JPS6213447B2 - - Google Patents
Info
- Publication number
- JPS6213447B2 JPS6213447B2 JP13027182A JP13027182A JPS6213447B2 JP S6213447 B2 JPS6213447 B2 JP S6213447B2 JP 13027182 A JP13027182 A JP 13027182A JP 13027182 A JP13027182 A JP 13027182A JP S6213447 B2 JPS6213447 B2 JP S6213447B2
- Authority
- JP
- Japan
- Prior art keywords
- earth
- guide frame
- shaft
- cutting device
- bit
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/18—Bulkheads or similar walls made solely of concrete in situ
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Description
【発明の詳細な説明】 本発明は地中連続壁の掘削方法に関する。[Detailed description of the invention] The present invention relates to a method for excavating a diaphragm wall.
地中連続壁は従来より幅広い用途に用いられ、
その有効性が評価されている。具体的には、建造
物の基礎、掘削土留及び本体壁、地下タンクの止
水壁及び本体壁、都市トンネルの立坑の土留等に
活用されている。この工法の長所は低騒音、低振
動で施工できる上、長深度の施工も可能で止水効
果が良く、本体構造の一部にも使えることであ
る。 Underground walls are used for a wider range of purposes than before,
Its effectiveness has been evaluated. Specifically, it is used for the foundations of buildings, excavated earth retaining and main body walls, underground tank water stop walls and main body walls, earth retaining of vertical shafts of urban tunnels, etc. The advantages of this construction method are that it can be constructed with low noise and vibration, can be constructed at long depths, has a good water-stopping effect, and can be used on parts of the main structure.
上記の用途の中でも都市トンネルの立坑築造の
際は、地中連続壁を用いて平面形状が矩形もしく
は多角形の施工が多かつた。この場合、従来の地
中連続壁掘削機は第1図に示すように幅40〜80
cm、長さ2〜3mの溝を一度に連続的に掘削し、
その工程を繰返して平面上に連続させて四角形ま
たは多角形状の立坑を完成していた。 Among the above-mentioned uses, when constructing vertical shafts for urban tunnels, underground continuous walls were often used and the planar shape was rectangular or polygonal. In this case, conventional underground wall excavators have a width of 40 to 80 mm, as shown in Figure 1.
cm, trenches with a length of 2 to 3 m are continuously excavated at once.
This process was repeated to create a rectangular or polygonal shaft.
この地中壁と立坑形状には次のような欠点があ
る。すなわち、地中壁で囲まれた、立坑内部を掘
削する際に第1図に見られるように多数の切梁を
必要とし、完成後の作業空間が狭いこと、長さ2
〜3mのスパンを連結するので、その継目からの
漏水が多いこと、平面形状が直線の地中壁で立坑
が構成されるので、周囲の土圧に抵抗するため地
中壁の断面を大きくする必要があること、などで
ある。 This underground wall and shaft shape has the following drawbacks. In other words, when excavating inside a shaft surrounded by underground walls, a large number of struts are required as shown in Figure 1, and the working space after completion is narrow, and the length is 2.
Since spans of ~3m are connected, there is a lot of water leakage from the joints, and since the shaft is composed of underground walls with a straight planar shape, the cross section of the underground walls must be made large to resist the surrounding earth pressure. It is necessary, etc.
上記の欠点を解消するために第2及び3図に示
すような円形立坑が考えられたが、従来工法で施
工すると継手が多いため、円形にしたメリツトが
充分に発揮できない。すなわち、継手からの漏水
が多く、周囲の土圧に切梁なしで抵抗するには滑
らかな円形形状の地中壁である必要があり、ま
た、施工時間も1スパンずつ掘削するので長時間
を要した。 In order to eliminate the above-mentioned drawbacks, a circular shaft as shown in Figures 2 and 3 was considered, but when constructed using conventional construction methods, there are many joints, so the merits of the circular shaft cannot be fully utilized. In other words, there is a lot of water leakage from the joints, and in order to resist the surrounding earth pressure without struts, the underground wall needs to have a smooth circular shape.In addition, the construction time is long because each span is excavated at a time. It took.
本発明は上記した欠点を解消するものである。
つまり、地表面から円環状に連続的に所定深度ま
で掘ることによつて、縦方向の継手をなくし、な
めらかな円形状の立坑を完成することができ、立
坑内の切梁が不要となりまた、連続的に掘るので
施工時間が大幅に縮小される。第4及び5図はこ
のようにして連続的に円形に地中壁を築造した例
である。 The present invention overcomes the above-mentioned drawbacks.
In other words, by continuously digging in a circular pattern from the ground surface to a predetermined depth, vertical joints can be eliminated and a smooth circular shaft can be completed, eliminating the need for struts inside the shaft. Since the excavation is carried out continuously, construction time is greatly reduced. Figures 4 and 5 are examples of continuous circular underground walls constructed in this manner.
以下、図面に従い本発明を説明する。 The present invention will be explained below with reference to the drawings.
第6図に示すように、地中連続壁用溝の予定位
置の外周に接して、適当な間隔で垂直に定規坑3
を予め設置する。また、予定位置には溝を1〜2
m深さに予じめ掘削しておき、溝の両側にはガイ
ドウオールを築造しておき、周囲の地下水位に応
じて粘土、ベントナイト等を適度に含んだ泥水を
満たしておく。 As shown in FIG.
be installed in advance. Also, place 1 to 2 grooves at the planned location.
The trench is excavated in advance to a depth of m, and guide walls are built on both sides of the trench and filled with muddy water containing an appropriate amount of clay, bentonite, etc., depending on the surrounding groundwater level.
切削装置2を懸架した案内枠1をワイヤー81
で吊つた状態でビツト24が溝の底に接するまで
下ろす。切削装置2に装備された走行用モーター
21の回転により、ビツト24で地盤を掘削しな
がら、切削装置2は案内枠1を走行する。掘削さ
れた土砂は、土砂排出用ポンプ23により、泥水
と共に地上に搬出される。案内枠1には複数個の
自動深度測定器を取付け、測定結果に応じて巻き
あげ用電動モーター82を操作して、案内枠1を
上下させる。巻きあげ用電動モーター82は、図
の例においては、定規抗3の本数に対応して4個
であるが、立坑の規模に応じて個数は調整される
(第6図に1台のみ記載してある)。また、巻き上
げ用電動モーター82は設置された台数が全て同
調して連動するようにされている。 The guide frame 1 on which the cutting device 2 is suspended is connected to the wire 81
While hanging it, lower it until the bit 24 touches the bottom of the groove. The cutting device 2 travels along the guide frame 1 while excavating the ground with the bit 24 by the rotation of a traveling motor 21 installed in the cutting device 2. The excavated earth and sand are transported to the ground together with muddy water by the earth and sand discharge pump 23. A plurality of automatic depth measuring devices are attached to the guide frame 1, and the hoisting electric motor 82 is operated according to the measurement results to move the guide frame 1 up and down. In the example shown in the figure, there are four electric motors 82 for hoisting, corresponding to the number of ruler shafts 3, but the number can be adjusted depending on the scale of the shaft (only one is shown in Fig. 6). ). Moreover, all the installed electric motors 82 for hoisting are arranged to operate in synchronization.
案内枠1は、第8,9及び10図に示すよう
に、上下面に突起11,12を持ち、切削装置2
を誘導する役目を担う。また、側面には走行用モ
ーター22のギヤとかみあう案内用ギヤ13が取
付けてある。案内枠1の断面の詳細は第9及び1
0図に示されている。 As shown in FIGS. 8, 9 and 10, the guide frame 1 has protrusions 11 and 12 on the upper and lower surfaces, and the cutting device 2
plays the role of guiding. Further, a guide gear 13 that meshes with the gear of the traveling motor 22 is attached to the side surface. Details of the cross section of guide frame 1 are shown in 9th and 1st.
It is shown in Figure 0.
切削装置2は第8図に示すように、走行用モー
ター21、ビツト回転用モーター22及び土砂排
出ポンプ23を塔載しており、下部にビツト24
と土砂吸入口25が設置されている。なお、図の
例では各モータとも1台であるが、立坑の規模に
より複数個設けられてもよい。 As shown in FIG. 8, the cutting device 2 is equipped with a traveling motor 21, a bit rotation motor 22, and a sand discharge pump 23, and a bit 24 at the bottom.
and a sediment inlet 25 are installed. In the illustrated example, there is one motor for each motor, but a plurality of motors may be provided depending on the scale of the shaft.
走行用モータ21の回転は、第9図に示される
ように、走行ギヤ211を経由して、案内枠1の
案内用ギヤ13に伝えられ、切削装置2が前進ま
たは後退する。切削装置2の重量またはビツト2
4で受ける掘削時の地盤反力は走行用ローラ21
2で案内枠1の上面または下面に伝えられ、切削
装置の走行をなめらかにする。 As shown in FIG. 9, the rotation of the travel motor 21 is transmitted to the guide gear 13 of the guide frame 1 via the travel gear 211, and the cutting device 2 moves forward or backward. Weight of cutting device 2 or bit 2
The ground reaction force during excavation received by the traveling roller 21
2 to the upper or lower surface of the guide frame 1, making the cutting device run smoothly.
第10図に示すように、ビツト回転用モータ2
2の回転はビツト回転用ギヤ221を経由してビ
ツト24に伝えられ、ビツトを回転する。図には
記載していないが、回転速度変換ギヤが必要とな
る場合もある。これは走行ギヤ211についても
同様である。 As shown in FIG. 10, the bit rotation motor 2
The rotation of the bit 24 is transmitted to the bit 24 via the bit rotation gear 221, and rotates the bit. Although not shown in the figure, a rotational speed conversion gear may be required. This also applies to the running gear 211.
地中連続壁用溝の施工は、第7図に示すよう
に、前述した手順でワイヤー巻きあげ用電動モー
タ82で案内枠1の深度を調節しながら進められ
る。掘削した土砂は土砂吸入口25から吸い上げ
られ、土砂排出用ポンプ23及び土砂排出パイプ
26を経由して地上に排出される。図には記載し
ていないが、土砂排出用ホース26及び電動機用
ケーブルは地上からクレーンで吊り下げられてい
る。 As shown in FIG. 7, the construction of the underground continuous wall trench is carried out by adjusting the depth of the guide frame 1 using the wire hoisting electric motor 82 according to the procedure described above. The excavated earth and sand is sucked up from the earth and sand suction port 25 and discharged to the ground via the earth and sand discharge pump 23 and the earth and sand discharge pipe 26. Although not shown in the figure, the earth and sand discharge hose 26 and the electric motor cable are suspended from the ground by a crane.
掘削中の案内枠1の水平方向の揺動は第6図に
示す定規杭3に嵌合する突起14で抑えられると
共に定規杭3の設置精度に合わせて掘削できる。
定規杭3の設置精度は高い方が望ましいが、それ
ぞれの定規杭3の建込精度が1/100程度でも、地
中連続壁用溝の掘削は可能である。 Horizontal swinging of the guide frame 1 during excavation is suppressed by a protrusion 14 that fits into the ruler pile 3 shown in FIG. 6, and excavation can be performed in accordance with the installation accuracy of the ruler pile 3.
Although it is desirable that the installation accuracy of the ruler piles 3 be high, it is possible to excavate a trench for an underground continuous wall even if the installation accuracy of each ruler pile 3 is about 1/100.
掘削が所要の深度まで達すると、案内枠1及び
切削装置2はワイヤー巻きあげ用電動機82で地
上まで引き上げられ、撤去される。その後、鉄筋
籠を投入し、コンクリートを打設することによつ
て、地中連続壁が完成される。 When the excavation reaches a required depth, the guide frame 1 and cutting device 2 are pulled up to the ground level by the wire hoisting motor 82 and removed. Thereafter, the underground continuous wall is completed by inserting reinforcing bars and pouring concrete.
本発明の方法によれば、例えば立坑の築造に適
用した場合には、円環状の立坑となるので従来必
要であつた多数の切梁が不要となり、作業空間が
広くなるので立坑内の作業の輻輳が防げるほか、
安全性が向上し、また、作業時間も短縮でき、地
中連続壁を継手なしで施工するので周囲の地盤か
らの漏水が大幅に減少し、円環状であるため周囲
の土圧及び水圧に対する抵抗力が大きくなり、従
つてコンクリート断面を減少することができ経済
的となる。また、地中連続壁の施工自体も、連続
的に施工することが可能なので、作業時間の短縮
と経費の節減が計れる。本発明の方法は、上記の
ほか、構造物の基礎、橋脚の大深度基礎などにも
利用でき、やはり上述したと同様の種々の利益を
もたらすことができる。 According to the method of the present invention, when applied to the construction of a shaft, for example, the shaft is circular, so there is no need for a large number of struts that were previously required, and the work space is widened, making it easier to work inside the shaft. In addition to preventing congestion,
Safety is improved and work time can be shortened. Since the diaphragm wall is constructed without joints, water leakage from the surrounding ground is significantly reduced, and the annular shape provides resistance to surrounding earth pressure and water pressure. The force is large and the concrete cross-section can therefore be reduced, making it economical. In addition, the construction of the underground continuous wall itself can be performed continuously, reducing work time and costs. In addition to the above, the method of the present invention can also be used for foundations of structures, deep foundations for bridge piers, etc., and can also bring about various benefits similar to those described above.
第1図は従来の工法で施工された立坑の平面
図、第2図は従来工法を応用して円形の立坑を施
工した平面図、第3図はその立面図、第4図は本
発明の装置で連続的に施工された立坑の平面図、
第5図はその立面図、第6図は案内枠、切削装置
及び定規杭の平面図、第7図(第6図における
−矢視図)は案内枠の上昇及び下降を説明する
図で、案内枠、定規杭及びワイヤー巻きあげ用電
動機の断面を示すものであり、第8図は切削装置
及び案内枠を円形立坑の内側からみた立面図、第
9図(第8図における−矢視図)は走行用モ
ータの位置で案内枠とともに切断した断面図、第
10図(第8図における−矢視図)はビツト
回転用モータの位置で案内枠とともに切断した断
面図である。
図において、1は案内枠、11は案内用突起
(上面)、12は案内用突起(下面)、13は案内
用ギヤ、14はガイド部、2は切削装置、21は
走行用モータ、211は走行用ギヤ、212は走
行用ローラ、22はビツト回転用モータ、221
はビツト回転用ギヤ、23は土砂排出ポンプ、2
4はビツト、25は土砂吸入口、26は土砂排出
ホース、3は定規杭、4は従来の装置による掘削
溝(コンクリート投入後)、5は本発明の装置に
よる掘削溝(コンクリート投入後)、6は立坑内
地盤、5′は本発明の装置による掘削溝、7は地
盤、81は吊りあげ用ワイヤー、82は吊りあげ
用モータ、83は滑車、41は腹起こし、42は
切梁、43は火打である。
Figure 1 is a plan view of a shaft constructed using the conventional construction method, Figure 2 is a plan view of a circular shaft constructed using the conventional construction method, Figure 3 is its elevation view, and Figure 4 is the invention of the present invention. A plan view of a vertical shaft constructed continuously using equipment such as
Figure 5 is an elevation view of the same, Figure 6 is a plan view of the guide frame, cutting device, and ruler pile, and Figure 7 (view from the - arrow in Figure 6) is a diagram explaining the raising and lowering of the guide frame. , a guide frame, a ruler pile, and a wire hoisting electric motor are shown in cross section; Figure 8 is an elevational view of the cutting device and guide frame seen from inside the circular shaft; Figure 9 (in Figure 8, the − arrow Fig. 10 (a view taken along the - arrow in Fig. 8) is a sectional view taken along with the guide frame at the position of the bit rotation motor. In the figure, 1 is a guide frame, 11 is a guide protrusion (upper surface), 12 is a guide protrusion (lower surface), 13 is a guide gear, 14 is a guide part, 2 is a cutting device, 21 is a traveling motor, and 211 is a Travel gear, 212 is a travel roller, 22 is a bit rotation motor, 221
is the bit rotation gear, 23 is the earth and sand discharge pump, 2
4 is a bit, 25 is an earth and sand inlet, 26 is an earth and sand discharge hose, 3 is a ruler pile, 4 is an excavation trench by a conventional device (after concrete is poured), 5 is an excavation trench by the device of the present invention (after concrete is poured), 6 is the ground in the shaft, 5' is the trench excavated by the device of the present invention, 7 is the ground, 81 is the lifting wire, 82 is the lifting motor, 83 is the pulley, 41 is the trundle, 42 is the strut, 43 is flint.
Claims (1)
し得る平面形状が円環状の案内桁1に、回転切削
刃、土砂排出用ポンプ及び走行装置を具備する切
削装置2を懸架し、該切削装置を該円環状案内桁
に沿つて連続的に走行させながら円環状の地中壁
用溝を施工することを特徴とする円環状地中壁築
造方法。1. A cutting device 2 equipped with a rotary cutting blade, an earth and sand discharge pump, and a traveling device is suspended on a guide girder 1 having an annular planar shape that can be raised and lowered along a plurality of vertical ruler piles 3. A method for constructing an annular underground wall, comprising constructing an annular underground wall groove while continuously running a device along the annular guide girder.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP13027182A JPS5921821A (en) | 1982-07-28 | 1982-07-28 | Circular underground wall construction |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP13027182A JPS5921821A (en) | 1982-07-28 | 1982-07-28 | Circular underground wall construction |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS5921821A JPS5921821A (en) | 1984-02-03 |
| JPS6213447B2 true JPS6213447B2 (en) | 1987-03-26 |
Family
ID=15030302
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP13027182A Granted JPS5921821A (en) | 1982-07-28 | 1982-07-28 | Circular underground wall construction |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS5921821A (en) |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS6263720A (en) * | 1985-09-12 | 1987-03-20 | Osaka Bosui Kensetsushiya:Kk | Construction work for round underground continuous wall |
| JP6832496B2 (en) * | 2017-02-16 | 2021-02-24 | 清水建設株式会社 | Construction method of intake / discharge port structure |
| CN110485434B (en) * | 2019-09-18 | 2021-07-23 | 建研地基基础工程有限责任公司 | Fabricated annular steel structure inner support structure system for deep foundation pit supporting and design method |
-
1982
- 1982-07-28 JP JP13027182A patent/JPS5921821A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS5921821A (en) | 1984-02-03 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN110158630B (en) | A ring-shaped underground continuous wall foundation for a long-span arch bridge in a thick overburden area | |
| CN116591148B (en) | Construction method of underground continuous wall system | |
| CN102888839A (en) | Construction method of static-pressure sleeve rotary digging filling pile | |
| CN114411756A (en) | Construction method and construction device for open-cut foundation pit of water-rich sand layer subway station without precipitation | |
| CN114108649A (en) | Foundation pit reinforcing construction method for mucky soil layer | |
| JP2002054131A (en) | Ground improvement structure and construction method that enables control of surrounding ground displacement | |
| CN106759106A (en) | A kind of constructing device and its construction method for revetment | |
| CN103866787B (en) | A kind of spacious reverse masonry method concrete cut that digs builds construction technology | |
| JPS6213447B2 (en) | ||
| CN209585079U (en) | The Yield rainfall relation building enclosure of beam is turned under a kind of subway station | |
| JP2726621B2 (en) | Caisson laying method and caisson blade structure | |
| CN207775897U (en) | A kind of supporting construction of rectangle interlocking pile | |
| CN111749292A (en) | Construction process for grooving wall-connecting ground in pipeline dense area | |
| JP3663155B2 (en) | Widening excavation apparatus and widening excavation method | |
| CN118187107A (en) | Construction method for supporting grid underground wall under complex slope environment condition | |
| JPH01146018A (en) | Method and apparatus for trenching ground | |
| GB2093090A (en) | Method and apparatus for making a deep trench | |
| JP7566235B1 (en) | Ground improvement methods | |
| JP2813061B2 (en) | Excavation method of continuous underground wall and its excavator | |
| CN108952007A (en) | Construction is positioned manually in a kind of permanent steel column | |
| CN107938682A (en) | A kind of supporting construction and its construction method of rectangle interlocking pile | |
| JPH0465932B2 (en) | ||
| JPH10121465A (en) | Continuos underground wall engineering method | |
| JPH0313696A (en) | Construction method for underground cave | |
| CN121088010A (en) | Open caisson construction method |