Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPS5812437B2 - Method for monitoring dry sand amount in muddy shield drilling method - Google Patents
[go: Go Back, main page]

JPS5812437B2 - Method for monitoring dry sand amount in muddy shield drilling method - Google Patents

Method for monitoring dry sand amount in muddy shield drilling method

Info

Publication number
JPS5812437B2
JPS5812437B2 JP7192277A JP7192277A JPS5812437B2 JP S5812437 B2 JPS5812437 B2 JP S5812437B2 JP 7192277 A JP7192277 A JP 7192277A JP 7192277 A JP7192277 A JP 7192277A JP S5812437 B2 JPS5812437 B2 JP S5812437B2
Authority
JP
Japan
Prior art keywords
excavation
dry sand
amount
sand amount
standard
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP7192277A
Other languages
Japanese (ja)
Other versions
JPS547735A (en
Inventor
広宣 山崎
文考 熊井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tekken Corp
Original Assignee
Tekken Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tekken Corp filed Critical Tekken Corp
Priority to JP7192277A priority Critical patent/JPS5812437B2/en
Publication of JPS547735A publication Critical patent/JPS547735A/en
Publication of JPS5812437B2 publication Critical patent/JPS5812437B2/en
Expired legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Description

【発明の詳細な説明】 この発明は泥水式シールド掘削工法における乾砂量の監
視方法に関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for monitoring the amount of dry sand in a muddy shield excavation method.

従来、泥水式シールド掘削工法において、掘削機の送水
管と排泥管とにそれぞれガンマ線密度計と流量計とを設
けて演算器により実掘削乾砂量を算出し、この乾砂量を
監視しながら掘削管理を行っていたが、乾砂量が増大し
た場合そのまま掘削を続行しても安全なのか、あるいは
掘削を中断して原因を究明すべきかどうかの判断が困難
であった。
Conventionally, in the mud shield excavation method, a gamma ray density meter and a flow meter were installed in the water pipe and mud drainage pipe of the excavator, the actual excavated dry sand amount was calculated by a calculator, and this dry sand amount was monitored. However, when the amount of dry sand increased, it was difficult to judge whether it was safe to continue excavation or whether to suspend excavation and investigate the cause.

この発明は上記のような従来の欠点を排除できる乾砂量
の監視方法を提供することを目的とする。
It is an object of the present invention to provide a method for monitoring the amount of dry sand that can eliminate the drawbacks of the conventional methods as described above.

この発明による方法は各基準掘削距離毎に掘削する泥水
式シールド掘削工法において、 (a)実瞬間掘削乾砂量を測定する測定工程と(b)前
記実瞬間掘削乾砂量の測定値を区分演算器に導き各基準
掘削距離を複数に分割してなる各分割区分ごとの平均瞬
間掘削乾砂量を算出する第1の算出工程と (c)前記第1の算出工程の算出値に各分割区分の掘削
時間を乗算して各分割区分の実掘削乾砂量を算出する第
2の算出工程と (d)前記第2の算出工程の算出値から各基準掘削距離
ごとの標準偏差を算出する第3の算出工程と (e)前記標準偏差の算出値に応じて後続の基準掘削距
離に対する管理限界を設定器に設定する設定工程と (f)前記第2の算出工程の算出値が管理限界内にある
.か否かを監視する監視工程と を備えてなることを特徴とするものである。
The method according to the present invention uses (a) a measurement step of measuring the actual instantaneous excavated dry sand amount, and (b) a measurement step of the actual instantaneous excavated dry sand amount in the muddy shield excavation method in which excavation is performed for each standard excavation distance. (c) a first calculation step of dividing each reference excavation distance into a plurality of parts to calculate the average instantaneous excavated dry sand amount for each division; and (c) dividing each into the calculated value of the first calculation step. A second calculation step of calculating the actual excavated dry sand amount of each division by multiplying the excavation time of the division; and (d) calculating the standard deviation for each standard excavation distance from the calculated value of the second calculation step. a third calculation step; (e) a setting step of setting a control limit for the subsequent standard excavation distance in a setting device according to the calculated value of the standard deviation; and (f) a setting step in which the calculated value of the second calculation step is the control limit. It is within. The present invention is characterized by comprising a monitoring step of monitoring whether or not.

この発明を図示の実施例を参照して以下に説明する。The invention will be explained below with reference to illustrated embodiments.

第1図において、1,2はそれぞれ泥水式シールド掘削
機(図示せず)の送水管および排泥管であって、送水管
1および排泥管2のそれぞれにガンマ線密度計3,4と
流量計5,6とを設け、各ガンマ線密度計3,4は変換
増幅器7を介してそれぞれ真比重設定器8,9に接続さ
せ、各流量計5,6は変換増幅器10を介して乗除演算
器1112に接続させる。
In FIG. 1, reference numerals 1 and 2 are a water pipe and a mud drainage pipe of a mud shield excavator (not shown), and gamma ray densitometers 3 and 4 and a flow rate are attached to the water pipe 1 and mud drainage pipe 2, respectively. Each gamma ray density meter 3, 4 is connected to a true specific gravity setting device 8, 9 through a conversion amplifier 7, and each flowmeter 5, 6 is connected to a multiplication/division calculator through a conversion amplifier 10. Connect to 1112.

各演算器11.12は真比重設定器8,9からの信号を
流量計5,6からの信号に乗尊してそれぞれ送水管1お
よび排泥管2内の乾砂量を算出する。
Each computing unit 11, 12 multiplies the signals from the true specific gravity setters 8, 9 by the signals from the flowmeters 5, 6 to calculate the amount of dry sand in the water pipe 1 and the mud removal pipe 2, respectively.

演算器11.12からの各信号を加減演算器13に導き
、引算して実瞬間掘削乾砂量を算出し、その信号を積算
演算器14に導いて基準掘削距離、例えばセグメントの
一リングの長さ即ち90cmの実掘削乾砂量を積算し、
監視盤15に表示する(特開昭50−80638参照)
Each signal from the calculators 11 and 12 is guided to the adder/subtractor 13, and subtracted to calculate the actual instantaneous excavated dry sand amount.The signals are led to the integration calculator 14 to calculate the standard excavation distance, for example, one ring of a segment. Accumulate the actual excavated dry sand amount for the length of 90cm,
Display on the monitoring panel 15 (see Japanese Patent Application Laid-Open No. 50-80638)
.

Sはスイッチである。更にこの発明では、加減演算器1
3からの実瞬間掘削乾砂量の信号を区分演算器16に導
き、分割区分に対する平均瞬間掘削乾砂量を算出し、平
均瞬間掘削乾砂量に分割区分掘削時間を乗算して分割区
分実掘削乾砂量を算出し、その信号を母集団器17に送
る。
S is a switch. Furthermore, in this invention, the addition/subtraction operator 1
The signal of the actual instantaneous excavated dry sand amount from 3 is led to the division calculator 16, and the average instantaneous excavated dry sand amount for the divided divisions is calculated, and the average instantaneous excavated dry sand amount is multiplied by the divided division excavation time to calculate the divided division actual. The amount of excavated dry sand is calculated and the signal is sent to the population device 17.

ここで分割区分とは前述した基準掘削距離を数分の一又
は数十分のーに分割した掘進の長さとする。
Here, the term "division" refers to the length of excavation obtained by dividing the standard excavation distance mentioned above into fractions or tens of minutes.

分割区分掘削時間は分割区分を掘進するのに要した時間
を指す。
Divided section excavation time refers to the time required to excavate a divided section.

区分演算器16で算出した分割区分実掘削乾砂量の信号
は母集団器17に送られ、母集団器17は分割区分実掘
削乾砂量を標本とする母集団の標準偏差を算出する。
The signal of the actual excavated dry sand amount of each divided section calculated by the divided section calculation unit 16 is sent to the population unit 17, and the population device 17 calculates the standard deviation of the population whose sample is the actual excavated dry sand amount of each divided section.

標準偏差は統計学の基本式から算出する。標準偏差の算
出値は次の基準掘削距離に対する管理限界として次の基
準掘削距離の掘削開始前に設定器18に設定し、管理限
界B,Bが監視盤15に表示される。
The standard deviation is calculated using a basic statistical formula. The calculated value of the standard deviation is set in the setting device 18 as a control limit for the next reference excavation distance before the start of excavation for the next reference excavation distance, and the control limits B, B are displayed on the monitoring panel 15.

すなわち、管理限界B,Bは第2図に示すように、実掘
削乾砂量Aが基準掘削距離に対する積算値で表示される
ので、標準偏差の算出過程で算出される母集団の平均値
を積算した値に標準偏差の正負値を順次加算した平行な
直線BBで表示される。
In other words, as shown in Figure 2, the control limits B and B are expressed as the cumulative value of the actual excavated dry sand amount A with respect to the standard excavation distance. It is displayed as a parallel straight line BB obtained by sequentially adding the positive and negative values of the standard deviation to the integrated value.

以上のように基準掘削距離を掘削している際に、後続の
基準掘削距離の管理限界を設定するとともに、現在掘削
中の実掘削乾砂量Aがその直前に設定された管理限界B
,B内に入っているか否かを監視するものである。
As described above, when excavating the standard excavation distance, the control limit for the subsequent standard excavation distance is set, and the actual excavated dry sand amount A currently being excavated is the control limit B set immediately before.
,B.

第2図において実掘削乾砂量Aが増大している部分が数
個所あるが、管理限界B,B内に入っている限りにおい
ては地質が直前の基準掘削距離に関するものとほぼ同様
であって、掘削が正常に行なわれていると判断し、掘削
を続行する。
In Figure 2, there are several areas where the actual excavated dry sand amount A has increased, but as long as it is within the control limits B and B, the geology is almost the same as that related to the previous standard excavation distance. , determines that the excavation is being performed normally, and continues excavation.

また実掘削乾砂量AがC部分のように管理限界B,Hの
外にはみ出した場合、掘削に異常が生じたと判断し、掘
削を中断して次の事項をチェックする。
Furthermore, if the actual excavated dry sand amount A protrudes outside the control limits B and H, as in part C, it is determined that an abnormality has occurred in the excavation, and the excavation is interrupted and the following items are checked.

(イ)各機器類の誤動作の有無 上記(イ)の事項が原因である場合は各機器類を調整し
て掘削を再び開始し、そうでない場合はさらに次の事項
をチェックする。
(b) Is there a malfunction in each equipment? If the cause is the item (a) above, adjust each equipment and start excavation again. If not, check the following items.

(ロ)余掘、路面沈下等の有無 (ハ)地質(密度)の変化の有無 (ニ)逸水量 これらのチェック事項の結果にもとずき、次の5項目に
対する調整をなしつつ掘削を再開する。
(b) Excess excavation, road surface subsidence, etc. (c) Changes in geology (density) (d) Loss of water Based on the results of these checks, excavation should be carried out while adjusting the following five items. resume.

(a)切羽水圧の調整 (b)安定液濃度の調整 (c)ジャッキ速度の調整 (d)送排泥流量の調整 (e)真比重の設定の調整 これらの調整により実掘削乾砂量Aが管理限界B,B内
に戻った時に掘削を開始する。
(a) Adjustment of face water pressure (b) Adjustment of stable liquid concentration (c) Adjustment of jacking speed (d) Adjustment of mud flow rate (e) Adjustment of true specific gravity setting These adjustments will reduce the actual excavated dry sand amount A Excavation will begin when the amount returns to within the control limits B and B.

これらの調整を行っても管理限界B,B内に戻らない時
は地質に大きな変化が生じたものと判断して管理限界の
補正を行ない、基準掘削距離を掘削する。
If it does not return to within control limits B and B even after making these adjustments, it is determined that a major change has occurred in the geology, the control limits are corrected, and the standard excavation distance is excavated.

尚、最初の基準掘削距離に対する管理限界はポーリング
した地質や経験から予想して設定する。
The control limit for the initial standard excavation distance is set based on predictions based on the polled geology and experience.

この発明によれば、既に掘削を終えた直前の基準掘削距
離における分割区分実掘削乾砂量を標本とする母集団の
標準偏差を算出し、この標準偏差に応じて次の基準掘削
距離に対する実掘削乾砂量の管理限界を設定するから、
地質が複雑であって分割区分実掘削乾砂量のばらつきが
大きい場合すなわち標準偏差が大きい場合は、管理限界
の幅が大きくなり、また地質が比較的均一であって分割
区分実掘削乾砂量のばらつきが小さい場合すなわち標準
偏差が小さい場合は管理限界の幅が小さくなり、したが
って掘進に伴う地質変化に応じた管理限界を設定でき、
このような管理限界内に実掘削乾砂量が入っているか否
かを監視することにより、十分好適な掘削管理を達成で
きる。
According to this invention, the standard deviation of a population sampled by the actual excavated dry sand amount of the divided divisions at the standard excavation distance immediately before the completion of excavation is calculated, and the actual excavation distance for the next standard excavation distance is calculated according to this standard deviation. By setting control limits for the amount of dry sand excavated,
If the geology is complex and the variation in the actual excavated dry sand volume for each division is large, that is, if the standard deviation is large, the width of the control limit will be large; When the dispersion of
By monitoring whether the actual excavated dry sand amount is within such control limits, sufficiently suitable excavation management can be achieved.

【図面の簡単な説明】[Brief explanation of drawings]

第1図はこの発明の方法の一実施例のためのブロック図
、第2図は監視盤の正面図である。 1……送水管、2……排泥管、3,4……ガンマ線密度
計、5,6……流量計、14……積算演算器、15……
監視盤、16……区分演算器、17……母集団器、18
……設定器、A……実掘削乾砂量、B,B……管理限界
FIG. 1 is a block diagram for one embodiment of the method of the present invention, and FIG. 2 is a front view of a monitoring panel. 1... Water pipe, 2... Sludge drain pipe, 3, 4... Gamma ray density meter, 5, 6... Flow meter, 14... Integration calculator, 15...
Monitoring panel, 16...Division calculator, 17...Population device, 18
... Setting device, A ... Actual excavated dry sand amount, B, B ... Control limit.

Claims (1)

【特許請求の範囲】 1 各基準掘削距離毎に掘削する泥水式シールド掘削工
法において、 (a)実瞬間掘削乾砂量を測定する測定工程と(b)前
記実瞬間掘削乾砂量の測定値を区分演算器に導き各基準
掘削距離を複数に分割してなる各分割区分ごとの平均瞬
間掘削乾砂量を算出する第1の算出工程と (c)前記第1の算出工程の算出値に各分割区分の掘削
時間を乗算して各分割区分の実掘削乾砂量を算出する第
2の算出工程と (d)前記第2の算出工程の算出値から各基準掘削距離
ごとの標準偏差を算出する第3の算出工程と (e)前記標準偏差の算出値に応じて後続の基準掘削距
離に対する管理限界を設定器に設定する設定工程と (f)前記第2の算出工程の算出値が管理限界内にある
か否かを監視する監視工程と を備えてなることを特徴とする泥水式シールド掘削工法
における乾砂量の監視方法。
[Claims] 1. In the mud shield excavation method in which excavation is performed for each reference excavation distance, (a) a measurement step of measuring the actual instantaneous excavated dry sand amount; and (b) a measured value of the actual instantaneous excavated dry sand amount. a first calculation step of dividing each standard excavation distance into a plurality of sections to calculate the average instantaneous excavated dry sand amount for each division; and (c) calculating the calculated value of the first calculation step. A second calculation step of calculating the actual excavated dry sand amount of each division by multiplying the excavation time of each division, and (d) calculating the standard deviation for each standard excavation distance from the calculated value of the second calculation step. (e) a setting step of setting a control limit for the subsequent standard excavation distance in a setting device according to the calculated value of the standard deviation; and (f) a setting step in which the calculated value of the second calculation step is 1. A method for monitoring the amount of dry sand in a muddy shield excavation method, comprising: a monitoring step for monitoring whether or not the amount is within a control limit.
JP7192277A 1977-06-17 1977-06-17 Method for monitoring dry sand amount in muddy shield drilling method Expired JPS5812437B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7192277A JPS5812437B2 (en) 1977-06-17 1977-06-17 Method for monitoring dry sand amount in muddy shield drilling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7192277A JPS5812437B2 (en) 1977-06-17 1977-06-17 Method for monitoring dry sand amount in muddy shield drilling method

Publications (2)

Publication Number Publication Date
JPS547735A JPS547735A (en) 1979-01-20
JPS5812437B2 true JPS5812437B2 (en) 1983-03-08

Family

ID=13474501

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7192277A Expired JPS5812437B2 (en) 1977-06-17 1977-06-17 Method for monitoring dry sand amount in muddy shield drilling method

Country Status (1)

Country Link
JP (1) JPS5812437B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6287835U (en) * 1985-11-21 1987-06-04

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4648037B2 (en) * 2005-03-04 2011-03-09 鹿島建設株式会社 Digging management method in shield method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6287835U (en) * 1985-11-21 1987-06-04

Also Published As

Publication number Publication date
JPS547735A (en) 1979-01-20

Similar Documents

Publication Publication Date Title
Bertoldi et al. A method for estimating the mean bed load flux in braided rivers
Bousmar et al. Momentum transfer for practical flow computation in compound channels
Maheepala et al. Hydrological data monitoring for urban stormwater drainage systems
US3946605A (en) Apparatus and method of measuring fluctuations of excavated mud amount in a slurry line
Bijankhan et al. Application of the submerged experimental velocity profiles for the sluice gate's stage-discharge relationship
CN115898845A (en) An automatic control system for large-scale two-fluid grouting
Shirley et al. A sediment yield equation from an erosion simulation model
JPS5812437B2 (en) Method for monitoring dry sand amount in muddy shield drilling method
Askew Variation in lag time for natural catchments
Savenije Determination of estuary parameters on basis of Lagrangian analysis
CN116295677A (en) Method for automatically measuring flow of large section of high sediment river
Gensen et al. Improving rating curve accuracy by incorporating water balance closure at river bifurcations
Srinivasan et al. Evaluation of runoff and erosion loss in micro-basins utilizing the hydrodynamic model WESP
JPS5822633B2 (en) Excavation management method and excavation management device for muddy water shield excavator
JPS5880094A (en) Face stable control of shield drilling machine
Clemmens Evaluating infiltration for border irrigation models
JPS6145040B2 (en)
US20030236639A1 (en) Sewer flow analysis method
JPH08286729A (en) Drainage pump operation support system
Parsons et al. A miniature flume for sampling interrill overland flow
JPH06257137A (en) Water level control method of stable liquid for underground continuous wall construction using atmospheric pressure sensor
JPH02278141A (en) Apparatus for measuring amount of excavated soil and excavation method
SU451007A1 (en) The method of controlling the process of preparation of the waste
JPS5831062Y2 (en) Pipe blockage detection device
JPS6057215A (en) Slurry quantity measuring device