JPH0326247B2 - - Google Patents
Info
- Publication number
- JPH0326247B2 JPH0326247B2 JP58171690A JP17169083A JPH0326247B2 JP H0326247 B2 JPH0326247 B2 JP H0326247B2 JP 58171690 A JP58171690 A JP 58171690A JP 17169083 A JP17169083 A JP 17169083A JP H0326247 B2 JPH0326247 B2 JP H0326247B2
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- crushing device
- reinforcing bar
- pipe
- backfill
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D9/00—Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof
- E02D9/005—Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof removing the top of placed piles of sheet piles
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Piles And Underground Anchors (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Description
【発明の詳細な説明】
この発明は、場打ちコンクリート基礎杭工法に
おける余盛部分の処理方法に関するものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for treating extra heap portions in cast-in-place concrete foundation pile construction methods.
発明の背景
場所打ちコンクリートくいは、ベントナイト懸
濁液等の泥水を使うことが多いため、少なくとも
コンクリート上端にレインタンス部分を除き50cm
以上の余盛部分を見込んでコンクリートを打設
し、後の杭頭処理に際してその部分を除くように
規定されている[1]。Background of the Invention Cast-in-place concrete piles often use muddy water such as bentonite suspension, so at least 50 cm (excluding the rain trough) at the top of the concrete is used.
It is stipulated that concrete should be poured taking into account the above-mentioned extra heap portion, and that this portion should be removed when processing the pile cap later [1].
従来はその部分を一般にブレーカー等ではつつ
ていたが、その方法では騒音や振動などが発生す
ると同時に、杭頭コンクリートに損傷を与える危
険性もある。 In the past, such areas were generally sealed with breakers, but this method not only generates noise and vibration, but also risks damaging the concrete pile cap.
これまでに、上記の騒音と振動を避けるために
次に述べる工法が提案されてきた。すなわち「第
1図」はその説明図で、10は鉄筋かごの全体、
12は立筋、14はフープ筋を示す。16は破砕
剤をいれたパイプで、フープ状にまるめて、余盛
部分の下端面の位置に当る鉄筋かごの上端近くの
内部にあらかじ入れてある。またその外側に中空
の縁切用のパイプ18が入れてある。また立筋1
2にも縁切り用のプラスチツクパイプ20がかぶ
せてある。 To date, the following construction methods have been proposed to avoid the above-mentioned noise and vibration. In other words, "Figure 1" is an explanatory diagram thereof, and 10 is the entire reinforcing bar cage,
12 indicates the erector muscle, and 14 indicates the hoop muscle. Reference numeral 16 denotes a pipe containing a crushing agent, which is rolled into a hoop shape and placed inside near the upper end of the reinforcing bar cage, which corresponds to the lower end of the extra heap. Moreover, a hollow pipe 18 for edge cutting is inserted on the outside thereof. Also, standing muscles 1
2 is also covered with a plastic pipe 20 for edge cutting.
コンクリートを打設した後、ある時間を経過し
た時に、破砕剤が水和反応をおこして非常に大き
い膨張圧を生ずる。この膨張によりコンクリート
にクラツク22ができて、コンクリート柱24か
ら余盛部分26が分離し、機械による引抜き処理
が可能になる[2]。 After a certain period of time has elapsed after the concrete is placed, the crushing agent undergoes a hydration reaction, creating a very large expansion pressure. This expansion creates a crack 22 in the concrete, which separates the reinforcement portion 26 from the concrete column 24, allowing it to be pulled out by a machine [2].
しかしこの工法の場合は、(1)必要な膨張圧が発
生するまで、たいへん長い時間がかかる、(2)作業
現場における破砕剤の取扱いが難しい、(3)また破
砕コンクリートが比較的大きいため、さらに小片
になるよう重ねての破砕処理を要する、などの問
題がある。 However, with this method, (1) it takes a very long time to generate the necessary expansion pressure, (2) it is difficult to handle the crushing agent at the work site, and (3) the crushed concrete is relatively large. Furthermore, there are problems such as the need for repeated crushing treatment to break down into small pieces.
そこで、今回の発明は、現場における取扱いが
容易で、杭体コンクリートを痛めることなく、か
つその作業に公害をともなわない余盛部分の処理
方法の提供を、目的とするものである。 Therefore, the object of the present invention is to provide a method for treating the excess heap portion that is easy to handle on site, does not damage the concrete pile, and does not cause pollution during the work.
発明の構成
「第2〜5図」に示すように、
(1) 堀削した穴のなかにあらかじめ建込んだ鉄筋
かご10の立筋12の上端部に、縁切り用のパ
イプ56をかぶせておくこと、
(2) 先端が円錐形または角錐形のラム38を持つ
油圧ジヤツキ34を複数本、同一水平面上にお
いて水平にかつ放射状に突出させた破砕装置3
0を、前記鉄筋かご10上端近くの内部に吊り
上げておいてコンクリートトを打設すること、
(3) その後、前記油圧ジヤツキ34を作動させ、
前記ラム38を前進させて余盛部分26の下面
にクラツク22を作ること、
(4) その後、前記破砕装置30を前記余盛の破砕
した部分とともに吊り上げ撤去すること、を特
徴とする。Structure of the Invention As shown in "Figures 2 to 5", (1) A pipe 56 for edge cutting is placed over the upper end of the vertical bar 12 of the reinforcing bar cage 10 that has been placed in advance in the excavated hole. (2) A crushing device 3 in which a plurality of hydraulic jacks 34 each having a ram 38 having a conical or pyramidal tip protrude horizontally and radially on the same horizontal plane.
(3) Then, operating the hydraulic jack 34,
The present invention is characterized in that the ram 38 is moved forward to create a crack 22 on the lower surface of the backfill portion 26, and (4) the crushing device 30 is then lifted up and removed together with the crushed portion of the backfill portion.
実施例
「第2、第3図」において、30はこの発明に
おいて使用する破砕装置の全体を示す。32はそ
の本体で、たとえば六角のブロツクからできてい
る。本体37からたとえば6本の油圧ジヤツキ3
4が水平にかつ放射状に突出している。38はラ
ムで、その先端はたとえば「第4図a」のように
円錐形40、または「同図b」のように下面43
の平らな三角錐42となつている。Embodiment In "Figures 2 and 3", 30 indicates the entire crushing device used in the present invention. 32 is its main body, which is made of, for example, a hexagonal block. For example, six hydraulic jacks 3 are connected to the main body 37.
4 protrudes horizontally and radially. 38 is a ram, the tip of which has a conical shape 40 as shown in Figure 4a, or a lower surface 43 as shown in Figure 4b.
It is shaped like a flat triangular pyramid 42.
44は吊りこみ用のガイドパイプで、その下端
は、本体32に固定してあり、その内部には油圧
ホース46(ジヤツキ34に通ずる)が入つてい
る。ジヤツキ34の下面には、たとえば鉄の板4
8がとりつけてあり、それには多数の孔50(コ
ンクリートを通すための)があけてある。 44 is a guide pipe for lifting, the lower end of which is fixed to the main body 32, and a hydraulic hose 46 (which leads to the jack 34) is placed inside the guide pipe. For example, an iron plate 4 is attached to the bottom surface of the jack 34.
8 is fitted, in which a number of holes 50 (for passing concrete) are drilled.
工法の説明
「第5図」のように、ガイドパイプ44の上端
を、適当な部材52で支持して、鉄筋かご10の
上端部の内面に吊りさげる。そして油圧ポンプ5
4を接続する。また立筋12に縁切り用のプラス
チツクパイプ56(たとえ塩化ビニル)をかぶせ
る。なお、「第1図」の場合と同様に、水平方向
の縁切り用のパイプ18をとりつけてもよい。Description of construction method As shown in FIG. 5, the upper end of the guide pipe 44 is supported by a suitable member 52 and suspended from the inner surface of the upper end of the reinforcing bar cage 10. and hydraulic pump 5
Connect 4. Furthermore, a plastic pipe 56 (for example, made of vinyl chloride) for edge cutting is placed over the vertical reinforcement 12. Incidentally, as in the case of "Fig. 1", a pipe 18 for cutting edges in the horizontal direction may be attached.
以上を状態でコンクリートを打設する。 Concrete is poured in the above condition.
その後ジヤツキ34に油を送りこんで作動させ
ると、「第6図」のように余盛部分26の下にク
ラツク22がはいる。なお、そのときラム38の
先端が、「第4図b」のように、下面43の平な
角錐形であると、クラツクが余盛部分の下面より
もさらに下方にまで入るということがないから、
コンクリートくいを必要以上にこわすということ
がなくなる。すなわち杭体を痛めることがない。 After that, when oil is supplied to the jack 34 and it is operated, the crack 22 is inserted under the excess portion 26 as shown in "Fig. 6". At this time, if the tip of the ram 38 has a pyramidal shape with a flat lower surface 43 as shown in Figure 4b, the crack will not go further below the lower surface of the excess portion. ,
There is no need to break concrete piles more than necessary. In other words, the pile body will not be damaged.
その後パイプ44の上端を機械でつかんでもち
あげる。すると金属板48やジヤツキ34によつ
て、余盛部分26が下からかかえられて、いつし
よにもちあげられる。 Thereafter, the upper end of the pipe 44 is grasped mechanically and lifted up. Then, the metal plate 48 and the jack 34 hold the excess portion 26 from below and lift it up.
発明の効果
(1) 騒音や振動を発生しない。また防塵的であ
る。Effects of the invention (1) No noise or vibration is generated. It is also dustproof.
(2) 薬剤を使用するのと違つて取扱いが容易でか
つ短時間に作業ができる。(2) Unlike using chemicals, it is easy to handle and can be done in a short time.
(3) 余盛部分より下方への杭体コンクリートを痛
めない。(3) Do not damage the pile concrete below the extra heap.
(4) 破砕装置30は、何回も繰りかえして使うこ
とができる。(4) The crushing device 30 can be used repeatedly.
(5) 鉄筋かごの立筋な上端部に、縁切り用のパイ
プをかぶせておくので、破砕後、余盛部分の吊
上げを支障なく行うことができる。(5) A pipe for edge cutting is placed over the vertical upper end of the reinforcing bar cage, so that after crushing, the extra heap can be lifted without any problem.
(6) 破砕装置を、鉄筋かごの上端近くの内部に吊
り下げておいてコンクリートを打設し、クラツ
クを作つた後、余盛の破砕した部分とともに吊
り上げ撤去するので;余盛部分を短時間に引抜
き撤去することができる。(6) The crushing device is suspended inside the reinforcing steel cage near the top end, and after pouring concrete and making cracks, it is lifted up and removed together with the crushed portion of the reinforcement; It can be pulled out and removed.
すなわち、引抜き撤去のために別のクレーンな
どを用いると仮定すると、破砕した余盛部分をク
レーンの先端な連結する作業が必要になるが、本
発明の場合はそのようなことが一切不要である。 In other words, assuming that another crane or the like is used for pulling out and removing, it would be necessary to connect the crushed extra material to the tip of the crane, but in the case of the present invention, such work is not necessary at all. .
[参考文献]
(1) (社)日本基礎建設協会、「場所打ちコンク
ートくい施工指針・同解説(案)」昭和54年4
月
(2) 松代他:「PPC工法による場所打ちコンクリ
ート杭の杭頭処理施工」、建築の技術 施工、
1983年9月、p.59〜63.[References] (1) Japan Foundation Construction Association, “Cast-in-place concrete pile construction guidelines and commentary (draft)” April 1972
Month (2) Matsushiro et al.: “Pile cap treatment construction of cast-in-place concrete piles using PPC method”, Architectural technology construction,
September 1983, p.59-63.
第1図は従来技術の説明図、第2図はこの発明
において使用する破砕装置の平面図、第3図はそ
の側面図、第4図a,bはラムの先端の形状の説
明図、第5図と第6図は工事方法の説明図。
10:鉄筋かご、22:クラツク、26:余盛
部分、30:破砕装置の全体、34:油圧ジヤツ
キ、38:ラム。
Fig. 1 is an explanatory diagram of the prior art, Fig. 2 is a plan view of the crushing device used in the present invention, Fig. 3 is a side view thereof, Figs. 4 a and b are explanatory diagrams of the shape of the tip of the ram, Figures 5 and 6 are explanatory diagrams of the construction method. 10: Rebar cage, 22: Cracks, 26: Excess portion, 30: Whole crushing device, 34: Hydraulic jack, 38: Ram.
Claims (1)
するに際して、 堀削した穴のなかにあらかじめ建込んだ鉄筋か
ごの立筋の上端部に、縁切り用のパイプ20をか
ぶせておくとともに;先端が円錐形または角錐形
のラムを持つ油圧ジヤツキを複数本、同一水平面
上において水平にかつ放射状に突出させた破砕装
置を、前記鉄筋かごの上端近くの内部に吊り下げ
ておいてコンクリートを打設し;その後、前記油
圧ジヤツキを作動させ、前記ラムを前進させて余
盛部分の下面にクラツクを作り;その後、前記破
砕装置を前記余盛の破砕した部分とともに吊り上
げ撤去することを特徴とする、基礎くいの余盛部
分の処理方法。[Scope of Claims] 1. When processing the excess portion of cast-in-place concrete piles, a pipe 20 for edge cutting is placed over the upper end of the vertical bar of the reinforcing bar cage that has been placed in the excavated hole in advance. Along with this, a crushing device consisting of a plurality of hydraulic jacks having rams with conical or pyramidal tips projecting horizontally and radially on the same horizontal plane is suspended inside near the upper end of the reinforcing bar cage to crush concrete. and then driving the hydraulic jack to move the ram forward to create a crack on the lower surface of the backfill portion; and then lifting and removing the crushing device together with the crushed portion of the backfill. A method for processing the excess heap of foundation piles.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP17169083A JPS6062331A (en) | 1983-09-17 | 1983-09-17 | Treatment of extra-banking portion of foundation pile |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP17169083A JPS6062331A (en) | 1983-09-17 | 1983-09-17 | Treatment of extra-banking portion of foundation pile |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS6062331A JPS6062331A (en) | 1985-04-10 |
| JPH0326247B2 true JPH0326247B2 (en) | 1991-04-10 |
Family
ID=15927882
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP17169083A Granted JPS6062331A (en) | 1983-09-17 | 1983-09-17 | Treatment of extra-banking portion of foundation pile |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS6062331A (en) |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5325004A (en) * | 1976-08-18 | 1978-03-08 | Mitsubishi Heavy Ind Ltd | Concreteepile rupturing apparatus |
| JPS5354322U (en) * | 1976-10-13 | 1978-05-10 |
-
1983
- 1983-09-17 JP JP17169083A patent/JPS6062331A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS6062331A (en) | 1985-04-10 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN104746892B (en) | Construction method that joist demolishes walls device and joist is demolished walls | |
| WO2023207250A1 (en) | Construction method for rapidly driving trestle steel pipe pile into sloped bare rock | |
| CN110820742A (en) | Construction method for breaking underwater cast-in-place pile head | |
| CN111005378A (en) | Construction method for breaking pile head of cast-in-situ bored pile through static spalling | |
| CN108166771A (en) | Steel reinforced concrete pool structural reform makes construction method | |
| CN115142418A (en) | Non-vibration pipe-drawing cage-preventing device for immersed cast-in-place pile and construction method thereof | |
| CN111456032B (en) | A foundation pit support system and its construction method | |
| CN109440781B (en) | Active inclined double-row pile foundation pit support method | |
| CN215906743U (en) | Tamping tool and tamping equipment | |
| CN110552346A (en) | Double-spraying double-shaft oblique cement-soil stirring and profile steel inserting integrated construction method and equipment | |
| CN212129138U (en) | Underground pile foundation demolishs device | |
| JPH0326247B2 (en) | ||
| JP7630362B2 (en) | Caisson method | |
| CN113585336B (en) | Quick construction method of sinking type concrete mixing station in soft foundation environment | |
| CN214424457U (en) | A mud anti-splash device for punching bored concrete pile construction | |
| JPH08105041A (en) | Pile head treatment method for cast-in-place foundation pile and tool for performing this treatment | |
| CN223880355U (en) | Supporting structure for steel sheet pile of large-scale slope toe of deep foundation pit | |
| CN109440780B (en) | Active type inclined single-row pile foundation pit supporting method | |
| JPH06341154A (en) | Construction of underground building frame | |
| CN112796690A (en) | Mud anti-splash device for punching cast-in-place pile construction and construction method | |
| JPH0960311A (en) | Lift-up dismantling method | |
| CN220888620U (en) | A segmented column pile steel column | |
| CN213417801U (en) | Pile head repairing structure of pile foundation | |
| CN111042132B (en) | Pile head breaking device and construction method thereof | |
| CN211922621U (en) | Rear-mounted breaking device with vibrator |