JPS6354116B2 - - Google Patents
Info
- Publication number
- JPS6354116B2 JPS6354116B2 JP1378983A JP1378983A JPS6354116B2 JP S6354116 B2 JPS6354116 B2 JP S6354116B2 JP 1378983 A JP1378983 A JP 1378983A JP 1378983 A JP1378983 A JP 1378983A JP S6354116 B2 JPS6354116 B2 JP S6354116B2
- Authority
- JP
- Japan
- Prior art keywords
- blasting
- tunnel
- hole
- excavation
- tunnel excavation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 238000009412 basement excavation Methods 0.000 claims description 35
- 238000005422 blasting Methods 0.000 claims description 23
- 238000005553 drilling Methods 0.000 claims description 15
- 238000000034 method Methods 0.000 claims description 14
- 239000011435 rock Substances 0.000 description 15
- 239000003795 chemical substances by application Substances 0.000 description 12
- 238000010276 construction Methods 0.000 description 4
- 239000002360 explosive Substances 0.000 description 3
- 235000019738 Limestone Nutrition 0.000 description 1
- 230000007423 decrease Effects 0.000 description 1
- 238000004880 explosion Methods 0.000 description 1
- 239000010438 granite Substances 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000006028 limestone Substances 0.000 description 1
- 239000011148 porous material Substances 0.000 description 1
- 239000000843 powder Substances 0.000 description 1
- 238000010008 shearing Methods 0.000 description 1
Landscapes
- Drilling And Exploitation, And Mining Machines And Methods (AREA)
Description
【発明の詳細な説明】
本発明は発破と膨張性破砕剤の併用により掘削
効率を高めたトンネル掘削工法に関する。従来ト
ンネル掘削工事は、火薬類使用による発破工法
か、トンネル掘進機などによる機械掘削工法など
によつて実施されて来た。特に、機械掘削工法で
は、岩石強度が600〜700Kg/cm2以上の岩石になる
と機械損耗がはげしく経済性や掘進速度などの面
から使用困難であるため、岩石トンネル掘削工法
の主体は発破工法で実施されている。しかし、発
破工法では、振動など周辺環境へ与える公害を抱
えており、人家、道路、鉄道などの保安物件が近
くにある所での施工が困難となつて来ている上、
発破振動による余掘、周辺岩石のゆるみなど安全
性及びトンネル耐久性などの面からも種々問題が
生じている。この中、余掘減少対策としてスムー
スプラスチング工法が多く採用されて来ている
が、硬岩の場合は、それなりの効果が認められて
も軟岩ではその効果が少ない欠点がある。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a tunnel excavation method that improves excavation efficiency by using a combination of blasting and an expandable crushing agent. Conventionally, tunnel excavation work has been carried out by a blasting method using explosives or a mechanical excavation method using a tunnel boring machine. In particular, with mechanical excavation methods, when the rock strength exceeds 600 to 700 kg/cm 2 , mechanical wear and tear is severe, making it difficult to use from the economical and excavation speed standpoints. It has been implemented. However, the blasting method causes pollution to the surrounding environment such as vibrations, and it is becoming difficult to carry out construction in areas where safety features such as residential buildings, roads, and railways are nearby.
Various problems have arisen in terms of safety and tunnel durability, such as over-excavation due to blasting vibrations and loosening of surrounding rocks. Among these, the smooth plasting method has been widely adopted as a measure to reduce over-excavation, but although it is effective on hard rocks, it has the disadvantage that it is less effective on soft rocks.
本発明者は軟岩、硬岩の別にかかわらず発破の
際の余掘を防止し且つ振動を減少させるトンネル
掘削工法につき鋭意研究の結果、トンネル掘削予
定部の外周に沿つて一定間隔でラインドリリング
を行ない、穿設された孔に膨張性破砕剤を適用し
た後、所定部分を発破すればよい事に着目し本発
明を完成させた。 As a result of intensive research into a tunnel excavation method that prevents over-excavation during blasting and reduces vibration, regardless of whether it is soft rock or hard rock, the inventor has found that line drilling is carried out at regular intervals along the outer circumference of the planned tunnel excavation area. The present invention was completed by focusing on the fact that it is sufficient to blast a predetermined portion after applying an expandable crushing agent to the drilled hole.
以下図面により本発明の内容を説明する。第1
図は本発明工法の実線態様を示す正面図である。
図中1は岩石のトンネル掘削予定部であり、その
外周1aに沿つて孔間隔20〜50cmでラインドリリ
ングを行なう。このようにして穿設された孔2,
2,2,…は孔径3〜8cm、孔長1.5〜5m程度
のもので、これらにプライスター〔小野田セメン
ト(株)製〕などの膨張性破砕剤を充填し、一定時
間、即ち岩石の孔2,2間を結ぶ亀裂が生ずるま
での時間養生する。その後孔2,2,2,…より
トンネルの中心側へ50〜100cm程度の間隙を設け、
これより中心側の位置にダイナマイト等の火薬を
装薬し、発破を行なう。 The contents of the present invention will be explained below with reference to the drawings. 1st
The figure is a front view showing a solid line aspect of the construction method of the present invention.
In the figure, reference numeral 1 indicates a planned area for tunnel excavation in the rock, and line drilling will be performed along its outer periphery 1a at a hole interval of 20 to 50 cm. Hole 2 drilled in this way,
2, 2, ... have a hole diameter of 3 to 8 cm and a hole length of about 1.5 to 5 m. These are filled with an expansive crushing agent such as Plaister (manufactured by Onoda Cement Co., Ltd.), and the pores of the rock are 2.Curing for a period of time until a crack appears between the two. After that, create a gap of about 50 to 100 cm from holes 2, 2, 2, ... towards the center of the tunnel,
Explosive powder such as dynamite is charged at a position closer to the center and blasting is performed.
なお、本発明の実際において前記孔の長さは、
これを長くする程トンネル掘削予定部より外側に
向つて穿孔される傾向があり5mを超える長さに
するのは好ましくない。また逆に短くするほど寸
法精度は良くなるが、膨張性破砕剤充填後必要破
砕力に達するまでの養生時間が長くかかるため、
トンネル掘削能率の上から1.5m未満は好ましく
ない。 In addition, in practice of the present invention, the length of the hole is:
The longer the tunnel is, the more likely it is that the tunnel will be drilled outward from the area where the tunnel is to be excavated, so it is not preferable to make it longer than 5 m. Conversely, the shorter the length, the better the dimensional accuracy will be, but it will take a longer curing time to reach the required crushing force after filling with the expandable crushing agent.
Less than 1.5m from the top of tunnel excavation efficiency is not preferable.
また発破は孔2,2,2,…より50cm未満の位
置にて行なうと余掘が生ずる慮れがある。 Moreover, if the blasting is carried out at a position less than 50 cm from holes 2, 2, 2, etc., there is a possibility that over-excavation will occur.
一方、トンネル掘削工法には掘削予定部1の中
央部1bを発破して芯抜きをした後、芯抜き部1
bの周辺の拡幅部1cを発破する方法があるがこ
の方法においても前述したようにトンネル外周に
沿つてラインドリリングを行い、かつ拡幅部1c
にも小孔3を適宜穿設して膨張性破砕剤を充填
し、一定期間養生した後、前述と同様に発破を行
えばよい。尚、拡幅部1cの穿孔としては、岩
質、トンネル径の大きさ等にもよるが、通常、孔
径2〜8cm、孔長3〜7m程度の孔を50〜70cm程
度隔で適数穿設するとよい。 On the other hand, in the tunnel excavation method, after blasting the central part 1b of the planned excavation part 1 and removing the core,
There is a method of blasting the widened part 1c around b, but in this method as well, line drilling is performed along the outer circumference of the tunnel as described above, and the widened part 1c is blasted.
A small hole 3 may be suitably drilled in the hole 3, filled with an expandable crushing agent, and after curing for a certain period of time, blasting may be carried out in the same manner as described above. In addition, as for the drilling of the widened part 1c, depending on the rock quality, the size of the tunnel diameter, etc., normally, an appropriate number of holes with a hole diameter of 2 to 8 cm and a hole length of 3 to 7 m are bored at intervals of 50 to 70 cm. It's good to do that.
以上のように芯抜き発破後に膨張破砕剤を用い
る場合には、膨張破砕剤充填後の発破量は通常の
1/2〜1/5の量で行うようにする。尚この工法にお
いて拡幅部1cの孔3の孔長はかなり長くしても
トンネル外周へ突出する慮れがなく、むしろ芯抜
き部1b、拡幅部1cの作業をしている間に膨張
性破砕剤の養生が十分できるので亀裂幅の拡大に
よるその後の掘削能率が向上する利益がある。 When using an expanding crushing agent after core blasting as described above, the amount of blasting after filling with the expanding crushing agent is 1/2 to 1/5 of the usual amount. In addition, in this construction method, even if the hole length of the hole 3 in the widened part 1c is considerably long, there is no possibility that it will protrude to the outer circumference of the tunnel. This has the benefit of increasing the subsequent excavation efficiency by expanding the crack width.
更に芯抜きした後に発破を行う方法では、前記
拡幅部1cよりも奥の位置の中央部1bをも該拡
幅部1cと同時に発破して芯抜きし、次の掘削工
法に利用するようにしてもよい。 Furthermore, in the method of performing blasting after coring, the center portion 1b located further back than the widened portion 1c may also be blasted and cored at the same time as the widened portion 1c, and used for the next excavation method. good.
以上説明したように本発明は、トンネル掘削予
定部の外周に所定間隔ごとに設けた複数の孔に、
更に記必要に応じて拡幅部に設けた複数の孔に膨
張性破砂剤を充填するため岩石に亀裂が生じるの
で発破を行う際に余掘が起らない。また掘削すべ
き岩石も亀裂が生じ脆くなつているので発破に要
する火薬量は少量で足りる。 As explained above, the present invention provides a plurality of holes provided at predetermined intervals around the outer circumference of a planned tunnel excavation area.
Furthermore, since the plurality of holes provided in the widened portion are filled with an expandable sand-breaking agent as necessary, cracks are generated in the rock, so no over-excavation occurs during blasting. Also, since the rock to be excavated has cracks and has become brittle, only a small amount of explosives is needed for blasting.
次に本発明の実施例を示す。 Next, examples of the present invention will be shown.
実施例 1
花崗岩地帯において上半断面半径2.3m、下半
1.5m掘下げる馬蹄形トンネル掘削工事において、
トンネル掘削予定部の外周を孔径50mm孔長2.5m
孔間隔30cmでラインドリリングを実施後直ちに膨
張性破砕剤〔プライスター(小野田セメント(株)
製〕を充填し、その後トンネル掘削予定部を孔径
32mm孔長1.5mで、芯抜部は4孔/m2、拡幅部3
孔/m2平均で穿孔する。この時ラインドリリング
部内側から拡幅部分までは50cm離して実施し、2
号榎ダイナマイト(100g/本)を用い、芯抜き
部は8本/孔拡幅部は芯抜き部より遠くなるに従
つて1本/孔ずつ減少させた装薬を行ない、段発
により岩石を破砕したところ、余掘はほとんど認
められずトンネル掘削予定部の岩石破壊が可能で
あつた。Example 1 In a granite area, the upper half section radius is 2.3 m, and the lower half
During excavation work for a horseshoe-shaped tunnel that goes down 1.5m,
The outer circumference of the planned tunnel excavation area is 50mm in diameter and 2.5m in length.
Immediately after line drilling with a hole spacing of 30cm, apply an expansive crushing agent [Plystar (Onoda Cement Co., Ltd.)
After that, the hole diameter of the planned tunnel excavation area is
32mm hole length 1.5m, cored part 4 holes/m 2 , widened part 3
Drill holes/m 2 on average. At this time, the distance from the inside of the line drilling part to the widening part is 50 cm, and 2
Using Gono dynamite (100g/piece), the cored part is 8 pieces/the hole widened part is charged with 1 piece/hole that decreases as the distance from the cored part increases, and the rock is crushed in stages. As a result, there was hardly any excess excavation, and it was possible to destroy the rock in the area where the tunnel was to be excavated.
実施例 2
石灰岩地帯での半径2.5mの上半断面先進掘削
トンネル工事において、中心部をVカツトで穿孔
し、ダイナマイトを用いて芯抜きを実施した後ト
ンネル掘削予定部の外周を孔間隔40cm孔径50mm、
孔長3mでラインドリリングをし、又、ラインド
リリング内部の拡幅部を発破装薬孔は孔径32m、
孔長1.5m、膨張性破砕剤充填孔は孔間隔50〜70
cm孔長5m、孔径50mmで穿孔し、直ちにラインド
リリング部分を含め膨張性破砕剤〔プライスター
(小野田セメント(株)製〕を充填し20時間養生後発
破装薬孔に5本/孔の2号榎ダイナマイト(100
g/本)を装薬し芯抜き部の近い程早く爆発する
よう雷管を用いて段発を実施したところ、1.5m
奥までの岩石掘削が可能となると同時にラインド
リリング外部の余掘が殆んど認められなかつた、
その後、ずり搬出、支保工設置などの作業を実施
した後、概に膨張性破砕剤はラインドリリング部
及び拡幅部では発破による掘削深さ以上に深く充
填されているため次の作業は芯抜き発破及び拡幅
部の発破用孔の穿孔発破作業を繰返し岩石掘削作
業を実施した。この結果ダイナマイト使用量も軽
減でき、また振動騒音も大幅に低下することがで
きた。Example 2 In the construction of an advanced excavation tunnel with a radius of 2.5m in the upper half of a limestone area, the center was drilled with a V-cut, the core was removed using dynamite, and then the outer periphery of the planned tunnel excavation area was drilled with a hole diameter of 40cm in diameter. 50mm,
Line drilling was performed with a hole length of 3 m, and the widened part inside the line drilling was blasted.The hole diameter of the charge hole was 32 m.
Hole length 1.5m, expandable crushing agent filling hole spacing 50-70
Drill a hole with a length of 5 m and a hole diameter of 50 mm, immediately fill the line drilling part with an expanding crushing agent [Plystar (manufactured by Onoda Cement Co., Ltd.)], and after curing for 20 hours, fill the blasting charge hole with 5 holes/2 holes. Goen Dynamite (100
When a detonator was used to detonate the charge closer to the core part and detonate faster, the explosion occurred at 1.5 m.
At the same time, it became possible to excavate the rock to the depths, and at the same time, there was hardly any excess excavation outside the line drilling.
After that, after carrying out work such as shearing and shoring installation, the expanding crushing agent is generally filled deeper than the excavation depth by blasting in the line drilling part and widening part, so the next work is core blasting. Rock excavation work was carried out repeatedly, including drilling and blasting of blasting holes in the widening section. As a result, the amount of dynamite used could be reduced, and vibration noise could also be significantly reduced.
第1図および第2図は本発明の実施態様を示す
正面説明図。
図面中、1はトンネル掘削予定部、1aは外
周、1bは芯抜き部、1cは拡幅部、2,3は孔
である。
1 and 2 are explanatory front views showing embodiments of the present invention. In the drawings, 1 is a planned tunnel excavation area, 1a is an outer periphery, 1b is a cored part, 1c is a widened part, and 2 and 3 are holes.
Claims (1)
間隙ごとにラインドリリングを行ない、穿設した
孔に膨張性破砕剤を充填し、一定時間養生した
後、該孔よりトンネル中心側へ所定距離離れた箇
所で発破を行うことを特徴とするトンネル掘削工
法。 2 トンネル掘削予定部の中央部を発破して芯抜
きする際、芯抜き部周辺の拡幅部に一定間隙ごと
に小孔を穿設し、かつトンネル掘削予定部の外周
に沿つて所定の孔間隙ごとにラインドリリングを
行い、これらの孔に膨張性破砕剤を充填し、一定
時間養生した後、ラインドリリングの孔からトン
ネル中心側へ所定距離離れた箇所で発破を行い、
芯抜き後又は芯抜きと共に掘削することを特徴と
するトンネル掘削工法。[Scope of Claims] 1. Line drilling is performed at predetermined hole gaps along the outer periphery of the planned tunnel excavation area, the drilled holes are filled with an expandable crushing agent, and after curing for a certain period of time, the tunnel is excavated from the hole. A tunnel excavation method characterized by performing blasting at a location a predetermined distance away from the center. 2. When blasting and coring the central part of the planned tunnel excavation area, small holes are drilled at regular intervals in the widened area around the cored part, and predetermined hole gaps are drilled along the outer periphery of the planned tunnel excavation area. Line drilling is performed each time, these holes are filled with an expandable crushing agent, and after curing for a certain period of time, blasting is performed at a location a predetermined distance away from the line drilling hole towards the center of the tunnel.
A tunnel excavation method characterized by excavating after or together with core removal.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1378983A JPS59141693A (en) | 1983-02-01 | 1983-02-01 | Tunnel drilling method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP1378983A JPS59141693A (en) | 1983-02-01 | 1983-02-01 | Tunnel drilling method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS59141693A JPS59141693A (en) | 1984-08-14 |
| JPS6354116B2 true JPS6354116B2 (en) | 1988-10-26 |
Family
ID=11843011
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP1378983A Granted JPS59141693A (en) | 1983-02-01 | 1983-02-01 | Tunnel drilling method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS59141693A (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS6419300A (en) * | 1987-07-11 | 1989-01-23 | Shimizu Construction Co Ltd | Blasting for underground excavation |
-
1983
- 1983-02-01 JP JP1378983A patent/JPS59141693A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS59141693A (en) | 1984-08-14 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN109026019A (en) | The method that water mill bores non-blasting rock move hole excavation construction | |
| CN108729924A (en) | A kind of urban hard rock tunnel mechanical excavation rapid constructing method | |
| CN108590688A (en) | A kind of TBM development machines and its tunneling construction method with hydraulic drill rig | |
| KR101889961B1 (en) | Excavation method for rock blasting having no-vibration | |
| JP2614396B2 (en) | Shaft excavation method by pre-boring | |
| JP2015025239A (en) | Tunnel excavation method | |
| WO2025218362A1 (en) | Combined excavation method for shaft in soft-over-hard composite strata | |
| JPS6354116B2 (en) | ||
| WO1991016524A1 (en) | Method of excavating tunnel | |
| Jimeno et al. | Drilling änd blasting of rocks | |
| CN112964143A (en) | Three-time blasting method for hollow hole straight-hole cut | |
| US3266845A (en) | Core and blast tunneling method | |
| JPH07103700A (en) | Underground space formation blasting method | |
| JPH0533577A (en) | Method for excavating steel tower foundation hole, etc. | |
| CN114810099A (en) | Ultra-thin rock stratum ultra-large span high-speed rail tunnel excavation construction method | |
| US4673218A (en) | Tunnel excavation method | |
| JP3486103B2 (en) | How to blast rock | |
| JPH09302654A (en) | Construction method and equipment for steel pipe sheet pile | |
| AU768956B2 (en) | Shaft sinking method | |
| JPH0319356B2 (en) | ||
| CN115420158B (en) | A rapid blasting pre-cracking method for shield tunnels | |
| JPH0835389A (en) | Excavation method for underground structures | |
| KR960013597B1 (en) | Tunnel Excavation Method | |
| JPS6124511B2 (en) | ||
| JPS6030837B2 (en) | Vertical shaft excavation method |