JPS6320973B2 - - Google Patents

Info

Publication number
JPS6320973B2
JPS6320973B2 JP55075461A JP7546180A JPS6320973B2 JP S6320973 B2 JPS6320973 B2 JP S6320973B2 JP 55075461 A JP55075461 A JP 55075461A JP 7546180 A JP7546180 A JP 7546180A JP S6320973 B2 JPS6320973 B2 JP S6320973B2
Authority
JP
Japan
Prior art keywords
column
concrete
beams
metal plate
main reinforcements
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP55075461A
Other languages
Japanese (ja)
Other versions
JPS573943A (en
Inventor
Naoshi Myazaki
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP7546180A priority Critical patent/JPS573943A/en
Publication of JPS573943A publication Critical patent/JPS573943A/en
Publication of JPS6320973B2 publication Critical patent/JPS6320973B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)
  • Rod-Shaped Construction Members (AREA)

Description

【発明の詳細な説明】 本発明はプレキヤスト鉄筋コンクリート造のラ
ーメン構造における柱梁の接合工法に係るもの
で、柱梁接合部において相対するプレキヤストコ
ンクリート梁の各主筋の露出端部を互いに平行す
るように柱部内に折曲げ、同両主筋の各露出端部
に亘つて有孔金属板を嵌着して両主筋を集束し、
次いで柱コンクリートを打設することを特徴とす
るもので、その目的とする処は簡単な構成で、構
造上信頼性の高いプレキヤスト鉄筋コンクリート
構造における柱梁の接合部を施工しうる改良され
た柱梁の接合工法を供する点にある。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for joining columns and beams in a rigid frame structure made of precast reinforced concrete. bent into the column part, and fit a perforated metal plate over each exposed end of both main reinforcements to focus both main reinforcements,
The feature is that column concrete is then poured, and its purpose is to create an improved column-beam joint in a precast reinforced concrete structure with a simple structure and high structural reliability. The point is that it provides a joining method.

本発明においては前記したように、プレキヤス
ト鉄筋コンクリートラーメン構造において連続す
るプレキヤストコンクリート梁の主筋を柱内にア
ンカーして、柱梁を接合するのに際して、柱梁接
合部において相対するプレキヤストコンクリート
梁の各主筋の露出端部を柱部内に互いに平行する
ように折曲げ、前記両主筋の各露出端部に亘つて
有孔金属板を嵌着して両者を集束するようにした
ので、柱梁接合空間内における各梁の主筋の交錯
が避けられ、部材の製作、建方が著しく簡略化さ
れるものである。
In the present invention, as described above, when connecting the columns and beams by anchoring the main reinforcements of continuous precast concrete beams in the columns in a precast reinforced concrete rigid frame structure, the precast concrete beams facing each other at the column-beam joint are The exposed ends of each main reinforcement were bent into the column so that they were parallel to each other, and a perforated metal plate was fitted across each exposed end of both main reinforcements to bring them together, resulting in a column-beam connection. This avoids crossing of the main reinforcements of each beam within the space, and significantly simplifies the manufacture and erection of members.

本発明においては前記したように柱梁接合部に
おいて相対するプレキヤストコンクリート梁の各
主筋の露出端部を柱部内に互いに平行するように
折曲げ、両者間に亘つて有孔金属板を嵌着して両
主筋の露出端部を集束したのち柱コンクリートを
打設し、同コンクリート内に前記各梁主筋の露出
端部をアンカーして柱梁の接合部を構成するよう
にしたので、前記有孔金属板が柱梁接合部におけ
る前記梁主筋の折曲げ碇着部に対する碇着コンク
リートを拘束して附着耐力を増大し、同梁主筋の
碇着深さの不足を補い、更に柱梁接合部において
相対するプレキヤストコンクリート梁の各主筋に
おける、柱部内に折曲げられた互いに平行な露出
端部に亘つて有孔金属板が嵌着され、両主筋の露
出端部間が集束されているので、同各主筋の引張
力を折曲部で直接的に連結させる効果により、柱
梁の剛接合部を構成するものである。
In the present invention, as described above, the exposed ends of the main reinforcements of the precast concrete beams facing each other at the column-beam joint are bent into the column so as to be parallel to each other, and a perforated metal plate is fitted between the two. After converging the exposed ends of both main reinforcements, column concrete was poured, and the exposed ends of each of the beam main reinforcements were anchored in the concrete to form a joint between the columns and beams. The hole metal plate restrains the anchoring concrete to the bent anchorage part of the beam main reinforcement at the column-beam joint, increases the attachment strength, compensates for the lack of anchorage depth of the beam main reinforcement, and further improves the anchoring depth of the beam main reinforcement. A perforated metal plate is fitted across the parallel exposed ends of each of the main reinforcements of the opposing precast concrete beams in the column, and the exposed ends of both main reinforcements are focused. By directly connecting the tensile forces of the main reinforcements at the bent portions, a rigid joint between the columns and beams is constructed.

このように前記有孔金属板を使用して梁主筋を
柱コンクリート内に碇着して、耐力的に十分な碇
着部を構成しうるものであるが、前記有孔金属板
の寸法、形状等を調整することによつて碇着部の
変形量を調節し、部材の剛性を調節することによ
つて部材の応力集中を回避したり、建物全体の構
造特性を改善しうるものである。
In this way, the beam main reinforcement can be anchored in the column concrete using the perforated metal plate, and an anchoring part with sufficient strength can be constructed. However, the dimensions and shape of the perforated metal plate are By adjusting the amount of deformation of the anchorage, and by adjusting the rigidity of the members, stress concentration in the members can be avoided and the structural characteristics of the entire building can be improved.

以下本発明を図示の実施例について説明する。 The present invention will be described below with reference to the illustrated embodiments.

Aはプレキヤストコンクリート梁、Bは柱打設
用の角筒状プレキヤストコンクリート型枠で、同
型枠Bの上端4辺に夫々前記梁Aの接合端部が載
架されている。
A is a precast concrete beam, B is a rectangular cylindrical precast concrete formwork for driving columns, and the joint ends of the beam A are mounted on the four upper sides of the formwork B, respectively.

而して相対する前記各梁Bにおける梁主筋1の
露出端部が前記型枠Bの上方において互いに近接
して平行するように垂直に曲成されている。
The exposed ends of the main beam reinforcements 1 in the opposing beams B are vertically curved so as to be close to and parallel to each other above the formwork B.

2は中央に透孔2aの穿設された有孔金属板
で、前記相対する梁Aにおける主筋1の露出端部
垂直折曲部1a間に亘つて嵌着して同各主筋1を
集束し、しかるのち前記型枠B内及び同型枠B上
における前記各梁Aに囲繞された部分に柱コンク
リートを打設し、同コンクリートに前記主筋1の
露出端部を碇着し、柱梁の剛接合部を構成するも
のである。
Reference numeral 2 denotes a perforated metal plate with a through hole 2a in the center, which is fitted between the vertical bent portions 1a of the exposed ends of the main reinforcements 1 in the opposing beams A to focus the main reinforcements 1. , Then, column concrete is poured in the portions of the formwork B and on the formwork B surrounded by the beams A, and the exposed ends of the main reinforcements 1 are anchored to the concrete, thereby increasing the rigidity of the column and beam. This constitutes a joint.

この際、前記有孔金属板2が前記主筋1に対す
る碇着コンクリート部を拘束して附着耐力を増大
し、前記主筋1の碇着深さの不足分を補足し、更
に前記主筋1に作用する引張力Tを直接的に連結
させ、前記各梁Aに囲繞されたコンクリート部分
の割列を防止して、剛接合部を構成するものであ
る。
At this time, the perforated metal plate 2 restrains the anchoring concrete portion to the main reinforcement 1 to increase the attachment strength, compensate for the lack of anchorage depth of the main reinforcement 1, and further acts on the main reinforcement 1. The tensile force T is directly connected to prevent the concrete portions surrounded by the beams A from splitting, thereby forming a rigid joint.

また前記有孔金属板2の寸法、形状等を調整し
てその変形度を調節し、部材剛性を制御して部材
の応力集中を避けたり、建物全体の構造特性を改
善しうるものである。
Further, by adjusting the size, shape, etc. of the perforated metal plate 2, the degree of deformation thereof can be adjusted, and the rigidity of the member can be controlled to avoid stress concentration in the member and improve the structural characteristics of the entire building.

なお図中3はスラブ筋、4は柱筋である。 Note that 3 in the figure is a slab reinforcement, and 4 is a column reinforcement.

以上本発明を実施例について説明したが、本発
明は勿論このような実施例にだけ局限されるもの
ではなく、本発明の精神を逸脱しない範囲内で
種々の設計の改変を施しうるものである。
Although the present invention has been described above with reference to embodiments, the present invention is, of course, not limited to such embodiments, and can be modified in various ways without departing from the spirit of the present invention. .

【図面の簡単な説明】[Brief explanation of drawings]

第1図及び第2図は夫々本発明に係るプレキヤ
スト鉄筋コンクリート構造における柱梁の接合工
法の一実施例の実施状況を示す横断平面図並に縦
断側面図、第3図は有孔金属板の平面図である。 A……プレキヤストコンクリート梁、B……プ
レキヤストコンクリート柱型枠、1……梁主筋、
1a……梁主筋の露出端部垂直折曲部、2……有
孔金属板、2a……透孔。
Figures 1 and 2 are a cross-sectional plan view and a longitudinal side view showing an embodiment of the method for joining columns and beams in a precast reinforced concrete structure according to the present invention, respectively, and Figure 3 is a plane view of a perforated metal plate. It is a diagram. A... Precast concrete beam, B... Precast concrete column formwork, 1... Beam main reinforcement,
1a... Vertical bent portion of the exposed end of the beam main reinforcement, 2... Perforated metal plate, 2a... Through hole.

Claims (1)

【特許請求の範囲】[Claims] 1 柱梁接合部において相対するプレキヤストコ
ンクリート梁の各主筋の露出端部を互いに平行す
るように柱梁接合部内に折曲げ、両主筋の各露出
端部に亘つて有孔金属板を嵌着して両主筋を集束
し、次いで前記柱コンクリートを打設することを
特徴とするプレキヤスト鉄筋コンクリート構造に
おける柱梁の接合工法。
1. Bend the exposed ends of the main reinforcements of the opposing precast concrete beams into the column-beam joint so that they are parallel to each other at the column-beam joint, and fit a perforated metal plate across each exposed end of both main reinforcements. 1. A method for joining columns and beams in a precast reinforced concrete structure, characterized in that both main reinforcements are bundled together, and then the column concrete is poured.
JP7546180A 1980-06-06 1980-06-06 Joint work of pillar beam in precast reinforced concrete structure Granted JPS573943A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7546180A JPS573943A (en) 1980-06-06 1980-06-06 Joint work of pillar beam in precast reinforced concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7546180A JPS573943A (en) 1980-06-06 1980-06-06 Joint work of pillar beam in precast reinforced concrete structure

Publications (2)

Publication Number Publication Date
JPS573943A JPS573943A (en) 1982-01-09
JPS6320973B2 true JPS6320973B2 (en) 1988-05-02

Family

ID=13576955

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7546180A Granted JPS573943A (en) 1980-06-06 1980-06-06 Joint work of pillar beam in precast reinforced concrete structure

Country Status (1)

Country Link
JP (1) JPS573943A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0319557U (en) * 1989-07-04 1991-02-26

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0623904B2 (en) * 1983-11-11 1994-03-30 松下電器産業株式会社 Fixing device
JPH01303470A (en) * 1988-05-31 1989-12-07 Sharp Corp Copying machine
KR100308757B1 (en) * 1998-09-12 2001-11-30 하진규 Development Devices and Methods of Precast Reinforced Concrete Beam Reinforcements in Beam-Column Joint

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5830459B2 (en) * 1978-11-02 1983-06-29 フジタ工業株式会社 Construction method of precast reinforced concrete structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0319557U (en) * 1989-07-04 1991-02-26

Also Published As

Publication number Publication date
JPS573943A (en) 1982-01-09

Similar Documents

Publication Publication Date Title
JPS6320973B2 (en)
JPH0634994Y2 (en) Pre-stress introduction Pre-cast steel reinforced concrete girder
JPH05287801A (en) Beam Reinforcement Structure in Ramen Structure Made of Precast Reinforced Concrete
JPH0953277A (en) Nuclear power plant construction method
JPH0621470B2 (en) Lap joint method of main bars in column and beam joints
US1141160A (en) Reinforced-concrete building construction.
JP2613552B2 (en) Precast concrete frame and its construction method
JPS61196035A (en) Construction of concrete building
JPS6018785B2 (en) Method for manufacturing reinforced concrete columns or prestressed concrete columns with beam mounting brackets
JPH0732642Y2 (en) Beam-column joint structure
JPH07279428A (en) Constructing method of continuous frame by prestressed reinforced concrete construction
JPH056335Y2 (en)
JPS62148769A (en) Construction of steel pipe concrete pillar
JPH01146035A (en) Connection section structure of filling steel pipe concrete post
JPS6335773B2 (en)
JPH0450721Y2 (en)
JPH07109121B2 (en) Manufacturing method of steel pipe concrete
JPH0448141B2 (en)
JPH0328547B2 (en)
JPH0823148B2 (en) Drop-in steel column base
JPH0681470A (en) Construction method for flat slab
JPH0637128Y2 (en) Joint structure of columns and beams
JPS628246Y2 (en)
JPH05306543A (en) Device for joining precast reinforced concrete column and beam
JPH0448143B2 (en)