Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPS5822605B2 - Underground continuous wall construction method - Google Patents
[go: Go Back, main page]

JPS5822605B2 - Underground continuous wall construction method - Google Patents

Underground continuous wall construction method

Info

Publication number
JPS5822605B2
JPS5822605B2 JP52110183A JP11018377A JPS5822605B2 JP S5822605 B2 JPS5822605 B2 JP S5822605B2 JP 52110183 A JP52110183 A JP 52110183A JP 11018377 A JP11018377 A JP 11018377A JP S5822605 B2 JPS5822605 B2 JP S5822605B2
Authority
JP
Japan
Prior art keywords
steel pipe
joint
trench
reinforcing bar
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP52110183A
Other languages
Japanese (ja)
Other versions
JPS5444308A (en
Inventor
菊池正光
吉田昌和
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP52110183A priority Critical patent/JPS5822605B2/en
Publication of JPS5444308A publication Critical patent/JPS5444308A/en
Publication of JPS5822605B2 publication Critical patent/JPS5822605B2/en
Expired legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【発明の詳細な説明】 この発明は新規な地下連続壁工法の提供に係わる。[Detailed description of the invention] This invention relates to the provision of a new underground continuous wall construction method.

地下連続壁の面内縦継手方法としては、従来より例えば
、昭和50年9月1日付発行に係わる、「地下連続壁工
法設計施工・・ンドブツク社団法人日本建設機械化協会
編技報堂」に於ける第9章の「施工」(95継手工)の
欄に記述される如(、インターロッキングパイプ方式、
ホゾ式、仕切鉄板方式、プレキャストコンクリート方式
、T形ブロックジヨイント方式、場所打杭組合せ方式、
形鋼ビームジョイナ方式、はつり出し接続方式等の各種
方式が開発されてはいるが、鉄筋篭が各エレメントごと
に接続されてなく、継手強度が一応満足出来るものにあ
ってもインターロッキングパイプの建て込み、縁切り引
き抜き、単なる引抜き、コンクリートブロックのボルト
継ぎ等の工程を要していて決して施工性はよ(なく、さ
らに鉄筋篭が各エレメントごとに接続されて一体となり
構造体として理想的であるものにあってはブロックジヨ
イントの引き抜き、複雑な鉄筋篭の組立、トレンチ掘削
後におけるはつり並びに鉄筋組立てと型枠組立て、ジヨ
イントボックスの建込みと引き抜き等の施工性の悪い工
程が多く、工期、コスト面に大きな影響を与えている。
As for the in-plane longitudinal joint method for underground continuous walls, for example, there has been a method published on September 1, 1975 in "Design and Construction of Underground Continuous Wall Construction Methods...Ndobuk Incorporated Association, Japan Construction Mechanization Association, Gihodo," Vol. As described in the "Construction" (95 joint work) column of Chapter 9 (interlocking pipe method,
Tenon method, partition steel plate method, precast concrete method, T-shaped block joint method, cast-in-place pile combination method,
Various methods have been developed, such as the shaped steel beam joiner method and the flanged connection method, but the reinforcing bar cages are not connected to each element, and even if the strength of the joints is satisfactory, it is difficult to construct interlocking pipes. It requires processes such as cutting in, edge cutting and pulling out, simple pulling out, and joining concrete blocks with bolts, so it is not easy to construct.In addition, the reinforcing bar cages are connected to each element, making it an ideal structure. There are many processes that are difficult to construct, such as pulling out block joints, assembling complicated reinforcing bar cages, chiseling and assembling reinforcing bars and formwork after excavating the trench, and erecting and pulling out joint boxes, etc. This has a major impact on costs.

本発明は叙上の事情に鑑みなされたもので、鉄筋篭が各
エレメントごとに接続されて一体となり構造体として理
想的なものをば、上述の全ての工程を不要としてなし得
るところの施工性の極めて良好な面内縦継手方法を提供
させんとするもので、その要旨とするところはトレンチ
掘削後の継手部に構造的に継手強度を満足するループ鉄
筋、打ち抜き鉄板等の部材をその側面に配設したところ
のロッキングパイプに相当する円形鋼管若しくは角形鋼
管を掘削底以深にまで埋設し、これを必要によっては砂
利などで押え、鉄筋篭ωり込み後、核鋼管内を含むコン
クリート打設を行なうことにある。
The present invention has been made in view of the above circumstances, and if the reinforcing bar cage is connected to each element and is integrated into an ideal structure, it can be performed without all the above-mentioned steps. The aim is to provide an extremely good in-plane vertical joint method, and the gist of this is that after excavating a trench, members such as loop reinforcing bars or punched iron plates that satisfy the structural strength of the joint are attached to the side surface of the joint. A circular steel pipe or a square steel pipe corresponding to the locking pipe installed in the hole is buried to a depth below the excavation bottom, and if necessary, it is pressed down with gravel, etc., and after the reinforcing bar cage is inserted, concrete is poured including the inside of the core steel pipe. The goal is to do the following.

以下、本発明の詳細を図にもとづいて説明する。Hereinafter, details of the present invention will be explained based on the drawings.

図中1は本発明が使用する上述ロッキングパイプに相当
するトレンチ幅と同等の外径を有する円形鋼管若しくは
角形鋼管で、その継手方向側面には鉄筋篭とラップして
構造的に継手強度を満足するところのループ鉄筋、引き
抜き鉄板等2・・・が配設されている。
1 in the figure is a circular steel pipe or a square steel pipe having an outer diameter equivalent to the trench width corresponding to the above-mentioned locking pipe used in the present invention, and the side surface in the direction of the joint is wrapped with a reinforcing bar cage to structurally satisfy the strength of the joint. Loop reinforcing bars, drawn iron plates, etc. 2... are provided.

円形鋼管による実施態様は第1図から第4図までに、ま
た角形鋼管による実施要領は第5図に示す。
An embodiment using a circular steel pipe is shown in FIGS. 1 to 4, and an embodiment using a square steel pipe is shown in FIG. 5.

本発明工法は先ず、トレンチ3の掘削完了後、該鋼管1
をトレンチ3の両端継手部コーナーに建て込むが、これ
は掘削域以降のアンカー効果が生じる深度りにまで埋設
する。
In the construction method of the present invention, first, after completing the excavation of the trench 3, the steel pipe 1 is
are buried at the corners of the joints at both ends of the trench 3, to a depth below the excavation area where an anchor effect occurs.

次いで、念のため砂利4等の充填による押えをするをよ
しとするが、これはアンカー効果が充分であって、打設
コンクリートによる側圧に充分耐え得る場合には省略し
てもよい(第1図)。
Next, as a precaution, it is recommended to hold the concrete in place by filling it with gravel 4, etc., but this may be omitted if the anchoring effect is sufficient and the concrete can sufficiently withstand the lateral pressure (see Figure 1). ).

次に、鉄筋節5をその両端を該ループ鉄筋、打ち抜き鉄
板等2とラップさせた態様にトレンチ3内に墨り込み、
コンクリート6の打設を行なう(第2図)。
Next, the reinforcing bar nodes 5 are inked into the trench 3 in such a manner that both ends thereof are wrapped with the loop reinforcing bars, punched iron plates, etc. 2,
Concrete 6 is placed (Figure 2).

この際、トレンチ3内と共に鋼管1内をも一緒にコンク
リート打設を施こしてしまう。
At this time, concrete is placed inside the trench 3 and the steel pipe 1 at the same time.

つまり、鋼管1を埋殺してエレメントの一部としてしま
う。
In other words, the steel pipe 1 is buried and becomes part of the element.

これには、1エレメントが完成する。This completes one element.

後は、隣接エレメントを同じ要領にて完成させテ行はハ
よく第3図は隣接エレメントのトレンチ3′掘削完了態
様を示し、第4図は鉄筋節5′の墨込み、コンクリート
σの打設を行って隣接エレメントとの一体接続が完成し
た態様を示す。
After that, the adjacent element was completed in the same way, and the process was complete. Figure 3 shows the completion of trench 3' excavation of the adjacent element, and Figure 4 shows the inking of reinforcing bar joint 5' and the pouring of concrete σ. This figure shows a state in which integral connection with adjacent elements is completed.

かかる本発明工法によるならば、ロッキングパイプに相
当する鋼管1はトレンチ掘削底に対して単なる載置にて
建て込まれるものではなく、掘削域以降の所定深度にま
で埋設されるものであるから下部からのコンクリートの
まわり込みの心配が皆無である利点を有すると共に埋殺
しのジヨイントとなり、ロッキングパイプにおけるが如
き縁切り引き抜き工程等が一切熱(てよく、施工性に極
めて有利である。
According to the construction method of the present invention, the steel pipe 1 corresponding to the locking pipe is not simply placed on the bottom of the trench excavation, but is buried to a predetermined depth below the excavation area. It has the advantage that there is no need to worry about the concrete going around it, and it also becomes a buried joint, and the process of cutting and pulling out edges, such as in rocking pipes, does not require any heat (heating), which is extremely advantageous for workability.

【図面の簡単な説明】[Brief explanation of drawings]

図は本発明の実施態様を示し、第1図Aは初期工程の平
面図、B図は縦断面図、第2図から第4図は順次、次工
程を示す平面図、第5図は他の実施要領を示す平面図で
ある。 符号の簡単な説明、1・・・円形若しくは角形鋼管、2
・・・ループ鉄筋1.打ち抜き鉄板、3,3′・・・ト
レンチ、4・・・砂利、5,5′・・・鉄筋節、6.ぎ
・・・打設コンクリート。
The figures show embodiments of the present invention, and FIG. 1A is a plan view of an initial process, FIG. FIG. Brief explanation of symbols: 1...Circular or square steel pipe, 2
...Loop reinforcing bar 1. Punched iron plate, 3, 3'... trench, 4... gravel, 5, 5'... reinforcing bar joint, 6. Gi...Pouring concrete.

Claims (1)

【特許請求の範囲】[Claims] 1 トレンチ掘削後の継手部コーナーに、構造的に継手
強度を満足するループ鉄筋、打ち抜き鉄板等の部材をそ
の継手方向側面に配設したところのトレンチ幅と同等の
外径を有する円形鋼管若しくは角形鋼管を掘削底以深の
アンカー効果の生じる深度にまで埋設してから、トレン
チ内に鉄筋篭をその両端を該ループ鉄筋、打ち抜き鉄板
とラップさせた態様にめり込み、次いで、コンクリート
打設を該鉄筋籠部と共に該鋼管内にも一緒に施こして1
エレメントを完成させ、以下、この手順を隣接エレメン
トに繰返して行なうことを特徴とする地下連続壁工法。
1 After excavating the trench, at the corner of the joint, members such as loop reinforcing bars or punched iron plates that satisfy the structural strength of the joint are placed on the side surface in the direction of the joint, and a circular steel pipe or square steel pipe with an outer diameter equivalent to the width of the trench is installed. After burying the steel pipe to a depth below the excavation bottom where an anchor effect occurs, a reinforcing bar cage is sunk into the trench with both ends wrapped around the loop reinforcing bars and punched steel plates, and then concrete is poured into the reinforcing bar cage. 1 and also inside the steel pipe.
An underground continuous wall construction method characterized by completing an element and then repeating this procedure for adjacent elements.
JP52110183A 1977-09-13 1977-09-13 Underground continuous wall construction method Expired JPS5822605B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP52110183A JPS5822605B2 (en) 1977-09-13 1977-09-13 Underground continuous wall construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP52110183A JPS5822605B2 (en) 1977-09-13 1977-09-13 Underground continuous wall construction method

Publications (2)

Publication Number Publication Date
JPS5444308A JPS5444308A (en) 1979-04-07
JPS5822605B2 true JPS5822605B2 (en) 1983-05-10

Family

ID=14529139

Family Applications (1)

Application Number Title Priority Date Filing Date
JP52110183A Expired JPS5822605B2 (en) 1977-09-13 1977-09-13 Underground continuous wall construction method

Country Status (1)

Country Link
JP (1) JPS5822605B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61100434A (en) * 1984-10-23 1986-05-19 Sekisui Plastics Co Ltd Method of molding container

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4940965A (en) * 1972-08-23 1974-04-17

Also Published As

Publication number Publication date
JPS5444308A (en) 1979-04-07

Similar Documents

Publication Publication Date Title
JP2003027462A (en) Construction method of underground continuous wall, and construction method of underground structure
JPS5822605B2 (en) Underground continuous wall construction method
JPS61122320A (en) Method of coupling continuous underground wall with underground structure
JPH0721196B2 (en) Reverse construction method of underground structure
KR101219451B1 (en) Concrete structure and construction method for the same, constructing method of underground wall as a retaining structural wall used in the same
JPH041811B2 (en)
JPH0220271Y2 (en)
JPS5853321Y2 (en) Element for mountain retainer
JPH01315520A (en) Construction method for underground external walls of buildings
JPS6248011B2 (en)
JP3000495B2 (en) Large-scale, deep steel continuous basement wall and method of constructing the same
JPS5841227Y2 (en) Element for mountain retainer
JPS6135359B2 (en)
JP2565452B2 (en) Construction method of self-supporting retaining wall
JP3171716B2 (en) Foundation construction method on inclined surface
JP2689743B2 (en) How to build an underground structure
JPH09209370A (en) Method for constructing foundation of building
JPS61257529A (en) Underground continuous wall construction work
JPS6029292Y2 (en) Semi-prefabricated conduit for underground cable pipes
JPH0598633A (en) Steel underground continuous wall and construction method thereof
JPS6340521Y2 (en)
JPS6315382Y2 (en)
JPS6313487B2 (en)
JPS6245369B2 (en)
JPH0315624Y2 (en)