JPS5840629B2 - Assembly method for power transmission towers - Google Patents
Assembly method for power transmission towersInfo
- Publication number
- JPS5840629B2 JPS5840629B2 JP8612979A JP8612979A JPS5840629B2 JP S5840629 B2 JPS5840629 B2 JP S5840629B2 JP 8612979 A JP8612979 A JP 8612979A JP 8612979 A JP8612979 A JP 8612979A JP S5840629 B2 JPS5840629 B2 JP S5840629B2
- Authority
- JP
- Japan
- Prior art keywords
- gate structure
- tower body
- tower
- steel
- jack
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【発明の詳細な説明】
本発明は送電用門形鉄塔、えぼし形鉄塔などの門構部を
有する鉄塔(以下、特殊鉄塔と称す)を組立てる工法に
関する。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a construction method for assembling a steel tower (hereinafter referred to as a special steel tower) having a gate structure, such as a gate-shaped steel tower for power transmission or an eboshi-shaped steel tower.
従来これらの特殊鉄塔を組立てる工法としては、例えば
えぼし形鉄塔に関して、第1図および第2図に示すよう
な工法を採っている。Conventionally, as a construction method for assembling these special steel towers, for example, the construction method shown in FIG. 1 and FIG. 2 has been adopted for elongated steel towers.
第1図に示す工法は、先ずえぼし型鉄塔の下部塔体部1
を組立て、これに2本の台枠3を順次適当な位置に取付
け、その先端に取付けた滑車4により、鉄塔の門構部2
0部材を順次吊上げて下部から順次組立てて行く方法で
、いわゆる2本台棒工法である。The construction method shown in Figure 1 begins with the construction of the lower tower body 1 of an Eboshi-type steel tower.
are assembled, and the two underframes 3 are sequentially attached to this at appropriate positions, and the gate structure 2 of the steel tower is
This is the so-called two-rod construction method, in which the 0 members are lifted one by one and assembled from the bottom.
矢印5は台枠3の支線の方向を示す。第2図に示す工法
は、先ず第1図と同様に鉄塔の下部塔体部1を組立て、
鉄塔の中心に垂直な鉄柱9およびそれより分岐して斜交
する2本の台枠10を設置し、台枠10の先端に取付け
た滑車4により、鉄塔の門構部2の部材を順次吊上げて
下部から順次組立てて行(方法で、鉄柱と金棒を組合せ
た方法である。Arrow 5 indicates the direction of the branch line of the underframe 3. The construction method shown in Figure 2 first assembles the lower tower body part 1 of the steel tower in the same way as in Figure 1,
A vertical steel column 9 and two underframes 10 that branch out from the column and intersect diagonally are installed at the center of the steel tower, and the members of the gate structure 2 of the steel tower are sequentially lifted by a pulley 4 attached to the tip of the underframe 10. This is a method that combines iron pillars and metal rods.
11は、台枠10の支線で鉄柱9の先端を介して矢印の
方向に引張られる。11 is a branch line of the underframe 10 and is pulled in the direction of the arrow through the tip of the steel column 9.
しかし、このような特殊鉄塔が大型化されると、門構部
2の第2図に示すビーム部6から腕金部7にかげての部
材の長大化、重量増のため、細長い鉄柱90強度的な問
題があり、部材をバランスを取りながら吊上げ、組合せ
ることは能力的に不可能に近い。However, when such a special steel tower becomes larger, the length and weight of the members extending from the beam part 6 to the armrest part 7 shown in FIG. Due to this problem, it is almost impossible to lift and assemble the parts while maintaining balance.
本発明は、上述の問題点に鑑み成されたもので、特殊鉄
塔の下部塔体部を延長した形状の仮設架台および昇降ジ
ヤツキを設置することにより、特殊鉄塔が大型化しても
、容易に、安定良く、かつ安全に門構部の組立てを行な
い得る門構部を有する送電用鉄塔の組立工法を提供せん
とするものである。The present invention has been made in view of the above-mentioned problems, and by installing a temporary pedestal in the shape of an extension of the lower body of the special steel tower and a lifting jack, even if the special steel tower becomes large, it can be easily It is an object of the present invention to provide a method for assembling a power transmission tower having a gate structure that allows the gate structure to be assembled stably and safely.
本発明は、門構部を有する送電用鉄塔を組立てる工法に
おいて、
(a) 前記鉄塔の前記門構部より下方の下部塔体部
を組立て、
(b) 前記下部塔体部の上方に、該下部塔体部と類
似構成の仮設架台と、その上面に昇降可能なジヤツキを
設置し、
(c) 前記ジヤツキ上に、前記門構部を構成するビ
ーム部および下端にヒンジ部を有する腕金部を順次延長
して組立てて、前記ジヤツキにて支持し
くd) 別に前記下部塔体部上に、上端にヒンジ部を
有する前記門構部を支える下部支持材を組立てて、前記
下部塔体部にて支持し、
(e)接合すべき前記2個のヒンジ部のずれを前記ジヤ
ツキを操作して修正し、ヒンジ部を接合し、前記鉄塔を
組立てた後、
(f) 前記仮設架台および前記ジヤツキを撤去する
ことを特徴とする送電用鉄塔の組立工法である。The present invention provides a method for assembling a power transmission tower having a gate structure, which includes: (a) assembling a lower tower body portion of the tower below the gate structure portion; (b) above the lower tower body portion; A temporary pedestal having a structure similar to that of the lower tower body part and a jack that can be raised and lowered are installed on the upper surface of the temporary pedestal, (c) A beam part constituting the gate structure part and a arm part having a hinge part at the lower end are installed on the jack. d) Separately, on the lower tower body part, assemble a lower support member that supports the gate structure part having a hinge part at the upper end, and on the lower tower body part. (e) After correcting the misalignment of the two hinge parts to be joined by operating the jacks, joining the hinge parts, and assembling the steel tower, (f) fixing the temporary pedestal and the jacks. This is a construction method for assembling power transmission towers that is characterized by the removal of .
本発明において、門構部を有する送電用鉄塔(特殊鉄塔
)とは、例えば門形鉄塔(柱体間を「はり」で連結した
門形の鉄塔)、えぼし形鉄塔(四角又は方形鉄塔の一種
で、塔体の中腹部が狭くなり、上部が拡がった形の鉄塔
)などの門構部を有する鉄塔を意味する。In the present invention, power transmission steel towers (special steel towers) having gate structures include, for example, gate-shaped steel towers (gate-shaped steel towers in which the column bodies are connected with "beams"), ebboshi-shaped steel towers (a type of square or rectangular steel towers), etc. refers to a steel tower with a gate structure, such as a steel tower with a narrow midsection and a widened top.
第3図は本発明の実施例により組立てた特殊鉄塔の一例
を示す正面図で、1は下部塔体部で、門構部22はビー
ム部6、腕金部7、下部支持材12等から構成され、上
部材と下部材はヒンジ部8により接合されている。FIG. 3 is a front view showing an example of a special steel tower assembled according to an embodiment of the present invention, in which 1 is the lower tower body part, and the gate structure part 22 is connected to the beam part 6, arm part 7, lower support member 12, etc. The upper member and the lower member are joined by a hinge portion 8.
13は電力線取付位置である。13 is a power line attachment position.
以下、本発明工法を図面を用いて実施例により説明する
。Hereinafter, the construction method of the present invention will be explained with reference to the drawings and examples.
第4図イ〜トは本発明工法の実施例を説明するため工程
順に示した構成図である。FIGS. 4A to 4E are block diagrams shown in the order of steps to explain an embodiment of the construction method of the present invention.
図において、第3図と同一の符号は同一の部分を示す。In the figure, the same reference numerals as in FIG. 3 indicate the same parts.
この場合、組立てる鉄塔は第3図に示したものと同じ特
殊鉄塔である。In this case, the steel tower to be assembled is the same special steel tower as shown in FIG.
先ずイ図に示すように、第2図に示したと同様な従来法
と同じ鉄柱9と台枠10を組合せた工法により、鉄塔2
0の門構部22より下方の下部塔体部1を組立てる。First, as shown in Figure A, the steel tower 2 is constructed using the same method of combining steel columns 9 and underframes 10 as in the conventional method shown in Figure 2.
The lower tower body part 1 below the gate structure part 22 of No. 0 is assembled.
次に下部塔体部1の上方に、下部塔体部1と類似した枠
組構成(例えば四本柱、先細)の仮設架台14を塔体部
1を延長した形で組立て、その上面の四隅にそれぞれ昇
降可能なジヤツキ15を設置する。Next, a temporary pedestal 14 with a framework structure similar to that of the lower tower body 1 (for example, four pillars, tapered) is assembled above the lower tower body 1 in the form of an extension of the tower body 1, and each of the four corners of the upper surface can be raised and lowered. Install a possible jack 15.
このジヤツキ15は第5図に一例を示すように、上円板
16と下円板17を連結するリンク機構17を有し、中
間のボルト18およびナツト19により、上円板16を
下田板17に対して昇降可能に操作するようになってい
る。This jack 15 has a link mechanism 17 that connects an upper disc 16 and a lower disc 17, as shown in an example in FIG. It is designed to be able to be raised and lowered.
そしてジヤツキ15の下円板17は仮設架台14の上面
に接続され、上円板16は鉄塔のビーム部6の中央部材
16の下面に接続される。The lower disk 17 of the jack 15 is connected to the upper surface of the temporary frame 14, and the upper disk 16 is connected to the lower surface of the central member 16 of the beam section 6 of the steel tower.
最初ジヤツキ15は上げた状態でセットする。At first, set the jack 15 in the raised position.
これらの四角枠組体の組立中又は組立後、必要により鉄
柱9の支線をこれらの枠組体に結び付ける。During or after the assembly of these rectangular frame bodies, the branch lines of the steel columns 9 are tied to these frame bodies as necessary.
ジヤツキ15上にはビーム部6の中央部材16を組立て
、次いで口図に示す如く、ビーム部60部材を滑車4に
より吊り上げて、中央部材16に接続し、順次延長して
組立てる。The central member 16 of the beam section 6 is assembled on the jack 15, and then, as shown in the drawing, the beam section 60 member is lifted up by the pulley 4, connected to the central member 16, and sequentially extended and assembled.
この場合−回で吊上げる部材の大きさは、ビー4部6の
一部又は全部いずれでも良く、要はこの部材の重量が鉄
塔の片側に一時的に偏よってかかった場合、この部材重
量および偏心荷重に対してジヤツキ15を含む仮設架台
14が耐えられる範囲内であれば良い。In this case, the size of the member to be lifted in one turn may be either part or all of the bee 4 section 6. In short, if the weight of this member is temporarily biased to one side of the steel tower, the weight of this member and It is sufficient that the temporary pedestal 14 including the jacks 15 can withstand the eccentric load.
勿論、図では鉄塔の右側のみの組立を示しているが、鉄
塔の左側でも右側と同様な部材の吊上げ、組立てを右側
と交互に行なうことにより、左右の均衡を保ちながら組
立てられる。Of course, the figure shows only the right side of the tower being assembled, but the left side of the tower can be assembled while maintaining balance between the left and right sides by lifting and assembling the same parts as on the right side alternately.
本発明では、組立門構部を支持するジヤツキ15を含む
仮設架台14が下部塔体部1と類似構成の頑丈な構造で
あるため、−回に吊上げ組立てる門構部220部材が大
きくても容易に、安定良く作業ができると共に、安全な
作業ができる。In the present invention, since the temporary pedestal 14 including the jacks 15 that support the assembled gate structure has a similar structure to the lower tower body 1, it is easy to lift and assemble the gate structure 220 members even if they are large. This allows for stable and safe work.
次にへ図に示すように、別に下部塔体部1上に、門構部
の下部支持材120部材の一部又は全部を吊上げ、組立
てる。Next, as shown in the figure, part or all of the lower support member 120 of the gate structure section is separately lifted and assembled onto the lower tower body section 1.
下部支持材12の上端にはヒンジ部8が取付げられてい
る。A hinge portion 8 is attached to the upper end of the lower support member 12.
この場合、下部支持材12の組立部材は頑丈な下部塔体
部1に支持されるので、組立作業は容易に安定して安全
に行ない得る。In this case, since the assembly members of the lower support member 12 are supported by the sturdy lower tower body part 1, the assembly work can be performed easily, stably and safely.
この下部支持材12の吊上げ、組立ては、門構部のヒン
ジ部8より上方のビーム部6および腕金部7の組立の途
中又は前後のいずれの時期に行なっても良く、先に上方
に組立てたビーム部又は腕金部7が、その吊上げに邪魔
にならない時期に行われることが必要である。The lifting and assembly of the lower support member 12 may be carried out either during or before or after the assembly of the beam part 6 and the arm part 7 above the hinge part 8 of the gate structure. It is necessary to carry out the lifting at a time when the lifted beam part or cross arm part 7 does not interfere with the lifting.
次いで二図に示すように、下端にヒンジ部8を有する腕
金部7が吊上げられ、ビーム部6に接続される。Next, as shown in FIG. 2, the arm part 7 having the hinge part 8 at the lower end is lifted up and connected to the beam part 6.
かくすることにより、ヒンジ部8より上方の門構部の上
部材はジヤツキ15上に、ヒンジ部8より下方の門構部
の下部材は下部塔体部1上に、それぞれ別個に支持され
るが、上部材、下部材にそれぞれ取付けられた接合され
るべきヒンジ部8には部材のたわみ、ずれ等により、ず
れがあり、係合しないのが普通である。As a result, the upper member of the gate structure above the hinge part 8 is supported separately on the jack 15, and the lower member of the gate structure below the hinge part 8 is supported separately on the lower tower body part 1. However, the hinge portions 8 attached to the upper and lower members to be joined are usually misaligned due to deflection, misalignment, etc. of the members, and thus do not engage.
このため、仮設架台14上の四隅のジヤツキ15を操作
して門構部の上部材のヒンジ部8の位置を上下左右に調
節して修正し、下部材のヒンジ部8に係合させて接合す
る。For this purpose, the position of the hinge part 8 of the upper member of the gate structure is adjusted vertically and horizontally by operating the jacks 15 at the four corners of the temporary frame 14, and the position of the hinge part 8 of the upper member of the gate structure is adjusted by engaging with the hinge part 8 of the lower member and joining. do.
この場合、四鴇のジヤツキ15は人手でモンキースパナ
により容易に昇降しうるものを用い得るので、ヒンジ部
8の保合は極めて容易に行ない得る9ヒンジ部8の接合
が終れば、ホ図に示すように、架空地線用椀金21、電
力線用腕金23.24等、必要なその他の部材を吊上げ
て組立てる。In this case, since the four-piece jack 15 can be easily raised and lowered by hand using a monkey wrench, the hinge part 8 can be secured very easily. As shown, other necessary members such as the overhead ground wire bracket 21, the power line arms 23 and 24, and the like are lifted and assembled.
これらの部材の組立ては、通常ヒンジ部接合の後で行な
うが、接合の前に行なっても良い。These members are usually assembled after the hinge portions are joined, but they may be assembled before the hinge portions are joined.
このようにして門構部22の組立が終れば、ジヤツキ1
5および仮設架台14を撤去しくへ図)、最後に鉄柱9
および金棒10を撤去して、鉄塔20の組立てを完了す
る(ト図)。After completing the assembly of the gate structure 22 in this way, the jack 1
5 and the temporary pedestal 14), and finally the steel pole 9.
Then, the metal rod 10 is removed to complete the assembly of the steel tower 20 (Figure 3).
第6図および第7図は、それぞれ本発明工法の他の実施
例を説明する構成図で、第6図はえぼし形鉄塔、第7図
は狭線問えぼし形鉄塔の場合を示す。FIGS. 6 and 7 are block diagrams illustrating other embodiments of the construction method of the present invention, in which FIG. 6 shows a case of an elongated steel tower, and FIG. 7 shows a case of a narrow-line elongated steel tower.
図において第4図と同一符号は同一の部分を示す。In the figure, the same reference numerals as in FIG. 4 indicate the same parts.
これらの場合も、第4図に示す場合と同様の手順により
鉄塔を組立て得ることは明らかである。It is clear that in these cases as well, the steel tower can be assembled using the same procedure as shown in FIG.
以上述べたように、本発明工法は、門構部を有する送電
用鉄塔を組立てる工法において、鉄塔の下部塔体部の上
方に、該下部塔体部と類似構成の仮設架台と、その上面
に昇降可能なジヤツキを設置し、該ジヤツキ上に、前記
門構部を構成するビーム部および下端にヒンジ部を有す
る腕金部を順次延長して組立てて、前記ジヤツキにて支
持するため、部材の組立て中の偏心重量および偏心荷重
が大きくなっても、前記ジヤツキを含む前記仮設架台が
頑丈で、上記偏心に充分耐え得るので、容易に、安定し
てかつ安全に組立て工事を行ない得ると共に、特に門構
部のビーム部から腕金部にかげての部材の長大化、重量
増を来す大型の鉄塔でも、−回の吊上げ、組立て重量を
増加しうるので、容易に能率的に工事を行ない得る効果
がある。As described above, the construction method of the present invention is a construction method for assembling a power transmission tower having a gate structure, in which a temporary pedestal with a structure similar to that of the lower tower body is installed above the lower tower body of the tower, and A jack that can be raised and lowered is installed, and on the jack, a beam part constituting the gate structure part and a arm part having a hinge part at the lower end are sequentially extended and assembled, and in order to be supported by the jack, the members are assembled. Even if the eccentric weight and eccentric load during assembly become large, the temporary frame including the jacks is strong and can withstand the eccentricity, so the assembly work can be easily, stably and safely carried out, and especially Even in the case of large steel towers, where the parts extending from the beam part of the gate structure to the armrest part become longer and heavier, the construction work can be carried out easily and efficiently, since the lifting and assembly weight can increase several times. There are benefits to be gained.
又本発明工法は、それぞれ別個に支持した門構部の上部
材と下部材のそれぞれに取付けられた接合すべき2個の
ヒンジ部のずれを人手で前記ジヤツキを操作して修正し
うるため、門構部の上部材と下部材との接合を極めて容
易に行ない得、従来のように、上部材の吊上げ中実施す
るヒンジ部の接合の困難性を全く解消するものである。Furthermore, in the construction method of the present invention, it is possible to correct the misalignment of the two hinge parts to be joined, which are attached to the upper and lower members of the gate structure, which are supported separately, by manually operating the jack, The upper member and the lower member of the gate structure can be joined extremely easily, and the difficulty of joining the hinge part during lifting of the upper member, which was conventional, is completely eliminated.
従って、本発明工法は益益大型化する門構部を有する送
電用鉄塔の組立工事を可能にし、最適の工法を提供する
ものである。Therefore, the construction method of the present invention makes it possible to assemble a power transmission tower having a gate structure that increases the profit and size, and provides an optimal construction method.
第1図および第2図はえぼし形鉄塔の従来の組立工法の
例をそれぞれ説明する図である。
第3図は本発明工法の実施例により組立てた特殊鉄塔の
一例を示す正面図である。
第4図イ〜トは本発明工法の実施例を説明するため工程
順に示した構成図である。
第5図は本発明の実施例に用いるジヤツキの一例を示す
側面図である。
第6図および第7図はそれぞれ本発明工法の他の実施例
を説明する構成図である。
1・・・下部塔体部、2・・・門構部、3,10・・・
金棒、4・・・滑車、5・・・支線の方向、6・・・ビ
ーム部、7・・・腕金部、8・・・ヒンジ部、9・・・
鉄柱、11・・・支線、12・・・下部支持材、13・
・・電力線取付位置、14・・・仮設架台、15・・・
ジヤツキ、16・・・上円板、17・・・下円板、18
・・・ボルト、19・・・ナツト、20・・・鉄塔、2
2・・・門構部。FIGS. 1 and 2 are diagrams each illustrating an example of a conventional assembly method for an elongated steel tower. FIG. 3 is a front view showing an example of a special steel tower assembled by an embodiment of the construction method of the present invention. FIGS. 4A to 4E are block diagrams shown in the order of steps to explain an embodiment of the construction method of the present invention. FIG. 5 is a side view showing an example of the jack used in the embodiment of the present invention. FIG. 6 and FIG. 7 are block diagrams explaining other embodiments of the construction method of the present invention, respectively. 1... Lower tower body part, 2... Gate structure part, 3, 10...
Metal rod, 4... Pulley, 5... Direction of branch line, 6... Beam part, 7... Bracelet part, 8... Hinge part, 9...
Steel column, 11... branch line, 12... lower support material, 13.
... Power line installation position, 14... Temporary mount, 15...
Jacket, 16... Upper disk, 17... Lower disk, 18
... Bolt, 19... Natsuto, 20... Steel tower, 2
2...Gate structure section.
Claims (1)
で (a) 前記鉄塔の前記門構部より下方の下部塔体部
を組立て、 (b) 前記下部塔体部の上方に、該下部塔体部と類
似構成の仮設架台と、その上面に昇降可能なジヤツキを
設置し、 (c) 前記ジヤツキ上に、前記門構部を構成するビ
ーム部および下端にヒンジ部を有する腕金部を順次延長
して組立てて、前記ジヤツキにて支持し、 (d) 別に前記下部塔体部上に、上端にヒンジ部を
有する前記門構部を支える下部支持材を組立てて、前記
下部塔体部にて支持し、 (e)接合すべき前記2個のヒンジ部のずれを、前記ジ
ヤツキを操作して修正し、ヒンジ部を接合し、前記鉄塔
を組立てた後、 (f) 前記仮設架台および、前記ジヤツキを撤去する
ことを特徴とする送電用鉄塔の組立工法。[Claims] 1. A construction method for assembling a power transmission tower having a gate structure (℃)
(a) Assemble the lower tower body below the gate structure of the steel tower, (b) Install a temporary pedestal with a similar configuration to the lower tower body above the lower tower body, and install a temporary pedestal with a structure similar to that of the lower tower body, and a platform that can be raised and lowered on its upper surface. (c) on the jack, a beam part constituting the gate structure part and a arm part having a hinge part at the lower end are successively extended and assembled, and supported by the jack; ( d) Separately, assemble a lower support member for supporting the gate structure having a hinge portion at its upper end on the lower tower body, and support it in the lower tower body; After correcting the misalignment of the hinge portion by operating the jacks, joining the hinge portions, and assembling the steel tower, (f) removing the temporary pedestal and the jacks. Assembly method.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP8612979A JPS5840629B2 (en) | 1979-07-06 | 1979-07-06 | Assembly method for power transmission towers |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP8612979A JPS5840629B2 (en) | 1979-07-06 | 1979-07-06 | Assembly method for power transmission towers |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS569568A JPS569568A (en) | 1981-01-31 |
| JPS5840629B2 true JPS5840629B2 (en) | 1983-09-07 |
Family
ID=13878090
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP8612979A Expired JPS5840629B2 (en) | 1979-07-06 | 1979-07-06 | Assembly method for power transmission towers |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS5840629B2 (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5645897Y2 (en) * | 1977-09-07 | 1981-10-27 | ||
| JP6134499B2 (en) * | 2012-11-14 | 2017-05-24 | 東京電力ホールディングス株式会社 | Steel tower assembly and dismantling method and equipment |
-
1979
- 1979-07-06 JP JP8612979A patent/JPS5840629B2/en not_active Expired
Also Published As
| Publication number | Publication date |
|---|---|
| JPS569568A (en) | 1981-01-31 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPS5840629B2 (en) | Assembly method for power transmission towers | |
| JP3988937B2 (en) | Steel tower raising method | |
| JP2927320B2 (en) | How to assemble a large hanging boiler | |
| JP2950726B2 (en) | Construction method of multi-layer suspension structure | |
| JP4318788B2 (en) | Anchor bolt installation method | |
| JP2529067B2 (en) | Crane flexible climbing method | |
| JPH11100902A (en) | Girder installation method | |
| JPS62309B2 (en) | ||
| JP2593122B2 (en) | Boiler installation method by small local block | |
| JP3412505B2 (en) | Slip form method | |
| JP2768237B2 (en) | Assembly translation method and beam joining method of large hanging boiler, and beam joining structure | |
| JP3894341B2 (en) | Disassembly method of boiler and boiler building | |
| JP2021116153A (en) | Support gantry for tower cranes and climbing methods using them | |
| JPH09151541A (en) | Method of cross-cut construction | |
| JPS6229584B2 (en) | ||
| JP2634271B2 (en) | Jack-up method and device | |
| JP2999118B2 (en) | Furnace scaffold | |
| JP2620090B2 (en) | Girder form support device and girder form support method | |
| JPH10196122A (en) | Arch support assembly system and method | |
| JPH08114302A (en) | Boiler installing method and boiler installation structural body | |
| JPH0431412Y2 (en) | ||
| JPH09228690A (en) | Steel tower construction method | |
| JP2005188080A (en) | Construction method for heightening steel tower | |
| JPH03228936A (en) | Truss frame and its erection method | |
| JP2776128B2 (en) | Lifting device for building frame |