JPS6156474B2 - - Google Patents
Info
- Publication number
- JPS6156474B2 JPS6156474B2 JP56039863A JP3986381A JPS6156474B2 JP S6156474 B2 JPS6156474 B2 JP S6156474B2 JP 56039863 A JP56039863 A JP 56039863A JP 3986381 A JP3986381 A JP 3986381A JP S6156474 B2 JPS6156474 B2 JP S6156474B2
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- steel
- truss
- temporary
- reactor building
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E30/00—Energy generation of nuclear origin
- Y02E30/30—Nuclear fission reactors
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【発明の詳細な説明】
本発明は、原子力発電所における原子炉建屋の
最上階層の建築施工方法に関する。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a construction method for the top floor of a nuclear reactor building in a nuclear power plant.
従来の原子炉建屋の最上階層の建築施工方法
は、第1図乃至第4図に示されるように、岩盤1
上に原子炉格納容器Aや原子炉圧力容器Bを収納
する原子炉建屋2の運転操作床面3までをコンク
リートで打設して養生し、この養生期間の経過
後、上記運転操作床面3から搬入装置(図示され
ず)を使用して巨大な上記圧力容器Bを圧力容器
基礎台2a上に設置する。他方、上記運転操作床
面3上にガータ・レール4aを備えた各鉄骨支柱
4及びトラス5aで構成される屋根鉄骨構造体5
を構築する。次に、第3図および第4図に示した
ように鉄骨コンクリート支柱6とコンクリート側
壁7を構築するための仮設足場8を上記トラス5
aの天上部まで積設する。 The conventional construction method for the top floor of a nuclear reactor building is as shown in Figures 1 to 4.
The operation floor surface 3 of the reactor building 2, which houses the reactor containment vessel A and the reactor pressure vessel B, is poured and cured with concrete, and after this curing period, the operation floor surface 3 is covered with concrete. Using a carry-in device (not shown), the gigantic pressure vessel B is installed on the pressure vessel foundation 2a. On the other hand, a roof steel structure 5 is constructed of each steel support column 4 and truss 5a provided with a gutter rail 4a on the operation floor 3.
Build. Next, as shown in FIG. 3 and FIG.
Stack it up to the top of a.
しかして、この仮設足場6を使用して上記各鉄
骨支柱4の間にコンクリートを打設して上記鉄骨
コンクリート6とコンクリート側壁7を構築し、
さらに、上記仮設足場8を使用して上記トラス5
aの上面にコンクリートを打設して屋根鉄骨構造
体5を構築し、次に、上記仮設足場8を解体して
撤去する。しかして、上記運転操作床面3の位置
する最上階層9に天井走行クレーン10の設置空
間を確保する。このようにして、最終的に、上記
ガーダレール4a上に天井走行クレーン10を走
行し得るように組立、調整し得るようになつてい
る。 Then, using this temporary scaffolding 6, concrete is poured between each of the steel supports 4 to construct the steel concrete 6 and concrete side wall 7,
Furthermore, using the temporary scaffolding 8, the truss 5
The roof steel structure 5 is constructed by pouring concrete on the upper surface of the roof, and then the temporary scaffolding 8 is dismantled and removed. Thus, an installation space for the overhead traveling crane 10 is secured on the top floor 9 where the operation floor 3 is located. In this way, it is finally possible to assemble and adjust the overhead crane 10 so that it can run on the girder rail 4a.
なお、上記天井走行クレーン10の組立作業
は、上記屋根鉄骨構造体5の一部に資材搬入口を
設けてあるので、天井走行クレーン10の組立終
了後は、上記資材搬入口を密閉し得るようになつ
ている。 In addition, during the assembly work of the overhead traveling crane 10, since a material entrance is provided in a part of the roof steel structure 5, after the assembly of the overhead traveling crane 10 is completed, it is necessary to close the material entrance. It's getting old.
しかしながら、上述した従来の原子炉建屋の最
上階層の建築施工方法では、原子炉建屋2の運転
操作床面3が打設・養生して完了し、最上階層の
鉄骨コンクリート支柱6、コンクリート側壁7及
び屋根鉄骨構造体5を構築し、一定の養生期間経
過後、上記最上階層9の全内周壁に亘つて建築工
事用として設置されている仮設足場8を解体撤去
する手順(工程)のために、天井走行クレーン1
0の塔載、組立、調整時間が大幅に遅れる。また
上記天井走行クレーンの搬入のために、資材搬入
口を屋根鉄骨構造体5に設けている関係上、天井
走行クレーン10の搬入後、上記仮開口部の閉塞
作業時間も順に遅延する。さらに、原子炉本体の
各種構造物や配管、配線等の据付工事も共に遅延
して、原子力発電所の建設工期が長くなり、これ
に追随して原子力発電所の納期も遅れる結果とな
る。 However, in the above-described conventional construction method for the top floor of the reactor building, the operation floor 3 of the reactor building 2 is completed by pouring and curing, and the steel concrete columns 6, concrete side walls 7 and concrete side walls 7 of the top floor are completed. For the procedure (process) of constructing the roof steel frame structure 5 and, after a certain curing period has elapsed, dismantling and removing the temporary scaffolding 8 installed for construction work across the entire inner peripheral wall of the top floor 9, Overhead crane 1
0 installation, assembly, and adjustment time will be significantly delayed. Furthermore, since a material entrance is provided in the roof steel frame structure 5 for carrying in the overhead traveling crane, the time required for closing the temporary opening will be delayed after the overhead traveling crane 10 is brought in. Furthermore, installation work for various structures, piping, wiring, etc. of the reactor itself will be delayed, resulting in longer construction times for nuclear power plants and correspondingly delayed delivery dates for nuclear power plants.
さらに又、従来の原子炉建屋の最上階層の建築
施工方法は、運転操作床面3上に全周壁に沿つて
仮設足場8を設置することにより、運転操作床面
3の有効作業面積が狭く制限されるから、各種工
事作業の能率も低下し、しかも長期間に亘つて、
仮設足場8が設置されているため、建設工事に影
響を及ぼすことになる。 Furthermore, in the conventional construction method for the top floor of a nuclear reactor building, the effective working area of the operation floor 3 is narrowly limited by installing temporary scaffolding 8 along the entire perimeter wall on the operation floor 3. As a result, the efficiency of various construction work decreases, and over a long period of time,
Since temporary scaffolding 8 has been installed, this will affect the construction work.
又一方、上記最上階床9における鉄骨コンクリ
ート支柱6、コンクリート側壁7及び屋根鉄骨構
造体5の建設工事は、高所作業であるから、資材
の搬入や他の工事作業とを勘案しながら長期に亘
つて進行しなければならず、安全性の見地からも
問題がある。特に、上記天井走行クレーン10の
稼動時期は、原子力発電所の全建設工程における
大きなクリテカルパスとなつているため、上記稼
動時期が遅延されると、他の建設工期が大幅に遅
延される等の難点がある。 On the other hand, the construction work of the steel concrete columns 6, the concrete side walls 7, and the roof steel structure 5 on the top floor 9 is work at high places, so it takes a long time to take into consideration the delivery of materials and other construction work. This poses a problem from a safety point of view. In particular, the operating timing of the above-mentioned overhead traveling crane 10 is a critical path in the entire construction process of a nuclear power plant, so if the above-mentioned operating timing is delayed, other construction periods will be significantly delayed. There are some difficulties.
本発明は、上述した難点を解消するために、鉄
骨コンクリート支柱、コンクリート側壁の構築
後、屋根鉄骨構造体と天井走行クレーンの建設作
業を同時に並行して行うようにし、しかも、第一
仮設足場を撤去して運転操作床面を広くし、これ
により、建設工期の大幅な短縮を図ると共に、早
期納期を図ることを目的とする原子炉建屋の建築
施工方法を提供するにある。 In order to solve the above-mentioned difficulties, the present invention allows the construction work of the roof steel frame structure and the overhead traveling crane to be carried out simultaneously and in parallel after the construction of the steel concrete columns and the concrete side walls, and furthermore, the first temporary scaffolding is To provide a construction method for a nuclear reactor building, which aims to significantly shorten the construction period and achieve early delivery by removing the reactor building and widening the operating floor surface.
以下、本発明を図示の一実施例について説明す
る。なお、本発明は上述した実施例の構成部材と
同じものには同じ符号を附して説明する。 Hereinafter, the present invention will be described with reference to an illustrated embodiment. It should be noted that the present invention will be described with the same reference numerals attached to the same components as those of the embodiments described above.
第5図乃至第7図において、符号1は原子力発
電所における岩盤であつて、この岩盤1には格納
容器Aや圧力容器Bを収納する原子炉建屋2の運
転操作床面3までをコンクリートを打設して養生
する。この養生期間の経過後、上記運転操作床面
3から巨大な圧力容器Bを搬入装置(図示され
ず)で圧力容器基礎台2a上に設置する。他方、
上記運転操作床面3上にはガーダレール4aを備
えた各鉄骨支柱4及び屋根鉄骨構造体5の骨格を
構成するトラス5aを構築する。 In FIGS. 5 to 7, reference numeral 1 is a bedrock in a nuclear power plant, and this bedrock 1 is covered with concrete up to the operation floor 3 of the reactor building 2 that houses the containment vessel A and pressure vessel B. Pour and cure. After this curing period has passed, the huge pressure vessel B is installed on the pressure vessel foundation 2a from the operation floor 3 using a carrying device (not shown). On the other hand,
On the operation floor surface 3, each steel support column 4 provided with a girder rail 4a and a truss 5a constituting the skeleton of the roof steel structure 5 are constructed.
次に、第5図及び第6図に示されるように、上
記運転操作床面3の外周に第一仮設足場8aを上
記トラス5aの下位まで積設する。しかる後、上
記第一仮設足場8aを使用して上記各鉄骨支柱4
の周り及び各鉄骨支柱4の間にコンクリートを打
設して鉄骨コンクリート支柱6とコンクリート側
壁7をそれぞれ構築する。なお、この場合、コン
クリート打設用の型枠の取付け、取外しが行われ
ると同時に、鉄筋7aも埋設される。 Next, as shown in FIGS. 5 and 6, a first temporary scaffolding 8a is stacked on the outer periphery of the operation floor 3 up to the bottom of the truss 5a. After that, each of the steel supports 4 is installed using the first temporary scaffolding 8a.
Concrete is poured around and between each steel frame support 4 to construct a steel concrete support 6 and a concrete side wall 7, respectively. In this case, the reinforcing bars 7a are also buried at the same time as the formwork for concrete placement is installed and removed.
しかる後、上記第一仮設足場8aは解体撤去し
て、天井走行クレーン10の設置空間を確保す
る。即ち、上記トラス5aの下位に形成される最
上階層9の上記運転操作床面3が全面に亘つて使
用できるようになる。 Thereafter, the first temporary scaffolding 8a is dismantled and removed to secure an installation space for the overhead traveling crane 10. That is, the operation floor surface 3 of the uppermost floor 9 formed below the truss 5a can be used entirely.
次に、上記鉄骨コンクリート支柱6の中程に設
けられたガーダレール4a上には天井走行クレー
ン10の組立、及び調整が開始する。 Next, assembly and adjustment of the overhead traveling crane 10 on the girder rail 4a provided in the middle of the steel-framed concrete column 6 begins.
他方、上記トラス5aの一部に型鋼梁11,1
2を並設する。しかして、この型鋼梁11,12
の上に第二仮設足場8bの足場板8cを敷設す
る。しかる後、上記第二仮設足場8bを、第6図
に示されるように、上記トラス5aの上部に突出
するように積設する。次に、上記第二仮設足場8
bを使用して、上記トラス5aの外側及び残余の
各鉄骨支柱4の周りと残余の各鉄骨支柱4の間に
コンクリートを打設して屋根鉄骨構造体5、残余
の鉄骨コンクリート支柱6及びコンクリート側壁
7を構築する(第6図参照)。このようにして、
最終時には、上記第二仮設足場8bを解体撤去す
ることにより、原子炉建屋の最上階層の建設及び
天井走行クレーン10の組立を同時に並行して施
工できるようになつている。 On the other hand, a part of the truss 5a is provided with shaped steel beams 11,1.
Install 2 in parallel. However, this type steel beam 11, 12
Scaffolding board 8c of second temporary scaffolding 8b is laid on top of this. Thereafter, the second temporary scaffold 8b is stacked so as to protrude above the truss 5a, as shown in FIG. Next, the second temporary scaffolding 8
b is used to pour concrete around the outside of the truss 5a, around each of the remaining steel columns 4, and between each of the remaining steel columns 4 to form the roof steel structure 5, the remaining steel concrete columns 6, and concrete. Build the side wall 7 (see Figure 6). In this way,
At the final stage, by dismantling and removing the second temporary scaffolding 8b, the construction of the top floor of the reactor building and the assembly of the overhead traveling crane 10 can be carried out simultaneously and in parallel.
以上述べたように本発明によれば、鉄骨コンク
リート支柱6及びコンクリート側壁7を構築した
後、上記屋根鉄骨構造体5と天井走行クレーン1
0とを並行して作業するようになつているので、
建設工期を大幅に短縮できるばかりでなく、作業
の安全性の向上を図ることもできる。 As described above, according to the present invention, after constructing the steel concrete support column 6 and the concrete side wall 7, the roof steel structure 5 and the overhead traveling crane 1 are assembled.
0 in parallel, so
Not only can construction time be significantly shortened, but work safety can also be improved.
第1図は従来の原子炉建屋の建築施工方法を説
明するための原子炉建屋の断面図、第2図は上記
原子炉建屋の屋根鉄骨構造体の一部を示す拡大断
面図、第3図は第2図中の鎖円Aの拡大断面図、
第4図は第3図中の鎖線B−Bに沿う拡大平面
図、第5図は本発明による原子炉建屋の建築施工
方法を説明するための原子炉建屋の断面図、第6
図は第5図中の鎖円Cの拡大断面図、第7図は同
上平面図である。
2……原子炉建屋、3……運転操作床面、4…
…鉄骨支柱、5……屋根鉄骨構造体、5a……ト
ラス、6……鉄骨コンクリート支柱、7……コン
クリート側壁、8……仮設足場、8a……第一仮
設足場、8b……第二仮設足場、10……天井走
行クレーン、11,12……型鋼梁。
Figure 1 is a cross-sectional view of the reactor building to explain the conventional construction method for the reactor building, Figure 2 is an enlarged cross-sectional view showing a part of the roof steel structure of the reactor building, and Figure 3 is a cross-sectional view of the reactor building. is an enlarged sectional view of chain circle A in Figure 2,
FIG. 4 is an enlarged plan view taken along the chain line B-B in FIG. 3, FIG.
The figure is an enlarged sectional view of chain circle C in FIG. 5, and FIG. 7 is a plan view of the same. 2...Reactor building, 3...Operation floor, 4...
... Steel support column, 5 ... Roof steel structure, 5a ... Truss, 6 ... Steel concrete support column, 7 ... Concrete side wall, 8 ... Temporary scaffolding, 8a ... First temporary scaffolding, 8b ... Second temporary scaffolding Scaffolding, 10...overhead crane, 11, 12...shaped steel beam.
Claims (1)
め、各鉄骨支柱及びトラスで構成される屋根鉄骨
構造体を構築し、次に、上記運転床面上に第一仮
設足場を上記トラスの下位まで積設し、この第一
仮設足場を使用して上記各鉄骨支柱の間にコンク
リートを打設して鉄骨コンクリート支柱及びコン
クリート側壁を構築し、しかる後、上記第一仮設
足場を解体撤去して天井走行クレーンの設置空間
を確保し、上記鉄骨コンクリート支柱の中程に設
けられたガーダレール上に上記天井走行クレーン
の組立を開始すると共に、他方、上記トラスの一
部に型鋼梁を並設し、この型鋼梁上に第二仮設足
場を上記トラス上部に突出するように積設し、こ
の第二仮設足場を使用して上記鉄骨支柱の間及び
上記トラス上にコンクリートを打設して鉄骨コン
クリート支柱、コンクリート側壁及び屋根鉄骨構
造体を構築し、しかる後、上記第二仮設足場を解
体撤去するようにしたことを特徴とする原子炉建
屋の建築施工方法。1. A roof steel structure consisting of each steel support and truss is constructed in advance above the operating floor of the reactor building, and then a first temporary scaffold is placed on the operating floor above the truss. The first temporary scaffolding is then used to pour concrete between each of the above steel supports to construct the steel concrete supports and concrete side walls, after which the first temporary scaffolding is dismantled and removed. The installation space for the overhead traveling crane was secured using A second temporary scaffold is placed on this shaped steel beam so as to protrude above the truss, and concrete is poured between the steel supports and on the truss using this second temporary scaffold to form steel concrete. A method for constructing a nuclear reactor building, comprising constructing columns, concrete side walls, and a roof steel structure, and then dismantling and removing the second temporary scaffolding.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP56039863A JPS57154098A (en) | 1981-03-19 | 1981-03-19 | Method of constructing nuclear reactor building |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP56039863A JPS57154098A (en) | 1981-03-19 | 1981-03-19 | Method of constructing nuclear reactor building |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS57154098A JPS57154098A (en) | 1982-09-22 |
| JPS6156474B2 true JPS6156474B2 (en) | 1986-12-02 |
Family
ID=12564800
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP56039863A Granted JPS57154098A (en) | 1981-03-19 | 1981-03-19 | Method of constructing nuclear reactor building |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS57154098A (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US6955985B2 (en) | 2002-06-28 | 2005-10-18 | Kopin Corporation | Domain epitaxy for thin film growth |
| US7002180B2 (en) | 2002-06-28 | 2006-02-21 | Kopin Corporation | Bonding pad for gallium nitride-based light-emitting device |
| US7122841B2 (en) | 2003-06-04 | 2006-10-17 | Kopin Corporation | Bonding pad for gallium nitride-based light-emitting devices |
-
1981
- 1981-03-19 JP JP56039863A patent/JPS57154098A/en active Granted
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US6955985B2 (en) | 2002-06-28 | 2005-10-18 | Kopin Corporation | Domain epitaxy for thin film growth |
| US7002180B2 (en) | 2002-06-28 | 2006-02-21 | Kopin Corporation | Bonding pad for gallium nitride-based light-emitting device |
| US7122841B2 (en) | 2003-06-04 | 2006-10-17 | Kopin Corporation | Bonding pad for gallium nitride-based light-emitting devices |
Also Published As
| Publication number | Publication date |
|---|---|
| JPS57154098A (en) | 1982-09-22 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US5119598A (en) | Method of construction of top slab for a nuclear containment building | |
| JPS6156474B2 (en) | ||
| JPH0657710A (en) | Construction of concrete main tower | |
| JPH0312184B2 (en) | ||
| JPS6335931A (en) | Construction of building of atomic power plant | |
| JPS5941530A (en) | Installation of foundation bolt for apparatus setting | |
| JPH06146311A (en) | Construction method of underground work by completely automatic building construction system | |
| JP2817591B2 (en) | Construction method of steel reinforced concrete building | |
| JP3273668B2 (en) | How to construct a containment vessel | |
| SU977644A1 (en) | Method for erecting cast-in-place buildings | |
| JPS62159092A (en) | Method of housing construction of nuclear power plant | |
| JPH0791876B2 (en) | Radiation shielding slab and its construction method | |
| JPS58118987A (en) | Reactor building construction method | |
| JPS6326211B2 (en) | ||
| JPH058305B2 (en) | ||
| JPH04149365A (en) | Construction method of beam | |
| CN119616148A (en) | Construction method of concrete decorative member of roof frame structure | |
| JPH01223248A (en) | Folded plate unit slab construction method | |
| JPH0366463B2 (en) | ||
| JPH0510465B2 (en) | ||
| JPS642742B2 (en) | ||
| JPS6135395A (en) | Method of constructing torus chamber in nuclear power plant | |
| JPS6345555B2 (en) | ||
| JPH0415857B2 (en) | ||
| JPS6245837A (en) | Construction work for foundation of turbine generator |