Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPH0243848B2 - - Google Patents
[go: Go Back, main page]

JPH0243848B2 - - Google Patents

Info

Publication number
JPH0243848B2
JPH0243848B2 JP58006712A JP671283A JPH0243848B2 JP H0243848 B2 JPH0243848 B2 JP H0243848B2 JP 58006712 A JP58006712 A JP 58006712A JP 671283 A JP671283 A JP 671283A JP H0243848 B2 JPH0243848 B2 JP H0243848B2
Authority
JP
Japan
Prior art keywords
footing
underground structure
steel material
construction method
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP58006712A
Other languages
Japanese (ja)
Other versions
JPS59134228A (en
Inventor
Isao Aihara
Toyoyuki Okajima
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP671283A priority Critical patent/JPS59134228A/en
Publication of JPS59134228A publication Critical patent/JPS59134228A/en
Publication of JPH0243848B2 publication Critical patent/JPH0243848B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)
  • Foundations (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【発明の詳細な説明】 この発明は、杭や地中連続壁などの地中構造物
とフーチングとの一体化工法に関し、より具体的
には、プレストレストコンクリート(以下PCと
略称する)用鋼材を埋設した地中構造物とコンク
リートの打設により形成されるフーチングとの一
体化工法に関するものである。
[Detailed Description of the Invention] The present invention relates to a method of integrating footings with underground structures such as piles and underground continuous walls, and more specifically, the present invention relates to a method of integrating footings with underground structures such as piles and underground continuous walls. This relates to a construction method that integrates a buried underground structure with a footing formed by pouring concrete.

従来、例えば予めPC用鋼材を緊張状態でコン
クリート中に埋設し、コンクリート製杭にプレス
トレス力を導入したいわゆるPC杭とフーチング
とを一体化する工法においては、地中に打ち込ん
だPC杭の杭上端をPC鋼材と一緒にカツトオフ
し、地上に杭頭部を若干露出させた状態でフーチ
ングとの接合を行なつていた。
Conventionally, in the construction method of integrating the so-called PC pile and footing, for example, by burying prestressing steel in concrete in a tensioned state and introducing prestress force into the concrete pile, the PC pile is driven into the ground. The upper end was cut off together with the prestressing steel material, and the pile head was slightly exposed above the ground before being joined to the footing.

しかしながら、このように杭上端をカツトオフ
すれば、杭頭部のプレストレスが減少し、フーチ
ングとの接合部近傍はPC杭にならないという問
題点があつた。
However, when the top end of the pile is cut off in this way, the prestress at the pile head is reduced, and the area near the joint with the footing does not become a PC pile.

このため、第1図あるいは第2図に示すよう
な、プレストレストの減少した部分を補強する工
法が提供されている。
For this reason, a method of reinforcing the portion where the prestress has decreased, as shown in FIG. 1 or 2, has been proposed.

すなわち、第1図に示す工法では、PC鋼材1
0とコンクリート12とからなるPC杭14を所
定の深さまで地中16に打ち込み、杭頭部18を
若干地上に突出した状態までカツトオフした後、
該PC杭14の外周に所定の深さの孔部20を掘
削し、この孔部20内に補強用鉄筋22の一部を
挿入した状態で建て込み、孔部20および中埋め
コンクリート部21へのコンクリート打設を行な
つた後、フーチング24をコンクリートで仕上げ
て一体化するものである。
In other words, in the construction method shown in Fig. 1, the PC steel material 1
A PC pile 14 made of 0 and concrete 12 is driven into the ground 16 to a predetermined depth, and the pile head 18 is cut off to a state slightly protruding above the ground.
A hole 20 of a predetermined depth is excavated around the outer periphery of the PC pile 14, and a part of reinforcing reinforcing bar 22 is inserted into this hole 20 and then built into the hole 20 and the filling concrete part 21. After pouring concrete, the footing 24 is finished with concrete and integrated.

また、第2図に示す工法は、PC杭14の打ち
込み、杭頭部18のカツトオフまでの工程は、上
記工法と同様であるが、この後にPC杭14の内
部の孔部20に補強用鉄筋22を一部挿入した状
態で建て込み、中埋めコンクリート部21のコン
クリート打設を行なつた後、フーチング24をコ
ンクリートで仕上げて一体化するものである。
In addition, in the construction method shown in FIG. 2, the steps from driving the PC pile 14 to cutting off the pile head 18 are similar to the construction method described above, but after this, reinforcing reinforcing steel is inserted into the hole 20 inside the PC pile 14. 22 is partially inserted, and after pouring concrete for the intermediate concrete portion 21, the footing 24 is finished with concrete and integrated.

しかしながら、このような工法においては、
PC杭とフーチング24の接合状態は、ある程度
補強されるものの、杭頭部18におけるプレスト
レスの減少分を回復するものではなく、根本的な
問題点の解消はなされていないという問題があつ
た。
However, in this construction method,
Although the joint state between the PC pile and the footing 24 is reinforced to some extent, the reduction in prestress at the pile head 18 is not recovered, and the fundamental problem has not been solved.

また、上述のようにPC杭14の外周部や内部
に孔部20を掘削することや、補強用鉄筋22を
建て込むことは、工期を短縮する上での障害とな
り、コストアツプにもなるという欠点を有するも
のであつた。
In addition, as mentioned above, drilling holes 20 on the outer periphery or inside of the PC pile 14 and erecting reinforcing bars 22 are disadvantageous in that they become an obstacle to shortening the construction period and increase costs. It had the following characteristics.

この発明は、上述したような従来工法の欠点に
着目し、これを解消すべくなされたものであり、
その目的とするところは、補強用の部材や掘削作
業を追加することなく施工できる経済的有利性を
有し、且つPC杭の頭部をカツトオフした場合で
もプレストレスの減少を回復できるとともに、
PC杭や地中連続壁とフーチングとの接合状態を
強化できる地中構造物とフーチングとの一体化工
法を提供するところにある。
This invention was made to focus on the drawbacks of the conventional method as described above and to solve them.
The purpose of this is to have an economical advantage in that it can be constructed without adding reinforcement members or excavation work, and also to be able to recover the decrease in prestress even if the head of the PC pile is cut off.
The purpose of this invention is to provide a construction method for integrating footings with underground structures that can strengthen the connection between PC piles, underground continuous walls, and footings.

上記目的を達成するため、この発明は。プレス
トレストコンクリート用鋼材を埋設したプレスト
レストコンクリート杭、場所打ち杭あるいは地中
連続壁からなる地中構造物とフーチングとを一体
化する工法において、該プレストレストコンクリ
ート用鋼材を該地中構造物の駆体から上方に突出
させ、この突出部分の外周にコンクリートの打設
により該フーチングを形成するとともに、該鋼材
の端部を該フーチングの上端より若干突出させ、
かつ、該鋼材の外周に定着部を形成し、該定着部
内で定着具を用いて該鋼材を緊張せしめることに
よりプレストレス力を導入し、該地中構造物と該
フーチングとを一体化することを特徴とする 以下にこの発明の好適な実施例を添付図面を参
照して説明する。
In order to achieve the above object, this invention has the following features. In a construction method that integrates a footing with an underground structure consisting of prestressed concrete piles, cast-in-place piles, or underground continuous walls in which steel materials for prestressed concrete are buried, the steel materials for prestressed concrete are removed from the base of the underground structure. projecting upward, forming the footing by pouring concrete around the outer periphery of the projecting portion, and making the end of the steel material slightly project from the upper end of the footing;
and by forming an anchoring part on the outer periphery of the steel material, and applying a prestress force by tensioning the steel material using a fixing tool within the anchoring part, thereby integrating the underground structure and the footing. Hereinafter, preferred embodiments of the present invention will be described with reference to the accompanying drawings.

なお、以下の説明においては、上記した従来の
施工法と同一若しくは相当する部分については、
同一符号を付すものである。
In the following explanation, parts that are the same as or equivalent to the conventional construction method described above will be referred to as
The same reference numerals are given.

第3図から第6図は、この発明に係る地中構造
物とフーチングとの一体化工法の一実施例を示す
ものである。
3 to 6 show an embodiment of the method of integrating an underground structure and a footing according to the present invention.

同図に示す一体化工法は、地中構造物としての
PC杭14と、フーチング24との一体化につい
て適用した場合を示すものでる。
The integrated construction method shown in the figure is suitable for underground structures.
This figure shows a case in which the PC pile 14 and the footing 24 are integrated.

一体化工法では、先ずPC用鋼材10を複数本
コンクリート12中に緊張した状態で埋設した
PC杭14が、所定の深さまで地中16に打ち込
まれる。
In the integrated construction method, first, multiple pieces of PC steel 10 were buried under tension in concrete 12.
A PC pile 14 is driven into the ground 16 to a predetermined depth.

このとき、地上に露出したPC杭14の上端部
26をカツトオフし、杭頭部18を若干地上に突
出した状態となすことは、従来工法と同様である
(第3図、第4図参照)。
At this time, the upper end 26 of the PC pile 14 exposed above the ground is cut off to leave the pile head 18 slightly protruding above the ground, which is the same as in the conventional construction method (see Figures 3 and 4). .

そして、同図に示すフーチング24とPC杭1
4との一体化工法においては、上述した従来工法
に対し以下に述べるような特徴点を有するもので
ある。
Then, the footing 24 and PC pile 1 shown in the same figure
The integrated construction method with 4 has the following features compared to the conventional construction method described above.

すなわち、上記PC杭14の躯体の上端部26
をカツトオフする際に、上記PC用鋼材10は、
カツトしないで、第4図に示すようにそのまま突
出部分28として残しておき、この部分の外周に
コンクリートを打設してフーチング24を形成す
る。
That is, the upper end 26 of the frame of the PC pile 14
When cutting off the steel material 10 for PC,
Without cutting, the protruding portion 28 is left as it is as shown in FIG. 4, and concrete is poured around the outer periphery of this portion to form the footing 24.

この場合、形成されたフーチング24の上端面
から前記突出部分28の先端がが突出するように
し、突出部分28の外周に凹状の定着部30を形
成する(第5図参照)。
In this case, the tip of the protruding portion 28 is made to protrude from the upper end surface of the formed footing 24, and a concave fixing portion 30 is formed on the outer periphery of the protruding portion 28 (see FIG. 5).

なお、このとき、予め上記PC用鋼材10の突
出部分28の先端側に、後述する定着具32と合
致する、ネジを周設した状態でコンクリート12
内に埋設しておけば、定着作業が容易になる。
In addition, at this time, the concrete 12 is placed in a state in which a screw is previously installed around the tip side of the protruding portion 28 of the steel material 10 for PC, which matches the fixing device 32 described later.
If it is buried inside, the fixing work will be easier.

また、前もつて形成すべきフーチング24の厚
み、PC杭14の地中16への埋設長および突出
させる杭頭部18長等を計算し、PC杭14の上
端に所定の長さだけPC用鋼材10の突出部分2
8を形成した状態で施工することも可能であり、
このようにすれば上述したカツトオフ作業も不要
となり、経済的にも有利となる。
In addition, the thickness of the footing 24 to be formed in advance, the length of the PC pile 14 buried in the ground 16, the length of the pile head 18 to be protruded, etc. are calculated, and a predetermined length of the PC pile is placed on the upper end of the PC pile 14. Projecting portion 2 of steel material 10
It is also possible to perform construction with 8 formed.
This eliminates the need for the above-mentioned cut-off operation, which is also economically advantageous.

この後に、上記定着部30内に定着具32を挿
入し、上記PC用鋼材10を緊張することで、杭
頭部18とフーチング24との間にプレストレス
力を導入して、PC杭14とフーチング24とを
一体化する(第6図参照)。
After this, the fixing tool 32 is inserted into the fixing section 30 and the prestressing steel material 10 is tensed, thereby introducing a prestress force between the pile head 18 and the footing 24, and thereby tightening the PC pile 14. The footing 24 is integrated with the footing 24 (see FIG. 6).

このPC用鋼材10に緊張力を導入するに当た
つては、上記フーチング24の打設コンクリート
が完全に固化する前に行なうことも可能であり、
要すれば、上記突出部分28に、鋼管製等のシー
スを被せておき、打設コンクリートの固化後にお
いて行なうこともまた可能である。
Introducing tension force into the PC steel material 10 can be done before the concrete placed in the footing 24 is completely solidified.
If necessary, it is also possible to cover the protruding portion 28 with a sheath made of steel pipe or the like and carry out the process after the poured concrete has solidified.

さて、上記のような構成でフーチング24と
PC杭14を一体化する工法においては、上述し
た従来工法のようにPC杭14の上端部26をカ
ツトオフして杭頭部18のプレストレスが減少し
ても、再びPC用鋼材10を緊張することでプレ
ストレスの回復がなされるとともに、PC杭14
とフーチング24の接合部にもプレストレスが導
入された状態で接合されるため、従来の補強用鉄
筋22よりもはるかに強固に接合され、カツトオ
フに伴う問題点は根本的に解消することができ
る。
Now, with the above configuration, the footing 24 and
In the construction method of integrating the PC pile 14, even if the prestress of the pile head 18 is reduced by cutting off the upper end 26 of the PC pile 14 as in the conventional construction method described above, the PC steel material 10 is not tensed again. As a result, the prestress is recovered and the PC pile 14
Since prestress is introduced into the joint between the footing 24 and the footing 24, the joint is much stronger than the conventional reinforcing reinforcing bar 22, and the problems associated with cut-off can be fundamentally solved. .

また、上述したような作用効果を発揮させるた
めの構成は、定着部30の形成、および定着具3
2の追加等比較的簡単なものであり、工期の短
縮、コストダウン等の経済的有利さをも有するも
のである。
Further, the configuration for exhibiting the above-mentioned effects includes the formation of the fixing section 30 and the fixing tool 3.
The addition of 2 is relatively simple, and it also has economic advantages such as shortening the construction period and reducing costs.

第7図はこの発明の第2実施例を示すものであ
り、その特徴点についてのみ説明すると、上記第
1の実施例が、PC杭14の上端部26をカツト
オフすることで予め埋設されていたPC杭14の
上部側を露出させて突出部分28としたのに対
し、この実施例では、上記PC鋼材10の外周に、
一端がデツドアンカー部36として埋設された、
比較的短尺な連結PC用鋼材33を、その他端側
が上記突出部28となるように設けたところにあ
る。
FIG. 7 shows a second embodiment of the present invention, and to explain only its features, it is different from the first embodiment in that it is buried in advance by cutting off the upper end 26 of the PC pile 14. Whereas the upper side of the PC pile 14 is exposed to form the protruding portion 28, in this embodiment, the outer periphery of the PC steel material 10 is
One end is buried as a dead anchor part 36,
A relatively short steel material 33 for connecting PC is provided so that the other end thereof becomes the protrusion 28 .

このような構成のPC杭においても、これを地
中16に、その杭頭部18が若干露出した状態ま
で打ち込み、その上部にフーチング24を形成
し、連結PC用鋼材33に定着具32を用いて緊
張しプレストレスを導入することで、上述した作
用効果を奏することができる。
Even in the case of a PC pile with such a configuration, it is driven into the ground 16 until the pile head 18 is slightly exposed, a footing 24 is formed on the top, and a fixing device 32 is used for the connecting PC steel material 33. By applying pre-stress by applying tension, the above-mentioned effects can be achieved.

第8図は、この発明の第3実施例を示すもので
あり、その特徴点についてのみ説明すると、上記
第1および第2の実施例がいずれも既存のPC杭
14を地中16に打ち込み地中構造物とするもの
であつたのに対し、この実施例では、地中構造物
は構築現場で縦孔を掘削し、この縦孔内にコンク
リートを打設して形成するいわゆる場所打ち杭3
4に適用したものである。
FIG. 8 shows a third embodiment of the present invention. To explain only its features, both the first and second embodiments are constructed by driving an existing PC pile 14 into the ground 16. In this embodiment, the underground structure is a so-called cast-in-place pile 3, which is formed by excavating a vertical hole at the construction site and pouring concrete into the vertical hole.
This is applied to 4.

同図に示すように、この実施例においては、場
所打ち杭34に埋設されるPC用鋼材10は、杭
頭部18から予め突出した状態で配置しておき、
この突出させた部分が上記突出部分28となり、
その他の点は上記第1の実施例と同様な工程でフ
ーチング部24との一体化がなされる。
As shown in the figure, in this embodiment, the prestressing steel material 10 to be buried in the cast-in-place pile 34 is placed in advance so as to protrude from the pile head 18.
This protruding portion becomes the protruding portion 28,
In other respects, integration with the footing portion 24 is performed in the same steps as in the first embodiment.

また第9図は、この発明の第4実施例を示すも
のである。
Further, FIG. 9 shows a fourth embodiment of the present invention.

同図に示す一体化工法は、フーチング24と地
中構造物としての地中連続壁35とを一体化する
場合について適用したものであり、その特徴とす
る点についてのみ説明すると、地中連続壁35内
に予め埋設されているPC用鋼材10は、その下
端部がデツドアンカー部36として埋め殺した状
態になつている。
The integration method shown in the figure is applied to the case of integrating the footing 24 and an underground continuous wall 35 as an underground structure. The lower end of the PC steel material 10 that has been buried in advance in the 35 is in a state where it is buried as a dead anchor part 36.

このように予めPC用鋼材10の下端部をデツ
ドアンカー部36とした場合においても、上述し
た実施例で説明した作用効果を発揮し得ることは
いうまでもない。
It goes without saying that even in the case where the lower end portion of the PC steel material 10 is made into the dead anchor portion 36 in advance, the effects described in the above-mentioned embodiments can be exhibited.

以上のように、この発明にかかる地中構造物と
フーチングとの一体化工法によれば、PC杭のカ
ツトオフに伴うプレストレスの減少を回復できる
とともに、地中構造物とフーチングの接合とを強
固にならしめることができる。
As described above, according to the method of integrating an underground structure and a footing according to the present invention, it is possible to recover from the decrease in prestress caused by cut-off of a PC pile, and also to strengthen the connection between the underground structure and the footing. can be made to become

【図面の簡単な説明】[Brief explanation of the drawing]

第1図および第2図は、従来工法により形成さ
れたプレストレストコンクリート杭とフーチング
とを示すそれぞれの断面図である。第3図から第
6図は、この発明に係る地中構造物とフーチング
との一体化工法の第1−実施例を工程順に示す各
工程の断面図であり、施工は順次第3図から第6
図の順に行なわれる。第7図はこの発明の第2実
施例を示すもので、同図aは断面図、同図bは杭
の上面図である。第8図は、この発明を場所打ち
杭とフーチングとの一体化に適用した第3実施例
を示す断面図である。第9図は、この発明を地中
連続壁とのフーチングの一体化に適用した第4実
施例を示す断面図である。 10……PC用鋼材、12……コンクリート、
14……PC杭、16……地中、18……杭頭部、
20……孔部、22……補強用鉄筋、24……フ
ーチング、26……上端部、28……突出部分、
30……定着部、32……定着具、35……地中
連続壁、36……デツドアンカー部。
FIG. 1 and FIG. 2 are cross-sectional views showing a prestressed concrete pile and a footing formed by a conventional method. Figures 3 to 6 are cross-sectional views showing each step of the first embodiment of the method for integrating an underground structure and footing according to the present invention in order. 6
This is done in the order shown. Fig. 7 shows a second embodiment of the present invention, in which Fig. 7a is a sectional view and Fig. 7b is a top view of the pile. FIG. 8 is a sectional view showing a third embodiment in which the present invention is applied to the integration of a cast-in-place pile and a footing. FIG. 9 is a sectional view showing a fourth embodiment in which the present invention is applied to the integration of a footing with an underground continuous wall. 10... Steel material for PC, 12... Concrete,
14...PC pile, 16...underground, 18...pile head,
20... Hole, 22... Reinforcing bar, 24... Footing, 26... Upper end, 28... Projecting part,
30...Fixing part, 32...Fixing tool, 35...Underground continuous wall, 36...Detsut anchor part.

Claims (1)

【特許請求の範囲】 1 プレストレストコンクリート用鋼材を埋設し
たプレストレストコンクリート杭、場所打ち杭あ
るいは地中連続壁からなる地中構造物とフーチン
グとを一体化する工法において、該プレストレス
トコンクリート用鋼材を該地中構造物の躯体から
上方に突出させ、この突出部分の外周にコンクリ
ートの打設により該フーチングを形成するととも
に、該鋼材の端部を該フーチングの上端より若干
突出させ、かつ、該鋼材の外周に定着部を形成
し、該定着部内で定着具を用いて該鋼材を緊張せ
しめることによりプレストレス力を導入し、該地
中構造物と該フーチングとを一体化することを特
徴とする地中構造物とフーチングとの一体化工
法。 2 特許請求の範囲第1項記載の工法において、
前記突出部分は、前記地中構造物の上端部をカツ
トオフして形成することを特徴とする地中構造物
とフーチングとの一体化工法。 3 特許請求の範囲第1項記載の工法において、
前記地中構造物の上端部近傍に下方の一部が埋設
された連結プレストレスト用鋼材を設け、この連
結プレストレス用鋼材を前記突出部分となすこと
を特徴とする地中構造物とフーチングとの一体化
工法。 4 特許請求の範囲第1項記載の工法において、
前記プレストレストコンクリート用鋼材の上端部
を予め前記地中構造物の上端より上方に突出した
状態に配設し、この部分を前記突出部分となすこ
とを特徴とする地中構造物とフーチングとの一体
化工法。
[Scope of Claims] 1. In a construction method that integrates a footing with an underground structure consisting of prestressed concrete piles, cast-in-place piles, or underground continuous walls in which steel materials for prestressed concrete are embedded, the steel materials for prestressed concrete are buried in the ground. The footing is made to protrude upward from the frame of the medium structure, and the footing is formed by pouring concrete around the outer periphery of this protruding portion, and the end of the steel material is slightly protruded from the upper end of the footing, and the outer periphery of the steel material is made to protrude upward from the frame of the medium structure. An underground structure characterized in that an anchoring section is formed in the anchoring section, and a prestressing force is introduced by tensioning the steel material using an anchoring tool within the anchoring section, thereby integrating the underground structure and the footing. A construction method that integrates the structure and footing. 2. In the construction method described in claim 1,
A method for integrating an underground structure and a footing, characterized in that the protruding portion is formed by cutting off an upper end portion of the underground structure. 3. In the construction method described in claim 1,
An underground structure and a footing characterized in that a connecting prestressing steel material whose lower part is buried is provided near the upper end of the underground structure, and the connecting prestressing steel material serves as the protruding part. Integrated construction method. 4. In the construction method described in claim 1,
Integration of an underground structure and a footing, characterized in that the upper end of the steel material for prestressed concrete is arranged in advance in a state that projects upward from the upper end of the underground structure, and this part is used as the projecting part. Chemical method.
JP671283A 1983-01-20 1983-01-20 Integration work of pile or continuous wall and footing Granted JPS59134228A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP671283A JPS59134228A (en) 1983-01-20 1983-01-20 Integration work of pile or continuous wall and footing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP671283A JPS59134228A (en) 1983-01-20 1983-01-20 Integration work of pile or continuous wall and footing

Publications (2)

Publication Number Publication Date
JPS59134228A JPS59134228A (en) 1984-08-01
JPH0243848B2 true JPH0243848B2 (en) 1990-10-01

Family

ID=11645888

Family Applications (1)

Application Number Title Priority Date Filing Date
JP671283A Granted JPS59134228A (en) 1983-01-20 1983-01-20 Integration work of pile or continuous wall and footing

Country Status (1)

Country Link
JP (1) JPS59134228A (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63233122A (en) * 1987-03-18 1988-09-28 Maeda Seikan Kk Combined structure of hollow concrete pile and footing having improved axial holding and horizontal deforming function
JPH0626583Y2 (en) * 1987-08-18 1994-07-20 日本鋼管株式会社 Connection structure between prefabricated pile and footing
KR100444555B1 (en) * 2001-05-22 2004-08-18 주식회사 한가람 Reinforced Method of Head in a Prestressed Spun High Strength Concrete Pile
CN102493470A (en) * 2011-11-16 2012-06-13 中铁三局集团有限公司 Foundation treatment method for simulating rigidly enlarged foundation
JP5727652B1 (en) * 2014-06-23 2015-06-03 黒沢建設株式会社 Pile head seismic isolation structure

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS55122916A (en) * 1979-03-16 1980-09-22 Kurosawa Kensetsu Kk Method for building prestressed concrete-made pier foundation

Also Published As

Publication number Publication date
JPS59134228A (en) 1984-08-01

Similar Documents

Publication Publication Date Title
JPH08284159A (en) Pile head joint structure
JPH0243848B2 (en)
JP2785063B2 (en) Joint construction method for all PC foundations
JPH11236713A (en) Column and pile joint method and joint structure
JPS59192145A (en) Fixing of iron pillar
JP3161886B2 (en) Foundation for small buildings
JPS63280153A (en) Reverse construction method for underground framework
JPH08296231A (en) Construction method for stabilizing slope, and construction method for extension in slope
JPH01244003A (en) Lock-shade and construction thereof
JPS605968A (en) Prestress introduction of pc slab in existing structure
JPH10131300A (en) Construction method of building by preceding construction of steel frame
JP2984728B2 (en) Construction method of cast-in-place concrete pile
JPS6135359B2 (en)
JPH0718681A (en) How to join precast concrete columns and foundations
JPH0714433Y2 (en) Connection structure between concrete pile head and footing
JPH07331666A (en) Slope cutting method
JP2000297440A (en) Underground outer wall and construction method thereof
JPH0447021A (en) Construction method for sheathing guide pile
JPH0381418A (en) Method for making steep slope of banking
JPH06108461A (en) Concrete pile, and connecting method for said concrete pile and foundation slab
JPS6313487B2 (en)
JP2001011874A (en) Construction method for structural stud using precast pile
JPH01125416A (en) Concrete pile
JPH04368519A (en) Anchor retaining wall
JPH0649987B2 (en) Underground continuous wall foundation construction method