Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPH02104832A - Joint construction of precast pre-stressed steel frame reinforced concrete beam - Google Patents
[go: Go Back, main page]

JPH02104832A - Joint construction of precast pre-stressed steel frame reinforced concrete beam - Google Patents

Joint construction of precast pre-stressed steel frame reinforced concrete beam

Info

Publication number
JPH02104832A
JPH02104832A JP25596188A JP25596188A JPH02104832A JP H02104832 A JPH02104832 A JP H02104832A JP 25596188 A JP25596188 A JP 25596188A JP 25596188 A JP25596188 A JP 25596188A JP H02104832 A JPH02104832 A JP H02104832A
Authority
JP
Japan
Prior art keywords
steel frame
reinforced concrete
joint
column
concrete beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP25596188A
Other languages
Japanese (ja)
Other versions
JPH07116756B2 (en
Inventor
Munehito Abe
阿部 宗人
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PS Concrete Co Ltd
Original Assignee
PS Concrete Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PS Concrete Co Ltd filed Critical PS Concrete Co Ltd
Priority to JP25596188A priority Critical patent/JPH07116756B2/en
Publication of JPH02104832A publication Critical patent/JPH02104832A/en
Publication of JPH07116756B2 publication Critical patent/JPH07116756B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

PURPOSE:To rationalize a joint construction of beams dynamically and, at the same time, to enable construction work by providing anchoring hardwares to the upper and lower edges of a steel frame buried to a PC beam and arranging PC steels between the anchoring hardwares. CONSTITUTION:In a joint section of a PC beam, anchorages 10, 10, 12 and 12 are respectively mounted to the upper and lower edges of a beam steel frame 3 buried to the beam 1. After that, PC steels 11 and 11 are arranged, one end of each of them is anchored to each of the anchorages 10, 10, 12 and 12, and the other end is anchored to each of the anchorages 10, 10, 12 and 12 of the opposite or next beam 1 after passing through a column 2. According to the constitution, the PC steels 11 and 11 can be functioned rationally in the upper and lower edges of the beam 1 in which the maximum tensile force or the maximum compressive force against bending load occurs.

Description

【発明の詳細な説明】 〔産業上のf:I用分野〕 本発明は、プレキャストプレストレスト鉄骨鉄筋コンク
リート梁の仕口構造に関する。
DETAILED DESCRIPTION OF THE INVENTION [Industrial f:I field] The present invention relates to a joint structure of a precast prestressed steel reinforced concrete beam.

[従来の技術] プレキャストプレストレスト鉄骨鉄筋コンクリート梁の
仕口III造は従来、第2図に示すように、鉄骨3を含
む梁1と柱とを結合するPC鋼材11を梁の側部に設け
、このPC鋼材11によって梁と柱とを緊張して剛結し
ていた。
[Prior Art] Conventionally, in the Shiguchi III construction of precast prestressed steel reinforced concrete beams, as shown in Fig. 2, PC steel members 11 are provided on the side of the beam to connect the beam 1 including the steel frame 3 and the column. The beam and column were rigidly connected with tension using PC steel material 11.

近時、梁にプレキャスト合成スラブを載置してスラブを
施工する工法が発達し、これに伴って、梁l内の鉄骨3
の上辺フランジを露出させた梁を用い、合成スラブ施工
時にこの鉄骨3の上辺フランジをコンクリート中に埋込
むプレストレスト鉄骨鉄筋コンクリート梁が現出してい
る7〔発明が解決しようとする課題] 本発明は、上記のようなプレキャストプレストレスト鉄
骨鉄筋コンクリート梁の仕口部構造において、従来の仕
口部とは異なった結合構造を創出し、施工が容易である
と共に力学的に合理的な構造を提供するものである。
Recently, a method of constructing a slab by placing a precast composite slab on a beam has developed, and with this, the steel frame 3 inside the beam
A prestressed steel-frame reinforced concrete beam has emerged in which a beam with an exposed top flange is used and the top flange of the steel frame 3 is embedded in concrete during construction of a composite slab.7 [Problems to be Solved by the Invention] The present invention In the joint structure of precast prestressed steel reinforced concrete beams as described above, we create a joint structure different from conventional joints, and provide a mechanically rational structure that is easy to construct. .

〔課題を解決するための手段] 本発明は、プレキャストプレストレスト鉄骨鉄筋コンク
リート梁の仕口部で梁に埋込まれた鉄骨の上縁および下
縁にそれぞれ定着金物を取付け。
[Means for Solving the Problems] The present invention attaches fixing hardware to the upper and lower edges of the steel frame embedded in the beam at the joint part of a precast prestressed steel reinforced concrete beam.

この定着金物にそれぞれ一端を定着すると共に、柱を通
過して柱の対面側または次の梁の定着部に他端を定着す
るPC鋼材を配設したことを特徴とするプレキャストプ
レストレスト鉄骨鉄筋コンクリート梁の仕口構造である
A precast prestressed steel reinforced concrete beam characterized by having one end fixed to each of the fixing hardware, and a PC steel material passing through the column and fixing the other end to the opposite side of the column or the fixing part of the next beam. It has a Shiguchi structure.

r作用] 梁に曲げ荷重が作用した場合に、梁断面の上縁および下
縁に最大引張(または圧縮)力が生ずる。従って、仕口
部を緊結するPC鋼材は梁の中立軸から最も遠い位置に
設けるのが合理的である。
r action] When a bending load is applied to a beam, maximum tensile (or compressive) force is generated at the upper and lower edges of the beam cross section. Therefore, it is reasonable to provide the PC steel material that connects the joint at the farthest position from the neutral axis of the beam.

しかるに従来の梁の構造では、仕口のPC鋼材を梁断面
の土下縁近くに設けることは、構造を複雑化し、施工も
容易でなかった0本発明はこれを改斗したもので合成ス
ラブ構造の出現とも相俟ってυ学的にも合理的で施工上
も極めて容易な構造となった。
However, in the conventional beam structure, installing the PC steel material for the joint near the bottom edge of the beam cross section complicates the structure and is not easy to construct. Coupled with the advent of this new structure, it has become a structure that is logically logical and extremely easy to construct.

〔実施例] 第1図は本発明の実施例の仕口部構造を示すもので、(
a)は平面断面図、(b)は側面断面図、(C)は正面
断面図である。プレキャストプレストレスト鉄骨鉄筋コ
ンクリート梁1の仕口部は、目板4で鉄骨3を柱2の鉄
骨5と接合する接合部と、鉄骨3の上縁に設けた定着部
IOと、鉄骨3の下縁に設けた定着部lOとを有してい
る。
[Example] Figure 1 shows the structure of the joint part of an example of the present invention.
(a) is a plan sectional view, (b) is a side sectional view, and (C) is a front sectional view. The joint part of the precast prestressed steel reinforced concrete beam 1 includes a joint part where the steel frame 3 is connected to the steel frame 5 of the column 2 with the batten 4, an anchor part IO provided at the upper edge of the steel frame 3, and a joint part at the lower edge of the steel frame 3. It has a fixing section lO provided therein.

この定着部1O1lOにそれぞれ一端を定着したPC鋼
材11.11は、それぞれその他端を、柱2の鉄骨5の
反対側の面に定着板12によって定着して構成されてい
る。
The PC steel materials 11.11 each have one end fixed to the fixing portion 1O11O, and the other end thereof is fixed to the opposite side of the steel frame 5 of the column 2 by a fixing plate 12.

この仕口部の施工手順は次の通りである。The construction procedure for this joint section is as follows.

梁lを吊上げ、仕口部の鉄骨3を目板4を用いて柱2の
鉄骨5と結合する。次に柱2を通過してPC鋼材11.
liを挿通し、その先端を梁lの定着部1O110に係
止する。
The beam 1 is lifted, and the steel frame 3 of the joint part is connected to the steel frame 5 of the column 2 using battens 4. Next, it passes through the pillar 2 and the PC steel material 11.
li is inserted, and its tip is locked to the fixing portion 1O110 of the beam l.

次に合成スラブ15を梁1の上に載置し、梁仕口部のコ
ンクリートおよびスラブの上部コンクリート14を打設
し、硬化した後ジヤツキを用いてPC鋼材11を緊張す
る。
Next, the composite slab 15 is placed on the beam 1, and the concrete at the beam joint and the upper concrete 14 of the slab are poured, and after hardening, the PC steel material 11 is tensioned using jacks.

次いで各定着部のコンクリート切欠部を後埋めコンクリ
ート13で埋め、躯体工事を完了する。
Next, the concrete cutout portions of each anchoring portion are filled with post-filling concrete 13, and the frame work is completed.

柱2が中間柱である場合は、柱を挟む梁lをそれぞれ別
々に柱に定着してもよく、また柱2を挟んで両側の梁1
のそれぞれの定着部相互間にPC鋼材11を定着する構
造としても良い、この場合、PC鋼材11に緊張力を付
与する時のジヤツキの反力を支持する支持部を一方の梁
lに予めセットしておけば良い。
If the column 2 is an intermediate column, the beams 1 sandwiching the column may be fixed to the column separately, or the beams 1 on both sides of the column 2 may be fixed to the column separately.
It is also possible to have a structure in which the PC steel material 11 is fixed between the respective fixing parts of the PC steel material 11. In this case, a support part that supports the reaction force of jacking when tension is applied to the PC steel material 11 is set in advance on one of the beams l. You should do it.

〔発明の効果J 本発明のプレキャストプレストレスト鉄骨鉄筋コンクリ
ート梁の仕口構造は力学的に合理的で施工が容易であり
、合成スラブの採用とも相まって、建築工事の合理化に
寄与する。
[Effect of the Invention J The joint structure of the precast prestressed steel reinforced concrete beam of the present invention is mechanically rational and easy to construct, and together with the use of synthetic slabs, it contributes to the rationalization of construction work.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明のプレキャストプレストレスト鉄骨鉄筋
コンクリート梁の仕口構造の仕口部を示すもので、(a
)は側面断面図、(b)は平面図、(C)は正面断面図
、第2図は従来の仕口部の正面図である。 ■・・・pc梁      2・・・柱3・・・梁の鉄
骨     4・・・目板5・・・柱の鉄骨     
IO・・・定着部11・−・pc鋼材    12一定
着部13・・・後埋めコンクリート 14・・・上部コンクリート
Figure 1 shows the joint part of the joint structure of the precast prestressed steel reinforced concrete beam of the present invention, (a
) is a side sectional view, (b) is a plan view, (C) is a front sectional view, and FIG. 2 is a front view of a conventional joint section. ■... PC beam 2... Column 3... Steel frame of beam 4... Batten 5... Steel frame of column
IO... Anchoring part 11... PC steel material 12 Fixed part 13... Post-filling concrete 14... Upper concrete

Claims (1)

【特許請求の範囲】[Claims] 1 プレキャストプレストレスト鉄骨鉄筋コンクリート
梁の仕口部で梁に埋込まれた鉄骨の上縁および下縁にそ
れぞれ定着金物を取付け、該定着金物にそれぞれ一端を
定着し柱を通過して柱の対面側または次の梁の定着部に
他端を定着するPC鋼材を配設したことを特徴とするプ
レキャストプレストレスト鉄骨鉄筋コンクリート梁の仕
口構造。
1. At the joint part of a precast prestressed steel reinforced concrete beam, fixing hardware is attached to the upper and lower edges of the steel frame embedded in the beam, and one end of each is fixed to the fixing hardware, passing through the column, and A joint structure of a precast prestressed steel reinforced concrete beam, characterized in that a prestressed steel reinforced concrete beam is provided with a PC steel material that fixes the other end to the anchoring part of the next beam.
JP25596188A 1988-10-13 1988-10-13 Precast prestressed steel reinforced concrete beam columns Beam connection Expired - Lifetime JPH07116756B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP25596188A JPH07116756B2 (en) 1988-10-13 1988-10-13 Precast prestressed steel reinforced concrete beam columns Beam connection

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP25596188A JPH07116756B2 (en) 1988-10-13 1988-10-13 Precast prestressed steel reinforced concrete beam columns Beam connection

Publications (2)

Publication Number Publication Date
JPH02104832A true JPH02104832A (en) 1990-04-17
JPH07116756B2 JPH07116756B2 (en) 1995-12-13

Family

ID=17285981

Family Applications (1)

Application Number Title Priority Date Filing Date
JP25596188A Expired - Lifetime JPH07116756B2 (en) 1988-10-13 1988-10-13 Precast prestressed steel reinforced concrete beam columns Beam connection

Country Status (1)

Country Link
JP (1) JPH07116756B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4889506B2 (en) * 2004-01-29 2012-03-07 イー・アイ・デュポン・ドウ・ヌムール・アンド・カンパニー Bulk transportation system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4889506B2 (en) * 2004-01-29 2012-03-07 イー・アイ・デュポン・ドウ・ヌムール・アンド・カンパニー Bulk transportation system

Also Published As

Publication number Publication date
JPH07116756B2 (en) 1995-12-13

Similar Documents

Publication Publication Date Title
US5299445A (en) Method of post-tensioning steel/concrete truss before installation
JP2927402B2 (en) Column-beam joint structure of concrete building
JPS6145042A (en) Mold frame for casting concrete
CA2114263A1 (en) Method of post-tensioning steel/concrete truss before installation
JPH02104832A (en) Joint construction of precast pre-stressed steel frame reinforced concrete beam
JPH0790933A (en) Construction method of structure
JPH08144425A (en) Prefabricated member of mixed structure and construction method of mixed structure
JP3586121B2 (en) Mixed structure of reinforced concrete column and steel beam and its construction method
JPH01137034A (en) Structure of composite building structure
JPH0586643A (en) Part and technique for jointing precast pc reinforced concrete structure
JPH0414567A (en) Laminated construction method for buildings
JPH0749681B2 (en) Steel frame / reinforced concrete composite construction method
JPH0478771B2 (en)
JPH0765368B2 (en) Precast concrete half flat slab
JP2813816B2 (en) Lift-up method using synthetic steel beams
JPH0732642Y2 (en) Beam-column joint structure
JP2001123675A (en) Building temporary receiving jig and temporary receiving structure
JPH03187436A (en) Supporting member for construction pillar of reinforced concrete building
JP3189081B2 (en) Manufacturing method of void type full precast two-way slab and void type full precast slab
JPH01121424A (en) Pc frame device for multistoried building
JPH0621476B2 (en) Structure of complex building structure
JPH0681470A (en) Construction method for flat slab
JPH01158146A (en) Method of torus-reinforced thin precast floor board driving formwork construction
JP2548597B2 (en) Joint structure of flat plate and true column
JPH0533388A (en) Joining section of precast reinforced concrete construction