JPS6227204B2 - - Google Patents
Info
- Publication number
- JPS6227204B2 JPS6227204B2 JP3735178A JP3735178A JPS6227204B2 JP S6227204 B2 JPS6227204 B2 JP S6227204B2 JP 3735178 A JP3735178 A JP 3735178A JP 3735178 A JP3735178 A JP 3735178A JP S6227204 B2 JPS6227204 B2 JP S6227204B2
- Authority
- JP
- Japan
- Prior art keywords
- sand
- hollow tube
- ground
- penetration
- piles
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Description
【発明の詳細な説明】
〔産業上の利用分野〕
本発明は、柔軟地盤中に砂等の粉粒体の締固め
砂杭を造成し、これによつて地盤改良を行うこと
を目的とする締固め砂杭の造成工法に関するもの
である。[Detailed Description of the Invention] [Field of Industrial Application] The purpose of the present invention is to improve the ground by creating compacted sand piles of granular material such as sand in soft ground. This relates to the construction method for compacted sand piles.
螺旋羽根の付いた中空管を使用し、その中空管
を軟弱地面に回転貫入した後、地盤中へ砂を排出
しながら地表面まで引抜いて行く工法は、従来か
らサンドドレーン工法として知られている(例え
ば、特開昭51−30113号公報参照)。
This construction method, which uses a hollow pipe with spiral blades, rotates the pipe into soft ground, and then pulls it out to the ground surface while discharging sand into the ground has been known as the sand drain method. (For example, see Japanese Patent Application Laid-Open No. 51-30113).
上記の工法は、砂を排出しながら中空管を引抜
くだけであつて、途中で再貫入させるものではな
いから、地盤中に形成されるものは、単なる砂杭
(サンドドレーン)であり、締固め砂杭でない。 The above construction method simply pulls out the hollow pipe while discharging the sand, and does not re-penetrate it midway through, so what is formed in the ground is simply a sand pile (sand drain) and is tightened. It is not a hardened sand pile.
締固め砂杭を造成する工法としては、例えば特
開昭48−37906号公報に示されているように、中
空管の上部に起振機を装備し、この振動力を利用
して地盤中に貫入させ、その後、中空管を一定長
さ引抜き、該中空管内の砂を地盤中に排出させ、
再び中空管を振動させながら貫入することにより
締固め砂杭を造成する工法がある。 As a construction method for creating compacted sand piles, for example, as shown in Japanese Patent Application Laid-Open No. 48-37906, a vibrating machine is installed at the top of a hollow pipe, and the vibrating force is used to create a concrete pile in the ground. The hollow tube is then pulled out for a certain length and the sand inside the hollow tube is discharged into the ground.
There is a construction method that creates compacted sand piles by penetrating the hollow pipe while vibrating it again.
しかし、この工法は、振動騒音が大きいために
公害問題が生じ、民家、事務所等に近接した場所
では施工できない問題がある。 However, this construction method causes pollution problems due to large vibration and noise, and has the problem that it cannot be constructed in areas close to private houses, offices, etc.
また、中空のオーガスクリユーを使用して石灰
杭を造成する方法が特開昭49−45518号公報に示
されているが、この場合のスクリユー羽根はピツ
チが不等間隔であるため、必ず地盤を攪乱するも
のであり、オーガスクリユーの先端によつて排出
した石灰の袋の柱を締固める機能もない。 Furthermore, Japanese Patent Application Laid-Open No. 49-45518 discloses a method of constructing lime piles using hollow auger screws, but since the pitches of the screw blades in this case are unevenly spaced, they are always ground level. It also has no function of compacting the column of lime bags discharged by the tip of the auger crew.
したがつて、かかる技術をそのまま締固め砂杭
の造成工法に適用することはできない。 Therefore, such technology cannot be directly applied to the construction method of compacted sand piles.
そこで、本発明は、上述のような問題点を解決
し、振動によることなく、しかも十分な締固め効
果をもつた締固め砂杭の造成工法を提供すること
を目的とする。 SUMMARY OF THE INVENTION Therefore, an object of the present invention is to solve the above-mentioned problems and provide a method for constructing compacted sand piles that is free from vibration and has a sufficient compaction effect.
上記の問題点を解決するために、本発明は、軟
弱地盤中に砂等の粉粒状体の締固め砂杭を造成す
るにあたり、外周面に一定ピツチの螺旋状推進翼
を設けた中空管を使用し、その中空管を所定深度
まで正回転させながら、貫入する初期貫入工程の
後に、中空管下端から砂を排出しかつ逆回転させ
ながら一定長さ引抜く引抜き工程と、中空管を再
び正回転させながら貫入せしめて上記の排出砂を
締固める再貫入工程を順次地表まで実施するサイ
クルをくり返し、かつ上記各工程において中空管
の貫入及び引抜き時の送り量を1回転当り推進翼
の1リード分に設定するようにしたものである。
In order to solve the above-mentioned problems, the present invention provides a hollow tube provided with spiral propulsion blades of a constant pitch on the outer peripheral surface when constructing a compacted sand pile of powder and granular materials such as sand in soft ground. After the initial penetration process, in which the hollow tube is rotated forward to a predetermined depth and penetrated, the sand is discharged from the lower end of the hollow tube, and the sand is pulled out for a certain length while rotating in the opposite direction, and the Repeat the cycle of sequentially carrying out the re-penetration process to the ground surface, in which the pipe is penetrated while rotating forward again and the above-mentioned discharged sand is compacted, and in each of the above processes, the feed rate when penetrating and withdrawing the hollow pipe is adjusted per rotation. This is set to one lead of the propulsion blade.
まず、第1図のように一定ピツチの螺旋状推
進翼4のついた中空管7を所定深度まで回転しな
がら貫入する(初期貫入工程)。この場合、貫入
の送り量を1回転当たり推進翼の1リード分とな
るよう中空管7の回転貫入装置の昇降温度を設定
する。所定深度まで達すると回転を止め、のよ
うにホツパー5,6から中空管7内に砂を投入す
る。次に中空管7内へ圧縮空気を供給して内部の
空気圧を十分高めた後、のように中空管7を逆
回転させながら一定長さ引抜くとともに内部の内
部の砂を中空管7の下端から地盤中に排出する
(引抜き工程)。この場合の引抜き方向の送りも前
記と同様に1回転1リード分に設定する。
First, as shown in FIG. 1, a hollow tube 7 equipped with spiral propulsion blades 4 of a constant pitch is penetrated while rotating to a predetermined depth (initial penetration step). In this case, the raising and lowering temperatures of the rotary penetrating device of the hollow tube 7 are set so that the penetrating feed amount is equal to one lead of the propulsion blade per rotation. When reaching a predetermined depth, the rotation is stopped and sand is thrown into the hollow tube 7 from the hoppers 5 and 6 as shown in the figure. Next, compressed air is supplied into the hollow tube 7 to sufficiently increase the internal air pressure, and then the hollow tube 7 is pulled out for a certain length while rotating in the opposite direction, and the sand inside is removed from the hollow tube. 7 into the ground (pulling process). In this case, the feed in the drawing direction is also set to one lead per revolution, as described above.
次にのように、再び中空管7を正回転(初期
貫入工程と同方向)させ、かつ1回転当り1リー
ド分の回転を与えながら貫入する(再貫入工
程)。この再貫入工程によつて排出砂の締固める
とともに、周囲地盤中に拡径させる。 As described below, the hollow tube 7 is again rotated in the normal direction (in the same direction as the initial penetration step), and the tube is penetrated while being rotated by one lead per rotation (re-penetration step). This re-penetration process compacts the discharged sand and causes it to expand into the surrounding ground.
以後、上記の引抜き工程と再貫入工程のサイク
ルを順次地表面に達するまで繰り返えす。第2図
はこの操作サイクルを、中空管7の先端物の深度
GLと、時間Tとの関係をグラフで示したもので
ある。 Thereafter, the above-described cycle of extraction process and re-penetration process can be repeated in sequence until reaching the ground surface. FIG. 2 shows this operation cycle at the depth of the tip of the hollow tube 7.
This is a graph showing the relationship between GL and time T.
上記の各工程において中空管の正回転による貫
入、逆回転による引抜きの各送り量は、1回転当
り1リード分となるように設定してある。そのた
め、貫入時、引抜き時とも地盤は撹乱されないの
で、初期貫入後の引抜き及び再貫入のサイクルの
繰返えしの際、中空管の回転に伴う抵抗が少な
く、再貫入時においては、回転力を効率よく、推
進力に変えることができる。この推進力と回転貫
入装置の重量とにより排出砂に締固め力を及ぼす
ことができる。 In each of the above steps, the feed amount of the hollow tube when it is inserted by forward rotation and when it is pulled out by reverse rotation is set to be one lead per rotation. Therefore, the ground is not disturbed during both penetration and withdrawal, so when the cycle of withdrawal and re-penetration is repeated after the initial penetration, there is less resistance due to the rotation of the hollow tube, and during re-penetration, the rotation Power can be efficiently converted into propulsive force. This propulsion force and the weight of the rotary penetration device can exert a compaction force on the discharged sand.
なお、中空管7の下端には、地盤の逆流防止の
ため従来周知の手段として開閉弁等が設けられ
る。 Note that an on-off valve or the like is provided at the lower end of the hollow pipe 7 as a conventionally known means to prevent backflow of the ground.
次に第3図に示す装置について説明すれば、1
はクレーン本体、7は中空管であり、その上端部
には、砂等の粉粒体投入用ホツパー5,6を設け
ている。4は中空管の外周に固定した推進翼であ
る。3は中空管を回転させる駆動手段の一例で、
電動モーターあるいは油圧モーターと減速機から
構成されリーダ2に昇降自在に取付けられてい
る。これは油圧モーターでもよい。8はリーダー
2を昇降するバケツトであり、前記ホツパー5に
砂等を供給する。 Next, the device shown in FIG. 3 will be explained.
1 is a crane main body, and 7 is a hollow tube, the upper end of which is provided with hoppers 5 and 6 for charging powder and granular materials such as sand. 4 is a propulsion blade fixed to the outer periphery of the hollow tube. 3 is an example of a driving means for rotating a hollow tube,
It is composed of an electric motor or a hydraulic motor and a speed reducer, and is attached to the leader 2 so that it can be moved up and down. This may be a hydraulic motor. 8 is a bucket that lifts and lowers the leader 2, and supplies sand, etc. to the hopper 5.
具体例を述べると、中空管径400mm、推進翼の
巾150mm、推進翼の傾きが15゜で推進翼の巻数が
10巻、貫入装置重量10ton、45KWの回転駆動装
置からなる回転貫入装置を使用して、施工長15m
の締固め砂杭を造成した。 To give a concrete example, the diameter of the hollow tube is 400 mm, the width of the propulsion blade is 150 mm, the inclination of the propulsion blade is 15°, and the number of turns of the propulsion blade is
The construction length is 15m using a rotary penetration device consisting of 10 rolls, penetration device weight of 10 tons, and a 45KW rotary drive device.
Compacted sand piles were created.
上記の回転貫入装置の仕様は、推進翼つき中空
管がネジ状に貫入し、中空管の推進力を締固め力
として発揮させる為の条件式から導かれた数値の
一例である。アースオーガなどのような地盤を掘
削しながら、貫入していく螺旋羽根つき中空管で
は、引抜きながら地盤中に砂を排出した後、再び
貫入して砂杭を締固めるものであつて、地盤を乱
しながら貫入及び引抜きを行うことになるので、
地盤から受ける抵抗が大きく、効率的でない。 The specifications of the rotary penetration device described above are an example of numerical values derived from the conditional expression for the hollow tube with propulsion vanes to penetrate in a threaded manner and to exert the propulsive force of the hollow tube as compaction force. A hollow pipe with spiral blades that penetrates the ground while excavating it, such as an earth auger, discharges sand into the ground while being pulled out, and then penetrates again to compact the sand pile. Penetration and withdrawal will be performed while disturbing the
The resistance received from the ground is large, making it inefficient.
拡径は(砂杭断面積)/(中空管断面積)が3
以上得られ、締固め力として、測定した結果、
10ton程度得られることがわかつた。この締固め
力は、推進力と装置重量から地盤と中空管のフリ
クシヨンを差し引いた値である。貫入時に貫入力
が不足する場合やさらに大きな締固め力を必要と
する場合、推進翼の巻数を増加し、あるいは、推
進翼の巾を大きくするか、引込み力を付加すれば
よい。又、締固め中に管内からエアーをかければ
さらに砂杭径を拡大することもできる。 The diameter expansion is (sand pile cross-sectional area) / (hollow pipe cross-sectional area) 3
The results obtained above and measured as compaction force are:
It was found that about 10 tons could be obtained. This compaction force is the value obtained by subtracting the friction of the ground and hollow tube from the propulsion force and the weight of the equipment. If the penetration force is insufficient during penetration or if a larger compaction force is required, the number of windings of the propulsion blades may be increased, the width of the propulsion blades may be increased, or retraction force may be added. Furthermore, the sand pile diameter can be further expanded by applying air from inside the pipe during compaction.
従来回転式サンドドレーン装置では中空管内の
砂量を計測する砂量計は使用されず、バケツト容
量とその砂投入回数によつて、地盤中に排出され
た砂量を推定しており、又砂が中空管から地盤中
に排出されるかどうかは中空管を地表面上に引抜
いた後中空管内に砂が残つているかどうかで確か
めていたにすぎない。しかし、本実施例では、砂
杭の品質管理を確実に行うために砂量計を使用
し、これによつて中空管内からの砂の排出の良否
及び中空管の貫入深度を表示する深度計と組み合
わせて、排出砂量から所定の砂杭径を造成するよ
うに再貫入長を決定することが可能である。 Conventional rotary sand drain equipment does not use a sand meter to measure the amount of sand in the hollow pipe, but estimates the amount of sand discharged into the ground based on the capacity of the bucket and the number of times sand is added. The only way to check whether sand was being discharged from the hollow tube into the ground was to check whether sand remained inside the hollow tube after it was pulled out above the ground surface. However, in this embodiment, a sand meter is used to ensure quality control of the sand pile, and a depth meter is used to display the quality of sand discharge from the hollow pipe and the penetration depth of the hollow pipe. In combination with this, it is possible to determine the re-penetration length so as to create a predetermined sand pile diameter from the amount of discharged sand.
本発明は、上記のように中空管の貫入及び引抜
き時の送り量を、1回転当たり推進量の1リード
分に設定したことにより、地盤を乱すことがな
い。そのため、中空管の引抜きと再貫入の繰返し
により排出砂を締固める際、その回転力を効率よ
く推進力(締固め力)に変えることができる。
The present invention does not disturb the ground because the feed amount during penetration and withdrawal of the hollow tube is set to one lead of the propulsion amount per revolution as described above. Therefore, when compacting the discharged sand by repeatedly pulling out and re-penetrating the hollow tube, the rotational force can be efficiently converted into propulsive force (compaction force).
そのため、特別の締固め装置を用いることな
く、無振動無騒音のシンプルな装置により締固め
砂杭を能率よく造成することができる。 Therefore, compacted sand piles can be efficiently created using a simple device that is vibrationless and noiseless, without using any special compaction equipment.
第1図は本発明工法の工程別断面図、第2図は
本発明工法の施工サイクルを示すグラフ、第3図
は施工装置の一例を示す一部切欠側面図である。
3……回転駆動装置、4……推進翼、5,6…
…ホツパー、7……中空管。
FIG. 1 is a sectional view of each step of the construction method of the present invention, FIG. 2 is a graph showing a construction cycle of the construction method of the present invention, and FIG. 3 is a partially cutaway side view showing an example of construction equipment. 3...Rotary drive device, 4...Propulsion blade, 5, 6...
...Hopper, 7...Hollow tube.
Claims (1)
造成するにあたり、外周面に一定ピツチの螺旋状
推進翼を設けた中空管を使用し、その中空管を所
定深度まで正回転させながら、貫入する初期貫入
工程の後に、中空管下端から砂を排出しかつ逆回
転させながら一定長さ引抜く引抜き工程と、中空
管を再び正回転させながら貫入せしめて上記の排
出砂を締固める再貫入工程を順次地表まで実施す
るサイクルをくり返し、、かつ上記各工程におい
て中空管の貫入及び引抜き時の送り量を1回転当
り推進翼の1リード分に設定することを特徴とす
る締固め砂杭の造成工法。1. When constructing compacted sand piles of powder and granular materials such as sand in soft ground, a hollow tube with spiral propulsion blades of a certain pitch on the outer circumferential surface is used, and the hollow tube is vertically pushed to a predetermined depth. After the initial penetration process in which the sand is penetrated while rotating, there is a drawing process in which the sand is discharged from the lower end of the hollow tube and pulled out for a certain length while being rotated in the opposite direction, and then the sand is penetrated again while being rotated in the forward direction to perform the above-mentioned discharge process. It is characterized by repeating a cycle in which the re-penetration process for compacting the sand is carried out sequentially to the ground surface, and in each of the above processes, the feed amount when penetrating and withdrawing the hollow tube is set to one lead of the propulsion blade per rotation. A construction method for compacted sand piles.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP3735178A JPS54128113A (en) | 1978-03-27 | 1978-03-27 | Method of creation construction of compaction sand pile |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP3735178A JPS54128113A (en) | 1978-03-27 | 1978-03-27 | Method of creation construction of compaction sand pile |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS54128113A JPS54128113A (en) | 1979-10-04 |
| JPS6227204B2 true JPS6227204B2 (en) | 1987-06-12 |
Family
ID=12495134
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP3735178A Granted JPS54128113A (en) | 1978-03-27 | 1978-03-27 | Method of creation construction of compaction sand pile |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS54128113A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2006016860A (en) * | 2004-07-02 | 2006-01-19 | Gosei Kogyo:Kk | Road bed improvement method and screw drill and rolling compaction pipe used in it |
-
1978
- 1978-03-27 JP JP3735178A patent/JPS54128113A/en active Granted
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2006016860A (en) * | 2004-07-02 | 2006-01-19 | Gosei Kogyo:Kk | Road bed improvement method and screw drill and rolling compaction pipe used in it |
Also Published As
| Publication number | Publication date |
|---|---|
| JPS54128113A (en) | 1979-10-04 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US3690109A (en) | Method and means for producing pile or like structural columns in situ | |
| JPH11509900A (en) | Improved auger stakeout | |
| JPH0531607B2 (en) | ||
| US5279502A (en) | Apparatus and method for constructing compacted granular or stone columns in soil masses | |
| US3485052A (en) | Method and means for forming concrete piles | |
| US3282055A (en) | Soil settling method | |
| US3807184A (en) | Method and means for producing pile or like structural columns in situ | |
| JP3754131B2 (en) | Ground improvement method | |
| US3426538A (en) | Method of making sand drains in situ | |
| JPS6227204B2 (en) | ||
| JP2004183310A (en) | Soil improvement method and apparatus | |
| CN1973092A (en) | Ground improvement device and ground improvement method | |
| JPS6342046B2 (en) | ||
| JP2001182047A (en) | Construction method and device for static improvement of soft ground | |
| JPS6225808B2 (en) | ||
| US3423944A (en) | Method for forming end bearing concrete piles | |
| JP2004270260A (en) | Non-removed earth foundation post construction apparatus and non-removed earth foundation pole construction method | |
| JP2000154532A (en) | Ground improvement method and its excavation equipment | |
| JPS5681719A (en) | Driving method of precast pile | |
| JPH0913372A (en) | Pile construction method | |
| JP2709382B2 (en) | An auger drill for drilling a spiral groove and a method of constructing a spiral groove on the peripheral wall of an underground hole with this auger drill. | |
| JPH0745672Y2 (en) | Earth auger | |
| JPS60115710A (en) | Improvement work of soft ground | |
| JP2000345554A (en) | Ground improvement method | |
| JP3524433B2 (en) | Improvement method of soft ground with hard layer |