Hanging scaffolding deviceInfo
- Publication number
- JPS6018508Y2 JPS6018508Y2 JP4464781U JP4464781U JPS6018508Y2 JP S6018508 Y2 JPS6018508 Y2 JP S6018508Y2 JP 4464781 U JP4464781 U JP 4464781U JP 4464781 U JP4464781 U JP 4464781U JP S6018508 Y2 JPS6018508 Y2 JP S6018508Y2
- Authority
- JP
- Japan
- Prior art keywords
- expressway
- floor
- horizontally
- pillars
- winder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Landscapes
- Bridges Or Land Bridges (AREA)
- Movable Scaffolding (AREA)
Description
【考案の詳細な説明】
この考案は吊足場装置に関し、特に高速道路桁の下面仕
上または補修時に用いる吊足場装置に関するものである
。[Detailed Description of the Invention] This invention relates to a suspended scaffolding device, and particularly to a suspended scaffolding device used for finishing or repairing the underside of a highway girder.
一般に高架となっている高速道路は、一般道路の中央に
沿って脚柱を立設し、該脚柱の上端に沿って橋桁を設け
て形威されているので、高速道路桁の下面仕上あるいは
補修等を行う場合には地上の一般道路を通行止めして吊
足場装置を組立て、そして高速道路桁の下面に吊下げる
ものであるが、この組立、吊下げ作業は前述のように一
般道路を通行止めしなければならないので全て深夜作業
となっていた。Elevated expressways are generally shaped by erecting pedestals along the center of the general road and installing bridge girders along the upper ends of the pedestals, so the underside of the expressway girder is finished or When carrying out repairs, etc., the above-ground general road is closed to traffic, and suspended scaffolding equipment is assembled and suspended from the underside of the expressway girder, but as mentioned above, this assembly and hanging work requires the closure of the general road. All work was done late at night because it had to be done.
従って深夜作業ということで労務費がかさむと共に、作
業上の安全の確保等の種々な問題が生じるという欠点を
有していた。Therefore, labor costs are high due to late-night work, and various problems arise, such as ensuring safety during work.
この考案は前述のような欠点を改善し、一般道路の通行
の一部を止めるだけで施行できるので昼間の作業でも行
うことのできる吊足場装置を提供することを目的とする
。The purpose of this invention is to improve the above-mentioned drawbacks and to provide a suspended scaffolding device that can be used even during the daytime because it can be implemented by simply stopping a portion of the traffic on a general road.
以下図面に示す実施例に基づいてこの考案を説明すると
、複数の長尺なパイプ乃至鋼棒から成るビーム1を縦、
横方向に並べると共に、隣接するビームの端部どうしを
連結具を介して連結固定して格子状をなす長方形状の基
板2を形威し、この基板2は、高速道路3の脚柱23間
の部分を、その長手方向において両側に2分割し、かつ
脚柱間の中央部で高速道路の幅方向に2分割して4分割
したものと略同−の大きさを有している。To explain this invention based on the embodiment shown in the drawings below, a beam 1 consisting of a plurality of long pipes or steel bars is
A rectangular board 2 is formed by arranging the beams in the horizontal direction and connecting and fixing the ends of adjacent beams to each other via connectors to form a lattice-like rectangular board 2. It has approximately the same size as a section divided into two on both sides in the longitudinal direction, and divided into two and quartered in the width direction of the expressway at the center between the pillars.
そして基板2の下面に、基板2の長さ方向に沿うと共に
、下端に車輪4を有しかつパイプ乃至鋼棒により枠組み
された長尺な補強枠5を垂直状に設けて前記基板2と連
結具を介して連結固定することにより移動可能な床盤6
を構威し、さらに前記補強枠5には前記基板2の上部に
位置する自昇降式のワインダ7が、高速道路桁のビーム
に対応するように設けられている。Then, a long reinforcing frame 5, which runs along the length of the board 2 and has wheels 4 at the lower end and is framed by pipes or steel bars, is provided vertically on the bottom surface of the board 2 and is connected to the board 2. Floor board 6 that can be moved by connecting and fixing it via tools
Furthermore, a self-elevating type winder 7 located above the base plate 2 is provided on the reinforcing frame 5 so as to correspond to the beam of the expressway girder.
このように構成された床盤6の全上面には複数の足場板
10が、各足場板10の一端部が隣接する一力の足場板
10の下方に、また他端部が、他方の足場板10の上方
にそれぞれ位置するように敷設されさらに敷設された足
場板10の上面に基板2の全面を覆うように防炎シート
11が敷設される。A plurality of scaffolding boards 10 are provided on the entire upper surface of the floor board 6 configured in this way, one end of each scaffolding board 10 is below the adjacent one-strength scaffolding board 10, and the other end is below the other scaffolding board 10. A flame retardant sheet 11 is laid so as to be positioned above the boards 10, and furthermore, a flameproof sheet 11 is laid on the upper surface of the laid scaffolding boards 10 so as to cover the entire surface of the substrate 2.
また前記床盤6の一側に沿ってL字状のシート取付梁1
2かその水平部分を基板2に固着することにより立設さ
れ、該シート取付梁12に防炎シート11を張設する。Also, along one side of the floor board 6 is an L-shaped seat mounting beam 1.
2 is erected by fixing its horizontal portion to the substrate 2, and the flameproof sheet 11 is stretched over the sheet attachment beam 12.
一方、高速道路桁の粱9を巻回している索条13の前記
粱9の下部分には滑車14が固着されており、各滑車1
4は前記床盤6が高速道路桁の下方に位置したとき床盤
6の上部に位置する各ワインタフに夫々対応するように
なっている。On the other hand, a pulley 14 is fixed to the lower part of the rope 9 of the cable 13 around which the wire 9 of the expressway girder is wound, and each pulley 1
Numerals 4 correspond to the wine toughs located above the floor board 6 when the floor board 6 is located below the expressway girder.
しかして前記床盤6を一般道路の車通折部以外の場所で
組立てたのちに車輪4により地上を移動させてこれを設
置しようとする高速道路3の脚柱間の4分割の1つの個
所の直下に位置し、かつ一側のシート取付梁12が高速
道路3の側方と対向するように位置させる。Therefore, after assembling the floor plate 6 at a place other than a traffic intersection on a general road, it is moved on the ground using wheels 4 and installed at one of the four divisions between the pillars of the expressway 3. The seat mounting beam 12 on one side faces the side of the expressway 3.
そして一端が床盤6に結着された吊下げ用索条8を前記
滑車14に巻回したのちその他端を各ワインダ7に巻回
して外部に導出する。Then, the suspension cable 8 whose one end is tied to the floor board 6 is wound around the pulley 14, and then the other end is wound around each winder 7 and led out to the outside.
こののち各ワインダ7の起動によって床盤6を上昇させ
て高速道路3の下面に接近させて前記高速道路の脚柱間
の4分割の1つの個所に対向させて吊下げる。Thereafter, by starting each winder 7, the floor plate 6 is raised, brought close to the underside of the expressway 3, and suspended so as to face one of the four divisions between the pillars of the expressway.
同様の方法により前記高速道路の脚柱間の4分割の他の
個所にもそれぞれ床盤6を吊下げ次いで各床盤6の基板
2のビーム1及び補強枠5の相互間を連結具で連結して
高速道路の脚柱間の全下面を覆うものである。Using the same method, the floor plates 6 are suspended from other parts of the four-way division between the pillars of the expressway, and then the beams 1 and reinforcing frames 5 of the base plate 2 of each floor plate 6 are connected with each other using connectors. This covers the entire lower surface between the pillars of the expressway.
(第4図)
モして床盤6を吊上げたのち第7図に示すように必要に
応じ水平梁9と床盤との適宜位置を索条17で連結する
。(FIG. 4) After hoisting the floor board 6, as shown in FIG. 7, the horizontal beam 9 and the floor board are connected at appropriate positions with cables 17 as required.
なお、いずれの場合であっても高速道路3の走行面端部
の路肩18にフック19を取付けて該フック19を介し
て索条20の両端をシート取付梁12の底部に結着l、
てシート取付梁12の強度を増加しており、また21は
梯子であって作業者が地上と床盤上とを往復する際に使
用するらのであり、22は高速道路の粱9と脚柱23と
の間を連結する連結具である。In either case, a hook 19 is attached to the road shoulder 18 at the end of the running surface of the expressway 3, and both ends of the cable 20 are tied to the bottom of the seat attachment beam 12 via the hook 19.
21 is a ladder used by workers to go back and forth between the ground and the floorboard, and 22 is a ladder 9 and a pedestal on an expressway. This is a connector that connects between 23 and 23.
この考案は前記のように作業を設置しようとする高速道
路の脚柱間の下面を縦、横に複数分割したその1つの分
割面に相当する大きさの床盤を組合わせて高速道路の脚
柱間下面全体を覆うようにするものであるから、通行量
のない部分での組立てが可能となり、従って従来のよう
に高速道路の下方の一般道路を全面通行止にすることな
く吊足場装置の吊下げ作業が行えて昼間作業ができ床盤
は他の設置区間にも再設置し得ると共に床盤の吊下げ設
置操作も容易に行えるほか床盤を高速道路の下面に近接
し得て該高速道路下面の補修作業などに便利であり、か
つ高速道路下面全体を覆うので、作業中の落下物が地上
に落下する惧れなく、地上での通行が安全に確保できる
という利点を有する。This idea was developed by dividing the lower surface between the pedestals of the expressway on which work is to be carried out into multiple sections vertically and horizontally, as described above, and combining a floor plate of a size corresponding to one of the divided planes. Since it covers the entire lower surface between pillars, it is possible to assemble it in areas with no traffic, and therefore it is possible to install suspended scaffolding equipment without completely closing off the general road below the expressway as in the past. The suspension work can be done during the day, the floorboard can be reinstalled in other installation sections, and the suspension and installation operation of the floorboard can be easily done. It is convenient for repair work on the underside of roads, and since it covers the entire underside of the expressway, it has the advantage of ensuring safe passage on the ground without the risk of falling objects falling to the ground during work.
図面は実施例を示し、第1図は基板の平面図、第2図は
組立てた状態を示した縦断面図、第3図は横断面図、第
4図は高速道路の下面に吊下げた状態を示す概略斜視図
、第5,6図は吊下げた際の要部を示す概略図、第7図
は他の実施例のものを示す図である。
図面において、1はビーム、2は基板、4は車輪、5は
補強枠、6は床盤、7はワインダ、8゜13.17,2
0は索条、9は高速道路の粱、11は防炎シート、12
はシート取付梁、14は滑車、15は連結杆、18は路
肩、19はフック、21は梯子である。The drawings show an example. Figure 1 is a plan view of the board, Figure 2 is a vertical cross-sectional view showing the assembled state, Figure 3 is a cross-sectional view, and Figure 4 is a board suspended under an expressway. FIGS. 5 and 6 are schematic diagrams showing the main parts when suspended, and FIG. 7 is a diagram showing another embodiment. In the drawing, 1 is a beam, 2 is a board, 4 is a wheel, 5 is a reinforcing frame, 6 is a floor board, 7 is a winder, 8° 13.17, 2
0 is a cable, 9 is a highway rope, 11 is a flame retardant sheet, 12
14 is a seat attachment beam, 14 is a pulley, 15 is a connecting rod, 18 is a road shoulder, 19 is a hook, and 21 is a ladder.
Claims (1)
速道路の脚柱間下面を横方向に2分割し縦方向に複数分
割したその1つに相当する大きさをもつ格子状の基板を
形成すると共に、その上面に足場を敷設し、また下面に
は補強枠と車輪とを取付けて移動可能な床盤を構威し、
この床盤の縦方向の一側に沿ってシート取付梁を立設す
ると共に、高速道路の粱と対応する所要位置に自昇降式
のワインダを複数個設け、このように構威された床盤を
、高速道路の梁に取付けて垂下した索条を前記ワインダ
に結合して、該ワインダを駆動することにより地上より
上昇して、前記取付梁が、高速道路の縦方向側面と対向
し、かつ床盤が高速道路の下面と対向するように前記高
速道路の梁に対し索条により吊下げ支持し、このように
して複数の床盤を縦横に配置して、前記高速道路の脚柱
間の下面を覆うように構威したことを特徴とする吊足場
装置。A lattice-shaped board that connects multiple beams vertically and horizontally and has a size equivalent to one of two horizontally divided lower surfaces between pillars of the expressway to be installed and multiple vertically divided sections. At the same time, scaffolding was laid on the top surface, and reinforcing frames and wheels were attached to the bottom surface to create a movable floor platform.
A seat mounting beam is erected along one side of the floor in the vertical direction, and a plurality of self-elevating winders are installed at required positions corresponding to the highway rails. is raised from the ground by connecting a hanging cable attached to a beam of the expressway to the winder and driving the winder, so that the attachment beam faces a longitudinal side surface of the expressway, and The floor plates are suspended and supported from the beams of the expressway by ropes so that they face the underside of the expressway, and in this way, a plurality of floor plates are arranged vertically and horizontally, and the floor plates are placed between the pillars of the expressway. A hanging scaffolding device characterized by being constructed so as to cover the lower surface.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP4464781U JPS6018508Y2 (en) | 1981-03-31 | 1981-03-31 | Hanging scaffolding device |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP4464781U JPS6018508Y2 (en) | 1981-03-31 | 1981-03-31 | Hanging scaffolding device |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS57157641U JPS57157641U (en) | 1982-10-04 |
| JPS6018508Y2 true JPS6018508Y2 (en) | 1985-06-05 |
Family
ID=29841569
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP4464781U Expired JPS6018508Y2 (en) | 1981-03-31 | 1981-03-31 | Hanging scaffolding device |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS6018508Y2 (en) |
-
1981
- 1981-03-31 JP JP4464781U patent/JPS6018508Y2/en not_active Expired
Also Published As
| Publication number | Publication date |
|---|---|
| JPS57157641U (en) | 1982-10-04 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP7265967B2 (en) | Cantilever device for bridge construction and bridge construction and demolition method | |
| JPS6018508Y2 (en) | Hanging scaffolding device | |
| JP2022097091A (en) | Manufacturing method of scaffold under elevated structure and delivering tool | |
| JPH0312172B2 (en) | ||
| JPS6213654A (en) | Assembling of air mat type suspension scaffold | |
| JPS6138066A (en) | Assembling of suspension scaffold | |
| JP2585174B2 (en) | How to fix scaffolding for temporary tents | |
| CN220150818U (en) | Steel truss type movable operation platform structure | |
| JP3100574B2 (en) | Suspended scaffold and its erection method | |
| JPH11293628A (en) | Hung scaffold assembling method for bridge | |
| JPH09184285A (en) | Exterior construction method for the bottom of elevated structures | |
| JPS598875A (en) | Construction of building roof | |
| JPH0533498A (en) | Construction transport scaffolding equipment | |
| JPS6124710A (en) | Assembling construction of suspension scaffold | |
| JPH0442435Y2 (en) | ||
| JPH0442434Y2 (en) | ||
| JPS621910A (en) | Working vehicle for repairing bridge and its construction | |
| JPH0326244B2 (en) | ||
| JP2590671B2 (en) | Construction method of steel frame using overhead crane frame | |
| JPS61282549A (en) | Working scaffold in tank | |
| JPS6335053Y2 (en) | ||
| JPS62121272A (en) | Construction of scaffold panel | |
| JPH0423927Y2 (en) | ||
| JPH0492006A (en) | Setting temporary bridge of hanging structure | |
| CN118727602A (en) | Bottom surface construction method for elevated steel box girder |