JPH0213695B2 - - Google Patents
Info
- Publication number
- JPH0213695B2 JPH0213695B2 JP58072137A JP7213783A JPH0213695B2 JP H0213695 B2 JPH0213695 B2 JP H0213695B2 JP 58072137 A JP58072137 A JP 58072137A JP 7213783 A JP7213783 A JP 7213783A JP H0213695 B2 JPH0213695 B2 JP H0213695B2
- Authority
- JP
- Japan
- Prior art keywords
- column
- reinforcement
- main reinforcement
- head
- beams
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Joining Of Building Structures In Genera (AREA)
- Rod-Shaped Construction Members (AREA)
Description
【発明の詳細な説明】
本発明はプレキヤスト鉄筋コンクリート軸組構
造における柱、梁接合方法に係るものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for joining columns and beams in a precast reinforced concrete framework structure.
従来のプレキヤスト鉄筋コンクリート軸組構造
における柱、梁の接合においては、架設時の安全
性を考慮すると、PC梁のPC柱における柱頭部に
対するかかり長さが4〜5cm以上必要となる。 When connecting columns and beams in a conventional precast reinforced concrete frame structure, considering safety during construction, the length of the PC beam over the column head of the PC column must be 4 to 5 cm or more.
しかしながらこのかかり長を大きくすると、
PC柱の柱頭部より突出した柱主筋に対する帯筋
の配筋が困難になるので、第1図及び第2図に示
すように、PC柱1の頂部に梁受け用の顎2を設
け、同顎2上にPC梁3をセツトし、柱頭部にお
けるPC柱、梁間に形成された接合空間内に接合
コンクリート4を打設していた。 However, if this length is increased,
Since it becomes difficult to place tie bars on the column main reinforcement that protrudes from the column head of the PC column, as shown in Figures 1 and 2, a jaw 2 for beam support is provided at the top of the PC column 1. A PC beam 3 was set on the jaw 2, and joint concrete 4 was placed in the joint space formed between the PC column and the beam at the column head.
前記のようにPC柱1の頂部に顎2を設ける従
来工法においては、同顎2が意匠上の障害とな
り、またPC梁3の長手方向端面には後打ちコン
クリートとの一体性を保持し、剪断力に抵抗でき
るようにコツター5を設ける必要があつた。 As mentioned above, in the conventional construction method in which the jaw 2 is provided at the top of the PC column 1, the jaw 2 becomes an obstacle to the design. It was necessary to provide the cotter 5 to resist shearing forces.
図中6は柱主筋、7は柱帯筋、8は梁上端筋、
9は肋筋である。 In the figure, 6 is the main column reinforcement, 7 is the column reinforcement, 8 is the beam top reinforcement,
9 is a rib muscle.
本発明は前記従来工法の欠点を除去するために
提案されたもので、梁の長手方向端部に、梁幅全
長に亘つて梁成方向に延びる垂直切欠き部が設け
られ、同切欠き部の下端に隣接して下端突出部片
が突設されたPC梁における同下端突出部片を、
PC柱の柱頭部における同部より突出する柱主筋
のかぶり部分に載架し、前記PC柱、梁間に形成
された接合空間内において、前記柱主筋の柱頭突
出部間に帯筋を配筋したのち、前記接合空間内に
コンクリートを打設することを特徴とするプレキ
ヤスト鉄筋コンクリート軸組構造の柱、梁接合方
法に係るものである。 The present invention has been proposed in order to eliminate the drawbacks of the conventional construction method, and is provided with a vertical notch extending in the beam growth direction over the entire width of the beam at the longitudinal end of the beam. The lower end protruding piece of the PC beam has the lower end protruding piece protruding adjacent to the lower end of the PC beam.
The reinforcement was placed on the covering part of the column main reinforcement that protruded from the same part of the column head of the PC column, and the band reinforcement was arranged between the column head protruding parts of the column main reinforcement within the joint space formed between the PC column and the beam. The present invention relates to a method for joining columns and beams of a precast reinforced concrete frame structure, which is characterized in that concrete is then poured into the joining space.
本発明によれば前記したように、梁の長手方向
端部に、梁幅全長に亘つて梁成方向に延びる垂直
切欠き部を設け、同切欠き部の下端に隣接して下
端突出部片が突設されたPC梁を構成し、同PC梁
における前記下端突出部片を、PC柱の柱頭部に
おける同部より突設された柱主筋のかぶり部分に
載架し、前記柱頭部におけるPC柱、梁間に形成
された空間に接合コンクリートを打設して、同
PC柱、梁を接合するようにしたものである。 According to the present invention, as described above, a vertical notch extending in the beam growth direction over the entire width of the beam is provided at the longitudinal end of the beam, and a lower end protruding piece is provided adjacent to the lower end of the notch. constitutes a PC beam with a protruding structure, and the lower end protruding piece of the PC beam is mounted on the covering part of the column main reinforcement that protrudes from the same part of the column head of the PC column, and the PC beam in the column head is Place joint concrete in the space formed between columns and beams, and
It is designed to connect PC columns and beams.
従つて本発明によれば、PC柱、梁の接合に際
して、PC柱の柱頭にPC梁受け用の顎を設ける必
要がなくなり、また前記PC梁の長手方向端部に
設けられた、梁幅全長に亘つて梁成方向に延びる
垂直切欠き部の存在によつて、PC柱の柱主筋に
接する位置でPC梁をセツトしても、柱頭部にお
けるPC柱、梁接合空間内における剪断補強用帯
筋の配筋作業が容易に行なわれる。 Therefore, according to the present invention, when joining a PC column and a beam, there is no need to provide a jaw for receiving the PC beam on the capital of the PC column, and the total beam width provided at the longitudinal end of the PC beam is eliminated. Due to the existence of a vertical notch that extends in the beam formation direction, even if the PC beam is set at a position where it touches the column main reinforcement of the PC column, the shear reinforcing band in the PC column at the column head and the beam joint space will be damaged. Reinforcement work can be done easily.
更に前記PC梁の長手方向端部において、前記
垂直切欠き部に隣接する下端突出部片がコツター
の用を兼ねるので、従来のようにPC梁の長手方
向端面にコツターを設ける必要がなくなる。 Further, at the longitudinal end of the PC beam, the lower end protruding piece adjacent to the vertical notch also serves as a cotter, so there is no need to provide a cotter on the longitudinal end face of the PC beam as in the conventional case.
以下本発明を図示の実施例について説明する。 The present invention will be described below with reference to the illustrated embodiments.
AはPC梁を示し、同梁の長手方向端部に、梁
幅全長に亘つて梁成方向に延びる垂直切欠き部1
1が設けられ、同切欠き部11の下端に隣接して
下端突出部片12が突設され、同突出部片12か
らは梁下端主筋13の端部が突設されるととも
に、同突出部片12の先端両側部にL型補強金物
14が碇着されている。 A indicates a PC beam, and there is a vertical notch 1 at the longitudinal end of the beam that extends in the beam growth direction over the entire width of the beam.
1 is provided, a lower end protruding piece 12 is protruded adjacent to the lower end of the notch 11, and the end of the beam lower end main reinforcement 13 is protruded from the protruding piece 12. L-shaped reinforcing hardware 14 is anchored on both sides of the tip of the piece 12.
なお前記PC梁Aの上端面は略々スラブ厚に等
しく欠截され、同欠截部上に肋筋15の上端が突
出している。 Note that the upper end surface of the PC beam A is cut out approximately equal to the thickness of the slab, and the upper end of the rib 15 protrudes above the cutout.
而して前記PC梁Aの下端突出部片12を柱主
筋16が突出するPC柱Bの柱頭部における同柱
主筋16のかぶり部分にセツトし、同柱頭部にお
けるPC柱、梁A,Bの接合空間内において、柱
主筋16に柱帯筋17を配筋する。この際前記
PC梁Aの垂直切欠き部11の存在によつて、前
記したようにPC柱Bにおける柱主筋16に接す
る位置にPC梁Aをセツトしても、前記柱梁接合
空間内における柱帯筋17の配筋作業が容易に行
なわれる。 Then, the lower end protruding piece 12 of the PC beam A is set in the covering part of the main reinforcement 16 of the PC column B at the head of the PC column B from which the main reinforcement 16 of the column protrudes, and In the joint space, the column reinforcements 17 are arranged on the column main reinforcements 16. At this time, the above
Due to the existence of the vertical notch 11 in the PC beam A, even if the PC beam A is set at a position in contact with the main column reinforcement 16 in the PC column B as described above, the column reinforcement 17 in the column-beam joint space Reinforcement work can be done easily.
なお前記PC梁Aの補強金物14をPC柱Bの柱
頭に埋設された金物に溶接して、仮設時の安全性
を図るものである。 The reinforcing hardware 14 of the PC beam A is welded to the hardware buried in the capital of the PC column B to ensure safety during temporary construction.
更にPC梁Aの肋筋15上端突出部と柱、梁接
合空間の上部に亘つて、梁上端主筋18を通し配
筋し、前記柱、梁接合空間及びPC梁A上部にコ
ンクリート19及び20を打設し、PC柱梁、及
びPC梁Aに端部を載架されたPC床板(図示せ
ず)を一体に接合する。 Furthermore, the main reinforcing bars 18 at the upper end of the beam are passed through the protruding part of the upper end of the reinforcing bars 15 of the PC beam A and the upper part of the column and beam joint space, and concrete 19 and 20 are placed in the column and beam joint space and the upper part of the PC beam A. Then, the PC columns and beams and the PC floorboards (not shown) whose ends are mounted on PC beams A are joined together.
第1図及び第2図は夫々従来のプレキヤスト鉄
筋コンクリート軸組構造の柱、梁接合部を示す縦
断面図並に平面図、第3図及び第4図は夫々本発
明の方法によつて構成されたプレキヤスト鉄筋コ
ンクリート軸組構造の柱、梁接合部を示す縦断面
図並に平面図、第5図はPC梁の斜面図である。
A…PC梁、B…PC柱、11…垂直切欠き部、
12…下端突出部片、16…柱主筋、17…柱帯
筋。
1 and 2 are longitudinal cross-sectional views and plan views showing the column and beam joints of a conventional precast reinforced concrete framework structure, respectively, and FIGS. 3 and 4 are respectively a plan view and a column constructed by the method of the present invention. Figure 5 shows a longitudinal section and a plan view showing the column and beam joints of the precast reinforced concrete frame structure, and Figure 5 is a slope view of the PC beam. A...PC beam, B...PC column, 11...vertical notch,
12... Lower end protruding piece, 16... Column main reinforcement, 17... Column strip reinforcement.
Claims (1)
方向に延びる垂直切欠き部が設けられ、同切欠き
部の下端に隣接して下端突出部片が突設された
PC梁における同下端突出部片を、PC柱の柱頭部
における同部より突出する柱主筋のかぶり部分に
載架し、前記PC柱、梁間に形成された接合空間
内において、前記柱主筋の柱頭突出部間に帯筋を
配筋したのち、前記接合空間内にコンクリートを
打設することを特徴とするプレキヤスト鉄筋コン
クリート軸組構造の柱、梁接合方法。1. A vertical notch extending in the beam growth direction over the entire width of the beam is provided at the longitudinal end of the beam, and a lower end projecting piece is protruded adjacent to the lower end of the notch.
The lower end protruding piece of the PC beam is mounted on the covering part of the column main reinforcement that protrudes from the same part of the column head of the PC column, and the column head of the column main reinforcement is placed in the joint space formed between the PC column and the beam. A method for joining columns and beams in a precast reinforced concrete frame structure, which comprises placing tie bars between protruding parts and then pouring concrete into the joining space.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP7213783A JPS59199936A (en) | 1983-04-26 | 1983-04-26 | Pillar and beam connection of ramen prefabricated house |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP7213783A JPS59199936A (en) | 1983-04-26 | 1983-04-26 | Pillar and beam connection of ramen prefabricated house |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS59199936A JPS59199936A (en) | 1984-11-13 |
| JPH0213695B2 true JPH0213695B2 (en) | 1990-04-05 |
Family
ID=13480595
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP7213783A Granted JPS59199936A (en) | 1983-04-26 | 1983-04-26 | Pillar and beam connection of ramen prefabricated house |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS59199936A (en) |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS544527B2 (en) * | 1973-05-12 | 1979-03-07 | ||
| JPS5145166B2 (en) * | 1973-11-27 | 1976-12-02 |
-
1983
- 1983-04-26 JP JP7213783A patent/JPS59199936A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS59199936A (en) | 1984-11-13 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH0348977B2 (en) | ||
| JP3160777B2 (en) | End joining method and structure of precast concrete beam attached to precast concrete beam | |
| JPH0213695B2 (en) | ||
| JPS6312987B2 (en) | ||
| JPH0123614B2 (en) | ||
| US4020132A (en) | Construction joint for reinforced concrete structures | |
| JPS6126484Y2 (en) | ||
| JP2758208B2 (en) | Joint method between column and steel reinforced concrete beam | |
| JPH01137032A (en) | Method of lap joint construction of main reinforcement in post and beam joining section | |
| JP2729132B2 (en) | How to join columns and precast concrete beams | |
| JPH0746652Y2 (en) | Precast Steel Reinforced Concrete Beam | |
| JP2700740B2 (en) | Prefabricated method using precast beam | |
| JPS5830459B2 (en) | Construction method of precast reinforced concrete structure | |
| JP3284391B2 (en) | Reinforced concrete frame and construction method | |
| JPS6335773B2 (en) | ||
| JPS5925931Y2 (en) | Composite girder using π-shaped steel | |
| JPH079921Y2 (en) | Joint structure between reinforced concrete column and steel beam | |
| JPS5926001Y2 (en) | Precast beam and girder joint structure | |
| JPS6232299B2 (en) | ||
| JPS6262213B2 (en) | ||
| JPH0323703B2 (en) | ||
| JPH0650010B2 (en) | Precast version | |
| JPH0533606Y2 (en) | ||
| JPH0216824B2 (en) | ||
| JP3749935B2 (en) | Column and beam construction method and enclosure |