JP7813624B2 - Method for constructing underground structure and underground structure - Google Patents
Method for constructing underground structure and underground structureInfo
- Publication number
- JP7813624B2 JP7813624B2 JP2022047002A JP2022047002A JP7813624B2 JP 7813624 B2 JP7813624 B2 JP 7813624B2 JP 2022047002 A JP2022047002 A JP 2022047002A JP 2022047002 A JP2022047002 A JP 2022047002A JP 7813624 B2 JP7813624 B2 JP 7813624B2
- Authority
- JP
- Japan
- Prior art keywords
- reinforcing bar
- main
- shaft
- underground structure
- retaining member
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Piles And Underground Anchors (AREA)
Description
本発明は、地中構造物の構築方法および地中構造物に関する。 The present invention relates to a method for constructing an underground structure and an underground structure.
深礎基礎は、一般に、地盤を掘削しながらライナープレートの左右ならびに上下の縁端を順次接続する手順を所定深度まで繰り返すことで、立坑の内側に土留壁を構築し、土留壁の内側に鉄筋を建て込み、さらにコンクリートを打設することによって施工される。一般に土留壁の内側に立て込まれる鉄筋は主鉄筋とフープ筋とを含むが、これらの鉄筋の建て込みに関する技術が種々提案されている。 Deep foundations are generally constructed by excavating the ground while repeatedly connecting the left, right, and top and bottom edges of the liner plate to a specified depth, constructing an earth-retaining wall inside the shaft, then erecting rebar inside the wall, and then pouring concrete. The rebar erected inside the earth-retaining wall generally includes main rebars and hoops, and various techniques have been proposed for erecting these rebars.
例えば特許文献1には、円柱状の杭穴の内部で、架台を所定間隔で設けた架台柱を壁面に沿って垂直方向に設置してフープ筋を仮保持するとともに、上下移動可能な吊り足場を用いてフープ筋を配筋結束し、浮足場を用いてコンクリートを打設し、さらに鉄筋を機械継手工法で連結して縦主筋とする技術が記載されている。 For example, Patent Document 1 describes a technique in which support columns with support structures set at predetermined intervals are installed vertically along the wall surface inside a cylindrical pile hole to temporarily hold hoop reinforcement, and the hoop reinforcement is tied together using a hanging scaffold that can be moved up and down, concrete is poured using a floating scaffold, and reinforcing bars are connected using a mechanical joint method to form longitudinal main reinforcement.
また、特許文献2には、掘削した立坑内に鉄筋組み立て用の足場を形成し、立坑周囲の地上で組立装置を用いてフープ筋を複数段毎に分けて環状に仮組みし、仮組みした複数段のフープ筋を順次立坑内に搬入し、次いで立坑内に主筋を挿入して足場を用いて主筋とフープ筋とを接続する技術が記載されている。 Patent Document 2 also describes a technique in which scaffolding for assembling reinforcing bars is formed inside an excavated shaft, hoop bars are divided into multiple stages and temporarily assembled into a ring using assembly equipment on the ground around the shaft, the temporarily assembled multiple stages of hoop bars are then carried into the shaft one by one, and main bars are then inserted into the shaft and the main bars and hoops are connected using the scaffolding.
さらに、特許文献3には、深礎立坑の坑口地上部にやぐら形の仮設架台を構築するとともに、同期運転可能な複数のチェーンホイルウインチを配置して支持リングを吊り支持し、支持リングに鉄筋篭を構成する縦筋を1本ずつ取り付け、縦筋の周囲に帯筋を溶接し、鉄筋篭としての剛性を確保した部分をチェーンホイルウインチの操作で支持リングとともに順次、深礎立坑内に吊り降ろす技術が記載されている。 Furthermore, Patent Document 3 describes a technology in which a tower-shaped temporary platform is constructed above ground at the entrance of a deep foundation shaft, multiple chain wheel winches that can be operated synchronously are arranged to suspend and support a support ring, the vertical bars that make up the rebar cage are attached to the support ring one by one, ties are welded around the vertical bars, and the section that has secured the rigidity of the rebar cage is then successively lowered into the deep foundation shaft together with the support ring by operating the chain wheel winch.
しかしながら、上記のような従来の鉄筋建て込み技術にはいくつかの課題がある。まず、特許文献1に記載されたように立坑内で鉄筋を組み立てる方法は、組み立てながら鉄筋外側のコンクリートかぶり厚を確認できるため施工の精度は高いが、組み立てに足場が必要であるため施工性は低く、また立坑内での作業が多くなるため安全性も高いとはいえない。特許文献2に記載されたように地上部である程度の組み立てを行ってから立坑内で接合する方法は、施工性や安全性は向上するが、大型の吊り下げ機械が必要になる。また、立坑内での作業は減るものの依然として存在する。特許文献3に記載されたように立坑口で組み立てを行いながら連続的に鉄筋を送り込む方法は、施工性や安全性はさらに向上するが、大掛かりな設備が必要になり、また立坑の外からの組み立て作業になるためコンクリートかぶり厚の確認が困難である。 However, the above-mentioned conventional rebar installation techniques pose several challenges. First, the method of assembling rebar inside a shaft, as described in Patent Document 1, allows for high construction precision because the concrete cover thickness outside the rebar can be checked while assembly is in progress, but requires scaffolding for assembly, making it less workable, and requires a lot of work inside the shaft, making it less safe. The method of assembling a certain amount of rebar above ground and then joining it inside the shaft, as described in Patent Document 2, improves construction efficiency and safety, but requires large hoisting machinery. Furthermore, while it reduces the amount of work inside the shaft, it still exists. The method of continuously feeding rebar while assembling it at the shaft entrance, as described in Patent Document 3, further improves construction efficiency and safety, but requires large-scale equipment, and since assembly work is done from outside the shaft, it is difficult to check the concrete cover thickness.
そこで、本発明は、簡易な設備で施工性および安全性、ならびに品質を向上させた鉄筋の建て込み工程を実施することが可能な、地中構造物の構築方法および地中構造物を提供することを目的とする。 The present invention therefore aims to provide a method for constructing an underground structure and an underground structure that allows for the reinforcing bar installation process to be carried out using simple equipment with improved workability, safety, and quality.
[1]地盤を掘削して立坑を形成する最初の掘削工程と、前記立坑の壁面に沿って土留部材を設置する土留部材設置工程と、前記土留部材に取り付けられた固定治具を用いて水平位置を固定しながら、前記立坑の内部に鉄筋を吊り降ろす最初の鉄筋建て込み工程と、前記地盤をさらに掘削して前記立坑を鉛直方向に掘り進める最後の掘削工程と、前記固定治具を用いて水平位置を固定しながら、前記最後の掘削工程で掘り進められた前記立坑の内部に前記鉄筋を吊り降ろす最後の鉄筋建て込み工程と、前記鉄筋を含む前記立坑の内部にコンクリートを打設するコンクリート打設工程とを含む、地中構造物の構築方法。
[2]前記最初の掘削工程と前記最後の掘削工程との間で、前記地盤を掘削して前記立坑を鉛直方向に掘り進める少なくとも1回の中間掘削工程と、前記固定治具を用いて水平位置を固定しながら、前記中間掘削工程で掘り進められた前記立坑の内部に前記鉄筋を吊り降ろす中間鉄筋建て込み工程とをさらに含む、[1]に記載の地中構造物の構築方法。
[3]前記土留部材は、高さ方向について波形断面を有する、[1]または[2]に記載の地中構造物の構築方法。
[4]前記立坑の壁面と前記土留部材との間に吹付けまたは充填のいずれかまたは両方によってグラウトを施工するグラウト施工工程をさらに含む、[1]から[3]のいずれか1項に記載の地中構造物の構築方法。
[5]前記鉄筋は、鉛直方向に配筋され、それぞれが複数の鉄筋を長さ方向に連結して構成される第1の主鉄筋および第2の主鉄筋を少なくとも含み、前記最後の鉄筋建て込み工程で前記第1の主鉄筋および前記第2の主鉄筋について先端が前記立坑の掘削底面まで到達させられたときに、前記第1の主鉄筋の連結位置と前記第2の主鉄筋の連結位置とが異なる高さに位置する、[1]から[4]のいずれか1項に記載の地中構造物の構築方法。
[6]前記複数の鉄筋のうち、既に建て込まれた鉄筋の上端に新たな鉄筋を接続してから、前記既に建て込まれた鉄筋および前記新たな鉄筋を一緒に吊り降ろす工程を含む、[5]に記載の地中構造物の構築方法。
[7]前記鉄筋は、鉛直方向に配筋される主鉄筋を含み、前記最初の鉄筋建て込み工程の後に、前記主鉄筋の突出部を前記固定治具に係止して前記主鉄筋の高さ位置を固定する固定工程をさらに含む、[1]から[6]のいずれか1項に記載の地中構造物の構築方法。
[8]地盤を掘削して形成された立坑の壁面に沿って設置された土留部材と、前記土留部材に取り付けられた固定治具と、前記固定治具に係合するように配置された鉄筋と、前記鉄筋を含む前記立坑の内部に打設されたコンクリートとを有する地中構造物。
[9]前記鉄筋は、鉛直方向に延びる主鉄筋を含み、前記固定治具は、前記主鉄筋の突出部を係止可能な構造を有する、[8]に記載の地中構造物。
[10]前記固定治具は、前記主鉄筋を挿入および離脱させることが可能な切り欠きを有する、[9]に記載の地中構造物。
[11]前記固定治具は、水平面内で回動することによって前記主鉄筋に接近および離隔する湾曲部を有する、[9]に記載の地中構造物。
[1] A method for constructing an underground structure, comprising: an initial excavation step of excavating the ground to form a vertical shaft; an earth retaining member installation step of installing earth retaining members along the wall surface of the vertical shaft; an initial reinforcing bar installation step of lowering reinforcing bars into the interior of the vertical shaft while fixing the horizontal position using a fixing jig attached to the earth retaining members; a final excavation step of further excavating the ground to excavate the vertical shaft in the vertical direction; a final reinforcing bar installation step of lowering reinforcing bars into the interior of the vertical shaft excavated in the final excavation step while fixing the horizontal position using the fixing jig; and a concrete pouring step of pouring concrete into the interior of the vertical shaft containing the reinforcing bars.
[2] A method for constructing an underground structure as described in [1], further comprising at least one intermediate excavation step between the first excavation step and the final excavation step, in which the ground is excavated and the shaft is dug vertically, and an intermediate reinforcing bar erection step, in which the reinforcing bar is lowered into the shaft dug in the intermediate excavation step while fixing its horizontal position using the fixing jig.
[3] A method for constructing an underground structure described in [1] or [2], wherein the retaining member has a corrugated cross section in the height direction.
[4] A method for constructing an underground structure described in any one of [1] to [3], further comprising a grouting step of applying grout between the wall surface of the shaft and the retaining member by either spraying or filling, or both.
[5] A method for constructing an underground structure described in any one of [1] to [4], wherein the reinforcing bars are arranged vertically and include at least a first main reinforcing bar and a second main reinforcing bar, each of which is composed of multiple reinforcing bars connected longitudinally, and when the tips of the first main reinforcing bar and the second main reinforcing bar reach the bottom of the excavated shaft in the final reinforcing bar installation process, the connection position of the first main reinforcing bar and the connection position of the second main reinforcing bar are located at different heights.
[6] A method for constructing an underground structure described in [5], which includes a step of connecting a new reinforcing bar to the upper end of an already installed reinforcing bar among the plurality of reinforcing bars, and then suspending the already installed reinforcing bar and the new reinforcing bar together.
[7] A method for constructing an underground structure described in any one of [1] to [6], wherein the reinforcing bars include main reinforcing bars arranged vertically, and further includes a fixing process, after the first reinforcing bar installation process, of engaging the protruding portion of the main reinforcing bars with the fixing jig to fix the height position of the main reinforcing bars.
[8] An underground structure comprising: retaining members installed along the wall surface of a vertical shaft formed by excavating the ground; fixing jigs attached to the retaining members; reinforcing bars arranged to engage with the fixing jigs; and concrete poured inside the vertical shaft containing the reinforcing bars.
[9] An underground structure described in [8], wherein the reinforcing bars include main reinforcing bars extending vertically, and the fixing jig has a structure capable of engaging the protruding portions of the main reinforcing bars.
[10] An underground structure as described in [9], wherein the fixing jig has a notch that allows the main reinforcing bars to be inserted and removed.
[11] An underground structure as described in [9], wherein the fixing jig has a curved portion that moves toward and away from the main reinforcing bars by rotating in a horizontal plane.
上記の構成によれば、立坑を段階的に掘削する工程と並行して鉄筋を順次吊り降ろすことによって鉄筋の建て込み工程が行われる。これによって立坑内で鉄筋建て込みのための足場が不要になるため、施工性および安全性が向上する。また、鉄筋の水平位置は土留部材に取り付けられる固定治具によって固定されるため、立坑内で作業をしなくても鉄筋の外側のコンクリートかぶり厚を確実に設定することができる。鉄筋は段階的に順次吊り降ろせばよいため、吊り降ろしのためのクレーンなどの機械は小型化することが可能である。このように、本発明によれば、簡易な設備で施工性および安全性、ならびに品質を向上させた鉄筋の建て込み工程を実施することができる。 With the above configuration, the rebar installation process is carried out by sequentially lowering the rebar in parallel with the process of excavating the shaft in stages. This eliminates the need for scaffolding within the shaft for installing the rebar, improving workability and safety. Furthermore, because the horizontal position of the rebar is fixed by a fixture attached to the retaining wall, the concrete cover thickness outside the rebar can be reliably set without having to work inside the shaft. Because the rebar only needs to be lowered in stages, machinery such as cranes used for lowering it can be made smaller. In this way, the present invention makes it possible to carry out a rebar installation process using simple equipment with improved workability, safety, and quality.
以下に添付図面を参照しながら、本発明の好適な実施形態について詳細に説明する。なお、本明細書および図面において、実質的に同一の機能構成を有する構成要素については、同一の符号を付することにより重複説明を省略する。 Preferred embodiments of the present invention will be described in detail below with reference to the accompanying drawings. Note that in this specification and drawings, components that have substantially the same functional configuration will be assigned the same reference numerals, and redundant explanations will be omitted.
(地中構造物の施工方法)
以下では、図1から図9を参照して、本発明の一実施形態に係る地中構造物である深礎基礎の構築方法について説明する。まず、図1は、地盤を掘削して立坑1を形成する掘削工程の第1段階(最初の掘削工程)、立坑1の壁面に沿って土留部材であるライナープレート2を設置する工程、および立坑1の壁面とライナープレート2との間にグラウト3を施工する工程の後で、立坑1の内部に主鉄筋4Aを建て込む工程(最初の鉄筋建て込み工程)を示す。主鉄筋4Aは鉛直方向に配筋され、立坑1の内周に沿って配列される鉄筋である。この建て込みの工程では、主鉄筋4Aの水平位置をライナープレート2に取り付けられた固定治具5を用いて固定しながら、立坑1の坑口1A側から主鉄筋4Aを立坑1の内部に吊り降ろす。図を簡単にするために省略されているが、図中の奥側に配置される主鉄筋4Aも、奥側のライナープレート2に取り付けられた固定治具を用いて水平位置が固定されている。
(Construction method for underground structures)
A method for constructing a caisson foundation, an underground structure, according to one embodiment of the present invention will be described below with reference to Figures 1 to 9. First, Figure 1 illustrates the first stage (first excavation step) of the excavation process, in which the ground is excavated to form a vertical shaft 1; the process of installing a liner plate 2, which is an earth-retaining member, along the wall of the vertical shaft 1; and the process of applying grout 3 between the wall of the vertical shaft 1 and the liner plate 2. This process is followed by the process of installing main reinforcing bars 4A inside the vertical shaft 1 (first reinforcing bar installation step). The main reinforcing bars 4A are vertically arranged along the inner periphery of the vertical shaft 1. During this installation step, the main reinforcing bars 4A are lowered into the vertical shaft 1 from the entrance 1A of the vertical shaft 1 while their horizontal positions are fixed using a fixing jig 5 attached to the liner plate 2. Although omitted for simplicity, the main reinforcing bars 4A located at the rear of the figure are also fixed in their horizontal positions using a fixing jig attached to the liner plate 2 at the rear.
ここで、本実施形態において、主鉄筋4Aは、図1に示された時点で先端が立坑1の掘削底面1Bまで到達する主鉄筋41A(第1の主鉄筋)と、この時点では先端が掘削底面1Bに到達しない状態で高さ位置が固定される主鉄筋42A(第2の主鉄筋)とを含む。なお、このように建て込みの過程で主鉄筋4Aの高さを互いに違いにすることの利点、および先端が掘削底面1Bに達しない状態で主鉄筋42Aの高さ位置を固定するための固定治具5の構造の例については後述する。 In this embodiment, the main reinforcing bars 4A include main reinforcing bars 41A (first main reinforcing bars) whose tips reach the excavated bottom surface 1B of the shaft 1 as shown in Figure 1, and main reinforcing bars 42A (second main reinforcing bars) whose tips are fixed at a height position before reaching the excavated bottom surface 1B. The advantages of making the main reinforcing bars 4A different heights during the erection process, and an example of the structure of the fixing jig 5 for fixing the height position of the main reinforcing bars 42A before their tips reach the excavated bottom surface 1B, will be described later.
次に、図2に示すように地盤を掘削して立坑1を鉛直方向に掘り進める掘削工程の第2段階(中間掘削工程)が行われ、図3に示すように掘り進められた立坑1の壁面に吹付けグラウト31が施工され、図4に示すように掘り進められた立坑1の壁面に沿ってライナープレート2が設置され、さらに図5に示すように吹付けグラウト31とライナープレート2との間に充填グラウト32が施工される。このようなライナープレート2およびグラウト3の施工方法については特開2020-105806号公報にも記載されており、このような施工方法を採用することによって経済的な設計と施工性の向上が可能である。ただし、本発明の実施形態に係るライナープレートおよびグラウトの施工方法はこの例には限られない。例えば吹付けグラウト31を省略して充填グラウト32のみを施工してもよいし、グラウト3自体を省略して、ライナープレート2に設けられた穴からコンクリートを流入させて立坑1の壁面とライナープレート2との間に充填してもよい。第2段階以外の掘削時についても同様であり、地盤条件などに応じて適切なグラウト3の施工方法を選択することができる。複数の段階の掘削工程でライナープレート2のみを設置した後に一括してグラウト3を施工してもよいし、各段階の掘削時でグラウト3の施工方法が異なっていてもよい。 Next, the second stage (intermediate excavation stage) of the excavation process is carried out, in which the ground is excavated and the shaft 1 is dug vertically, as shown in Figure 2. Then, sprayed grout 31 is applied to the wall of the excavated shaft 1 as shown in Figure 3. A liner plate 2 is installed along the wall of the excavated shaft 1 as shown in Figure 4. Furthermore, filled grout 32 is applied between the sprayed grout 31 and the liner plate 2 as shown in Figure 5. This type of application method for the liner plate 2 and grout 3 is also described in JP 2020-105806 A, and adopting this application method enables economical design and improved workability. However, the application method for the liner plate and grout according to embodiments of the present invention is not limited to this example. For example, the sprayed grout 31 may be omitted and only the filled grout 32 may be applied. Alternatively, the grout 3 may be omitted and concrete may be poured through holes in the liner plate 2 to fill the gap between the wall of the shaft 1 and the liner plate 2. The same applies to excavation other than the second stage, and an appropriate grout 3 application method can be selected depending on ground conditions, etc. In a multi-stage excavation process, the grout 3 may be applied all at once after only the liner plate 2 is installed, or the grout 3 application method may be different for each stage of excavation.
次に、図6および図7に示すように、掘り進められた立坑1の内部に主鉄筋を建て込む工程(中間鉄筋建て込み工程)が行われる。まず、図6に示すように主鉄筋4A(主鉄筋41A,42A)の上部にカプラー61,62で新たな主鉄筋4B(主鉄筋41B,42B)を接続し、図7に示すように接続された主鉄筋4A,4Bを吊り降ろす。ここでも、主鉄筋41Aの先端は立坑1の掘削底面1Bに到達させられるのに対して、主鉄筋42Aは先端が掘削底面1Bに到達しない状態で高さ位置を固定される。なお、本実施形態では主鉄に用いられる鉄筋の接続にカプラーを用いるが、他の実施形態ではカプラーと呼ばれるもの以外の機械式継手や、重ね継手、ガス圧接継手または溶接継手で鉄筋が接続されてもよく、接続方法は特に限定されない。 Next, as shown in Figures 6 and 7, the process of erecting main rebars (intermediate rebar erection process) is carried out inside the excavated shaft 1. First, as shown in Figure 6, new main rebars 4B (main rebars 41B, 42B) are connected to the top of main rebars 4A (main rebars 41A, 42A) using couplers 61, 62, and the connected main rebars 4A, 4B are lowered as shown in Figure 7. Here again, the tip of main rebar 41A is allowed to reach the excavated bottom surface 1B of the shaft 1, while the tip of main rebar 42A is fixed at a fixed height without reaching the excavated bottom surface 1B. Note that while couplers are used to connect the rebars used for the main rebar in this embodiment, in other embodiments, the rebars may be connected using mechanical joints other than those called couplers, lap joints, gas pressure welding joints, or welded joints; the connection method is not particularly limited.
上記で図6に示された例では、既に建て込まれた主鉄筋4Aの上端にカプラー61,62などを用いて主鉄筋4Aに新たな主鉄筋4Bを接続した上で、主鉄筋4A,4Bを一緒に吊り降ろしている。別の例として、先に主鉄筋4Aを吊り降ろしてから、主鉄筋4Aにカプラー61,62などを用いて新たな主鉄筋4Bを接続してもよい。この場合、カプラー61,62を予め地上で主鉄筋4Aの上端に取り付けてから主鉄筋4Aを吊り降ろしてもよいし、立坑1の内部で主鉄筋4Bを接続する時に主鉄筋4Aの上端にカプラー61,62を取り付けてもよい。別の例として、主鉄筋4Aの下端にカプラー61,62などを用いて新たな主鉄筋4Bを接続してもよい。この場合、主鉄筋4Aは、吊り降ろさずに、カプラー61,62を予め主鉄筋4Aの下端に取り付けてから主鉄筋4Bを吊り降ろして主鉄筋4Bを主鉄筋4Aの下端にカプラー61,62を介して接続してもよい。 In the example shown in Figure 6 above, new main rebars 4B are connected to the upper ends of the already installed main rebars 4A using couplers 61, 62, etc., and then the main rebars 4A, 4B are lowered together. As another example, the main rebars 4A may be lowered first, and then new main rebars 4B may be connected to the main rebars 4A using couplers 61, 62, etc. In this case, couplers 61, 62 may be attached to the upper ends of the main rebars 4A on the ground beforehand, and then the main rebars 4A may be lowered, or couplers 61, 62 may be attached to the upper ends of the main rebars 4A when connecting the main rebars 4B inside the shaft 1. As another example, new main rebars 4B may be connected to the lower ends of the main rebars 4A using couplers 61, 62, etc. In this case, instead of lowering the main reinforcing bar 4A, couplers 61 and 62 can be attached to the lower end of the main reinforcing bar 4A in advance, and then the main reinforcing bar 4B can be lowered and connected to the lower end of the main reinforcing bar 4A via couplers 61 and 62.
以下、同様にして中間掘削工程および中間鉄筋建て込み工程を繰り返し、地盤をさらに掘削して立坑1を鉛直方向に掘り進めながら、掘り進められた立坑1の内部に主鉄筋を立て込む。図8は、掘削工程の最終段階(最後の掘削工程)で立坑1が所定の設計深さに到達し、最終段階で掘り進められた立坑1の内部への主鉄筋の建て込み工程(最後の鉄筋建て込み工程)が行われた状態を示す。なお、図8および図9は、図7までとは別個の例であるため、各鉄筋のカプラーの位置は必ずしも一致しない。図示されているように、最後の鉄筋建て込み工程では、主鉄筋41,42のすべてについて先端が立坑1の掘削底面1Bに到達させられる。 The intermediate excavation process and intermediate rebar installation process are repeated in the same manner, further excavating the ground and digging the shaft 1 vertically while installing the main rebars inside the excavated shaft 1. Figure 8 shows the final stage of the excavation process (final excavation process) in which the shaft 1 has reached the specified design depth and the final stage of the process of installing the main rebars inside the excavated shaft 1 (final rebar installation process) has been carried out. Note that Figures 8 and 9 are different examples from those shown up to Figure 7, so the positions of the couplers for each rebar do not necessarily match. As shown, in the final rebar installation process, the tips of all of the main rebars 41 and 42 reach the excavated bottom surface 1B of the shaft 1.
上述のように、本実施形態において、主鉄筋41,42は、それぞれ複数の鉄筋をカプラー61,62で長さ方向に連結して構成される。図6および図7の例で示されたように、掘削の途中では主鉄筋41(第1の主鉄筋)を構成する主鉄筋41A,41Bと主鉄筋42(第2の主鉄筋)を構成する主鉄筋42A,42Bとの間でカプラー61,62の高さ位置を揃える一方で、主鉄筋の先端高さ位置を互いに違いにしていたため、図8に示すように主鉄筋41,42の先端を掘削底面1Bまで到達させると、主鉄筋41のカプラー61による連結位置と、主鉄筋42のカプラー62による連結位置とが、異なる高さに位置する。これによって、構造上の弱点になる連結位置の高さがすべての主鉄筋について揃ってしまうことがなくなり、主鉄筋を含む深礎基礎全体の強度を向上させることができる。なお、図示された例では連結位置が異なる高さに位置する2種類の主鉄筋が配置されるが、連結位置がそれぞれ異なる高さに位置する3種類以上の主鉄筋が配置されてもよい。 As described above, in this embodiment, the main reinforcing bars 41, 42 are each constructed by connecting multiple reinforcing bars longitudinally with couplers 61, 62. As shown in the examples of Figures 6 and 7, during excavation, the height positions of the couplers 61, 62 are aligned between the main reinforcing bars 41A, 41B constituting the main reinforcing bar 41 (first main reinforcing bar) and the main reinforcing bars 42A, 42B constituting the main reinforcing bar 42 (second main reinforcing bar), but the tip height positions of the main reinforcing bars are set to different heights. As a result, when the tips of the main reinforcing bars 41, 42 reach the bottom of the excavation 1B, as shown in Figure 8, the connection position of the main reinforcing bar 41 via the coupler 61 and the connection position of the main reinforcing bar 42 via the coupler 62 are located at different heights. This prevents the connection positions from being aligned for all main reinforcing bars, which could be a structural weakness, and improves the strength of the entire foundation, including the main reinforcing bars. In the illustrated example, two types of main rebars are placed with their connection positions located at different heights, but three or more types of main rebars may be placed with their connection positions located at different heights.
最後に、図9に示すように主鉄筋41,42を含めた立坑1の内部にコンクリート7を打設して、深礎基礎が完成する。なお、図示された例の深礎基礎はコンクリート7が立坑1の内部全体に打設される中実構造であるが、他の例ではコンクリートが内部に空間を空けて打設される中空構造であってもよい。中空構造の地中構造物は、深礎基礎以外にも(構造物としての)立坑、または集水井などとして利用することができる。中空構造の内部の空間に地山掘削時の残土などの土砂を投入した上で、深礎基礎として利用してもよい。また、掘削工程の段階を繰り返す回数は特に限定されない。例えば、掘削工程は第2段階までであってもよく、あるいはより多くの段階が繰り返されてもよい。 Finally, as shown in Figure 9, concrete 7 is poured inside the shaft 1, including the main reinforcing bars 41, 42, to complete the caisson foundation. Note that while the caisson foundation in the illustrated example has a solid structure in which concrete 7 is poured throughout the entire interior of the shaft 1, in other examples it may have a hollow structure in which the concrete is poured leaving a space inside. In addition to caisson foundations, underground structures with hollow structures can also be used as vertical shafts (as structures) or drainage wells. The hollow structure may also be used as a caisson foundation after earth and sand, such as surplus soil from excavating the natural ground, are poured into the internal space. Furthermore, there is no particular limit to the number of times the excavation process steps are repeated. For example, the excavation process may be repeated up to the second step, or more steps may be repeated.
なお、本実施形態では、高さ方向について波形断面を有するライナープレート2を土留部材として配置している。ライナープレート2が波形断面を有することによって、外側に施工されるグラウト3および内側に打設されるコンクリート7との間で例えば異形鉄筋のようなずれ止め効果が得られる。また、ライナープレート2は高さ方向および幅方向についてボルトなどを用いて互いに連結されているため、コンクリート7の高さ方向の補強材(主鉄筋代替)および幅方向の補強材(フープ筋代替)としても機能する。従って、本実施形態では深礎基礎の鉄筋が鉛直方向に配筋される主鉄筋4A,4B,4Cのみを含み、図示された例のように立坑1の周方向に配筋されるフープ筋を含まないか、または通常の設計よりもフープ筋の数は削減されている。このような深礎基礎の設計については、例えば特開2021-080628号公報にも記載されている。本発明の他の実施形態ではフープ筋を配筋することも可能であり、その場合はフープ筋を接合した主鉄筋が先端を揃えた状態で吊り降ろされる。この場合、主鉄筋のカプラー部分の補強については別途考慮される。なお、ライナープレートと呼ばれるものの他にも、同様の機能を有する各種の部材を土留部材として使用することができる。 In this embodiment, a liner plate 2 with a corrugated cross section in the height direction is used as an earth retaining member. The corrugated cross section of the liner plate 2 provides a shear-stop effect, similar to that of deformed reinforcing bars, between the grout 3 applied on the outside and the concrete 7 poured on the inside. Furthermore, because the liner plates 2 are connected to each other in the height and width directions using bolts or other means, they also function as reinforcement for the concrete 7 in the height direction (substitute for main reinforcing bars) and in the width direction (substitute for hoop reinforcing bars). Therefore, in this embodiment, the reinforcing bars of the deep foundation foundation include only main reinforcing bars 4A, 4B, and 4C arranged vertically, and do not include hoop reinforcing bars arranged circumferentially around the shaft 1, as in the illustrated example, or the number of hoop reinforcing bars is reduced compared to conventional designs. Such a deep foundation foundation design is also described, for example, in JP 2021-080628 A. In other embodiments of the present invention, hoop reinforcing bars can also be arranged, in which case the main reinforcing bars connected to the hoop reinforcing bars are lowered with their tips aligned. In this case, reinforcement of the coupler portion of the main rebar is considered separately. In addition to so-called liner plates, various other materials with similar functions can also be used as earth retaining members.
上記で説明したような本実施形態に係る地中構造物の施工方法によれば、立坑1を段階的に掘削する工程と並行して、立坑1の坑口1A側から主鉄筋4A,4B,4Cを順次吊り降ろすことによって鉄筋の建て込み工程が行われる。これによって立坑1内で鉄筋建て込みのための足場が不要になるため、施工性および安全性が向上する。また、主鉄筋4A,4B,4Cの水平位置はライナープレート2に取り付けられた固定治具5によって固定されるため、立坑1内で作業をしなくても主鉄筋4A,4B,4Cの外側のコンクリートかぶり厚を確実に設定することができる。また、フープ筋を省略する場合は主鉄筋4A、4B,4Cを1本(1組)ずつ吊り降ろすことが可能であるため、吊り降ろしのために大型のクレーンなどの機械は必要とされない。フープ筋を配置する場合も、従来よりもフープ筋の数が削減されていれば、吊り降ろしのためのクレーンなどの機械は小型化することが可能である。 According to the underground structure construction method of this embodiment described above, the rebar installation process is carried out by sequentially lowering the main rebars 4A, 4B, and 4C from the entrance 1A of the shaft 1 in parallel with the process of excavating the shaft 1 in stages. This eliminates the need for scaffolding for installing the rebars inside the shaft 1, improving workability and safety. Furthermore, because the horizontal positions of the main rebars 4A, 4B, and 4C are fixed by fixing jigs 5 attached to the liner plate 2, the concrete cover thickness outside the main rebars 4A, 4B, and 4C can be reliably set without work inside the shaft 1. Furthermore, if hoops are omitted, the main rebars 4A, 4B, and 4C can be lowered one by one (one set at a time), eliminating the need for large cranes or other machinery for lowering. Even when hoops are installed, if the number of hoops is reduced compared to conventional methods, the machinery used for lowering the rebars, such as cranes, can be made smaller.
図10から図12は、本発明の一実施形態に係る地中構造物の施工方法の変形例を示す図である。最終的に第1の主鉄筋の連結位置と第2の主鉄筋の連結位置とを異なる高さに位置させる方法として、図1から図7に示した例では掘削の途中の連結位置の高さを揃えつつ、主鉄筋の先端高さ位置を互いに違いにし、かつ先端位置が深い方の主鉄筋の先端を掘削底面に到達させる方法を説明したが、以下で説明するように他の方法も適用可能である。なお、以下の図10から図12は、上記の例における図1の段階に相当する。 Figures 10 to 12 are diagrams showing modified examples of a construction method for underground structures according to one embodiment of the present invention. As a method for ultimately positioning the connection positions of the first main reinforcing bars and the second main reinforcing bars at different heights, the examples shown in Figures 1 to 7 explain a method in which the connection positions during excavation are aligned at the same height, the tip heights of the main reinforcing bars are made different, and the tip of the main reinforcing bar with the deeper tip reaches the bottom of the excavation. However, as explained below, other methods are also applicable. Note that Figures 10 to 12 below correspond to the stage shown in Figure 1 in the above example.
例えば、図10に示された例のように、主鉄筋41A,42Aの先端高さ位置を互い違いにしつつ、先端位置が深い方の主鉄筋41Aも掘削底面1Bには到達しない状態で高さ位置を固定してもよい。あるいは、図11に示された例のように、掘削の途中の時点で、主鉄筋41A,42Aの先端高さ位置を揃えていずれも掘削底面1Bに到達させてもよい。この場合、掘削の途中の時点で、主鉄筋41,42の連結位置は異なる高さになる。また、図12に示された例のように、主鉄筋41A,42Aの先端高さ位置を揃えつつ、主鉄筋41A,42Aのいずれの先端も掘削底面1Bには到達しない状態で高さ位置を固定してもよい。 For example, as shown in the example in Figure 10, the tip height positions of the main rebars 41A, 42A may be staggered, and the height position of the main rebar 41A with the deeper tip position may be fixed so that it does not reach the bottom surface 1B of the excavation. Alternatively, as shown in the example in Figure 11, the tip height positions of the main rebars 41A, 42A may be aligned at a point in the middle of excavation so that both reach the bottom surface 1B of the excavation. In this case, the connecting positions of the main rebars 41, 42 will be at different heights at a point in the middle of excavation. Also, as shown in the example in Figure 12, the tip height positions of the main rebars 41A, 42A may be aligned, and the height positions may be fixed so that neither tip of the main rebars 41A, 42A reaches the bottom surface 1B of the excavation.
(鉄筋の固定方法)
図13は、本発明の一実施形態において鉄筋の高さ位置を固定する方法の例を示す図である。なお、図を簡単にするために、立坑1の径方向の断面内に位置する1対の鉄筋、およびこれらの鉄筋を固定する固定治具以外は図示を省略している。図示された例では、上記で図1に示した例と同様に立坑1の掘削工程の第1段階が終わり、主鉄筋が建て込まれている。この例において、主鉄筋4Aは図1の例よりも短尺であり、既に上部にカプラー6Aを介して主鉄筋4Bが接続されている。さらに、主鉄筋4Bの上端にはまだ他の鉄筋は接続されていないが、カプラー6Bが先行して取り付けられている。ここで、カプラー6A,6Bは、例えば主鉄筋4A,4Bのそれぞれの端部に形成されたねじ切り部分(おねじ)を螺合させるねじ孔(めねじ)が貫通した筒状の部材である。主鉄筋4A,4Bに取り付けられたカプラー6A,6Bは、主鉄筋4A,4Bよりも外径が大きい突出部を形成する。図示された例では、主鉄筋4A,4Bの長さに合わせて固定治具5を配置し、突出部であるカプラー6A,6Bを固定治具5に係止させることで、主鉄筋4A,4Bの高さ位置が固定される。従って、この後、立坑1の第2段階の掘削をする間は主鉄筋4A,4Bの高さ位置を保持し、掘削が終わってから主鉄筋4A,4Bを吊り降ろすことができる。
(Method of fixing rebar)
FIG. 13 is a diagram showing an example of a method for fixing the height position of rebars in one embodiment of the present invention. For simplicity, only a pair of rebars located within the radial cross section of the shaft 1 and the fixing jigs for securing these rebars are shown. In the illustrated example, the first stage of the excavation process for the shaft 1 has been completed, as in the example shown in FIG. 1 , and the main rebars have been installed. In this example, the main rebar 4A is shorter than the example shown in FIG. 1 , and the main rebar 4B has already been connected to its upper part via a coupler 6A. Furthermore, although no other rebars have yet been connected to the upper end of the main rebar 4B, the coupler 6B has already been attached. Here, the couplers 6A and 6B are cylindrical members with threaded holes (internal threads) that thread onto the threaded portions (external threads) formed at the respective ends of the main rebars 4A and 4B. The couplers 6A and 6B attached to the main rebars 4A and 4B form protrusions with larger outer diameters than the main rebars 4A and 4B. In the illustrated example, the height positions of the main reinforcing bars 4A, 4B are fixed by positioning the fixing jig 5 to match the length of the main reinforcing bars 4A, 4B and engaging the protruding couplers 6A, 6B with the fixing jig 5. Therefore, thereafter, the height positions of the main reinforcing bars 4A, 4B can be maintained during the second stage of excavation of the shaft 1, and the main reinforcing bars 4A, 4B can be lowered after excavation is completed.
図14は、図13に示された例で利用可能な固定治具の第1の例を示す図である。図示された例において、固定治具5Aは全体として一方が二又になった板状であり、二又の根元部分にはライナープレート2への取り付け孔51が形成され、二股の部分には向かい合う辺が平行な切り欠き52が形成される。図14(a)に示されるように、主鉄筋4Aの上端にカプラー6Aを取り付けた状態で、主鉄筋4Aを固定治具5Aの切り欠き52に挿入し、カプラー6Aを切り欠き52の両側で固定治具5Aの上面に載置することによってカプラー6Aを係止し、主鉄筋4Aの高さ位置を固定することができる。主鉄筋4A(および主鉄筋4B)の挿入、ならびにカプラー6A(およびカプラー6B)の係止を可能にするために、切り欠き52の内寸は、主鉄筋4A(および主鉄筋4B)の外径よりも大きく、カプラー6A(およびカプラー6B)の外径よりも小さい。 Figure 14 shows a first example of a fixing jig that can be used in the example shown in Figure 13. In the example shown, the fixing jig 5A is generally plate-shaped with one fork, and an attachment hole 51 for the liner plate 2 is formed at the base of the fork, and a notch 52 with parallel opposing sides is formed in the fork. As shown in Figure 14(a), with a coupler 6A attached to the upper end of a main reinforcing bar 4A, the main reinforcing bar 4A can be inserted into the notch 52 of the fixing jig 5A and the coupler 6A can be placed on the top surface of the fixing jig 5A on both sides of the notch 52 to engage the coupler 6A and fix the height position of the main reinforcing bar 4A. To allow for the insertion of the main rebar 4A (and main rebar 4B) and the engagement of the coupler 6A (and coupler 6B), the inner dimension of the notch 52 is larger than the outer diameter of the main rebar 4A (and main rebar 4B) and smaller than the outer diameter of the coupler 6A (and coupler 6B).
図14(b)に示されるようにカプラー6Aに上方から主鉄筋4Bを取り付けて主鉄筋4A,4Bを接続し、さらに主鉄筋4Bの上端にカプラー6Bを取り付けてから、図14(c)に示すように主鉄筋4A,4Bの水平位置を固定治具5Aから離れるように、すなわち立坑1(図示せず)の中心に向かってずらす。これによって、カプラー6Aが切り欠き52から離脱し、固定治具5Aによるカプラー6Aの係止が解除される。この状態で、図14(d)に示すように主鉄筋4A,4Bを吊り降ろし、今度は主鉄筋4Bを切り欠き52に挿入する。これによって、吊り降ろし後の主鉄筋4A,4Bの高さ位置を、カプラー6Bを固定治具5Aに係止することによって固定することができる。 As shown in Figure 14(b), the main rebar 4B is attached to the coupler 6A from above to connect the main rebars 4A and 4B. Then, as shown in Figure 14(c), the coupler 6B is attached to the upper end of the main rebar 4B. The horizontal position of the main rebars 4A and 4B is then shifted away from the fixing jig 5A, i.e., toward the center of the shaft 1 (not shown). This disengages the coupler 6A from the notch 52, releasing it from the fixing jig 5A. In this state, the main rebars 4A and 4B are lowered, as shown in Figure 14(d), and the main rebar 4B is then inserted into the notch 52. The height position of the main rebars 4A and 4B after lowering can be fixed by engaging the coupler 6B with the fixing jig 5A.
図15は、図13に示された例で利用可能な固定治具の第2の例を示す図である。図示された例において、固定治具5Bは取り付け部と湾曲部とを有する板状であり、取り付け部にはライナープレート2への取り付け孔51が形成され、湾曲部の内側にはC字形の内縁53が形成される。図15(a)に示されるように、主鉄筋4Aの上端にカプラー6Aを取り付けた状態で、固定治具5Bの内縁53を主鉄筋4Aに沿わせ、カプラー6Aを内縁53の外側で固定治具5Bの上面に載置することによってカプラー6Aを係止し、主鉄筋4Aの高さ位置を固定することができる。カプラー6Aを安定的に係止するために、内縁53は、部分的に平面形状の曲率半径が主鉄筋4A(および主鉄筋4B)の外周面の曲率半径よりも大きく、カプラー6A(およびカプラー6B)の外周面の曲率半径よりも小さい部分を有することが好ましい。 Figure 15 shows a second example of a fixing jig that can be used in the example shown in Figure 13. In the illustrated example, the fixing jig 5B is plate-shaped and has an attachment portion and a curved portion. The attachment portion has an attachment hole 51 for connecting to the liner plate 2, and a C-shaped inner edge 53 is formed on the inside of the curved portion. As shown in Figure 15(a), with a coupler 6A attached to the upper end of a main reinforcing bar 4A, the inner edge 53 of the fixing jig 5B is aligned with the main reinforcing bar 4A, and the coupler 6A is placed on the top surface of the fixing jig 5B outside the inner edge 53 to lock the coupler 6A and fix the height position of the main reinforcing bar 4A. To stably lock the coupler 6A, it is preferable that the inner edge 53 has a planar shape with a radius of curvature that is greater than the radius of curvature of the outer surface of the main reinforcing bar 4A (and main reinforcing bar 4B) and smaller than the radius of curvature of the outer surface of the coupler 6A (and coupler 6B).
図15(b)に示されるようにカプラー6Aに上方から主鉄筋4Bを取り付けて主鉄筋4A,4Bを接続し、さらに主鉄筋4Bの上端にカプラー6Bを取り付けてから、図15(c)に示すように取り付け孔51を中心にして固定治具5Bを水平面内で回動させ、主鉄筋4Aから離隔させる。これによって、カプラー6Aが固定治具5Bの内縁53から離れ、固定治具5Bによるカプラー6Aの係止が解除される。この状態で、図15(d)に示すように主鉄筋4A,4Bを吊り降ろし、再び取り付け孔51を中心にして固定治具5Bを水平面内で回動させて主鉄筋4Bに接近させ、今度は内縁53を主鉄筋4Bに沿わせる。これによって、吊り降ろし後の主鉄筋4A,4Bの高さ位置を、カプラー6Bを固定治具5Bに係止することによって固定することができる。このような固定治具5Bは、主鉄筋4A,4Bの水平位置を移動させることなく高さ位置の固定および解除を切り替えることができるため、例えば主鉄筋4A,4Bに加えてフープ筋が配置され、主鉄筋4A,4Bとフープ筋とを接合した状態で吊り降ろす場合でも利用可能である。 As shown in Figure 15(b), the main rebar 4B is attached to the coupler 6A from above to connect the main rebars 4A and 4B. Then, as shown in Figure 15(c), the fixing jig 5B is rotated in the horizontal plane around the mounting hole 51 to move it away from the main rebar 4A. This moves the coupler 6A away from the inner edge 53 of the fixing jig 5B, releasing the coupler 6A from its engagement with the fixing jig 5B. In this state, the main rebars 4A and 4B are lowered as shown in Figure 15(d), and the fixing jig 5B is again rotated in the horizontal plane around the mounting hole 51 to move it closer to the main rebar 4B, this time aligning the inner edge 53 with the main rebar 4B. The height positions of the main rebars 4A and 4B after lowering can be fixed by engaging the coupler 6B with the fixing jig 5B. This type of fixing jig 5B can fix and release the vertical position without moving the horizontal position of the main reinforcing bars 4A, 4B, so it can also be used, for example, when hoops are placed in addition to the main reinforcing bars 4A, 4B and the main reinforcing bars 4A, 4B are lowered while still connected to the hoops.
図16は、図13に示された例で利用可能な固定治具の第3の例を示す図である。図示された例では、固定治具5Cが立坑1の坑口1A(図示せず)にフラットバーやアングルを用いて固定される環状部材である。固定治具5Cの内周には複数の切り欠き54が形成される。切り欠き54は、上記で図14を参照して説明した例における切り欠きと同様に、主鉄筋を挿入することが可能な部分である。固定治具5Cの内周には、立坑1の周方向における主鉄筋の配筋間隔に対応する間隔で切り欠き54が形成される。それぞれの切り欠き54に主鉄筋を挿入し、カプラーを係止することによって、上記の図14および図15の例と同様に主鉄筋の高さ位置を固定することができる。また、切り欠き54から主鉄筋を離脱させ、カプラーの係止を解除することによって、主鉄筋をさらに吊り降ろすことができる。このような固定治具5Cは、例えば固定治具のライナープレートへの取り付けが困難な場合でも利用可能である。 Figure 16 shows a third example of a fixing jig that can be used in the example shown in Figure 13. In the illustrated example, the fixing jig 5C is an annular member fixed to the shaft entrance 1A (not shown) of the shaft 1 using flat bars or angles. Multiple notches 54 are formed on the inner periphery of the fixing jig 5C. Similar to the notches in the example described above with reference to Figure 14, these notches 54 are portions into which main rebars can be inserted. The inner periphery of the fixing jig 5C is formed with notches 54 spaced at intervals corresponding to the spacing of the main rebars circumferentially around the shaft 1. By inserting the main rebars into each notch 54 and engaging the couplers, the height position of the main rebars can be fixed, as in the examples of Figures 14 and 15 above. Furthermore, by removing the main rebars from the notches 54 and releasing the couplers, the main rebars can be further lowered. This type of fixing jig 5C can be used, for example, even in cases where it is difficult to attach the fixing jig to a liner plate.
上記で説明した例ではカプラー6A,6Bを固定治具5A,5B,5Cに係止することによって主鉄筋4A,4Bの高さ位置が固定されるが、他の例では、主鉄筋4A,4Bの中間部にスリーブ状の部材を圧接したり、その他の部材を溶接したりして突出部を形成し、固定治具5A,5B,5Cに係止してもよい。固定治具5A,5Bについては、図13に示された例のように取り付け孔51を用いてライナープレート2の最上段を含む複数の段に取り付けられてもよいし、最上段だけに取り付けられてもよい。 In the example described above, the height positions of the main reinforcing bars 4A and 4B are fixed by engaging the couplers 6A and 6B with the fixing jigs 5A, 5B, and 5C. However, in other examples, a sleeve-shaped member may be pressed against the middle of the main reinforcing bars 4A and 4B, or another member may be welded to form a protrusion, which can then be engaged with the fixing jigs 5A, 5B, and 5C. The fixing jigs 5A and 5B may be attached to multiple tiers of the liner plate 2, including the top tier, using the mounting holes 51, as in the example shown in Figure 13, or they may be attached to just the top tier.
なお、本発明の実施形態は上記で説明したように固定治具に主鉄筋の突出部を係止することによって高さ位置を固定する例には限定されず、主鉄筋の高さ位置の固定には別途設けられるクランプなどの手段が用いられてもよい。また、上記の固定治具5A,5B,5Cのように主鉄筋の水平位置および高さ位置を固定することが可能な固定治具と、主鉄筋の水平位置だけを固定する固定治具とが併用されてもよい。主鉄筋の高さ位置を固定する固定治具は、例えば各主鉄筋の最上段に1か所だけ配置されてもよい。なお、上記で説明された例では高さ方向について複数の固定治具が配置されているが、少なくとも1か所の固定治具で水平位置を固定すれば、例えば掘削終了時点で主鉄筋の先端を掘削底面に当接させることによって2点支持を構成し、主鉄筋の水平位置を安定させることができる。 Note that embodiments of the present invention are not limited to the example described above in which the height position of the main rebar is fixed by engaging the protruding portion of the main rebar with the fixing jig; a separate clamp or other means may be used to fix the height position of the main rebar. Furthermore, fixing jigs capable of fixing the horizontal and vertical positions of the main rebar, such as fixing jigs 5A, 5B, and 5C described above, may be used in combination with fixing jigs that fix only the horizontal position of the main rebar. A fixing jig that fixes the height position of the main rebar may be placed in only one location, for example, on the topmost level of each main rebar. Note that while multiple fixing jigs are placed in the height direction in the example described above, if the horizontal position is fixed with at least one fixing jig, two-point support can be achieved by, for example, abutting the tip of the main rebar against the bottom of the excavation at the end of excavation, thereby stabilizing the horizontal position of the main rebar.
以上、添付図面を参照しながら本発明の好適な実施形態について詳細に説明したが、本発明はかかる例に限定されない。本発明の属する技術の分野における通常の知識を有する者であれば、請求の範囲に記載された技術的思想の範疇内において、各種の変更例または修正例に想到し得ることは明らかであり、これらについても、当然に本発明の技術的範囲に属するものと了解される。 The above describes in detail preferred embodiments of the present invention with reference to the accompanying drawings, but the present invention is not limited to such examples. It is clear that a person with ordinary skill in the technical field to which the present invention pertains can conceive of various modifications or alterations within the scope of the technical ideas set forth in the claims, and it is understood that these also naturally fall within the technical scope of the present invention.
1…立坑、1A…坑口、1B…掘削底面、2…ライナープレート、3…グラウト、31…吹付けグラウト、32…充填グラウト、4A,4B,4C,41,41A,41B,42,42A,42B…主鉄筋、5,5A,5B,5C…固定治具、51…取り付け孔、52,54…切り欠き、53…内縁、61,62,6A,6B…カプラー、7…コンクリート。 1... shaft, 1A... mine entrance, 1B... excavation bottom, 2... liner plate, 3... grout, 31... sprayed grout, 32... filled grout, 4A, 4B, 4C, 41, 41A, 41B, 42, 42A, 42B... main reinforcing bars, 5, 5A, 5B, 5C... fixing jig, 51... mounting hole, 52, 54... notch, 53... inner edge, 61, 62, 6A, 6B... coupler, 7... concrete.
Claims (9)
前記第1の掘削工程で掘り進められた前記立坑の壁面に沿って第1の土留部材を設置する第1の土留部材設置工程と、
前記第1の土留部材に取り付けられた固定治具を用いて水平位置を固定しながら、前記立坑の内部に鉛直方向に配筋される鉄筋を吊り降ろす第1の鉄筋建て込み工程と、
前記地盤をさらに掘削して前記立坑を鉛直方向に掘り進める少なくとも1回の第2の掘削工程と、
前記第2の掘削工程で掘り進められた前記立坑の壁面に沿って第2の土留部材を設置する少なくとも1回の第2の土留部材設置工程と、
前記固定治具を用いて水平位置を固定しながら、前記第2の掘削工程で掘り進められた前記立坑の内部に前記鉄筋を吊り降ろす少なくとも1回の第2の鉄筋建て込み工程と、
前記鉄筋を含む前記立坑の内部にコンクリートを打設するコンクリート打設工程と
を含み、
前記鉄筋は、前記第1の土留部材または前記第2の土留部材の近傍に配置され、長さ方向に連結される第1の鉄筋および第2の鉄筋を含む、地中構造物の構築方法。 a first excavation step of excavating the ground to form a vertical shaft;
a first earth retaining member installation step of installing a first earth retaining member along a wall surface of the vertical shaft excavated in the first excavation step ;
A first reinforcing bar erection process in which reinforcing bars arranged vertically inside the vertical shaft are lowered while fixing the horizontal position using a fixing jig attached to the first retaining member;
at least one second excavation step of further excavating the ground to excavate the shaft in a vertical direction;
At least one second earth retaining member installation step of installing a second earth retaining member along a wall surface of the shaft excavated in the second excavation step;
At least one second reinforcing bar erection step of lowering the reinforcing bar into the shaft excavated in the second excavation step while fixing the horizontal position using the fixing jig;
a concrete pouring step of pouring concrete into the shaft containing the reinforcing bar ,
A method for constructing an underground structure , wherein the reinforcing bars include a first reinforcing bar and a second reinforcing bar that are placed near the first earth retaining member or the second earth retaining member and connected in the longitudinal direction .
最後に実施される前記第2の鉄筋建て込み工程で前記第1の主鉄筋および前記第2の主鉄筋について先端が前記立坑の掘削底面まで到達させられたときに、前記第1の主鉄筋の連結位置と前記第2の主鉄筋の連結位置とが異なる高さに位置する、請求項1から請求項4のいずれか1項に記載の地中構造物の構築方法。 The reinforcing bars include at least a first main reinforcing bar and a second main reinforcing bar, and the first main reinforcing bar and the second main reinforcing bar are respectively configured by the first reinforcing bar and the second reinforcing bar connected in a longitudinal direction;
A method for constructing an underground structure described in any one of claims 1 to 4 , wherein when the tips of the first main reinforcing bar and the second main reinforcing bar reach the bottom of the excavated shaft in the final second reinforcing bar installation process, the connection position of the first main reinforcing bar and the connection position of the second main reinforcing bar are located at different heights.
前記第1の鉄筋建て込み工程の後に、前記突出部を前記固定治具に係止して前記第1の鉄筋の高さ位置を固定する固定工程をさらに含む、請求項1から請求項5のいずれか1項に記載の地中構造物の構築方法。 At least the end or middle portion of the first reinforcing bar is formed with a protruding portion having an outer diameter larger than that of other portions,
A method for constructing an underground structure as described in any one of claims 1 to 5 , further comprising a fixing step of engaging the protrusion with the fixing jig to fix the height position of the first reinforcing bar after the first reinforcing bar erection step.
前記土留部材に取り付けられた固定治具と、
鉛直方向に配筋され、前記固定治具に係合するように配置された鉄筋と、
前記鉄筋を含む前記立坑の内部に打設されたコンクリートと
を有し、
前記鉄筋は、長さ方向に連結される第1の鉄筋および第2の鉄筋を含み、
少なくとも前記第1の鉄筋には他の部分よりも外径が大きい突出部が形成され、
前記固定治具は、前記突出部を係止可能な構造を有する地中構造物。 an earth retaining member installed along the wall surface of a vertical shaft formed by excavating the ground;
A fixing jig attached to the retaining member;
A reinforcing bar arranged vertically and disposed so as to engage with the fixing jig;
and concrete poured inside the shaft containing the reinforcing bar ,
The reinforcing bars include a first reinforcing bar and a second reinforcing bar connected in a longitudinal direction;
At least the first reinforcing bar has a protruding portion having an outer diameter larger than that of other portions,
The fixing jig is an underground structure having a structure capable of engaging the protrusion .
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2022047002A JP7813624B2 (en) | 2022-03-23 | 2022-03-23 | Method for constructing underground structure and underground structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2022047002A JP7813624B2 (en) | 2022-03-23 | 2022-03-23 | Method for constructing underground structure and underground structure |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2023140927A JP2023140927A (en) | 2023-10-05 |
| JP7813624B2 true JP7813624B2 (en) | 2026-02-13 |
Family
ID=88206509
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2022047002A Active JP7813624B2 (en) | 2022-03-23 | 2022-03-23 | Method for constructing underground structure and underground structure |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP7813624B2 (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP7565121B1 (en) | 2024-01-17 | 2024-10-10 | 株式会社丸和 | Connecting fitting set and connecting method |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2000282777A (en) | 1999-03-29 | 2000-10-10 | Nishimatsu Constr Co Ltd | Reinforcing bar fixture and rebar construction method |
| JP2016180266A (en) | 2015-03-25 | 2016-10-13 | 東京鐵鋼株式会社 | Pile cage |
| JP2020105806A (en) | 2018-12-27 | 2020-07-09 | 日鉄建材株式会社 | Method for constructing underground structure, and underground structure |
| JP2020204163A (en) | 2019-06-14 | 2020-12-24 | 日鉄建材株式会社 | Reinforcing bar arrangement device and reinforcing bar construction method |
| JP2021080628A (en) | 2019-11-14 | 2021-05-27 | 日鉄建材株式会社 | Design method of underground structure, construction method of underground structure and underground structure |
Family Cites Families (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS4518839Y1 (en) * | 1966-03-28 | 1970-07-31 | ||
| JP3564669B2 (en) * | 1994-07-20 | 2004-09-15 | 東急建設株式会社 | Reinforcement spacer and foundation pile method |
| JP5164778B2 (en) * | 2008-10-06 | 2013-03-21 | 株式会社ディビーエス | Pile head joint structure |
| JP5943988B2 (en) * | 2014-12-08 | 2016-07-05 | 株式会社タック | Template and fixing plate for column reinforcement assembly |
-
2022
- 2022-03-23 JP JP2022047002A patent/JP7813624B2/en active Active
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2000282777A (en) | 1999-03-29 | 2000-10-10 | Nishimatsu Constr Co Ltd | Reinforcing bar fixture and rebar construction method |
| JP2016180266A (en) | 2015-03-25 | 2016-10-13 | 東京鐵鋼株式会社 | Pile cage |
| JP2020105806A (en) | 2018-12-27 | 2020-07-09 | 日鉄建材株式会社 | Method for constructing underground structure, and underground structure |
| JP2020204163A (en) | 2019-06-14 | 2020-12-24 | 日鉄建材株式会社 | Reinforcing bar arrangement device and reinforcing bar construction method |
| JP2021080628A (en) | 2019-11-14 | 2021-05-27 | 日鉄建材株式会社 | Design method of underground structure, construction method of underground structure and underground structure |
Also Published As
| Publication number | Publication date |
|---|---|
| JP2023140927A (en) | 2023-10-05 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| EP2708658A1 (en) | Batch-installation-type large-caliber underwater casing installation structure using sheet pile and method for constructing same | |
| JP3249789B2 (en) | Reinforcement method for columnar structures | |
| KR101187174B1 (en) | Pre-founded Column System having Bearing-Shear Band and Beam-Column Connection System using Grouted Jacket having Bearing-Shear Band for Top-Down or Common Construction | |
| JP7813624B2 (en) | Method for constructing underground structure and underground structure | |
| KR20060092552A (en) | Construction method of unsupported downward frame using cast-in-place pile | |
| KR100849226B1 (en) | Earthquake temporary facility by ClP and this construction method | |
| KR102267641B1 (en) | PHC pile construction method using joint PHC pile and detachable auxiliary pile | |
| JP2022114198A (en) | Installation method for spring spacers, reinforcing bar cages and underground piles | |
| KR101256311B1 (en) | Structual deepening method | |
| JP7543164B2 (en) | Earth retaining structures | |
| JP4993132B2 (en) | Foundation reinforcement method for existing structures | |
| JP2023121248A (en) | Well head foot protection member for liner plate earth-retaining wall, and well head foot protection method of liner plate earth-retaining wall | |
| KR100673475B1 (en) | PC girder member for base frame frame, assembly structure and method of construction | |
| KR101238640B1 (en) | Pre-founded Column having Bearing-Shear Band for Top-Down or Common Construction | |
| JP6677564B2 (en) | Reinforced basket and connection method of reinforced basket | |
| KR101238639B1 (en) | Pre-founded Column having Bearing-Shear Band for Top-Down or Common Construction | |
| JP2018119338A (en) | Horizontal resistance structure of existing building and construction method of horizontal resistance structure of existing building | |
| CN222685498U (en) | A foundation pit support structure | |
| JP7342343B2 (en) | How to install piles | |
| JP2007107233A (en) | Construction method for earth retaining structure | |
| KR101797982B1 (en) | Pipe structure with reinforcing bar and construction method of concrete file using the same | |
| JP7543162B2 (en) | Steel earth retaining panel, earth retaining structure using said steel earth retaining panel, and construction method for said earth retaining structure | |
| JP7634399B2 (en) | Earth retaining structures | |
| KR101255610B1 (en) | Structure construction method and structure of use it | |
| KR101238641B1 (en) | Pre-founded Column having Bearing-Shear Band for Top-Down or Common Construction |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20250108 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20250829 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20250902 |
|
| A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20251029 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20260127 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20260202 |
|
| R150 | Certificate of patent or registration of utility model |
Ref document number: 7813624 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |