JPS5854210B2 - Chichiyurenzokuhekisekouhou - Google Patents
ChichiyurenzokuhekisekouhouInfo
- Publication number
- JPS5854210B2 JPS5854210B2 JP48091196A JP9119673A JPS5854210B2 JP S5854210 B2 JPS5854210 B2 JP S5854210B2 JP 48091196 A JP48091196 A JP 48091196A JP 9119673 A JP9119673 A JP 9119673A JP S5854210 B2 JPS5854210 B2 JP S5854210B2
- Authority
- JP
- Japan
- Prior art keywords
- sheet
- water
- reinforcing bar
- concrete
- attached
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Landscapes
- Underground Or Underwater Handling Of Building Materials (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
- Piles And Underground Anchors (AREA)
Description
【発明の詳細な説明】
この発明は地中連続壁の施工法に関するもので、その目
的は地下水の影響を受けることなく容易にしかも完全な
地中壁を構築することができる施工法を提供することに
ある。[Detailed Description of the Invention] This invention relates to a construction method for an underground continuous wall, and its purpose is to provide a construction method that can easily and completely construct an underground wall without being affected by groundwater. There is a particular thing.
一般に地中に連続壁を施工する場合には施工位置を所定
深さまで掘削し、配筋をおこない、コンクリートを充填
して構築されるが、しばしかコンクリートが地下水に流
水して強度上問題があった。Generally, when constructing a continuous wall underground, the construction site is excavated to a predetermined depth, reinforcement is placed, and then filled with concrete. Ta.
この発明は、前記従来の問題点に対処するために提案さ
れたものである。This invention has been proposed to address the above-mentioned conventional problems.
以下図示する実施例により説明すると、掘削孔内に垂直
に配設された縦筋1の外側に格子状鉄筋網2を添接する
。To describe the embodiment shown below, a lattice-like reinforcing bar network 2 is attached to the outside of a vertical bar 1 vertically disposed in an excavated hole.
そして更にこの鉄筋網2の外側を被覆するように、比較
曲目の粗い透水性布よりなるシート3を取付ける。Further, a sheet 3 made of a water-permeable cloth with a relatively coarse curve is attached so as to cover the outside of the reinforcing bar net 2.
次いでシート3内に浸透してくる地下水等の水を汲み上
げ、しかる後シート3内にコンクリートを打設する。Next, water such as groundwater that has permeated into the sheet 3 is pumped up, and then concrete is poured into the sheet 3.
この際シート3は透水性布からなるので、シート3内に
土砂が侵入するのを防止できる。At this time, since the sheet 3 is made of water-permeable cloth, it is possible to prevent dirt from entering the sheet 3.
以上のような操作を順次繰り返し、所定の長さ連続壁を
構築するものである。The above operations are repeated in sequence to construct a continuous wall of a predetermined length.
この発明は以上の構成からなり、シートは透水性の商よ
りなるので、打設されたコンクリートが流出することな
く、僅かにその水分が外部に浸透し、掘削孔壁にシート
が密着することにより、孔壁の崩落を防止しながら施工
することができる。This invention has the above-mentioned structure, and since the sheet is made of water-permeable material, the poured concrete does not flow out, but a slight amount of water permeates to the outside, and the sheet adheres to the wall of the excavation hole. , construction can be carried out while preventing the hole wall from collapsing.
またシート内には地下水等の水が浸透してくるが、スラ
イムは入ってこないので、水を汲み上げることによりス
ライムの影響を受けずに完全にドライな状態でコンクリ
ート打設を行なうことができ、また水を汲み上げること
なく水中コンクリート打設も可能である。In addition, although water such as groundwater permeates into the sheet, slime does not enter the sheet, so by pumping up the water, concrete can be placed in a completely dry state without being affected by slime. It is also possible to place concrete underwater without pumping up water.
そして水を汲み上げる際にシートは掘削孔壁の土庄を受
けるが、鉄筋網、および縦筋によって補強されているの
で、土庄に充分耐えうる。When pumping up water, the sheet is exposed to the soil of the borehole wall, but since it is reinforced with a reinforcing bar net and vertical bars, it can withstand the soil.
図面はこの発明の実施例を示すもので、第1図は横断面
図、第2図は縦断面図である。
1・・・・・・縦筋、2・・・・・・鉄筋網、3・・・
・・・シート。The drawings show an embodiment of the invention, and FIG. 1 is a cross-sectional view, and FIG. 2 is a vertical cross-sectional view. 1... Vertical reinforcement, 2... Rebar network, 3...
...Sheet.
Claims (1)
、さらにこの鉄筋網の外側を被覆するようにスライムが
侵入できない透水性布からなるシートを取付け、前記シ
ート内にコンクリートを充填することを特徴とする地中
連続壁施工法。1. A reinforcing bar net is attached to the outer periphery of the vertical bars placed in the excavation hole, and a sheet made of water-permeable cloth that prevents slime from penetrating is attached to cover the outside of this reinforcing bar net, and concrete is placed inside the sheet. An underground continuous wall construction method characterized by filling.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP48091196A JPS5854210B2 (en) | 1973-08-14 | 1973-08-14 | Chichiyurenzokuhekisekouhou |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP48091196A JPS5854210B2 (en) | 1973-08-14 | 1973-08-14 | Chichiyurenzokuhekisekouhou |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS5038914A JPS5038914A (en) | 1975-04-10 |
| JPS5854210B2 true JPS5854210B2 (en) | 1983-12-03 |
Family
ID=14019678
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP48091196A Expired JPS5854210B2 (en) | 1973-08-14 | 1973-08-14 | Chichiyurenzokuhekisekouhou |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS5854210B2 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS6024212U (en) * | 1983-07-22 | 1985-02-19 | 株式会社資生堂 | Container for viscous liquid with application part inserted |
Families Citing this family (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5397205A (en) * | 1977-02-04 | 1978-08-25 | Hazama Gumi | Method of placing dry concrete under water |
| JPS5436962U (en) * | 1977-08-19 | 1979-03-10 | ||
| JPS55101935U (en) * | 1979-01-08 | 1980-07-16 | ||
| JPS58180923U (en) * | 1982-05-26 | 1983-12-02 | 理研興業株式会社 | Waterway with anti-surfacing device |
| JPS6319326A (en) * | 1986-07-11 | 1988-01-27 | リン ジユエイ ジエ | Pit foundation discharge soil compacting construction method |
| JPH0247436A (en) * | 1988-08-10 | 1990-02-16 | Marutaka Concrete Kogyo Kk | Concrete block laid in water channel |
| JPH0258645A (en) * | 1988-08-24 | 1990-02-27 | Marutaka Concrete Kogyo Kk | Concrete block laid on waterway |
| JPH0538082U (en) * | 1991-10-18 | 1993-05-21 | 鳥居化成株式会社 | U-shaped groove made of synthetic resin |
| JPH061480U (en) * | 1992-06-17 | 1994-01-11 | キョーセー株式会社 | Wastewater treatment ditch |
| JPH06193125A (en) * | 1992-12-25 | 1994-07-12 | Daikaron Kako:Kk | Preventing device for u-shaped gutter from rising |
| JP6392156B2 (en) * | 2015-03-30 | 2018-09-19 | 中日本ハイウェイ・エンジニアリング東京株式会社 | U-shaped groove |
Family Cites Families (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR1221687A (en) * | 1959-01-05 | 1960-06-03 | Improved method of making piles cast in the ground | |
| FR1311040A (en) * | 1962-01-19 | 1962-11-30 | Nibler G M B H | Method of implanting building elements, by in situ concreting, or the like, in stagnant or slow-flowing liquids, and formwork usable for this implantation |
| FR1339485A (en) * | 1962-11-27 | 1963-10-04 | Wests Piling Construct | Pile improvements |
-
1973
- 1973-08-14 JP JP48091196A patent/JPS5854210B2/en not_active Expired
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS6024212U (en) * | 1983-07-22 | 1985-02-19 | 株式会社資生堂 | Container for viscous liquid with application part inserted |
Also Published As
| Publication number | Publication date |
|---|---|
| JPS5038914A (en) | 1975-04-10 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPS5854210B2 (en) | Chichiyurenzokuhekisekouhou | |
| CN107119695A (en) | Operation frame body for canceling basement exterior wall backfill and construction method | |
| US3396546A (en) | Method of producing concrete piles for foundations | |
| JP2619704B2 (en) | Underground structure lifting prevention method | |
| JP3648299B2 (en) | Consolidation promotion method for soft ground | |
| JPS6119771B2 (en) | ||
| JPS5936058B2 (en) | How to construct a structure using underground continuous walls | |
| JP2506398B2 (en) | Construction method of cast-in-place concrete pile | |
| JPH1030228A (en) | Construction method of underground continuous wall and box type steel | |
| JP2588075B2 (en) | Underground building construction method | |
| JPH06240656A (en) | Groundwater reduction method | |
| JPS583092B2 (en) | Concrete | |
| JPS61254716A (en) | Setting of in-place concrete pile | |
| JPH03233018A (en) | Steel tubular concrete pile | |
| JPH0317314A (en) | Execution of underground continuous wall | |
| JPS6350491B2 (en) | ||
| JPH073781A (en) | Construction method of foundation footing on cast-in-place concrete pile head. | |
| JPS62242020A (en) | Method for constructing underground structure | |
| JPH0433326B2 (en) | ||
| JPH0572481B2 (en) | ||
| JPH0517952A (en) | Constructing method for underground wall | |
| JPS637416A (en) | Construction of hollow concrete structure under ground | |
| RU29734U1 (en) | Concrete Dam Drainage Device | |
| JPH10140557A (en) | Construction method of cast-in-place continuous wall with hollow part | |
| JPH0699940B2 (en) | Method of constructing underground skeleton and formwork for underground skeleton construction |