JPS6226381B2 - - Google Patents
Info
- Publication number
- JPS6226381B2 JPS6226381B2 JP19947482A JP19947482A JPS6226381B2 JP S6226381 B2 JPS6226381 B2 JP S6226381B2 JP 19947482 A JP19947482 A JP 19947482A JP 19947482 A JP19947482 A JP 19947482A JP S6226381 B2 JPS6226381 B2 JP S6226381B2
- Authority
- JP
- Japan
- Prior art keywords
- wire
- membrane
- construction
- carried out
- work
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Landscapes
- Tents Or Canopies (AREA)
Description
【発明の詳細な説明】
この発明は、空気膜構造構築物の施工法の提案
に係わる。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a proposal for a construction method for an air membrane structure construction.
空気膜構造の構築物は、我が国では、殆んど例
がないが、現在行なわれている工法としては、第
1図、第2図に示されるような工法で施工してい
る。 Although there are almost no examples of structures with air membrane structures in Japan, the construction methods currently in use are as shown in Figures 1 and 2.
すなわち、第1図に示すのは、先ず、ワイヤー
1をレツカー2、軍用ヘリコプター2′等により
躯体3上端のリングビーム4に先行架設を行ない
(a図)、その後、該ワイヤー1交点の締め付け並
びに膜5貼を該ワイヤー1に架設のゴンドラ6で
行なう(b図)方法若しくは、第2図に示す如
く、所定の膜面レベル下部に全面にステージ7を
架け、これを用いてワイヤー1、膜5を貼る方法
の2種類がある。 That is, as shown in FIG. 1, first, the wire 1 is pre-erected on the ring beam 4 at the upper end of the frame 3 using a retrieval car 2, a military helicopter 2', etc. (Figure a), and then the intersection of the wire 1 is tightened and The film 5 is pasted using a gondola 6 installed on the wire 1 (Figure b), or as shown in Figure 2, a stage 7 is hung over the entire surface below a predetermined film surface level, and this is used to paste the wire 1 and the film. There are two ways to paste 5.
いずれも観覧席S等の内部構築物の完了後に膜
屋根の架構工事が行なわれる。 In both cases, the construction of the membrane roof structure will be carried out after the internal structures such as the bleachers S are completed.
しかるに、叙上の如き要領の工法にあつては、
先ず、膜屋根架構の点については、第1図の工法
では高所作業の為、交点、膜の接続等の品質管理
が不十分となりやすく、ワイヤーの精度の不良、
膜のよれ等が発生し易い、又、工期的にも非能率
であつて長く、安全面も問題があり、他方、第2
図の工法では、前者の問題点を消去し得るが、高
い所への架設はステージが膨大なものとなり、工
期、コストの面で問題となる。 However, in the case of the construction method as described above,
First of all, regarding the membrane roof frame, since the construction method shown in Figure 1 involves work at high places, quality control of intersections, membrane connections, etc. is likely to be insufficient, resulting in poor wire accuracy,
The membrane is prone to twisting, the construction period is inefficient and long, and there are safety issues.
The construction method shown in the figure can eliminate the former problem, but the construction at a high place involves a huge number of stages, which poses problems in terms of construction time and cost.
又、工期の点については、内部構築物の施工を
露天で行なうものであるため、天候によつて工期
が影響を受けることとならざるを得ないが、現在
のきびしい受注条件のなかで特に、短工期を克服
しなければならない工事が多くなつているのに、
天候のために作業不能となる日が多くなり一層工
期もきびしくなるという難点がある。 In addition, regarding the construction period, since the internal structures will be constructed outdoors, the construction period will inevitably be affected by the weather, but given the current strict order conditions, it is especially Even though there are more and more construction projects that have to overcome the construction period,
The disadvantage is that there are many days when work is impossible due to weather, making the construction period even more difficult.
本発明は、叙上の事情に鑑み、上記の諸難点を
全く解消し得る新規な工法を開発すべくなされた
もので、その要旨とするところは、観覧席等の内
部構築物を除く外周躯体工事を先行し、当該躯体
内周面に立設の架設ワイヤー吊り上げガイドポス
トにワイヤー端部を係止させて当該ポストの中途
所定位置まで上昇させ、この状態にてワイヤー交
点の締め付け並びに膜貼を地上作業にて行ない、
完了後、ワイヤーをさらに上昇させて躯体上端の
リングビームに配設の取付用金具にワイヤー端部
を枢止組み付け、しかる後、該ポストを撤去する
として、膜屋根架構作業をワイヤー、膜の架設が
高所に於ける作業があつたのを地上作業でなし得
るものとして作業性(品質)の向上、工期短縮、
安全性の増加を図るとすると共に、当該膜屋根架
設が完了後、デフレート状態の膜面上部に水を貯
めると共に膜面中央部下面と地上間にロープ等を
架け渡して張設して風に対して安定させ、かかる
膜屋根の養生下で観覧席等の内部構築物、内部施
設の内部作業を行なうとして天候の如何にかかわ
らず、作業を可能として工期の短縮化を実現した
点にある。 In view of the above-mentioned circumstances, the present invention was made to develop a new construction method that can completely eliminate the above-mentioned difficulties. The ends of the wires are first secured to the wire lifting guide posts erected on the periphery of the structure, and the posts are raised to a predetermined position midway.In this state, the wire intersections are tightened and the membrane is pasted on the ground. Do it at work,
After completion, the wire is raised further and the end of the wire is pivotally assembled to the mounting bracket installed on the ring beam at the top of the frame. After that, the post is removed and the membrane roof frame work is carried out by wire and membrane erection. Improve work efficiency (quality), shorten construction time, and improve work efficiency (quality) by performing work on the ground instead of work at height
In order to increase safety, after the construction of the membrane roof is completed, water will be stored in the upper part of the deflated membrane surface, and a rope or the like will be strung between the central lower surface of the membrane surface and the ground to protect it from the wind. By stabilizing the membrane roof, work on internal structures such as bleachers and internal facilities can be carried out regardless of the weather, thereby shortening the construction period.
以下、これを実施例図にもとづいて詳細に説明
する。 Hereinafter, this will be explained in detail based on embodiment figures.
すなわち、第3図に於いて、図中8は外周躯
体、9は当該外周躯体8内周縁に立設の架設ワイ
ヤー吊り上げガイドポストで、これは、各架設ワ
イヤー10両端が沿移動可に係止組付けられるも
のであつて、各架設ワイヤーにつき外周躯体8周
辺に相対峙して設置されるものである。 That is, in FIG. 3, reference numeral 8 denotes an outer peripheral frame, and 9 denotes an erection wire lifting guide post erected on the inner peripheral edge of the outer circumferential frame 8, and both ends of each erection wire 10 are locked so as to be movable along the outer circumferential frame. It is assembled, and each construction wire is installed facing each other around the outer peripheral frame 8.
該架設ワイヤー10は該ポスト9に沿つて上昇
移動制御されるが、その駆動手段としては、スト
ロークジヤツキとピニオン・ラツクの組合せ等
種々考えられるが、図示例にあつては、架設ワイ
ヤー10の端部に装着の金具11を吊るワイヤー
ロープ12を該ポスト9上端上端に配設の滑車1
3を介して地上に設置のウインチ14で巻取るも
のとしている。 The erection wire 10 is controlled to move upward along the post 9. Various driving means are possible, such as a combination of a stroke jack and a pinion rack, but in the illustrated example, the movement of the erection wire 10 is controlled. A wire rope 12 for hanging a metal fitting 11 attached to the end is connected to a pulley 1 disposed at the upper end of the post 9.
3 and wind it up with a winch 14 installed on the ground.
かくして、全ての架設ワイヤー10の両端をポ
スト9に組み付けたならば、これを集中制御でも
つて地上作業に好適な所定高さとなるポスト9中
途所定位置まで上昇させて一旦停止し、この状態
にて地上作業による架設ワイヤー交点の締め付け
並びに膜15の貼作業をとり行なう。 In this way, once both ends of all the construction wires 10 have been assembled to the posts 9, they are raised to a predetermined position midway through the posts 9, which is a predetermined height suitable for ground work, using centralized control, and then stopped once. Tightening of the intersections of the construction wires and pasting of the membrane 15 are carried out on the ground.
しかる後、この交点締め付け並びに膜貼を完了
した架設ワイヤー10′を再度上昇させ、該外周
躯体8上端のリングビーム16に配設の取付用ア
ンカー17に該端部金具11を枢止組付すること
で架設がなされる。 Thereafter, the construction wire 10' having completed the intersection tightening and membrane pasting is raised again, and the end fitting 11 is pivotally assembled to the mounting anchor 17 disposed on the ring beam 16 at the upper end of the outer frame 8. Erection is done by this.
このあと、ワイヤーロープ12を端部金具11
より取りはずすと共に該ポスト9を撤去する。 After this, attach the wire rope 12 to the end fitting 11.
At the same time, the post 9 is removed.
図に於いて、架設ワイヤー10′の点鎖線態様
は内圧付加にて屋根膜がふくらんだインフレート
の態様を示す。 In the figure, the dotted chain line of the construction wire 10' indicates an inflated state in which the roof membrane swells when internal pressure is applied.
叙上実施例に於ける該架設ワイヤー端部金具1
1と架設ワイヤー吊り上げガイドポスト9の詳細
を第4図、第5図に示す。 The construction wire end fitting 1 in the above embodiment
1 and the construction wire lifting guide post 9 are shown in detail in FIGS. 4 and 5.
第4図a,bは架設ワイヤー端部金具11を示
し、これは略コの字状枠11aの前面壁11bに
架設ワイヤー10端部のボルトロツド10aを挿
通させ、ワツシヤー18、止めボルト19…にて
止着させ、両側壁11c,11′cのテール部を
ブラケツト11dに構成して、これと該取付用ア
ンカー17の先端部に穿孔の透孔17aとの間に
止めボルト(図示省略)を差し渡すことによつて
リングビーム16に対しての架設ワイヤー10の
枢止をなすとし、枠11a前端部には鞍状の吊フ
ツク11eが溶接されてあり、これにワイヤーロ
ープ12が止められて上記の金具11の吊りがな
されるものとし、さらに、該両側壁11c,1
1′cより取付軸11f,11′fを突設し、これ
にローラー11g,11′gを組み付け、これを
図示の如く、該ポスト9を構成するところの対峙
組付けのH鋼柱20,20′間に渡架させること
によつて、ポスト9に対する係止をなさしめたも
のである。尚、図中21,21′は該ローラー1
1g,11′g脱係防止用のためにH鋼柱20,
20′端部に溶接のレールである。 FIGS. 4a and 4b show the end fitting 11 for the construction wire, in which the bolt rod 10a at the end of the construction wire 10 is inserted through the front wall 11b of the approximately U-shaped frame 11a, and the washer 18, fixing bolt 19... The tails of both side walls 11c and 11'c are formed into a bracket 11d, and a fixing bolt (not shown) is inserted between the bracket 11d and the through hole 17a formed at the tip of the mounting anchor 17. The construction wire 10 is pivotally fixed to the ring beam 16 by passing it over, and a saddle-shaped hanging hook 11e is welded to the front end of the frame 11a, to which the wire rope 12 is fastened. The metal fittings 11 mentioned above shall be suspended, and the both side walls 11c, 1
Mounting shafts 11f, 11'f are provided protruding from 1'c, and rollers 11g, 11'g are assembled thereto, and as shown in the figure, the H steel columns 20, 20, which are assembled facing each other and which constitute the post 9, are mounted. 20', it is possible to lock the post 9. In addition, 21 and 21' in the figure are the rollers 1.
1g, 11'g H steel column 20 to prevent disengagement.
The rail is welded at the 20' end.
次に、ポスト9は第5図に詳示され、これは図
示例では上述の如く、H鋼柱20,20′を所定
間隔をもつて対峙させ、ヨークを渡架させて架構
構成される。 Next, the post 9 is shown in detail in FIG. 5, and in the illustrated example, as described above, the post 9 is constructed by having the H steel columns 20, 20' facing each other at a predetermined distance and spanning the yokes.
図中22はリングビーム16との間に差し渡し
のスペーサーである。 In the figure, 22 is a spacer extending between the ring beam 16 and the ring beam 16.
叙上の如く構成される本発明工法に於ける膜屋
根架構にあつては、ワイヤー交点の締め付け並び
に膜貼の全てを地上作業でもつてなし得るため、
良好なる品質管理のもとで作業し得、かつ、作業
性も向上し得、工期短縮、安全性、コストが著し
く改善され、特に、大規模な模構造の場合、安全
性、工期、コストに大きなメリツトを発揮するこ
ととなる。 In the case of the membrane roof frame according to the construction method of the present invention constructed as described above, all of the tightening of wire intersections and membrane pasting can be done on the ground.
Work can be carried out under good quality control, and work efficiency can be improved, reducing construction time, and significantly improving safety and cost. Especially in the case of large-scale mock structures, safety, construction time, and cost are significantly improved. This will bring great benefits.
次いで、第6図に示す如く、架設の完了したデ
フレート状態の膜屋根23上部に水24を貯める
と共に膜面中央部下面と地上間にロープ25,…
等を架け渡して張設して風に対して安定させ、か
かる膜屋根23の養生下にて、観覧席S等の内部
構築物、内部施設の内部作業をとり行なう。 Next, as shown in FIG. 6, water 24 is stored in the upper part of the deflated membrane roof 23, which has been completely erected, and ropes 25,...
etc., to stabilize against the wind, and work on internal structures such as the bleachers S and internal facilities is carried out under the protection of the membrane roof 23.
尚、この状態での降雨等による必要以上の貯水
に対しては膜面中央にドレイン26を設け、各グ
リツトからオーバーフローした水を下へ流して排
水してコントロールすれば良い。 Incidentally, in order to prevent water from accumulating more than necessary due to rain or the like in this state, a drain 26 may be provided at the center of the membrane surface, and the water overflowing from each grit may be drained by flowing downward to control it.
この内部作業は天候に一切影響されないので、
工期の短縮化に大いに寄与する。 This internal work is completely unaffected by the weather, so
This greatly contributes to shortening the construction period.
第1図a,b並びに第2図は従来工法の説明
図、第3図は、本発明工法に於ける膜屋根架構の
説明図、第4図a,bは本発明工法に於ける膜屋
根架構に使用する一治具の平面、側面図、第5図
a,bは本発明工法に於ける膜屋根架構に使用す
るポストの側面、正面図、第6図は本発明工法に
於ける内部作業の態様を示す説明図である。
S……観覧席、8……外周躯体、9……ガイド
ポスト、10……架設ワイヤー、15……膜、1
6……リングビーム、23……膜屋根、25……
ロープ。
Figures 1a and b and Figure 2 are explanatory diagrams of the conventional construction method, Figure 3 is an explanatory diagram of the membrane roof frame in the construction method of the present invention, and Figures 4a and b are diagrams of the membrane roof in the construction method of the present invention. A plan view and a side view of one jig used in the frame; Figures 5a and b are side and front views of a post used in the membrane roof frame in the construction method of the present invention; Figure 6 is a view of the interior in the construction method of the present invention. FIG. 2 is an explanatory diagram showing a mode of work. S...Seat, 8...Periphery frame, 9...Guide post, 10...Erection wire, 15...Membrane, 1
6...Ring beam, 23...Membrane roof, 25...
rope.
Claims (1)
行し、当該躯体内周面に立設の架設ワイヤー吊り
上げガイドポストにワイヤー端部を係止させて当
該ポストの中途所定位置まで上昇させ、この状態
にてワイヤー交点の締め付け並びに膜貼を地上作
業にて行ない、完了後、ワイヤーをさらに上昇さ
せて躯体上端にリングビームに配設の取付用金具
にワイヤー端部を枢止組み付け、しかる後、該ポ
ストを撤去し、膜屋根架構作業をとり行ない、当
該膜屋根架設が完了後、デフレート状態の膜面上
部に水を貯めると共に膜面中央部下面と地上間に
ロープを架け渡して張設して風に対して安定さ
せ、かかる膜屋根の養生下で観覧席等の内部構築
物、内部施設の内部作業を行なうとしてなること
を特徴とする空気膜構造構築物の施工法。1. Construction of the outer frame excluding the internal structures of the audience seats is carried out in advance, and the end of the wire is locked to the wire lifting guide post erected on the periphery of the frame, and the post is raised to a predetermined position midway, and this condition is maintained. Tightening the wire intersections and pasting the membrane are carried out on the ground. After completion, the wire is raised further and the wire end is pivotally assembled to the mounting bracket provided on the ring beam at the top of the structure. The posts were removed and the membrane roof construction work was carried out. After the construction of the membrane roof was completed, water was stored in the upper part of the deflated membrane surface, and a rope was strung between the lower surface of the center of the membrane surface and the ground. A construction method for an air membrane structure structure, which is stabilized against wind, and is characterized in that internal work on internal structures such as bleachers and internal facilities is carried out under the protection of such a membrane roof.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP19947482A JPS5988551A (en) | 1982-11-13 | 1982-11-13 | Construction of air membran structured construction |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP19947482A JPS5988551A (en) | 1982-11-13 | 1982-11-13 | Construction of air membran structured construction |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS5988551A JPS5988551A (en) | 1984-05-22 |
| JPS6226381B2 true JPS6226381B2 (en) | 1987-06-09 |
Family
ID=16408394
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP19947482A Granted JPS5988551A (en) | 1982-11-13 | 1982-11-13 | Construction of air membran structured construction |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS5988551A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS62136491U (en) * | 1986-02-21 | 1987-08-27 |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH0816406B2 (en) * | 1988-02-05 | 1996-02-21 | 太陽工業株式会社 | Suspension Membrane Extension Method for Suspended Membrane Roof Structure |
-
1982
- 1982-11-13 JP JP19947482A patent/JPS5988551A/en active Granted
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS62136491U (en) * | 1986-02-21 | 1987-08-27 |
Also Published As
| Publication number | Publication date |
|---|---|
| JPS5988551A (en) | 1984-05-22 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN108532769A (en) | A kind of jack-up construction method of the additional elevator shaft structure of assembled | |
| CN211691069U (en) | Installation and displacement monitoring structure of spoke type beam string | |
| CN108625483A (en) | A kind of equipment for the additional elevator shaft structure jack-up construction of assembled | |
| CN111794381A (en) | Reverse cable-stayed device for installing cable-supported grid steel structure and implementation method thereof | |
| US4880024A (en) | Self-supporting tent | |
| CN208345549U (en) | A kind of additional elevator shaft structure of assembled being adapted to jack-up construction | |
| JPH06101274A (en) | Method of constructing roof of cable dome | |
| JPS6226381B2 (en) | ||
| CN108584646A (en) | A kind of additional elevator shaft structure of the assembled being adapted to jack-up construction | |
| JP2946074B2 (en) | Large roof erection method | |
| CN216040726U (en) | Integral overturning and erecting device for steel cable tower | |
| JP3072214B2 (en) | Temporary shed | |
| CN214626865U (en) | A steel cable lap joint structure of photovoltaic support | |
| JPS5988553A (en) | Construction of air membran structured construction | |
| CN213682477U (en) | Upper cover structure system applied to track operation line | |
| JPS58345Y2 (en) | FRP high quality hardware | |
| CN221806784U (en) | Large-span topography photovoltaic support structure | |
| CN212688721U (en) | Jig frame for hoop prestress assembly type installation | |
| JP2663102B2 (en) | Long span canopy equipment and its construction method | |
| CN222526439U (en) | Wind turbine tower rain cover | |
| CN215291317U (en) | Truss car platform convenient to equipment and economy | |
| JP3111446B2 (en) | Gas station canopy manufacturing method | |
| JPS5988552A (en) | Construction of film structure | |
| JPS5841160A (en) | Method and apparatus for preventing pain scattering in painting work of high chimney | |
| JPH04176931A (en) | Distance controlling system for lift up method for stretch chord beam |