JPS6347861B2 - - Google Patents
Info
- Publication number
- JPS6347861B2 JPS6347861B2 JP58018138A JP1813883A JPS6347861B2 JP S6347861 B2 JPS6347861 B2 JP S6347861B2 JP 58018138 A JP58018138 A JP 58018138A JP 1813883 A JP1813883 A JP 1813883A JP S6347861 B2 JPS6347861 B2 JP S6347861B2
- Authority
- JP
- Japan
- Prior art keywords
- precast
- cast
- concrete
- board
- place concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
- E04B5/16—Load-carrying floor structures wholly or partly cast or similarly formed in situ
- E04B5/32—Floor structures wholly cast in situ with or without form units or reinforcements
- E04B5/36—Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor
- E04B5/38—Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor with slab-shaped form units acting simultaneously as reinforcement; Form slabs with reinforcements extending laterally outside the element
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Panels For Use In Building Construction (AREA)
- Floor Finish (AREA)
- Steps, Ramps, And Handrails (AREA)
Description
本発明は、梁間に掛け渡したプレキヤスト板と
その上面に打設する現場打コンクリートとを一体
化させて合成床とするプレキヤスト板を用いた床
工法に関する。
従来、PCコンクリート製のプレキヤスト板を
用いた床工法においては、梁間に掛け渡したプレ
キヤスト板の上面に現場打コンクリートを打設し
ている。ところで、コンクリート構造物の応力度
は一般に厚さの二乗に比例することが知られてい
る。従つてプレキヤスト板の上面に現場打コンク
リートを打設した場合、両者が完全一体となつて
いるならば、両者を重ねた厚さを応力度算定のた
めの一構造物厚さとみることができるが、両者の
結合が不充分な場合には、プレキヤスト板の応力
度のみで全体の応力度の算定をしなければならな
い。
そこで、平滑なプレキヤスト板の上面に単に現
場打コンクリートを打設した場合には、両者の結
合が充分でないから、結果として必要な応力度を
得るためには、プレキヤスト板の厚さが大きくな
らざるを得ない。
このような点に着目し、プレキヤスト板と現場
打コンクリートを一体化し、応力度の算定に際し
て全体の厚さを一体の構造物として考慮し得る方
法としては、断面が略三角形の篭筋の一辺をプレ
キヤスト板内に埋め込み、残りの二辺をプレキヤ
スト板の表面に露出させておき、これを現場打コ
ンクリート内に埋め込んで両者を一体化させる合
成床工法が開発されている。
しかし、この従来工法は、プレキヤスト板の表
面に篭筋の一部を突出させるものであるため、プ
レキヤスト板の連続成形ができず、製造コストが
高く、しかも保管や運搬及び設置の際に突出して
いる篭筋が変形しやすいため取り扱いを慎重に行
わなければならず作業性にも問題があつた。
本発明は上述した従来の問題にかんがみ、成形
が容易で廉価なプレキヤスト板を使用し、しか
も、床の構築時には何ら特別の部材ないし工程を
加えることなく容易に施行することができ、プレ
キヤスト板と現場打コンクリートの一体化が確実
に得られ、全体を一体成形した床と同様の厚さで
必要な応力度が得られる床工法の提供を目的と
し、その要旨とするところは、鉄骨もしくはコン
クリート製の梁間にコンクリート製プレキヤスト
板を掛け渡し、その上面に現場打コンクリートを
一体に打設する床工法において、上記プレキヤス
ト板は表面に多数の凹陥部を互いに近接させ千鳥
状に分散配列させたものを用い、このプレキヤス
ト板を上記凹陥部が少なくとも掛け渡し方向に対
しては斜行して配列するよう設置した後、前記プ
レキヤスト板の表面及び凹陥部内に前記現場打コ
ンクリートを打ち込んで、前記凹陥部内の打込み
コンクリートをシヤコツターとして作用させて該
プレキヤスト板と現場打コンクリートとを一体化
することにより、上記プレキヤスト板における上
記梁の長手に沿う方向へのせん断応力の分配の平
均化を図つたことを特徴とする床工法にある。
なお、上記凹陥部を近接させた千鳥状の分散配
置とは、後述の実施例に示されているように、プ
レキヤスト板の掛け渡し方向に向けて一列に並ん
だ各凹陥部とこれに隣接して並んだ列の各凹陥部
とが互いちがいに、掛け渡し方向からみて部分的
に入り組んだ位置関係にあり、したがつて、掛け
渡し方向に対して斜行する凹陥部列が認められる
ような配置関係を示すものである。
次に本発明の一実施例を図面に即して説明す
る。
まず、第1図〜第4図により本発明に使用する
コンクリート製のプレキヤスト板について説明す
る。
第1図は本発明に使用するプレキヤスト板の一
例の部分斜視図であり、このプレキヤスト板Aは
その肉厚内に長手方向に向けて複数の中空孔1,
1……が貫通開口されているとともに、中空孔の
下部位置、要すれば上下位置に多数本のPC鋼線
2,2……が緊張されて埋設されている。
一方上面には多数の浅床の凹陥部3,3……が
形成されている。この凹陥部3,3は、一例とし
て第2図に示すように垂直の内壁上部から底部の
径を小さくしたテーパー状に形成し、その大きさ
は開口部直径aを25mm、底部直径bを17mm、深さ
hを5mm、テーパー面の角度αを45゜とし、梁に
直交する掛け渡し方向に対して斜行する千鳥状の
配列としている。
この凹陥部3の平面形状は、上述した円形のほ
か、三角、四角、その他の多角形状など適宜の形
状でよく、その大きさも適宜変更してよい。
また、本発明に使用するプレキヤスト板は、第
3図に示すプレキヤスト板A′のように中空孔を
有しない中実の形状とし、長手方向にPC鋼線2
を緊張埋設して表面に多数の凹陥部3を形成した
ものでよい。
この各プレキヤスト板A,A′の製造法の一例
をあげると、床面等の平面型上にPC鋼線2を緊
張しておき、これを埋め込むようにコンクリート
を打設しつつ型枠を移動させる即時脱型方式によ
り成形し、表面を平らに仕上げた後、その上面に
第4図に示すような円形ドラム4の外周に多数の
突起5,5……を突設した凹陥部成形型を転接さ
せて凹陥部3の型付けを順次行う。
このようにして表面に型付けを行つた後、静置
して硬化させ、一定以上の強度に達した後、必要
な長さに切断して単位長さのプレキヤスト板とす
る。
次に、上記プレキヤスト板Aを使用して合成床
を構築する工程について説明する。
まず、プレキヤスト板Aを一定間隔をおいて横
架した梁間に掛け渡す。梁がコンクリート梁であ
る場合には、第5図に示すように梁10の上面に
アンカー鉄筋11を突出させ、その両側にプレキ
ヤスト板A,Aの端部を載置し、同図上で左右に
延びる掛け渡し方向に掛け渡す。また梁が鉄骨で
ある場合には第6図に示すように梁12の中央に
スタツド13を突設しておき、その両側にプレキ
ヤスト板A,Aの端部を載置する。
このようにしてプレキヤスト板A,A……を多
数掛け渡した後、その上面に現場打コンクリート
用の鉄筋15を組み、現場打コンクリートBをプ
レキヤスト板A,A間及びその上面全面に打設
し、一体化した合成床とする。
このようにして構築された合成床は現場打コン
クリートBがプレキヤスト板A表面の凹陥部3,
3……に入り込んで硬化することによつて、凹陥
部3,3……内のコンクリートがシヤコツターと
なり、プレキヤスト板Aと現場打コンクリートB
とが一体化され、プレキヤスト板の凹陥部が掛け
渡し方向に斜行しているので、せん断応力分布の
掛け渡し方向及び、これと直角な方向における平
均化が図られ、垂直方向の荷重による曲げに対
し、一体となつて作用することとなる。またプレ
キヤスト板A相互間は前述したシヤコツターの作
用により現場打コンクリートを介して一体化され
る。
試験例
第7図に示す厚さh1が100mm、幅Xが500mmの
PCプレキヤスト板Aの表面に第2図及びその説
明に示す大きさ及び形状の凹陥部3を幅方向ピツ
チ35mm、長手方向ピツチ44mmの間隔にして千鳥状
に一面を形成し、その上面に厚さh2が80mmの場所
打コンクリートBを打設して全体の厚さhを180
mmとした合成床試験片を製造し、これと前記PC
プレキヤスト板A単体とについて短期載荷実験を
行つたところ、その結果は第1表に示すとおりで
あつた。
The present invention relates to a floor construction method using a precast board that integrates a precast board spanning between beams and cast-in-place concrete poured on the top surface to form a composite floor. Conventionally, in the floor construction method using precast boards made of PC concrete, cast-in-place concrete is placed on the top surface of the precast boards that span between the beams. By the way, it is known that the stress level of concrete structures is generally proportional to the square of the thickness. Therefore, when cast-in-place concrete is placed on the top of a precast board, if the two are completely integrated, the thickness of the two overlapping can be regarded as the thickness of the structure for calculating the stress level. If the bond between the two is insufficient, the overall stress must be calculated based only on the stress of the precast plate. Therefore, if cast-in-place concrete is simply placed on the top surface of a smooth precast board, the bond between the two will not be sufficient, and as a result, in order to obtain the necessary stress level, the thickness of the precast board will have to be increased. I don't get it. Focusing on these points, a method that allows the precast board and cast-in-place concrete to be integrated and the overall thickness of the structure to be taken into account when calculating the stress level is to A synthetic floor construction method has been developed that involves embedding it within a precast board, leaving the remaining two sides exposed on the surface of the precast board, and embedding it in cast-in-place concrete to integrate the two. However, in this conventional method, a part of the gauntlet ribs protrudes from the surface of the precast board, so the precast board cannot be continuously formed, the manufacturing cost is high, and the gravure bars protrude during storage, transportation, and installation. Because the gauntlet ribs are easily deformed, they had to be handled carefully, which caused problems in workability. In view of the above-mentioned conventional problems, the present invention uses a precast board that is easy to form and is inexpensive, and can be easily implemented without adding any special members or processes when constructing a floor. The purpose is to provide a floor construction method that reliably integrates cast-in-place concrete and provides the necessary stress level with the same thickness as a floor that is entirely formed in one piece. In the floor construction method, a concrete precast board is stretched between the beams of the concrete, and cast-in-place concrete is poured on the top surface of the precast board. After installing this pre-cast board so that the recesses are arranged obliquely at least with respect to the direction of hanging, the cast-in-place concrete is poured into the surface of the pre-cast board and into the recesses, and the concrete in the recesses is poured into the recesses. By integrating the precast board and the cast-in-place concrete by causing the poured concrete to act as a shackle starter, the shear stress distribution in the direction along the length of the beam in the precast board is averaged. There is a floor construction method. Note that the above-mentioned staggered distributed arrangement in which the recesses are placed close to each other means that each recess is arranged in a line in the direction in which the precast board is stretched and the recesses are adjacent to each other, as shown in the examples described later. The recesses in the rows lined up are different from each other and have a partially intricate positional relationship when viewed from the spanning direction, so that the rows of recesses are oblique to the spanning direction. It shows the relationship. Next, one embodiment of the present invention will be described with reference to the drawings. First, the concrete precast board used in the present invention will be explained with reference to FIGS. 1 to 4. FIG. 1 is a partial perspective view of an example of a precast board used in the present invention, and this precast board A has a plurality of hollow holes 1 in its thickness in the longitudinal direction.
1... is opened through the hollow hole, and a large number of PC steel wires 2, 2... are buried under tension in the lower part of the hollow hole, and if necessary in the upper and lower positions. On the other hand, a large number of shallow recesses 3, 3, . . . are formed on the upper surface. As shown in FIG. 2, the recesses 3, 3 are formed in a tapered shape with a diameter reduced from the top of the vertical inner wall to the bottom, with an opening diameter a of 25 mm and a bottom diameter b of 17 mm. , the depth h is 5 mm, the angle α of the tapered surface is 45 degrees, and the beams are arranged in a staggered manner obliquely with respect to the spanning direction perpendicular to the beam. The planar shape of the concave portion 3 may be not only the circular shape described above but also any other suitable shape such as triangular, square, or other polygonal shape, and its size may also be changed as appropriate. Furthermore, the precast plate used in the present invention has a solid shape without hollow holes, as shown in the precast plate A' shown in FIG.
A large number of recesses 3 may be formed on the surface by embedding under tension. To give an example of the manufacturing method for each of these precast plates A and A', the PC steel wire 2 is placed under tension on a flat mold such as a floor surface, and the formwork is moved while pouring concrete to embed it. After molding using the immediate demolding method and finishing the surface flat, a concave mold with a large number of protrusions 5, 5, etc. protruding from the outer periphery of a circular drum 4 as shown in FIG. The molding of the concave portion 3 is sequentially performed by rolling contact. After the surface is molded in this manner, it is allowed to stand and harden, and after reaching a certain level of strength, it is cut into required lengths to obtain precast plates of unit length. Next, the process of constructing a synthetic floor using the precast board A will be described. First, the precast board A is stretched between horizontal beams at regular intervals. If the beam is a concrete beam, as shown in Figure 5, the anchor reinforcing bars 11 are protruded from the upper surface of the beam 10, and the ends of the precast plates A and A are placed on both sides of the anchor reinforcement bars 11, as shown in Figure 5. It spans in the span direction that extends to . If the beam is a steel frame, a stud 13 is provided protruding from the center of the beam 12 as shown in FIG. 6, and the ends of the precast plates A, A are placed on both sides of the stud 13. After a large number of precast plates A, A, etc. are spanned in this way, reinforcing bars 15 for cast-in-place concrete are installed on the top surface, and cast-in-place concrete B is poured between the precast plates A and A and over the entire upper surface thereof. , an integrated composite floor. In the composite floor constructed in this way, the cast-in-place concrete B is placed in the concave portion 3 on the surface of the precast board A,
3... By entering and hardening, the concrete inside the recesses 3, 3... becomes a stagnation, and the precast board A and cast-in-place concrete B
Since the concave portion of the precast plate is oriented obliquely in the direction of passing, the shear stress distribution is averaged in the direction of passing and in the direction perpendicular to this, and bending due to vertical loads is achieved. They will act as one. Further, the precast plates A are integrated with each other via cast-in-place concrete by the action of the above-mentioned concrete starter. Test example The thickness h1 shown in Fig. 7 is 100 mm and the width X is 500 mm.
On the surface of the PC precast board A, recesses 3 having the size and shape shown in FIG. Pour cast-in-place concrete B with h 2 of 80 mm to make the overall thickness h 180 mm.
A composite floor test piece with a diameter of mm was manufactured, and this and the PC
A short-term loading experiment was conducted on precast plate A alone, and the results were as shown in Table 1.
【表】
また、第1表中の合成床試験片No.1についてた
わみ試験を行つたところ、第8図のグラフに示す
とおりであり、打継ぎ面の滑り量は第9図のグラ
フ、断面の平面保持は第10図のグラフに示すと
おりであつた。
検 討
(1) 強度と破壊性状について
ひび割れ荷重および最大耐力とも実験置は一
体としての計算置を上廻つており、強度の面か
ら床板の一体性が確認された。
また破壊性状も通常の曲げまたはせん断破壊
であり、打継ぎ面の破壊現象は終局まで認めら
れず、破壊性状からも一体性が確認された。
(2) 荷重変形曲線について
いずれの実験値も弾性剛性は計算値を上廻つ
ている。また、曲線の履歴特性をみても打継ぎ
面の一体性が失われたような現象は認められな
い。
これらのことから床板の一体性が確認され
た。
(3) ひび割れ性状について
ひび割れは打継ぎ面をほぼ一直線状に通過し
ており、打継ぎ面に沿つた進展は認められな
い。従つてひび割れ性状の面からも床板の一体
性が確認された。
(4) 打継ぎ面のすべりについて
打継ぎ面のすべりは0ないし0.01mm以下であ
り、一体性が保持されていることが確認され
た。
(5) 平面保持性について
厚み方向の歪度のプロツトの結果をみると、
断面がほぼ平面を保持していることが認められ
る。従つてコンクリート製プレキヤスト板の上
面に現場打コンクリートを一体に打設して成形
した合成床板の一体性が確認された。
結 論
以上のとおり、強度、剛性、破壊性状、ひび割
れ性状、打継ぎ面のすべり、断面の平面保持性の
いずれの面からも合成床板の構造的一体性が確認
された。
本発明は上述の如く構成され、プレキヤスト板
の表面に多数の凹陥部を千鳥状に設けておき、そ
の上面に場所打コンクリートを打設して凹陥部に
嵌り合う場所打コンクリートにシヤコツターの役
目を果させるようにしたことにより、せん断応力
分散の平均化が期待され、実験例に示されている
ように強固な一体化が果され、施工に際し、プレ
キヤスト板と場所打コンクリートとの全体の厚さ
を一体構造物の厚さとして強度の算定ができ、そ
の結果、コスト、作業性の面において、従来工法
に比べて極めて有利になつたことが明らかであ
る。[Table] In addition, when a deflection test was conducted on synthetic floor test piece No. 1 in Table 1, the results were as shown in the graph in Figure 8. The flatness was maintained as shown in the graph of FIG. Discussion (1) Regarding strength and fracture properties Both the cracking load and maximum yield strength of the experimental setup exceeded the calculated setup as a single piece, confirming the integrity of the floorboard from the standpoint of strength. Furthermore, the fracture behavior was normal bending or shear fracture, and the fracture phenomenon of the joint surface was not observed until the end, and integrity was confirmed from the fracture behavior. (2) Regarding the load deformation curve The elastic stiffness of all experimental values exceeds the calculated values. Furthermore, when looking at the history characteristics of the curve, no phenomenon in which the integrity of the joining surface was lost was observed. These confirmed the integrity of the floorboards. (3) About crack properties The crack passes through the splicing surface almost in a straight line, and no progress is observed along the splicing surface. Therefore, the integrity of the floorboards was confirmed from the viewpoint of crack properties. (4) Regarding slippage on the joint surface The slippage on the joint surface was 0 to 0.01 mm or less, confirming that integrity was maintained. (5) Regarding flatness retention Looking at the results of plotting the skewness in the thickness direction, we find that
It is observed that the cross section maintains a substantially flat surface. Therefore, the integrity of the composite floor board, which was formed by integrally casting cast-in-place concrete on the top surface of a precast concrete board, was confirmed. Conclusion As described above, the structural integrity of the composite floorboard was confirmed in terms of strength, rigidity, fracture property, cracking property, slippage on the joint surface, and ability to maintain the plane of the cross section. The present invention is constructed as described above, and a large number of recesses are provided in a staggered manner on the surface of a precast board, and cast-in-place concrete is poured on the upper surface of the recesses, so that the cast-in-place concrete that fits into the recesses serves as a caster. As a result, it is expected that the shear stress distribution will be averaged, and as shown in the experimental example, a strong integration will be achieved. It is clear that the strength can be calculated using the thickness of the integrated structure, and as a result, it is extremely advantageous compared to conventional construction methods in terms of cost and workability.
第1図はプレキヤスト板の一例の部分斜視図、
第2図は凹陥部の同拡大断面図、第3図はプレキ
ヤスト板の他の例の部分斜視図、第4図は凹陥部
成形型の断面図、第5図はプレキヤスト板端部の
設置状態の一例の部分断面図、第6図は同じく他
の例の断面図、第7図は合成床試験片の断面図、
第8図はたわみ試験結果を示すグラフ、第9図は
打継ぎ面のすべり量を示すグラフ、第10図は断
面の平面保持を示すグラフである。
A……プレキヤスト板、B……場所コンクリー
ト、1……中空孔、2……PC鋼線、3……凹陥
部、10,12……梁。
Figure 1 is a partial perspective view of an example of a precast board;
Figure 2 is an enlarged sectional view of the recessed part, Figure 3 is a partial perspective view of another example of the precast board, Figure 4 is a sectional view of the mold for the recessed part, and Figure 5 is the installed state of the end of the precast board. A partial sectional view of one example, FIG. 6 is a sectional view of another example, and FIG. 7 is a sectional view of a synthetic floor test piece.
FIG. 8 is a graph showing the results of the deflection test, FIG. 9 is a graph showing the amount of slippage of the joint surface, and FIG. 10 is a graph showing the maintenance of the flatness of the cross section. A... Precast board, B... Place concrete, 1... Hollow hole, 2... PC steel wire, 3... Concave part, 10, 12... Beam.
Claims (1)
リート製プレキヤスト板を掛け渡し、その上面に
現場打コンクリートを一体に打設する床工法にお
いて、上記プレキヤスト板は表面に多数の凹陥部
を互いに近接させ千鳥状に分散配列させたものを
用い、このプレキヤスト板を上記凹陥部が少なく
とも掛け渡し方向に対しては斜行して配列するよ
うに設置した後、前記プレキヤスト板の表面及び
凹陥部内に前記現場打コンクリートを打ち込ん
で、前記凹陥部内の打込みコンクリートをシヤコ
ツターとして作用させて該プレキヤスト板と現場
打コンクリートとを一体化することにより、上記
プレキヤスト板における上記梁の長手に沿う方向
へのせん断応力の分配の平均化を図つたことを特
徴とする床工法。1. In a floor construction method in which concrete precast boards are stretched between steel frames or concrete beams, and cast-in-place concrete is poured on the top surface, the precast boards have a number of recesses on the surface that are close to each other and distributed in a staggered manner. After installing this precast board so that the recessed portions are arranged obliquely at least with respect to the spanning direction, pour the cast-in-place concrete into the surface of the precast board and into the recessed portion. By integrating the precast board and the cast-in-place concrete by making the poured concrete in the recess act as a shackle, the distribution of shear stress in the direction along the length of the beam in the precast board can be averaged. A floor construction method that is characterized by its unique design.
Priority Applications (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP58018138A JPS59145855A (en) | 1983-02-08 | 1983-02-08 | Floor construction using precast panel |
| KR1019840000615A KR900006763B1 (en) | 1983-02-08 | 1984-02-07 | Floor construction using precast panel |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP58018138A JPS59145855A (en) | 1983-02-08 | 1983-02-08 | Floor construction using precast panel |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS59145855A JPS59145855A (en) | 1984-08-21 |
| JPS6347861B2 true JPS6347861B2 (en) | 1988-09-26 |
Family
ID=11963239
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP58018138A Granted JPS59145855A (en) | 1983-02-08 | 1983-02-08 | Floor construction using precast panel |
Country Status (2)
| Country | Link |
|---|---|
| JP (1) | JPS59145855A (en) |
| KR (1) | KR900006763B1 (en) |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS62606U (en) * | 1985-06-18 | 1987-01-06 | ||
| JPH02261147A (en) * | 1989-03-31 | 1990-10-23 | Shimizu Corp | Structure of large reinforced concrete slub |
| KR101415369B1 (en) * | 2012-04-26 | 2014-07-04 | 서울시립대학교 산학협력단 | Surface treatment method for increasing shear bond strength of precast concrete member manufactured by extrusion |
Family Cites Families (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS4864213U (en) * | 1971-11-22 | 1973-08-15 | ||
| JPS5419703Y2 (en) * | 1973-09-25 | 1979-07-19 | ||
| JPS566844A (en) * | 1979-06-26 | 1981-01-24 | Koken Sekkei Kenkyusho Kk | Floor structure |
| JPS57199615U (en) * | 1981-06-17 | 1982-12-18 |
-
1983
- 1983-02-08 JP JP58018138A patent/JPS59145855A/en active Granted
-
1984
- 1984-02-07 KR KR1019840000615A patent/KR900006763B1/en not_active Expired
Also Published As
| Publication number | Publication date |
|---|---|
| JPS59145855A (en) | 1984-08-21 |
| KR840007934A (en) | 1984-12-11 |
| KR900006763B1 (en) | 1990-09-21 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR101229263B1 (en) | Slab-type box girder with a vertical connecting structure made by precast concrete and method constructing the bridge thereof | |
| JPS6347861B2 (en) | ||
| JPH05106339A (en) | Precast concrete formwork for concrete splicing | |
| JP5536988B2 (en) | Construction method of steel plate concrete structure | |
| JPS6156740B2 (en) | ||
| JP3418606B2 (en) | Girder members for PC bridge | |
| JPH1193316A (en) | Pc board for reinforced concrete floor slab and production form for pc board | |
| JPH10245922A (en) | Stepped floor execution method using perforated pc panel for composite floor | |
| JPH0426483Y2 (en) | ||
| KR20190080461A (en) | Concrete slab and method for manufacturing concrete slab | |
| JPH10110498A (en) | Half precast slab and method of constructing hollow flat slab using the same | |
| KR102923601B1 (en) | Module for load-bearing wall and manufacturing method thereof | |
| WO1991000400A1 (en) | Prefabricated floor slab | |
| KR102805389B1 (en) | the deck plate in half PC slab and the half PC slab using the same and the manufacturing method thereof | |
| JP7455931B1 (en) | Precast board manufacturing method and precast board | |
| JPS6322241Y2 (en) | ||
| JP3245106B2 (en) | Steel composite composite bridge using precast prestressed concrete slab | |
| JPS60144439A (en) | Construction of outer concrete wall using truss panel for outer wall | |
| JPS59114313A (en) | Construction of prestressed concrete floor panel in road bridge | |
| JPH0639823B2 (en) | Joint structure between precast concrete slab and beam | |
| KR920009316B1 (en) | 3D Prefabricated Rebar for HALF PRECAST Concrete Slabs | |
| JPS5817773Y2 (en) | Prestressed concrete girder for road bridge | |
| KR101962709B1 (en) | Composite deck slab construction method with trench | |
| JP2025072188A (en) | Concrete foundation structure | |
| JP2853528B2 (en) | Construction method of composite floorboard |