停電の原因に応じた対処法に関する対処情報を更に含む前記停電情報を取得する、
請求項1~7のいずれか一項に記載の停電原因通知システム。
The acquisition unit acquires the power outage information further including response information regarding a response method according to a cause of the power outage.
The power outage cause notification system according to any one of claims 1 to 7.
電力系統と顧客の宅内の負荷との間の電路に介在し、少なくとも停電の発生時に前記顧客の端末と通信可能に接続されて、前記停電の原因を前記顧客に前記端末を介して通知するブレーカであって、
前記端末には、少なくとも前記停電の原因を通知するアプリケーションソフトウェアがインストールされており、
前記停電の発生時に、前記端末の前記アプリケーションソフトウェアを起動する起動部と、
前記停電の発生時に、前記停電が、前記電力系統に起因する停電である系統停電か、前記ブレーカ自身がトリップ状態となったことに起因する停電である宅内停電か、を示す原因情報を少なくとも含む停電情報を取得する取得部と、
前記取得部が取得した前記停電情報を、前記起動部が起動した前記アプリケーションソフトウェアに引き渡す出力部と、
前記系統停電の発生時に、少なくとも前記起動部、前記取得部及び前記出力部に電力を供給する電源部と、
前記ブレーカを前記端末と通信可能に接続するための接続操作を受け付ける受付部と、を備え、
前記接続操作に応じて前記端末と通信可能に接続される、
ブレーカ。
A breaker that is interposed in an electric path between a power grid and a load in a customer's home, that is communicably connected to a terminal of the customer at least when a power outage occurs, and that notifies the customer of the cause of the power outage via the terminal,
application software that notifies the user of at least the cause of the power outage is installed on the terminal;
a startup unit that starts the application software of the terminal when the power outage occurs;
An acquisition unit that acquires power outage information including at least cause information indicating whether the power outage is a system power outage caused by the power system or an in-home power outage caused by the breaker itself being tripped, when the power outage occurs;
An output unit that transfers the power outage information acquired by the acquisition unit to the application software started by the startup unit;
A power supply unit that supplies power to at least the startup unit, the acquisition unit, and the output unit when the grid power outage occurs;
a reception unit that receives a connection operation for connecting the breaker to the terminal so that the breaker can communicate with the terminal,
A communication connection is established with the terminal in response to the connection operation.
breaker.
電力系統と顧客の宅内の負荷との間の電路に介在し、少なくとも停電の発生時に前記顧客の端末と通信可能に接続されて、前記停電の原因を前記顧客に前記端末を介して通知するブレーカであって、
前記端末には、少なくとも前記停電の原因を通知するアプリケーションソフトウェアがインストールされており、
前記停電の発生時に、前記端末の前記アプリケーションソフトウェアを起動する起動部と、
前記停電の発生時に、前記停電が、前記電力系統に起因する停電である系統停電か、前記ブレーカ自身がトリップ状態となったことに起因する停電である宅内停電か、を示す原因情報を少なくとも含む停電情報を取得する取得部と、
前記取得部が取得した前記停電情報を、前記起動部が起動した前記アプリケーションソフトウェアに引き渡す出力部と、
前記系統停電の発生時に、少なくとも前記起動部、前記取得部及び前記出力部に電力を供給する電源部と、を備え、
前記端末は、前記端末の前記アプリケーションソフトウェアを通じて前記顧客への情報提供を行うサーバと常時通信可能に接続され、
前記ブレーカは、前記サーバと常時通信可能に接続され、
前記起動部は、前記ブレーカと前記サーバの間の接続が切断されたことに応じて、前記端末の前記アプリケーションソフトウェアを起動する、
ブレーカ。
A breaker that is interposed in an electric path between a power grid and a load in a customer's home, that is communicably connected to a terminal of the customer at least when a power outage occurs, and that notifies the customer of the cause of the power outage via the terminal,
application software that notifies the user of at least the cause of the power outage is installed on the terminal;
a startup unit that starts the application software of the terminal when the power outage occurs;
An acquisition unit that acquires power outage information including at least cause information indicating whether the power outage is a system power outage caused by the power system or an in-home power outage caused by the breaker itself being tripped, when the power outage occurs;
An output unit that transfers the power outage information acquired by the acquisition unit to the application software started by the startup unit;
a power supply unit that supplies power to at least the startup unit, the acquisition unit, and the output unit when the grid power outage occurs;
the terminal is constantly connected to a server that provides information to the customer through the application software of the terminal so as to be able to communicate with the server;
the breaker is connected to the server so as to be able to communicate with the server at all times;
the launching unit launches the application software of the terminal in response to the disconnection of the connection between the breaker and the server.
breaker.
電力系統と顧客の宅内の負荷との間の電路に介在し、少なくとも停電の発生時に前記顧客の端末と通信可能に接続されるブレーカ、に付随して用いられ、前記停電の原因を前記ブレーカから前記端末を介して前記顧客に通知する停電原因通知システム、の1以上のコンピュータによって実行される停電原因通知方法であって、
前記端末には、少なくとも前記停電の原因を通知するアプリケーションソフトウェアがインストールされており、
停電原因通知システムは、
前記電力系統に起因する停電である系統停電の発生時に、少なくとも前記1以上のコンピュータに電力を供給する電源部と、
前記ブレーカを前記端末と通信可能に接続するための接続操作を受け付ける受付部と、を備え、
前記ブレーカは、前記接続操作に応じて前記端末と通信可能に接続され、
前記停電の発生時に、前記端末の前記アプリケーションソフトウェアを起動する起動ステップと、
前記停電の発生時に、前記停電が、前記電力系統に起因する停電である系統停電か、前記ブレーカがトリップ状態となったことに起因する停電である宅内停電か、を示す原因情報を少なくとも含む停電情報を取得する取得ステップと、
前記取得ステップで取得された前記停電情報を、前記起動ステップで起動された前記アプリケーションソフトウェアに引き渡す出力ステップと、を含む、
停電原因通知方法。
A power outage cause notification method executed by one or more computers in a power outage cause notification system used in conjunction with a breaker that is interposed in an electric path between a power grid and a load in a customer's home and is connected to be able to communicate with a terminal of the customer at least when a power outage occurs, and that notifies the customer of the cause of the power outage from the breaker via the terminal,
application software that notifies the user of at least the cause of the power outage is installed on the terminal;
The power outage cause notification system is
a power supply unit that supplies power to at least the one or more computers when a grid power outage occurs, the power outage being caused by the power grid;
a reception unit that receives a connection operation for connecting the breaker to the terminal so that the breaker can communicate with the terminal,
the breaker is connected to the terminal in a manner that allows communication with the terminal in response to the connection operation;
a startup step of starting the application software of the terminal when the power outage occurs;
An acquisition step of acquiring power outage information including at least cause information indicating whether the power outage is a system power outage caused by the power system or an in-home power outage caused by the breaker being tripped, when the power outage occurs;
An output step of transferring the power outage information acquired in the acquisition step to the application software started in the start step,
How to notify the cause of power outage.
電力系統と顧客の宅内の負荷との間の電路に介在し、少なくとも停電の発生時に前記顧客の端末と通信可能に接続されるブレーカ、に付随して用いられ、前記停電の原因を前記ブレーカから前記端末を介して前記顧客に通知する停電原因通知システム、の1以上のコンピュータによって実行される停電原因通知方法であって、
前記端末には、少なくとも前記停電の原因を通知するアプリケーションソフトウェアがインストールされており、
停電原因通知システムは、前記電力系統に起因する停電である系統停電の発生時に、少なくとも前記1以上のコンピュータに電力を供給する電源部を備え、
前記端末は、前記端末の前記アプリケーションソフトウェアを通じて前記顧客への情報提供を行うサーバと常時通信可能に接続され、
前記ブレーカは、前記サーバと常時通信可能に接続され、
前記停電の発生時に、前記端末の前記アプリケーションソフトウェアを起動する起動ステップと、
前記停電の発生時に、前記停電が、前記電力系統に起因する停電である系統停電か、前記ブレーカがトリップ状態となったことに起因する停電である宅内停電か、を示す原因情報を少なくとも含む停電情報を取得する取得ステップと、
前記取得ステップで取得された前記停電情報を、前記起動ステップで起動された前記アプリケーションソフトウェアに引き渡す出力ステップと、を含み、
前記サーバが前記起動ステップを実行し、
前記サーバの前記起動ステップでは、前記ブレーカと前記サーバの間の接続が切断されたことに応じて、前記端末の前記アプリケーションソフトウェアを起動する、
停電原因通知方法。
A power outage cause notification method executed by one or more computers in a power outage cause notification system used in conjunction with a breaker that is interposed in an electric path between a power grid and a load in a customer's home and is connected to be able to communicate with a terminal of the customer at least when a power outage occurs, and that notifies the customer of the cause of the power outage from the breaker via the terminal,
application software that notifies the user of at least the cause of the power outage is installed on the terminal;
The power outage cause notification system includes a power supply unit that supplies power to at least the one or more computers when a grid power outage occurs, the power outage being caused by the power grid;
the terminal is constantly connected to a server that provides information to the customer through the application software of the terminal so as to be able to communicate with the server;
the breaker is connected to the server so as to be able to communicate with the server at all times;
a startup step of starting the application software of the terminal when the power outage occurs;
An acquisition step of acquiring power outage information including at least cause information indicating whether the power outage is a system power outage caused by the power system or an in-home power outage caused by the breaker being tripped, when the power outage occurs;
An output step of transferring the power outage information acquired in the acquisition step to the application software started in the start-up step,
The server performs the initiating step;
In the step of starting the server, the application software of the terminal is started in response to the disconnection of the connection between the breaker and the server.
How to notify the cause of power outage.
請求項11又は12に記載の停電原因通知方法を1以上のコンピュータに実行させるための、
プログラム。
A method for causing one or more computers to execute the power outage cause notification method according to claim 11 or 12,
program.
JP2021106080A 2021-06-25 2021-06-25 Power outage cause notification system, breaker, power outage cause notification method and program Active JP7787657B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2021106080A JP7787657B2 (en) 2021-06-25 2021-06-25 Power outage cause notification system, breaker, power outage cause notification method and program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2021106080A JP7787657B2 (en) 2021-06-25 2021-06-25 Power outage cause notification system, breaker, power outage cause notification method and program

Publications (2)

Publication Number Publication Date
JP2023004429A JP2023004429A (en) 2023-01-17
JP7787657B2 true JP7787657B2 (en) 2025-12-17

Family

ID=85100400

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2021106080A Active JP7787657B2 (en) 2021-06-25 2021-06-25 Power outage cause notification system, breaker, power outage cause notification method and program

Country Status (1)

Country Link
JP (1) JP7787657B2 (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007006656A (en) 2005-06-27 2007-01-11 Chugoku Electric Power Co Inc:The Power failure information transmitter and power failure information transmitting system
JP2007336692A (en) 2006-06-15 2007-12-27 Chugoku Electric Power Co Inc:The System for notifying information about service interruption
JP2010250508A (en) 2009-04-14 2010-11-04 Chugoku Electric Power Co Inc:The Power information management method
JP2016185020A (en) 2015-03-26 2016-10-20 東芝ライテック株式会社 Communication system and distribution board
JP2017108482A (en) 2015-12-07 2017-06-15 日東工業株式会社 Power distribution board system
US20190058354A1 (en) 2017-08-15 2019-02-21 Carling Technologies, Inc. Electronic Status Reporting Circuit Breaker
JP2020072639A (en) 2018-10-29 2020-05-07 パナソニックIpマネジメント株式会社 Monitoring system, monitoring method, program, and distribution board

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007006656A (en) 2005-06-27 2007-01-11 Chugoku Electric Power Co Inc:The Power failure information transmitter and power failure information transmitting system
JP2007336692A (en) 2006-06-15 2007-12-27 Chugoku Electric Power Co Inc:The System for notifying information about service interruption
JP2010250508A (en) 2009-04-14 2010-11-04 Chugoku Electric Power Co Inc:The Power information management method
JP2016185020A (en) 2015-03-26 2016-10-20 東芝ライテック株式会社 Communication system and distribution board
JP2017108482A (en) 2015-12-07 2017-06-15 日東工業株式会社 Power distribution board system
US20190058354A1 (en) 2017-08-15 2019-02-21 Carling Technologies, Inc. Electronic Status Reporting Circuit Breaker
JP2019036533A (en) 2017-08-15 2019-03-07 カーリング テクノロジーズ、 インコーポレイテッドCarling Technologies, Inc. Electronic status reporting circuit breaker
JP2020072639A (en) 2018-10-29 2020-05-07 パナソニックIpマネジメント株式会社 Monitoring system, monitoring method, program, and distribution board

Also Published As

Publication number Publication date
JP2023004429A (en) 2023-01-17

Similar Documents

Publication Publication Date Title
US10551430B2 (en) Remote diagnostic system and method for circuit protection devices such as miniature circuit breakers
CA2873492C (en) Wireless branch circuit energy monitoring system
CN102263645B (en) Power management method and power management system for communication equipment
JP6647756B2 (en) Distribution board monitoring system
CN110120700A (en) Power supply system and its control method
Sankaranarayanan et al. ABASH—Android based smart home monitoring using wireless sensors
JP7365643B2 (en) Monitoring system, monitoring method, program, and distribution board
JP7787657B2 (en) Power outage cause notification system, breaker, power outage cause notification method and program
JP2024091143A (en) Precursor detection system, breaker, distribution board, precursor detection method and program
US12470055B2 (en) Downloadable firmware for programmable circuit breakers
JP7850005B2 (en) Circuit breakers and distribution boards
CN110021997A (en) A kind of intelligent power distribution loop fault detection method and system
JP5336941B2 (en) Power monitoring system
JP7526187B2 (en) Apparatus and method for monitoring a circuit under load using a circuit breaker - Patents.com
KR20190000462U (en) An Apparatus For Automatically Notifying The Restoration Of A System Power Based On Internet of Things
JP2024091144A (en) State estimation system, breaker, distribution board, state estimation method and program
KR20210087232A (en) System for monitoring supplied power and operating method thereof
CN111063584A (en) Electronic molded case circuit breaker
JP2017126266A (en) Monitoring system, monitoring method, and program thereof
JP2016082732A (en) Sequence re-interconnection device and sequence re-interconnection system
JPH0488821A (en) Fault current detector
JP2021103458A (en) Fire detection system and repeater
JPH03135330A (en) System parallel-off detecting apparatus

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20240221

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20241211

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20250107

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20250310

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20250617

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20250812

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20251111

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20251205

R150 Certificate of patent or registration of utility model

Ref document number: 7787657

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150