JPS5851091B2 - Earth retention shoring method - Google Patents
Earth retention shoring methodInfo
- Publication number
- JPS5851091B2 JPS5851091B2 JP6303579A JP6303579A JPS5851091B2 JP S5851091 B2 JPS5851091 B2 JP S5851091B2 JP 6303579 A JP6303579 A JP 6303579A JP 6303579 A JP6303579 A JP 6303579A JP S5851091 B2 JPS5851091 B2 JP S5851091B2
- Authority
- JP
- Japan
- Prior art keywords
- earth
- earth retaining
- shoring
- retention
- trench
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Description
【発明の詳細な説明】
この発明は溝掘削等の土木建設作業等における土留支保
工法に関するものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to an earth retention shoring method for civil engineering construction work such as trench excavation.
コンクリート管の埋設工事やボックスカルバート埋設工
事等の土木建設作業には溝掘削工事が必要であり、その
掘削した溝には土留支保が必要である。Civil engineering construction work such as concrete pipe burying work and box culvert burying work requires trench excavation work, and the excavated trench requires earth retaining support.
この土留支保のために従来一般に使用されている方法は
、掘削される溝の両側に間隔をおいてレールを配設し、
このレールに土留パネルを支持させ、この土留パネルで
溝の側面を土留めするものである。The conventional method commonly used for this earth retention support is to arrange rails at intervals on both sides of the trench to be excavated.
This rail supports an earth retaining panel, and this earth retaining panel secures the sides of the ditch.
対向するし=−ル間には棒状のサポートを配設してレー
ル間の対向間隔を保持する。A rod-shaped support is disposed between the opposing rails to maintain the opposing spacing between the rails.
溝の側面の土圧は先ず土留パネルに伝達され、土留パネ
ルからレールに伝達され、さらにガイドレールからサポ
ートに伝達されるように構成されている。The earth pressure on the sides of the trench is first transmitted to the earth retaining panel, from the earth retaining panel to the rail, and further from the guide rail to the support.
このような土留支保工法は、土留支保装置自体の組立及
び分解が容易でなく、これが作業の期間を延長させ、工
事費を高騰させるだけでなく、溝掘削の作業が進行する
につれて、溝の深さ方向で土留支保位置が変化する場合
に、これに合わせて土留パネルを変位させる作業が容易
でなく、これも作業期間を延長させる原因となっている
。In this earth retention shoring construction method, the earth retention shoring device itself is not easy to assemble and disassemble, which not only prolongs the work period and increases construction costs, but also increases the depth of the trench as the trench excavation work progresses. When the earth retaining support position changes in the horizontal direction, it is not easy to displace the earth retaining panel in accordance with this change, which also causes an extension of the work period.
この発明は上記の如き事情に鑑みてなされたものであっ
て、土留支保作業を容易かつ迅速に行ない得る土留支保
工法を提供することを目的とするものである。This invention has been made in view of the above-mentioned circumstances, and it is an object of the present invention to provide an earth retention shoring method that allows earth retention shoring work to be carried out easily and quickly.
この目的に対応して、この発明の土留支保工法は、対向
しかつ平行に位置する2枚の土留パネルと4部で一方の
土留パネルに枢着し他端部で他方の土留パネルに枢着し
相互に平行に位置する複数のサポートと及び2枚の土留
パネル間にわたした安全索とを備えた土留支保装置を掘
削途中の溝若しくは掘削した溝内に位置させて溝の土留
めを行なうことを特徴としている。Corresponding to this purpose, the earth retaining shoring method of the present invention consists of two earth retaining panels located opposite and parallel to each other, four parts are pivotally connected to one earth retaining panel, and the other end is pivotally connected to the other earth retaining panel. An earth retaining shoring device equipped with a plurality of supports located parallel to each other and a safety cable stretched between two earth retaining panels is placed in a trench that is being excavated or within an excavated trench to perform earth retaining of the trench. It is characterized by
以下この発明の詳細を一実施例を示す図面について説明
する。The details of this invention will be explained below with reference to the drawings showing one embodiment.
第1図に示す如く、この発明の土留支保工法では土留支
保装置1によって、溝aの側面す、 b’の土留めを行
なう。As shown in FIG. 1, in the earth retaining shoring method of the present invention, earth retaining is carried out on the side surfaces s and b' of the groove a by means of an earth retaining shoring device 1.
土留支保装置1は、第1図、第2図及び第3図に示す如
く、2枚の土留パネル2a、2bと、4本の取付材3a
、3b、3c、3dと、及び4本の交換サポート4a、
4b、4ct 4dと、及び4本の安全索5a、5b、
5c、5dとを備えている。As shown in FIGS. 1, 2, and 3, the earth retaining support device 1 includes two earth retaining panels 2a, 2b and four mounting members 3a.
, 3b, 3c, 3d, and four replacement supports 4a,
4b, 4ct 4d, and four safety ropes 5a, 5b,
5c and 5d.
土留パネル2a、2bは掘削する溝の両側に位置し、相
互に平行にかつ対向して位置すべきものである。The retaining panels 2a, 2b are located on both sides of the trench to be excavated, and should be located parallel to and opposite each other.
取付部材3a、3cは垂直に位置しかつ土留パネルの幅
方向(溝の長さ方向)に間隔を置いて土留パネル2aの
内側面に固着されている。The attachment members 3a and 3c are vertically located and fixed to the inner surface of the retaining panel 2a at intervals in the width direction of the retaining panel (the length direction of the groove).
一方、取付部材3b及び3dは垂直に位置しかつ土留パ
ネルの幅方向に間隔を置いて土留パネル2bの内側面に
固着している。On the other hand, the attachment members 3b and 3d are vertically located and fixed to the inner surface of the retaining panel 2b at intervals in the width direction of the retaining panel.
取付部材3 a p3b、3c及び3dはそれぞれ溝型
断面を有し、それぞれのウェブで土留パネルに固着して
いる。The attachment members 3 a p 3 b, 3 c and 3 d each have a channel-shaped cross section and are fixed to the retaining panel by their respective webs.
取付部材3a及び3cの間隔と取付部材3b及び3dの
間隔とは等しく、取付部材3aと3bとは対向し、取付
部材3cと3dとは対向している。The spacing between the mounting members 3a and 3c is equal to the spacing between the mounting members 3b and 3d, and the mounting members 3a and 3b face each other, and the mounting members 3c and 3d face each other.
4本の交換サポート4a、4b、4c、及び4dはそれ
ぞれ剛性棒状若しくは筒状の本体6と本体6の両端に取
り付けられている先端金具7とから成り、先端金具7は
取付部材3a〜3dに固着若しくはピンを介して枢着す
る。The four replacement supports 4a, 4b, 4c, and 4d each consist of a rigid rod-shaped or cylindrical main body 6 and a tip fitting 7 attached to both ends of the main body 6, and the tip fitting 7 is attached to the mounting members 3a to 3d. Pivotally attached by fixation or pin.
このサポー)4a〜4dは別の長さのものと取換えるこ
とによりサポー)4a〜4dの全体の長さを任意に換え
ることができ、したがって土留パネル2a、2bの対向
間隔を調整することができる。By replacing these supports 4a to 4d with ones of different length, the overall length of supports 4a to 4d can be changed arbitrarily, and therefore the spacing between the earth retaining panels 2a and 2b can be adjusted. can.
一方、それぞれの取付部材3a〜3dにはブラケッ)9
a、9bが設けられており、このブラケツ)9a、9b
に安全索5a〜5dのいずれかの先端が係止する。On the other hand, each mounting member 3a to 3d has a bracket) 9.
a, 9b are provided, and this bracket) 9a, 9b
The tip of any one of the safety cables 5a to 5d is locked to.
安全索はそれぞれ紐状の本体11と本体11の一端に取
り付けられた連続する複数リンクの鎖12と、及び本体
11の他端に取り付けられた係止金具13とからなって
いる。Each safety rope is composed of a string-like main body 11, a chain 12 of a plurality of continuous links attached to one end of the main body 11, and a locking metal fitting 13 attached to the other end of the main body 11.
安全索5a〜5dは対向する取付部材3a、3dの間に
上部のブラケッ)9aと下部のブラケツ)9bとに斜め
にわたされており、安全索の一端の鎖12は取付部材の
上部のブラケッ)9aに係止し、他端の係止金具13は
対向する取付部材の下部のブラケッ)9bに係止する。The safety cables 5a to 5d are passed diagonally between the upper bracket (9a) and the lower bracket (9b) between the opposing mounting members 3a and 3d, and the chain 12 at one end of the safety cable is connected to the upper bracket (9a) of the mounting member. ) 9a, and the locking metal fitting 13 at the other end is locked to the lower bracket () 9b of the opposing mounting member.
ブラケツ)9aに係止する鎖12のリンクを選択するこ
とにより安全索の長さを調整することができる。The length of the safety rope can be adjusted by selecting the link of the chain 12 that is engaged with the bracket 9a.
このように構成された土留支保装置1を組立てる場合に
は、筐ず土留パネル2aの内側(対向面)を上向きに置
き、サポー)4a〜4d及び安全索5a〜5dを取り付
ける。When assembling the earth retaining support device 1 configured in this way, the inner side (opposing surface) of the earth retaining panel 2a is placed facing upward, and the supports 4a to 4d and safety cables 5a to 5d are attached.
次にこの土留パネル2aの内側を下向きにして平吊りで
下側の他方の土留パネル2bに接近させサポートを土留
パネル2bの取付部材に連結しかつ安全索も取付部材に
係止する。Next, this retaining panel 2a is hung flat with the inside facing downward to approach the other lower retaining panel 2b, and the support is connected to the mounting member of the retaining panel 2b, and the safety cable is also locked to the mounting member.
このようにすれば土留パネル2a、2bを含む土留支保
装置は箱形になり、安全に自立する土留支保装置となる
。In this way, the earth retaining shoring device including the earth retaining panels 2a and 2b becomes box-shaped and becomes a safe self-supporting earth retaining shoring device.
こうして組立が完了した土留支保装置はその場で自立さ
せるか或いは掘削した溝内に吊金具を使用して吊込み自
立させる。The earth retaining support device, which has been assembled in this way, can be made to stand on its own on the spot, or it can be hung into an excavated trench using a hanging fitting to make it stand on its own.
この発明の土留支保工法は、前記の如く構成されかつ組
立てられた土留支保装置1を使用する。The earth retention shoring method of the present invention uses the earth retention shoring device 1 constructed and assembled as described above.
昔ず地質の良好な場所では土留支保装置1を組立てた後
、予め掘削した溝の中に落し込むのを原則とする。In principle, in places with good geology, the earth retaining support device 1 is assembled and then dropped into a pre-excavated trench.
位置ぎめと安定のためにパネルプロテクターを使用して
若干の圧入を行ない左右の高低差はできるだけ小さくす
るようにする。For positioning and stability, use a panel protector and press-fit it slightly to minimize the difference in height between the left and right sides.
この状態で土留支保装置により土留めを行ない溝の掘削
を行なう。In this state, earth retaining equipment is used to retain the earth and the trench is excavated.
諸要箇所の溝掘削工事が終了した後に配管、配線を行な
い、さらに埋立てを行なった後に土留支保装置を引き抜
くことになる。After the trench excavation work at various important points is completed, piping and wiring will be installed, and after the land is filled, the earth retaining support device will be pulled out.
この引き抜きにはパネル吊金具を4点にかけて土留パネ
ルを両側平行に引き抜く。For this purpose, hang the panel hangers at four points and pull out the retaining panel parallel to both sides.
土留パネルを抜き終る手前で安全索の係止部の1箇所を
はずしてから反対側の吊金具をはずしてその1″1!吊
り上げると第4図に示す如く折り畳み姿となる。Before removing the earth retaining panel, remove one of the locking parts of the safety cable, remove the hanging fitting on the opposite side, and lift it up 1"1! to form a folded position as shown in Figure 4.
との支保装置の他の場所への移動はその移動距離が短距
離の場合には第4図に示す折り畳んだ状態の11運搬す
ればよいし、また運搬距離が遠距離の場合には土留パネ
ル、サポート、安全索などを分解して運搬することにな
る。To move the shoring device to another location, if the distance to be moved is short, it can be transported in the folded state shown in Figure 4, or if the distance to be transported is long, it can be transported by using the earth retaining panel. , supports, safety ropes, etc. will be disassembled and transported.
なお、土留支保装置1の使用中は、安全のために隣り合
う土留支保装置を連結する必要がある場合には、第3図
に示す如く、接続レール14を清除に立設し、この接続
レール14によって隣り合う土留パネルを連結し若しく
は端部の位置決めをする。During use of the earth retention shoring device 1, if it is necessary to connect adjacent earth retention shoring devices for safety, as shown in Fig. 3, the connecting rail 14 is cleared and installed, 14 to connect adjacent retaining panels or to position the ends.
次に地質が不安定な場所での溝掘削の土留めの場合は第
5図に示す通りにする。Next, in the case of earth retention for trench excavation in places with unstable geology, do as shown in Figure 5.
1ず、溝a/を地部れの恐れのない深さ捷で掘削し、こ
の溝a/に組立が完了した土留支保装置1をたて込み、
次に溝a′を掘り進めて土留パネル2aをh点1で押し
下げ、さらに溝a/を掘り進めて土留パネル2bをi点
筐で押し下げ、このような操作を繰返して、土留パネル
2aをj点に、土留パネル2bをに点に、とそれぞれ交
互に押し下げるっこのように両側の土留パネル2a、2
bを片側ずつ取付部材3a、3c若しくは取付部材3b
、3dと交換サポート4a、4b、4c及び4dとの・
枢着点を中心として揺動させて交互に押し込むことによ
り、最適な土留支保点での土留支保を行なうことになる
。1. First, excavate a groove a/ to a depth that does not cause the risk of soil collapse, and erect the assembled earth retaining support device 1 into this groove a/.
Next, dig the groove a' and push down the earth retaining panel 2a at point h 1. Further dig the groove a/ and push down the earth retaining panel 2b at point i. Repeat this operation to lower the earth retaining panel 2a to j. The earth retaining panels 2a, 2 on both sides are pressed down alternately, like a bracket.
b on each side of the mounting members 3a, 3c or mounting member 3b.
, 3d and exchange support 4a, 4b, 4c and 4d.
By swinging around the pivot point and pushing in alternately, earth retention can be supported at the optimum earth retention support point.
この場合、安全索のチェーンを1リンクまたは2リンク
弛めることにより押込み動作を容易に行なうことができ
る。In this case, the pushing operation can be easily performed by loosening one or two links of the chain of the safety rope.
以上の説明から明らかな通り、この発明によれば、土留
支保の最適地点において土留支保作業を容易かつ迅速に
行なうことが可能な土留支保工法を得ることができる。As is clear from the above description, according to the present invention, it is possible to obtain an earth retention shoring construction method that allows earth retention shoring work to be easily and quickly performed at the optimum earth retention shoring location.
第1図はこの発明の一実施例に係る土留支保工法を示す
正面図、第2図は第1図に示す土留支保装置の側面図、
第3図は第1図に示す土留支保装置の平面図、第4図は
土留支保装置を折り畳んだ状態を示す正面図、及び第5
図はこの発明の他の実施例に係る土留支保工法を正す正
面説明図である。
1・・・・・・土留支保装置、2a、2b・・・・・・
土留パネル、3a〜3d・・・・・・取付部材、4a〜
4d・・・・・・サポート、5a〜5d・・・・・・安
全索、8・・・・・・ピン、9a、9b・・・・・・ブ
ラケット、14・・・・・接続レール。FIG. 1 is a front view showing an earth retaining shoring method according to an embodiment of the present invention, FIG. 2 is a side view of the earth retaining shoring device shown in FIG. 1,
FIG. 3 is a plan view of the earth retention shoring device shown in FIG. 1, FIG. 4 is a front view showing the earth retention shoring device in a folded state, and
The figure is a front explanatory view for correcting the earth retaining shoring method according to another embodiment of the present invention. 1...Earth retention support device, 2a, 2b...
Earth retaining panel, 3a-3d...Mounting member, 4a-
4d...Support, 5a-5d...Safety rope, 8...Pin, 9a, 9b...Bracket, 14...Connection rail.
Claims (1)
部で一方の前記土留パネルに枢着し他端部で他方の前記
土留パネルに枢着し相互に平行に位置する複数のサポー
トと及び2枚の前記土留パネル間にわたした安全索とを
備えた土留支保装置を掘削途中の溝若しくは掘削した溝
内に位置させて前記溝の土留めを行なうことを特徴とす
る土留支保工法。 2 前記安全索の長さを調節し前記安全索が許容する範
囲内で前記溝の掘削に応じて前記2枚の土留パネルを交
互に前記溝の深さ方向に移動させて土留めを行なうこと
を特徴とする特許請求の範囲第1項記載の土留支保工法
。[Scope of Claims] 1. Two earth retaining panels facing each other and located in parallel, one end of which is pivotally connected to one of the earth retaining panels, the other end of which is pivotally connected to the other earth retaining panel, and located parallel to each other. The method is characterized in that an earth retaining shoring device equipped with a plurality of supports and a safety rope stretched between two of the earth retaining panels is positioned in a trench in the middle of excavation or in an excavated trench to retain earth in the trench. Earth retention shoring method. 2 Adjusting the length of the safety rope and moving the two earth retaining panels alternately in the depth direction of the groove according to the excavation of the groove within the range allowed by the safety rope to perform earth retaining. An earth retention shoring method according to claim 1, characterized in that:
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP6303579A JPS5851091B2 (en) | 1979-05-22 | 1979-05-22 | Earth retention shoring method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP6303579A JPS5851091B2 (en) | 1979-05-22 | 1979-05-22 | Earth retention shoring method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS55155826A JPS55155826A (en) | 1980-12-04 |
| JPS5851091B2 true JPS5851091B2 (en) | 1983-11-14 |
Family
ID=13217660
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP6303579A Expired JPS5851091B2 (en) | 1979-05-22 | 1979-05-22 | Earth retention shoring method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS5851091B2 (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP4802011B2 (en) * | 2006-03-01 | 2011-10-26 | 英子 小西 | Tightening device for kimono strips |
-
1979
- 1979-05-22 JP JP6303579A patent/JPS5851091B2/en not_active Expired
Also Published As
| Publication number | Publication date |
|---|---|
| JPS55155826A (en) | 1980-12-04 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| RU2149946C1 (en) | Framed bridge support | |
| JPS5851091B2 (en) | Earth retention shoring method | |
| JPS5873623A (en) | Sheathing work for excavated trench and sheeting therefor | |
| JPS6088725A (en) | Sheathing work of excavated trench | |
| JP2000257069A (en) | Earth retaining and earth retaining construction method | |
| JP2654719B2 (en) | Simple underground continuous wall method | |
| JP3250324U (en) | Sheet Pile Wall | |
| JPH0989159A (en) | Pipe laying method, support work and support assembly | |
| JP3637423B2 (en) | Cutting method | |
| JP3093937B2 (en) | Pipe laying method | |
| JP3003233U (en) | Soil retaining device | |
| JPH08302691A (en) | Sheathing unit for laying of underground buried pipe | |
| JPS5842508Y2 (en) | Crosspiece support device for earthworks | |
| JPS594723A (en) | Sheathing and timbering work for excavated trench | |
| JPS6088724A (en) | Sheathing work of excavated trench | |
| JPS6027157Y2 (en) | Equipment for pulling out earth retaining structures, etc. in excavated trenches | |
| JPH07300856A (en) | Earth retaining device | |
| JPH0346612B2 (en) | ||
| JPH07189254A (en) | Soil retaining device | |
| JPH0726561A (en) | Soil retaining device | |
| JPH0529248Y2 (en) | ||
| JP2592901B2 (en) | How to put a long pipe into the groove in sheet pile construction | |
| JPH0893967A (en) | Carrying-in device for cable protecting pipe in conduit line laying | |
| JP2018003349A (en) | Hanging-type scaffold device and construction pier building method using the same | |
| JP3054071B2 (en) | Method and apparatus for erecting steel for underground continuous wall |