JPS6252086B2 - - Google Patents
Info
- Publication number
- JPS6252086B2 JPS6252086B2 JP56100438A JP10043881A JPS6252086B2 JP S6252086 B2 JPS6252086 B2 JP S6252086B2 JP 56100438 A JP56100438 A JP 56100438A JP 10043881 A JP10043881 A JP 10043881A JP S6252086 B2 JPS6252086 B2 JP S6252086B2
- Authority
- JP
- Japan
- Prior art keywords
- soil
- improved
- ground
- rotary excavation
- amount
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/12—Consolidating by placing solidifying or pore-filling substances in the soil
- E02D3/126—Consolidating by placing solidifying or pore-filling substances in the soil and mixing by rotating blades
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Structural Engineering (AREA)
- Agronomy & Crop Science (AREA)
- Environmental & Geological Engineering (AREA)
- Soil Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Description
【発明の詳細な説明】
本発明は、海底等における軟弱地盤を硬化剤に
よつて硬化改良する工法およびその処理機に関す
るものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a construction method for hardening and improving soft ground on the ocean floor or the like using a hardening agent, and a treatment machine therefor.
従来の軟弱地盤の改良工事の施工を、地盤改良
台船を使用して海底の軟弱地盤を硬化改良し、護
岸を構築する場合について説明すると、第1図に
示すように櫓2、地盤改良処理機3、処理機の昇
降用ウインチ4、硬化剤サイロ5、硬化剤スラリ
製造用のプラント6、操作室7、係留ウインチ
8、アンカー8′等の設備を備えた地盤改良台船
1によつて、下端部に回転掘削・撹拌機構(後
記)を有する多軸の地盤改良処理機3を、昇降ウ
インチ4によつて櫓2から吊り、回転掘削・撹拌
機構を回転し掘削しつつ自重により海面C下の軟
弱地盤Aの深部まで貫入し所期の深度に達したの
ち、回転掘削・撹拌機構を回転しながら上昇、引
抜きし、かつその上部で硬化剤を吐出して、硬化
剤と軟弱土とを混練しながら単位の改良杭を軟弱
地盤A中に造成し、さらに、地盤改良処理機3の
位置を少し動かし、再度前記の作業を繰返して改
良杭群Bを造成する。その改良杭群Bは、第2図
に示すような単位改良杭群12、または既設改良
杭に隣設改良杭をラツプさせて施工した壁状杭1
3、格子状杭14、ブロツク状杭15等の土中構
造物を造成して軟弱地盤Aを硬化改良土にすると
ともに、その上側にケーソン護岸9、埋立土10
等を施工するようになつている。 To explain the conventional construction of soft ground improvement work in which a ground improvement barge is used to harden and improve the soft ground on the seabed and construct a seawall, as shown in Figure 1, the turret 2, the ground improvement treatment By means of a soil improvement barge 1 equipped with equipment such as a machine 3, a winch 4 for raising and lowering the processing machine, a hardener silo 5, a plant 6 for manufacturing hardener slurry, an operation room 7, a mooring winch 8, and an anchor 8'. A multi-axis ground improvement treatment machine 3, which has a rotary excavation/stirring mechanism (described later) at the lower end, is suspended from the tower 2 by an elevating winch 4, and the rotary excavation/stirring mechanism is rotated and excavated while the sea surface C is lowered by its own weight. After penetrating deep into the soft ground A below and reaching the desired depth, the rotary excavation/stirring mechanism is rotated as it rises and pulled out, and the hardening agent is discharged from the top to mix the hardening agent and soft soil. A unit of improved piles is created in soft ground A while kneading, and then the position of the ground improvement processing machine 3 is slightly moved and the above operation is repeated again to create an improved pile group B. The improved pile group B is a unit improved pile group 12 as shown in Fig. 2, or a wall pile 1 constructed by wrapping an adjacent improved pile around an existing improved pile.
3. Create underground structures such as lattice piles 14 and block piles 15 to turn soft ground A into hardened and improved soil, and above it, caisson revetment 9 and reclaimed soil 10
etc. are being constructed.
さらに、前記の改良杭群Bの施工は、第3図
A,Bに示すように地盤改良処理機3の下端部に
設けている掘削翼28、撹拌翼29、回転軸30
よりなる回転掘削・撹拌機構Dによつて、既設改
良杭31に対して(a)量ラツプさせて回転掘削・撹
拌機構Dを回転駆動しながら垂直に貫入すること
により、既設改良杭31のラツプ部分(a)量を切削
しながら掘削したのち、さらに回転掘削・撹拌機
構Dを回転しつつ同一軌跡で垂直に上昇、引抜き
するとともに、その上部にて硬化剤吐出具111
から硬化剤を吐出し、硬化剤を軟弱土に混練して
既設改良杭31に隣接改良杭114を接合させて
順次に施工している。 Furthermore, the construction of the improved pile group B is carried out using the excavating blades 28, stirring blades 29, and rotating shaft 30 provided at the lower end of the soil improvement processing machine 3, as shown in FIGS. 3A and 3B.
The existing improved pile 31 is rapped by (a) vertically penetrating the existing improved pile 31 while driving the rotary excavating/stirring mechanism D to rotate. After excavating while cutting the portion (a), the rotary excavation/stirring mechanism D is further rotated and vertically raised and pulled out along the same trajectory, and at the top thereof, the curing agent discharging tool 111 is removed.
A hardening agent is discharged from the soil, the hardening agent is mixed into the soft soil, and the adjacent improved piles 114 are joined to the existing improved piles 31 and constructed in sequence.
また、前記の地盤改良処理機3は、第5図A,
Bに示すように処理機駆動部39、支柱および回
転軸等よりなる処理機本体40、処理機駆動部3
9から突設されサブリーダ42のレールに昇降自
在に嵌合したガイド部材41、サブリーダ42の
下端部にあつて処理機本体40を昇降自在に嵌挿
したガイド部材43、地盤改良台船1上の櫓2に
設けられたサブリーダ42を昇降可能に拘束した
ガイド部材115、別のサブリーダ44、処理機
駆動部39を別のサブリーダ44に昇降自在に嵌
合させた接合金物45、処理機本体40を昇降自
在に拘束・ガイドしたガイド装置46等によつて
構成されており、その処理機本体40の下端部に
設けられている回転掘削・撹拌装置Dを積極的に
水平方向に移動させたり、垂直方向の移動を制御
できるようになつてはいない。 In addition, the ground improvement processing machine 3 shown in FIG. 5A,
As shown in FIG.
A guide member 41 protruding from the sub-leader 42 and fitted in the rail of the sub-leader 42 in a vertically movable manner; A guide member 115 that restrains the sub-leader 42 provided on the tower 2 so that it can be raised and lowered, another sub-leader 44, a joining metal fitting 45 that fits the processing machine drive unit 39 to another sub-leader 44 so that it can be raised and lowered, and the processing machine main body 40. It is composed of a guide device 46 etc. that is restrained and guided so as to be able to move up and down, and the rotary excavation/agitation device D provided at the lower end of the processing machine main body 40 can be actively moved horizontally or vertically. It is not yet possible to control directional movement.
従つて、前記の地盤改良処理機3により改良杭
群Bを施工すると、その回転掘削・撹拌機構Dを
垂直方向に貫入、引抜きしたいニーズに対し、地
盤抵抗のアンバラ、機器荷重のアンバラ等により
その軌道が外れ曲行するのを回避できない。その
ため、第3図Bに示すように既設改良杭31と隣
接改良杭114との間に硬化剤が混練されていな
い未改良土34を残すおそれがあり、また、隣設
改良杭114を次々に連設すると、第4図Aに示
すように垂直線イに対し、貫入、引抜線ロ,ロ′
の曲折が大きくなり、既設改良杭31と隣接改良
杭114との間にラツプ接合部19のほかに大き
い未改良土20の部分が生ずるようになつて、単
位改良杭相互の接合性が悪化し、改良杭の垂直性
も損われるようになり、改良杭群の施工不良即ち
地盤改良が不十分になる難点がある。 Therefore, when the improved pile group B is constructed using the ground improvement treatment machine 3, the rotary excavation/stirring mechanism D needs to be penetrated and pulled out in the vertical direction, but due to uneven ground resistance, uneven equipment load, etc. It is impossible to avoid going off track and making a curve. Therefore, as shown in FIG. 3B, there is a risk that unimproved soil 34 in which no curing agent has been mixed may remain between the existing improved pile 31 and the adjacent improved pile 114, and the adjacent improved pile 114 may be removed one after another. When installed in series, as shown in Fig. 4A, the penetration and pull-out lines RO and RO'
As a result, a large portion of unimproved soil 20 is formed between the existing improved pile 31 and the adjacent improved pile 114 in addition to the lap joint 19, and the bondability between the unit improved piles deteriorates. , the verticality of the improved piles is also impaired, resulting in poor construction of the group of improved piles, that is, insufficient ground improvement.
本発明は、前記のような難点を解消した軟弱地
盤の改良工法およびその改良処理機に係り、地盤
改良処理機の回転掘削・撹拌機構を駆動して軟弱
地盤中に貫入、引抜きし、硬化剤と軟弱土とを混
練して地盤を硬化改良する軟弱地盤改良工法にお
いて、貫入の当初に既改良土とのラツプ量を少め
にし同程度のラツプ量を保ちながら貫入し、回転
掘削・撹拌機構の近くに設けた水平張出機構によ
る制御により貫入の途中からラツプ量を大きくし
て貫入、掘削し、引抜時は前記ラツプ量を大きく
した位置から垂直に引抜いて既改良土の一部を削
りながら地盤を硬化改良する軟弱地盤改良工法、
回転掘削・撹拌機構を駆動し既改良土に一部ラツ
プさせて軟弱地盤中に貫入、引抜きするととも
に、回転掘削・撹拌機構の近くに配設した硬化剤
吐出具から硬化剤を吐出して軟弱土と混練して地
盤を硬化改良する地盤改良処理機において、前記
回転掘削・撹拌機構の近くに、同回転掘削・撹拌
機構を貫入、引抜時に回転掘削・撹拌機構を既改
良土側に移動せしめかつ垂直方向に制御する水平
張出機構を配設した軟弱地盤改良処理機に特徴を
有するものであつて、その目的とする処は、既改
良土(改良杭群)に対する隣設改良土(隣設改良
杭)の接合性を向上するとともに地盤改良を円滑
に施工することができる軟弱地盤改良工法を供す
る点にあり、さらに、前記工法に用いて同工法を
可能とする軟弱地盤改良処理機を供する点にあ
る。 The present invention relates to an improved construction method for soft ground that eliminates the above-mentioned difficulties, and an improved treatment machine for the same. In the soft ground improvement method, which hardens and improves the ground by kneading it with soft soil, the amount of lap with the improved soil is reduced at the beginning of penetration, the amount of lap is maintained at the same level, and the rotary excavation/agitation mechanism is used. Under the control of a horizontal extension mechanism installed near the hole, penetration and excavation are carried out by increasing the amount of lap from the middle of penetration, and when pulling out, the hole is pulled out vertically from the position where the amount of lap is increased to scrape off a part of the improved soil. Soft ground improvement method that hardens and improves the ground while
The rotary excavation/stirring mechanism is driven to penetrate and pull out the soft ground by partially wrapping it in the improved soil, and the hardening agent is discharged from the hardening agent dispensing tool placed near the rotary excavation/stirring mechanism to loosen the soft ground. In a soil improvement treatment machine that hardens and improves the ground by mixing it with soil, the rotary excavating and stirring mechanism is inserted near the rotary excavating and stirring mechanism, and when pulled out, the rotary excavating and stirring mechanism is moved to the improved soil side. It is characterized by a soft ground improvement treatment machine that is equipped with a horizontal extension mechanism that controls in the vertical direction. The object of the present invention is to provide a soft ground improvement method that improves the bonding properties of (improved piles) and allows for smooth ground improvement. It is in the point of providing.
本発明は、前記した構成になつており、貫入時
には当初に既改良土とのラツプ量を少なめにし、
貫入途中からラツプ量を大きくして貫入、掘削
し、引抜時にはその位置から垂直に引抜いて既改
良土の一部を削りながら地盤を硬化改良するた
め、既改良土と隣設改良土相互間に未改良土が介
在される不具合が解消され、回転掘削・撹拌機構
の近くに設けた水平張出機構によつて、貫入途中
における前記ラツプ量の増大、引抜時の垂直方向
制御を容易とし、ラツプ量が必要最少限になると
ともに施工精度が高められ、改良土の接合性(連
設)が著しく向上されるとともに、精度のよい施
工が可能となるため迅速、円滑に施工できて作業
能率が大巾に向上される。 The present invention has the above-mentioned configuration, and at the time of penetration, the amount of overlap with the improved soil is initially reduced,
Penetration and excavation are carried out by increasing the amount of lap from the middle of penetration, and when pulling out, it is pulled out vertically from that position to harden and improve the ground while scraping a part of the improved soil. The problem of unimproved soil being interposed has been resolved, and the horizontal extension mechanism installed near the rotary excavation/agitation mechanism makes it easier to increase the amount of lap during penetration and to control the vertical direction during extraction. The amount required is minimized, construction accuracy is improved, and the bondability (continuous installation) of the improved soil is significantly improved.It also enables highly accurate construction, which allows for quick and smooth construction and greatly increases work efficiency. It will be greatly improved.
また、本発明においては、地盤改良処理機の回
転掘削・撹拌機構の近くに、貫入、引抜時に回転
掘削・撹拌機構を既改良土側に移動せしめ、かつ
垂直方向に制御する水平張出機構を配設している
ので、貫入、引抜中に随時に回転掘削・撹拌機構
を水平方向の移動とそれにより垂直方向に制御す
ることができ、かつその作動は水平張出機構によ
つて直接に行なわれるため地圧などに十分に対抗
できる強力なものとなり、確実、正確に作動でき
て高精度の施工を可能にすることができる。 In addition, in the present invention, a horizontal extension mechanism is provided near the rotary excavation/agitation mechanism of the soil improvement treatment machine to move the rotary excavation/agitation mechanism toward the improved soil side during penetration or withdrawal, and to control it in the vertical direction. Because of this, the rotary excavation/agitation mechanism can be moved in the horizontal direction and thereby controlled in the vertical direction at any time during penetration and extraction, and its operation is performed directly by the horizontal extension mechanism. Because of this, it is strong enough to withstand ground pressure, and can operate reliably and accurately, making it possible to perform highly precise construction.
以下本発明の実施例を図示について説明する。
第3図C,Dに本発明の軟弱地盤改良工法の実施
例が示されており、その実施例の工法は、後記す
る地盤改良処理機の回転掘削・撹拌機構Eを回転
駆動し、貫入の当初には既改良土31に対する計
画上のラツプ(a)に対し少ないラツプ量(b)にし、貫
入途中からラツプ量を大きくしつつ貫入、掘削し
て、所定深度に達した時に前記の計画ラツプ量(a)
に至らしめ、引抜時には回転掘削・撹拌機構Eを
回転しながらその位置から垂直に上昇、引抜きに
より、既改良土の部分Cを切削しつつ、同時に回
転掘削・撹拌機構Eの上部において硬化剤吐出具
111から硬化剤を撹拌されている軟弱土中に送
込み、硬化剤と軟弱土とを混練して隣接部に改良
土を施工する工法にしている。この工法において
は、回転掘削・撹拌機構Eの回転軸30部分が、
第3図Dに示すように貫入の当初においてはハ線
上を垂直に下降し、途中においてその軌道が修正
されて既改良土31側に偏向する斜線ハ′をたど
り、さらにその位置から垂直に上昇する垂直線ニ
に沿つて移動するとともに、回転掘削・撹拌機構
Eの既改良土側の先端軌跡は線37から線38と
なり、その回転掘削・撹拌機構Eによる既改良土
の切削り量は、貫入当初のラツプ量(b)、貫入途中
から次第にラツプ量(a)に達し、引抜時には残りの
ラツプ量(c)部分を切削ることになる。 Embodiments of the present invention will be described below with reference to the drawings.
An embodiment of the soft ground improvement method of the present invention is shown in FIGS. Initially, the planned lap amount (b) for the improved soil 31 is set smaller than the planned lap (a), and from the middle of penetration, penetration and excavation are carried out while increasing the lap amount, and when the predetermined depth is reached, the planned lap amount is Amount (a)
At the time of pulling out, the rotary excavation/stirring mechanism E is rotated and lifted vertically from that position.By pulling out, part C of the improved soil is cut, and at the same time, hardening agent is discharged from the upper part of the rotary excavation/stirring mechanism E. The method is such that a hardening agent is sent into the stirred soft soil from a tool 111, the hardening agent and the soft soil are kneaded, and improved soil is constructed in the adjacent area. In this method, the rotating shaft 30 of the rotary excavation/stirring mechanism E is
As shown in Figure 3D, at the beginning of the penetration, it descends vertically on the line C, and midway through, its trajectory is corrected and deflects toward the improved soil 31, following the diagonal line C', and then rises vertically from that position. The locus of the tip of the rotary excavation/stirring mechanism E on the improved soil side changes from line 37 to line 38, and the amount of cut of the improved soil by the rotary excavation/stirring mechanism E is as follows: The lapping amount (b) at the beginning of penetration, gradually reaches the lapping amount (a) during the penetration, and the remaining lapping amount (c) is cut off at the time of extraction.
次に、前記実施例の工法に用いられる地盤改良
処理機の実施例について説明すると、同実施例の
概要は、第6図A,Bに示すように処理機機体支
柱48、同処理機機体支柱48に取付けられた回
転軸30用軸受49、回転軸駆動原動機50、掘
削翼28と撹拌翼29とよりなる回転掘削・撹拌
機構Eの部分に付設された水平張出機構F、およ
び同水平張出機構Fの遠隔駆動装置51により構
成され、多軸構造になつている。さらにその回転
掘削・撹拌装置Eと水平張出機構Fを第7図A,
Bの拡大図によつて説明すると、撹拌翼29が多
段に配設され、その水平張出機構Fの一方の張出
部材47は格納状態で、他方の張出部材47′は
張出した作動状態で示され、第7図Bで示すよう
に処理機機体支柱48に対し回転掘削・撹拌機構
Eが4個1組に配設されるとともに、両張出部材
47,47′は両側に配設された構造になつてい
る。 Next, an example of the soil improvement treatment machine used in the construction method of the above embodiment will be explained.The outline of the example is as shown in FIGS. 6A and B. A bearing 49 for the rotating shaft 30 attached to the rotating shaft 30, a rotating shaft driving prime mover 50, a horizontal extending mechanism F attached to a portion of the rotary excavating/agitating mechanism E consisting of the excavating blade 28 and the stirring blade 29, and the horizontal extending mechanism F It is composed of a remote drive device 51 of the output mechanism F, and has a multi-axis structure. Furthermore, the rotary excavation/stirring device E and horizontal extension mechanism F are shown in Figure 7A.
Referring to the enlarged view of B, the stirring blades 29 are arranged in multiple stages, and one of the extending members 47 of the horizontal extending mechanism F is in the retracted state, and the other extending member 47' is in the extended operating state. As shown in FIG. 7B, a set of four rotary excavating/agitating mechanisms E are arranged on the processing machine body support 48, and both projecting members 47 and 47' are arranged on both sides. It has a well-structured structure.
次に、前記の水平張出機構Fの第1実施例を第
8図A,B,Cに示しており、図中52,53は
張出部材、55は支柱48に取付けられ、ピン5
4により張出部材52を回転自在に接合したブラ
ケツト、57は支柱48に取付けられ、ピン56
によりリンク58を回転自在に接合したブラケツ
ト、59は張出部材53およびリンク58を回転
自在に接合したピン、60は張出部材の駆動装
置、61は張出部材52と駆動装置60を回転自
在に接合したピン、63は支柱48に取付けら
れ、ピン62により駆動装置60を回転自在に接
合したブラケツト、65,64は張出部材の格納
時および作動時におけるストツパ、116は回転
軸フランジにより構成されている。 Next, a first embodiment of the above-mentioned horizontal extension mechanism F is shown in FIGS.
4 is a bracket to which the overhanging member 52 is rotatably joined; 57 is attached to the support column 48;
a bracket to which the link 58 is rotatably joined, 59 a pin to which the overhang member 53 and the link 58 are rotatably joined, 60 a drive device for the overhang member, 61 a rotatable link between the overhang member 52 and the drive device 60; A pin 63 is attached to the support column 48, and a bracket to which the drive device 60 is rotatably connected by the pin 62, 65 and 64 are stoppers for storing and operating the overhanging member, and 116 is a rotating shaft flange. has been done.
また、第9図A,Bには水平張出機構Fの第2
実施例が示されており、図中66は張出部材、6
7,68はピン69および70により回転自在に
張出部材66に接合したブラケツト、71,72
は支柱48に接合し、ブラケツト73,74をピ
ン75および76により回転自在に支持したブラ
ケツト、77はピン78および79の間隔がほぼ
ピン69,70の間隔と等しい寸法を有するリン
ク、80は張出部材の駆動装置、81は支柱48
に取付けられ、ピン82により駆動装置80を回
転自在に支持したブラケツトにより構成されてい
る。 In addition, Fig. 9A and B show the second part of the horizontal extension mechanism F.
An example is shown, and in the figure 66 is an overhanging member;
7, 68 are brackets 71, 72 rotatably joined to the overhanging member 66 by pins 69 and 70;
77 is a link having a dimension in which the distance between pins 78 and 79 is approximately equal to the distance between pins 69 and 70, and 80 is a tension member. A drive device for the ejecting member, 81 is the support column 48
The drive device 80 is rotatably supported by a pin 82.
さらに、第10図A,Bには水平張出機構Fの
第3実施例が示されており、図中83は張出部
材、84,85はピン86および87により回転
自在に張出部材83に接合したブラケツト、8
8,89は支柱48に接合し、リンク90,91
をピン92および93により回転自在に支持した
ブラケツト、94はピン95および96の間隔に
ほぼピン86,87の間隔に等しい寸法を有する
バー、97は張出用のテンシヨンバー、98は格
納用テンシヨンバー、99は駆動装置、100は
支柱48に取付けられピン101により回転自在
に駆動装置99を支持したブラケツト、102は
ピン103により回転自在に支柱48に取付けら
れたリンク、104は駆動装置99をリンク10
2に回転自在に接合したピン、105は長穴10
7においてピン108によりリンク102と接合
したテンシヨンバー97のヘツド金物、106は
長穴109においてピン110によりリンク10
2と接合したテンシヨンバー98のヘツド金物、
117は張出部材の張出状態を示しており、それ
らによつて第3実施例が構成されている。本発明
の実施例は、前記したようになつており、本発明
の軟弱地盤改良工法は、下端部に回転掘削・撹拌
機構Eを備えた多軸が一体となつた地盤改良処理
機(第6図、第7図参照)を第1図に示すように
昇降ウインチ4により櫓2より吊り、回転掘削・
撹拌機構Eを回転しながら、自重により軟弱地盤
の深層まで貫入し、所期の深度に達したら、回転
掘削・撹拌機構Eの上方位置で硬化剤吐出具11
1から硬化剤を吐出しながら、掘削翼、撹拌翼2
8,29を回転し、硬化剤を軟弱土と混練しつつ
処理機を引上げ単位改良杭(改良土)を造成す
る。この単位改良杭を僅かずつラツプさせて施工
し、単位改良杭を相互に接合することにより、軟
弱地盤に一体となつた第2図に示すような改良土
即ち土中構造物を造成することができる。 Furthermore, a third embodiment of the horizontal extension mechanism F is shown in FIGS. 10A and 10B. Bracket joined to 8
8 and 89 are connected to the support column 48, and links 90 and 91
a bracket rotatably supported by pins 92 and 93; 94 is a bar having a dimension that is approximately equal to the distance between pins 95 and 96 and the distance between pins 86 and 87; 97 is a tension bar for extension; 98 is a tension bar for storage; 99 is a drive device, 100 is a bracket that is attached to the support column 48 and rotatably supports the drive device 99 with a pin 101, 102 is a link that is rotatably attached to the column 48 with a pin 103, and 104 is a link that connects the drive device 99 to a link 10.
2 is rotatably connected to the pin, 105 is the elongated hole 10
At 7, the head hardware of the tension bar 97 is connected to the link 102 by a pin 108, and at 106, the link 10 is connected to the link 10 by a pin 110 at an elongated hole 109.
Head hardware of tension bar 98 joined with 2,
Reference numeral 117 indicates the extended state of the projecting member, which constitutes the third embodiment. The embodiment of the present invention is as described above, and the soft ground improvement method of the present invention is a ground improvement processing machine (No. 6 7) is suspended from the tower 2 by an elevating winch 4 as shown in FIG.
While rotating the stirring mechanism E, the hardening agent discharge tool 11 penetrates deep into the soft ground due to its own weight, and when the desired depth is reached, the hardening agent dispensing tool 11 is placed at a position above the rotary excavation/stirring mechanism E.
While discharging the curing agent from 1, the drilling blade and stirring blade 2
8 and 29 to mix the curing agent with the soft soil and pull up the processing machine to create unit improved piles (improved soil). By constructing these unit improvement piles by wrapping them little by little and joining the unit improvement piles to each other, it is possible to create improved soil, that is, an underground structure integrated into soft ground, as shown in Figure 2. can.
従来工法においては、第3図Aに示すように隣
設改良杭114を計画量(a)ラツプ(20〜30cm)さ
せるべく施工したところ、改良杭施工時における
処理機の軌跡のずれ量が大きくなり、単位改良杭
接合面に第4図Aのような未改良土20を残し、
また、第4図Bに示すように深部にて単位改良杭
相互間に未改良土113を生じ、単位改良杭の相
互あるいは一方が外れ勝手になり、接合部のラツ
プ19,27が外れるようになる。 In the conventional construction method, as shown in Figure 3A, when the adjacent improved pile 114 was constructed to make the planned amount (a) wrap (20 to 30 cm), the amount of deviation in the trajectory of the processing machine during construction of the improved pile was large. , leaving unimproved soil 20 as shown in Figure 4A on the joint surface of the unit improved pile,
In addition, as shown in Figure 4B, unimproved soil 113 occurs between the unit improved piles in the deep part, and one or both of the unit improved piles tend to come off each other, causing the laps 19 and 27 at the joint to come off. Become.
また、従来の施工における単位改良杭の接合に
ついては、第3図Aにおいて既改良杭に対して(a)
量ラツプさせて処理機を垂直に貫入し、処理機を
同一軌跡で引抜くことにより、貫入時切削された
硬化剤混練土を喪失した接合部に再度完全に硬化
剤混練土を充填することにあるが、深層において
貫入時と完全に同一軌跡で引抜くことは難しく、
既設改良杭の切削面未改良土34を残すことにな
る。 In addition, regarding the connection of unit improved piles in conventional construction, (a) for the improved piles in Figure 3A
By penetrating the processing machine vertically and pulling it out along the same trajectory, the joints where the hardening agent mixed soil that was cut during penetration was lost can be completely filled with hardening agent mixed soil again. However, it is difficult to pull out in the deep layer with exactly the same trajectory as when penetrating.
Unimproved soil 34 will remain on the cut surface of the existing improved pile.
ところが、この実施例工法では、第3図Cに示
すように、計画上のラツプ量(a)に対し、少ないラ
ツプ量(b)により貫入し、深層に到つて水平張出機
構Fを作動してラツプを所期の(a)量まで、処理機
の軌道を変更したのち、既改良土を新規に(c)量切
削しながら、硬化剤混練土を充填するため、単位
改良杭即ち既改良土と隣設改良土間の接合部が完
全となり連続性が得られる。 However, in this embodiment method, as shown in Fig. 3C, the burlap penetrates with a smaller lapping amount (b) than the planned lapping amount (a), reaches a deep layer, and activates the horizontal extension mechanism F. After changing the trajectory of the processing machine to reach the desired (a) amount of rap, the improved soil is cut to a new amount (c), and the unit improvement pile, i.e. The joint between the soil and the adjacent improved soil will be complete and continuity will be achieved.
また、従来の処理機では、機体自体の積極的な
移動制御機構を備えてなく、また長い回転軸によ
り回転掘削、撹拌機構Dが駆動部から離されてい
るため、貫入、引抜時における垂直方向からのず
れ動きを回避することができなかつたが、この実
施例の処理機では、貫入、引抜の間、随時に水平
張出機構Fを作動させることにより、その張出部
材を張出して地盤側に当てたその反力により回転
掘削・撹拌部Eを水平方向に動かし、即ち既改良
土側に移動させることができるから、貫入、引抜
の軌跡修正が可能であり、またその作動により垂
直方向への制御もできる。前記のような実施例工
法が可能となり完全な単位改良杭間の接合を果す
ことができる。第7図Bにおいては、回転掘削・
撹拌機構Eを後方向に軌道修正するために、水平
張出機構e,dを張出し、後方側壁より水平抵抗
力を得ている状態を示し、同様に前方に移動した
い時は水平張出機構a,bを、左方に移動したい
時には水平張出機構fを、右方に移動したい時は
制御装置cを張出して抵抗を得ることにより、回
転掘削・撹拌機構Eをどの方向にも水平に移動さ
せることができる。 In addition, conventional processing machines do not have an active movement control mechanism for the machine itself, and the rotary excavation and stirring mechanism D is separated from the drive unit due to the long rotation shaft, so the vertical direction during penetration and extraction is However, in the processing machine of this embodiment, by operating the horizontal extension mechanism F at any time during penetration and extraction, the extension member is extended to the ground side. The reaction force applied to the rotary excavation/agitation part E can be moved horizontally, that is, toward the improved soil side, so it is possible to correct the trajectory of penetration and extraction, and its operation also allows it to move in the vertical direction. can also be controlled. The construction method of the above-mentioned embodiments becomes possible, and complete joints between unit improved piles can be achieved. In Figure 7B, rotary excavation
In order to correct the trajectory of the stirring mechanism E in the backward direction, the horizontal extension mechanisms e and d are extended and the horizontal resistance force is obtained from the rear side wall. , b, to the left, by extending the horizontal extension mechanism f, and when wanting to move it to the right, by extending the control device c to obtain resistance, the rotary excavation/stirring mechanism E can be moved horizontally in any direction. can be done.
第8図A,B,Cにおいて、張出部材52,5
3を張出した状態で、貫入時は水平張出機構53
が、引抜時は張出部材52が、当該改良面積外の
側壁あるいは各良面積内の土流によりあるいは当
該改良面積外の側壁を切削することにより抵抗を
得ることができる。第9図A,Bにおいては、張
出部材を張出した状態において、張出部材66を
当該改良面積外の側壁に当てて水平方向反力を得
るものであり、張出部材がいかなる張出状態にお
いても処理機機体に平行状態にあるようブラケツ
ト73,74がピン69,70と同一ピン間隔寸
法のリンク77で結ばれている。 In FIGS. 8A, B, and C, the overhanging members 52, 5
3 is extended, and when penetrating, the horizontal extension mechanism 53
However, during pulling out, the overhanging member 52 can obtain resistance by cutting the side wall outside the improved area, the earth flow within each good area, or by cutting the side wall outside the improved area. In FIGS. 9A and 9B, a horizontal reaction force is obtained by applying the overhanging member 66 to a side wall outside the improved area when the overhanging member is in an extended state. Also, brackets 73 and 74 are connected to pins 69 and 70 by links 77 having the same pin spacing so that they are parallel to the processing machine body.
第10図A,Bにおいて、張出部材83の構造
は、前記張出部材52,53および66の中間の
機能即ち側壁を切削することと側壁に押付けるこ
とにより水平反力を得るものであり、張出部材を
処理機機体に平行に張出すため、同一装置のリン
ク90,91をピン86,87間隔と同一ピン間
隔寸法長さのバー94により連結されている。そ
のテンシヨンバー97を引くと、張出部材83が
張出し、テンシヨンバー98を引くと張出部材8
3が格納される。また、駆動装置99の液圧シリ
ンダ、空気圧シリンダ、またはスクリユーシリン
ダ等が矢示のように伸びるとテンシヨンバー97
が引かれ、この間テンシヨンバー98はヘツドの
ピン穴の遊びにより動かず、一方、駆動装置99
が矢示のように縮むとテンシヨンバー98が引か
れ、テンシヨンバー97は動かない。即ち駆動装
置の伸縮動作により遠隔の張出部材93を操作す
る2本のロツドが交互に一方のみ引き動作をし、
小径の長大なロツドにより安全な動力伝達を行な
い得る。 In FIGS. 10A and 10B, the structure of the overhang member 83 has an intermediate function between the overhang members 52, 53, and 66, that is, it obtains a horizontal reaction force by cutting the side wall and pressing against the side wall. In order to project the projecting member parallel to the processing machine body, links 90 and 91 of the same device are connected by a bar 94 having the same pin distance and length as the pins 86 and 87. When the tension bar 97 is pulled, the overhang member 83 is extended, and when the tension bar 98 is pulled, the overhang member 8
3 is stored. Also, when the hydraulic cylinder, pneumatic cylinder, screw cylinder, etc. of the drive device 99 extends as shown by the arrow, the tension bar 97
is pulled, and during this time the tension bar 98 does not move due to play in the pin hole of the head, while the drive device 99
When it contracts as shown by the arrow, the tension bar 98 is pulled and the tension bar 97 does not move. That is, the two rods that operate the remote extension member 93 alternately pull only one of them by the expansion and contraction operation of the drive device.
Safe power transmission can be achieved by a long rod with a small diameter.
実施例は前記のようになつており、本実施例工
法においては、前記の水平張出機構Fの併設によ
り、貫入、掘削時の当初にはラツプを少なく即ち
浅目にし、深層に到つた貫入途中においてラツプ
量を大きくする方向に軌道を修正し、貫入終了時
の深いラツプ位置から引抜くことにより既改良土
を削りながら、硬化剤を混練することができるの
で、接合面に未改良土を残すことがなくなり、単
位改良杭間即ち既改良土間の接合性を向上でき
る。また、施工精度が高くなり迅速、円滑に施工
することができる。 The embodiment is as described above, and in the construction method of this embodiment, the above-mentioned horizontal extension mechanism F is also installed, so that the lap is reduced at the beginning of penetration and excavation, that is, it is made shallow, and the penetration that reaches deep layers is prevented. By correcting the trajectory in the direction of increasing the amount of lap midway through and pulling out from the deep lap position at the end of penetration, the hardening agent can be mixed while scraping the improved soil, so unimproved soil can be mixed in at the joint surface. There is no need to leave anything behind, and the connectivity between unit improved piles, that is, between improved soil, can be improved. In addition, the construction accuracy is increased and construction can be carried out quickly and smoothly.
また、実施例の水平張出機構Fを備えた処理機
により、地盤中の深層において処理機の軌道が任
意に変えられることになり、かつ、その水平張出
機構Fは処理機の回転掘削・撹拌機構Dを直接に
強力に水平方向に移動できるため、前記の接合性
を完全な状態にできて、改良土が一連に一体とな
つたものにすることができる。 In addition, the processing machine equipped with the horizontal extension mechanism F of the embodiment allows the trajectory of the processing machine to be changed arbitrarily in deep layers of the ground, and the horizontal extension mechanism F allows the processing machine to perform rotary excavation and Since the stirring mechanism D can be moved directly and strongly in the horizontal direction, the above-mentioned bonding properties can be perfected, and the improved soil can be made into a series of integral pieces.
従来、単位改良杭間の接合性の不安から、単位
改良杭内深度に比し、設計上の改良地盤強度に大
きい安全率がとられ、処理機の単位改良面積内の
撹拌性能が生かされなかつたが、この実施例処理
機の水平張出機構の機能により改良杭間の完全な
接合が得られ、改良地盤全体の信頼性を向上、経
済設計に基づき地盤改良の全体規模を縮小できる
ことにより、地盤改良性能が大巾に高められる。 Conventionally, due to concerns about the bondability between unit improved piles, a large safety factor was taken for the designed improved ground strength compared to the depth inside the unit improved piles, and the agitation performance within the unit improved area of the processing machine was not utilized. However, due to the function of the horizontal extension mechanism of this example treatment machine, a complete connection between the improved piles can be obtained, the reliability of the improved ground as a whole is improved, and the overall scale of the ground improvement can be reduced based on economic design. Ground improvement performance is greatly improved.
従来の処理機では地盤抵抗のアンバランスある
いは機械荷重のアンバランス等に生ずる僅かな水
平力により、改良地盤に大きな影響を及ぼしてい
たが、この実施例では、回転掘削・撹拌機構部分
に水平張出機構を設けているため、水平張出機構
部を直接に強力な作動によつて水平方向に移動で
き、ラツプ量の調整、垂直方向の制御を随時にで
きる。 In conventional processing machines, slight horizontal force caused by unbalanced ground resistance or unbalanced mechanical load had a large effect on the improved soil, but in this example, horizontal tension is applied to the rotary excavation and stirring mechanism. Since the extending mechanism is provided, the horizontal extending mechanism can be directly moved in the horizontal direction by strong operation, and the amount of wrap can be adjusted and the vertical direction can be controlled at any time.
さらに、処理機の掘削・撹拌軌道制御上重要か
つ有効な回転掘削、撹拌機構の軸上方位置に、多
軸ある掘削・撹拌軸間の支柱側面に取付座を設
け、引込時には掘削面内土流又は側壁より抵抗を
受けることが極く少なく、張出時には大きい抵抗
を得るように、格納、展開でき、各水平張出装置
を処理機機体周囲に配置することにより平面上
X、Yどちらの方向あるいは複合した方向に任意
に制御可能である。 Furthermore, above the axis of the rotary excavation and agitation mechanism, which is important and effective for controlling the excavation and agitation trajectory of the processing machine, a mounting seat is provided on the side of the support between the multi-axis excavation and agitation axes, and when the machine is pulled in, earth flow within the excavation surface is achieved. Or, it can be stored and expanded so that it receives very little resistance from the side walls and receives a large amount of resistance when extended, and by placing each horizontal extension device around the processing machine body, it can be moved in either the X or Y direction on the plane. Alternatively, it can be arbitrarily controlled in multiple directions.
前記説明では、海底等における軟弱地盤改良に
ついて述べたが、それに限らず一般の軟弱地盤の
改良にも適用可能である。 In the above description, the improvement of soft ground on the seabed and the like has been described, but the present invention is not limited thereto and can also be applied to improvement of general soft ground.
以上本発明を実施例について説明したが、勿論
本発明はこのような実施例にだけ局限されるもの
ではなく、本発明の精神を逸脱しない範囲内で
種々の設計の改変を施しうるものである。 Although the present invention has been described above with reference to embodiments, it goes without saying that the present invention is not limited to such embodiments, and that various design modifications can be made without departing from the spirit of the present invention. .
第1図は海底軟弱地盤改良と護岸工事の従来例
を示す見取図、第2図は改良杭群の各種形状図、
第3図A,Bは従来の地盤改良の施工説明図、第
3図C,Dは本発明の地盤改良工法の実施例説明
図、第4図A,Bは従来の地盤改良の状態図、第
5図A,Bは従来の軟弱地盤改良処理機の概要
図、第5図Cは本発明の地盤改良処理機の実施例
概要図、第6図A,Bは第5図Cの一部拡大機構
を示す側面図と正面図、第7図A,Bは回転掘
削・撹拌機構と水平張出機構部分の実施例を示す
拡大側面図と同水平張出機構の平面配置図、第8
図A,B,Cは水平張出機構の詳細を示す第1実
施例の側面図、正面図およびA―A断面(上半部
分)とB―B断面(下半部分)図、第9図A,B
は水平張出機構の第2実施例を示す側面図と同A
―A断面図、第10図A,Bは水平張出機構の第
3実施例を示す側面図とその駆動装置正面図であ
る。
A:軟弱地盤、B:改良杭群(改良土)、D,
E:回転掘削・撹拌機構、F:水平張出機構、
3:地盤改良処理機、111:硬化剤吐出具、2
8:掘削翼、29:撹拌翼。
Figure 1 is a sketch showing conventional examples of submarine soft ground improvement and revetment construction, Figure 2 is a diagram of various shapes of improved pile groups,
Figures 3A and B are construction explanatory diagrams of conventional ground improvement, Figures 3C and D are illustrations of an embodiment of the soil improvement method of the present invention, and Figures 4A and B are state diagrams of conventional soil improvement. Figures 5A and B are a schematic diagram of a conventional soft ground improvement treatment machine, Figure 5C is a schematic diagram of an embodiment of the soil improvement treatment machine of the present invention, and Figures 6A and B are a part of Figure 5C. A side view and a front view showing the enlarging mechanism, FIGS.
Figures A, B, and C are a side view, front view, AA cross section (upper half) and BB cross section (lower half) of the first embodiment showing details of the horizontal extension mechanism, and FIG. A, B
A is a side view showing the second embodiment of the horizontal extension mechanism.
-A sectional view, and FIGS. 10A and 10B are a side view and a front view of the drive device of the third embodiment of the horizontal extension mechanism. A: Soft ground, B: Improved pile group (improved soil), D,
E: Rotary excavation/stirring mechanism, F: Horizontal extension mechanism,
3: Ground improvement processing machine, 111: Hardening agent discharge tool, 2
8: Drilling blade, 29: Stirring blade.
Claims (1)
して軟弱地盤中に貫入、引抜きし、硬化剤と軟弱
土とを混練して地盤を硬化改良する軟弱地盤改良
工法において、貫入の当初に既改良土とのラツプ
量を少なめにし同程度のラツプ量を保ちながら貫
入し、回転掘削・撹拌機構の近くに設けた水平張
出機構による制御により貫入の途中からラツプ量
を大きくして貫入、掘削し、引抜時は前記ラツプ
量を大きくした位置から垂直に引抜いて既改良土
の一部を削りながら地盤を硬化改良することを特
徴とする軟弱地盤改良工法。 2 回転掘削・撹拌機構を駆動し既改良土に一部
ラツプさせて軟弱地盤中に貫入、引抜きするとと
もに、回転掘削・撹拌機構の近くに配設した硬化
剤吐出具から硬化剤を吐出し軟弱土と混練して地
盤を硬化改良する地盤処理機において、前記回転
掘削・撹拌機構の近くに、同回転掘削・撹拌機構
を貫入、引抜時に既改良土側へ移動せしめかつ垂
直方向に制御する水平張出機構を配設したことを
特徴とする軟弱地盤改良処理機。[Scope of Claims] 1. In a soft ground improvement method in which a rotary excavation/agitation mechanism of a ground improvement processing machine is driven to penetrate into and pull out soft ground, and the hardening agent and soft soil are kneaded to harden and improve the ground. At the beginning of penetration, the amount of lapping with the improved soil is reduced to maintain the same amount of lapping, and the amount of lapping is reduced from the middle of penetration by controlling the horizontal extension mechanism installed near the rotary excavation and stirring mechanism. A soft ground improvement method characterized by penetrating and excavating a large amount of lap, and when pulling it out, pulling it out vertically from the position where the lap amount is large, and scraping away a part of the improved soil to harden and improve the ground. 2 The rotary excavation/stirring mechanism is driven to partially wrap the improved soil and penetrate into and pull out the soft ground, and the hardening agent is discharged from the hardening agent dispensing tool placed near the rotary excavation/stirring mechanism to loosen the soft ground. In a ground treatment machine that hardens and improves the ground by kneading it with soil, a horizontal machine is installed near the rotary excavation/stirring mechanism to move the rotary excavation/stirring mechanism toward the improved soil side when penetrating or pulling it out, and to control it in the vertical direction. A soft ground improvement treatment machine characterized by being equipped with an overhang mechanism.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP10043881A JPS584018A (en) | 1981-06-30 | 1981-06-30 | Method and device for improving soft ground |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP10043881A JPS584018A (en) | 1981-06-30 | 1981-06-30 | Method and device for improving soft ground |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS584018A JPS584018A (en) | 1983-01-11 |
| JPS6252086B2 true JPS6252086B2 (en) | 1987-11-04 |
Family
ID=14273942
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP10043881A Granted JPS584018A (en) | 1981-06-30 | 1981-06-30 | Method and device for improving soft ground |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS584018A (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS60199112A (en) * | 1984-03-21 | 1985-10-08 | Toa Harbor Works Co Ltd | Ground improvement work by deep layer mixing treatment of cement |
| CN102635368B (en) * | 2011-05-09 | 2014-12-03 | 上海申通地铁集团有限公司 | Dual-liquid micro-disturbance grouting strengthening method for soft-soil subway tunnel |
Family Cites Families (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5178009A (en) * | 1974-12-27 | 1976-07-07 | Kitagawa Iron Works Co | HEDORODAMARINOTOKUTEIBUBUNNIRENZOKUKOKASONYORU ANTEIJIBANOTSUKURUHOHO |
| JPS5178010A (en) * | 1974-12-27 | 1976-07-07 | Kitagawa Iron Works Co | HEDORODAMARINOTOKUTEIBUBUNNIRENZOKUKOKASONYORU ANTEIJIBANOTSUKURUHOHO |
| JPS5384312A (en) * | 1976-12-30 | 1978-07-25 | Kitagawa Iron Works Co | Machine for treating weak ground |
-
1981
- 1981-06-30 JP JP10043881A patent/JPS584018A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS584018A (en) | 1983-01-11 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US4904119A (en) | Process for placing a piling in the ground, a drilling machine and an arrangement for implementing this process | |
| JP6076383B2 (en) | Ground improvement pile construction method and ground improvement pile construction equipment | |
| JP2000319881A (en) | Method for continuous lap drilling by leader auger machine and device used therefor | |
| KR20120069970A (en) | Soft ground improvement method excavating rod of ground excavating device | |
| JPS6252086B2 (en) | ||
| KR102270555B1 (en) | Method for reinforcing ground using grouting bead and helical pile | |
| JP4074198B2 (en) | How to remove existing piles | |
| CN108951623A (en) | A kind of three axis high-pressure rotary-spray two-way stirring pile construction methods | |
| WO2003085208A1 (en) | Method and system for placing at least one foundation element in the ground | |
| JP4796197B2 (en) | Ground improvement body construction apparatus and ground improvement body construction method | |
| CN214169045U (en) | A three-axis cement-soil mixing drilling device | |
| JPH02125016A (en) | Hollow drilling grouting method | |
| KR102826775B1 (en) | a method for grouting with Low Pressure SGR type | |
| CN208363084U (en) | A kind of NEW TYPE OF COMPOSITE pile foundation with higher level bearing capacity | |
| JPS60203726A (en) | Ground improving device | |
| JPS6131244B2 (en) | ||
| CN223510928U (en) | A shield tunneling machine anti-rotation tooling | |
| JP2004162504A (en) | Drilling machine | |
| JP3005741B2 (en) | Ground improvement method | |
| CN119321331B (en) | A shield parameter adjustment method, support device and starting end drilling method | |
| JP4929378B2 (en) | Composite pile and composite pile construction method | |
| JP3678935B2 (en) | Consolidation pile construction method | |
| JP6553101B2 (en) | Ground improvement stirring device | |
| JP2002371550A (en) | Construction method of soil cement composite ready-made pile | |
| CN119308685A (en) | A shield starting end reinforcement structure and method and drilling method |