JPH026904B2 - - Google Patents
Info
- Publication number
- JPH026904B2 JPH026904B2 JP9343679A JP9343679A JPH026904B2 JP H026904 B2 JPH026904 B2 JP H026904B2 JP 9343679 A JP9343679 A JP 9343679A JP 9343679 A JP9343679 A JP 9343679A JP H026904 B2 JPH026904 B2 JP H026904B2
- Authority
- JP
- Japan
- Prior art keywords
- pipe
- steel frame
- vertical
- hardware
- pipes
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【発明の詳細な説明】
本発明は、高層建物内に冷暖房用、給湯用、排
水用等の管を垂直に配管する竪パイプ工法に関す
るもので、施工精度の向上、施工時間の短縮、安
全性の向上、施工管理の簡略化を目的としてなさ
れたものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a vertical pipe construction method for vertically piping pipes for cooling and heating, hot water supply, drainage, etc. in high-rise buildings, which improves construction accuracy, shortens construction time, and improves safety. This was done with the aim of improving the quality of construction work and simplifying construction management.
竪パイプ工法は、通常は建物建上り後において
シヤフト内に所要の竪パイプを施設するものであ
り、高層建物においては、揚重、接続、すみ出
し、固定、伸縮吸収、等の現場作業が多く施工管
理に多大の注力を必要とする。例えば、従来の代
表的な工法では、建物のコンクリート工事が終了
したあとで、竪パイプを施設するために形成され
たシヤフト内で配管工事を行なうのが通常であ
り、この配管工事では、建物内の或る階毎に、切
断したパイプを或る階層から次の階層まで接続す
る分だけ運び上げておき、この運び上げたパイプ
をシヤフト内に取入れながら(上へ吊り上げる
か、或いは下に吊り下げて)下から上に向かつて
シヤフト内で順次継ぎ足して行くという処法が取
られているが、シヤフト内は狭く換気もよくない
のでこのパイプの接続作業(通常は溶接工を含
む)は非常に危険な作業となつている。特にシヤ
フトに床がない場合には吊り足場によつてこの作
業を行なわねばならず、パイプの落下や搬入時の
衝突の危険があり足場から足を踏み外す危険すら
ある。そしてこの危険性は高層になるほど高ま
る。また、上階に運び上げるパイプは建物内で運
搬可能で且つその階からシヤフト内に取入れ可能
な長さに切断されることが必要で、階高が通常の
ビルの約3.6m程度の場合には2.0〜2.75mの長さ
に切断されるのが通常であり、このため、全長を
繋ぐまでにはシヤフト内での接合数が必然的に多
くなり、配管数が多いとその溶接箇所は非常に多
くなつて多大の労力を必要とし、すみ出しや伸縮
吸収などの精度向上に大変な苦労を伴うことにな
る。 The vertical pipe construction method usually involves installing the necessary vertical pipes inside the shaft after the building is erected, and for high-rise buildings, there is a lot of on-site work such as lifting, connecting, extending, fixing, and absorbing expansion and contraction. Requires significant focus on construction management. For example, in typical conventional construction methods, piping work is usually carried out inside a shaft formed to install vertical pipes after concrete work for a building is completed; For each floor, the cut pipes are carried up for connection from one floor to the next, and while the pipes are taken into the shaft (either by lifting them up or by hanging them down). The method used is to add pipes one by one inside the shaft from the bottom to the top, but since the inside of the shaft is small and poorly ventilated, the work to connect the pipes (which usually involves welding) is extremely difficult. It has become dangerous work. In particular, if the shaft does not have a floor, this work must be carried out using a suspended scaffold, and there is a risk of falling pipes, collisions during transport, and even the risk of stepping off the scaffold. And this risk increases as you get higher up. In addition, the pipes carried to the upper floors must be cut to a length that can be transported within the building and inserted into the shaft from that floor. is usually cut to a length of 2.0 to 2.75 m, so the number of joints within the shaft will inevitably increase until the entire length is connected, and if there are many pipes, the welding points will be very difficult. This requires a great deal of effort, and it is very difficult to improve accuracy in areas such as extrusion and expansion/contraction absorption.
本発明は、このような従来の竪パイプ工法の問
題点を解決し、現場作業を可及的に合理化すると
共に施工精度も向上せしめる高層建物の竪パイプ
工法を開発したものである。すなわち本発明は、
高層建物内に所定本数の相互に平行な竪パイプ群
を配設するにあたり、複数層階分の互いに等しい
長さを有する複数本の短パイプを吊り金物に互い
に平行に施工間隔を開けて吊るすように構成して
なる短パイプユニツトを、鉄骨建方のタワークレ
ーンによつて鉄骨建方が実質上終了した節に竪に
して揚重する工程と、この揚重した短パイプユニ
ツトの下端を既設の下層階パイプ群の上端に接続
する作業を鉄骨建方が実質上終了した節もしくは
その下の節で行なう工程とを、建物の鉄骨建方の
進行と並行して進行させてゆき、形成される竪パ
イプ群を前記短パイプユニツトの接続回数よりも
少ない固定回数でいづれかの階で固定金物を用い
て固定することを特徴とするものである。そのさ
い短パイプユニツトは予め工場生産で組立てたも
のを使用することができる。 The present invention solves the problems of the conventional vertical pipe construction method, and has developed a vertical pipe construction method for high-rise buildings that streamlines on-site work as much as possible and improves construction accuracy. That is, the present invention
When installing a predetermined number of mutually parallel vertical pipes in a high-rise building, a plurality of short pipes with equal lengths for multiple stories are hung from hanging hardware parallel to each other with construction intervals. The process of vertically lifting a short pipe unit constructed of The process of connecting the upper end of the lower floor pipe group at the node where the steel frame erection is substantially completed or the node below it is carried out in parallel with the progress of the steel frame erection of the building. It is characterized in that the vertical pipe group is fixed at any floor using a fixing hardware less than the number of times the short pipe unit is connected. In this case, the short pipe unit can be pre-assembled in a factory.
以下に図面に示した実施例(都内の37階建のビ
ル施工例)に従つて本工法を具体的に説明する。 This construction method will be specifically explained below according to an example (construction example of a 37-story building in Tokyo) shown in the drawings.
本実施例は、合計6本の竪パイプを垂直に立上
げる例であり、6本のパイプ群(冷水往還管、蒸
気管、排水管からなる)を3本づつに2分割した
短パイプユニツトを工場生産して現場に搬送して
施工した例を示す。 This example is an example in which a total of six vertical pipes are set up vertically, and a short pipe unit is constructed by dividing a group of six pipes (consisting of a cold water return pipe, a steam pipe, and a drainage pipe) into two parts of three pipes each. This is an example of a product manufactured in a factory and transported to the site for construction.
第1〜2図は、4階分の長さを有する短パイプ
ユニツト1をタワークレーン2によつて揚重して
いる状態を示し、第1図は(N−1)節の吊込図
(その吊込手順は第7図で後述する)、第2図はN
節の吊込図(その吊込手順は第9図で後述する)
である。これらの図に見られるように、各短パイ
プユニツト1(以後、単にユニツト1と記す)は
鉄骨建方の進行に沿つて、鉄骨建方のタワークレ
ーン2によつて揚重して吊込む。 Figures 1 and 2 show a short pipe unit 1 having a length equivalent to four floors being lifted by a tower crane 2, and Figure 1 is a lifting diagram of node (N-1) ( The hanging procedure will be described later in Figure 7), and Figure 2 shows N
Knot hanging diagram (the hanging procedure will be explained later in Figure 9)
It is. As seen in these figures, each short pipe unit 1 (hereinafter simply referred to as unit 1) is lifted and suspended by a steel frame erection tower crane 2 along the progress of steel frame erection.
各ユニツト1は3本の短パイプ(4層階の長さ
を有する)を所定間隔(施工間隔)に固定したも
のである。この固定は、工場において、第3〜4
図に示した仮固定金物3および第5図に示した吊
り金物4を使用して行なう。仮固定金物3は現場
ヤードにトラツク搬送する場合の仮の固定に使用
されるものであり、第5図の吊り金物4はユニツ
ト1の1方の端近くに取付けられており、第6図
に示すように、この吊り金物にワイヤー5をかけ
シヤツクル6を介してタワークレーン2のフツク
にかけて吊上げるのに使用される。この吊上げに
さいしては仮固定金物3は取外されている。この
仮固定金物3および吊り金物4としては、図示の
ようにUボルト7を用いて各パイプを金物に固定
するようなものを使用するのが便宜である。 Each unit 1 consists of three short pipes (having a length of four stories) fixed at predetermined intervals (construction intervals). This fixing is done at the 3rd to 4th place at the factory.
This is done using the temporary fixing hardware 3 shown in the figure and the hanging hardware 4 shown in FIG. The temporary fixing hardware 3 is used for temporary fixing when transporting the unit by truck to the site yard, and the hanging hardware 4 shown in Fig. 5 is attached near one end of the unit 1, As shown, a wire 5 is connected to this hanging hardware via a shackle 6 to the hook of a tower crane 2, which is used to lift it. During this lifting, the temporary fixing hardware 3 is removed. As the temporary fixing hardware 3 and the hanging hardware 4, it is convenient to use U-bolts 7 as shown in the figure to fix each pipe to the hardware.
(N−1)節の吊込手順を第7図に従つて述べ
ると、フロアのコンクリート打設が終了している
(N−1)・3F、(N−1)・2F、(N−1)・1F、
(N−1)・4Fの各スリーブ開口8に貫通するよ
うに、ユニツトを吊降し、吊り金物4のワイヤー
5を外し、タワークレーンは次のユニツト(合計
6本の竪パイプを、3本のパイプからなるユニツ
ト2組を用いて構成するので、各節で2組のユニ
ツトが必要である)の吊込みにかかる。この状態
でユニツトは吊り金物4によつて、N−1・3F
に受けられており、ユニツトのパイプ下端は、
(N−2)節のパイプ上端より若干浮き上つた位
置にある。次いで、吊り金物4のUボルトをゆる
め、(N−2)節の各パイプの上に(N−1)節
の各パイプをのせる。そのさい、各パイプの上端
には、第8図に示す如きガイド9を予め溶接で取
付けておき、各パイプ端もテーパー10を付けて
おくとよい。次いで吊り金物4を、この(N−
1)・3Fにアンカーボルトで固定し、芯出しが完
了する。さらに後続のN節の床板工事が完了した
あと、(N−1)節と(N−2)節のパイプ接合
後の本溶接を行ない、吊り金物4を外して、次回
の吊り込み用として盛替える。 The lifting procedure for the (N-1) section is described according to Figure 7.The concrete placement of the floors (N-1), 3F, (N-1), 2F, and (N-1) has been completed. )・1F,
(N-1) - Suspend the unit so that it passes through each sleeve opening 8 of 4F, remove the wire 5 of the hanging hardware 4, and then move the tower crane to the next unit (total of 6 vertical pipes, 3 Since it is constructed using two sets of units consisting of pipes, two sets of units are required at each node). In this state, the unit is attached to N-1/3F by the hanging hardware 4.
The lower end of the unit's pipe is
It is located slightly above the top of the pipe at node (N-2). Next, the U bolts of the hanging hardware 4 are loosened, and each pipe of the (N-1) node is placed on each pipe of the (N-2) node. In this case, it is preferable that a guide 9 as shown in FIG. 8 be attached to the upper end of each pipe by welding in advance, and that each pipe end should also be tapered 10. Next, attach the hanging hardware 4 to this (N-
1)・Fix on the 3rd floor with anchor bolts and complete centering. Furthermore, after the subsequent floor plate work at section N is completed, the main welding after joining the pipes at section (N-1) and section (N-2) is performed, and the hanging hardware 4 is removed and placed for the next suspension. Change.
次にN節(鉄骨建方節)の吊込手順を第9図に
従つて述べると、まず、N節最上管(N・3F)
にスリーブ11を取付ける。このスリーブ11
は、(N−1)節の吊込時に共吊りしてN・3Fに
とり込んでおくとよい。このスリーブ11にN節
ユニツトを吊込んでその自重をあづける(ワイヤ
ーを外す)。このときの(N−1)節のパイプと
の隙間を約4〜5cmとしておく。あとは、(N−
1)節で述べたのと同様の手順で(N−1)節の
パイプと接続し、吊り金物4を外す。ただし、こ
のN節の芯出しは、第10図に示す如き、三つ割
りのスリーブ12を、(N−1)・4F、N・1F、
N・2Fに取付け、アングルビース13をスリー
ブ12に点溶接することによつて行なうとよい。 Next, the procedure for lifting the N section (steel frame erection section) will be described according to Figure 9. First, the N section top pipe (N 3F)
Attach sleeve 11 to. This sleeve 11
It is better to hang them together and take them into N.3F when hanging the (N-1) node. The N-joint unit is suspended in this sleeve 11 to release its own weight (remove the wire). At this time, the gap between the (N-1) node and the pipe should be approximately 4 to 5 cm. After that, (N-
1) Follow the same procedure as described in section (N-1) to connect the pipe at section (N-1) and remove the hanging hardware 4. However, when centering the N section, as shown in Fig. 10, the three-split sleeve 12 is divided into (N-1)・4F, N・1F,
It is preferable to attach the angle bead 13 to the sleeve 12 by spot welding it to the sleeve 12.
このようにして、順次鉄骨建方の進行に沿つて
ユニツトを接続してゆく。すなわち鉄骨建方が実
質上終了した節において、その鉄骨建方のタワー
クレーンを使用してユニツトを揚重し、この揚重
と既設パイプ群との接続を、鉄骨建方が終了した
節またはその下の節で行なうという作業を鉄骨建
方の進行と共に並行して行なつてゆく。しかし、
この吊り込み時のスリーブへの固定だけでは最終
強度を補償できない。そこで、形成される竪パイ
プの固定階を必要数だけ取るようにする。そのさ
い、前記のスリー部の固定によつても一定の保持
力をもつので、固定階(固定回数)はユニツトの
接続回数よりもはるかに少なくても(35階建の場
合1〜5個でも)よい。この固定階では、第11
〜12図に示す如き固定金物15を使用するとよ
い。この固定金物15は、四方からのパイプ押え
16の台板17を防振ゴム18を介して枠体19
に接続するようになつており、パイプを弾力的に
固定できるようにしておくとよい。他方、この固
定金物15を使用しないフリーの階においては、
第13図のような振れ止め施工を施すとよい。 In this way, units are successively connected as the steel frame erection progresses. In other words, at the node where the steel frame erection has essentially been completed, the tower crane for that steel frame is used to lift the unit, and the connection between this lift and the existing pipe group is carried out at the node where the steel frame erection has been completed or at that point. The work carried out in the sections below will be carried out in parallel with the progress of steel frame erection. but,
The final strength cannot be guaranteed only by fixing to the sleeve during this hanging. Therefore, the number of fixed floors of the vertical pipe to be formed is determined to be the required number. At that time, the fixing of the three parts described above also provides a certain holding force, so even if the number of fixed floors (fixed number of times) is much less than the number of connected units (in the case of a 35-story building, even if there are 1 to 5 units) )good. On this fixed floor, the 11th
It is preferable to use a fixing hardware 15 as shown in FIGS. This fixed hardware 15 connects the base plate 17 of the pipe holder 16 from all sides to the frame 19 via vibration isolating rubber 18.
It is recommended that the pipe be connected to the pipe so that it can be fixed elastically. On the other hand, on the free floor where this fixed hardware 15 is not used,
It is best to install a steady rest as shown in Figure 13.
この振れ止め施工は、スリーブ8とパイプ20
の間〓におけるパイプ20外周にウレタンまたは
木製の介装材21を取付け、その外側にロツクウ
ール22を敷いてモルタル23を流し込んで行な
うとよい。この振れ止め施工は、保温施工を行な
う場合はこれと同時に行なうと便宜である(第1
3図における24は保温材例えばグラスウールを
示す)。 This steady rest construction consists of sleeve 8 and pipe 20.
It is preferable to attach a urethane or wooden interposition material 21 to the outer periphery of the pipe 20 in the gap, spread rock wool 22 on the outside, and pour mortar 23 into it. It is convenient to perform this steady rest construction at the same time as heat insulation construction (first step).
24 in Figure 3 indicates a heat insulating material such as glass wool).
以上のように本工法は、高層建物の鉄骨建方が
実質上終了した節(N節)において、そのN節の
コンクリート打設前に、その鉄骨建方のタワーク
レーンを利用して、予め所定の間隔をもつて比較
的長さの長い同長さのパイプ同士を固定したパイ
プユニツトを揚重し、これを該鉄骨建方のN節ま
たは(N−1)節において、既設パイプ群との接
合工事を行なものであり、基本的には鉄骨工事中
に竪パイプ工事も行なうということになるから、
従来のようにコンクリート工事終了後のシヤフト
内での配管接続工事のような既述の問題は殆んど
回避することができる。すなわち、パイプを出来
上がつた建物階層に運び入れることは必要ではな
いので、本発明で使用する使用するパイプの長さ
は、図示の実施例のように4階分に相当するよう
な長いものを使用することができ、このために、
竪パイプ全長を少ない接続回数で繋ぎ合わせるこ
とができると共に、各パイプは吊り金物によつて
予め施工間隔に定められた間隔をもつて吊り込ま
れるから施工精度が格段に向上し、溶接工を含む
接続作業も従来のシヤフト内作業のような既設の
狭〓空間で行なう場合に比べて危険性の上からも
作業性の面でも非常に良好となる。したがつて本
発明によれば、鉄骨建方の進行に沿つて合理的に
竪パイプ群の施工が実施でき、従来の如き、縦シ
ヤフト完了後の施工法に比して、他の工事との繁
雑な調節並びに現場作業の管理の繁雑さから解放
され精度よくかつ安全に高層ビルの竪パイプ群を
構築することができる。 As described above, this construction method uses the tower crane for the steel frame construction at the node (N node) where the steel frame erection of a high-rise building is substantially completed, before placing concrete at the N node. A pipe unit in which relatively long pipes of the same length are fixed to each other with an interval of This involves joining work, and basically vertical pipe work is also done during steel frame work.
Most of the problems previously mentioned, such as pipe connection work within the shaft after concrete work is completed, can be avoided. In other words, since it is not necessary to transport the pipe to the completed building level, the length of the pipe used in the present invention is long enough to cover four floors as in the illustrated embodiment. For this, you can use
The entire length of vertical pipes can be connected with fewer connections, and each pipe is suspended by a hanging hardware at predetermined intervals, which greatly improves construction accuracy, including the welder. The connection work is also much better in terms of danger and workability compared to the conventional work inside the shaft, which is carried out in a narrow existing space. Therefore, according to the present invention, the vertical pipe group can be constructed rationally as the steel frame erection progresses, and compared to the conventional construction method after the vertical shaft is completed, it is possible to construct the vertical pipe group more easily than with other construction work. It is possible to accurately and safely construct a group of vertical pipes for a high-rise building without having to worry about complicated adjustments and management of on-site work.
第1図は本発明法に従う(N−1)節のユニツ
ト吊込み時の施工図、第2図はN節のユニツト吊
込み時の施工図、第3図は仮固定金物の平面図、
第4図は第3図の正面図、第5図は吊り金物の正
面図、第6図は吊り金物の使用状態を示す正面
図、第7図は(N−1)節のユニツト吊込み時の
施工図、第8図はパイプ接続部の拡大図、第9図
はN節のユニツト吊込時の施工図、第10図は三
つ割スリーブの平面図、第11図は固定金物の平
面図、第12図は固定金物の正面図、第13図は
振り止め施工部の拡大断面図である。
1……ユニツト、2……タワークレーン、3…
…仮固定金物、4……吊り金物、8,11,12
……スリーブ、15……固定金物、23……ウレ
タンまたは木製の介装材。
Fig. 1 is a construction drawing of section (N-1) when the unit is suspended according to the method of the present invention, Fig. 2 is a construction drawing of section N when the unit is suspended, Fig. 3 is a plan view of the temporary fixing hardware,
Figure 4 is a front view of Figure 3, Figure 5 is a front view of the hanging hardware, Figure 6 is a front view showing how the hanging hardware is used, and Figure 7 is when the unit at section (N-1) is suspended. Fig. 8 is an enlarged view of the pipe connection, Fig. 9 is a drawing of the N-section unit when it is suspended, Fig. 10 is a plan view of the three-split sleeve, and Fig. 11 is a plan view of the fixing hardware. 12 is a front view of the fixing hardware, and FIG. 13 is an enlarged sectional view of the swing stop construction part. 1...Unit, 2...Tower crane, 3...
... Temporary fixing hardware, 4... Hanging hardware, 8, 11, 12
... Sleeve, 15 ... Fixed hardware, 23 ... Urethane or wooden interposition material.
Claims (1)
プ群を配設するにあたり、複数層階分の互いに等
しい長さを有する複数本の短パイプを吊り金物に
互いに平行に施工間隔を開けて吊るすように構成
してなる短パイプユニツトを、鉄骨建方のタワー
クレーンによつて鉄骨建方が実質上終了した節に
竪にして揚重する工程と、この揚重した短パイプ
ユニツトの下端を既設の下層階パイプ群の上端に
接続する作業を鉄骨建方が実質上終了した節もし
くはその下の節で行なう工程とを、建物の鉄骨建
方の進行と並行して進行させてゆき、形成される
竪パイプ群を前記短パイプユニツトの接続回数よ
りも少ない固定回数でいづれかの階で固定金物を
用いて固定することを特徴とする高層建物の竪パ
イプ工法。 2 竪パイプ群は、冷水管、蒸気管および排水管
からなる特許請求の範囲第1項記載の竪パイプ工
法。 3 短パイプユニツトは、予め工場生産で組立て
られたものである特許請求の範囲第1項または第
2項記載の竪パイプ工法。[Claims] 1. When arranging a predetermined number of mutually parallel vertical pipe groups in a high-rise building, a plurality of short pipes having mutually equal lengths of multiple stories are hung parallel to each other on hanging hardware. The process of vertically hoisting short pipe units configured to be suspended at construction intervals using a tower crane for steel frame erection at the joint where steel frame erection has substantially completed; The process of connecting the lower end of the pipe unit to the upper end of the existing lower floor pipe group at the node where the steel frame erection is substantially completed or the node below it is carried out in parallel with the progress of the steel frame erection of the building. A vertical pipe construction method for a high-rise building, characterized in that the group of vertical pipes formed is fixed using a fixing hardware on any floor with a number of fixing times that is less than the number of times that the short pipe units are connected. 2. The vertical pipe construction method according to claim 1, wherein the vertical pipe group includes a cold water pipe, a steam pipe, and a drainage pipe. 3. The vertical pipe construction method according to claim 1 or 2, wherein the short pipe unit is assembled in advance in a factory.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP9343679A JPS5616768A (en) | 1979-07-23 | 1979-07-23 | Method of placing vertical pipe in skyscraper |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP9343679A JPS5616768A (en) | 1979-07-23 | 1979-07-23 | Method of placing vertical pipe in skyscraper |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS5616768A JPS5616768A (en) | 1981-02-18 |
| JPH026904B2 true JPH026904B2 (en) | 1990-02-14 |
Family
ID=14082256
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP9343679A Granted JPS5616768A (en) | 1979-07-23 | 1979-07-23 | Method of placing vertical pipe in skyscraper |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS5616768A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH0454280A (en) * | 1990-06-22 | 1992-02-21 | Mitsubishi Motors Corp | Ignition timing controller |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH04258463A (en) * | 1991-02-08 | 1992-09-14 | Asahi Kogyosha:Kk | Vertical pipe erecting method for multistoried reinforced concrete building |
| JP2858958B2 (en) * | 1994-06-15 | 1999-02-17 | シチズン時計株式会社 | Driving method of inkjet head |
| JP6180350B2 (en) * | 2014-03-20 | 2017-08-16 | 三機工業株式会社 | 竪 pipe installation stand, construction plant structure and 竪 pipe installation method |
-
1979
- 1979-07-23 JP JP9343679A patent/JPS5616768A/en active Granted
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH0454280A (en) * | 1990-06-22 | 1992-02-21 | Mitsubishi Motors Corp | Ignition timing controller |
Also Published As
| Publication number | Publication date |
|---|---|
| JPS5616768A (en) | 1981-02-18 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN104847102B (en) | Attachment type raise scaffold is received attached wall method and the device thereof of section in external wall | |
| US3175654A (en) | Stair unit assemblies | |
| CN108643572A (en) | Concrete crossbeam support, shellfish thunder platform construction and steel strand wires combined installation method | |
| CN115306137B (en) | Operation platform structure for installing suspended ceiling at bottom of high-altitude corridor and construction method thereof | |
| CN108277993A (en) | A kind of steel bar truss floor support plate hanging brace device and its assembling production method | |
| JPH026904B2 (en) | ||
| US4416095A (en) | Support hanger kit for suspension ceilings and method of installation | |
| CN119145627A (en) | Three-dimensional climbing high-altitude construction system for large-span steel mesh frame daylighting roof | |
| CN107130521A (en) | Method for constructing large-section beam bailey bracket hoisting mold of pit cliff wall section | |
| CN208518359U (en) | Automatic climbing brooder system in extremely frigid zones building structure | |
| CA1146333A (en) | Chimney | |
| JP2004270377A (en) | Column-beam preassembled reinforcement body, and preassembled reinforcement method using the same | |
| JPS58176342A (en) | Construction of building | |
| CN213597351U (en) | A safe operation channel structure for installing three-way pipe truss | |
| US4312163A (en) | Reinforced structural member and method of fabrication | |
| CN118622004B (en) | Detachable overturning formwork supporting device for lower hanging side beam and construction method | |
| CN206707229U (en) | One kind installation lattice column operating platform | |
| CN216042545U (en) | Hanging basket penetrating and climbing frame structure for construction of high-rise building outer wall finish coat | |
| JP2876991B2 (en) | Steel frame method for high-rise buildings | |
| JPH0791904B2 (en) | Push-up device | |
| JPS6137426B2 (en) | ||
| RU2312960C1 (en) | Method to erect additional stories for building reconstruction | |
| JPS5920501Y2 (en) | Safety handrail of firebrick construction machine | |
| JPH0528248Y2 (en) | ||
| JPS6246758Y2 (en) |