JPS6028977B2 - Construction method and device for underground structures - Google Patents
Construction method and device for underground structuresInfo
- Publication number
- JPS6028977B2 JPS6028977B2 JP53087723A JP8772378A JPS6028977B2 JP S6028977 B2 JPS6028977 B2 JP S6028977B2 JP 53087723 A JP53087723 A JP 53087723A JP 8772378 A JP8772378 A JP 8772378A JP S6028977 B2 JPS6028977 B2 JP S6028977B2
- Authority
- JP
- Japan
- Prior art keywords
- shaft
- leading
- tunnel
- trailing
- underground
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Description
【発明の詳細な説明】
〈産業上の利用分野)
この出願の発明は低温液化ガスタンクを地下タンクとし
て構築する場合に、地盤中に形成する止水壁等の地盤中
の構造物の坑道を用いて築造方法と該築造方法に直接使
用する築造装置に関する発明であり、特に、坑道を掘進
するプロセスに先導坑道から後続坑道掘削士砂を凝固材
を混入したもの等で該後続坑道を埋戻すことにより地盤
中に内在的に構築物を築造してしまうようにした地中構
造物の築造方法とそれに直接使用する菱薄に係る発明で
ある。[Detailed description of the invention] <Industrial application field> The invention of this application uses a tunnel of a structure in the ground, such as a water-stop wall formed in the ground, when constructing a low-temperature liquefied gas tank as an underground tank. This invention relates to a construction method and a construction device directly used in the construction method, and in particular, to backfilling of the trailing shaft with sand from a leading shaft to a trailing shaft excavator mixed with a coagulating material in the process of digging a shaft. This invention relates to a method for constructing an underground structure in which the structure is built intrinsically in the ground, and a rhombus thin film directly used therein.
く従来技術)
周知の如く地盤中に構造物を築造する施工態様は種々あ
るが、近時構造物の大型化によってさまざまな問題が新
たに生じてきている。(Prior Art) As is well known, there are various construction methods for constructing structures in the ground, but as structures have recently become larger, various new problems have arisen.
例えば、LMG等の低温液化ガスの貯蔵タンクでは公害
、風致、景観等の対策として地下式タンクが築造される
場合があるが、地下深部に於ける不透水層とタンク底板
や側坂間の地下水が不可避的な温度降下に伴って凍上を
生じ、設計施工上問題となる。For example, in storage tanks for low-temperature liquefied gas such as LMG, underground tanks are sometimes constructed as a countermeasure against pollution, scenery, and scenery, but underground water flows between the impermeable layer deep underground and between the tank bottom plate and side slope. Frost heave occurs due to the inevitable drop in temperature, which poses a problem in design and construction.
〈発明が解決しようとする問題点〉
したがって、これに対処するにはタンク側部に於て不透
水層まで止水壁を築造することにより、該止水壁と不透
水層とタンク底板間の地下水を脱水すれば良いが、地下
100肌を越す真相部に存在する不透水層までに達する
止水壁を現在の連続地中壁工法によって構築することは
工事の規模が大きい等の点から不可能に近く、そのため
、現実にはせし、ぜし、地下30机程度までしか築造さ
れ得ないという止水壁の制約によりタンク容量も規制さ
れてしまう欠点があった。<Problems to be Solved by the Invention> Therefore, in order to solve this problem, by constructing a water-stop wall up to the impermeable layer on the side of the tank, the gap between the water-stop wall, the impermeable layer, and the tank bottom plate is improved. It is sufficient to dehydrate the groundwater, but it is not practical to construct a cutoff wall that reaches the impermeable layer that exists in the depths of more than 100 layers underground using the current continuous underground wall construction method due to the large scale of the construction work. This is close to possible, and as a result, in reality, only about 30 tanks can be built underground, which means that the tank capacity is also restricted due to the water-stop wall.
さりながら、前述の如く、備蓄量増大等のタンクの大型
化のニーズがあるため、タンクの巨大化は設計条件を困
難にし、脱水の実現のためには「上記止水壁の地下10
0肌を越す深度の不透水層までの構築が望まれるように
なってきている。However, as mentioned above, there is a need for larger tanks to increase storage capacity, etc., so increasing the size of the tank makes the design conditions difficult.
It has become desirable to construct an impermeable layer with a depth exceeding zero skin.
而して、上述の従来技術において単にスケールアップで
対処することは現実には技術的に種々の難点があった。
勿論、地中構造物としての対処技術は上記止水壁に限る
ものではないが、およそ、地表からの構築をする限りで
は超深度に達し、且つ、大サイズの壁体等の築造では掘
削精度、掘削装備、構築工法、掘削土砂搬出等の問題を
伴わざるを得ないものである。Therefore, in the above-mentioned conventional technology, there are various technical difficulties in dealing with the problem simply by scaling up.
Of course, the techniques for dealing with underground structures are not limited to the above-mentioned cut-off walls, but as long as they are constructed from the ground surface, they can reach ultra-deep depths, and when constructing large-sized walls, excavation precision is required. However, it is inevitable that there will be problems with excavation equipment, construction methods, excavated soil, etc.
この発明の目的は上述従来技術に基づく地中構造物の施
工の問題点を解決すべき技術的課題とし、技術的発想の
完全転換によって垂直の施工を水平に連続させる代わり
に水平の施工を垂直に重ねるようにして止水壁等を形成
し得るようにし、建設産業における地中掘削技術利用分
野に益する優れた地中構造物の築造方法及び装置を提供
せんとするものである。The purpose of this invention is to solve the problems of construction of underground structures based on the above-mentioned prior art as a technical problem to be solved. It is an object of the present invention to provide an excellent method and apparatus for constructing an underground structure that can be stacked to form a water-stopping wall, etc., and that is useful in the field of underground excavation technology application in the construction industry.
く問題点を解決するための手段・作用〉
上述目的に沿い先述特許請求の範囲を要旨とするこの発
明の構成は、前述問題点を解決するために既知のトンネ
ル工法を利用することにより、常に切羽に近いところに
作業点を置き、地中に水平の坑道を掘進するに先導坑道
と後続坑道の間にて先導坑道より後続坑道に掘削土砂を
セメント等の凝固材を混入したものを混合して埋設する
ようにして埋戻し的に地盤坑壁を一種の型枠に用いて構
造体を築造することを基本とし、更に、該築造工程を用
いて種々の地下構造物を垂直方向に積み重ねながら形成
させるようにした技術的手段を講じたものである。Means and operation for solving the above-mentioned problems In accordance with the above-mentioned object, the structure of the present invention, which is summarized in the above-mentioned claims, always achieves the above-mentioned problems by utilizing the known tunnel construction method. A work point is placed near the face, and a horizontal tunnel is excavated into the ground. Between the leading shaft and the trailing shaft, the excavated soil is mixed with a coagulating material such as cement from the leading shaft to the trailing shaft. The basic method is to build structures using the ground tunnel walls as a type of formwork by backfilling them, and furthermore, using this construction process, various underground structures can be stacked vertically. This technology takes technical measures to allow the formation of
〈実施例〉
次に、この出願の発明の実施例を図面に従って説明すれ
ば以下の通りである。<Example> Next, an example of the invention of this application will be described below with reference to the drawings.
第la,lb図に示す態様はこの出願の発明の基本的態
様を示す実施例であって、地山1の地盤2内に地表Gか
ら所定の掘進機3を用いて在釆のトンネル工法により先
導坑道4を掘削していく。The embodiment shown in Figures 1a and 1b is an embodiment showing the basic embodiment of the invention of this application, in which a predetermined excavator 3 is used to dig into the ground 2 of the ground 1 from the ground surface G by the existing tunnel construction method. Lead shaft 4 will be excavated.
原理的には該先導坑道4で発生する掘削土砂をもって直
ちに後尾部を埋戻せばよいが、これは所謂「ミミズの生
態」そのままであって、構造物を形成しない。そこで、
掘進機3をして先端部の掘削装置5と中央部の搬送機構
部6、後部の充填部の埋戻し作業部7から構成させ、地
盤2の状況によっては所謂シールド型の掘削機とし、掘
削土砂を構造材に適するよう加工する。In principle, the trailing portion can be immediately backfilled with the excavated soil generated in the leading tunnel 4, but this remains the so-called "earthworm ecology" and does not form a structure. Therefore,
The excavator 3 is made up of an excavator 5 at the tip, a transport mechanism section 6 at the center, and a backfilling section 7 at the rear filling section. Process earth and sand to make it suitable for structural materials.
勿論、土砂の搬出に見合わせて外部からコンクリートの
供給をしても良いことは当然である。Of course, it is also possible to supply concrete from outside in conjunction with the removal of earth and sand.
而して、該先導坑道4が後尾部から掘削土砂を排除し構
造物の部分形成をしながら所定長の長さを完坑した後、
該先導坑道4上に可及的に近接して平行に次段の後続坑
道8を○,のレベルから同じ掘進機3を作動させて上述
同様に掘削形成させていく。そして、該後続坑道8の掘
削土砂は搬送機構部6のコンベヤにより充填部7にてそ
れを骨材としてセメントと混合させ、ソィルコンクリー
ト等にして第la図に示す様に下段の先導坑道4に埋戻
しながら充填材として充填し、地中構造物の部分9とし
て形成させその工程を継続させる。After the leading tunnel 4 has completed a predetermined length while removing the excavated earth and sand from the rear part and partially forming the structure,
The same excavator 3 is operated to excavate and form the following tunnel 8 in the next stage as close to and parallel to the leading tunnel 4 from the level indicated by ○ in the same manner as described above. Then, the excavated earth and sand of the following tunnel 8 is mixed with cement as aggregate in the filling section 7 by the conveyor of the conveyance mechanism section 6, and is turned into soil concrete etc. as shown in FIG. It is filled as a filler while backfilling, forming part 9 of the underground structure, and the process is continued.
その間、掘削士砂はセメントを加え補給水(もしくは手
近な地下水等を用い)と共に充分蝿拝混合されて圧嬢さ
せ、その断面は第lb図に示す様にされる。During this time, the excavator's sand is thoroughly mixed with cement and make-up water (or using nearby groundwater, etc.) to compress it, and its cross section is made as shown in Figure lb.
尚、同図に於て右半部の地山1の表現は、構造物の擁壁
として形成し、点線部分1′を切士掘削部分とする態様
を示すものである。Incidentally, the expression of the ground mass 1 in the right half of the figure shows an embodiment in which it is formed as a retaining wall of a structure, and the dotted line portion 1' is an excavated portion.
而して、第2図に示す実施例は上述基本態様に従う態様
を説明するものであって、上記先導坑道4と後続坑道8
とは2段を1組とした一連の作業として考えられ、上記
実施例に於ける後尾部での埋戻し1こよる構築による一
層合理化するものである。The embodiment shown in FIG. 2 explains an embodiment according to the above-mentioned basic embodiment, and includes the leading tunnel 4 and the following tunnel 8.
This can be considered as a series of operations in which two stages are set as one set, and the construction is further streamlined by one backfilling at the rear part in the above embodiment.
即ち、上述態様では先導坑道4の後尾部は同時に地表G
からの材料の補給部でもあるから、埋戻し作業と重複し
現実的でない。That is, in the above embodiment, the rear part of the leading tunnel 4 is simultaneously
Since it is also a replenishment section for materials from the ground, it is not practical as it overlaps with backfilling work.
そのため、この2作業を1組として扱えば、先導坑道4
を一時空洞としておき、後続坑道8を掘進するに従って
、その後尾部からの補給に煩されることなく掘削土砂を
埋戻し機構部を構築することが出来る。Therefore, if these two operations are treated as one set, the lead tunnel 4
is temporarily made into a cavity, and as the subsequent tunnel 8 is excavated, it is possible to construct a backfilling mechanism with excavated earth and sand without having to worry about replenishing from the rear part.
ここで、先導坑道4内には、構造物の構築以前に空洞が
崩壊するのを防止し、又、先導坑道4上方に対する掘進
機3の支持のためにセグメント支保工10、及び、その
盛り替えを行って施行を続ける。Here, in the leading tunnel 4, segment supports 10 are installed to prevent the cavity from collapsing before the construction of the structure, and to support the excavator 3 above the leading shaft 4, and to replace the segment supports 10. and continue enforcement.
このようにして2段目の後続坑道8が掘進されると、図
示する如く第3の後続坑道8′が第2の後続坑道8の上
段に同じく掘進機3を稼動させて上述同様埋戻し裡に下
段坑道8に掘削土砂とセメント等の凝固材を混合して充
填し地中構造物の部分9を接続させて構築形成する。When the second succeeding tunnel 8 is excavated in this way, a third succeeding tunnel 8' is dug into the upper stage of the second succeeding tunnel 8 by similarly operating the excavator 3 and backfilling the same as described above. Then, the lower tunnel 8 is filled with a mixture of excavated earth and sand and a coagulating material such as cement, and the parts 9 of the underground structure are connected and constructed.
尚、上述プロセスにおいて、セメントや水の材料の他に
2段目以上の坑道8,8′の掘進機3用の動力、水、ェ
ア等はケーブル(パイプ)11の接続により行い、場合
によっては余剰土砂も水と共に混合状態で接続パイプを
介して最上段の後続坑道8′から地表Gへ排出する。In addition, in the above-mentioned process, in addition to cement and water, power, water, air, etc. for the excavator 3 in the tunnels 8 and 8' in the second and higher stages are provided by connecting cables (pipes) 11, and in some cases Excess earth and sand are also discharged to the ground surface G from the uppermost succeeding tunnel 8' through a connecting pipe in a mixed state with water.
尚、掘進機3の前進は常法にならって後方支保工101
こ反力を取っても、周辺地山との摩擦に反力を取っても
良く−、又、下段の構築済みの構造物の部分9に油圧ジ
ャッキの推進反力をとるようにしても良い。In addition, the advance of the excavator 3 follows the usual method, and the rear support 101
The reaction force may be taken from this reaction force, the reaction force may be taken from friction with the surrounding ground, or the propulsion reaction force of the hydraulic jack may be taken from the part 9 of the lower structure that has already been constructed. .
更に、構築材としてのソィルコンクリート等は防水剤入
りが好ましいが、第3図に示す様に止水板12を打継ぎ
部に入れるようにしても良い。Further, it is preferable that soil concrete or the like used as a construction material contains a waterproofing agent, but a water stop plate 12 may be inserted into the pouring joint as shown in FIG.
そして、地中構造物としての各部分9の補強は水平方向
を主筋とし、垂直方向を副筋としてメッシュ筋12′を
埋戻しのコンクリート打設前に補給組込みを行う。又、
垂直方向の鞍手を少くするために、クリンブネツトを用
いるのが有効で、水平筋を入れるだけで上下のラップロ
スを避けて接続することが可能である。The reinforcement of each part 9 as an underground structure is carried out using mesh reinforcements 12' as main reinforcements in the horizontal direction and secondary reinforcements in the vertical direction, and is supplemented and incorporated before backfilling with concrete. or,
In order to reduce the number of vertical saddles, it is effective to use a crimp net, and by simply adding horizontal striations, it is possible to connect the top and bottom without lap loss.
このようにして各部分9の上下方向接続は第4図の様に
形成されるが、勿論、垂直構造に限るものではなく、断
面額斜カーブ状でも可能である。In this way, the vertical connection of each part 9 is formed as shown in FIG. 4, but of course the structure is not limited to a vertical structure, and a cross-section having an oblique curve shape is also possible.
上記実施例はこの出願の発明の最も基本的態様であり、
原理的な発生順に可能性を説明してきたものである。次
に、上述2発明からより実際的に具体化される第3の発
明について、掘進機3、及び、掘進プロセス、埋戻しプ
ロセスを第5,6a〜6d図に基づいて説明すると、掘
進機3はシールド型の掘進機とするのが良く、本体円筒
状ケーシング13に油圧ジャッキ14を介して前設され
た掘削装置15を装備して進退可能状態で掘削し、掘削
土砂は該掘削装置15の後部の搬送機構部6のコンベア
16によりコンクリートミキサー17に投入され、セメ
ントと水を混合燈拝し、上記埋戻し機構部7から下方の
先導坑道4の後方へと投入される。The above embodiment is the most basic aspect of the invention of this application,
The possibilities have been explained in the order in which they occurred in principle. Next, regarding a third invention that is more practically embodied from the above-mentioned two inventions, the excavator 3, the excavation process, and the backfilling process will be explained based on FIGS. 5 and 6a to 6d. It is preferable to use a shield type excavator, which is equipped with an excavator 15 installed in front of the cylindrical casing 13 of the main body via a hydraulic jack 14, and excavates in a state where it can advance and retreat. The cement is put into a concrete mixer 17 by the conveyor 16 of the rear conveyance mechanism section 6, and the cement and water are mixed and then thrown from the backfilling mechanism section 7 to the rear of the leading tunnel 4 below.
而して、前記第2の発明で先導坑道4と後続坑道との組
合せを行ったことに対応して、当該第3の発明では上述
上段に於ける作業に対して下段に於けるプロセスと装置
が開示され、詳示するに初段の先導坑道4の始端には連
接機構部18としてケーシソグ13と同径のサブケーシ
ングが設置され、後続坑道8のスタートした時点で掘進
機3のケーシング13下端に設けた接続部19を介して
上下一体に連接される。Therefore, in response to the combination of the leading tunnel 4 and the trailing tunnel in the second invention, the third invention provides a process and equipment in the lower stage for the work in the upper stage. In detail, a sub-casing having the same diameter as the casing 13 is installed as a connecting mechanism part 18 at the starting end of the first-stage leading tunnel 4, and when the trailing shaft 8 starts, a sub-casing is installed at the lower end of the casing 13 of the excavator 3. The upper and lower parts are integrally connected via the connecting portion 19 provided.
ここに該接続部19はケーシングの両円筒体を直接外接
させることなく、前段との打継ぎに要する寸法を離隔さ
せておく寸法とする。Here, the connecting portion 19 does not directly circumscribe the two cylindrical bodies of the casing, but has a dimension that allows a distance required for connection with the previous stage.
又、連接機構部18のサブケーシングは掘進機3の本体
のケーシング13と上面に於て連通し、上下の作業が行
われるべく前方作業室20と後方成形部21が仕切壁2
2によって構成されている。Further, the sub-casing of the connecting mechanism section 18 communicates with the casing 13 of the main body of the excavator 3 on the upper surface, and the front working chamber 20 and the rear molding section 21 are connected to the partition wall 2 so that vertical work can be performed.
It is composed of 2.
尚、23,23は所望の関口を持った作業床である。Note that 23, 23 is a work floor having a desired entrance.
そして、先導坑道4に前段プロセスで予め坑蟹に蓬込ん
で巻立てられた支保工としてのセグメント24,11を
前部作業室20で解体し、上記ケーシング13の上部に
軸方向に沿って設けられたレール25のトロリーホィス
ト26により該解体セグメント24を吊り上げ後送し、
本体ケーシング13の後部の作業室27で掘削後続坑道
8′に盛り替えて支保工18として蓬込み巻立てる。Then, the segments 24 and 11 used as supports, which had been rolled up in the leading shaft 4 by hanging down in the shaft in advance in the previous stage process, are dismantled in the front work room 20, and installed on the upper part of the casing 13 along the axial direction. The dismantled segment 24 is lifted and transported by the trolley hoist 26 on the rail 25,
In the working chamber 27 at the rear of the main body casing 13, it is transferred to the tunnel 8' following excavation and rolled up as a support 18.
このようにして、搬送機構部6は、前方上方から後方下
方への掘削土砂輸送投入と、前方下方から後方上方への
器材の移動と、構築材料の混練の3作業を行うようにさ
れている。又、該ケーシング本体13の後部の油圧ジャ
ッキ28をして支保工11に推進反力をとるようにし、
更に、サブケーシング18の底部29の油圧ジャッキ2
8により下方の地中構造物部分9に反力をとり全装置に
対する上下の偏橋推進が生じないようにして掘進する。In this way, the transport mechanism section 6 performs three operations: transporting excavated soil from the upper front to the lower rear, moving equipment from the lower front to the upper rear, and kneading construction materials. . In addition, a hydraulic jack 28 at the rear of the casing body 13 is used to take a propulsion reaction force to the shoring 11,
Furthermore, the hydraulic jack 2 at the bottom 29 of the sub-casing 18
8, the underground structure portion 9 below is subjected to a reaction force, and the excavation is carried out in a manner that prevents the vertically biased propulsion of all the equipment from occurring.
次に「前記ミキサー17によって鷹梓混合された掘削土
砂を主骨材とするコンクリートはもサブケーシング亀8
の埋戻し作業部である後部充填部7‘こて前部作業室2
0側から供給されるメッシュ筋12′と共にサプケーシ
ング亀燈の後半の成形部30‘こ投入され、上面に仮設
角材31を埋設しておく。Next, "Concrete casing 8 whose main aggregate is the excavated soil mixed by the mixer 17"
Rear filling section 7' which is the backfilling section of trowel front working chamber 2
The mesh strips 12' supplied from the 0 side are inserted into the molded part 30' in the latter half of the sap casing turtle light, and a temporary square member 31 is buried in the upper surface.
そして、該サブケーシング18の仕切壁22を前方型枠
とし充填され下段先行既設地中構造部分9に打継がれ、
その場合、該既設地中構造部分9に対してはそのラック
部32に確実に噛合い打継がれる。Then, the partition wall 22 of the sub-casing 18 is used as a front formwork to be filled and connected to the lower preceding existing underground structure part 9,
In that case, the rack portion 32 of the existing underground structure portion 9 is reliably engaged and connected.
尚、33は作業床であり、前部作業室20内下方のセグ
メントと補強メッシュのためのものである。Note that 33 is a working floor, which is used for the lower segment and reinforcing mesh inside the front working chamber 20.
又、上記充填部7に於て「第6c図に示す様に、所定間
隔を介して平行な一対の型枠34,34を設けて該型枠
34,34間のみにソィルコンクリートの充填材を埋戻
し充填して地中構造部分9としても良く、サブケーシン
グ18との間の間隙には掘削土砂35を埋戻して第6d
図に示す様にするのが良いし、又、設計によっては1個
のみ型枠34を設けて第14図に示す様に一側平面他側
弧型のDの字型の地中構造部分9の連続体にしても良い
o尚、地中構造部分9の上面打継部を凹凸式ラックに形
成することは前述の角材31をソィルコンクリ−ト硬化
前に脱型すれば良く、これによりシールド型掘進機3の
推進反力を確実にとることが出来る。In addition, in the filling section 7, a pair of parallel formworks 34, 34 are provided at a predetermined interval as shown in Fig. 6c, and soil concrete filling material is placed only between the formworks 34, 34. may be backfilled to form the underground structure part 9, and the gap between the subcasing 18 and the subcasing 18 may be backfilled with excavated soil 35 to form the 6th d
It is preferable to use the structure as shown in the figure, or depending on the design, only one formwork 34 may be provided, as shown in FIG. 14, as shown in FIG. It is also possible to form the upper surface joint part of the underground structure part 9 into a concave-convex type rack by removing the square timber 31 from the mold before the soil concrete hardens. The propulsion reaction force of the excavator 3 can be reliably taken.
このようにして、先導坑道8と後続坑道8″とに於てシ
ールド型掘進機3を用いて全構築作業、即ち、上下2段
の掘削、セグメント盛り替え、埋戻し充填が現地に於て
交叉して同時平行的に行われることになる。In this way, all the construction work in the leading tunnel 8 and the trailing tunnel 8'' using the shield type excavator 3, that is, the excavation of the upper and lower two stages, segment replacement, and backfilling, are carried out at the same time on site. This will be done simultaneously and in parallel.
而して、上述原理的発明に基づいて低温液化ガス地下タ
ンクを構築する場合の超深度不透水層までの地中止水壁
の構造物を築造する第4の発明について以下説明すると
、例えば、第7,8図に示す様に、地盤2に構築する予
定の地下タンク形成部位36に対して設定距離離隔した
部位に充分に下方深部にある不透水層に達するまで設定
サイズの立坑のアクセス坑38を適宜に掘削し、その底
部39より該止水壁を構築するべく第7図に示す様に、
掘進機3により第1段の先導坑道4を円環状に掘削し、
該アクセス坑38に達させ、更に、該アクセス抗38を
連絡用兼発進部として第2段の上部後続坑道8′を第8
図に示す様に平行裡に掘削し、上述したプロセスにより
支保エー1を巻立て、解体し〜盛り替え者立て、掘削、
ソィルコンクリート埋戻し充填を行し、勺止水壁40の
地下構造物の部分9を順次上方に継足して円形に築造し
ていく。The fourth invention for constructing an underground water wall structure up to an ultra-deep impermeable layer when constructing a low-temperature liquefied gas underground tank based on the above-mentioned principle invention will be described below. As shown in Figures 7 and 8, an access shaft 38 of a predetermined size is installed at a predetermined distance away from the underground tank formation site 36 that is planned to be constructed in the ground 2 until it reaches an impermeable layer located sufficiently below and deep. As shown in Fig. 7, in order to excavate the water cut-off wall appropriately from the bottom 39,
The first stage leading tunnel 4 is excavated in a circular shape by the excavator 3,
The access shaft 38 is used as a communication and starting part to connect the upper trailing shaft 8' of the second stage to the eighth stage.
As shown in the figure, excavation is carried out in parallel, and using the process described above, the support A1 is rolled up, dismantled, replaced, excavated,
Soil concrete backfilling is carried out, and the underground structure portion 9 of the water stop wall 40 is successively added upward to construct a circular structure.
その間、動力、水、ェア「コンクリート等の補充連結、
及び、余剰土砂の排出は後続坑道8から該アクセス坑3
8で中継処理するようにする。During this time, power, water, air, replenishment connections for concrete, etc.
Excess earth and sand is discharged from the subsequent tunnel 8 to the access shaft 3.
8 to perform relay processing.
この時ト屈伸工事は1周周回毎に発進部に帰房するので
、該発進部で掘進機3を上昇させても良いが、この間に
坑道1段分の軽度の上昇勾配をとるように坑道8をスパ
イラル状に屈伸するのがより現実的である。即ち、当該
実施例では掘削坑道はスパイラルに連続して周回する唯
1本の坑道となり、上述のような先導、後続の関係がな
くなるから先導部、後続部、先段、後段等と言い替える
ことになる。At this time, the tunnel excavator 3 may be raised at the starting point since the bending and stretching work returns to the starting point after each lap. It is more realistic to bend and stretch 8 in a spiral shape. That is, in this embodiment, the excavation tunnel is the only tunnel that circulates continuously in a spiral, and the above-mentioned relationship between leading and trailing is eliminated, so it can be referred to as leading part, trailing part, first stage, rear stage, etc. Become.
勿論、スパイラル掘削、埋戻し、打設の各プロセスにお
いてアクセス抗38自体も順次鶴固めて埋込まれてしま
ってよい。そして、上述プロセスに用いられるシールド
型掘進機は本体を中心に前後部を関節式に構成するか、
或は、所定の曲率をもたせて曲折させておく。Of course, in each process of spiral excavation, backfilling, and pouring, the access pit 38 itself may be sequentially hardened and buried. The shield type excavator used in the above process is constructed with front and rear parts articulated around the main body, or
Alternatively, it may be bent with a predetermined curvature.
そして、この掘進機は1基を用いても良いが、複数基位
相をずらせて平行状態で作動させるのがよい。Although one excavator may be used, it is preferable to operate a plurality of excavators in a parallel state with their phases shifted.
勿論、防水コンクリート、配筋等の施工は前述態様を用
いるものであり、屈伸に伴うジャッキ反力、セグメント
盛り替え、瀦拝混合等の作業は実質同一作業により行う
。Of course, the above-mentioned method is used for construction of waterproof concrete, reinforcement, etc., and operations such as jack reaction force due to bending and stretching, repositioning of segments, and mixing of worship services are performed by substantially the same operations.
このようにして施工することにより、第9図に示す様に
、アクセス坑38の底部39を発進部兼連絡部として先
導部と後続部とを平行に接続させて掘進機3によりスパ
イラル状に形成させることにより、最終的には、第10
図に示す様に、地下タンク予定部位36を完全に囲橋し
た止水壁40を不透水層37に到達させて地上まで形成
させることが出来る。By constructing in this way, as shown in FIG. 9, the bottom 39 of the access shaft 38 is used as a starting part and a connecting part, and the leading part and the trailing part are connected in parallel and formed in a spiral shape by the excavator 3. Finally, the 10th
As shown in the figure, a water stop wall 40 that completely surrounds the planned underground tank site 36 can be formed to reach the impermeable layer 37 and extend above ground.
又、上述実施例は1本のアクセス坑道38を削孔して施
工した態様であるが、第11図に示す様に、複数本のア
クセス坑道38,38…・・・削孔し、不透水層37内
に第1段の発進部41,41・・・・・・を該アクセス
坑道38の底部に設けて設定スパイラルの部分先導坑道
4,4・…・・を掘削し、次位のアクセス坑道38に達
するまでに隣位の先導坑道4の後続坑道8となる角度に
斜行掘進するようにし、続いて、次の上段の後続坑道8
,8……を平行状態に掘削し、したがって、第12図の
如く、複段スパイラル施工を能率良く行うことが出来る
。Further, in the above-mentioned embodiment, one access tunnel 38 was drilled and constructed, but as shown in FIG. A first-stage starting part 41, 41, . Diagonal excavation is carried out at an angle to form the trailing shaft 8 of the adjacent leading shaft 4 until reaching the shaft 38, and then the trailing shaft 8 of the next upper stage is dug.
, 8... are excavated in parallel, so that multi-stage spiral construction can be carried out efficiently as shown in Fig. 12.
これを理解のために卑近な例をとれば、理髪店の3色ス
パイラル看板を想起すればよい。To understand this, let's take a common example: think of a three-color spiral signboard for a barber shop.
当該実施例に於ては大径の止水壁40等を構築する場合
、アクセス坑道38,38・・・・・・が複数あるので
通常の鉱山技術、トンネル技術を応用して動力、ェア、
コンクリートの搬入補給が可能であり、又「余剰土砂の
排出も効率良く行える。In this embodiment, when constructing a large-diameter water stop wall 40, etc., there are multiple access tunnels 38, 38, etc., so normal mining technology and tunnel technology can be applied to provide power and air supply. ,
Concrete can be brought in and replenished, and excess earth and sand can also be efficiently discharged.
このようにして、各アクセス坑道38,38・・・…も
埋戻して充填することにより、第13図展開図に示す様
に、結果的に、地中壁40を確実に構築することが可能
となる。尚、この出願の発明の実施例は低温液化ガス地
下タンクの止水壁構築にのみ用いられるものでなく、四
隅にアクセス抗を有する角形構造物の如他の地中構造物
にも適用可能であることは勿論である。In this way, by backfilling and filling each access tunnel 38, 38..., it is possible to reliably construct the underground wall 40 as shown in the exploded view in Figure 13. becomes. Note that the embodiments of the invention of this application are not only used for constructing water-stop walls for underground tanks of low-temperature liquefied gas, but can also be applied to other underground structures such as rectangular structures having access pits at the four corners. Of course there is.
又、アクセス坑を施工に伴う連絡坑とする場合、地上と
の華直坑でなく、許容される限りのスパイラルランプウ
ェィとしてトラック、重機の搬出入可能にすれば複数個
所の連絡達通が可能となって複数のアクセス抗を要しな
い。In addition, if the access shaft is used as a connecting shaft during construction, it is possible to communicate with multiple locations by using a spiral rampway to the extent permitted to allow trucks and heavy equipment to be brought in and out, rather than a direct shaft with the ground. This eliminates the need for multiple access lines.
そして、先導坑道と後続坑道の上下二重接続掘削による
掘削、埋戻し等の施工プロセスはスパイラル工法のみに
限られるものでないことも勿論である。It goes without saying that the construction process, such as excavation and backfilling by vertical double connection excavation of the leading tunnel and the trailing tunnel, is not limited to only the spiral construction method.
く発明の効果)
以上、この出願の発明によれば、基本的に地盤中に構築
物を築造するに際し、該地盤中に坑道を掘削し、掘削に
伴う掘削土砂を掘削坑道後部に凝固材と共に混合して埋
戻すことにより坑道自体の中に構造物を部分的に形成す
ることが出来、したがって、それを反復することにより
、地表から打頂に構築域を掘削してコンクリートを充填
する等の従来のプロセスとは全く発想を異にし坑道、即
ち、地盤を一種の枠型として利用出釆、施工が極めてシ
ンプルに行え、地上構築物に何ら影響されないで地中に
構造物を築造することが可能となる穣れた効果が奏され
る。As described above, according to the invention of this application, basically when constructing a structure in the ground, a tunnel is excavated in the ground, and the excavated soil accompanying the excavation is mixed with a coagulating material at the rear of the excavated tunnel. It is possible to partially form structures within the shaft itself by backfilling and therefore by repeating it, conventional techniques such as excavating the construction area from the surface to the crest and filling it with concrete can be achieved. The concept is completely different from that of the previous process, and it is extremely simple to launch and construct a tunnel, which uses the ground as a type of frame, and it is possible to construct underground structures without being affected by above-ground structures. A pure effect is produced.
又、この施工の展開として先導坑道に重複達通可能に接
続させてその上部に後続坑道を掘削し、先導坑道の後部
に後続坑道掘削土砂を凝固材と混合して埋戻すことによ
り、それを反復したプロセスにして坑道掘削を行うだけ
で、その原理発明に基づき、一層合理的に地下構築物が
築造出来、しかも、相隣る先導、及び、後続坑道のみで
地下構造物の施工が出来、更に、掘削土砂を骨村として
使用出来、施工が極めて能率的に行えるメリットがある
。In addition, as a further development of this construction, a subsequent tunnel is excavated above the leading tunnel by connecting it to the leading shaft in an overlapping manner, and the soil excavated in the trailing shaft is mixed with coagulation material and backfilled at the rear of the leading shaft. Based on the principle invention, underground structures can be built more rationally by simply carrying out tunnel excavation in a repeated process, and furthermore, underground structures can be constructed using only adjacent leading and trailing shafts. This has the advantage that excavated earth and sand can be used as a bone structure, making construction extremely efficient.
加えて、地盤中に一たんアクセス坑を少くとも1本設け
てスパイラル坑道を上記先導坑道、及び、後続坑道とし
て重複近接させて掘削し、上記埋戻し施工を行うことに
より、アクセス坑を掘削した後はあたかも地表から掘進
するのと同じくスパイラル坑を掘削させるだけで一種の
自動反射条件で地下構築物が築造される効果がある。In addition, at least one access hole was once established in the ground, and the spiral tunnel was excavated in close proximity to each other as the leading tunnel and the following tunnel, and the backfilling work was performed as described above to excavate the access shaft. After that, just by digging a spiral shaft, just like digging from the ground surface, an underground structure will be built under a kind of automatic reflection condition.
更に、先導坑道に支保工を行い、先導坑道と後続坑道と
の間の接続運通部を作業部として接続坑道の掘削土砂を
凝固材と共に先導坑道後部に埋戻す共に支保工を盛り替
えて後続坑道の後部支保工とすることによりほぼ1段分
の支保工村によって両坑道が連続して補強され、安全に
作業が行える効果が奏される。In addition, shoring was provided for the leading shaft, and the connecting transport section between the leading shaft and the following shaft was used as a working section to backfill the excavated earth and sand from the connecting shaft with coagulation material into the rear of the leading shaft, and the shoring was replaced to construct the trailing shaft. By using the rear shoring, both tunnels are continuously reinforced by approximately one stage of shoring, making it possible to carry out work safely.
而して、上述施工に施工に供される地中構造物の築造装
置においては通常のシールド型掘削機が利用出来、先端
に掘削装置を有し「中部に掘削土砂搬送機構、埋戻し機
構、支保工盛替え機構、後部に支保工機構を有させるこ
とにより、上下2段型の1つのコンパクトタイプとして
セットされ〜上下の2機能の作業が有機的に併行して達
成され、しかも、上方によって反力をとり、確実に掘進
が可能であり、当該装置のみで地中構造物が形成出釆る
という効果がある。Therefore, a normal shield type excavator can be used as the construction equipment for the underground structure used for the above-mentioned construction. By having a shoring replacement mechanism and a shoring mechanism at the rear, it is set as one compact type with upper and lower tiers ~ The work of the upper and lower functions is achieved organically in parallel, and the It takes force and enables reliable excavation, and has the effect of forming and ejecting underground structures using only this device.
又、埋戻し機構部に型枠を付設することにより地中に設
計厚さの構造物が形成される利点もある。Furthermore, by attaching a formwork to the backfilling mechanism, there is an advantage that a structure with a designed thickness can be formed underground.
結論として、この出願の発明は地表から構築される地下
構造物の深さによる影響を全く解除するために、縦方向
の作業を水平に連続させる代りに水平方向の作業を垂直
方向に連接して構造体を構築するようにしたことによっ
て、基本的なトンネル掘進の技術を上方のまま利用して
掘進作業部位に於てその端で構築の作業を行うことを可
能にしたものであり〜予想される困難な深部作業を掘進
の長さ方向の要素だけで処理出来る点で全く画期的な技
術を提供し得るものである。In conclusion, the invention of this application connects the horizontal work vertically instead of continuing the vertical work horizontally in order to completely eliminate the influence of the depth of underground structures constructed from the ground surface. By constructing the structure, it was possible to use basic tunnel excavation techniques from above and carry out construction work at the edge of the excavation work site. This technology can provide a completely revolutionary technology in that it can handle difficult deep-depth work using only elements in the length direction of excavation.
図面のこの出願の発明の実施例を示すものであり、第l
a,lb,2図は藤理的実施例の部分縦断面図であり、
第lb図は第la図のb−b断面図、第3図は第1図m
−m断面図、第4図は第1,2図による地中構築物の断
面図、第5図はシールド型掘進機及び施工の断面図、第
6a,6b,6c,6d図はそれぞれ第5図A−A、B
−B、C−C、D−D断面図、第7,8図は地下タンク
止水壁構造態様説明図、第9,10図は同プロセス及び
地中止水壁形成断面図、第11,12図は他の地下タン
ク止水壁築造プロセス模式図、第13図は第11,12
図施工の展開説明図、第14図は他の地中構造物部分断
面図である。
2・…・・地盤、47 8・・・・・・坑道、9・…・
・構造物の部分、40……構造物、4……先導坑道、8
,8′・…・・後続坑道、18・…・・連通部、7…・
・・埋戻し作業部、38・・・・・・アクセス坑、11
・・・・・・支保工、13・・・…掘削機本体、5…・
・・掘削装置、25,26・・・・・・支保工移送機構
、16…・・・搬送機構、17...・・・埋戻し機構
、14,28,29・・・…ジャッキ機構、34・・・
・・・型枠。
第la図
第lb図
第2図
第3図
第4図
第5図
第6a図
第6b図
第6c図
第6d図
第7図
第8図
第9図
第10図
第11図
第12図
第13図
第14図The drawings show embodiments of the invention of this application, and are
Figures a, lb, and 2 are partial longitudinal cross-sectional views of Fujiri's embodiment;
Figure lb is a sectional view taken along line bb of Figure la, Figure 3 is Figure 1 m.
-m sectional view, Figure 4 is a sectional view of the underground structure shown in Figures 1 and 2, Figure 5 is a sectional view of the shield type excavator and construction, and Figures 6a, 6b, 6c, and 6d are respectively shown in Figure 5. A-A, B
-B, C-C, D-D sectional views, Figures 7 and 8 are explanatory diagrams of the underground tank water stop wall structure, Figures 9 and 10 are sectional views of the same process and underground water stop wall formation, and Figures 11 and 12 The figure is a schematic diagram of the process of constructing water stop walls for other underground tanks.
Figure 14 is a development explanatory diagram of construction, and Figure 14 is a partial sectional view of another underground structure. 2... Ground, 47 8... Mine shaft, 9...
・Structure part, 40... Structure, 4... Leading tunnel, 8
, 8'...Following tunnel, 18...Communication part, 7...
...Backfilling work section, 38...Access pit, 11
... Shoring, 13 ... Excavator body, 5 ...
... Excavation equipment, 25, 26 ... Shoring transfer mechanism, 16 ... Transport mechanism, 17. .. .. ... Backfilling mechanism, 14, 28, 29... Jack mechanism, 34...
...Formwork. Fig. la Fig. lb Fig. 2 Fig. 3 Fig. 4 Fig. 5 Fig. 6a Fig. 6b Fig. 6c Fig. 6d Fig. 7 Fig. 8 Fig. 9 Fig. 10 Fig. 11 Fig. 12 Fig. 13 Figure 14
Claims (1)
重複連通可能で平行な後続坑道を掘削し、該後続坑道の
先導坑道に対する連通部を埋戻し作業部として該先導坑
道後部に後続坑道掘削土砂に凝固材を混入したもので埋
戻すことにより該掘削坑道自体の中に構造物を築造する
ことを特徴とする地中構造物の築造方法。 2 地盤中に坑道を形成するに先導坑道と該先導坑道に
重複連通可能な平行後続坑道を掘削し、該先導坑道の後
部に支保工構築し、而して該後続坑道の先導坑道に対す
る連通部において支保工を解体して後続坑道後部に盛替
え組付けするようにすると共に該連通部を埋戻し作業部
として該先導坑道後部に後続坑道掘削土砂に凝固材を混
入したもので埋戻しを行うことにより該掘削坑道自体の
中に構造物を築造することを特徴とする地中構造物の築
造方法。 3 地表から地盤内所定深度に少くとも1本のアクセス
坑を掘削し、該アクセス坑を連絡通路として用いながら
地中深部からスパイラル状の坑道を掘削し、掘削後部に
支保工を構築し、該スパイラル坑道は所定の周回の後該
坑道の既設部分を先導部とする平行な後続部として相互
に重複連通し、これら重複する上下の坑道にて先導部の
支保工を解体して後続部に盛替え組付けするようにする
と共に後続部の掘削土砂に凝固材を混入したもので先導
部に埋戻しを行い、これを上下に向かつて繰返して掘削
坑道自体の中に円筒状構造物を築造することを特徴とす
る地中構造物の築造方法。 4 地中構造物の築造装置であつて、掘削機本体は先端
部に掘削装置を有すると共に後部に支保工機構を有し、
中部に掘削土砂搬送機構及び後続坑道埋戻し機構を備え
更に地盤に対する推進機構を有し、而して該中部には支
保工盛替え用と後続坑道埋戻し作業用の連通部が接続可
能にされて成ることを特徴とする地中構造物の築造装置
。 5 地中構造物の築造装置であつて、掘削機本体は先端
部に掘削装置を有し、後部に支保工機構を有し、中部に
掘削土砂搬送機構及び後続坑道埋戻し機構を備えて地盤
に対する推進機構を有し、而して該中部には支保工盛替
え用と後続坑道埋戻し用連通部が接続可能にされており
、該連通部内の埋戻し作業部には型枠が付設されて成る
ことを特徴とする地中構造物の築造装置。[Scope of Claims] 1. To form a tunnel in the ground, a leading shaft and a trailing shaft that can overlap and communicate with the leading shaft are excavated in parallel, and the communicating part of the trailing shaft to the leading shaft is used as a backfilling work part. 1. A method for constructing an underground structure, which comprises backfilling the rear part of a leading tunnel with soil mixed with a coagulating material from excavation of a subsequent shaft to construct a structure within the shaft itself. 2. To form a tunnel in the ground, excavate a leading shaft and a parallel trailing shaft that can overlap and communicate with the leading shaft, construct a shoring at the rear of the leading shaft, and then connect the trailing shaft to the leading shaft. At this point, the shoring is dismantled and reassembled at the rear of the trailing shaft, and the communicating section is used as a backfilling work area, and the rear of the leading shaft is backfilled with soil excavated in the trailing shaft mixed with coagulant. A method for constructing an underground structure, characterized in that the structure is constructed within the excavation shaft itself. 3. Excavate at least one access hole from the ground surface to a predetermined depth in the ground, use the access hole as a communication passage to excavate a spiral tunnel from deep underground, construct a support at the rear of the excavation, and After making a predetermined circuit, the spiral shafts overlap and communicate with each other as parallel trailing parts with the existing part of the shaft as the leading part, and in these overlapping upper and lower shafts, the shoring of the leading part is dismantled and installed in the trailing part. At the same time, the leading part is backfilled with solidified material mixed with the excavated soil of the succeeding part, and this is repeated up and down to build a cylindrical structure within the excavation shaft itself. A method for constructing an underground structure characterized by the following. 4. An underground structure construction device, the excavator body having an excavator at the tip and a shoring mechanism at the rear,
The central part is equipped with an excavated soil transport mechanism and a subsequent tunnel backfilling mechanism, and further has a propulsion mechanism for the ground, and a communication section for shoring replacement and subsequent tunnel backfilling work can be connected to the central part. An underground structure construction device characterized by comprising: 5. A device for constructing underground structures, in which the excavator body has an excavator at the tip, a shoring mechanism at the rear, and an excavated soil conveyance mechanism and a subsequent tunnel backfill mechanism in the middle. It has a propulsion mechanism for the shaft, and a communication section for shoring replacement and subsequent tunnel backfilling can be connected to the middle part, and a formwork is attached to the backfilling work section in the communication section. An underground structure construction device characterized by comprising:
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP53087723A JPS6028977B2 (en) | 1978-07-20 | 1978-07-20 | Construction method and device for underground structures |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP53087723A JPS6028977B2 (en) | 1978-07-20 | 1978-07-20 | Construction method and device for underground structures |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS5516139A JPS5516139A (en) | 1980-02-04 |
| JPS6028977B2 true JPS6028977B2 (en) | 1985-07-08 |
Family
ID=13922822
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP53087723A Expired JPS6028977B2 (en) | 1978-07-20 | 1978-07-20 | Construction method and device for underground structures |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS6028977B2 (en) |
-
1978
- 1978-07-20 JP JP53087723A patent/JPS6028977B2/en not_active Expired
Also Published As
| Publication number | Publication date |
|---|---|
| JPS5516139A (en) | 1980-02-04 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN113153308A (en) | Construction method for double arch tunnel collapse section | |
| CN114483056B (en) | Method for treating collapse roof caving hole of high-speed railway shallow-buried tunnel within 15m of height of collapse cavity | |
| CN115341910A (en) | A tunnel construction method with complex geological conditions under expressway and tunnel | |
| CN116044415A (en) | A kind of tunnel pile foundation underpinning construction method | |
| CN112343614B (en) | U-shaped shield tunneling machine-based overlapped-spliced comprehensive pipe gallery construction method | |
| CN112412472B (en) | Borehole wall reverse operation system and construction method of pipe jacking well in soft soil area and its application | |
| JPS6028977B2 (en) | Construction method and device for underground structures | |
| JP2893349B2 (en) | Large section tunnel structure and its construction method. | |
| JPS61186623A (en) | Method of building foundation of building | |
| JPH09151471A (en) | Movable formwork device and method of constructing underground structure using the same | |
| JPH04309692A (en) | Underground space construction method | |
| CN114165242A (en) | Mechanical construction method for hard rock small-section cable tunnel | |
| JPS6117696A (en) | Construction of underground head | |
| JPH0584773B2 (en) | ||
| CN113833479B (en) | Construction method of main line shield tunnel and ramp connection structure | |
| JPS6248011B2 (en) | ||
| JP2016008377A (en) | Rectangular cross-section propulsion method | |
| JPS6322916A (en) | Construction of continuous underground wall in artificial islet | |
| JPH04309694A (en) | Underground space construction method | |
| JP4180347B2 (en) | Construction method of underground continuous wall and underground continuous wall | |
| JP2617418B2 (en) | Construction method of underground large space structure | |
| JPH0414599A (en) | Structure and construction method of branch part of underground tunnel | |
| JPS62206119A (en) | Construction of continuous cut-off wall | |
| JPH0238627A (en) | Rebuilding of existing building | |
| JPH0317397A (en) | Method and apparatus for constructing space under ground |