JPH0327701B2 - - Google Patents
Info
- Publication number
- JPH0327701B2 JPH0327701B2 JP58116483A JP11648383A JPH0327701B2 JP H0327701 B2 JPH0327701 B2 JP H0327701B2 JP 58116483 A JP58116483 A JP 58116483A JP 11648383 A JP11648383 A JP 11648383A JP H0327701 B2 JPH0327701 B2 JP H0327701B2
- Authority
- JP
- Japan
- Prior art keywords
- chute
- concrete
- garter
- truss
- traveling
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000009434 installation Methods 0.000 claims description 7
- 239000000463 material Substances 0.000 claims description 5
- 238000010276 construction Methods 0.000 description 3
- 238000000034 method Methods 0.000 description 3
- 238000000926 separation method Methods 0.000 description 3
- 238000007796 conventional method Methods 0.000 description 2
- 230000003014 reinforcing effect Effects 0.000 description 2
- 238000005266 casting Methods 0.000 description 1
- 238000005056 compaction Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
- 238000004804 winding Methods 0.000 description 1
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Description
【発明の詳細な説明】
本発明は、高落差の位置へコンクリートを打設
する場合のコンクリート打設装置に関する。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a concrete pouring device for pouring concrete into a position with a high head.
地下構造物の規模が大きくなると、その構築深
度も深くなり、このためのコンクリート工事につ
いていえば、コンクリートの打設量においても地
下部分が地上を上廻るような場合も少なくない。 As the scale of an underground structure increases, its construction depth also increases, and when it comes to concrete work for this purpose, there are many cases where the amount of concrete placed underground exceeds that above ground.
そこで、かゝる高落差の位置へコンクリートを
打設する場合、従来の縦シユートで行うときはコ
ンクリート骨材の分離が生じたり、高落差によつ
て打設部分に大きな衝撃を与えるため打設作業の
危険性が増大する。 Therefore, when pouring concrete into a position with such a high head, when concrete is poured using a conventional vertical chute, separation of the concrete aggregate may occur, or the high head may cause a large impact on the pouring area. Increased risk of work.
これらの欠点を解消して縦シユート内を階段的
に順次コンクリートを送りコンクリート骨材の分
離を防止し、かつ落差の衝撃を減少させたコンク
リート打設用のシユートを出願人は既に出願して
いる。このシユートは第1図および第2図に示し
た如くである。すなわち、第1図に示した如く、
1は可撓性材または所定間隔毎に可撓性材からな
るシユートであり、2はシユート1の所定間隔毎
にシユート外周に捲着に設置されたバルブ装置で
繞囲枠3内に空気圧Pの供給を受けるチユーブ4
がシユート1をとり囲む態様にて内装されてい
る。 The applicant has already filed an application for a chute for concrete pouring that eliminates these drawbacks, feeds concrete stepwise in a vertical chute, prevents separation of concrete aggregate, and reduces the impact of drops. . This chute is as shown in FIGS. 1 and 2. That is, as shown in Figure 1,
1 is a flexible material or a chute made of a flexible material at predetermined intervals, and 2 is a valve device that is wound around the outer periphery of the chute at predetermined intervals of the chute 1 to control air pressure P within the surrounding frame 3. tube 4 supplied with
is installed in a manner surrounding the chute 1.
そこでバルブ装置2の弁機能はチユーブ4が空
気圧Pでふくらんでシユート1を押しつぶしてコ
ンクリートの通路を閉塞することによつて閉弁と
し、前記空気圧Pの解除若しくは第1図に示した
如くバルブ装置2で閉塞中のバルブ装置2で仕切
られるシユート1の内部にコンクリート5が一定
量滞溜したときのコンクリート重量が、空気圧P
によるバルブ装置2の閉塞力に打ち勝つて自動的
に開弁の如く作用して滞溜コンクリートの一部を
次のバルブ装置2の方に落下させ、それが順次繰
返されてコンクリート5が供給されて行く。第1
図a,b,cおよびdはこの状態を示すものであ
つて、バルブ装置2は空気圧Pの供給を受けてシ
ユート1を所定間隔毎に閉塞状態にしている。い
まコンクリート5が上部より供給されると第1番
目に位置するバルブ装置2により閉塞されたシユ
ート1の内部上方にコンクリート5は第1図aに
示す如く滞溜する。ついで、この滞溜コンクリー
ト5が一定量に達すれば滞溜コンクリート5の自
重によりバルブ装置2は開方向に押し拡げられて
滞溜コンクリート5の一部は第1番目のバルブ装
置を通過し、第2番目のバルブ装置2で閉塞され
たシユート1の内部上方に第1図bの如く滞溜す
る。コンクリート5が順次供給されるに従つて第
2番目のバルブ装置2で閉塞されたシユート1の
内部上方に滞溜するコンクリート5の量が第1図
cに示す如く増加する。 Therefore, the valve function of the valve device 2 is closed when the tube 4 is inflated by the air pressure P and crushes the chute 1 and blocks the concrete passage. The weight of concrete when a certain amount of concrete 5 accumulates inside the chute 1 partitioned by the valve device 2 which is closed at 2 is the air pressure P.
It overcomes the closing force of the valve device 2 caused by the valve device 2 and automatically acts like a valve opening, causing a part of the accumulated concrete to fall toward the next valve device 2, and this is repeated one after another to supply concrete 5. go. 1st
Figures a, b, c and d show this state, in which the valve device 2 is supplied with air pressure P and closes the chute 1 at predetermined intervals. When the concrete 5 is now supplied from above, the concrete 5 accumulates in the upper part of the inside of the chute 1 which is closed by the first valve device 2, as shown in FIG. 1a. Then, when a certain amount of accumulated concrete 5 is reached, the valve device 2 is pushed open in the opening direction by the weight of the accumulated concrete 5, and a part of the accumulated concrete 5 passes through the first valve device, and then the valve device 2 is opened. It accumulates in the upper part of the inside of the chute 1 which is closed by the second valve device 2, as shown in FIG. 1b. As the concrete 5 is sequentially supplied, the amount of concrete 5 accumulated in the upper part of the inside of the chute 1 closed by the second valve device 2 increases as shown in FIG. 1c.
ついで第2番目のバルブ装置2で閉塞されたシ
ユート1の内部上方に滞溜するコンクリート5が
一定量に達すれば上述したと同様に第2番目のバ
ルブ装置2は開方向に押し拡げられて滞溜コンク
リート5の一部は第1図dに示した如く第3番目
のバルブ装置2で閉塞されたシユート1の内部上
方に落下して行く。 Then, when the concrete 5 accumulated in the upper part of the inside of the chute 1 closed by the second valve device 2 reaches a certain amount, the second valve device 2 is pushed open in the opening direction and the concrete 5 accumulates. A portion of the pooled concrete 5 falls into the upper part of the inside of the chute 1 which is closed by the third valve device 2, as shown in FIG. 1d.
上記の作用が繰り返されてコンクリート1は供
給されるため、コンクリート5に於いて考察しな
ければならない落差は、バルブ装置2の配設され
ている所定間隔ということとなり、コンクリート
骨材の分離もなく、高落差による衝撃の問題も解
決する。 Since the above action is repeated and the concrete 1 is supplied, the head that must be considered for the concrete 5 is the predetermined interval at which the valve device 2 is arranged, and there is no separation of concrete aggregate. This also solves the problem of impact caused by high drops.
なお、シユート1は少なくともバルブ装置2挿
通部分すなわち所定間隔毎に可撓性でなければな
らない。 Note that the chute 1 must be flexible at least at the portion through which the valve device 2 is inserted, that is, at predetermined intervals.
またバルブ装置2の一例は第2図にその断面を
示した如く繞囲枠3はヒンジ6にて両開きに取付
け取りはずしに便なるように2分割構成とし、7
は繞囲枠3を閉止するためのボルト・ナツトを示
す。4は挿通されたシユート部1をとり囲む態様
に繞囲枠3に内装したチユーブで、チユーブ4の
空気孔は繞囲枠3に設けた穿孔に取付けられる口
金具8を装着し、この口金具8を通してエアホー
ス9に連結されていて、エアホース9を通して空
気圧の供給を受けるように構成されている。な
お、10はエアホース9の保護カバーである。 Further, in an example of the valve device 2, as shown in the cross section in FIG. 2, the enclosing frame 3 is divided into two parts with a hinge 6 to facilitate installation and removal.
indicates bolts and nuts for closing the surrounding frame 3. Reference numeral 4 denotes a tube built into the surrounding frame 3 so as to surround the inserted chute portion 1, and the air hole of the tube 4 is fitted with a fitting 8 which is attached to a hole provided in the surrounding frame 3. It is connected to an air hose 9 through the air hose 8 and is configured to receive air pressure through the air hose 9. Note that 10 is a protective cover for the air hose 9.
本発明は、上記したバルブ付シユートを用い
て、その打設範囲を拡大したコンクリート打設装
置を提供することを目的とするものであつて、そ
の要旨とするところは、門型走行ガーターのガー
タートラスの一方の片半部下位に走行自在に設け
られ一端側に第1のホツパを介して可撓性材また
は所定間隔毎に可撓性材からなるシユートとシユ
ートの所定間隔毎にシユート外周に捲着態様に設
けられて空気圧の供給を受けてシユートを閉塞す
るバルブ作用をするバルブ装置とからなるバルブ
付シユートを連結した走行コンベヤと、門型走行
ガーターのガータートラスの他方の片半部上位に
トラス基端からほぼ中央部にわたつて配された固
定コンベヤと、固定コンベヤ先端から側方に位置
する走行コンベヤに搬送コンクリートを盛替える
樋と、門型走行ガーターのガータートラスに固着
され外部から搬入されたコンクリートを受け入
れ、固定コンベヤに供給する第2のホツパと、走
行コンベヤ配置側のガータートラス上を走行自在
とするクレーンとを備えたことを特徴とするコン
クリート打設装置とすることにより、移動可能な
走行コンベヤに固定したホツパ先端に固着したバ
ルブ付シユートを、前記走行コンベヤの移動でコ
ンクリートの打設位置に対応した位置にまで移動
させ、外部から供給されたコンクリートを前記走
行コンベヤ上に落して盛替えし、このコンクリー
トを前記バルブ付シユートを通して垂直に打設す
ると、高落差になるに従つてバルブ付シユートの
重量が増加し、シユートの下端を横に引いて所定
位置に打設するような従来の方法によるときは困
難であつたコンクリートの打設範囲が拡大され、
かつまた前記ホツパーの高さ位置を自由に変更可
能とすれば種々のコンクリート打設部位に容易に
対応させることができるとした点にある。 An object of the present invention is to provide a concrete pouring device that uses the above-described valved chute and has an expanded concrete pouring range. A flexible member or a chute made of flexible material is provided at a predetermined interval through a first hopper on one end side of the chute, which is movably provided below one half of the truss, and attached to the outer circumference of the chute at a predetermined interval. A traveling conveyor connected to a chute with a valve, which is comprised of a valve device that is arranged in a winding manner and acts as a valve to close the chute when supplied with air pressure, and the upper half of the other half of the garter truss of the gate-type traveling garter. There is a fixed conveyor arranged from the base end of the truss to almost the center, a gutter that transfers conveyed concrete from the tip of the fixed conveyor to a traveling conveyor located to the side, and a gutter fixed to the garter truss of the gate-shaped traveling garter and conveyed from the outside. By providing a concrete placing device characterized by comprising a second hopper that receives concrete carried in and supplies it to a fixed conveyor, and a crane that can freely travel on a garter truss on the side where the traveling conveyor is arranged, A chute with a valve fixed to the tip of a hopper fixed to a movable traveling conveyor is moved to a position corresponding to the concrete placement position by the movement of the traveling conveyor, and concrete supplied from the outside is placed on the traveling conveyor. When the concrete is poured vertically through the above-mentioned valved chute, the weight of the valved chute increases as the head becomes higher, and the lower end of the chute is pulled sideways and poured into the specified position. The range of concrete placement, which was difficult to achieve using conventional methods such as
Furthermore, if the height position of the hopper can be freely changed, it can be easily adapted to various concrete placement locations.
以下、これを図にもとづいて詳細に説明する。 This will be explained in detail below based on the drawings.
すなわち、第3図a,b,cおよびdは本発明
のコンクリート打設装置の実施例の構成を示す平
面図、正面図および部分図である。 That is, FIGS. 3a, b, c, and d are a plan view, a front view, and a partial view showing the structure of an embodiment of the concrete pouring apparatus of the present invention.
13は門型走行ガーターであり、たとえば建築
工事の仮設桟橋等を利用して設置してあるレール
14に設置され、ガーダ駆動用モータ15により
駆動されて自走する。 Reference numeral 13 denotes a gate-shaped traveling garter, which is installed on a rail 14 installed, for example, on a temporary pier for construction work, and is driven by a girder drive motor 15 to run on its own.
走行ガーター13のトラスの一方の片半部下位
にはレール16を固着し、レール16上を第1の
ホツパ17を固着したトロリー18が移動自在に
設けてある。ホツパ17の先端にはシユート1と
バルブ装置2とからなるバルブ付シユート11が
固着されており、ホツパ17に供給されたコンク
リートを打設位置に供給するようになつている。 A rail 16 is fixed to the lower half of one half of the truss of the traveling garter 13, and a trolley 18 to which a first hopper 17 is fixed is movably provided on the rail 16. A valved chute 11 consisting of a chute 1 and a valve device 2 is fixed to the tip of the hopper 17, and is adapted to supply concrete supplied to the hopper 17 to a pouring position.
一方、走行ガーター13には外部から搬入され
たコンクリートを受け入れる第2のホツパ19が
固着してあり、また走行ガーター13のトラスの
他方の片半部上位にはホツパ19の排出口に対応
する位置に一端が対向し、走行ガーター13に沿
つて他端が走行ガーター13のほぼ中央位にまで
延長された固定コンベヤ20が固着してある。 On the other hand, a second hopper 19 is fixed to the traveling garter 13 for receiving concrete brought in from outside, and a position corresponding to the discharge port of the hopper 19 is located above the other half of the truss of the traveling garter 13. A fixed conveyor 20 is fixedly fixed, with one end facing the running garter 13 and the other end extending along the running garter 13 to approximately the center of the running garter 13.
走行ガーター13のトラス内には移動可能に走
行コンベヤ21が装着してあり、走行コンベヤの
一端は第3図cに示す如くトロリー18とたとえ
ば連結ピン22により着脱自在に連結してある。
また連結ピン22によりトロリー18は走行コン
ベヤ21の他端とも連結することができる。従つ
て走行コンベヤの移動に従つてトロリー18は一
体として同時に移動する。 A traveling conveyor 21 is movably mounted within the truss of the traveling garter 13, and one end of the traveling conveyor is detachably connected to the trolley 18 by, for example, a connecting pin 22, as shown in FIG. 3c.
Further, the trolley 18 can be connected to the other end of the traveling conveyor 21 by the connecting pin 22. Therefore, as the traveling conveyor moves, the trolley 18 moves simultaneously as a unit.
固定コンベヤ20の他端と、走行コンベヤ21
の上面との間にはたとえば樋23により連絡さ
れ、固定コンベヤ20にて搬送されたコンクリー
トは樋23を通つて走行コンベヤ21の上面に排
出されるように構成する。 The other end of the fixed conveyor 20 and the traveling conveyor 21
For example, a gutter 23 communicates with the upper surface, and the concrete conveyed by the fixed conveyor 20 is configured to be discharged to the upper surface of the traveling conveyor 21 through the gutter 23.
走行ガーター13の走行コンベヤ21配置側上
部には移動可能にシユート設置用クレーン24を
設置する。そこで、シユート設置用クレーン24
の走行の障害とならないようにシユート設置用ク
レーン24の走行路からはずれた位置に固定コン
ベヤ20が位置し、かつ固定コンベヤ20の他端
上面は走行コンベヤ21の上面より高い位置とな
るように固定コンベヤの位置は選択してある。ク
レーン24を樋23の反対側で使用する場合は盛
替えする。 A chute installation crane 24 is movably installed at the upper part of the traveling garter 13 on the side where the traveling conveyor 21 is disposed. Therefore, the chute installation crane 24
The fixed conveyor 20 is located at a position away from the traveling path of the chute installation crane 24 so as not to obstruct the traveling of the chute, and the upper surface of the other end of the fixed conveyor 20 is fixed at a higher position than the upper surface of the traveling conveyor 21. The location of the conveyor has been selected. If the crane 24 is to be used on the opposite side of the gutter 23, it must be rearranged.
まず、走行コンベヤ21および走行ガーター1
3の位置を移動させてバルブ付シユート11の先
端がコンクリート打設位置に対応するように設定
する。この場合、第3図bに示す如く走行ガータ
ー13の中央から左側にコンクリート打設位置が
あるときは走行コンベヤとトロリー18との関係
は第3図bの実線の如くでよいが、コンクリート
位置が走行ガーターの中央から右側にあるときは
走行コンベヤ21の他端にトロリー18を連結す
る。 First, the traveling conveyor 21 and the traveling garter 1
3 is moved so that the tip of the valved chute 11 corresponds to the concrete placement position. In this case, if the concrete placement position is on the left side from the center of the traveling garter 13 as shown in FIG. 3b, the relationship between the traveling conveyor and the trolley 18 may be as shown by the solid line in FIG. 3b, but the concrete position is A trolley 18 is connected to the other end of the traveling conveyor 21 when it is on the right side from the center of the traveling garter.
なお、バルブ付シユート11の位置移動に際
し、その移動路中に障害物がある場合は、シユー
ト設置用クレーン24のウインチでバルブ付シユ
ート11を吊り上げて障害物をかわせばよい。 In addition, when moving the position of the valved chute 11, if there is an obstacle in the movement path, the valved chute 11 may be hoisted up by the winch of the chute installation crane 24 to avoid the obstacle.
そこで、たとえばミキサー車などにより外部か
ら搬入されたコンクリートはホツパ19に投入さ
れ、ホツパ19から排出したコンクリートは固定
コンベヤ20および樋23を経由して走行コンベ
ヤ21上に搬送される。走行コンベヤ21上のコ
ンクリートは走行コンベヤ21によりホツパ17
を介してバルブ付シユート11を通り所定位置に
打設される。 Therefore, concrete carried in from the outside by a mixer truck or the like is put into the hopper 19, and the concrete discharged from the hopper 19 is conveyed onto the traveling conveyor 21 via the fixed conveyor 20 and the gutter 23. The concrete on the traveling conveyor 21 is transferred to the hopper 17 by the traveling conveyor 21.
It passes through the valved chute 11 and is cast into a predetermined position.
この場合、上記した如くトロリー18が第3図
bの実線の如く走行コンベヤの一端と連結されて
いるときと、トロリー18が走行コンベヤの他端
と連結されているときとでは走行コンベヤのベル
トの走行方向を逆にすることは勿論である。 In this case, as described above, when the trolley 18 is connected to one end of the traveling conveyor as shown by the solid line in FIG. 3b, and when the trolley 18 is connected to the other end of the traveling conveyor, the belt of the traveling conveyor is Of course, the direction of travel can be reversed.
また、シユート設置用クレーン24はシユート
設置時以外は天井クレーンとして利用することが
できる。 Further, the chute installation crane 24 can be used as an overhead crane except when installing a chute.
また、バルブ付シユートの先端側に第3図dに
示した如くバイブレータ吊下げアーム25を固定
し、バイブレータ吊下げアーム25にバイブレー
タ吊下げ装置26を介してバイブレータ27に装
着し、コンクリート打設時、バイブレータ27を
作用させてコンクリート締固め作業を軽減するこ
ともできる。 In addition, a vibrator hanging arm 25 is fixed to the tip side of the chute with a valve as shown in FIG. 3d, and a vibrator 27 is attached to the vibrator hanging arm 25 via a vibrator hanging device 26. , the concrete compaction work can also be reduced by operating the vibrator 27.
なお、以上本発明のコンクリート打設装置にお
いて走行コンベヤ21の移動の方法については説
明していないが、これは従来から用いられている
方法、たとえばドラムに巻回したワイヤのそれぞ
れの先端を走行コンベヤの枠体などの一端および
他端に各別に固着し、ドラムを回転させることに
より移動させる方法を用いればよい。 Although the method of moving the traveling conveyor 21 in the concrete placing apparatus of the present invention has not been described above, this method is similar to the conventional method, for example, by moving each tip of a wire wound around a drum to the traveling conveyor. A method may be used in which the drums are separately fixed to one end and the other end of a frame body, etc., and moved by rotating a drum.
以上説明した如く本発明によれば、バルブ付シ
ユート11を用いてそのコンクリートの打設範囲
が拡大され、また配筋上に設置するものがないた
め配筋を乱したり、汚したりすることがなくな
る。 As explained above, according to the present invention, the range of concrete placement is expanded by using the valved chute 11, and since there is nothing to install on the reinforcing bars, there is no need to disturb or pollute the reinforcing bars. It disappears.
また作業員の作業は容易となり労力の軽減にも
つながる他、打設コストも低下する効果がある。 Furthermore, the work of the workers becomes easier, which leads to a reduction in labor, and also has the effect of lowering the casting cost.
またさらに、上記は地下階用に適用する如く説
明したが地上階においても積層工法等においても
そのまゝ適用することができる。 Furthermore, although the above description has been made as if it were applied to a basement floor, it can be applied as is to a ground floor or to a layered construction method.
さらに、滞溜コンクリートの自重で自動的に開
弁するところのバルブ付シユートを水平方向に移
動させて用いたので、移動体にもかかわらず弁制
御機構の手当て不要という利点を有し、かつ、か
かる移動にもかかわらず何んらの措置を要するこ
となく確実にその上端供給口にコンクリートを搬
送し得るとしているので実際上極めて便利であ
る。 Furthermore, since the chute with a valve, which automatically opens due to the weight of accumulated concrete, is moved horizontally, it has the advantage of not requiring a valve control mechanism even though it is a mobile object. Despite such movement, concrete can be reliably conveyed to the upper end supply port without requiring any measures, which is extremely convenient in practice.
第1図a,b,cおよびdはバルブ付シユート
の構成およびその作用の説明に供する図、第2図
aおよびbはバルブ付シユートのバルブ装置の一
例の構成横断面図および縦断面図、第3図a,
b,cおよびdは本発明装置の実施例の平面図、
正面図および部分図である。
1……シユート、2……バルブ装置、11……
バルブ付シユート、13……走行ガーター、1
7,19……ホツパ、20……固定コンベヤ、2
1……走行コンベヤ。
FIGS. 1 a, b, c, and d are diagrams for explaining the configuration of a chute with a valve and its function; FIGS. 2 a and b are cross-sectional views and vertical sectional views of an example of a valve device of a chute with a valve; Figure 3a,
b, c and d are plan views of embodiments of the device of the present invention;
They are a front view and a partial view. 1...Chute, 2...Valve device, 11...
Chute with valve, 13... Traveling garter, 1
7,19...Hopper, 20...Fixed conveyor, 2
1... Traveling conveyor.
Claims (1)
片半部下位に走行自在に設けられ一端側に第1の
ホツパを介して可撓性材または所定間隔毎に可撓
性材からなるシユートとシユートの所定間隔毎に
シユート外周に捲着態様に設けられて空気圧の供
給を受けてシユートを閉塞するバルブ作用をする
バルブ装置とからなるバルブ付シユートを連結し
た走行コンベヤと、門型走行ガーターのガーター
トラスの他方の片半部上位にトラス基端からほぼ
中央部にわたつて配された固定コンベヤと、固定
コンベヤ先端から側方に位置する走行コンベヤに
搬送コンクリートを盛替える樋と、門型走行ガー
リーのガータートラスに固着され外部から搬入さ
れたコンクリートを受け入れ、固定コンベヤに供
給する第2のホツパと、走行コンベヤ配置側のガ
ータートラス上を走行自在とするクレーンとを備
えたことを特徴とするコンクリート打設装置。1. A chute made of flexible material or a chute made of flexible material provided at predetermined intervals through a first hopper on one end side, which is freely movable below one half of the garter truss of a gate-type traveling garter. A traveling conveyor that connects a chute with a valve, which is comprised of a valve device that is wound around the outer periphery of the chute at predetermined intervals and acts as a valve to close the chute when supplied with air pressure, and a garter truss of a gate-type traveling garter. A fixed conveyor is placed above the other half of the truss, extending from the base end of the truss to approximately the center of the truss. A concrete pouring device characterized by comprising: a second hopper fixed to a garter truss that receives concrete brought in from outside and supplies it to a fixed conveyor; and a crane capable of moving freely over the garter truss on the side where the traveling conveyor is arranged. Installation equipment.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP58116483A JPS59109664A (en) | 1983-06-28 | 1983-06-28 | Concrete casting apparatus |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP58116483A JPS59109664A (en) | 1983-06-28 | 1983-06-28 | Concrete casting apparatus |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS59109664A JPS59109664A (en) | 1984-06-25 |
| JPH0327701B2 true JPH0327701B2 (en) | 1991-04-16 |
Family
ID=14688225
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP58116483A Granted JPS59109664A (en) | 1983-06-28 | 1983-06-28 | Concrete casting apparatus |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS59109664A (en) |
-
1983
- 1983-06-28 JP JP58116483A patent/JPS59109664A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS59109664A (en) | 1984-06-25 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN110528410A (en) | The prefabricated equipment for supporting patient with burn of prefabricated assembled box culvert and installation method | |
| CN109869164A (en) | Combination hydraulic formwork jumbo pours the construction method of porous separate tunnel | |
| US4694465A (en) | Apparatus for automatically charging scrap into an arc furnace | |
| JPH0327701B2 (en) | ||
| US4171194A (en) | Plant for the production of concrete elements | |
| US1716125A (en) | Method of lining tunnels with concrete and apparatus therefor | |
| JP2001207449A (en) | Concrete casting equipment | |
| US5035592A (en) | Apparatus for concrete supply and form vibration | |
| JPH0328556B2 (en) | ||
| JPH0327702B2 (en) | ||
| CN113148695A (en) | Mine underground double-flow-guide automatic ore drawing device | |
| JPH0327700B2 (en) | ||
| JPH027954Y2 (en) | ||
| JP4422922B2 (en) | Concrete lining apparatus and concrete lining method | |
| JPH08254098A (en) | Stamping device of lining concrete for tunneling method | |
| JP7370213B2 (en) | Concrete pouring hopper | |
| CN212862960U (en) | Material conveying and weighing device in concrete production | |
| JPH0925724A (en) | Concrete placing hopper | |
| US4321223A (en) | Process for placing concrete through high head | |
| JP2002115397A (en) | Concrete conveying and placing device and manufacturing method for concrete pc floor board | |
| JP3235967B2 (en) | Tunnel forming method and tunnel for forming tunnel | |
| JP3395565B2 (en) | Dam concrete placement device and method | |
| JP4230645B2 (en) | Concrete embankment construction method and construction equipment | |
| RU21205U1 (en) | MEANS FOR UNLOADING RAILWAY CARS | |
| JP2842105B2 (en) | Superfluid concrete casting method |