JPS5933721B2 - Track construction method - Google Patents
Track construction methodInfo
- Publication number
- JPS5933721B2 JPS5933721B2 JP50122916A JP12291675A JPS5933721B2 JP S5933721 B2 JPS5933721 B2 JP S5933721B2 JP 50122916 A JP50122916 A JP 50122916A JP 12291675 A JP12291675 A JP 12291675A JP S5933721 B2 JPS5933721 B2 JP S5933721B2
- Authority
- JP
- Japan
- Prior art keywords
- injection
- track
- temperature
- sleepers
- injected
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Landscapes
- Railway Tracks (AREA)
Description
【発明の詳細な説明】
本発明は軌道の枕木と道床の間に注入層をおく軌道工法
において、注入材料を加熱状態で注入する構築工法をと
る場合において、加熱注入材料の冷却速度を速め、該軌
道構築所要時間の短縮をはかるための工法に関するもの
である。DETAILED DESCRIPTION OF THE INVENTION The present invention is a track construction method in which an injection layer is placed between track sleepers and the track bed, and when a construction method is used in which the injection material is injected in a heated state, the cooling rate of the heated injection material is accelerated and the This relates to a construction method for shortening the time required for track construction.
近時鉄道輸送量の増加とともに列車の通過量も増し、そ
れに伴って軌道、特に道床保守作業の頻度が増している
。BACKGROUND OF THE INVENTION In recent years, as the amount of railway transportation has increased, the amount of trains passing has also increased, and as a result, the frequency of track maintenance work, especially the track bed, has increased.
いっぽう列車の通過量が増せばそれだけ保、@作業ので
きる時間は短縮されるため保線作業の省力化が可能な軌
道方式が必要となってきた。On the other hand, as the number of trains passing increases, the time required for track maintenance work becomes shorter, so there is a need for a track system that can save labor during track maintenance work.
すなわち、従来のバラスト道床に代って例えば、コンク
リート道床にしたり、バラスト道床を一体化するなどの
方式が検討されている。That is, methods such as replacing the conventional ballast trackbed with a concrete trackbed or integrating the ballast trackbed are being considered.
本発明の目的は、こうした改良道床とは異なり軌道の枕
木と道床の間に注入材料の層をおく新規な軌道方式にお
いて、注入材料を加熱状態で注入する構築工法により、
その構築所要時間の短縮をはかるものである。The purpose of the present invention is to provide a new track system in which a layer of injected material is placed between track sleepers and the trackbed, unlike such improved trackbeds, by a construction method in which the injected material is injected in a heated state.
The aim is to shorten the time required for its construction.
この軌道構造における注入材料は枕木を介して伝達され
る通過車輛による各種応力などを下部構造である道床に
対して平均的に分散させ、それと同時に枕木を通して伝
達される振動をできるだけ吸収し、道床への衝撃力を緩
和し道床を保護して砕石摩損を少くし保線工事のサイク
ルを延ばすことができる。The injected material in this track structure evenly disperses various stresses caused by passing vehicles transmitted through the sleepers to the trackbed, which is the lower structure, and at the same time absorbs as much vibrations transmitted through the sleepers as possible to the trackbed. It is possible to reduce the impact force of the road, protect the trackbed, reduce the wear and tear of crushed stones, and extend the cycle of track maintenance work.
上記の注入材料には、物性的に次のような特性が要求さ
れる。The above-mentioned injection material is required to have the following physical properties.
すなわち、枕木を介して伝わる圧縮応力に対して年間を
通して必要以上の変形があっては好ましくないし、また
いっぽう固すぎると振動を十分吸収することができなく
なる。That is, it is undesirable if the sleeper deforms more than necessary throughout the year in response to the compressive stress transmitted through the sleeper, and on the other hand, if the sleeper is too hard, it will not be able to absorb vibrations sufficiently.
さらには枕木と道床の間に注入材料を注入する際には液
状でなければ枕木と道床間に注入することも困難となる
。Furthermore, when injecting the material between the sleepers and the track bed, it is difficult to inject the material between the sleepers and the track bed unless it is liquid.
従って作業時には液状であって、硬化してからは強靭で
、各種応力に対して変形も少なく、しかも振動吸収性の
良い材料が要求される。Therefore, there is a need for a material that is liquid during operation, strong after hardening, less deformed by various stresses, and has good vibration absorption properties.
一方、この軌動方式を新設軌道において採用する場合は
、十分な作業時間をとることが可能な場合が多いが、既
設の営業線の軌道をこの軌道方式に切り換える場合は極
めて難かしい問題にぶつかる。On the other hand, when adopting this track system for newly constructed tracks, it is often possible to take sufficient work time, but when switching to this track system for existing commercial line tracks, extremely difficult problems are encountered. .
すなわち、営業線をこの軌道方式に切り換える場合は、
時間的に終電車が通過した後始発電車が来るまでの極め
て短時間の間に工事を行わなければならない。In other words, when switching a commercial line to this track system,
Construction work must be carried out within an extremely short period of time, from when the last train passes until the arrival of the first generating car.
線路によって異なるが、特に改良軌道を必要とする都市
近郊の路線においては大体4時間程度の作業時間しかな
いのが一般的である。Although it varies depending on the line, the work time is generally only about four hours, especially on lines near urban areas that require improved track.
このような短時間の間に作業としては在来レール、枕木
の撤去、道床面の調整、整備、新枕木、レールの搬入、
それぞれの位置、水準の調整、注入材料の注入などを確
実に実施しなければならない。In such a short period of time, the work involved removing the existing rails and sleepers, adjusting and maintaining the track bed surface, bringing in new sleepers and rails,
Adjustment of each location, level, and injection of injection materials must be carried out reliably.
またこれら構築作業の所要時間としては、これら各作業
に要する作業時間のみならず、注入材料の固化時間が加
わる。Furthermore, the time required for these construction operations includes not only the operation time required for each of these operations but also the solidification time of the injection material.
すなわち、注入材料は注入時は液体状でろるが、注入後
は固化しなければ注入材料としての役に立たない。In other words, the injection material is liquid and solid when injected, but it is useless as an injection material unless it solidifies after injection.
したがって、注入材料が注入後固化して所要の強度を出
すまでの固化所要時間も、構築作業時間としてみておか
なければならない。Therefore, the time required for the injection material to solidify after injection and achieve the required strength must also be considered as the construction work time.
使用する注入材料を加熱状態で注入する場合を考えると
、注入材料が熱硬化性の場合で注入後注入温度から10
℃〜20℃位低下した場合でも所要の強度を有するもの
であれば特に問題はないが、熱硬化性注入材料であって
も例えば十分な硬化がなされていない状態では、注入材
料の温度が高いと強度が出ないものもあり、このような
材料は供用させる為にはやはり強度の出る温度まで注入
材料を冷却しなければ使用に耐えない。Considering the case where the injection material used is injected in a heated state, if the injection material is thermosetting, the injection temperature should be 10% lower than the injection temperature after injection.
Even if the temperature drops by about 20°C, there is no particular problem as long as it has the required strength, but even if it is a thermosetting injection material, for example, if it has not been sufficiently cured, the temperature of the injection material will be high. In order to put these materials into service, the injected material must be cooled to a temperature at which strength is obtained.
また、熱可塑性材料を注入材料として高温度で注入する
場合は、明らかに冷却固化して所定の強度が出る温度ま
で冷却しなければならない。Furthermore, when a thermoplastic material is injected as an injection material at a high temperature, it must be cooled to a temperature at which it solidifies and attains a predetermined strength.
この冷却所要時間は実質的には軌道構築作業においては
非常に大きな部分を占め、この冷却時間の短縮は工事ス
ピードを向上させる重要な要素であることが判明したの
で注入材料が急速に冷却する軌道構築T法妃関して、例
えば注入層となる部分に予め設置した小口径金属管に注
入材の注入後冷却剤等を流して注入材料の冷却を促進す
る方法や注入材料に金属片を混入させておき注入材料の
熱伝導を改善する方法など種々の冷却方法の実験を行な
った。This cooling time actually occupies a very large part of the track construction work, and shortening this cooling time has been found to be an important factor in improving construction speed. Regarding construction T method, for example, there is a method of promoting cooling of the injection material by flowing a coolant etc. after injection of the injection material into a small diameter metal pipe installed in advance in the part that will become the injection layer, or a method of mixing metal pieces into the injection material. Experiments were conducted on various cooling methods, including methods to improve the heat conduction of the injected material.
その結果加熱された注入材料を注入する前に道床間及び
枕木に散水して浸潤状態にしておいた場合、注入後軌道
上面に散水した場合、及び両者を併用した場合にはこれ
ら散水を全〈実施しなかった場合に比べて注入材の温度
が急速に降下して散水の冷却効果の顕著なことが明らか
となった。As a result, if the heated injection material is sprinkled between trackbeds and sleepers to make it wet, if it is sprinkled on the top of the track after injection, or if both are used together, all of these waterings are It became clear that the temperature of the injection material decreased rapidly compared to the case where no injection was performed, and the cooling effect of water spraying was significant.
従ってこれらの冷却方法を軌道構築において適用するこ
とにより軌道構築時間を短縮する新規な軌道構築方法と
なることが分った。Therefore, it has been found that applying these cooling methods to orbit construction will result in a new orbit construction method that shortens orbit construction time.
そこで本発明の目的は、枕木と道床間に注入材料の層を
設ける軌道構築工法において、加熱注入材料を注入する
以前に道床、枕木に散水するかおよびまたは注入後に枕
木に散水することによって軌道構築時間を短縮する新規
な軌道構築法を提供するにある。Therefore, an object of the present invention is to construct a track by sprinkling water on the trackbed and sleepers before injecting the heated injection material, and/or by sprinkling water on the sleepers after pouring the heated injection material, in a track construction method in which a layer of injected material is placed between the sleepers and the track bed. The objective is to provide a new trajectory construction method that saves time.
以下、本発明をその実施例について添付図面を参照しつ
つ説明する。Hereinafter, embodiments of the present invention will be described with reference to the accompanying drawings.
第1図は本発明の一実施例の断面図を、第2図は同じく
平面図を示す。FIG. 1 shows a sectional view of an embodiment of the present invention, and FIG. 2 shows a plan view of the same.
1は枕木で2は枕木の中に設けられた注入材料の注入口
で上端は直径8Cmの円形、下端は直径6cmの円形を
なすラッパ形のものである。1 is a sleeper, and 2 is a trumpet-shaped inlet for injection material provided in the sleeper, with the upper end being a circle with a diameter of 8 cm, and the lower end being a circle with a diameter of 6 cm.
3は注入層、4は軌条、5はバラスト道床である。3 is an injection layer, 4 is a rail, and 5 is a ballast track bed.
第2図は第1図の平面図で締結装置6が軌条の座金とも
なりかつ軌条を枕木に固定している。FIG. 2 is a plan view of FIG. 1, in which the fastening device 6 also serves as a washer for the rail and fixes the rail to the sleeper.
枕木1は長さ2m、巾73.3 cm1枕木間隔10c
mであり、枕木の平均厚さ約16cmである。Sleeper 1 is 2 m long, 73.3 cm wide, and 10 cm apart between sleepers.
m, and the average thickness of the sleepers is approximately 16 cm.
注入層3の厚さは約3cmでるる。The thickness of the injection layer 3 is approximately 3 cm.
道床5はバラスト道床を転圧後6号砕石(直径約12m
m)を散布転圧して作った。Track bed 5 is made of No. 6 crushed stone (approximately 12 m in diameter) after compacting the ballast track bed.
m) was spread and rolled.
加熱した注入材料は注入口2より注入し、注入口におけ
る注入材料の冷却固化後のレベルは枕木上面より約10
cmであった。The heated injection material is injected from the injection port 2, and the level of the injection material at the injection port after cooling and solidifying is approximately 10% higher than the top surface of the sleeper.
It was cm.
注入材料の冷却温度変化を把握するため、注入口の上部
より熱電対を挿入し、感温部は注入口における道床面ど
枕木下面の中間位置に設定した。In order to understand changes in the cooling temperature of the injected material, a thermocouple was inserted from the top of the injection port, and the temperature sensing part was set at a position between the track bed surface and the lower surface of the sleeper at the injection port.
使用した注入材料は熱可塑性物質で、180℃に加熱し
たものを注入した。The injection material used was a thermoplastic material, and the injection material was heated to 180°C.
注入直後の温度測定点の温度指示値は大体160℃付近
を指したが、これは道床あるいは枕木と熱交換して約2
0℃位低下したものと考えらねる。The temperature reading at the temperature measurement point immediately after injection was approximately 160°C, but this is due to heat exchange with the track bed or sleepers, which is about 2.
It is thought that the temperature dropped by about 0℃.
注入後の注入層の温度変化の状況を第3図および第4図
に示した。Figures 3 and 4 show how the temperature of the injection layer changes after the injection.
第3図は天候曇、気温−2℃における注入層の温度変化
実測値であり、第4図は天候用、気温10℃における注
入層の温度変化実測値である。FIG. 3 shows actual measured values of the temperature change of the injection layer under cloudy weather and an air temperature of -2°C, and FIG. 4 shows actual measured values of the temperature change of the injection layer under cloudy weather and an air temperature of 10°C.
両者とも国鉄本線切り替え工事を実施した時のものであ
り、注入材料、注入温度、改良軌道の形式は全く同一で
ある。Both were made when the Japan National Railways main line switching work was carried out, and the injection materials, injection temperature, and type of improved track are exactly the same.
第3図、第4図を比較すると明らかなように、曇の日に
実施した第3図では、注入直後160℃から注入層温度
が60℃まで下るのに112分かかったのに対して、第
4図の雨の日の場合は注入直後160℃から注入温度が
60℃に下るまで34分と1時間以上も短縮された。As is clear from comparing Figures 3 and 4, in Figure 3, which was carried out on a cloudy day, it took 112 minutes for the temperature of the injection layer to drop from 160 °C to 60 °C immediately after injection. In the case of a rainy day shown in Figure 4, the time required for the injection temperature to drop from 160°C to 60°C immediately after injection was 34 minutes, which was more than an hour.
この両者の差について、高温度で注入された注入材料の
熱量が、道床の砕石に付着した水分を蒸発させ、水分の
蒸発潜熱として置換されるとともに、直接注入材料と接
してはいない道床部に伝わった熱量も道床各部の水分蒸
発熱として移行することにより、道床部の温度が水分の
少ない場合と比べより低下し、従って注入層の温度をよ
り早く冷却したものである。Regarding the difference between the two, the amount of heat from the injected material injected at high temperature evaporates the water adhering to the crushed stones on the road bed, and is replaced by the latent heat of vaporization of the water. The transferred heat also transfers as heat of moisture evaporation to various parts of the trackbed, so the temperature of the trackbed becomes lower than when there is less moisture, and therefore the temperature of the injection layer is cooled more quickly.
また、注入層の上側で接している枕木について言えば、
枕木が下面では高温度の注入材料と接することにより枕
木の温度が上昇するが、枕木上面において水があるため
、枕木に移った熱量は容易に枕木上面の水分蒸発熱によ
って除去され、枕木温度が水分のない場合と比べ早く冷
却されるため、注入層の温度は上面からも、より早く冷
していくものである。Also, regarding the sleepers that are in contact with the upper side of the injection layer,
The temperature of the sleeper rises as the sleeper comes into contact with the high-temperature injection material on the bottom surface, but since there is water on the top surface of the sleeper, the heat transferred to the sleeper is easily removed by the heat of moisture evaporation on the top surface of the sleeper, and the temperature of the sleeper increases. Since the injection layer is cooled more quickly than when there is no moisture, the temperature of the injection layer also decreases more quickly from the top.
このように本発明により道床と枕木の間に注入材料を5
0℃以上の加熱状態で注入する方法において、あらかじ
め加熱注入材料を注入する前の時点で道床および/また
は枕木に散水をしておくか、加熱注入材料を注入した後
の時点で、枕木の上に散水するか、また【jいずれか一
方法だけでも実施すれば加熱注入材料の冷却速度が早ま
り、この軌道構築の所要時間が短縮でき、従って1日当
りの工事量を増すことができる。In this way, according to the present invention, five injection materials are placed between the track bed and the sleepers.
In the method of injection in a heated state of 0°C or higher, the track bed and/or sleepers are sprinkled with water before the heated injection material is injected, or the top of the sleepers is sprinkled with water after the heated injection material is injected. If only one method is applied, the cooling rate of the heated injection material will be accelerated, the time required for track construction will be shortened, and the amount of work per day can be increased.
新設軌道にこの軌道方式を採用する場合にも、この散水
冷却促進法を用いることは作業時間の短縮に役立つもの
である。Even when this track system is adopted for newly constructed tracks, using this water cooling promotion method will help reduce work time.
第1図は本発明の一実施例の断面図、第2図は第1図の
平面図、第3図は天候曇における注入層の温度変化を示
すグラフ、第4図は天候用における注入層の温度変化を
示すグラフである。
1・・・・・・枕木、2・・・・・・材料注入口、3・
・・・・・注入層、4・・・・・・軌条、5・・・・・
・バラスト、6・・・・・・レール締結装置。Fig. 1 is a cross-sectional view of an embodiment of the present invention, Fig. 2 is a plan view of Fig. 1, Fig. 3 is a graph showing the temperature change of the injection layer in cloudy weather, and Fig. 4 is the injection layer for weather use. 2 is a graph showing temperature changes. 1...Sleeper, 2...Material injection port, 3.
...Injection layer, 4...Rail, 5...
・Ballast, 6...Rail fastening device.
Claims (1)
法において、加熱注入材料を注入する以前に道床および
枕木に散水すること、および加熱注入材料を注入した後
に軌道上面に散水することのうちの少くとも1つの散水
を行うことによって、該軌道構築所要時間を短縮するこ
とを特徴とする軌道構築工法。1. In the track construction method in which a layer of injection material is placed between the sleepers and the track bed, water is sprinkled on the track bed and sleepers before the heated injection material is injected, and water is sprinkled on the top of the track after the heated injection material is injected. A track construction method characterized by shortening the time required for track construction by performing at least one water sprinkling.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP50122916A JPS5933721B2 (en) | 1975-10-14 | 1975-10-14 | Track construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP50122916A JPS5933721B2 (en) | 1975-10-14 | 1975-10-14 | Track construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS5249504A JPS5249504A (en) | 1977-04-20 |
| JPS5933721B2 true JPS5933721B2 (en) | 1984-08-17 |
Family
ID=14847764
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP50122916A Expired JPS5933721B2 (en) | 1975-10-14 | 1975-10-14 | Track construction method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS5933721B2 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS6379112A (en) * | 1986-09-24 | 1988-04-09 | Hitachi Vlsi Eng Corp | Remote control device |
Family Cites Families (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5217603B2 (en) * | 1972-09-05 | 1977-05-17 |
-
1975
- 1975-10-14 JP JP50122916A patent/JPS5933721B2/en not_active Expired
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS6379112A (en) * | 1986-09-24 | 1988-04-09 | Hitachi Vlsi Eng Corp | Remote control device |
Also Published As
| Publication number | Publication date |
|---|---|
| JPS5249504A (en) | 1977-04-20 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US3878987A (en) | Railway track structure | |
| US4925094A (en) | Concrete railroad ties | |
| US3999276A (en) | Method of laying railroad rail | |
| JPS5933721B2 (en) | Track construction method | |
| Xu et al. | Mechanical properties of foamed polyurethane solidified ballasted track | |
| US3056555A (en) | Grade crossing | |
| CN210394986U (en) | Device for preventing and treating slurry pumping of ballast railway track bed | |
| WO2009036990A1 (en) | Railway superstructure devices | |
| US1512125A (en) | Method of making surface coverings | |
| CN108797397B (en) | A repair construction method suitable for long longitudinal slope bridge deck | |
| JPS6020521B2 (en) | Paved track switching construction method for commercial lines | |
| US2045253A (en) | Cushioned car rail | |
| CN108612076A (en) | A kind of unit plate type non-fragment orbit railway sub-grade frost boiling method of discrimination | |
| US1552109A (en) | Pavement | |
| US2348365A (en) | Protective coating for concrete pavements | |
| JPS5829363B2 (en) | Kidney injury and child abuse | |
| JP2022169909A (en) | Method of construction of ballast track and ballast track | |
| JPH04247104A (en) | Water permeable subgrade and method of constructing the same | |
| USRE15823E (en) | Railroad crossino or froo and method of making the same | |
| CN205062577U (en) | Railway roadbed structure of railway | |
| CN114561837B (en) | Pouring method with semi-flexible asphalt concrete as track lap joint material | |
| JPS6327601A (en) | Improvement of road foundation for track | |
| US869645A (en) | Railway-tie. | |
| US1478508A (en) | William p | |
| US2499939A (en) | Permanent railway bed |