JPS5944445B2 - Construction method for offshore structures - Google Patents
Construction method for offshore structuresInfo
- Publication number
- JPS5944445B2 JPS5944445B2 JP8590380A JP8590380A JPS5944445B2 JP S5944445 B2 JPS5944445 B2 JP S5944445B2 JP 8590380 A JP8590380 A JP 8590380A JP 8590380 A JP8590380 A JP 8590380A JP S5944445 B2 JPS5944445 B2 JP S5944445B2
- Authority
- JP
- Japan
- Prior art keywords
- pile
- panel structure
- mortar
- construction method
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Landscapes
- Revetment (AREA)
Description
【発明の詳細な説明】
本発明は海洋構造物の施工法に関するもので、更に詳し
くは防波堤や消波堤等のような水深の浅い海洋に設置さ
れる杭式海洋構造物の施工法に関するものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a construction method for marine structures, and more particularly to a construction method for pile-type marine structures such as breakwaters and breakwaters installed in shallow ocean waters. It is.
従来杭式海洋構造物の施工法としては、通常第1図に示
すごとく鋼管杭1を打設後、杭の上部同志を連結部材1
5を介して現場溶接等で接合して行く方法又は第2図に
示すごとく予め海底地盤上にガイドやジャケット構造物
を仮据付けにしておき、これに杭1を挿入して打設して
行く方法が採用されている。Conventional construction methods for pile-type offshore structures usually involve driving steel pipe piles 1 as shown in Figure 1, and then connecting the upper parts of the piles with connecting members 1.
5, by welding on site, etc., or by temporarily installing a guide or jacket structure on the seabed ground in advance as shown in Figure 2, and inserting and driving the pile 1 into this. method has been adopted.
しかしながら、前者の施工方法の場合、棺の打ち込み精
度の確保が困難であるうえ、施工作業自体、杭打ち精度
に左右されるため、現場での工期短縮が難しいという欠
点があり、又後者の施工方法の場合、杭打ち精度が確保
できるというメリットがあるが、構造的に複雑高価で施
工性の点でも劣るため、特に消波堤のような海面附近の
消波パネル部分が重要視される海洋構造物ではより構造
的にも施工性の点でも簡単な施工法の開発が望まれてい
る。However, in the case of the former construction method, it is difficult to ensure the precision of driving the coffin, and the construction work itself depends on the precision of piling, so it is difficult to shorten the construction period on site. This method has the advantage of ensuring pile driving accuracy, but it is structurally complex, expensive, and inferior in terms of construction workability, so it is particularly important for offshore applications where wave-dissipating panels near the sea surface, such as wave-dissipating levees, are important. For structures, it is desired to develop a construction method that is simpler in terms of structure and workability.
この発明はかかる従来技術の欠点に鑑み創案されたもの
で、その目的は現場での海上・海中工事を減らすことに
より工期の短縮をはかると共に作業困難な海上でそれ程
厳しい精度で施工しなくても十分所期の構造物を設置で
きる海洋構造物の施工法1を提供することにある。This invention was devised in view of the shortcomings of the prior art, and its purpose is to shorten the construction period by reducing on-site offshore/underwater construction work, and also to reduce the need for construction work to be performed with such strict precision at sea, where work is difficult. An object of the present invention is to provide a construction method 1 for marine structures that can fully install the desired structure.
以下本考案の詳細を第3図及び第4図に示すカーテン式
消波堤の施工法を例に説明する。The details of the present invention will be explained below, taking as an example the method of constructing a curtain-type wave-dissipating levee shown in FIGS. 3 and 4.
図において、1は鋼管杭、2は鋼管杭1の外径より所定
寸法だけ大きい内径を有する所定長さの鋼管製外管3と
各外管3を鋼管杭の設計上の打ち込み間隔と同一の所定
間隔に連結せしめる消波板4形成用の連結パネルとから
一体に構成されたパネル構造の鋼製溶接構造体、5は外
周側所定位置にモルタル注入口(図示せず)を備えた外
管上蓋、6は抗1の周面に外嵌可能で、かつ外管嵌合状
態において外管3下面を閉塞可能に設けられた環状のモ
ルタル受板で、該受板6はその上面に設けた係止金具T
及び吊金具8を介して外管3の下端側周面に設けた係止
金具9に係止することにより外管下面に密着状に保持さ
れている。In the figure, 1 is a steel pipe pile, 2 is a steel pipe outer pipe 3 of a predetermined length having an inner diameter larger than the outer diameter of the steel pipe pile 1 by a predetermined dimension, and each outer pipe 3 is inserted at the same driving interval as the designed steel pipe pile. A steel welded structure with a panel structure that is integrally formed with connecting panels for forming wave-absorbing plates 4 that are connected at predetermined intervals, and 5 is an outer pipe equipped with a mortar injection port (not shown) at a predetermined position on the outer circumference. The upper cover 6 is an annular mortar receiving plate which can be fitted onto the circumferential surface of the resistor 1 and can close the lower surface of the outer tube 3 when the outer tube is fitted, and the receiving plate 6 is provided on the upper surface thereof. Locking metal fitting T
It is held in close contact with the lower surface of the outer tube by being locked to a locking fitting 9 provided on the lower end side circumferential surface of the outer tube 3 via a hanging fitting 8.
10は外管3を抗1にかぶせた後、抗1、外管3及びモ
ルタル受板6によって形成された環状の間隙にモルタル
注入口から充填されたモルタルで、これによりパネル構
造体2は抗1と一体に接合される。Reference numeral 10 denotes mortar that is filled from the mortar injection port into the annular gap formed by the resistor 1, the outer tube 3, and the mortar receiving plate 6 after the outer tube 3 is placed over the resistor 1. 1 and are integrally joined.
11は該外管3上部に打設された上部波返し工である。Reference numeral 11 denotes an upper corrugation work installed on the upper part of the outer pipe 3.
同外管3の内側にはモルタルと杭の付着力を増大させる
ため突起物を設けてもよく、又外管の上蓋下面の外周側
所定位置には適当な位置決め部材を付設し、外管を鋼管
杭にかぶせた時、両者の間隙がほぼ一定になるようにす
ることができる。A protrusion may be provided on the inside of the outer tube 3 to increase the adhesion force between the mortar and the piles, and an appropriate positioning member may be attached to a predetermined position on the outer circumference of the lower surface of the upper lid of the outer tube, so that the outer tube can be fixed. When placed over a steel pipe pile, the gap between the two can be made almost constant.
勿論上記突起物又は位置決め部材等を設ける場合、外管
を打ち込み誤差のある杭上部に嵌合できるように外管の
内径、突起物長さ等を適当に設定されることは当然であ
る。Of course, when the protrusion or positioning member is provided, the inner diameter of the outer tube, the length of the protrusion, etc. should be set appropriately so that the outer tube can be fitted to the upper part of the pile with an error in driving.
次にこの考案による施工手順を第4図により説明する。Next, the construction procedure according to this invention will be explained with reference to FIG.
■ 先ず棺打ち船12により現場で抗1を所定間隔に打
設する(第4図イ)。■ First, the coffin boat 12 drives the columns 1 at predetermined intervals at the site (Fig. 4A).
■ 次に予め一体構造に組み立てられ塗装仕上げの施さ
れたパネル構造体2(図示の例では4本の外管3と3枚
の消波パネル4により一体に構成されている)を第4図
口のごとくクレーン船12で順次吊り上げ、パネル構造
体2の各外管3をそれぞれ対応する杭1に嵌合して据付
ける。■ Next, the panel structure 2 (in the illustrated example, it is made up of four outer tubes 3 and three wave-dissipating panels 4), which has been preassembled into an integral structure and given a paint finish, is shown in Figure 4. The panel structure 2 is sequentially lifted up by a crane ship 12, and each outer tube 3 of the panel structure 2 is fitted into its corresponding pile 1 and installed.
■ 次いで接続用消波パネル4′をクレーン船で吊上げ
、第4図へのごとく各パネル構造体2間に下ろして各パ
ネル構造体同志な消波パネル4′を介して接合した後、
抗1と外管3との隙間に上蓋のモルタル注入口からモル
タル10を注入充填することにより杭とパネル構造体を
一体に接合する。■ Next, the connecting wave-dissipating panels 4' are lifted up by a crane ship, and lowered between each panel structure 2 as shown in Fig. 4, and each panel structure is joined via the similar wave-dissipating panels 4'.
The pile and the panel structure are integrally joined by injecting mortar 10 into the gap between the shaft 1 and the outer pipe 3 from a mortar injection port in the upper cover.
■ 次に上部波返し工11を外管3上に打設することに
より消波堤の施工が完了する(第4図二)。■ Next, the construction of the wave-dissipating bank is completed by placing the upper wave return work 11 on the outer pipe 3 (Fig. 4-2).
同上述説明では海洋構造物の施工法としてパネル構造の
消波堤を例に説明したが、勿論この範囲に限定されず例
えばジャケット式パネル構造物の施工等にも有効に利用
できることは云うまでもない。In the above explanation, a panel-structured breakwater was used as an example of the construction method for marine structures, but it goes without saying that the method is not limited to this scope and can be effectively used, for example, in the construction of jacket-type panel structures. do not have.
即ち、この発明の施工法は杭打ち込み、もしくは杭の建
て込み(海底が岩盤の場合)が可能な海域でのあらゆる
海洋構造物に適用でき、その経済性を発揮させる事がで
きる。That is, the construction method of the present invention can be applied to any marine structure in a sea area where pile driving or pile erecting (when the seabed is bedrock) is possible, and its economic efficiency can be demonstrated.
例えば棧橋、ドルフィン、岩壁等の港湾構造物、石油掘
削用の小型プラットフォーム、海面上の橋梁の基礎、海
洋レジャー設備、水面貯水場の周囲仕切柵、開口部アバ
フロータ−ゲート其の他あらゆる海洋構造物に応用でき
る。For example, port structures such as bridges, dolphins, rock walls, small platforms for oil drilling, foundations of bridges on the sea surface, marine leisure facilities, partition fences around water reservoirs, openings above floater gates, and all other marine structures. Can be applied to things.
本発明は上述のごとく杭を打設した後、パネル構造体又
はジャケット式パネル構造体の外管を杭頭部に嵌合し、
各杭と各外管との間隙にモルタル受板入して杭とパネル
構造体を接合するようにしたので、海上作業が容易とな
るうえ、海中作業を殆んど皆無と出来、工期短縮、工費
節減及び安全性の向上等に大きく寄与するものである。In the present invention, after driving the pile as described above, the outer pipe of the panel structure or jacket type panel structure is fitted to the pile head,
By inserting a mortar plate into the gap between each pile and each outer pipe to connect the piles and the panel structure, offshore work is not only easier, but also almost no underwater work is required, shortening the construction period. This greatly contributes to reducing construction costs and improving safety.
さらに従来、杭構造物施工上の最大の問題点は、打設さ
れた杭の誤差をいかに吸収するかという点にあったが、
この発明によれば外管の内径、換言すれば杭と外管との
間隙を適当に選択設定することにより杭の打ち込み精度
許容誤差が大きくとれるため海上作業が極めて容易にな
る利点がある。Furthermore, in the past, the biggest problem in the construction of pile structures was how to absorb errors in the piles that were driven.
According to the present invention, by appropriately selecting and setting the inner diameter of the outer tube, in other words, the gap between the pile and the outer tube, the tolerance for driving accuracy of the pile can be increased, which has the advantage of making offshore work extremely easy.
第1図及び第2図はそれぞれ従来の施工法を示す概略図
、第3図イは本発明方法によって施工された消波堤を示
す部分斜視図、同図口はイ図のA防断面、第4図はイ2
2ロ、ハび二は本発明方法による消波堤の施工手順を示
す額略図である。
1:杭、2:パネル構造体、3:外管、4,41:消波
板(連結パネル)、5:上蓋、6:モルタル受板、10
:モルタル、12:杭打ち船、S:水面、L:海底面。Figures 1 and 2 are schematic diagrams showing the conventional construction method, respectively, Figure 3A is a partial perspective view showing a wave-dissipating levee constructed by the method of the present invention, and the opening in the figure is the A breakwater section in Figure A; Figure 4 is A2
2B and 2B are schematic diagrams showing the procedure for constructing a wave-dissipating levee according to the method of the present invention. 1: Pile, 2: Panel structure, 3: Outer pipe, 4, 41: Wave-dissipating plate (connected panel), 5: Upper cover, 6: Mortar receiving plate, 10
: Mortar, 12: Pile driver, S: Water surface, L: Seabed surface.
Claims (1)
可能なモルタル受部を備えた所定長さの複2数本の外管
をそれぞれ連結パネルを介して設計上の杭打設問間と同
一間隔に連結せしめて一体のパネル構造体となし、複数
本の杭を所定間隔をあけて海底地盤に打設せしめた後、
該各杭上端部に上記パネル構造体の各外管をかぶせた後
、上記外管と杭との間隙にそれぞれモルタルを充填して
杭とパネル構造体とを結合するようにしたことを特徴と
する海洋構造物の施工法。1 Two or more outer pipes of a predetermined length, each having an inner diameter larger than the outer diameter of the pile and having a mortar receiver at the lower end that can be fitted onto the surrounding surface of the pile, are connected through connecting panels to drive the pile according to the design. After connecting the panels at the same intervals as the gaps between the questions to form an integrated panel structure, and driving multiple piles into the seabed soil at predetermined intervals,
After each outer pipe of the panel structure is placed over the upper end of each of the piles, each gap between the outer pipe and the pile is filled with mortar to connect the pile and the panel structure. construction method for marine structures.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP8590380A JPS5944445B2 (en) | 1980-06-26 | 1980-06-26 | Construction method for offshore structures |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP8590380A JPS5944445B2 (en) | 1980-06-26 | 1980-06-26 | Construction method for offshore structures |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS5712706A JPS5712706A (en) | 1982-01-22 |
| JPS5944445B2 true JPS5944445B2 (en) | 1984-10-30 |
Family
ID=13871801
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP8590380A Expired JPS5944445B2 (en) | 1980-06-26 | 1980-06-26 | Construction method for offshore structures |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS5944445B2 (en) |
Families Citing this family (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS6019808A (en) * | 1983-07-12 | 1985-02-01 | Taisei Corp | Construction of underwater leg using jacket |
| JPS61193118U (en) * | 1985-05-24 | 1986-12-01 | ||
| US20150010364A1 (en) * | 2009-01-15 | 2015-01-08 | Ocean Brick System (O.B.S.) Ltd. | Deep-water port |
| JP7354872B2 (en) * | 2020-02-20 | 2023-10-03 | Jfeエンジニアリング株式会社 | Jacketed structure and its construction method |
-
1980
- 1980-06-26 JP JP8590380A patent/JPS5944445B2/en not_active Expired
Also Published As
| Publication number | Publication date |
|---|---|
| JPS5712706A (en) | 1982-01-22 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US3859806A (en) | Offshore platform | |
| AU2011368478B2 (en) | Batch-installation-type large-caliber underwater casing installation structure using sheet pile and method for constructing same | |
| US3624702A (en) | Offshore platform support | |
| JP3423394B2 (en) | Underwater frame structure | |
| KR102310131B1 (en) | Floatable concrete block structure and manufacturing method therefor | |
| JPS589206B2 (en) | Land-based plant construction method | |
| CN111206577A (en) | Construction method of steel guide wall foundation of sea area deepwater anchorage foundation | |
| JP2001107319A (en) | Aseismic reinforcing method of pier and aseismic reinforced structure | |
| JP3905776B2 (en) | Revetment structure | |
| CN111172988B (en) | A grouting pipe system for rock-embedded piles in rock-embedded sections of a pipe frame implanted with a pile-first method | |
| JPS5944445B2 (en) | Construction method for offshore structures | |
| JP3330018B2 (en) | Dry work method and work box used for it | |
| CN212200387U (en) | Diaphragm wall foundation steel guide wall structure in deep water soft silt area | |
| JPH09235714A (en) | Steel pipe pile for underwater structure and its construction method | |
| CN209816899U (en) | Floating pile-stabilizing platform for construction of steel pipe piles of offshore jacket type fan foundation | |
| CN111119159A (en) | A ground connection wall foundation steel guide wall structure in deep water and weak silt areas | |
| JP2817466B2 (en) | Work box | |
| USRE30823E (en) | Offshore platform | |
| JP4018288B2 (en) | Artificial ground made of box that can pass water and its construction method | |
| CN111441338B (en) | Unlocking repair method for steel sheet pile with dense sand layer | |
| JP3310452B2 (en) | Method of constructing continuous wall in water area and guide device for construction | |
| JP2022163916A (en) | Method for constructing foundation of on-water structure | |
| JP2953823B2 (en) | Construction method of offshore substructure | |
| JPH0423952Y2 (en) | ||
| CN119981113B (en) | Leakage sealing system and construction method of steel pipe pile interlocking cofferdam in marine environment with large tidal range |