Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPS6358976B2 - - Google Patents
[go: Go Back, main page]

JPS6358976B2 - - Google Patents

Info

Publication number
JPS6358976B2
JPS6358976B2 JP58205429A JP20542983A JPS6358976B2 JP S6358976 B2 JPS6358976 B2 JP S6358976B2 JP 58205429 A JP58205429 A JP 58205429A JP 20542983 A JP20542983 A JP 20542983A JP S6358976 B2 JPS6358976 B2 JP S6358976B2
Authority
JP
Japan
Prior art keywords
plate
reinforcing bar
trailing
groove
panel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP58205429A
Other languages
Japanese (ja)
Other versions
JPS6098010A (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP20542983A priority Critical patent/JPS6098010A/en
Publication of JPS6098010A publication Critical patent/JPS6098010A/en
Publication of JPS6358976B2 publication Critical patent/JPS6358976B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【発明の詳細な説明】 <産業上の利用分野> この発明は、地中連続壁、特に、円筒状の地下
タンクの土留・止水壁として使用される円筒状連
続壁の構築に有効な施工方法に関するものであ
る。
[Detailed Description of the Invention] <Industrial Application Field> The present invention is an effective construction method for constructing underground continuous walls, particularly cylindrical continuous walls used as earth retaining and water-stop walls for cylindrical underground tanks. It is about the method.

<この発明が解決しようとする問題点> 第1図、第2図に示すのは、地下タンクの工事
の概要であり、地下タンク1の地中連続壁2は、
連続壁を円周方向に結合して全体を単体の円筒シ
エル構造としなければならず、このため継手部に
曲げ剛性をもたせなければならない。
<Problems to be Solved by the Invention> Figures 1 and 2 show an outline of the construction of an underground tank.
The continuous walls must be joined in the circumferential direction to form a single cylindrical shell structure, and therefore the joint must have bending rigidity.

そのため、第3図に示すように、先行パネル鉄
筋籠3Aと後行パネル鉄筋籠4Aの端部横筋どう
しをラツプさせる鉄筋重ね継手方式が採られてい
る。
Therefore, as shown in FIG. 3, a reinforcing bar overlap joint method is adopted in which the end transverse reinforcements of the leading panel reinforcing bar cage 3A and the trailing panel reinforcing bar cage 4A are lapped together.

このような方式の場合、第4図、第5図に示す
ように、両側に先行パネル3を構築した後、中央
に後行掘削溝5を掘削し後行パネル4を構築する
ことになるが、溝5の掘削後、掘削不可能な箇所
Pに掘り屑がたまり、コンクリートと置換できな
くなるという問題がある。
In the case of such a method, as shown in Figures 4 and 5, after constructing the leading panels 3 on both sides, the trailing excavation groove 5 is excavated in the center and the trailing panel 4 is constructed. , after excavation of the trench 5, there is a problem that the excavated debris accumulates in the location P where it is impossible to excavate, making it impossible to replace it with concrete.

<発明の目的> この発明は、このような事情に鑑みて提案され
たもので、その目的は、鉄筋重ね継手方式の地中
連続壁を能率良く経済的に構築できる施工方法を
提供することにある。
<Purpose of the invention> This invention was proposed in view of the above circumstances, and its purpose is to provide a construction method that can efficiently and economically construct an underground continuous wall using reinforcing bar lap joints. be.

<発明の構成> この発明に係る地中連続壁の施工方法は、先行
して掘削された先行掘削溝に、溝長手方向端部に
仕切板を有するとともにこの仕切板から横筋が所
定長さで突出するように構成された先行パネル鉄
筋籠を建込んでコンクリートを打設し、先行パネ
ル鉄筋籠の突出した横筋を覆い得る断面略コ字状
の保護板の基板の両側より延出した延出板の外面
にロツキングチユーブを取付け、該保護板を前記
仕切板に沿つて建込み、次いで、隣接する後行掘
削溝を掘削した後前記保護板を引き抜き、続いて
前記後行掘削溝に、後行パネル鉄筋籠を、その溝
長手方向端部の横筋が前記先行パネル鉄筋籠の突
出した横筋とラツプするように建込んでコンクリ
ートを打設するようにしたものである。
<Structure of the Invention> The method for constructing an underground continuous wall according to the present invention is to provide a previously excavated trench with a partition plate at the longitudinal end of the trench, and to extend a transverse line from the partition plate with a predetermined length. A preceding panel reinforcing bar cage configured to protrude is erected and concrete is poured, and a protective plate having a substantially U-shaped cross section is extended from both sides of the substrate to cover the protruding horizontal reinforcement of the preceding panel reinforcing bar cage. Attach a locking tube to the outer surface of the plate, erect the protective plate along the partition plate, then, after excavating an adjacent trailing excavation groove, pull out the protective plate, and then into the trailing excavation groove, Concrete is placed by erecting the trailing panel reinforcing bar cage so that the horizontal reinforcement at the longitudinal end of the groove overlaps with the protruding horizontal reinforcement of the preceding panel reinforcing bar cage.

<実施例> 以下、この発明を図示する一実施例に基づいて
説明する。この実施例は、地下タンクの円筒状の
地中連続壁の場合であり、第6図、第7図に示す
ような、所定曲率で湾曲する先行パネル10と後
行パネル11とを交互に配設して構成される。
<Example> The present invention will be described below based on an illustrative example. This embodiment is a case of a cylindrical underground continuous wall of an underground tank, and leading panels 10 and trailing panels 11 curved at a predetermined curvature are alternately arranged as shown in FIGS. 6 and 7. established and configured.

先行パネルの鉄筋籠10A、後行パネルの鉄筋
籠11Aは、それぞれ縦筋12、横筋13を有
し、さらに、所定の曲率を保持するようにラチス
筋14等で抵抗する構成とされている。
The reinforcing bar cage 10A of the leading panel and the reinforcing bar cage 11A of the trailing panel each have vertical reinforcements 12 and horizontal reinforcements 13, and are further configured to resist with lattice reinforcements 14 and the like so as to maintain a predetermined curvature.

さらに、先行パネル鉄筋籠10Aは、その両端
部には仕切鋼板15が設けられるとともにこの仕
切鋼板15から横筋13Aが所定長さで突出する
ように構成されている。横筋13、縦筋12はネ
ジバーとされ、横筋13はナツト16により仕切
鋼板15に固定される。
Further, the preceding panel reinforcing bar cage 10A is configured such that partition steel plates 15 are provided at both ends thereof, and horizontal reinforcements 13A protrude from the partition steel plates 15 by a predetermined length. The horizontal reinforcement 13 and the vertical reinforcement 12 are screw bars, and the horizontal reinforcement 13 is fixed to the partition steel plate 15 with a nut 16.

仕切鋼板15は、両面に止水鋼板17,17′、
両端部にコンクリート回り込み防止用シート18
およびコンクリート流出防止用ゴム板19が取付
けられ、さらに、両端部には、半円状で後行パネ
ル側に湾曲するガイド部20が形成され、後述す
る保護板の建込みの際の案内とされている。
The partition steel plate 15 has water-stop steel plates 17, 17' on both sides.
Concrete wrap prevention sheet 18 on both ends
A rubber plate 19 for preventing concrete spillage is attached, and guide portions 20 having a semicircular shape and curving toward the trailing panel are formed at both ends, and are used as guides when installing a protection plate to be described later. ing.

後行パネル鉄筋籠11Aの端部の横筋13B
は、内側に折曲げられ先行パネル鉄筋籠10Aの
横筋13Aと所定の間隔をおいてラツプするよう
にされている。さらに、横筋13Bの縦筋12は
内側に配設され、横筋13Aの内側にはフラツト
バー21が配設され、このフラツトバー21は後
行パネル鉄筋籠11A挿入時の案内となる。
Horizontal reinforcement 13B at the end of trailing panel reinforcing bar cage 11A
is bent inward to wrap with the horizontal reinforcement 13A of the preceding panel reinforcing bar cage 10A at a predetermined distance. Furthermore, the vertical bars 12 of the horizontal bars 13B are arranged on the inside, and a flat bar 21 is arranged on the inside of the horizontal bars 13A, and this flat bar 21 serves as a guide when inserting the trailing panel reinforcing bar cage 11A.

次に、保護板22は、第9図に示すように、先
行パネル10の端部に取付けられ、後行掘削溝掘
削時にこの端部を保護するもので、断面コ字状と
されている。この保護板22は、中央に凹部を有
する基板22Aと、先行掘削溝の側壁に接触せず
に基板22Aから仕切鋼板15に向かつて延出す
る延出板22Bからなり、この延出板22Bの外
面にロツキングチユーブ23が取付けられてい
る。保護板22の建込終了後に、ロツキングチユ
ーブ23内に泥水を注入し膨らませれば、保護板
22と先行掘削溝側壁との間隔が塞さがれ掘削屑
の侵入が防止されることになる。
Next, as shown in FIG. 9, the protection plate 22 is attached to the end of the preceding panel 10 to protect this end during excavation of the trailing excavation trench, and has a U-shaped cross section. This protection plate 22 consists of a base plate 22A having a concave portion in the center, and an extension plate 22B that extends from the base plate 22A toward the partition steel plate 15 without contacting the side wall of the preceding excavation groove. A locking tube 23 is attached to the outer surface. After the construction of the protection plate 22 is completed, if muddy water is injected into the locking tube 23 and the rocking tube 23 is inflated, the gap between the protection plate 22 and the side wall of the preceding excavation trench is closed, thereby preventing excavation debris from entering. .

さらに、保護板22は、鉄筋籠10A,11A
と同様に複数のロツトに分割され順次継ぎ足して
建込まれるが、第10図に示すように最下端の保
護板22にのみ、ガイド部20に係合する係合突
起24が延出板22Bの先端に突設されている。
これは、建込時に、先行パネル端部すなわち仕切
鋼板15の鉛直方向たわみに対して容易に追随で
きるようにするためである。さらに、このような
最下端の保護板22には、仕切鋼板清掃用ブラシ
25、突出横筋13A清掃用ブラシ26、止水鋼
板17清掃用ブラシ27がそれぞれの部材15,
13A,16に押圧状態で取付けられている。先
行パネルの端部は長期間泥水中に放置されるた
め、スライムが付着しているため、後行パネル鉄
筋籠建込み直前に前記スライム、掘削屑を除去し
てやる必要があるが、このような構成であれば、
保護板22の引き抜きと同時に清掃を行なうこと
ができる。
Furthermore, the protection plate 22
In the same way, it is divided into a plurality of lots and added to them one after another, but as shown in FIG. It is protruded at the tip.
This is to make it possible to easily follow the vertical deflection of the preceding panel end, that is, the partition steel plate 15, during erection. Further, on the lowermost protection plate 22, a partition steel plate cleaning brush 25, a protruding horizontal strip 13A cleaning brush 26, a water stop steel plate 17 cleaning brush 27 are attached to the respective members 15,
It is attached to 13A and 16 in a pressed state. Since the ends of the leading panels are left in muddy water for a long period of time, slime is attached to them, so it is necessary to remove the slime and excavated debris just before constructing the reinforcing bar cages of the trailing panels. If,
Cleaning can be performed simultaneously with pulling out the protection plate 22.

次に、保護板22と保護板22との接合の一例
を第11図、第12図に示す。これは、ボルト孔
28を有する継ぎ板29を、保護板22の上端か
ら突出させて補強板30を介して保護板22に取
付けるとともに保護板22の下端にボルト孔31
を有する補強板32を添着し、ボルト・ナツトで
接合するものである。なお、ロツキングチユーブ
23は、下端に薄いゴム板33により接続する。
Next, an example of joining the protective plates 22 to each other is shown in FIGS. 11 and 12. In this case, a joint plate 29 having bolt holes 28 is made to protrude from the upper end of the protection plate 22 and is attached to the protection plate 22 via a reinforcing plate 30.
A reinforcing plate 32 having a diameter is attached to the reinforcing plate 32 and joined with bolts and nuts. Note that the locking tube 23 is connected to the lower end by a thin rubber plate 33.

次に、第13図、第14図に示すのは、先行パ
ネルガイド34であり、先行掘削溝35の端部に
挿入されるパイプ36と、このパイプ36に鉛直
方向に間隔をおいて配設された位置決め部材37
からなる。この位置決め部材37は、先行掘削溝
35端部の半円溝に位置する半円状の円筒部38
と、仕切鋼板15に向かつて突出し止水鋼板17
を挾んで一対とされた突出部39を備えている。
Next, FIG. 13 and FIG. 14 show the preceding panel guide 34, which includes a pipe 36 to be inserted into the end of the preceding excavation groove 35, and a pipe 36 arranged at intervals in the vertical direction. positioning member 37
Consisting of This positioning member 37 has a semicircular cylindrical portion 38 located in a semicircular groove at the end of the preceding excavation groove 35.
and a water-stop steel plate 17 protruding toward the partition steel plate 15.
It is provided with a pair of protrusions 39 sandwiching the two.

以上のような構成において、次のような工程順
で施工を行なう。
In the above configuration, construction is performed in the following process order.

第15図に示すように、先行溝35を掘削す
る。
As shown in FIG. 15, a leading groove 35 is excavated.

第16図に示すように、先行パネルガイド3
4を先行溝35の両端部に建込む。
As shown in FIG. 16, the preceding panel guide 3
4 are built into both ends of the leading groove 35.

第17図に示すように、先行パネル鉄筋籠1
0Aを建込む。
As shown in Fig. 17, the preceding panel reinforcing bar cage 1
Set up 0A.

第18図に示すように、コンクリートを打設
すれば、第19図に示すように、先行パネル1
0が得られる。
As shown in Fig. 18, if concrete is poured, as shown in Fig. 19, the preceding panel 1
0 is obtained.

第20図に示すように、保護板22を先行パ
ネル10の端部に建込む。
As shown in FIG. 20, a protection plate 22 is installed at the end of the preceding panel 10.

第21図に示すように、後行溝40を掘削す
る。
As shown in FIG. 21, a trailing groove 40 is excavated.

第22図に示すように、スライム処理を行な
う。
As shown in FIG. 22, slime processing is performed.

第23図に示すように、保護板22を引き抜
きつつ先行パネル10の端部の清掃を行なう。
As shown in FIG. 23, the end portion of the preceding panel 10 is cleaned while the protective plate 22 is being pulled out.

第24図に示すように、後行パネル鉄筋籠1
1Aの建込みを行なう。
As shown in Fig. 24, trailing panel reinforcing bar cage 1
Construction of 1A will be carried out.

第25図に示すように、コンクリートを打設
して後行パネルを得る。
As shown in FIG. 25, concrete is poured to obtain trailing panels.

このような工程を順次円周方向に繰り返すこと
により円筒状の地中連続壁が構築される。
By sequentially repeating these steps in the circumferential direction, a cylindrical underground continuous wall is constructed.

なお、以上は、円筒状の地中連続壁について示
したが、直線状の連続壁などにも本発明に係る施
工方法を有効に適用できる。
Although the above description has been made regarding a cylindrical underground continuous wall, the construction method according to the present invention can also be effectively applied to a linear continuous wall.

<発明の効果> 前述のとおり、この発明によれば比較的簡単な
構成の保護板を使用し、ロツキングチユーブによ
り先行掘削溝の端部を後行溝の掘削時に後行掘削
溝より完全に遮断し、掘削屑の侵入を防止するこ
とができ、先行パネルの仕切鋼板より突出した横
筋を後行パネル横筋と重ねる際の先行パネルの横
筋の清掃を容易なものとすることができるから、
鉄筋重ね継手方式の地中連続壁を能率良く経済的
に構築できる。
<Effects of the Invention> As described above, according to the present invention, a protective plate with a relatively simple structure is used, and the locking tube allows the end of the leading excavated groove to be completely secured from the trailing excavated groove when excavating the trailing groove. This makes it possible to block and prevent the intrusion of excavation debris, and to make it easier to clean the horizontal stripes of the leading panel when the horizontal strips protruding from the partition steel plate of the preceding panel are overlapped with the horizontal strips of the trailing panel.
It is possible to efficiently and economically construct an underground continuous wall using the reinforcing bar lap joint method.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図、第2図は、地下タンクの工事の概略を
示す横断面図、第3図は、地中連続壁の鉄筋重ね
継手を示す概略平面図、第4図、第5図は、地中
連続壁の掘削溝の掘削方法を示す平面図、縦断面
図、第6図は先行パネルを示す平面図、第7図は
後行パネルを示す平面図、第8図は、この発明に
係る鉄筋重ね継手を示す平面図、第9図は先行パ
ネルの保護板を示す平面図、第10図は、その下
端部を示す斜視図、第11図は、保護板の接合部
分を示す斜視図、第12図は、保護板の接合状況
を示す斜視図、第13図、第14図は、先行パネ
ルガイドを示す平面図、正面図、第15図ないし
第25図は、この発明に係る施工方法を工程順に
示した縦断面図である。 1……地下タンク、2……地中連続壁、3……
先行パネル、4……後行パネル、5……後行掘削
溝、10……先行パネル、11……後行パネル、
10A,11A……鉄筋籠、12……縦筋、1
3,13A,13B……横筋、14……ラチス
筋、15……仕切鋼板、16……ナツト、17,
17′……止水鋼板、18……コンクリート回り
込み防止用シート、19……コンクリート流出防
止用ゴム板、20……ガイド部、21……フラツ
トバー、22……保護板、22A……基板、22
B……延出板、23……ロツキングチユーブ、2
4……係合突起、25,26,27……清掃用ブ
ラシ、28……ボルト孔、29……継ぎ板、30
……補強板、31……ボルト孔、32……補強
板、33……ゴム板、34……先行パネルガイ
ド、35……先行掘削溝、36……パイプ、37
……位置決め部材、38……円筒部、39……突
出部、40……後行掘削溝。
Figures 1 and 2 are cross-sectional views showing the outline of underground tank construction, Figure 3 is a schematic plan view showing reinforcing bar lap joints for underground walls, and Figures 4 and 5 are underground tank construction diagrams. FIG. 6 is a plan view showing a leading panel, FIG. 7 is a plan view showing a trailing panel, and FIG. FIG. 9 is a plan view showing the protection plate of the preceding panel; FIG. 10 is a perspective view showing the lower end thereof; FIG. 11 is a perspective view showing the joint portion of the protection plate; FIG. 12 is a perspective view showing how the protection plates are joined; FIGS. 13 and 14 are plan views and front views showing the preceding panel guide; and FIGS. 15 to 25 are construction methods according to the present invention. FIG. 1... Underground tank, 2... Underground continuous wall, 3...
Leading panel, 4... Trailing panel, 5... Trailing excavation groove, 10... Leading panel, 11... Trailing panel,
10A, 11A...Reinforcement cage, 12...Vertical reinforcement, 1
3, 13A, 13B...Horizontal bar, 14...Lattice bar, 15...Partition steel plate, 16...Nut, 17,
17'...Waterstop steel plate, 18...Sheet for preventing concrete from running around, 19...Rubber plate for preventing concrete outflow, 20...Guide portion, 21...Flat bar, 22...Protection plate, 22A...Substrate, 22
B... Extension plate, 23... Locking tube, 2
4... Engaging protrusion, 25, 26, 27... Cleaning brush, 28... Bolt hole, 29... Joint plate, 30
... Reinforcement plate, 31 ... Bolt hole, 32 ... Reinforcement plate, 33 ... Rubber plate, 34 ... Leading panel guide, 35 ... Leading excavation groove, 36 ... Pipe, 37
... Positioning member, 38 ... Cylindrical portion, 39 ... Projection part, 40 ... Trailing excavation groove.

Claims (1)

【特許請求の範囲】[Claims] 1 先行して掘削された先行掘削溝に、溝長手方
向端部に仕切板を有するとともにこの仕切板から
横筋が所定長さで突出するように構成された先行
パネル鉄筋籠を建込んでコンクリートを打設し、
先行パネル鉄筋籠の突出した横筋を覆い得る断面
略コ字状の保護板の基板の両側より延出した延出
板の外面にロツキングチユーブを取付け、該保護
板を前記仕切板に沿つて建込み、次いで、隣接す
る後行掘削溝を掘削した後前記保護板を引き抜
き、続いて、前記後行掘削溝に、後行パネル鉄筋
籠を、その溝長手方向端部の横筋が前記先行パネ
ル鉄筋籠の突出した横筋とラツプするように建込
んでコンクリートを打設することを特徴とする地
中連続壁の施工方法。
1. A preceding panel reinforcing bar cage, which has a partition plate at the longitudinal end of the groove and is configured such that horizontal reinforcements protrude at a predetermined length from the partition plate, is erected in the previously excavated trench, and then concrete is poured. Pour the concrete,
A locking tube is attached to the outer surface of the extended plate extending from both sides of the base plate of the protective plate having a substantially U-shaped cross section capable of covering the protruding horizontal reinforcement of the preceding panel reinforcing bar cage, and the protective plate is constructed along the partition plate. Then, after excavating an adjacent trailing excavation groove, the protection plate is pulled out, and then a trailing panel reinforcing bar cage is placed in the trailing excavation groove so that the transverse reinforcement at the longitudinal end of the groove is aligned with the preceding panel reinforcing bar. A method of constructing an underground continuous wall, which is characterized by placing concrete so as to overlap the protruding horizontal bars of a cage.
JP20542983A 1983-11-01 1983-11-01 Execution of underground continuous wall Granted JPS6098010A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP20542983A JPS6098010A (en) 1983-11-01 1983-11-01 Execution of underground continuous wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP20542983A JPS6098010A (en) 1983-11-01 1983-11-01 Execution of underground continuous wall

Publications (2)

Publication Number Publication Date
JPS6098010A JPS6098010A (en) 1985-06-01
JPS6358976B2 true JPS6358976B2 (en) 1988-11-17

Family

ID=16506706

Family Applications (1)

Application Number Title Priority Date Filing Date
JP20542983A Granted JPS6098010A (en) 1983-11-01 1983-11-01 Execution of underground continuous wall

Country Status (1)

Country Link
JP (1) JPS6098010A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0349772U (en) * 1989-09-22 1991-05-15

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0393032A4 (en) * 1987-06-12 1991-05-08 Foundation Technology (Aust) Pty. Ltd. Reinforcement for continuously-cast concrete walls
KR102240488B1 (en) * 2020-08-10 2021-04-16 우창래 Connecting box for underground continuous wall and construction method using them same

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5420049B2 (en) * 1972-06-10 1979-07-19
JPS5231650B2 (en) * 1972-08-15 1977-08-16

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0349772U (en) * 1989-09-22 1991-05-15

Also Published As

Publication number Publication date
JPS6098010A (en) 1985-06-01

Similar Documents

Publication Publication Date Title
US5547316A (en) Prefabricated members of sectional monolithic wall in ground, design of wall built up of said members, and method for erection of said wall
JP7454113B2 (en) Steel sheet pile connection structure and steel sheet pile connection method
KR101567742B1 (en) PHC pile and construction method of underground structure using the same
JPS6358976B2 (en)
KR100779608B1 (en) Precast concrete block for retaining wall
KR20220065461A (en) WIRE STRUCTURE FOR STAGGERED LAPPING IN SLURRY WALL, SLURRY WALL and CONSTRUCTION METHOD FOR THE SAME
JPS5988533A (en) Coupling steel member of underground continuous wall
JPH084033A (en) Construction method of the pressure barrier against the outer perimeter of the building
JP2792554B2 (en) Installation method of caisson for breakwater
JP2004360241A (en) Construction method of steel underground diaphragm wall
JP3002697B2 (en) External waterproof sheet laying method for continuous underground wall
JP3082054B2 (en) Large-scale, deep steel continuous basement wall and method of constructing the same
JPH0786226B2 (en) Steel sheet pile joint structure
JP4537795B2 (en) How to build a box culvert
JP2003171928A (en) Synthetic underground wall and method of constructing the same
JPH10195866A (en) Underground diaphragm wall
JP7551456B2 (en) How to build an earth retaining structure
JPH07896B2 (en) Construction method for underground wall
JPH06180006A (en) Water area structure and construction thereof
JPH07127051A (en) Structure of rebar cage for continuous underground wall construction and its construction method
JP2002081056A (en) Steel pipe sheet pile wall construction method
JPH11124846A (en) Construction method of underground continuous wall and underground continuous wall
JPH11324557A (en) How to build a shaft
JPH081063B2 (en) Underground continuous wall construction method and underground continuous wall construction formwork
JPS6012491B2 (en) Continuous underground wall construction method