JPH0320550B2 - - Google Patents
Info
- Publication number
- JPH0320550B2 JPH0320550B2 JP14747084A JP14747084A JPH0320550B2 JP H0320550 B2 JPH0320550 B2 JP H0320550B2 JP 14747084 A JP14747084 A JP 14747084A JP 14747084 A JP14747084 A JP 14747084A JP H0320550 B2 JPH0320550 B2 JP H0320550B2
- Authority
- JP
- Japan
- Prior art keywords
- tower
- steel pipe
- arm
- steel
- column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 229910000831 Steel Inorganic materials 0.000 claims description 76
- 239000010959 steel Substances 0.000 claims description 76
- 230000005540 biological transmission Effects 0.000 claims description 10
- 238000000034 method Methods 0.000 claims description 3
- 238000010276 construction Methods 0.000 description 6
- 230000007246 mechanism Effects 0.000 description 4
- 238000004804 winding Methods 0.000 description 4
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
Landscapes
- Electric Cable Installation (AREA)
- Suspension Of Electric Lines Or Cables (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Working Measures On Existing Buildindgs (AREA)
Description
【発明の詳細な説明】
〔産業上の利用分野〕
送電用鉄塔において、近年都市近郊の過密化に
伴い、既設の送電線に接近して建造物が建設され
る場合に送電線と建造物との離隔距離が不足する
ことから、送電線の高さを更に高い位置に移設す
る必要が生ずる。[Detailed Description of the Invention] [Industrial Application Field] In recent years, with the increasing density in urban areas, power transmission towers are being constructed in close proximity to existing power transmission lines. Due to the insufficient separation distance between the lines, it becomes necessary to relocate the power transmission lines to a higher position.
本発明は、かかる事情に際し、塔高を増加させ
鉄塔のかさ上げ工法に関するものである。 The present invention relates to a construction method for increasing the tower height and raising the height of the steel tower under such circumstances.
〔従来技術と問題点〕
従来、この種のかさ上げ工法には、鉄塔の外側
に枠組構成体に設け、上部鉄塔を支承する上部梁
をシリンダによりせり上げたり、或いは枠組構成
体の内部に設けた昇降台上に乗せた鉄塔上部を下
方よりせり上げたりして、その下方に鉄塔下部を
取付ける工法等がみられる(特公昭50−32526号、
特公昭48−26614号公報)。[Prior art and problems] Conventionally, this type of raising construction method involves installing a beam on a frame structure outside the steel tower and raising the upper beam that supports the upper steel tower with a cylinder, or installing it inside the frame structure. There is a construction method in which the upper part of the steel tower is placed on a lifting platform, raised from below, and the lower part of the steel tower is attached below it (Special Publication No. 32526, 1983).
Special Publication No. 48-26614).
しかし、これらの工法では、特に枠組構成体を
鉄塔の外側に設けるため、大きな作業用地を必要
とし、かかる用地のない狭い場所又は用地確保の
困難な場合にはかさ上げ作業の施行が不可能であ
る欠点があつた。 However, these construction methods require a large work site, especially since the framework structure is installed outside the tower, and it is impossible to carry out the raising work in narrow spaces where such land is not available or in cases where it is difficult to secure land. There was a certain drawback.
また、枠組構成体の組立てに時間がかかること
から、かさ上げ作業のために長時間停電するか、
バイパス送電のための仮鉄塔の建設を必要とする
欠点があつた。 In addition, since it takes time to assemble the framework, there may be long power outages due to the raising work.
The disadvantage was that it required the construction of a temporary tower for bypass power transmission.
本発明は上記欠点を解消するもので、その手段
は、既設鉄塔の塔体頂部に取付けた上部滑車ロー
プ等により単位鋼管を順次連結しながら塔芯に沿
い頂部までせり上げ、地線を塔体頂部のアームに
一時移設し、所定本数の単位鋼管の連結により構
成される単柱鋼管塔を下方に取付けた下部滑車ロ
ープ等により塔頂よりさらに所定高さまでせり上
げ、単柱鋼管塔の最下部に接続した単位鋼管の下
端を基礎コンクリートに固定し、鉄塔のかさ上げ
作業後、単柱鋼管塔を鉄塔の対辺材により固定支
持し、単柱鋼管塔に地線を移設すると共にアーム
を取付け、該アームに鉄塔の旧アームの電線を移
設し、旧アーム及び旧アーム部分の塔体を解体除
去することにあり、せり上げた単柱鋼管塔をかさ
上げ鉄塔として使用するものである。
The present invention solves the above-mentioned drawbacks, and its means are to raise the ground wire along the tower core to the top while sequentially connecting the unit steel pipes using an upper pulley rope attached to the top of the tower body of the existing steel tower. The single-column steel pipe tower, which is constructed by connecting a predetermined number of unit steel pipes, will be temporarily relocated to the arm at the top and raised further from the top to a predetermined height using a lower pulley rope, etc. attached below, and the lowest part of the single-column steel pipe tower will be raised from the top to a predetermined height. The lower end of the unit steel pipe connected to the tower is fixed to the foundation concrete, and after raising the height of the tower, the single-column steel pipe tower is fixedly supported by the opposing side members of the tower, the ground wire is relocated to the single-column steel pipe tower, and an arm is attached. The electric wires from the old arm of the steel tower will be transferred to the arm, and the old arm and the tower body of the old arm portion will be dismantled and removed, and the raised single-column steel pipe tower will be used as the raised steel tower.
本発明の実施例を図面を参照して説明する。 Embodiments of the present invention will be described with reference to the drawings.
第1図において、1は既設鉄塔であり、この鉄
塔1内に単柱鋼管塔2を建設する。 In FIG. 1, 1 is an existing steel tower, and a single column steel pipe tower 2 will be constructed within this steel tower 1.
而して、この単柱鋼管塔2は次の工法により組
立てられる。 This single-column steel pipe tower 2 is assembled by the following construction method.
(a) 第2図に示すように、鉄塔1の塔体頂部に上
部滑車3を吊設すると共に鉄塔1内の作業の邪
魔になる対辺材を取外す。(a) As shown in FIG. 2, the upper pulley 3 is suspended from the top of the tower body of the steel tower 1, and the opposing sap material that gets in the way of work inside the steel tower 1 is removed.
(b) 地上に設置した上部巻上げ機4の巻胴から繰
り出した上部ワイヤーロープ5を案内滑車を介
して上記の上部滑車3に掛け回して鉄塔1内に
吊下する。(b) The upper wire rope 5 let out from the winding drum of the upper hoist 4 installed on the ground is hung around the above-mentioned upper pulley 3 via the guide pulley and suspended inside the steel tower 1.
(c) 鉄塔1内の地上に所定長さの単位鋼管2aを
必要本数搬入する。(c) Deliver the required number of unit steel pipes 2a of a predetermined length to the ground within the steel tower 1.
(d) 鉄塔1の塔体頂部から塔高の約1/3下つた位
置でかつ水平材1aのある個所と、地上から塔
高の約1/3上つた同様の個所に夫々ガイド機構
6を取付ける。(d) Install guide mechanisms 6 at a location approximately 1/3 below the tower height from the top of the steel tower 1 and where the horizontal member 1a is located, and at a similar location approximately 1/3 above the tower height from the ground. Install.
このガイド機構6は第6図に示すように、複
数のガイドローラー6aを有する枠体6bに締
結した4本の支持ワイヤーロープ6cの他端
を、ガイドローラ6aが鉄塔1の中心に位置す
るように水平材1aの四隅に締結する。 As shown in FIG. 6, this guide mechanism 6 connects the other ends of four support wire ropes 6c fastened to a frame 6b having a plurality of guide rollers 6a so that the guide rollers 6a are located at the center of the steel tower 1. Fasten it to the four corners of the horizontal member 1a.
(e) 上部ワイヤーロープ5の吊下端に上記搬入さ
れた単位鋼管2aの上端を結着し、上部巻上げ
機4を操作して単位鋼管2aを吊上げ、その下
に次の単位鋼管2aをフランジ結合しながら上
記ガイドローラー6a内を通して順次結合吊上
げ、上部ワイヤーロープ5の巻き代限度(塔体
頂部近く)まで吊上げる。(e) Tie the upper end of the carried-in unit steel pipe 2a to the hanging end of the upper wire rope 5, operate the upper hoisting machine 4 to lift the unit steel pipe 2a, and flange-join the next unit steel pipe 2a below it. While passing through the guide roller 6a, the rope is successively connected and lifted up to the winding limit of the upper wire rope 5 (near the top of the tower body).
(f) 第3図に示すように、鉄塔1の地上から適宜
高さ位置(10m程度)で、水平材1aのある個
所の対角に夫々下部滑車7を吊下げ、地上に設
置した2個の下部巻上げ機8の巻胴から上記所
定本数の単位鋼管2aを連結した単柱鋼管塔2
をせり上げる下部ワイヤーロープ9を繰り出
し、案内滑車を介して上記下部滑車7に掛け回
わして鉄塔1内に吊下げる。(f) As shown in Figure 3, two lower pulleys 7 are suspended diagonally from the horizontal member 1a at an appropriate height (approximately 10 m) above the ground of the steel tower 1, and two pulleys are installed on the ground. A single-column steel pipe tower 2 in which the predetermined number of unit steel pipes 2a are connected from the winding drum of the lower winding machine 8.
A lower wire rope 9 is let out to raise the lower wire rope 9, and is hung around the lower pulley 7 via a guide pulley and suspended inside the steel tower 1.
(g) 塔体頂部のアーム1bに仮アーム10を取付
け、この仮アーム10に塔頂の地線11を一時
移設し、塔頂を解体除去する。(g) Attach a temporary arm 10 to the arm 1b at the top of the tower body, temporarily relocate the ground wire 11 at the top of the tower to this temporary arm 10, and dismantle and remove the tower top.
(h) 下部ワイヤーロープ9の各先端のフツクを単
柱鋼管塔2の最下部の単位鋼管2aの下部に掛
け、(この際、上部滑車3を取除く)下部巻上
げ機8を操作して単柱鋼管2を塔頂より上方へ
せり上げる。(h) Hook the hooks at each end of the lower wire rope 9 to the lower part of the unit steel pipe 2a at the bottom of the single-column steel pipe tower 2 (at this time, remove the upper pulley 3), and operate the lower hoist 8 to Raise the column steel pipe 2 upward from the top of the tower.
(i) 所定高さまでのせり上げには、単柱鋼管塔2
の最下端に単位鋼管2aを必要本継ぎ足し、こ
の単位鋼管2aを予め地上に打設した基礎コン
クリート15のアンカーボルトに固定する。(i) Single-column steel pipe tower 2 shall be used to raise the tower to the specified height.
The necessary number of unit steel pipes 2a are added to the lowest end of the unit steel pipe 2a, and the unit steel pipes 2a are fixed to anchor bolts of the foundation concrete 15 cast in advance on the ground.
(j) 第4図に示すように、鉄塔1の所要個所に対
辺材1cを取付け、この対辺材1cに単柱鋼管
塔2を塔芯に位置するように固定する。(j) As shown in Fig. 4, opposite sill members 1c are attached to required locations on the steel tower 1, and the single-column steel pipe tower 2 is fixed to this opposite sill member 1c so as to be located at the tower core.
(k) 単柱鋼管塔2の頂部に地線11を移設する。(k) Relocate the ground wire 11 to the top of the single-column steel pipe tower 2.
(l) 片側送電回線を停止して、単柱鋼管塔2に片
側の各アーム12,13,14の取付け、これ
に旧アームの各電線を移設する。(l) Stop the power transmission line on one side, attach each arm 12, 13, and 14 on one side to the single-column steel pipe tower 2, and transfer the electric wires of the old arm to it.
上記旧アームを解体除去し、上記片側送電回
線を復旧する。 The old arm will be dismantled and removed, and the one-sided power transmission line will be restored.
(m) 他側送電回線について、上記(l)と同様の作
業をする。(m) Perform the same work as in (l) above for the other side's power transmission line.
(n) 両送電回線の旧アーム部分の塔体を解体除
去する。(n) The tower bodies of the old arms of both transmission lines will be dismantled and removed.
以上により、第5図に示すかさ上げ鉄塔が完成
する。 Through the above steps, the raised steel tower shown in FIG. 5 is completed.
(a) 既設鉄塔を、その敷地内で安全かつ短期間に
かさ上げすることができる。
(a) Existing steel towers can be raised safely and quickly within the site.
(b) やぐら形の鉄塔部分が単柱鋼管塔の最下段の
アームの下方部分を包囲し、かつ対辺材で単柱
鋼管塔を固定支持するので、やぐら形の鉄塔部
分が水平荷重を分担し、単柱鋼管塔は垂直荷重
のみを分担すればよく、したがつて、その外径
は小さくて済み経済的である。(b) The tower-shaped steel tower section surrounds the lower part of the lowest arm of the single-column steel pipe tower, and the single-column steel pipe tower is fixedly supported by the opposing sap, so the tower-shaped steel tower section shares the horizontal load. , the single-column steel pipe tower only needs to share the vertical load, and therefore its outer diameter can be small, making it economical.
(c) 小径の単柱鋼管塔にアームが取付けられるの
で、その張り出し巾は旧鉄塔部分のアームの張
り出し巾より小さくすることが可能であり、電
線下用地も少なくて済む。(c) Since the arm is attached to a small-diameter single-column steel pipe tower, its overhang width can be made smaller than the arm overhang width of the old steel tower section, and less land is needed under the electric wires.
(d) やぐら形の鉄塔部分で風向きに対する乱流が
起るので、単柱鋼管塔に整流が起生し難く、し
たがつて振動の発生を抑制し得る。(d) Since turbulence in relation to the wind direction occurs in the tower-shaped steel tower section, rectification is difficult to occur in the single-column steel pipe tower, and the occurrence of vibration can therefore be suppressed.
なお、本発明においては、既設鉄塔のかさ上げ
工法について説明したが、上記のように、基礎コ
ンクリートに固設した単柱鋼管塔の下半部をやぐ
ら形の鉄塔で包囲し、かつ鋼管塔を対辺材で支持
し、単柱鋼管塔は垂直荷重を、やぐら形の鉄塔が
水平荷重を夫々分担する構成となつているので、
これを新設の送電用鉄塔を建設する場合の構成に
適用することも可能である。 In addition, in the present invention, the method of raising the height of an existing steel tower has been explained, but as mentioned above, the lower half of a single-column steel pipe tower fixed to the foundation concrete is surrounded by a tower-shaped steel tower, and the steel pipe tower is Supported by opposing saplings, the single-column steel pipe tower takes the vertical load, and the tower-shaped steel tower takes the horizontal load.
It is also possible to apply this to the configuration when constructing a new power transmission tower.
第1図は既設鉄塔の正面図、第2図〜第4図は
本発明に係るかさ上げ工法の実施例の説明図、第
5図はかさ上げ完了後の正面図、第6図はガイド
機構の説明図である。
1……既設鉄塔、2……単柱鋼管塔、2a……
単位鋼管、3……上部滑車、4……上部巻上げ
機、5……上部ワイヤーロープ、6……ガイド機
構、7……下部滑車、8……下部巻上げ機、9…
…下部ワイヤーロープ、10……仮アーム、11
……地線、12,13,14……アーム、15…
…基礎コンクリート。
Figure 1 is a front view of the existing steel tower, Figures 2 to 4 are explanatory diagrams of an embodiment of the raising method according to the present invention, Figure 5 is a front view after the raising is completed, and Figure 6 is the guide mechanism. FIG. 1...Existing steel tower, 2...Single column steel pipe tower, 2a...
Unit steel pipe, 3... Upper pulley, 4... Upper hoist, 5... Upper wire rope, 6... Guide mechanism, 7... Lower pulley, 8... Lower hoist, 9...
... Lower wire rope, 10 ... Temporary arm, 11
...Ground wire, 12,13,14...Arm, 15...
...Foundation concrete.
Claims (1)
プ等により単位鋼管を順次連結しながら塔芯に沿
い頂部までせり上げ、地線を塔体頂部のアームに
一時移設し、所定本数の単位鋼管の連結により構
成される単柱鋼管塔を鉄塔の下方に取付けた下部
滑車ロープ等により塔頂よりさらに所定高さまで
せり上げ、単柱鋼管塔の最下部に接続した単位鋼
管の下端を基礎コンクリートに固定し、鉄塔のか
さ上げ作業後、単柱鋼管塔を鉄塔の対辺材により
固定支持し、単柱鋼管塔に地線を移設すると共に
アームを取付け、該アームに鉄塔の旧アームの電
線を移設し、旧アーム及び旧アーム部分の塔体を
解体除去することを特徴とする送電用鉄塔のかさ
上げ工法。1. Raise the unit steel pipes along the tower core to the top while sequentially connecting them using upper pulley ropes etc. attached to the top of the tower body of the existing steel tower. Temporarily relocate the ground wire to the arm at the top of the tower body, and A single-column steel pipe tower made up of connections is raised from the top of the tower to a specified height using a lower pulley rope attached to the bottom of the tower, and the lower end of the unit steel pipe connected to the bottom of the single-column steel pipe tower is fixed to the foundation concrete. After the work to raise the height of the steel tower, the single-column steel pipe tower was fixed and supported by the opposite side members of the steel tower, the ground wire was relocated to the single-column steel pipe tower, an arm was attached, and the electric wires from the old arm of the steel tower were transferred to the arm. , a method of raising the height of a power transmission tower, which is characterized by dismantling and removing the old arm and the tower body of the old arm part.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP14747084A JPS6128680A (en) | 1984-07-18 | 1984-07-18 | Rising construction method of transmission iron tower |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP14747084A JPS6128680A (en) | 1984-07-18 | 1984-07-18 | Rising construction method of transmission iron tower |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS6128680A JPS6128680A (en) | 1986-02-08 |
| JPH0320550B2 true JPH0320550B2 (en) | 1991-03-19 |
Family
ID=15431110
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP14747084A Granted JPS6128680A (en) | 1984-07-18 | 1984-07-18 | Rising construction method of transmission iron tower |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS6128680A (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2006316409A (en) * | 2005-05-10 | 2006-11-24 | Kansai Electric Power Co Inc:The | Compound steel pipe steel tower and construction method therefor |
| JP5688827B2 (en) * | 2010-07-02 | 2015-03-25 | 東京電力株式会社 | Reconstruction method of existing steel tower |
-
1984
- 1984-07-18 JP JP14747084A patent/JPS6128680A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS6128680A (en) | 1986-02-08 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106698208B (en) | A kind of hanging device and hanging method for being transported outside high-rise building | |
| CN110065892B (en) | Hoisting device and hoisting method for indoor hoisting of prefabricated combined pipeline | |
| CN210012524U (en) | Hoisting device for indoor hoisting of prefabricated combined pipeline | |
| JP2639361B2 (en) | Construction method of steel pipe / concrete composite structure pier | |
| CN116853963B (en) | A hoisting device and hoisting method for main beam of cable-stayed bridge | |
| JP2002047805A (en) | Construction method of vertical pipe and lifting device used in the method | |
| JPH0320550B2 (en) | ||
| JP2004036235A (en) | Construction method for heightening steel tower | |
| JPH04231509A (en) | Laying method for cable | |
| JPH05286694A (en) | Construction method and crane for assembling external type steel tower | |
| JP3297196B2 (en) | Composite balance and method for loading heavy objects using composite balance | |
| CN220364263U (en) | Suspension type lifting construction system | |
| JPH0667511U (en) | Electric automatic special support lifting device | |
| JP2858891B2 (en) | Construction method of large span dome roof | |
| CN221987941U (en) | An assembled building lifting device | |
| JP2584418B2 (en) | Overhang construction method and stress improvement device for synthetic cable-stayed bridge | |
| JPS6222904A (en) | Method of lifting steam drum | |
| CN113789725B (en) | Suspension bridge construction method and lifting device | |
| CN221664249U (en) | A construction structure of a sliding form support system | |
| CN110670590B (en) | Movable ground anchor for mounting conical section of steel structure cooling tower and construction method thereof | |
| JP2817208B2 (en) | Construction method of rack steel frame | |
| JP3671242B2 (en) | How to install the equipment | |
| JPH0827903A (en) | All weather type building method | |
| JPH02140372A (en) | Iron tower pushing-up construction method | |
| SU937684A1 (en) | Method and apparatus for erecting a mast |