JPS5947780B2 - Push-up construction method for buildings - Google Patents
[go: Go Back, main page]

JPS5947780B2 - Push-up construction method for buildings - Google Patents

Push-up construction method for buildings

Info

Publication number
JPS5947780B2
JPS5947780B2 JP10487078A JP10487078A JPS5947780B2 JP S5947780 B2 JPS5947780 B2 JP S5947780B2 JP 10487078 A JP10487078 A JP 10487078A JP 10487078 A JP10487078 A JP 10487078A JP S5947780 B2 JPS5947780 B2 JP S5947780B2
Authority
JP
Japan
Prior art keywords
columns
beam support
column
building
push
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP10487078A
Other languages
Japanese (ja)
Other versions
JPS5532815A (en
Inventor
達 岩井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP10487078A priority Critical patent/JPS5947780B2/en
Publication of JPS5532815A publication Critical patent/JPS5532815A/en
Publication of JPS5947780B2 publication Critical patent/JPS5947780B2/en
Expired legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】 この発明は、地上基礎部に設置した油圧ジヤツキだけで
、これを上下に移動させることなく、またクレーンの使
用なしに段階的に建物を押上げ架構できるもので、すな
わち基礎上に設置した複数個のジヤツキ上にプレキャス
トコンクリート製柱、梁受部材を置き、これに梁をかけ
渡した後に、ジヤツキの数個を順次交互に作動させ、こ
れにより柱を構成すべき縦横細分割したプレキャストコ
ンクリ−I・製ブロック体を1本ずつ柱、梁受部材下に
組入れ、接合して柱を段階的に作成しながら構造全体を
押上げることを特徴とするものである。
[Detailed Description of the Invention] This invention allows a building to be lifted up and constructed in stages using only a hydraulic jack installed on the ground foundation, without moving it up or down or using a crane. Precast concrete columns and beam support members are placed on multiple jacks installed on the foundation, and after the beam is spanned, several jacks are activated in turn, alternating the length and width of the columns. The feature is that finely divided precast concrete blocks are assembled one by one under columns and beam support members, and are joined to create columns in stages while pushing up the entire structure.

従来行なわれている押上げ(ジヤツキアップ)架構法は
、あらかじめ多数の鉄骨柱などを建てておき、これらに
沿って尺取り主力式に油圧ジヤツキを上昇させ、鉄骨梁
などを、このジヤツキで押上げるものであるが、この方
法では梁部材と共にジヤツキ本体も上方に移動しなけれ
ばならず、従って多層階の建物を構築する場合には、上
階の梁を押上げた後に、一度ジャッキを地面に降ろし、
改めてその下の階の梁をジヤツキに乗せて押上げるとい
う手間を繰り返さねばならなかった。
The conventional push-up (jettsuki-up) construction method involves erecting a large number of steel columns in advance, raising hydraulic jacks along these columns using the main force, and pushing up the steel beams with these jacks. However, with this method, the jack body must be moved upward along with the beam members, so when constructing a multi-story building, the jack must be placed on the ground once after the beams on the upper floors are pushed up. Unload,
I had to repeat the process of placing the beam on the floor below on a jack and pushing it up again.

また、上述のごとき鉄骨柱を必要とするため、これを建
てるためにクレーン等を用いなければならず、ジヤツキ
アップ工法におけるクレーン不要という利点が著しく損
なわれていた。
Furthermore, since the above-mentioned steel columns are required, a crane or the like must be used to erect them, and the advantage of the jack-up construction method, which does not require a crane, is significantly impaired.

この発明は、上記不都合を解消するもので、次に図面に
従って実施例を説明する。
The present invention solves the above-mentioned disadvantages, and embodiments thereof will now be described with reference to the drawings.

まず、作業手順としで、第1図に示すように、地中に基
礎杭1を頭部を地上面に並べ揃えで打設したのち、建物
地階部分を掘削し、基礎杭1間に仮設作業台2を設置す
る。
First, as shown in Figure 1, the work procedure is to drive foundation piles 1 into the ground with their heads aligned and aligned on the ground surface, then excavate the basement of the building, and perform temporary construction between the foundation piles 1. Install stand 2.

この基礎杭1の頭部には第2図で示されるような肉厚鋼
板3が設置され、その各隅角部には貫通孔4が設けられ
ている。
A thick steel plate 3 as shown in FIG. 2 is installed at the head of the foundation pile 1, and a through hole 4 is provided at each corner of the thick steel plate 3.

次いで、第3図に示すように、肉厚鋼板3上に4個で1
組の油圧ジヤツキ5を設置し、その上に第4図に示すよ
うな柱頭部に位置するべきプレキャストコンクリート柱
、梁受部材6を置き、これに第5図のプレキャストコン
クリート梁7を接合し、一体化するが、接合方法の一つ
として、柱、梁受部材6、梁7に水平貫通孔8,9を設
けて、孔内にプレストレス鋼素を通し、緊張する方法が
考えられる。
Next, as shown in FIG.
A set of hydraulic jacks 5 is installed, a precast concrete column and a beam support member 6 to be located at the column head as shown in FIG. 4 are placed thereon, and a precast concrete beam 7 shown in FIG. 5 is joined to this. One possible joining method is to provide horizontal through-holes 8 and 9 in the columns, beam support members 6, and beams 7, and to pass a prestressed steel element through the holes to tighten the parts.

このようにして、油圧ジヤツキ5のうち、まず3個を用
いて柱、梁接合部材6を押上げ残った1個のジヤツキ上
に第6図に示すような柱を構成すべき縦、横に細分割さ
れたプレキャストコンクリートブロック体10の1個を
入れ、このジヤツキを伸ばす。
In this way, first of all, three of the hydraulic jacks 5 are used to push up the column/beam joint member 6, and on the remaining one jack, the columns shown in FIG. 6 are to be constructed vertically and horizontally. One of the finely divided precast concrete block bodies 10 is inserted and this jack is stretched.

次いで、先に伸ばした3個のジヤツキのうち1つを縮め
て、同じくブロック体10をさらに1つ入れ、これを伸
ばし、残り2つのジヤツキも同様に作動させると、柱体
の横分割部分の一部が柱、梁受部材下に組入れられると
ともに、組立てた構造全体が、ブロック体10の縦幅だ
けビルドアップされ、かつ構造物は常に4個のジヤツキ
のうち3個で支承されている。
Next, by retracting one of the three jacks that were extended earlier, inserting one more block body 10 and extending it, and operating the remaining two jacks in the same way, the horizontally divided portion of the column will be A portion is assembled under the pillar and beam support member, and the entire assembled structure is built up by the vertical width of the block body 10, and the structure is always supported by three of the four jacks.

更に、ジヤツキを順次交互に作動させ、柱体を段階的に
作成していくが、この縦横分割ブロック体10の相互の
結合で、横方向の結合は、水平貫通孔11を設け、第7
図に示すようにネジ鋼棒12を挿入し、端部をナツト1
3で締めつけるようにし、縦方向は垂直貫通孔14を設
けて柱縦方向全体にプレストレス鋼棒を連通させ、柱、
梁受部材6に設けた垂直貫通孔15にも連通させて全体
を緊張すればよい。
Furthermore, the jacks are operated alternately in order to create the pillar bodies step by step. By connecting the vertically and horizontally divided block bodies 10 to each other, the horizontal connection is achieved by providing the horizontal through holes 11 and forming the seventh column.
Insert the threaded steel rod 12 as shown in the figure, and tighten the end with the nut 1.
3, and a vertical through hole 14 is provided in the vertical direction to communicate a prestressed steel rod throughout the column in the vertical direction.
It is sufficient to connect the vertical through hole 15 provided in the beam support member 6 to tension the entire body.

以上の作業を終了した段階で、建物の一層部分のラーメ
ン構造体が押上げ形成されたわけであるが、多層階の建
物を目的とする場合は、第8図に示すような四分割され
た柱、梁受部材16を1片づつ組入れ、これに梁7をか
け渡し、柱体を構成しながら順次押上げ構築する。
At the stage where the above work is completed, the rigid frame structure of the one-story part of the building has been pushed up, but if the purpose is to build a multi-story building, it is necessary to form pillars divided into four parts as shown in Figure 8. The beam support members 16 are assembled one by one, the beams 7 are placed over these, and the columns are successively pushed up and constructed.

なお、垂直方向のブレストス鋼棒での緊張方法であるが
、第9図に示すように、柱、梁受部材6.16に設けた
垂直貫通孔15の直径を上部大、下部小の二段階のもの
とし、最上部の柱、梁受部材6では、ジヤツキ上への設
置に先立って、垂直貫通孔15に、ネジ鋼棒17を通し
ておく。
In addition, regarding the tensioning method using vertical Brest steel rods, as shown in Fig. 9, the diameter of the vertical through hole 15 provided in the column and beam support member 6.16 is set in two stages: large in the upper part and small in the lower part. In the uppermost column and beam support member 6, a threaded steel rod 17 is passed through the vertical through hole 15 prior to installation on the jack.

この鋼棒17は、上部と下部とにおいて、それぞれナラ
1−18゜19で締付けられ部材に固定されている。
This steel rod 17 is fixed to the member by being tightened at an angle of 1-18 degrees 19 at the upper and lower portions, respectively.

次いで、上から二番目の梁構造が完成した時点で、第1
0図に示すように、階高に相当する長さのネジ鋼棒20
を柱の垂直貫通孔14に下から入れる。
Next, when the second beam structure from the top is completed, the first
As shown in Figure 0, a threaded steel rod 20 with a length corresponding to the floor height is
into the vertical through hole 14 of the column from below.

このネジ鋼棒20の下端は第11図のように、ナツト2
1と一体に形成され、上端を最上部の柱、梁受部材6内
のナツト19に挿入し、これをネジ込めば、垂直方向で
のプレストレスが得られる。
The lower end of this threaded steel rod 20 is connected to a nut 2 as shown in FIG.
1, and by inserting the upper end into the nut 19 in the uppermost pillar/beam support member 6 and screwing it in, prestress in the vertical direction can be obtained.

このようにして、ラーメン形成の操作をくり返し、最上
階より次階へと建物が押上がっていき、最上部の柱、梁
受部材16を肉厚鋼板3上に設置するに際しては、ジヤ
ツキ5を1つづつ取除きながら、四分割部分を1片づつ
組入れ、最下階の柱に垂直に通すネジ鋼棒20は、肉厚
鋼板3よりも下方に貫通孔4を通して突き出す長さのも
のとし、鋼板3の下面よりナツトで締付ければ柱は基礎
杭1に固定される。
In this way, by repeating the rigid-frame forming operation, the building is pushed up from the top floor to the next floor, and when installing the top column and beam support member 16 on the thick steel plate 3, The threaded steel rod 20, which is removed one by one and inserted one by one into the four-divided parts, and passed perpendicularly to the pillar on the lowest floor, has a length that projects through the through hole 4 below the thick steel plate 3, The column is fixed to the foundation pile 1 by tightening the nut from the lower surface of the steel plate 3.

以上のごとく、この発明は、基礎杭上に設置した油圧ジ
ヤツキのみで、別途クレーン等を使用することなく、し
かも、ジヤツキ本体を上下に移動させることなく、建物
を押上げ構築できるものである。
As described above, the present invention allows a building to be pushed up using only the hydraulic jack installed on the foundation pile, without using a separate crane or the like, and without moving the jack body up and down.

さらに、建物の最上階ラーメンが最初に出来上がるので
、この梁の上にデツキプレートなどを置き、コンクリー
トを打設してスラブを作り、これを雨や雪に対する被覆
として、それ以下の階の架構作業は天候に影響されない
という利点がある。
Furthermore, since the top floor of the building is completed first, deck plates are placed on top of the beams, concrete is poured to create a slab, and this is used as a cover against rain and snow for the construction of the floors below. has the advantage of not being affected by the weather.

【図面の簡単な説明】[Brief explanation of drawings]

第1図はこの発明の建造物の押上げ架構法の実施例を示
す正面図、第2. 3. 4.5. 6. 8図は実施
例の要部の斜面図、第7. 9.10.11図は同上の
断面図である。 1・・・・・・基礎杭、2・・・・・・仮設作業台、3
・・・・・・肉厚鋼板、4・・・・・・貫通孔、5・・
・・・・ジヤツキ、6,16・・・・・・柱、梁受部材
、7・・・・・・梁、8. 9.11・・・・・・水平
貫通孔、10・・・・・・ブロック体、12,1乙20
・・・・・・ネジ鋼棒、13.18.19.21・・・
・・・ナツト、14.15・・・・・・垂直貫通孔。
FIG. 1 is a front view showing an embodiment of the push-up frame method for buildings according to the present invention, and FIG. 3. 4.5. 6. Figure 8 is a perspective view of the main part of the embodiment, and Figure 7. 9.10.11 is a sectional view of the same as above. 1...Foundation pile, 2...Temporary workbench, 3
...Thick steel plate, 4...Through hole, 5...
... Jacket, 6, 16 ... Column, beam support member, 7 ... Beam, 8. 9.11...Horizontal through hole, 10...Block body, 12, 1 Otsu 20
...Screw steel rod, 13.18.19.21...
... Nut, 14.15 ... Vertical through hole.

Claims (1)

【特許請求の範囲】[Claims] 1 基礎上に設置した複数個のジヤツキ上にプレキャス
トコンクリート製柱、梁受部材を置き、これに梁をかけ
渡した後に、ジヤツキの数個を順次交互に作動させ、こ
れにより柱を構成すべき縦横細分割したプレキャストコ
ンクリート製ブロック体を1体ずつ柱、梁受部材下に組
入れ、接合しで、柱を段階的に作成しながら構造体全体
を押上げることを特徴とする建造物の押上げ架構法。
1. After placing precast concrete columns and beam support members on multiple jacks installed on the foundation and spanning the beams, several jacks should be activated in turn, thereby forming a column. Pushing up of a building is characterized by building up precast concrete blocks that are divided vertically and horizontally into small pieces one by one under columns and beam support members, and then joining them to push up the entire structure while creating columns in stages. Framing method.
JP10487078A 1978-08-30 1978-08-30 Push-up construction method for buildings Expired JPS5947780B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10487078A JPS5947780B2 (en) 1978-08-30 1978-08-30 Push-up construction method for buildings

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10487078A JPS5947780B2 (en) 1978-08-30 1978-08-30 Push-up construction method for buildings

Publications (2)

Publication Number Publication Date
JPS5532815A JPS5532815A (en) 1980-03-07
JPS5947780B2 true JPS5947780B2 (en) 1984-11-21

Family

ID=14392252

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10487078A Expired JPS5947780B2 (en) 1978-08-30 1978-08-30 Push-up construction method for buildings

Country Status (1)

Country Link
JP (1) JPS5947780B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6155239A (en) * 1984-08-16 1986-03-19 津田駒工業株式会社 Apparatus for automatic repairing control of inferior weft yarn

Also Published As

Publication number Publication date
JPS5532815A (en) 1980-03-07

Similar Documents

Publication Publication Date Title
US4294052A (en) Prefabricated load bearing structure
JPS5947780B2 (en) Push-up construction method for buildings
US3552080A (en) Method for erecting multistory buildings
JP3137448B2 (en) Construction method of concrete main tower
JP2897663B2 (en) How to build underground structures
JPH04161566A (en) Constructing apparatus for large space building
US4137684A (en) Building panel
JP2696486B2 (en) Building construction method
RU2836225C1 (en) Method of erection of monolithic and prefabricated monolithic frames
CN87103631A (en) The building construction method of composite building
JP2894217B2 (en) Building structural frame
SU1038422A1 (en) Pillar foundation
JP2508931B2 (en) Lift slab method
JP3252675B2 (en) All-weather temporary roof
JPH0657769A (en) Underground structure and its construction method
JPH0711160B2 (en) Construction method of frame in steel building
JP3124152B2 (en) Collapse prevention frame
JP3030591B2 (en) Building method
RU2002116423A (en) The method of construction of the bezelless frame of the building by the method of lifting floors
JPH0415841B2 (en)
JP3002795B2 (en) How to build a building with a basement
JPH0684686B2 (en) Standing method for precast concrete columns
CN117226992A (en) A device for prefabricating pre-tensioned hollow slabs and its construction method
CN120211477A (en) A formwork support system and construction method for high-altitude corridor structure
JPH05321222A (en) Provisionally installed landing bridge and its method of construction