Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPS6160206B2 - - Google Patents
[go: Go Back, main page]

JPS6160206B2 - - Google Patents

Info

Publication number
JPS6160206B2
JPS6160206B2 JP53103127A JP10312778A JPS6160206B2 JP S6160206 B2 JPS6160206 B2 JP S6160206B2 JP 53103127 A JP53103127 A JP 53103127A JP 10312778 A JP10312778 A JP 10312778A JP S6160206 B2 JPS6160206 B2 JP S6160206B2
Authority
JP
Japan
Prior art keywords
pressure vessel
concrete
reinforcing bar
bar cage
fluid
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP53103127A
Other languages
Japanese (ja)
Other versions
JPS5530059A (en
Inventor
Shozaburo Nanjo
Yutaka Ishimoda
Akira Torio
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Construction Co Ltd
Original Assignee
Sumitomo Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Construction Co Ltd filed Critical Sumitomo Construction Co Ltd
Priority to JP10312778A priority Critical patent/JPS5530059A/en
Publication of JPS5530059A publication Critical patent/JPS5530059A/en
Publication of JPS6160206B2 publication Critical patent/JPS6160206B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Description

【発明の詳細な説明】 この発明は鉄筋コンクリート構造による中空大
口径場所打杭の施工法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a construction method for hollow large-diameter cast-in-place piles having a reinforced concrete structure.

従来中空大口径場所打杭の施工に際してはコン
クリート側圧に耐えうる強度、剛性を有する内型
枠を竪孔内に建込んだ鉄筋籠の内側に挿入してコ
ンクリートを打設する。したがつて内型枠は埋殺
しになる場合が多く、経済的でない。
Conventionally, when constructing hollow large-diameter cast-in-place piles, concrete is poured by inserting an inner formwork that has the strength and rigidity to withstand concrete lateral pressure inside a reinforcing bar cage built in a shaft. Therefore, the inner formwork is often buried, which is not economical.

また内型枠として可撓性の袋を挿入し、この袋
内に流体を注入する方法も知られているが底部コ
ンクリートを後打ちする必要がある等施工が複雑
である。
Another method is known in which a flexible bag is inserted as the inner formwork and fluid is injected into the bag, but the construction is complicated as it requires post-casting of the bottom concrete.

この発明は前記従来の問題点を解消すべく開発
したもので、以下その詳細を図示した実施例によ
つて説明する。
The present invention was developed to solve the above-mentioned conventional problems, and details thereof will be explained below with reference to illustrated embodiments.

先ずスタンドパイプ1を建て、泥水工法を応用
して掘削機2により竪孔Aを全断面掘削する。
First, a standpipe 1 is erected, and the entire section of the shaft A is excavated using the excavator 2 using the muddy water construction method.

次いで筒状の鉄筋籠3を竪孔A内にクレーン等
により吊下して建込む。なおその際鉄筋籠3は順
次継足すことができる。また鉄筋籠の内側には細
い鉄筋またはロープ等の縦方向の線状ガイド4を
円周方向に間隔を置いて設け、またガイド4の底
部には鉄筋籠3に係止した椀状の底型枠5を設け
る。
Next, the cylindrical reinforcing bar cage 3 is suspended and erected into the pit A using a crane or the like. In this case, the reinforcing bar cages 3 can be added one after another. Furthermore, vertical linear guides 4 such as thin reinforcing bars or ropes are provided at intervals in the circumferential direction inside the reinforcing bar cage, and a bowl-shaped bottom mold that is fixed to the reinforcing bar cage 3 is provided at the bottom of the guide 4. A frame 5 is provided.

次いで鉄筋籠3の内側に可撓性の圧力容器6を
挿入しながら、その圧力容器6内に注入ホース7
等によつて流体を注入する。
Next, while inserting the flexible pressure vessel 6 inside the reinforcing bar cage 3, the injection hose 7 is inserted into the pressure vessel 6.
Inject the fluid by, for example,

圧立容器6はゴム、合成樹脂、合成繊維、薄い
金属板等からなり、必要により上蓋8、圧力計9
等を設ける。流体としては水、泥水、空気等を注
入しかつ加圧する。そして圧力容器6を挿入後に
流体をポンプまたはコンプレツサーにより加圧注
入する。
The pressurized container 6 is made of rubber, synthetic resin, synthetic fiber, thin metal plate, etc., and is equipped with an upper lid 8 and a pressure gauge 9 as necessary.
etc. will be established. Water, muddy water, air, etc. are injected as fluid and pressurized. After inserting the pressure vessel 6, fluid is injected under pressure using a pump or compressor.

次いでトレミー管10を通じ、コンクリート1
1を竪孔Aの圧力容器6の外周に鉄筋籠3を埋設
するよう打設する。コンクリート11の硬化後圧
力容器6を、流体を排除して撤去することにより
杭を完成する。
Next, the concrete 1 is passed through the tremie pipe 10.
1 is cast so as to bury the reinforcing bar cage 3 on the outer periphery of the pressure vessel 6 in the shaft A. After the concrete 11 hardens, the pressure vessel 6 is removed by removing the fluid, thereby completing the pile.

この発明は以上の構成からなり、流体を注入し
た圧力容器を内型枠として中空コンクリート杭を
現場打ちすることができる。そして圧力容器が可
撓性であるので流体を排除することにより脱型が
容易となり再使用が可能となる。
The present invention has the above-described configuration, and a hollow concrete pile can be cast on-site using a pressure vessel into which a fluid is injected as an inner formwork. Since the pressure vessel is flexible, removing the fluid facilitates demolding and enables reuse.

また筒状鉄筋籠の内側の円周方向に間隔をおい
て縦方向の線状ガイドを設けることにより圧力容
器の挿入を容易とし、またコンクリート打設によ
る加圧後の偏心を防止できる。また圧力容器の下
面にはコンクリート打設によつて浮力が作用する
が、この浮力によつて圧力容器が浮上する恐れが
あるが、ガイドの底部には鉄筋籠に係止した椀状
の底型枠に接するように挿入してあるので、その
位置決めが確実であるとともに圧力容器が浮上す
ることを防止できる。
Further, by providing vertical linear guides at intervals in the circumferential direction inside the cylindrical reinforcing bar cage, insertion of the pressure vessel is facilitated, and eccentricity after pressurization due to concrete placement can be prevented. In addition, buoyancy acts on the bottom surface of the pressure vessel due to concrete pouring, and there is a risk that the pressure vessel will float due to this buoyancy. Since it is inserted so as to be in contact with the frame, its positioning is reliable and the pressure vessel can be prevented from floating up.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図、第2図、第3図および第4図は、この
発明の施工過程の概要を示した断面図である。 A……竪孔、1……スタンドパイプ、2……掘
削機、3……鉄筋籠、4……ガイド、5……底型
枠、6……圧力容器、7……注入ホース、8……
上蓋、9……圧力容器、10……トレミー管、1
1……コンクリート。
FIG. 1, FIG. 2, FIG. 3, and FIG. 4 are cross-sectional views showing an outline of the construction process of the present invention. A... Pit, 1... Stand pipe, 2... Excavator, 3... Rebar cage, 4... Guide, 5... Bottom formwork, 6... Pressure vessel, 7... Injection hose, 8... …
Upper lid, 9...pressure vessel, 10...tremie tube, 1
1...Concrete.

Claims (1)

【特許請求の範囲】[Claims] 1 地中に竪孔を掘削し、内側の円周方向に間隔
をおいて縦方向の線状ガイドを設け、ガイドの底
部には鉄筋籠に係止した椀状の底型枠を設けた筒
状鉄筋籠を前記竪孔内に建込み、その内側に可撓
性の圧力容器を前記ガイドおよび底型枠に接する
ように挿入し、前記圧力容器内に流体を注入した
状態で圧力容器の外側に前記鉄筋籠を埋設するよ
うコンクリートを打設し、コンクリートの硬化後
圧力容器内の流体を排除することを特徴とする中
空大口径場所打杭の施工法。
1 A vertical hole is excavated in the ground, vertical linear guides are installed at intervals in the inner circumferential direction, and a bowl-shaped bottom formwork is attached to a reinforcing bar cage at the bottom of the guide. A shaped reinforcing bar cage is built in the shaft, a flexible pressure vessel is inserted inside the cage so as to be in contact with the guide and the bottom form, and with fluid injected into the pressure vessel, the outside of the pressure vessel is 1. A method for constructing hollow large-diameter cast-in-place piles, the method comprising: pouring concrete to bury the reinforcing bar cage in the concrete, and removing the fluid in the pressure vessel after the concrete has hardened.
JP10312778A 1978-08-24 1978-08-24 Working process for piling into hollow and big bore Granted JPS5530059A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10312778A JPS5530059A (en) 1978-08-24 1978-08-24 Working process for piling into hollow and big bore

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10312778A JPS5530059A (en) 1978-08-24 1978-08-24 Working process for piling into hollow and big bore

Publications (2)

Publication Number Publication Date
JPS5530059A JPS5530059A (en) 1980-03-03
JPS6160206B2 true JPS6160206B2 (en) 1986-12-19

Family

ID=14345891

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10312778A Granted JPS5530059A (en) 1978-08-24 1978-08-24 Working process for piling into hollow and big bore

Country Status (1)

Country Link
JP (1) JPS5530059A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6423001U (en) * 1987-07-29 1989-02-07

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02186009A (en) * 1989-01-11 1990-07-20 Asuku Kenkyusho:Kk Bottom-spreaded open caisson foundation
KR100494354B1 (en) * 2002-12-11 2005-06-13 손기택 Reinforcement structure for dike and constructing method thereof
JP4803458B2 (en) * 2007-11-13 2011-10-26 清水建設株式会社 Construction method of ground vibration propagation suppression structure
CN108385671A (en) * 2018-02-09 2018-08-10 中国冶集团有限公司 For hollow or underwater cast-in-place pile construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6423001U (en) * 1987-07-29 1989-02-07

Also Published As

Publication number Publication date
JPS5530059A (en) 1980-03-03

Similar Documents

Publication Publication Date Title
CN102767189B (en) Set bearing platform foundations and construction method thereof
JPS6160206B2 (en)
JP4449532B2 (en) Rapid construction method of shaft by convex joint of deep bottom shaft
JPH0598636A (en) Cylindrical shell foundation and construction method thereof
JPH11152763A (en) Submerged box connection method
JPS6383314A (en) Method for preparing cast-in place pile
KR0148168B1 (en) Concrete pouring in trench using Styropole ball
JP3748615B2 (en) Construction method of cylindrical underground structure
JP3399574B2 (en) How to build an underground tank
JPH0246127B2 (en) CHUKUKONKURIITOKISEIKUINOSEIZOHOHO
JP2949341B1 (en) Underwater girder construction method
JPH08177044A (en) Construction method of cast-in-place concrete pile and formwork device for forming pile head used in the construction method
JPH073781A (en) Construction method of foundation footing on cast-in-place concrete pile head.
CN109518685A (en) A kind of prefabricated pilework and its construction method under water
JPH0323689B2 (en)
JPS6237171B2 (en)
JPH0797811A (en) Pile head treatment method for driven-in-place pile
JPS6352193B2 (en)
JPH08144686A (en) Construction method of shaft
JP2667489B2 (en) Method and apparatus for forming bottom plate of casing shaft
JP3030571B2 (en) Outer shell of offshore structure and construction method of offshore structure
JP2571730B2 (en) How to build a deep circular shaft
JP2581602B2 (en) Waste treatment method
JP2002002881A (en) Structure for preventing floating and deformation of resin tank
JPH027959Y2 (en)