Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPS5848713B2 - Building construction method - Google Patents
[go: Go Back, main page]

JPS5848713B2 - Building construction method - Google Patents

Building construction method

Info

Publication number
JPS5848713B2
JPS5848713B2 JP8577679A JP8577679A JPS5848713B2 JP S5848713 B2 JPS5848713 B2 JP S5848713B2 JP 8577679 A JP8577679 A JP 8577679A JP 8577679 A JP8577679 A JP 8577679A JP S5848713 B2 JPS5848713 B2 JP S5848713B2
Authority
JP
Japan
Prior art keywords
building
ground
parts
construction
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP8577679A
Other languages
Japanese (ja)
Other versions
JPS569566A (en
Inventor
茂次 早川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP8577679A priority Critical patent/JPS5848713B2/en
Publication of JPS569566A publication Critical patent/JPS569566A/en
Publication of JPS5848713B2 publication Critical patent/JPS5848713B2/en
Expired legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】 本発明は建築物の施工方法、とくに不等沈下の予想され
る場合の建築物の施工方法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method of constructing a building, particularly a method of constructing a building where uneven settlement is expected.

建築物は、適当な地業によって支持地盤に強固に安定し
て支持されるが、建築物が大型になると、その下方の支
持地盤そのものに部分的な組成上の差異を持ち、いわゆ
る圧密沈下の差によって、長年月を経るに至らぬうちに
も、建物各部に沈降量の差を生じ、不等沈下が惹起する
諸種の障害をもたらす。
Buildings are firmly and stably supported by the supporting ground through appropriate earthworks, but as buildings grow larger, the underlying supporting ground itself has local compositional differences, resulting in so-called consolidation settlement. Due to these differences, even before many years have passed, differences in the amount of subsidence occur in different parts of the building, resulting in various problems caused by uneven subsidence.

従来、とくに長い建築物では、構造継手を設けて、不当
沈下に基く応力による構造躯体の破壊を回避し、あるい
は、杭地業や、地盤改良等によって地盤の圧密沈降の影
響を消去するようにしていた。
Traditionally, especially in long buildings, structural joints have been installed to avoid the destruction of the structural frame due to stress caused by undue settlement, or the effects of consolidation settlement of the ground have been eliminated through piling construction, ground improvement, etc. was.

しかし、近時建築物の高層化に伴い、超高層建築物では
、その高層部と低層部に大きな自重の差があり、比較的
均質な地盤にあっても、支持地盤には大きな圧密度の差
が生じ、前記したものとは別の不等沈下が問題となって
きた。
However, as buildings have become taller in recent years, there is a large difference in self-weight between high-rise and low-rise parts of superhigh-rise buildings, and even if they are on relatively homogeneous ground, the supporting ground has a large degree of consolidation. Differences have arisen, and uneven settlement, which is different from the one mentioned above, has become a problem.

この解決の手段の一つは、建物を直接深い支持層で支持
することと、そのような支持層まで杭地業を施工し、高
層部と低層部とで杭の本数を対応させ、圧密による不等
沈下を生じさせない方法であった。
One way to solve this problem is to directly support the building with a deep support layer, construct pile construction up to such a support layer, match the number of piles between high-rise areas and low-rise areas, and prevent consolidation. This was a method that would not cause uneven settlement.

本発明は、地面下の堅硬な支持地層が岩盤に似たもので
あって、それが建築物敷地内で一方に傾斜し、表層土の
厚さが圧密量の差となって建築物に影響するような地盤
を対象にして、建築物の施工に当って完成された解決方
法であって、建築物を堅硬な支持層のある部分と、岩盤
が傾斜し、表層士の深い部分とに二分し、両部分の圧密
量の差を予め求めて、この差に等しい寸法だけ圧密代と
して後者の部分を前者より浅く設定し、両部分の分割部
分に分離帝を設けて両部分の沈降挙動による構造上の応
力を絶縁することを主旨とするものである。
In the present invention, the hard supporting stratum under the ground is similar to bedrock, and it slopes to one side within the building site, and the thickness of the surface soil causes a difference in the amount of consolidation, which affects the building. This is a solution that was perfected when constructing buildings on ground that is difficult to maintain, and it divides the building into two parts: a part with a solid support layer and a part with a deep surface layer where the bedrock is sloping. The difference in the amount of consolidation between the two parts is determined in advance, and the latter part is set to be shallower than the former by a dimension equal to this difference, and a separation barrier is provided between the two parts to determine the settling behavior of the two parts. The purpose is to insulate structural stress.

このような考え万は、軟弱な地盤上に建つ建築物を増築
するような場合に採用されたことてはある。
This kind of thinking has been used in cases where buildings built on soft ground are being expanded.

即ち、在来部分では圧密沈降が十分進行して沈降が停止
しており、増築部分ではこれから沈降が始まるので、増
築部分では、将来の沈降量に等しい寸法だけ施工の基準
面を上方に移し、在来、増築の両部分の間には相対変位
を許容する構造継手を設け、要するに長期Oこ亘る「時
間」の作用によって圧密沈降の現象を吸収したものであ
り、その過渡期には両部分の基準面の段差がもたらす障
害は不可避のものであった。
In other words, in the conventional area, consolidation settlement has progressed sufficiently and settlement has stopped, and in the expanded area, settling will begin, so in the expanded area, the construction reference plane is moved upward by a dimension equal to the future amount of sedimentation. Traditionally, a structural joint was installed between the two parts of an extension to allow relative displacement, and in short, the phenomenon of consolidation settlement was absorbed by the action of "time" over a long period of time, and during the transition period, both parts The obstacles caused by the level difference in the reference plane were unavoidable.

本発明は上記のような圧密度の差にまともに取り組み、
「時間」の作用を消去するようにした建築物の施工方法
を提供するもので、以下実施例につき、図面を参照して
詳細に説明する。
The present invention deals with the above-mentioned difference in the degree of compaction,
This invention provides a construction method for a building that eliminates the effect of "time", and examples thereof will be described in detail below with reference to the drawings.

第1図ないし第3図において、Gは建築物Aの敷地地盤
、Rは堅硬な支持地盤(以下「岩盤」という。
In Figures 1 to 3, G is the site ground of building A, and R is solid supporting ground (hereinafter referred to as ``bedrock'').

)、Eは圧密の対象となる表層士である。上記建築物A
は、岩盤Rに直接支持される部分AIと、表層土Eを介
して傾斜した深い岩盤R上に支持される部分A2 とに
二分される。
), E is a surface worker subject to consolidation. Building A above
is divided into a portion AI that is directly supported on the bedrock R and a portion A2 that is supported on the inclined deep bedrock R through the surface soil E.

なお、第1図において2点鎖線で示すように岩盤R′が
一層深い位置にある場合には、建築物Aの全体が表層土
E1, E2を介して支持されることになるが、表層土
E1, E2の圧密の差を扱う限りにおいで同一である
ので、簡単のため以下岩盤Rにういて説明する。
Note that if the bedrock R' is located at a deeper position, as shown by the two-dot chain line in Figure 1, the entire building A will be supported through the surface soil E1 and E2, but the surface soil As far as the difference in consolidation between E1 and E2 is concerned, they are the same, so for the sake of simplicity, the following explanation will be based on rock R.

建築物Aはまた、鉄骨鉄筋コンクIJ−ト(SRC)又
は鉄筋コ/クIJ−4(RC)造の地下室部分Bと、鉄
骨鉄筋コンクリート造の地上階部分Cとから成り、建築
物Aの二部分A,,A2の互に対応する地下部B1,
B2及び地上部C1, C2の間に分離帯Sが設けられ
る。
Building A also consists of a basement part B made of steel reinforced concrete (SRC) or reinforced concrete IJ-4 (RC), and a ground floor part C made of steel reinforced concrete. Underground parts B1 and A2 correspond to each other.
A separation strip S is provided between B2 and above-ground parts C1 and C2.

建築物Aは、柱10、梁20、底版30、床版40、外
壁50、間仕切60を躯体部として構成されている。
The building A is composed of pillars 10, beams 20, bottom slabs 30, floor slabs 40, outer walls 50, and partitions 60 as a frame part.

なお51は地下部分外壁50の外側に、堀削に先立って
地上から施工された柱列壁による土留壁である。
Reference numeral 51 designates an earth retaining wall made of columnar walls constructed from above ground prior to excavation on the outside of the underground external wall 50.

敷地地盤Gは、地質調査の根切堀削によって、例えば、
岩盤Rは砂岩、表層土Eは砂質粘土層、圧密の対象とな
る層厚は2〜4m,というよう1こ調べられ、これをも
とに建築物Aの二部分A, IA2の圧密差dsc!′
ILが岩盤Rの沈下を無視して算出される。
Site ground G is determined by excavation during geological survey, for example,
The bedrock R is sandstone, the surface soil E is a sandy clay layer, and the layer thickness to be consolidated is 2 to 4 m.Based on this, the consolidation difference between the two parts A and IA2 of building A was determined. dsc! ′
IL is calculated ignoring the subsidence of bedrock R.

ところで、建築物Aの二部分AI * A2間にdSc
IrLの不等沈下が生ずれば、二等部分A1,A2の柱
10.10の間隔l(第1図)、つまり梁20の長さに
対する変形の許容量をはるかに超過するので、二部分A
1, A,,間には前述のように分離帯Sを設け、梁2
0、底版30、床版40、外壁50等にはA1部分とA
2部分の間に、それぞれ絶縁部20S,30S,40S
,50S(第4図ないし第8図参照、これらについでは
後述する)を設け、こうしておいてA2部分は底版30
の下面を設計面よりdscrrL上方に設定して浅く施
工する。
By the way, there is a dSc between the two parts AI*A2 of building A.
If uneven settlement of IrL occurs, the distance l between the columns 10.10 of the two equal parts A1 and A2 (Fig. 1), that is, the allowable amount of deformation for the length of the beam 20, will be far exceeded, so the two parts A
1. A separation strip S is provided between the beams 2 and 2 as described above.
0, bottom plate 30, floor plate 40, outer wall 50, etc. have A1 part and A
Insulating parts 20S, 30S, 40S are provided between the two parts, respectively.
, 50S (see Figures 4 to 8, these will be described later), and in this way the A2 part is the bottom plate 30.
Set the bottom surface above dscrrL from the design surface and construct shallowly.

さらに、建築物AのA2部分で沈下量かdscrfLに
達し、A1,A2両部分が設計面で一致するには長期に
亘る沈下期間が必要であるため、工期は延弓し実際的で
ない。
Furthermore, the amount of settlement reached dscrfL in the A2 part of the building A, and a long period of subsidence is required for both the A1 and A2 parts to match in terms of design, which would prolong the construction period and be impractical.

しかも沈降量が設定通りに進行しないときには、分割し
た両部分A,,A2において設計面が同一面になり切ら
ず、分離帯S部分における接続が、斜面になる不都合が
ある。
Moreover, when the amount of sedimentation does not proceed as set, the design surfaces of both the divided portions A, , A2 do not become the same plane, and the connection at the separation zone S portion becomes inconveniently sloping.

そこで本発明においては、A2部分に上載荷重をかけて
沈下期間を短縮する。
Therefore, in the present invention, an overload is applied to the A2 portion to shorten the subsidence period.

すなわち、第2図と第3図に示すように、間仕切60に
施工用壁体61を追加して外壁50、間仕切60と共に
底版30の上に完全な周壁を形成することにより、A2
部分の地下部B2ヲ、水槽Pに構成し、この水槽Pに所
定の水深に水を張り、水深に見合う上載荷量を得て直下
の地盤に対して強制圧密の作用を持たせ、短期間に長期
分の圧密を達成させる。
That is, as shown in FIGS. 2 and 3, by adding the construction wall 61 to the partition 60 and forming a complete peripheral wall on the bottom plate 30 together with the outer wall 50 and the partition 60, the A2
The underground part B2 of the part is constructed into a water tank P, and this water tank P is filled with water to a predetermined depth to obtain an overload amount commensurate with the water depth and have a forced consolidation effect on the ground directly below, for a short period of time. achieve long-term consolidation.

ここで上記水槽Pは、各階の床版40をそのままに、階
段室その他の開口部で上下に連絡し、適宜の水街処理を
施して大水槽として完成する。
Here, the water tank P is completed as a large water tank by leaving the floor slabs 40 of each floor as they are, connecting the upper and lower parts through staircases and other openings, and performing appropriate water treatment.

この水槽方式による上載荷重は、建築物A2の上方への
構築進行に伴・う自重の増加{こ対して、水槽Pからの
排水による減量の調節が自在かつ容易である。
The overload due to this water tank method is an increase in its own weight as the construction progresses upwards of the building A2 (on the other hand, the weight loss due to drainage from the water tank P can be freely and easily adjusted).

しかも、水槽P中の水の重量に加えて、建築物Aの外方
で地下部分B2より深所に設けたディープウエルDPか
らの揚水に伴う、地下水の脱水の有効利用をはかると、
圧密対象の表層士E中の間隙水圧を降下させて建築物の
沈降を促進することもできる。
Moreover, in addition to the weight of the water in the water tank P, if we aim to effectively utilize the dewatering of groundwater due to pumping from the deep well DP, which is located outside of the building A and deeper than the underground part B2,
It is also possible to reduce the pore water pressure in the surface layer E to be consolidated to promote settling of the building.

上記において、追加の槽壁となる壁体61は、建築物A
の構築終了後に解体される。
In the above, the wall body 61 serving as an additional tank wall is the building A.
will be dismantled after construction is completed.

本発明に係る施工方法によって構築された建築物Aにお
いては、その底版30の下面に、大略、建物自重;15
t/m、上載荷重;10t/m”の接地圧がかかり、A
2部分の不等沈下dsを20ynmに設定して所期通り
の施工をなすことができた。
In the building A constructed by the construction method according to the present invention, on the lower surface of the bottom plate 30, approximately 15
t/m, overload; ground pressure of 10t/m" is applied, A
We were able to complete the construction as planned by setting the uneven settlement ds of the two parts to 20 ynm.

ところで本発明の実施にあたって重要な解決手段となる
分離帯Sの説明に移る。
By the way, we will now turn to a description of the separation strip S, which is an important means of solving the problem in carrying out the present invention.

第4図ないし第8図は、床版40、梁20、外壁50及
び底版30等の分離帯Sの部分を示すもので、建築物A
2部分の構築に際しては、第4図と第5図及び第8図に
示すように土圧伝達部材81,82;83,84の組を
A1とA2部分に設けて土圧によりA2部分がA1側に
接近しないようにする。
Figures 4 to 8 show parts of the separation strip S such as the floor slab 40, beam 20, outer wall 50, bottom slab 30, etc.
When constructing the two parts, as shown in Figs. 4, 5, and 8, sets of earth pressure transmitting members 81, 82; 83, 84 are provided in the A1 and A2 parts, so that the A2 part becomes A1 due to the earth pressure. Avoid getting close to the side.

第4図、第5図において士圧伝達部材81はA1側の地
下1階と地下2階の床版40及び梁20にその一方の端
部81aを分離帯Sの部分に突き出した状態でアンカー
ボルト85により水平に固定する一方、他の土圧伝達部
材82は、A2側の地下1階と地下2階の床版40及び
梁20に、一方の端部82aを上記土庄伝達部材81の
端面に当接させてアンカーボルト85により水平に固定
し、A2部分の沈降が自由に行われるようにしてA2部
分のAI側への接近を阻止する。
In FIGS. 4 and 5, the pressure transmitting member 81 is anchored to the floor slabs 40 and beams 20 of the first and second basement floors on the A1 side with one end 81a protruding into the separation strip S. While being fixed horizontally with bolts 85, the other earth pressure transmission member 82 is attached to the floor slab 40 and beam 20 of the first basement floor and second basement floor on the A2 side, with one end 82a attached to the end surface of the earth pressure transmission member 81. The A2 part is brought into contact with the AI side and fixed horizontally with an anchor bolt 85, so that the A2 part can freely sink, thereby preventing the A2 part from approaching the AI side.

また第8図において士圧伝達部材83は底版30と最下
階の床版41間の地中梁42の位置においてA1側に水
平に固定する一方、他の土圧伝達部材84は底版30と
最下階の床版41間のA2側の地中梁42に固定し、上
記士圧伝達部材83の端面に当接させて、上記と同様に
A2部分の沈降が自由に行われるようにしてA2部分の
A1側への接近を阻止する。
In addition, in FIG. 8, the earth pressure transmission member 83 is fixed horizontally to the A1 side at the position of the underground beam 42 between the bottom slab 30 and the floor slab 41 on the lowest floor, while the other earth pressure transmission member 84 is connected to the bottom slab 30. It is fixed to the underground beam 42 on the A2 side between the floor slabs 41 on the lowest floor, and brought into contact with the end face of the pressure transmitting member 83, so that the A2 part can freely settle in the same way as above. Prevent the A2 portion from approaching the A1 side.

第6図は上階C1,C2における梁20の架構鉄骨梁2
1における絶縁部20Sを示すもので、この部分では土
庄の考慮は不要であるが、梁20の鉄筋コンクリート補
完の時点までは、分離帯S部分では鉄骨21も端面を近
接させて上下方向の相対移動を許して切断されておりこ
こに鉄骨仮接合88を設けてある。
Figure 6 shows the frame steel beam 2 of the beam 20 on the upper floors C1 and C2.
This shows the insulating part 20S in 1, and there is no need to consider the tonosho in this part, but until the time when the beam 20 is supplemented with reinforced concrete, the steel frame 21 in the separation zone S part also has its end faces close to each other and is subject to relative movement in the vertical direction. The steel frame temporary joint 88 is provided here.

即ち接手板22は正規に設計されたものを用いるが、本
接合のボルトは用いず、仮止めボルト23によって接合
し、しかもボルト径を正規のボルトより細目のものを使
用して該部分における沈降差に対応させておき、絶縁部
20Sの後打ちコンクリートの打設前に正規のボルトに
よって正規の接合を完成させる。
In other words, the joint plate 22 is one that is officially designed, but the bolts for the actual joint are not used, and the joint is made with a temporary bolt 23, and the diameter of the bolt is smaller than that of the regular bolt to prevent settling in that part. The difference is made to correspond to the difference, and a regular connection is completed with regular bolts before pouring concrete for the insulating part 20S.

建築物Aの二部分A1, A2の構築が終了し、かつA
2部分が予定量沈降し終わったら、上記の各絶縁部20
S,30S,40S,50Sに非収縮性コンクリート等
のコンクリート86を打設して二部分A, , A2を
一体に結合する。
The construction of two parts A1 and A2 of building A has been completed, and A
After the two parts have settled by the predetermined amount, each of the above-mentioned insulating parts 20
Concrete 86 such as non-shrinkable concrete is placed on S, 30S, 40S, and 50S to join the two parts A, , and A2 together.

この場合、二部分AH s A2の各部の鉄筋8γは分
離帯Sにおいて相互にラップさせる。
In this case, the reinforcing bars 8γ of each part of the two-part AH s A2 are overlapped with each other in the separation strip S.

底版30と外壁50の分離帯Sの部分の外面側には第7
図と第8図に示すように非加硫ブチルゴム等の止水板8
9を設け漏水の遮断を計る。
On the outer surface side of the separation strip S between the bottom plate 30 and the outer wall 50, a seventh
Water stop plate 8 made of non-vulcanized butyl rubber, etc., as shown in the figure and Fig. 8.
9 to prevent water leakage.

90は二部分AI ,A2の底版30の底面に設けられ
た止水鉄板で91は予備の伸縮ひだである。
90 is a water-stop iron plate provided on the bottom surface of the bottom plate 30 of the two parts AI and A2, and 91 is a preliminary expansion and contraction fold.

なお、土圧伝達部材81,82,83は後打コンクリ−
1− 8 6の打設硬化後建築物Aから取り外す。
Note that the earth pressure transmission members 81, 82, and 83 are made of post-cast concrete.
1-8 Remove from building A after pouring and hardening in step 6.

第9図は、表層土E2が砂質粘土でかつその厚さか4m
の場合における、建築物A2の構築の進行と上載荷重の
調節に伴う沈下量の想定沈降曲線を示すもので、建築物
A2の構築の進行と上載荷重の調節は次の通りである。
Figure 9 shows that the surface soil E2 is sandy clay and its thickness is about 4 m.
This shows an assumed settlement curve of the amount of settlement due to the progress of construction of building A2 and adjustment of overburden load in the case of , and the progress of construction of building A2 and adjustment of overload load are as follows.

〔実測開始日〕[Actual measurement start date]

地下3隔構築、上載荷重(水):/t/m、全体の接地
圧; 3.8 8 t/if 〔60日目〕 地下2階、地下1階、地上1階構築、 全体の接地圧; 1 0 t/77J 〔80日目〕 地下3階と地下2階に上載荷重(水)を追加、全体の接
地圧; 1 5.3 8 t/m”(90日目〕〜・ 地下2階と地下1階に上載荷重(水)を追加、全体の接
地圧; 1 9.2 6 t/ m’なお、この図の1
点鎖線は一般的な沈下の予想曲線であり、これと実線で
示される実施効果の対比から分るように上載荷重による
大きな沈降促進効果が認められる。
Construction of 3 underground spaces, overload (water): /t/m, total ground pressure; 3.8 8 t/if [60th day] Construction of 2 basement floors, 1 basement floor, and 1 floor above ground, overall ground pressure ; 10 t/77J [80th day] Added overload (water) to the 3rd basement floor and the 2nd basement floor, total ground pressure: 1 5.3 8 t/m" (90th day) - Basement 2 Add overload (water) to the first floor and the first basement floor, total ground pressure: 1 9.2 6 t/m' Note that 1 in this figure
The dotted chain line is a general expected settlement curve, and as can be seen from the comparison between this and the implementation effect shown by the solid line, a large settlement promotion effect due to overburden load is recognized.

以上説明したように、本発明においては、支持地盤の各
部の圧密量の想定にもとづいて、建築物を2又はそれ以
上の複数部分に分割し、各部における想定沈下量の差に
対応して、その部分の基準面を設計面の上方に設定して
施工するので、不等沈下の回避のための特別な地業を施
すことなく直接基礎を実現させて短期間の工期を実現す
ることができる。
As explained above, in the present invention, a building is divided into two or more parts based on the estimated amount of consolidation of each part of the supporting ground, and corresponding to the difference in the estimated amount of settlement in each part, Since the reference plane of that part is set above the design plane and construction is carried out, the foundation can be built directly without special land works to avoid uneven settlement, and the construction period can be shortened. .

また、分離帯の補完も建築工程内に並行して実施可能で
あり、その後の不測の応力による変形も許容値内で処理
できる範囲に納めることが可能である。
In addition, supplementation of the separation strip can be carried out in parallel with the construction process, and subsequent deformation due to unexpected stress can be kept within the allowable range.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の施工方法により構築された建築物の一
部を破断して示した正面図、第2図は第1図の建築物の
地下2階の横断面図、第3図は同地下3階の横断面図、
第4図と第5図は地下1,2階に設けられる土圧伝達部
材の設備状態を示す平面図と側面図、第6図は梁の絶縁
部を示す断面図、第7図は地下外壁の絶縁部を示す断面
図、第8図は底版及地中梁部分の絶縁部を示す断面図、
第9図は建築物の構築の進行と上載荷重の調節に伴う沈
下量の想定沈降曲線を示す、時間一沈下量図である。 A・・・・・・建築物、AH s A2・・・・・・部
分、B1,B2・・・・・・地下部、C1,C2・・・
・・・地上部、G・・・・・・敷地地盤、R・・・・・
・岩盤、S・・・・・・分離帯、P・・・・・・水槽。
Figure 1 is a partially cutaway front view of a building constructed using the construction method of the present invention, Figure 2 is a cross-sectional view of the second basement floor of the building shown in Figure 1, and Figure 3 is a cross-sectional view of the second basement floor of the building shown in Figure 1. A cross-sectional view of the third basement floor,
Figures 4 and 5 are a plan view and a side view showing the state of the earth pressure transmission members installed on the first and second basement floors, Figure 6 is a cross-sectional view showing the insulating parts of the beams, and Figure 7 is the underground outer wall. Figure 8 is a cross-sectional view showing the insulation part of the bottom slab and underground beam.
FIG. 9 is a time-settlement diagram showing an assumed settlement curve of the amount of settlement accompanying the progress of construction of a building and adjustment of the overload load. A... Building, AH s A2... Part, B1, B2... Basement, C1, C2...
...Ground level, G...Site ground, R...
・Bedrock, S... Separation zone, P... Water tank.

Claims (1)

【特許請求の範囲】 1 支持地盤の傾斜又は階層の相異によって敷地地盤に
不等沈下の予想される建築物の施工方法において、敷地
地盤の各部の圧密量の想定にもとづいて、当該建築物を
2又はそれ以上の複数部分に分割し、各部における想定
沈下量の差に対応して、その部分の基準面を設計面の上
方に設定するとともに、分割した建築物の各部分間には
分離帯を設け、各部分ごとに設定沈下量に対応した上載
荷重を載荷してその部分の地盤の圧密沈降を強制的に促
進し、各部分の沈降が終了した時期に前記分離帯を充填
接続して一体の建築物として施工することを特徴とする
建築物の施工方法。 2 建築物の載荷部分に水槽を設け上載荷重として水を
用いることを特徴とする特許請求の範囲第1項記載の建
築物の施工方法。 3 上載荷重は、当該建築物の上層部の施工進行に伴い
、逐次減量除去することを特徴とする特許請求の範囲第
1項又は第2項記載の建築物の施工方法。
[Scope of Claims] 1. In a construction method for a building in which uneven settlement is expected in the site ground due to the slope of the supporting ground or differences in floors, the building construction method is based on the assumption of the amount of consolidation of each part of the site ground. The building is divided into two or more parts, and the reference plane for each part is set above the design surface according to the difference in expected settlement amount in each part, and separation is made between each part of the divided building. A belt is provided, and an overburden load corresponding to the set settlement amount is applied to each part to forcibly promote consolidation settling of the ground in that part, and when the settling of each part is completed, the separation belt is filled and connected. A construction method for a building characterized by constructing it as an integrated building. 2. A construction method for a building according to claim 1, characterized in that a water tank is provided in a load-bearing part of the building and water is used as the load. 3. The method for constructing a building according to claim 1 or 2, wherein the overload load is gradually reduced and removed as the construction of the upper layer of the building progresses.
JP8577679A 1979-07-06 1979-07-06 Building construction method Expired JPS5848713B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP8577679A JPS5848713B2 (en) 1979-07-06 1979-07-06 Building construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP8577679A JPS5848713B2 (en) 1979-07-06 1979-07-06 Building construction method

Publications (2)

Publication Number Publication Date
JPS569566A JPS569566A (en) 1981-01-31
JPS5848713B2 true JPS5848713B2 (en) 1983-10-29

Family

ID=13868275

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8577679A Expired JPS5848713B2 (en) 1979-07-06 1979-07-06 Building construction method

Country Status (1)

Country Link
JP (1) JPS5848713B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61202426U (en) * 1985-06-11 1986-12-19

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59106538A (en) * 1982-12-03 1984-06-20 三菱レイヨン株式会社 Raising of spun yarn

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61202426U (en) * 1985-06-11 1986-12-19

Also Published As

Publication number Publication date
JPS569566A (en) 1981-01-31

Similar Documents

Publication Publication Date Title
KR100866162B1 (en) Construction method of chair-type freestanding wall
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN105525627B (en) A kind of two-way anchor fixed board retaining wall and its construction method
CN102995659B (en) Method for constructing from central area to periphery of ultra-large type underground engineering
CN104018518A (en) Prefabricated underground diaphragm wall and method for constructing outer basement wall and floor slabs
CN104453274A (en) Method for supporting underground layer increasing of existing building by supporting structure and underpinning structure
CN105756091B (en) A Construction Method of Subway Station Foundation Pit Controlling the Deformation of Adjacent Buildings
JP2012107479A (en) Method for constructing underground and aboveground structure
US7025537B2 (en) Subterranean structures and methods for constructing subterranean structures
CN110593080B (en) A trestle system and construction method combined with an internal support system
CN106193120B (en) Basement is encorbelmented, and bottom plate is inverse to make structure and construction method
CA2673876A1 (en) Shoring free excavation and basement construction apparatus and method
KR102021496B1 (en) Retaining wall construction method and retaining wall structure by the method
JP3930954B2 (en) Construction method of structure
KR20110052360A (en) Underground construction method that allows continuous construction of the basement outer wall by using the slab's steel film without the installation of strips
KR100831332B1 (en) Underground wall for civil engineering and construction method
KR101256311B1 (en) Structual deepening method
JP4159148B2 (en) Construction method of shaft
CN114809015B (en) Temporary support system and permanent structure combined construction method for open cut subway station
CN111042214A (en) Anti-floating structure of shallow-soil-covered underground structure and construction method thereof
CN216194772U (en) Foundation pit supporting and water stopping system
KR20070052109A (en) Simultaneous construction of slab and exterior wall and underground reverse casting using slim composite floor structure
JPS5848713B2 (en) Building construction method
Dellaria et al. Combining multiple techniques to complete an urban deep excavation
JP7275844B2 (en) WALL-LIKE STRUCTURE AND METHOD OF CONSTRUCTING WALL-LIKE STRUCTURE