JPS5915000B2 - Computer-based load runback control method for power generation plants - Google Patents
[go: Go Back, main page]

JPS5915000B2 - Computer-based load runback control method for power generation plants - Google Patents

Computer-based load runback control method for power generation plants

Info

Publication number
JPS5915000B2
JPS5915000B2 JP51090843A JP9084376A JPS5915000B2 JP S5915000 B2 JPS5915000 B2 JP S5915000B2 JP 51090843 A JP51090843 A JP 51090843A JP 9084376 A JP9084376 A JP 9084376A JP S5915000 B2 JPS5915000 B2 JP S5915000B2
Authority
JP
Japan
Prior art keywords
load
runback
reduction rate
power generation
control method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP51090843A
Other languages
Japanese (ja)
Other versions
JPS5316823A (en
Inventor
義彦 戸田
進 増澤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Tokyo Shibaura Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Shibaura Electric Co Ltd filed Critical Tokyo Shibaura Electric Co Ltd
Priority to JP51090843A priority Critical patent/JPS5915000B2/en
Publication of JPS5316823A publication Critical patent/JPS5316823A/en
Publication of JPS5915000B2 publication Critical patent/JPS5915000B2/en
Expired legal-status Critical Current

Links

Landscapes

  • Protection Of Generators And Motors (AREA)
  • Control Of Eletrric Generators (AREA)

Description

【発明の詳細な説明】 本発明は計算機による負荷ランバック制御方法に係わり
、特に負荷ランバック進行過程の最適制35御値の決定
及び制御結果の適否を判定する方法に関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a load runback control method using a computer, and more particularly to a method for determining an optimal control value for a load runback proceeding process and determining the appropriateness of the control result.

発電機の固定子巻線直接水冷却方式においては、冷却系
統が故障すると、導体内を流れる冷却水が断水あるいは
減水したり、冷却水が十分冷えないうちに導体に供給さ
れる場合がある。
In a generator stator winding direct water cooling system, if the cooling system fails, the cooling water flowing through the conductors may be cut off or reduced, or the cooling water may be supplied to the conductors before it is sufficiently cooled.

この状態ではもはや冷却不能となるため、固定子巻線導
体は異常に高温となり、発電機を危険状態に至らせるた
め、速やかに負荷電流を減少させる動作が必要となる。
この動作は普通負荷ランバツク動作と呼ばれている。従
来の負荷ランバツクは、冷却水圧力低、或は冷却水温度
高などのいわゆる冷却水断といわれる故障が発生すると
、原動機(例えばタービン)の負荷制限器に対し負荷減
少指令が出て、発電機が冷却水断状態で運転できる規定
負荷まで許容時間内に負荷減少するように制御される。
In this state, cooling is no longer possible, and the stator winding conductor becomes abnormally high in temperature, putting the generator in a dangerous state, so it is necessary to quickly reduce the load current.
This operation is commonly called load runback operation. With conventional load runback, when a so-called cooling water cutoff occurs due to low cooling water pressure or high cooling water temperature, a load reduction command is issued to the load limiter of the prime mover (for example, a turbine), and the generator is The load is controlled so that the load is reduced within the allowable time to the specified load that can be operated with cooling water cut off.

第1図は負荷ランバツク進行過程の説明図であり、実線
1は理想的な状態、23は失敗状態を示す。第1図にお
いてT。時点にて冷却水断となつた後、実線1のように
一定変化率で負荷ランバツクが進行し、許容時間T経過
後のT,時点でその発電機の冷却水断規定負荷値になつ
ていれば、負荷ランバツク成功と判断され、更に故障発
生時の冷却水電導度により決る一定時間、運転続行可能
である。もし時点T,にて規定負荷値に下がつていなか
つた場合は、負荷ランバツク失敗と判断され直ちに発電
機トリツプさせる。しかしながら、この従来の方法には
次のような不具合があつた。まず第1図における破線2
で示したようにT1時点では確かに負荷電流は規定値ま
で減少していても、その減少過程においてT2時点まで
は何らかの原因でほとんど負荷が減少しなかつた場合で
あり、また第1図における一点鎖線3で示したように、
負荷ランバツクが何らかの原因でうまく動作せず、全負
荷のまま運転が続行し、T1の時点で初めて失敗と判断
され発電機トリツプとなる場合である。
FIG. 1 is an explanatory diagram of the progress of load runback, where solid line 1 indicates an ideal state and line 23 indicates a failed state. T in FIG. After the cooling water is cut off at point T, the load runback progresses at a constant rate of change as shown by solid line 1, and reaches the specified load value for cooling water cutoff for that generator at point T, after the allowable time T has elapsed. For example, it is determined that the load runback is successful, and operation can be continued for a certain period of time determined by the conductivity of the cooling water at the time the failure occurs. If the load has not fallen to the specified load value at time T, it is determined that the load runback has failed and the generator is immediately tripped. However, this conventional method had the following problems. First, dashed line 2 in Figure 1
As shown in Figure 1, even though the load current has indeed decreased to the specified value at time T1, the load hardly decreases for some reason until time T2 in the process of reduction. As shown by chain line 3,
This is a case where load runback does not work properly for some reason, and operation continues with full load, and failure is determined for the first time at time T1, causing the generator to trip.

いずれの場合もコイル内の冷却水の沸騰が始まり、局部
過熱、水の層切れなどの問題が生じ、発電機は極めて危
険な状態となる。もつとも、負荷ランバツク中、TOか
らT,までの中間点で負荷検出器により負荷を検出して
負荷ランバツクの進行を検証することもできるが、その
時点前後の負荷ランバツクの経過を考えた場合、やはり
前述したような不安が残り、十分な方策とはいえない。
In either case, the cooling water in the coils begins to boil, causing problems such as local overheating and water delamination, which puts the generator in an extremely dangerous condition. Of course, it is also possible to verify the progress of load runback by detecting the load with a load detector at an intermediate point from TO to T during load runback, but if we consider the progress of load runback before and after that point, The concerns mentioned above remain, and it cannot be said to be a sufficient measure.

又、中間における負荷検出点数を増すとしても、負荷検
出用の従来の負荷検出継電器は、単一般定のため、各負
荷検出点毎に設けなければならないので、中間の負荷検
出点数は適用上制限をうけるため、やはり満足な方策と
はいえない更に従来の負荷ランバツクは、プラントの運
転状態にかかわらず最初の負荷ランバツク指令のみで、
一律に負荷ランバツク動作が行なわれていた。
Furthermore, even if the number of load detection points in the middle is increased, the conventional load detection relay for load detection has a single general specification and must be installed at each load detection point, so the number of load detection points in the middle is limited in terms of application. In addition, conventional load runbacks require only the first load runback command regardless of the operating status of the plant.
Load runback operations were performed uniformly.

しかし、発電機は常に全負荷運転しているとは限らず、
詳細は後述するが、全負荷よりも小さい負荷で運転して
いたときの負荷ランバツクは、全負荷運転時の負荷ラン
バツクよりもゆるやかに時間をかけてでき、それだけ原
動機側に無理がかからないので、プラントトリツプに至
る可能性を小さくすることができる。ところが、従来の
負荷検出継電機を使用した回路では、一定時間後の単一
般定の負荷電流検出をするだけの制御しかできないため
、運転状態に応じた最適設定値を計算し負荷ランバツク
制御指令を出すという機能は実現できなかつた。本発明
の目的は、以上の点に鑑み、プラント運転状態に応じた
最適制御値を計算し、負荷ランバツク全過程において負
荷ランバツクが設定どおりに進行しているか否かを連続
的に監視し、適切な負荷ランバツク制御指令や、機器保
護のためにトリップ指令を出すことのできる計算機によ
る負荷ランバツク制御方法を提供することにある。
However, generators are not always operating at full load.
The details will be explained later, but the load runback when operating at a load smaller than the full load can be done more slowly than the load runback during full load operation, and there is less strain on the prime mover, so the plant The possibility of tripping can be reduced. However, in circuits using conventional load detection relays, control is only possible by detecting a single fixed load current after a certain period of time, so it is necessary to calculate the optimal setting value according to the operating condition and issue a load runback control command. It was not possible to achieve this function. In view of the above points, the purpose of the present invention is to calculate the optimal control value according to the plant operating state, continuously monitor whether the load runback is progressing as set during the entire load runback process, and It is an object of the present invention to provide a load runback control method using a computer that can issue load runback control commands and trip commands for equipment protection.

まず本発明の実施例の説明に人る前に理想的な最適負荷
減少率の計算方法の一例を述べる。第1図における負荷
ランバツク開始時点と、冷却水断規定負荷値を原点にと
ると第2図の如くなる。ここで負荷減少率即ち、発電機
の負荷電流が減少する状態は時間の関数であり第2図の
如く定数を決めると、となる。
First, before describing the embodiments of the present invention, an example of a method for calculating an ideal optimum load reduction rate will be described. If the starting point of load runback in FIG. 1 and the prescribed load value for cooling water cutoff are taken as the origin, the result will be as shown in FIG. 2. Here, the load reduction rate, that is, the state in which the load current of the generator decreases, is a function of time, and when a constant is determined as shown in FIG. 2, it becomes.

負荷ランバツク開始後この負荷電流1が発電機を流れる
とき、固定子巻線内の水に加えられる熱量Hは、固定子
巻線の抵抗分をR、電力から熱量に換算する係数をk1
、発電機の放熱や構造に起因する損失をK2とすると、
次のようになる発電機設計上の要求から、全負荷電流L
1が流れていたときの負荷ランバツク完了制限時間はT
,と決められるから2式のHの値は一定で、その発電機
固有のものとなる。つまり、冷却水断状態になつてから
H以上の熱量が加わわれば、固定子巻線内の冷却水は沸
騰しはじめる。
When this load current 1 flows through the generator after the start of load runback, the amount of heat H added to the water in the stator winding is determined by R, the resistance of the stator winding, and k1, the coefficient for converting electric power into heat amount.
, if the loss due to the heat radiation and structure of the generator is K2, then
From the following generator design requirements, the full load current L
The load runback completion time limit when 1 is flowing is T.
, so the value of H in the two equations is constant and unique to that generator. In other words, if a heat amount of H or more is applied after the cooling water is cut off, the cooling water in the stator winding starts to boil.

従つて負荷ランバツク途中でH以上の熱量が加わわりそ
うだと予想されるときは、負荷制限器を更に動作させた
り、それでもだめな場合は発電機をトリツプさせ名必要
がある。また2式は冷却水断直前に発電機に流れていた
負荷電流1の大きさによつて、負荷ランバツク完了制限
時間Tが変化することを意味する。
Therefore, if it is predicted that a heat amount of H or more is likely to be added during load runback, it is necessary to operate the load limiter further or, if that does not work, to trip the generator. Furthermore, Equation 2 means that the load runback completion time limit T changes depending on the magnitude of the load current 1 flowing through the generator immediately before the cooling water is cut off.

つまり冷却水断直前の負荷電流が、全負荷電流よりも小
さかつた場合は、それだけ時間を長くかけて負荷ランバ
ツクできることになる。負荷ランバツク完了制限時間T
は次式より求められる。番晶11↓ また、運転状態に応じた理想的な最適負荷減少率Kは次
の如く求められる。
In other words, if the load current immediately before the cooling water is cut off is smaller than the full load current, it will take a longer time to run back the load. Load runback completion time limit T
is obtained from the following formula. 11 ↓ Moreover, the ideal optimum load reduction rate K according to the operating condition can be obtained as follows.

H 次に、実際の負荷電流の減少率kを求めるには、微少時
間△tの間の電流変化分を△として△I/△tを計算す
ればよい。
H Next, in order to obtain the actual reduction rate k of the load current, ΔI/Δt can be calculated by setting Δ to the current change amount during the minute time Δt.

即ち、時刻tにおける負荷電流をnとしたとき、△t後
の負荷電流を11+1とすると、実際の負荷電流減少率
kは次の如くなる。
That is, when the load current at time t is n, and the load current after Δt is 11+1, the actual load current reduction rate k is as follows.

従つて4式のKの値と、5式のkの値を△t毎に比較す
れば、実際の負荷減少率が理想的に進行しているかどう
か監視ができることになる。
Therefore, by comparing the value of K in equation 4 and the value of k in equation 5 every Δt, it is possible to monitor whether the actual load reduction rate is progressing at an ideal rate.

αを余裕値とした場合、K−α≦k≦K+αのときは負
荷ランバツクは正常に動作していると判断し、k>K+
αの場合は負荷ランバツクがききすぎているから、負荷
制限の動作をやめ、k<K−αなら負荷ランバツクをも
つと 力にしなければならないから負荷ランバツク動作
を更に強めるようにする。一定時間後まだk<K−αの
状態にあるならば、何らかの原因で負荷ランバツタが正
常に動作していないことになるから、トリツプ信号を出
し機器を安全に保護する。次に、この方法を実現させる
ための装置について説明する。
When α is the margin value, when K-α≦k≦K+α, it is determined that the load runback is operating normally, and k>K+
In the case of α, the load runback is too strong, so the load limiting operation is stopped, and if k<K-α, the load runback must be made into a force, so the load runback is further strengthened. If k<K-α still exists after a certain period of time, it means that the load runbatter is not operating normally for some reason, so a trip signal is issued to safely protect the equipment. Next, an apparatus for implementing this method will be described.

第3図にその概要を示す。即ち、発電機1が原動機2に
より駆動され運転しているときに、発電機冷却水断が圧
カスイツチや温度スイツチなどの故障検出装置3により
検出されると、負荷ランバツク制御装置4は、CT5を
介して得られるそのときの負荷電流を基に、最適制御値
の計算をして負荷制限器6へ制御信号を出し、原動機2
への主蒸気量を加減弁7により減少させたり、あるいは
トリツプ信号を出したりするように構成する。前記負荷
ランバツク制御装置4は発電所の制御に使われている電
子計算機や、いわゆるマイクロコンピユータなどの計算
機の機能の一部を第4図に示したフローチヤートをプロ
グラムして動作させることにより得られる。
Figure 3 shows the outline. That is, when the generator 1 is driven and operated by the prime mover 2 and a failure detection device 3 such as a pressure switch or a temperature switch detects a failure detection device 3 such as a pressure switch or a temperature switch, the load runback control device 4 activates the CT5. Based on the current load current obtained through
The main steam amount to be reduced by a regulating valve 7 or a trip signal is issued. The load runback control device 4 can be obtained by programming and operating part of the functions of a computer such as an electronic computer used for controlling a power plant or a so-called microcomputer according to the flowchart shown in FIG. .

次に第4図に示したフローチヤートの内容について説明
する。
Next, the contents of the flowchart shown in FIG. 4 will be explained.

(1)プログラムをスタートさせnを1と定義して負荷
電流を読み込みその値を1nとして記憶する。
(1) Start the program, define n as 1, read the load current, and store the value as 1n.

(2)読み込んだInを基に最適負荷減少率Kを4式に
より計算しその値を記憶し、負荷ランバツク完了制限時
間Tを3式により計算し記憶する。
(2) Based on the read In, calculate the optimum load reduction rate K using the 4 formula and store the value, and calculate the load runback completion time limit T using the 3 formula and store it.

(3)冷却水断の故障がなければサンプリング時間Ts
の周期でKとTの値を求める計算をくり返しその記憶が
その都度更新されていく。この結果故障直前の運転状態
に応じた最適負荷減少率と負荷ランバツク完了制限時間
Tが計算され記憶されていることになる。(4)冷却水
断の故障発生で、第1段の負荷制限器への負荷ランバツ
ク信号を出す。
(3) Sampling time Ts if there is no cooling water cutoff failure
The calculations to obtain the values of K and T are repeated at a cycle of , and the memory is updated each time. As a result, the optimum load reduction rate and load runback completion time limit T corresponding to the operating state immediately before the failure are calculated and stored. (4) In the event of a cooling water cutoff failure, a load runback signal is sent to the first stage load limiter.

(5)実際の負荷電流の減少率を求めるため△tの時間
をカウントする。
(5) Count the time Δt to find the actual rate of decrease in load current.

(6)以降実行する計算は負荷ランバツク完了制限時間
T以内かどうかを判定する。
(6) In the subsequent calculations, it is determined whether the load runback completion time limit T has passed.

T以内ならば減少率を比較する次のプログラムへとすす
み、もしTを越えていたら負荷ランバツクは終了したこ
とになるから、プログラムをストツプさせる。(7)
n△t後の負荷電流を読み込みIn+1とする。
If it is within T, the program proceeds to the next program for comparing the reduction rates; if it exceeds T, it means that the load runback has ended, and the program is stopped. (7)
The load current after nΔt is read and set as In+1.

(8)△t前の負荷電流値はInとして記憶されている
。ら実際の負荷減少率kを5式により計算する。(9)
実際の負荷減少率kと最適負荷減少率Kとを比較する。
(8) The load current value before Δt is stored as In. The actual load reduction rate k is calculated using equation 5. (9)
The actual load reduction rate k and the optimal load reduction rate K are compared.

k>K+αなら更に負荷制限器を動作させる必要はない
ので負荷制限器の動作をやめさせ、nをn+1と定義し
なおして更に監視をすすめる。0Ik>K+αでない場
合は、k<K−αか否かを判別させる。
If k>K+α, there is no need to further operate the load limiter, so the operation of the load limiter is stopped, n is redefined as n+1, and further monitoring is performed. If 0Ik>K+α, it is determined whether k<K−α.

もしk<K−αでない場合はK−α≦k>K+αという
ことになり負荷ランバツクは正常に動作しているから、
変数mを1にりセツトすると共にnをn+1と定義しな
おして、更に△t後の負荷減少率を計算し比較する作業
をくり返す。k<K−αならば更に負荷制限器を動作さ
せて負荷減少を強力にしなければならないから第2番目
或は第3番目の負荷制限器への信号を出す。
If k<K-α, then K-α≦k>K+α, and the load runback is operating normally.
The variable m is reset to 1 and n is redefined as n+1, and the process of calculating and comparing the load reduction rate after Δt is repeated. If k<K-α, it is necessary to further operate the load limiter to make the load reduction stronger, so a signal is sent to the second or third load limiter.

ADk<K−αの状態が負荷ランバツクのプラントの正
常応答時間TR以内かどうかをm△tと比較し、T・8
以内ならば、mをm+1と定義しなおすと共にnをn+
1と定義しなおして次の△t後の負荷減少率を検証する
Compare m△t to see if the state of ADk<K-α is within the normal response time TR of the plant for load runback, and calculate T・8
If it is within, redefine m as m+1 and n as n+
1 and verify the load reduction rate after the next Δt.

Q]) k<Kbときは、負荷ランバツクが何らかの原
因で正常に動作していない場合の変化率と判断し直ちに
トリツプ信号を出す。
Q]) When k<Kb, it is determined that the rate of change is when the load runback is not operating normally for some reason, and a trip signal is immediately issued.

′ (代)もしもk<K−α,K〉K−αの状態が存在し、
TRを越えた場合も負荷ランバツクが何らかの原因で正
常に動作していないから、直ちにプラントトリツプ信号
を出し、プログラムもストツプさせる。
′ (v.) If there exists a state where k<K-α, K>K-α,
Even if TR is exceeded, the load runback is not operating normally for some reason, so a plant trip signal is immediately issued and the program is also stopped.

Q3) kくK−αのときはほとんど負荷ランバック動
作が行なわれない場合であるから、発電プラントに対し
直ちにトリツプ指令を出し、プログラムもストツプさせ
る。
Q3) When K - α, there is almost no load runback operation, so a trip command is immediately issued to the power generation plant and the program is also stopped.

以上述べた本発明によれば、冷媒断の故障発生時点にお
けるプラント運転状態に応じた最適負荷減少率Kを計算
し、多段階的に負荷制限器6を動炸させることにより、
従来にくらベプラントに必要以上に無理を強いることが
なくなるので負荷ランバツクの成功率を高めることがで
きる。
According to the present invention described above, by calculating the optimal load reduction rate K according to the plant operating state at the time of occurrence of the refrigerant cutoff failure and activating the load limiter 6 in multiple stages,
Compared to the conventional method, it is no longer necessary to force the plant more than necessary, so the success rate of load runback can be increased.

また負荷ランバツクが理想的に進行しているか否かを常
時監視できるため、従来技術に比べ監視能力が非常に高
まり、その結果負荷ランバツク途中においても負荷ラン
バツク動作の失敗が予想されるときは直ちにプラント・
トリツプ指令を出すなどの予測制御が可能となり、機器
をより早く安全に保護することができる。なお、以上述
べた実施例は固定子巻線を水冷却する場合であるが、水
冷却の代りに他の冷却媒体例えば水素ガスを用いて冷却
するようにした発電機にも適用することができる。
In addition, since it is possible to constantly monitor whether or not the load runback is progressing ideally, the monitoring ability is greatly improved compared to conventional technology.・
Predictive control such as issuing trip commands becomes possible, allowing equipment to be protected more quickly and safely. Although the embodiments described above are for cooling the stator windings with water, they can also be applied to generators that use other cooling media, such as hydrogen gas, instead of water cooling. .

また、上記実施例では負荷電流をサンプリングすること
により、負荷ランバツク完了制限時間T最適負荷減少率
K更にkを求めるようにしたが、計器用変圧器(PT)
および計器用変流器(CT)により発電機の電力をサン
プリングし、T,Kおよびkを求めるようにしてもよい
In addition, in the above embodiment, the load runback completion time limit T optimal load reduction rate K and k are obtained by sampling the load current.
The power of the generator may also be sampled using a current transformer (CT) to determine T, K, and k.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は負荷ランバツクの進行過程を説明する図、第2
図は第1図から得られる時間と負荷電流の変化を示す図
、第3図は本発明方法を適用するシステムの概念図、第
4図は本発明方法の一実施例で使用するプログラムのフ
ローチヤートである。
Figure 1 is a diagram explaining the progress of load runback, Figure 2
The figure shows the change in time and load current obtained from Figure 1, Figure 3 is a conceptual diagram of a system to which the method of the present invention is applied, and Figure 4 is the flow of a program used in an embodiment of the method of the present invention. It's a chat.

Claims (1)

【特許請求の範囲】 1 発電機の冷却装置が故障したら、発電機出力をラン
バックするようにした下記のステップからなる発電ブラ
ントの計算機による負荷ランバック制御方法。 (イ)発電機に固有の熱容量および発電機の出力電気量
のサンプリング値から、そのときの出力の大きさに応じ
た最適負荷減少率Kおよび負荷ランバック完了制限時間
Tを計算し、(ロ)発電機冷却装置の故障により原動機
に負荷ランバック指令を与え、(ハ)負荷ランバック動
作中に得られる発電機出力電気量のサンプリング値から
実際の負荷減少率にを計算し、(ニ)前記最適負荷減少
率Kと実際の負荷減少率kとが予定の関係にあるか否か
を検出し、負荷ランバック動作を継続するか中止するよ
うにした発電プラントの計算機による負荷ランバック制
御方法。 2 特許請求の範囲第1項に記載の方法において、前記
最適負荷減少率Kと実際の負荷減少率kとがα>IK−
kIのとき(但しα:余裕値) そのまま負荷ランバックを続行させるようにした発電プ
ラントの計算機による負荷ランパック制御方法。 3 特許請求の範囲第1項に記載の方法において、最適
負荷減少率Kと実際の負荷減少率kとがα<k−Kのと
き、負荷ランラック動作を一時中止するようにした発電
プラントの計算機による負荷ランバック制御方法。 4 特許請求の範囲第1項に記載の方法において、最適
負荷減少率Kと、実際の負荷減少率kとがk<K−αの
とき、更に強力な負荷ランバック動作を行なわせるよう
にした発電プラントの計算機による負荷ランバック制御
方法。 5 特許請求の範囲第1項に記載の方法において、最適
負荷減少率Kと、実際の負荷減少率kとが、予定時間以
上k<K−α のとき、発電プラントにトリップ指令を出すようにした
発電プラントの計算機による負荷ランバック制御方法。 6 特許請求の範囲第1項に記載の方法において、最適
負荷減少率kとがk≪K−α のとき、直ちに発電プラントにトリップ指令を出すよう
にした発電プラントの計算機による負荷ランバック制御
方法。
[Scope of Claims] 1. A load runback control method using a computer for a power generation blunt, which includes the following steps, in which the generator output is runback when the cooling device of the generator breaks down. (b) Calculate the optimal load reduction rate K and load runback completion time limit T according to the magnitude of the output at that time from the heat capacity specific to the generator and the sampled value of the output electricity amount of the generator; ) Give a load runback command to the prime mover due to a failure of the generator cooling system, (c) Calculate the actual load reduction rate from the sampled value of the generator output electricity obtained during the load runback operation, and (d) A computer-based load runback control method for a power generation plant, which detects whether or not the optimum load reduction rate K and the actual load reduction rate K have a scheduled relationship, and continues or stops load runback operation. . 2. In the method according to claim 1, the optimum load reduction rate K and the actual load reduction rate k are such that α>IK−
A computer-based load runback control method for a power generation plant that continues load runback when kI (α: margin value). 3. A power generation plant calculator that temporarily suspends load run rack operation when the optimum load reduction rate K and the actual load reduction rate k are α<k-K in the method set forth in claim 1. load runback control method. 4. In the method set forth in claim 1, when the optimum load reduction rate K and the actual load reduction rate k satisfy k<K-α, a stronger load runback operation is performed. Computer-based load runback control method for power generation plants. 5. In the method according to claim 1, when the optimum load reduction rate K and the actual load reduction rate k are equal to or longer than the scheduled time k<K-α, a trip command is issued to the power generation plant. A computer-based load runback control method for power generation plants. 6. A load runback control method using a computer for a power generation plant, in which a trip command is immediately issued to the power generation plant when the optimum load reduction rate k is k≪K−α in the method set forth in claim 1. .
JP51090843A 1976-07-31 1976-07-31 Computer-based load runback control method for power generation plants Expired JPS5915000B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP51090843A JPS5915000B2 (en) 1976-07-31 1976-07-31 Computer-based load runback control method for power generation plants

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP51090843A JPS5915000B2 (en) 1976-07-31 1976-07-31 Computer-based load runback control method for power generation plants

Publications (2)

Publication Number Publication Date
JPS5316823A JPS5316823A (en) 1978-02-16
JPS5915000B2 true JPS5915000B2 (en) 1984-04-06

Family

ID=14009855

Family Applications (1)

Application Number Title Priority Date Filing Date
JP51090843A Expired JPS5915000B2 (en) 1976-07-31 1976-07-31 Computer-based load runback control method for power generation plants

Country Status (1)

Country Link
JP (1) JPS5915000B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5510821A (en) * 1978-07-07 1980-01-25 Toshiba Corp Load run-back device

Also Published As

Publication number Publication date
JPS5316823A (en) 1978-02-16

Similar Documents

Publication Publication Date Title
JPS5852196B2 (en) Reactor control device
US4832898A (en) Variable delay reactor protection system
JP3954659B2 (en) Enhanced protection system against transient overpower
JPS6146799B2 (en)
JPS5915000B2 (en) Computer-based load runback control method for power generation plants
US5631937A (en) Method and apparatus for protecting a PWR from departure from nucleate boiling and hot leg boiling
JP2519268B2 (en) Nuclear power plant load follow-up operation control device
JP3011451B2 (en) Reactor power control system for boiling water nuclear power plant
JPH0196598A (en) Functional hierarchical configuration output control system
US4361535A (en) Control system and process for the operation of nuclear reactors
JPH0464099A (en) Feed water controller of steam generation plant
JPH0617741A (en) Turbine generator automatic control protection device
JP2734483B2 (en) Operation control device for pressurized water reactor
JPH0559903A (en) Load runback device
JP2000131480A (en) Reactor recirculation pump control system and power supply device
JPH0161036B2 (en)
JPH04308442A (en) Controller for generator refrigrant of power generating facility
JP2004279221A (en) Reactor power controller
JP3080762B2 (en) Steam turbine protection device
JPS6120684B2 (en)
JPH0113080B2 (en)
CN120488225A (en) Liquid level control method and device for steam generator of nuclear power station, electronic equipment and medium
JPS6252274B2 (en)
JPH0432799A (en) Nuclear reactor operation area limiting device
JPS6114731B2 (en)