Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPS5833341B2 - Dome construction method - Google Patents
[go: Go Back, main page]

JPS5833341B2 - Dome construction method - Google Patents

Dome construction method

Info

Publication number
JPS5833341B2
JPS5833341B2 JP9492579A JP9492579A JPS5833341B2 JP S5833341 B2 JPS5833341 B2 JP S5833341B2 JP 9492579 A JP9492579 A JP 9492579A JP 9492579 A JP9492579 A JP 9492579A JP S5833341 B2 JPS5833341 B2 JP S5833341B2
Authority
JP
Japan
Prior art keywords
dome
periphery
assembled
ground
present
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP9492579A
Other languages
Japanese (ja)
Other versions
JPS5620251A (en
Inventor
衛 川口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP9492579A priority Critical patent/JPS5833341B2/en
Publication of JPS5620251A publication Critical patent/JPS5620251A/en
Publication of JPS5833341B2 publication Critical patent/JPS5833341B2/en
Expired legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】 本発明は、野球場、体育館、集会場、その他広大な空間
に適用されるドーム屋根の構築法の改良に係るものであ
る。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to an improvement in a method of constructing a dome roof that is applied to baseball stadiums, gymnasiums, assembly halls, and other large spaces.

従来この種の屋根構造の構築法として最も一般的なもの
は、屋根直下の全面積に亘って仮設足場を設けてその上
で屋根構造を組立てる方法である。
Conventionally, the most common method for constructing this type of roof structure is to provide temporary scaffolding over the entire area directly under the roof, and then assemble the roof structure thereon.

しかしながらこの方法は仮設足場に多大の費用を要する
のみならず、屋根の組立が高所作業となるため、施工精
度、作業安全性、能率の点からみて望ましい方法とはい
い難い。
However, this method not only requires a large amount of money for temporary scaffolding, but also requires work at a high place to assemble the roof, so it cannot be said to be a desirable method in terms of construction accuracy, work safety, and efficiency.

前記全面足場の代りに、ドーム直下の数個所に仮設鉄塔
を配設し、地上で部分的に組んだドーム部材のブロック
をこれら仮設鉄塔の頂部に支持させて組上げていく方法
も採用されているが、この方法も程度の差こそあれ、前
記の方法と同じような短所を有している。
Instead of the full-scale scaffolding described above, a method has also been adopted in which temporary steel towers are placed at several locations directly beneath the dome, and blocks of dome components that have been partially assembled on the ground are supported and assembled on the tops of these temporary steel towers. However, this method also has the same disadvantages as the above-mentioned method, although there are differences in degree.

本発明はこのような実情に鑑みて提案されたものであっ
て、周辺を下部構造で支持された球面若しくはこれに類
似の多面体形状を有するドーム骨組構造の構築に際して
、ドーム周辺部近傍における同一平面上の円周方向部材
の取付を保留し、且つ節点にヒンジを介装してなるドー
ム周辺部を前記下部構造上に設置するとともに、ドーム
中央部をその配設位置直下における地上に近いレベルで
組立てて前記ドーム周辺部と接合し、しかるのちドーム
全体を扛上して前記ドーム各部が所定位置に達したのち
、前記保留円周方向部材を追加接合することを特徴とす
るドーム構築法に係るもので、その目的とする処はドー
ム部材の大部分を地上に近いレベルで組立てることによ
って、仮設材の大幅な節減を図るとともに、施工精度、
作業安全性のみならず作業能率をも向上しうる、改良さ
れたドーム構築法を供する点にある。
The present invention has been proposed in view of the above-mentioned circumstances. When constructing a dome frame structure having a spherical or similar polyhedral shape whose periphery is supported by a substructure, it is possible to The peripheral part of the dome, which is made by suspending the installation of the upper circumferential member and having hinges interposed at the nodes, is installed on the lower structure, and the central part of the dome is placed at a level close to the ground directly below the installation position. The dome construction method is characterized in that the dome is assembled and joined to the peripheral part of the dome, and then the entire dome is lifted up and after each part of the dome reaches a predetermined position, the retaining circumferential member is additionally joined. The purpose of this is to assemble most of the dome components at a level close to ground level, which will significantly reduce the amount of temporary construction materials and improve construction accuracy.
The object of the present invention is to provide an improved dome construction method that can improve not only work safety but also work efficiency.

以下本発明を実施例について説明する。The present invention will be described below with reference to Examples.

Aはドーム中央部、Bは周辺下部構造Cで支持されたド
ーム周辺部で、第1図に示すように前記両部A、Bの骨
組は地上に近いレベルで組立て、連結される。
A is the central part of the dome, and B is the peripheral part of the dome supported by the peripheral substructure C. As shown in FIG. 1, the frameworks of both parts A and B are assembled and connected at a level close to the ground.

この際ドーム周辺部Bにおける骨組の組立時、周辺近傍
における同一平面内の円周方向部材1の取付を保留する
At this time, when assembling the frame around the dome periphery B, the attachment of the circumferential member 1 in the same plane near the periphery is suspended.

かくして構成されたドーム骨組は幾何学的不安定架構と
なる。
The dome frame constructed in this manner becomes a geometrically unstable frame.

換言すればドーム部材の寸法を何等変えることなく、ド
ームの幾何学的形状を、第1図、第2図或いは第3図に
示す如く自由に変化せしめることかできる。
In other words, the geometric shape of the dome can be freely changed as shown in FIGS. 1, 2, or 3 without changing the dimensions of the dome member.

同時にドームの前記したような幾何学的不安定架構によ
る運動が可能になるように、ドーム周辺部Bにおける節
点2,3.4に第5図及び第6図に一例を示す如き部材
の相対的回転を許容するヒンジを介装する。
At the same time, in order to enable movement of the dome due to the above-mentioned geometrically unstable frame, relative members such as those shown in FIGS. 5 and 6 are attached to the nodes 2, 3. A hinge is provided to allow rotation.

従って図示の実施例のドームは組立の段階において、第
1図に示す如くドーム周辺部Bの最外周縁の節点4を下
部構造C上の所定位置に支持したまま、且つドーム部材
の寸法を変えることなく、ドーム中央部Aをその正規の
配設位置直下の地上に近いレベルで組立てることができ
る。
Therefore, during the assembly stage of the dome of the illustrated embodiment, the outermost node 4 of the dome periphery B remains supported at a predetermined position on the substructure C, as shown in FIG. 1, and the dimensions of the dome member are changed. The dome central part A can be assembled at a level close to the ground directly below its regular installation position without any trouble.

この場合、第3図と比較すれば明らかなように、ドーム
の最終形状を最初から直接構築する場合に比して仮設足
場を大幅に節減することができる。
In this case, as is clear from a comparison with FIG. 3, the need for temporary scaffolding can be significantly reduced compared to the case where the final shape of the dome is constructed directly from scratch.

また作業が地上に近いレベルで行なわれるため、施工精
度、作業安全性及び能率が向上されるものである。
Furthermore, since the work is carried out at a level close to the ground level, construction accuracy, work safety, and efficiency are improved.

前記のように地上に近いレベルで組立てられたドームを
扛上して、第2図に示す状態を経て第3図に示す最終の
形状をとるようにし、この段階で前に保留されていた円
周方向部材1を所定位置に追加接合して安定したドーム
骨組を完成するものであって、本実施例においては前記
ドームの扛上方法として空気圧力式を採用している。
The dome assembled at a level close to the ground as described above is lifted up, passes through the state shown in Fig. 2, and assumes the final shape shown in Fig. 3, and at this stage the previously reserved circle is lifted up. A stable dome framework is completed by additionally joining the circumferential members 1 at predetermined positions, and in this embodiment, a pneumatic method is adopted as the method for raising the dome.

即ち第2図に示すようにドーム内の空間5に、送風機(
図示せず)を使用して空気を送入し、ドーム内の空気圧
を外気圧より上昇させ、この圧力差によってドームを上
昇せしめる。
That is, as shown in Fig. 2, a blower (
(not shown) is used to introduce air to raise the air pressure inside the dome above the outside air pressure, and this pressure difference causes the dome to rise.

この場合、ドームの上昇に必要な圧力差を確保するため
に、ドーム表面に相当程度の気密性が要求されるもので
あるが、この中、ドーム中央部A、及び節点2゜3.2
を頂点とする三角パネル、並に節点4,3゜4を頂点と
する三角パネルはドームの上昇運動中も形状を変えない
ので、これらの部分は空気送入以前に屋根仕上を完了さ
せることによって特別に気密対策を必要としない。
In this case, a considerable degree of airtightness is required on the dome surface in order to secure the pressure difference necessary for the dome to rise.
The triangular panels with vertices at , as well as the triangular panels with nodes 4 and 3°4 as vertices, do not change shape during the upward movement of the dome, so these parts can be removed by completing the roof finishing before air is introduced. No special airtight measures are required.

しかしながら節点2゜3.4.3を頂点とする四辺形は
、ドームの上昇運動中にその形状を大きく変えるので、
この部分には仮設のキャンパス皮膜を被覆して気密を図
っている。
However, the quadrilateral whose apex is node 2°3.4.3 changes its shape significantly during the upward movement of the dome, so
This area is covered with a temporary canvas membrane to ensure airtightness.

なお前記ドームの扛上時、節点2と地盤との間に調整用
ケーブル6を数本対称位置に張設し、同ケーブル6をウ
ィンチで調整することによってドームの上昇速度と、上
昇中の形態を制御しうるものである。
When lifting the dome, several adjustment cables 6 are stretched in symmetrical positions between the node 2 and the ground, and by adjusting the cables 6 with a winch, the speed of the dome's rise and its shape during the rise can be adjusted. can be controlled.

このように上昇中のドームの運動の制御が容易なことも
本発明の特徴の一つである。
It is also one of the features of the present invention that the movement of the dome during rising can be easily controlled in this way.

第7図及び第8図は本発明の他の実施例を示し、前記実
施例におけるドーム周辺部Bを内周部B1と外周部B2
とに2分して、同各部B1.B2における各同一平面内
の円周方向部材1,1の取付を保留する他は前記実施例
と同一工程でドームが組立てられるものである。
7 and 8 show another embodiment of the present invention, in which the dome periphery B in the embodiment is divided into an inner periphery B1 and an outer periphery B2.
Divide into two parts, and each part B1. The dome is assembled in the same steps as in the previous embodiment except that the mounting of the circumferential members 1, 1 in the same plane at B2 is suspended.

かくしてドーム中央部の組立作業を前記実施例における
よりも更に地上に近いレベルで行なわれるようにし、こ
れによって仮設足場を更に節減し、工期を大幅に縮減し
うるものである。
In this way, the assembly work of the central part of the dome can be carried out at a level closer to the ground than in the previous embodiment, thereby further reducing the need for temporary scaffolding and significantly shortening the construction period.

なお図中前記実施例と均等部分には同一符号が符されて
いる。
In the drawings, parts equivalent to those of the above embodiment are designated by the same reference numerals.

第9図及び第10図は本発明をシュベドラー型ドームの
構築に適用した場合の実施例を示し、ドーム組立時にお
いて、ドーム周辺部Bにおける節点3を結ぶ円周方向部
材の中、1個置きの部材1の取付を保留し、また地上近
くのレベルで形成されたドームの扛上方法として、従来
のリフトアップ工法におけるのと同様の方法を採用して
いる。
9 and 10 show an embodiment in which the present invention is applied to the construction of a Shvedler type dome. When assembling the dome, every one of the circumferential members connecting the nodes 3 in the dome periphery B is The installation of the member 1 is suspended, and the same method as in the conventional lift-up method is adopted as a method for lifting the dome formed at a level near the ground.

即ち対称位置に配設された仮設鉄塔7の頂部にセンタホ
ール型ジヤツキを主機とする扛重装置8を設置し、吊り
材9によって節点2を吊り上げてドームを上昇せしめる
方法を用いている。
That is, a method is used in which a hoisting device 8 whose main engine is a center hole jack is installed at the top of a temporary steel tower 7 arranged at a symmetrical position, and the node 2 is hoisted up by a hanging member 9 to raise the dome.

図中前記各実施例と均等部分には同一符号が符されてい
る。
In the drawings, parts equivalent to those of the above embodiments are designated by the same reference numerals.

なお前記実施例はドームを支持する下部構造Cが基礎の
場合を示しているが、下部構造Cは柱列体、或いは壁体
であってもよく、また競技場の観覧席構造体のようなも
のであってもよい。
Although the above embodiment shows the case where the substructure C supporting the dome is the foundation, the substructure C may be a series of pillars or a wall, and may also be a structure such as a stadium seating structure. It may be something.

またドーム周辺部の節点4は必らずしも水平面上にある
必要はなく、斜面上にあってもよい。
Further, the nodes 4 around the dome do not necessarily have to be on a horizontal plane, but may be on a slope.

本鼻明においては前記したように、ドーム周辺部近傍に
おける同一平面上の円周方向部材の取付を保留するとと
もに、節点にヒンジを介装することによって得られた、
同ドーム周辺部と、その配設位置直下において組立てら
れ前記ドーム周辺部に連結されるドーム中央部とよりな
るドーム全体の幾何学的不安定架橋を利用して、ドーム
全体を地上近くのレベルで組立てこれを扛上しうるもの
である。
In this invention, as mentioned above, the mounting of the circumferential members on the same plane near the periphery of the dome is suspended, and the hinges are interposed at the nodes.
Utilizing the geometrically unstable bridge of the entire dome, which consists of the peripheral part of the dome and the central part of the dome that is assembled directly under the dome and connected to the peripheral part of the dome, the entire dome can be built at a level near the ground. Once assembled, it can be lifted up.

また同ドームを所定位置まで扛上したのち、前記保留円
周方向部材を追加接合してドームを完成するようにした
ので、上昇後のドームを安定させるための追加作業が最
小限で済む。
Further, after the dome is raised to a predetermined position, the retaining circumferential member is additionally joined to complete the dome, so that additional work for stabilizing the dome after being raised can be minimized.

更にドームの扛上時、前記したように、ドーム中央部と
ドーム周辺部との節点と地盤との間に調整用ケープルを
介装して同ケーブルを調整することによって、ドームの
上昇運動の制御が容易に行なわれるものである。
Furthermore, when the dome is raised, as mentioned above, the ascending movement of the dome can be controlled by interposing an adjustment cable between the node between the center of the dome and the periphery of the dome and the ground, and adjusting the cable. is easily performed.

このように本発明の方法は従来のドーム構築法に比して
経済性、施工精度及び作業安全性並に作業能率の点にお
いて多くの利点を有するものである。
As described above, the method of the present invention has many advantages over conventional dome construction methods in terms of economy, construction accuracy, work safety, and work efficiency.

以上本発明を実施例について説明したが、本発明は勿論
このような実施例にだけ局限されるものではなく、本発
明の精神を逸脱しない範囲内で種々の設計の改変を施し
うるものである。
Although the present invention has been described above with reference to embodiments, the present invention is, of course, not limited to such embodiments, and can be modified in various ways without departing from the spirit of the present invention. .

【図面の簡単な説明】[Brief explanation of the drawing]

第1図乃至第3図は本発明に係るドーム構築法の一実施
例の工程を示す縦断面図、第4図は第3図の平面図、第
5図及び第6図は夫々周辺ドーム部のヒンジ部分を示す
縦断面国益に平面図、第7図及び第8図は夫々本発明の
方法の他の実施例の実施状況を示す縦断面国益に平面図
、第9図及び第10図は夫々本発明の方法の更に他の実
施例の実施状況を示す縦断面国益に平面図である。 A・・・・・・ドーム中央部、B・・・・・・ドーム周
辺部、1・・・・・・円周方向部材、2,3.4・・・
・・・節点。
1 to 3 are longitudinal cross-sectional views showing the steps of an embodiment of the dome construction method according to the present invention, FIG. 4 is a plan view of FIG. 3, and FIGS. 5 and 6 respectively show the peripheral dome portion. FIGS. 7 and 8 are plan views in longitudinal section showing the hinge portion of the invention, FIGS. 7 and 8 are plan views in longitudinal section showing the state of implementation of other embodiments of the method of the present invention, and FIGS. 9 and 10 are FIG. 6 is a longitudinal sectional view and a plan view showing the implementation status of further embodiments of the method of the present invention, respectively; A... Central part of the dome, B... Peripheral part of the dome, 1... Circumferential member, 2, 3.4...
···node.

Claims (1)

【特許請求の範囲】[Claims] 1 周辺を下部構造で支持された球面若しくはこれに類
似の多面体形状を有するドーム骨組構造の構築に際して
、ドーム周辺部近傍における同一平面上の円周方向部材
の取付を保留し、且つ節点にヒンジを介装してなるドー
ム周辺部を前記下部構造上に設置するとともに、ドーム
中央部をその配設位置直下における地上に近いレベルで
組立てて前記ドーム周辺部と接合し、しかるのちドーム
全体を扛上して前記ドーム各部が所定位置に達したのち
、前記保留円周方向部材を追加接合することを特徴とす
るドーム構築法。
1. When constructing a dome frame structure having a spherical or similar polyhedral shape whose periphery is supported by a substructure, the installation of circumferential members on the same plane near the periphery of the dome is suspended, and hinges are not installed at the nodes. The surrounding part of the dome formed by the interposition is installed on the lower structure, and the central part of the dome is assembled at a level close to the ground directly below the installation position and joined to the surrounding part of the dome, and then the entire dome is lifted up. After each part of the dome reaches a predetermined position, the retaining circumferential member is additionally joined.
JP9492579A 1979-07-27 1979-07-27 Dome construction method Expired JPS5833341B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9492579A JPS5833341B2 (en) 1979-07-27 1979-07-27 Dome construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9492579A JPS5833341B2 (en) 1979-07-27 1979-07-27 Dome construction method

Publications (2)

Publication Number Publication Date
JPS5620251A JPS5620251A (en) 1981-02-25
JPS5833341B2 true JPS5833341B2 (en) 1983-07-19

Family

ID=14123539

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9492579A Expired JPS5833341B2 (en) 1979-07-27 1979-07-27 Dome construction method

Country Status (1)

Country Link
JP (1) JPS5833341B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002129655A (en) * 2000-10-26 2002-05-09 Takenaka Komuten Co Ltd Construction method of roof frame

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS587735U (en) * 1981-07-09 1983-01-19 旭技研株式会社 Processing basket vertical movement device in surface treatment equipment
JP7062829B1 (en) * 2021-11-26 2022-05-06 犬飼 八重子 Vertical stand used to construct a dome-shaped member network with straight members

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002129655A (en) * 2000-10-26 2002-05-09 Takenaka Komuten Co Ltd Construction method of roof frame

Also Published As

Publication number Publication date
JPS5620251A (en) 1981-02-25

Similar Documents

Publication Publication Date Title
US5067288A (en) Dome structure
US5010695A (en) Cable-stay roof for stadium or arena and method of construction of same
JPH051446A (en) Roof structure formed by combination of triangle shapes
JPS60238556A (en) Roof structure and building of roof
JP2981061B2 (en) How to build a cable dome roof
JPS5833341B2 (en) Dome construction method
CN115199051B (en) Construction method of large span canopy for football field
CN117166773B (en) Traction lifting installation method of suspension ball structure of stay cable
US4651496A (en) Method of erecting a cable stay roof over an existing structure
JP2579715B2 (en) External tower crane
JP3690435B2 (en) Dome roof structure and construction method thereof
JPH09111943A (en) Building with dome roof
JPH0539637A (en) Construction method for domed roof and heavy hoist therefor
JP3328790B2 (en) High-rise building assembly method
JPH0718743A (en) Construction method for large span domelike roof
JPH10184015A (en) Method for constructing roof dome
JP2004162418A (en) Construction method of frame between girders
JP3664815B2 (en) Roof dome construction method
Schober et al. The Sky Reflector‐Net for the Fulton Center, New York
JP2996870B2 (en) Roof structure frame method
JPH0431524A (en) Construction method of dome frame
JP2785112B2 (en) All-weather construction method for high-rise buildings
JPH0460038A (en) Constructing method of large span dome roof
JP2577321B2 (en) Construction method of above-ground flat bottom cylindrical storage tank
JPH08184101A (en) Building construction method