Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPS5851083B2 - Construction method for connecting girders using prestressed steel girders - Google Patents
[go: Go Back, main page]

JPS5851083B2 - Construction method for connecting girders using prestressed steel girders - Google Patents

Construction method for connecting girders using prestressed steel girders

Info

Publication number
JPS5851083B2
JPS5851083B2 JP9830481A JP9830481A JPS5851083B2 JP S5851083 B2 JPS5851083 B2 JP S5851083B2 JP 9830481 A JP9830481 A JP 9830481A JP 9830481 A JP9830481 A JP 9830481A JP S5851083 B2 JPS5851083 B2 JP S5851083B2
Authority
JP
Japan
Prior art keywords
girder
girders
steel
concrete
prestressed steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP9830481A
Other languages
Japanese (ja)
Other versions
JPS584005A (en
Inventor
二三男 岩村
滉 渡辺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kawada Industries Inc
Original Assignee
Kawada Industries Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kawada Industries Inc filed Critical Kawada Industries Inc
Priority to JP9830481A priority Critical patent/JPS5851083B2/en
Publication of JPS584005A publication Critical patent/JPS584005A/en
Publication of JPS5851083B2 publication Critical patent/JPS5851083B2/en
Expired legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

【発明の詳細な説明】 本発明は通称プレビームと称されるプレストレス鋼桁を
用いた橋梁の架設に際してのプレストレス鋼桁の架設法
、特にこのプレストレス鋼桁による連結桁の架設法に関
するものである。
[Detailed Description of the Invention] The present invention relates to a method for constructing a prestressed steel girder when constructing a bridge using a prestressed steel girder, commonly called a prestressed steel girder, and particularly to a method for constructing a connecting girder using the prestressed steel girder. It is.

橋梁用架設桁として、鋼桁に予め前たわみ荷重を与えて
おいて、引張側となる下フランジに該下フランジを包む
ようなコンクリートを打設し、このコンクリートの硬化
後前たわみ荷重を解除して鋼桁の復元力により下フラン
ジコンクリートにプレストレス応力を導入するようにし
た通称プレビームと称されるプレストレス鋼桁は既に公
知である(特公昭33−10424号)。
As a bridge construction girder, a forward deflection load is applied to the steel girder in advance, concrete is placed around the lower flange that will be the tension side, and the forward deflection load is released after the concrete hardens. A prestressed steel girder commonly referred to as a pre-beam is already known (Japanese Patent Publication No. 33-10424), which introduces prestress stress into the lower flange concrete by the restoring force of the steel girder.

このようなプレストレス鋼桁を現場において架設したの
ちウェブコンクリート及び床版コンクリートの打設を行
って鋼桁を完全にコンクリートにより被覆した桁はプレ
ビーム合成桁と称されている。
A girder in which such a prestressed steel girder is erected on site and then web concrete and slab concrete are placed to completely cover the steel girder with concrete is called a pre-beam composite girder.

このプレビーム合成桁は下フランジコンクリートと床版
コンクリートとが鋼桁と台底されているために曲げ剛度
が大きくなり、通常の合成桁よりも桁高を低くすること
ができるという点で、桁高製限を受けるような橋梁の施
工に対しては極めて有利である。
This pre-beam composite girder has a high bending stiffness because the lower flange concrete and deck concrete are attached to the steel girder, and the girder height can be lower than that of a normal composite girder. This is extremely advantageous for construction of bridges that are subject to production limits.

また鋼桁自体が露出していないために塗装等の維持管理
が不要であること、騒音が生じないこと、耐火性を有す
ることなどの利点を有する。
Additionally, since the steel girder itself is not exposed, it has the advantage of not requiring maintenance such as painting, not generating noise, and being fire resistant.

このような長所をもつプレビーム合成桁は、構成要素と
しての鋼桁が予め下フランジにプレストレスコンクリー
トが付は加えられた形で形成されているために、鋼桁相
互を一体に連結する場合の処理構造等に問題があり、従
来では多く単純支持型式の橋梁に利用されるのが通例で
あった。
The pre-beam composite girder has such advantages because the steel girder as a component is formed with prestressed concrete added to the lower flange in advance, so it is difficult to connect the steel girders together. Due to problems with the processing structure, etc., it has traditionally been used for simply supported type bridges.

しかし乍らプレビーム合成桁もプレストレス鋼桁の連結
構造の問題点が解決されて連結桁型式への応用が可能と
なれば、本来のプレビーム合55tlr6をもつ有利さ
を耐震性、車輛走行性等の点で有利な連結桁型式の橋橋
梁に結びつげることができ、プレビーム合成桁の利用範
囲を一層拡大することができる。
However, if the problems with the prestressed steel girder connection structure are solved and it becomes possible to apply the pre-beam composite girder to a connected girder type, the advantages of the original pre-beam composite girder of 55 tlr6 will be improved in terms of earthquake resistance, vehicle running properties, etc. It can be connected to a bridge of the connecting girder type which is advantageous in terms of this, and the range of use of the pre-beam composite girder can be further expanded.

本発明は上記のような目的のもとに開発されたものであ
り、複数のプレストレス鋼桁の桁端を互に掛は違い構造
により連接して最終的な単一の中間支点前により支持さ
せ、この状態でまず中間支点部分近を残した径間部に床
版コンクリートを打設して支配的な死荷重は単純桁系に
より受けもたせ、その後左右の鋼桁露出部分をボルト等
により連結して該連結部の床版コンクリート打設を行う
と共に下フランジコンクリート部の境界面を接着剤によ
り連結することにより、地覆、高欄、舗装等の小さな後
死荷重及び車輛等の活荷重は連続桁系により受けもたせ
るようにしたことを特徴とするプレストレス鋼桁による
連結桁の架設法を提供しようとするものである。
The present invention was developed based on the above-mentioned purpose, and the girder ends of a plurality of prestressed steel girders are connected by a structure that is different from each other and supported by a final single intermediate support. In this state, first concrete slabs were poured in the span area that remained near the intermediate supporting point, and the dominant dead load was borne by the simple girder system, and then the exposed parts of the left and right steel girders were connected using bolts, etc. By pouring concrete for the connecting section and connecting the boundary surface of the lower flange concrete section with adhesive, small dead loads such as ground cover, handrails, pavement, etc. and live loads of vehicles, etc. can be continuously reduced. The object of the present invention is to provide a method for constructing a connecting girder using prestressed steel girders, which is characterized by being supported by a girder system.

次に本発明に係る架設法を図示の実施例により詳記すれ
ば、第1図は本架設法に用いるプレストレス鋼桁の桁端
の構造を示す斜視図であり、aは一方の鋼桁11の右端
、bは他方の鋼桁12の左端を示している。
Next, the construction method according to the present invention will be described in detail with reference to illustrated embodiments. FIG. 11, and b indicates the left end of the other steel girder 12.

鋼桁11の桁端はウェブ21の半部の高さ程度の部分を
上7ランジ31を含むようにL字形に切欠して、この切
欠面とウェブ21の先端面とには夫々ウェブ2.と直交
する内奥垂直端面板4.と水平端面板4□及び先端垂直
端面板43とが溶接されている。
The girder end of the steel girder 11 is cut out in an L shape so as to include the upper 7 langes 31 at a portion approximately half the height of the web 21, and a web 2. Inner vertical end plate perpendicular to 4. The horizontal end plate 4□ and the vertical end plate 43 are welded together.

また水平端面板42の中間部と下フランジ51との間に
は補剛板6、が設げられており、この補剛板6□の設け
られた位置の水平端面板42の中央部には支承ピン7が
突設されている。
Further, a stiffening plate 6 is provided between the middle part of the horizontal end plate 42 and the lower flange 51, and the center part of the horizontal end plate 42 at the position where the stiffening plate 6□ is provided is A support pin 7 is provided protrudingly.

一方鋼桁12の桁端はウェブ22の半部の高さ程度の部
分を下7ランジ5□を含むように逆り字形に切欠して、
この切欠崩とウェブ2□の先端面とには夫々ウェブ22
と直交する内奥垂直端面板401と水平端面板402
及び先端垂直端面板403とが溶接され、また水平端面
板402の中間部と上7ランジ3□との間には補剛板6
2が設けられている。
On the other hand, the girder end of the steel girder 12 is cut out in an inverted shape so as to include the lower 7 langes 5□ at a portion about the height of half of the web 22.
The web 22 is located between the notch and the end surface of the web 2□.
An inner vertical end plate 401 and a horizontal end plate 402 perpendicular to
and the vertical end plate 403 are welded together, and a stiffening plate 6 is welded between the intermediate part of the horizontal end plate 402 and the upper 7 langes 3□.
2 is provided.

コレらの鋼桁11.1□は図示しないが、いずれも前た
わみ曲げ荷重を与えられた状態で引張側となる下フラン
ジ5□ 、5□にコンクリート8□8□が打設され、こ
のコンクリートの硬化後前たわみ荷重を解除することに
より下フランジコンクリート8□ 、82にプレストレ
ス応力が与えられた状態となっている。
Although these steel girders 11.1□ are not shown, concrete 8□8□ is placed on the lower flanges 5□ and 5□, which are on the tensile side, when a forward bending load is applied. By releasing the front deflection load after curing, prestress stress is applied to the lower flange concrete 8□, 82.

上記のプレストレス鋼桁の架設は、第2図a乃至eに示
す順序により行われる。
The erection of the prestressed steel girders described above is carried out in the order shown in FIGS. 2a to 2e.

即ち第2図aに示す如く所定位置に中間支点前10が据
付けられたのち前前記プレストレス鋼桁1□を一方の沓
9□と中間支点前10とによって架設する。
That is, as shown in FIG. 2A, after the intermediate fulcrum front 10 is installed at a predetermined position, the front prestressed steel girder 1□ is erected by one shoe 9□ and the intermediate fulcrum front 10.

この架設の段階でプレストレス鋼桁11にはウェブ21
の両側に第1図に示すように端部を除いてウェブコンク
リート111が設けられているが、このウェブコンクリ
ート111は後の工程としての床版コンクリート13、
.132の打設と同時に行ってもよい。
At this stage of erection, the web 21 is attached to the prestressed steel girder 11.
As shown in FIG. 1, web concrete 111 is provided on both sides of the concrete bar 111 except for the ends.
.. This may be done simultaneously with the pouring of 132.

沓9□と10とによりプレストレス鋼桁1□が架設され
たのち、第2図す及び第3図に示す如くこの鋼桁1.に
おける桁欠切端部4の支承ピン7と他方の沓92との間
に一方のプレストレス鋼桁1□を架設する。
After the prestressed steel girder 1□ is erected by the shoes 9□ and 10, this steel girder 1. One prestressed steel girder 1 □ is constructed between the support pin 7 of the girder cutout end 4 and the other foot 92 in the girder.

この鋼桁12は第1図すに示す桁切欠端部40の水平端
面40□が既架設桁1□における支承ピン7により支持
されるように架設される。
This steel girder 12 is constructed so that the horizontal end surface 40□ of the girder notch end 40 shown in FIG.

またこQ鋼桁12には前記鋼桁1□と同様に端部40を
除いてウェブ22にコンクリート112が予め打設され
ている。
Further, in this Q steel girder 12, concrete 112 is placed in advance on the web 22 except for the end portion 40, similar to the steel girder 1□.

次に第2図Cに示す如く両鋼桁11.1□における桁切
欠端部4,40の水平端面4□ と402とをボルト1
2の仮締めにより連接すると共に、両鋼桁11 .12
における桁切欠端部4,40のある中間支点部分を残し
た部分の上フランジ3□ 、32に床版コンクリート1
31.132を打設し、この床版コンクリート13□
、132をプレストレス鋼桁1□ 、12と台底させて
径間部にプレビーム合成桁を形成する。
Next, as shown in FIG.
At the same time, both steel girders 11. 12
Floor slab concrete 1 is placed on the upper flange 3□, 32 of the part where the intermediate fulcrum part with the girder notch end 4, 40 is left.
31.132 was poured, and this concrete floor slab 13□
, 132 and the prestressed steel girders 1□ and 12 to form a pre-beam composite girder in the span.

なおその際両鋼桁i、、i2のボルト12による連接は
、支承ピン7の支持による両鋼桁のたわみ角度を拘束し
ないように配慮する。
At this time, care is taken to connect both steel girders i, i2 with bolts 12 so as not to restrict the deflection angle of both steel girders due to support of bearing pins 7.

この時点において両鋼桁18,1□における死荷重は単
純桁系により受けもたれていることSなる。
At this point, the dead load on both steel girders 18, 1□ is being borne by the simple girder system.

次にこの状態において第3図に示す如く両鋼桁11゜1
2の桁切欠端部4,40を前記ボルト12の本締めによ
る外、垂直端面板41 と403及び43と40□とを
ボルト14により連結し、更に上フラン3mと3□ と
る立上り連結板15..15□間に挿通したボルト16
によりしっかりと連結して、両鋼桁18,12が連続と
なるようにする。
Next, in this state, as shown in Fig. 3, both steel girders 11°1
In addition to final tightening of the bolts 12, the vertical end plates 41 and 403 and 43 and 40□ are connected by the bolts 14, and the upper flanges 3m and 3□ are connected to the rising connecting plate 15. .. .. Bolt 16 inserted between 15□
Connect more firmly so that both steel girders 18, 12 are continuous.

両鋼桁り、12の連結後は、第2図dに示す如く両鋼桁
11.12における中間支点部分のウェブにコンクリー
ト113及び上フランジに床版コンクリート133の打
設を行う。
After the two steel girders 12 are connected, as shown in FIG. 2d, concrete 113 is poured into the web of the intermediate fulcrum portion of both steel girders 11 and 12, and slab concrete 133 is poured into the upper flange.

尚図示はしないが、この段階で各主桁間を結ぶ中間支点
上横桁コンクリートの打設も合せて行う。
Although not shown in the drawings, at this stage concrete is also placed on the transverse girders above the intermediate supports that connect the main girders.

その後左右側桁10,1□の下フランジコンクリ−ト5
□ 、5□の境界面に接着剤17の注入を行い、該接着
剤17の硬化後において桁は連続桁として架設され、そ
れ以後第2図eに示すように地覆、高欄、舗装等の後死
荷重或は車輛等の活荷重を支えることSなる。
After that, the left and right side girders 10, 1□ lower flange concrete 5
Adhesive 17 is injected into the interface between □ and 5□, and after the adhesive 17 hardens, the girder is erected as a continuous girder. From then on, as shown in Figure 2 e, the girder is constructed as a continuous girder. It supports the dead load afterward or the live load of vehicles, etc.

本発明に係る架設法は上記の工程よりなり、次の如き利
点を有する。
The construction method according to the present invention includes the above steps and has the following advantages.

即ちゴ般の連結桁の施行に際しては、当初左右の桁を単
純桁系として架設する段階で左右の桁の接続端部を2個
の低音により夫々別個に支え、両帝の連結後2個の低音
を撤去して1個の中間支点部に置き換えるという作業を
必要とする。
In other words, when constructing Gohan's connecting girders, at the stage when the left and right girders are initially constructed as a simple girder system, the connecting ends of the left and right girders are supported separately by two basses, and after connecting the two girders, the connecting ends of the left and right girders are supported separately. It is necessary to remove the bass and replace it with one intermediate fulcrum.

これに対し本発明の架設法においては、夫々の鋼桁の接
続端部は一方をL字形切欠部、他方を逆り字形切欠部と
しか、まず一方のL字形切欠端部4を有する方の鋼桁1
1を1個の中間支点部10によって支え、他方の逆り字
形切欠端部40を有する方の鋼桁1□は、中間支点部1
0により支持された既架設桁11のL字形切欠端部4上
に逆り字形切欠端部40が支承ピン7によって支えられ
るようにして架設するため、2本の鋼桁の連結部を支え
る中間支点部10は1個で足りると共に、これを最初か
ら据付けておくことが可能なので、沓移設等の繁雑な作
業を一切必要とせず作業能率の著しい向上を期待できる
On the other hand, in the construction method of the present invention, the connecting ends of each steel girder have an L-shaped notch on one side and an inverted-shaped notch on the other. steel girder 1
1 is supported by one intermediate fulcrum part 10, and the other steel girder 1□ having the inverted-shaped notch end 40 supports the intermediate fulcrum part 1
Since the inverted-shaped notched end 40 is to be constructed on the L-shaped notched end 4 of the existing girder 11 supported by the support pin 7, an intermediate part supporting the connecting part of the two steel girders is installed. Since only one fulcrum part 10 is sufficient and it can be installed from the beginning, there is no need for any complicated work such as relocating the shoe, and a significant improvement in work efficiency can be expected.

しかも両鋼桁11 .12の連結前の荷重に対しては、
一方〇鋼桁11は中間支点部10、他方の鋼桁12は支
承ピン7を中心にしてたわみ角を発生させることになり
、仮架設の段階ではこれらのたわみ角を例等拘束する構
造とはなっていないので、支配的な死荷重は単純桁系に
より受けもたせるという連結桁架設に際しての単純桁系
の機能は忠実に保持されるという利点を有する。
Moreover, both steel girders are 11. For the load before connection of 12,
On the other hand, the steel girder 11 generates a deflection angle around the intermediate fulcrum part 10, and the other steel girder 12 generates a deflection angle around the bearing pin 7. At the stage of temporary erection, it is difficult to construct a structure that restrains these deflection angles, for example. Therefore, the dominant dead load is borne by the simple girder system, which has the advantage of faithfully maintaining the function of the simple girder system when constructing the connected girder.

また両鋼桁1□ 、1□の連結は桁切欠端部4゜40に
おけるボルト接続のため、桁製作誤差、桁架設、誤差を
容易に吸収でき架設、連結作業が著しく容易であると共
に、このボルト接続は水平端面4□ 、40□に対する
ボルト12による連結、垂直端面4□ 、403と43
.4(Lに対するボルト14による連結とを有するた
め、連結架設後に作用する後死荷重、活荷重に対する鋼
桁の曲げや剪断力に充分対処できる。
In addition, since the connection between the two steel girders 1□ and 1□ is made by bolt connection at the girder notch end 4°40, girder manufacturing errors, girder erection errors can be easily absorbed, and the erection and connection work is extremely easy. Bolt connections include horizontal end faces 4□, 40□ with bolts 12, vertical end faces 4□, 403 and 43
.. 4 (connection to L by bolts 14), it can sufficiently cope with bending and shearing force of the steel girder due to dead load and live load that act after the connection is constructed.

更に上7ランジ3□ 。32を連結するボルト16は、
その立上り連結板15□ 、152と共に7ランジカ伝
達及び床版コンクリート133に対するズレ止め機能を
はたすこと工なる。
Further up 7 lunges 3□. The bolt 16 connecting 32 is
Together with the rising connecting plates 15□ and 152, it functions to transmit 7 lances and prevent slipping of the concrete floor slab 133.

しかも本架設法においては複数の鋼桁を桁相互の確実な
連結により連結桁とするため、架設の段階で支配的な死
荷重は単純桁系で受けもたせ、連結後において地覆、高
欄、舗装等の比較的小さな後死荷重及び活荷重を連続桁
系により受けもたせること工なり、中間支点部の負の曲
げモーメントを通常の連続桁より大幅に軽減1でき、こ
の負の曲げモーメントにより生ずる床版引張応力、それ
に伴う床版コンクリートのひg割れを軽減できる。
In addition, in this construction method, multiple steel girders are connected to each other to form a connected girder, so the dominant dead load at the stage of erection is borne by the simple girder system, and after the connection, the ground covering, parapet, pavement, etc. By using a continuous girder system to support relatively small dead loads and live loads such as It can reduce the tensile stress of the slab and the associated cracking of the slab concrete.

またプレビーム合成桁としての利点である低騒音性、維
持管理の容易性、耐卒性を活した状態で連続桁系として
の耐震性、車輛走行性が向上し、モーメントバランスが
良好であるので単純桁より経済的となる等の利点を有す
るものである。
In addition, while taking advantage of the advantages of pre-beam composite girders, such as low noise, ease of maintenance, and anti-gradation, the continuous girder system improves earthquake resistance and vehicle running performance, and has a good moment balance, making it simple. It has advantages such as being more economical than digits.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図a及びbは本発明に係る架設法に用いるプレスト
レス鋼桁の桁端の構造を示す斜視図、第2図a乃至eは
加設工程を説明する側面図、第3図は鋼桁の連結部を示
す拡大側面図、第4図は第2図aにおける■−■線にお
ける断面図、第5図は第2図CにおけるV−V線におけ
る断面図、第6図は第2図dにおけるVl−Vl線にお
ける断面図である。 図において、11.12・・・プレストレス鋼桁、2□
、22・・・ウェブ、30,31・・・上フランジ、4
,40・・・桁切欠端部、51.5□・・・下フランジ
、7・・・支承ピン、8□ 、8□・・・下フランジプ
レストレスコンクリート、10・・・中間支点部、11
1,122 。 113・・・ウェブコンクリート、12,14,16・
・・ボルト、13..13□ 、133・・・床版コン
クリート、11・・・接着剤。
Figures 1 a and b are perspective views showing the structure of the girder end of a prestressed steel girder used in the erection method according to the present invention, Figures 2 a to e are side views illustrating the addition process, and Figure 3 is a 4 is a sectional view taken along the line ■-■ in FIG. 2a, FIG. 5 is a sectional view taken along the line V-V in FIG. 2C, and FIG. It is a sectional view taken along the line Vl-Vl in Figure d. In the figure, 11.12...Prestressed steel girder, 2□
, 22... Web, 30, 31... Upper flange, 4
, 40... Girder notch end, 51.5□... Lower flange, 7... Support pin, 8□, 8□... Lower flange prestressed concrete, 10... Intermediate fulcrum part, 11
1,122. 113...web concrete, 12, 14, 16.
...Bolt, 13. .. 13□, 133...floor slab concrete, 11...adhesive.

Claims (1)

【特許請求の範囲】[Claims] 1 桁端にL字形切欠部を有するプレストレス鋼桁と、
桁端に逆り字形切欠部を有するプレストレス鋼桁とを中
間支点上において前記切欠部の掛は違いにより架設し、
両鋼桁の中間支点部付近を残した夫々の径間部に床版コ
ンクリート等を打設して径間部をプレストレス鋼桁によ
る合成桁とし、その後中間支点上の左右鋼桁切欠部をボ
ルト等により連結して鋼桁を一体に連続せしめ、中間支
点部における残余のコンクリート打設を行うと共に該中
間支点部の左右両桁下フランジコンクリート境界面に接
着剤注入を行うことによってその後に作用する後死荷重
、活荷重等に対して連続桁として荷重を受けもたせるこ
とを特徴とするプレストレス鋼桁による連結桁の架設法
1. A prestressed steel girder having an L-shaped notch at the end of the girder;
A prestressed steel girder having an inverted-shaped notch at the end of the girder is erected on an intermediate support with the hooks of the notch being different,
Concrete slabs, etc., are poured into the spans of both steel girders, leaving the areas near the intermediate supports, and the spans are made into composite girders made of prestressed steel girders.Then, the notches on the left and right steel girders above the intermediate supports are constructed. After connecting the steel girders with bolts, etc., and placing the remaining concrete at the intermediate fulcrum, adhesive is injected into the concrete interface between the lower flange of both the left and right girders at the intermediate fulcrum. A method for constructing connected girders using prestressed steel girders, which is characterized by the ability to receive loads such as dead loads and live loads as continuous girders.
JP9830481A 1981-06-26 1981-06-26 Construction method for connecting girders using prestressed steel girders Expired JPS5851083B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9830481A JPS5851083B2 (en) 1981-06-26 1981-06-26 Construction method for connecting girders using prestressed steel girders

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9830481A JPS5851083B2 (en) 1981-06-26 1981-06-26 Construction method for connecting girders using prestressed steel girders

Publications (2)

Publication Number Publication Date
JPS584005A JPS584005A (en) 1983-01-11
JPS5851083B2 true JPS5851083B2 (en) 1983-11-14

Family

ID=14216179

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9830481A Expired JPS5851083B2 (en) 1981-06-26 1981-06-26 Construction method for connecting girders using prestressed steel girders

Country Status (1)

Country Link
JP (1) JPS5851083B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100517812B1 (en) * 2002-10-24 2005-09-29 동부엔지니어링 주식회사 Protection structure of collapse for gerber truss bridge
KR100458046B1 (en) * 2004-04-01 2004-11-26 (주)에스오씨건설엔지니어링 Struture for continuing intermediate support of compositive girder bridge
JP4866743B2 (en) * 2007-01-09 2012-02-01 アジア航測株式会社 Fall bridge prevention device and Gerber bridge
KR101244403B1 (en) 2010-10-14 2013-03-18 브릿지테크놀러지(주) Prestressed Concrete Beam, connecting structure of the same and method of connecting the same.

Also Published As

Publication number Publication date
JPS584005A (en) 1983-01-11

Similar Documents

Publication Publication Date Title
CN101080534B (en) Manufacturing method for prestressed steel composite girder
KR20030048849A (en) System composed of asymmetric steel section with web opening and concrete
JP3877995B2 (en) How to build a string string bridge
JPH11158812A (en) Hollow slab bridge and method of construction
JPH04228710A (en) Road slab for bridge
JPS5851083B2 (en) Construction method for connecting girders using prestressed steel girders
JPS5834607B2 (en) Erection method of prefabricated prestressed steel girder
JP2838608B2 (en) Connection structure of girder and steel beam
JP2000104219A (en) Construction method of composite truss bridge
JP2004011300A (en) PC composite structure, PC bridge and method for introducing prestress
JP2000038797A (en) Semi-precast floor slab
JPH09221706A (en) Floor slab for road surface and layout method thereof
JP2002275833A (en) Continuous girder method and girder structure for existing bridges
JPH0338245Y2 (en)
JP2910860B2 (en) Partial half PCa board
JPS5832243B2 (en) Continuous type bridge using prestressed steel girders
JPH02311639A (en) Construction of composite floor
JP2004232229A (en) Precast concrete slab
JP2853528B2 (en) Construction method of composite floorboard
JP2000087313A (en) Construction method of composite slab bridge and composite slab bridge
JPH04302607A (en) Composite girder and girder part of bridge beam
JP3189081B2 (en) Manufacturing method of void type full precast two-way slab and void type full precast slab
CN119434513A (en) A kind of local prestressed support-free prefabricated floor and construction method thereof
JPH10227011A (en) Steel formwork with main rebar for bridge slab and method of slab construction of bridge using it
KR100601097B1 (en) Plate girder