Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPH0340765B2 - - Google Patents
[go: Go Back, main page]

JPH0340765B2 - - Google Patents

Info

Publication number
JPH0340765B2
JPH0340765B2 JP30069186A JP30069186A JPH0340765B2 JP H0340765 B2 JPH0340765 B2 JP H0340765B2 JP 30069186 A JP30069186 A JP 30069186A JP 30069186 A JP30069186 A JP 30069186A JP H0340765 B2 JPH0340765 B2 JP H0340765B2
Authority
JP
Japan
Prior art keywords
pile
steel pipe
piles
joint
erected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP30069186A
Other languages
Japanese (ja)
Other versions
JPS63156113A (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP30069186A priority Critical patent/JPS63156113A/en
Publication of JPS63156113A publication Critical patent/JPS63156113A/en
Publication of JPH0340765B2 publication Critical patent/JPH0340765B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は、土木建築分野における大深度基礎、
あるいは、土留壁等に用いられる建込杭の継杭構
築方法に関する。
[Detailed Description of the Invention] (Industrial Application Field) The present invention is applicable to deep foundations in the field of civil engineering and construction;
Alternatively, the present invention relates to a method for constructing joint piles for erected piles used for earth retaining walls and the like.

(従来の技術) 大深度の基礎や土留壁を築くために、長尺の鋼
管杭を使用する工法は広く採用されており、丸鋼
管や角鋼管の杭を用い打撃打込みや振動圧入、あ
るいは、油圧押込み工法によつて所要の深さに建
込む手段が適宜に実施されている。
(Conventional technology) Construction methods using long steel pipe piles are widely used to construct deep foundations and earth retaining walls. A means of constructing to a required depth using the hydraulic pushing method has been appropriately implemented.

而して、さらに大規模な設備を支持するため、
中掘り挿入工法も開発され、特公昭52−11131号
公報には既成段付杭の沈設方法(以下A発明とい
う)として大深度の基礎杭の建込み手段が開示さ
れている。
Therefore, in order to support even larger facilities,
A hollow insertion method has also been developed, and Japanese Patent Publication No. Sho 52-11131 discloses a method for erecting deep foundation piles as a method for sinking existing stepped piles (hereinafter referred to as Invention A).

第20図は、該A発明を説明するための長尺建
込杭の沈設状況を示す概略縦断面図である。筒状
ケーシング1を中掘り工法によつて地中の所定深
さまで沈設し、該筒状ケーシング1内に小径下杭
2a,2bを同様に水中掘削装置3および押圧装
置4等を利用して沈設すると共に、該小径下杭2
bに大径上杭5aを溶接手段等により継杭し、さ
らに、逐次中掘り建込みを実施して前記小径下杭
2a,2b、大径上杭5a,5bからなる段付杭
6を所定深さにまで建込む。
FIG. 20 is a schematic vertical cross-sectional view showing the state of sinking of a long erected pile for explaining invention A. A cylindrical casing 1 is sunk to a predetermined depth in the ground by a hollow digging method, and small-diameter lower piles 2a and 2b are similarly sunk into the cylindrical casing 1 using an underwater excavation device 3, a pressing device 4, etc. At the same time, the small diameter lower pile 2
A large-diameter upper pile 5a is attached to b by welding means, etc., and stepped piles 6 consisting of the small-diameter lower piles 2a, 2b and large-diameter upper piles 5a, 5b are formed by sequentially digging and erecting. Build deep.

その後、前記筒状ケーシング1を引抜き、該段
付杭6の外周面と孔壁間に充填剤を充填する方法
であつて、基礎杭の上部に作用する鉛直荷重と水
平荷重は前記大径上杭に負担させ、主として鉛直
荷重を負担するのみで良い基礎杭下部には、前記
小径下杭をあてると言う、理想的な段付杭を効率
よく沈設する手段を提供している。
Thereafter, the cylindrical casing 1 is pulled out and a filler is filled between the outer peripheral surface of the stepped pile 6 and the hole wall, and the vertical load and horizontal load acting on the upper part of the foundation pile are applied to the large diameter. The present invention provides a means for efficiently sinking ideal stepped piles by applying the small-diameter lower pile to the lower part of the foundation pile, which only needs to bear the vertical load.

(発明が解決しようとする問題点) 前記A発明は、筒状ケーシング1を地上に立設
し、圧入した後、泥水工法によつて内部を掘削し
て中空化する初期工程に引続き、小径下杭を建込
み、中掘り工法によつて沈設する第2工程が終わ
つた時点で、円錐台状に形成された大径上杭の下
端と小径下杭の上端を溶接する手段を採用してお
り、前記円錐台状に加工するコストと溶接コスト
が嵩むほか、作業時間が意外に長くなるという問
題点がある。
(Problems to be Solved by the Invention) In the invention A, after the cylindrical casing 1 is erected on the ground and press-fitted, following the initial process of excavating the inside to make it hollow using the muddy water method, At the end of the second step of erecting the piles and sinking them using the medium digging method, we use a method of welding the lower end of the large-diameter upper pile, which is shaped like a truncated cone, and the upper end of the small-diameter lower pile. However, there are problems in that the cost of processing the truncated cone and the welding cost are high, and the working time is unexpectedly long.

また、段付杭の沈設が終わつた後、前記筒状ケ
ーシング1を引抜く工程と段付杭外周面と孔壁間
に充填材(通常はコンクリートを用いる)を充填
する工程があり、共に作業時間が長くなること
と、特殊な工具が必要であるため作業費が高くな
るという問題点があり、多数の長尺建込杭を用い
ることが必要な井筒構築の如き基礎杭築造には経
済的見地から採用できず改良方法が望まれてい
た。
In addition, after the stepped pile has been set, there is a step of pulling out the cylindrical casing 1 and a step of filling a filler (usually concrete) between the outer circumferential surface of the stepped pile and the hole wall. There are problems in that it takes a long time and requires special tools, which increases the work cost, and it is not economical to construct foundation piles such as Izutsu construction, which requires the use of a large number of long piles. From this point of view, it could not be adopted, and an improved method was desired.

(問題点を解決するための手段) 本発明は、短期間に建込杭を所定の深さに沈設
することが可能で、しかも、極めて経済的に多数
の杭を構築できる方法を提供することを目的と
し、また、非常に建込み深さの大きい基礎杭を迅
速に、かつ、経済的に構築できる方法の提供を他
の目的とするものであり、さらに、異なつた他の
目的は大重量建造物の井筒型基礎の構築に適した
方法を提供することにある。
(Means for Solving the Problems) The present invention provides a method that allows erecting piles to be sunk to a predetermined depth in a short period of time, and also allows building a large number of piles extremely economically. The purpose of this invention is to provide a method for quickly and economically constructing foundation piles with very large depths, and its other purpose is to provide a method for quickly and economically constructing foundation piles with very large depths. The object of the present invention is to provide a method suitable for constructing well-shaped foundations for buildings.

本発明は、前述の目的を達成する方法であり、
管径を異にする複数の鋼管杭を用いて建込杭を構
築するに際し、あらかじめ各鋼管杭の継部内周面
に突起を配設しておき、地盤を掘削しながら前記
鋼管杭を径の大きいものから順次内挿しながら圧
入してお互の継部が重なるように建込み、最終杭
を所定建込深度に建込んだ後に、鋼管杭内部にコ
ンクリートを充填することを特徴とする建込杭の
継杭構築方法を要旨とする。
The present invention is a method for achieving the above objects,
When constructing an erected pile using multiple steel pipe piles with different pipe diameters, a protrusion is placed in advance on the inner peripheral surface of the joint of each steel pipe pile, and while excavating the ground, the steel pipe pile is A construction method characterized by inserting and press-fitting the piles in order from the largest piles so that their joints overlap, and after erecting the final pile to a predetermined depth, filling the inside of the steel pipe pile with concrete. The summary is the method of constructing joint piles.

(作用) 本発明の方法は、大径杭を中掘圧入した後、逐
次径小杭を中堀圧入によつて内挿しつつ縦設する
ので、方法が極めて簡便でありながら、大深度の
長尺杭を容易に構築することが可能で、掘削量も
前述のA発明に比し少量で済む。
(Function) In the method of the present invention, after a large-diameter pile is press-fitted into a medium excavation, small-diameter piles are sequentially inserted and vertically installed by press-fitting into a medium excavation. It is possible to easily construct piles, and the amount of excavation can be reduced compared to the above-mentioned Invention A.

また、継杭手段が杭相互をコンクリート接合す
る手段であるため、非常に簡便であり、溶接手段
に比し費用が著しく低額である。
Furthermore, since the connecting pile means is a means for joining the piles together with concrete, it is very simple and costs significantly less than welding means.

このとき、継杭にあたり、継部部分充填手段を
採用する場合は、コンクリート費用をさらに低く
することが出来る。
At this time, if a method of partially filling the joint is used for the joint pile, the concrete cost can be further reduced.

また、前述のA発明のように、筒状ケーシング
を圧入し再び引く抜くような複雑な工程が無いの
で、作業用装置や工具等の費用も少額である。
Furthermore, since there is no complicated process of press-fitting the cylindrical casing and pulling it out again as in the above-mentioned invention A, the cost of working equipment, tools, etc. is also small.

さらに、耐荷重性の点については、前記段付杭
と同様に鉛直荷重と水平荷重は上部の大径杭に負
担させ、下部において、主として鉛直荷重に対し
てのみ負担すれば目的が達せられる杭について
は、設計の限度において、最小径の杭を採用する
手段により経済性を発揮させることが出来る。
Furthermore, in terms of load-bearing capacity, similar to the stepped piles, vertical loads and horizontal loads can be borne by the large-diameter piles at the top, and the purpose can be achieved by mainly bearing only the vertical loads at the bottom. For this reason, economic efficiency can be achieved by using piles with the smallest diameter within the limits of the design.

而して、本発明では、円錐台状に加工した部材
を用いて管径の異なる鋼管杭を溶接することがな
いので、鋼管杭の種別に対する制約を考慮する必
要が無く、既製品、新製品を問わず、目的に応じ
て最適な鋼管杭を自由に選択し、経済設計を行う
ことが出来る。
Therefore, in the present invention, there is no need to weld steel pipe piles with different pipe diameters using a member processed into a truncated cone shape, so there is no need to consider restrictions on the type of steel pipe piles, and it is possible to use ready-made products or new products. Regardless of the purpose, you can freely select the most suitable steel pipe pile and perform economical design.

また、本発明において、上部に鋼管矢板(角
型、丸型いずれでも良い)を採用すると、構造的
に非常に頑丈で、水平荷重や鉛直荷重に対して優
秀な性能を備えた筒手用や土留用の基礎を経済的
に構築することが出来る。
In addition, in the present invention, if a steel pipe sheet pile (either square or round type is used) is used for the upper part, it is structurally very strong and has excellent performance against horizontal and vertical loads. Foundations for earth retaining can be constructed economically.

(実施例) 以下、本発明を図面に示す実施例に従つて詳細
に説明する。
(Example) Hereinafter, the present invention will be described in detail according to an example shown in the drawings.

第1図は、本発明において、鋼管杭を中堀圧入
する途中工程を示す概略部分断面図であつて、建
込作業車7を用い、アースオーガ8、アースオー
ガ駆動装置9、押圧装置10を介して上部鋼管杭
11を中堀圧入法により建込んだ後、下部鋼管杭
12に支持管13を接続して、中堀圧入を実施し
ている状況を示すものであるが、それ迄の工程順
序を第2図a,b,cに示す。
FIG. 1 is a schematic partial sectional view showing an intermediate process of press-fitting a steel pipe pile into a trench in the present invention. After the upper steel pipe pile 11 is erected by the hollow press-in method, the support pipe 13 is connected to the lower steel pipe pile 12, and the hollow press-in is carried out. Shown in Figure 2 a, b, and c.

第2図aは、上部鋼管杭11の内部にアースオ
ーガ8を内挿して、中堀圧入を開始した状況を示
す概略部分断面図で、第2図bは、所定深さにま
で沈設し、内部土砂を排除した上部鋼管杭11の
中に、支持管13に接続された下部鋼管杭12を
挿入すると共に、該支持管13、下部鋼管杭12
の中にアースオーガ8を挿入し、中堀圧入を開始
した状況を示す概略部分断面図であり、第2図c
は、下部鋼管杭12を所定の深さにまで沈設し、
アースオーガ8を引抜く直前の状況を示す概略部
分断面図であつて、鋼管杭を3本以上沈設する場
合も同様な手順で実施するが、リーダ14やアー
スオーガ8については、適宜な長さのものを採用
することはいうまでも無い。
Fig. 2a is a schematic partial cross-sectional view showing the state in which the earth auger 8 is inserted into the inside of the upper steel pipe pile 11 and press-fitting into the trench has started, and Fig. 2b is a schematic partial cross-sectional view showing the state in which the earth auger 8 is inserted into the inside of the upper steel pipe pile 11 and press-fitting is started. The lower steel pipe pile 12 connected to the support pipe 13 is inserted into the upper steel pipe pile 11 from which earth and sand has been removed, and the support pipe 13 and the lower steel pipe pile 12 are
Fig. 2c is a schematic partial cross-sectional view showing the situation where the earth auger 8 is inserted into the hole and press-fitting is started;
The lower steel pipe pile 12 is sunk to a predetermined depth,
This is a schematic partial cross-sectional view showing the situation just before pulling out the earth auger 8. The same procedure is followed when sinking three or more steel pipe piles, but the leader 14 and the earth auger 8 are set to appropriate lengths. Needless to say, we will adopt the one from

次に、第3図〜第6図は、前述の中堀圧入によ
つて建込んだ上部鋼管杭11、下部鋼管杭12か
らなる長尺建込杭15の先端根固め、および、継
杭手順を示す概略断面図であつて、第3図に示す
ように、根固めロツド16を長尺建込杭15中に
挿入すると共に、支持管13の上部に高圧水注入
装置(図示せず)を取付け、根固めロツド16の
先端刃先部17から高圧水を噴射して鋼管内側の
洗浄と先端空腔18の掘削を行い、ついで、水か
らセメントミルクに切替えて、第4図に示すよう
に球根19を構成し、支持管13を引抜く。
Next, FIGS. 3 to 6 show the steps for hardening the tip of the long erected pile 15, which consists of the upper steel pipe pile 11 and the lower steel pipe pile 12, which were erected by the above-mentioned hollow press-in method, and the connecting pile procedure. As shown in FIG. 3, the foot protection rod 16 is inserted into the long erected pile 15, and a high-pressure water injection device (not shown) is attached to the upper part of the support pipe 13. , high-pressure water is injected from the cutting edge 17 of the root hardening rod 16 to clean the inside of the steel pipe and excavate the cavity 18 at the tip. Then, the water is switched to cement milk, and the bulb 19 is sprayed as shown in FIG. , and then pull out the support tube 13.

次に、第5図に示すように、下端に閉塞板20
を有する鉄筋篭21を鉄線22a,22bを用い
て長尺建込杭15の継部23(詳細は後述する)
の位置に吊下げる。
Next, as shown in FIG.
A reinforcing bar basket 21 having a structure is connected to a joint 23 of a long erected pile 15 using iron wires 22a and 22b (details will be described later).
hang it in position.

第5図の24a,24bは、該鉄線22a,2
2bの止金具を示す。ついで、第6図のように前
記継部23にトレミー管(図示せず)によつてコ
ンクリートを部分充填25して長尺建込杭15の
継杭を行うが、コンクリートが固化した後、前記
鉄線22a,22bは上部鋼管杭11中に切落と
す。この実施例では、使用コンクリートも少量で
済み、工期も極めて短期間とすることが出来る。
24a and 24b in FIG. 5 are the iron wires 22a and 2
2b is shown. Next, as shown in FIG. 6, the joint portion 23 is partially filled with concrete 25 using a tremie pipe (not shown), and the long erected pile 15 is jointed. The iron wires 22a and 22b are cut into the upper steel pipe pile 11. In this embodiment, only a small amount of concrete can be used, and the construction period can be extremely short.

さて、第7図は、前述の上部鋼管杭11と下部
鋼管杭12に加えて、さらに先端鋼管杭26を継
杭した長尺建込杭27の概略断面図であり、80〜
100mの大深度用の例に係るこの例では、長尺建
込杭27の杭内全部にコンクリートを充填してお
り、鉄筋については、適宜に挿入して良いが、必
要性が薄い場所では鉄筋を省略することも自由で
ある。
Now, FIG. 7 is a schematic cross-sectional view of a long erected pile 27 in which, in addition to the above-mentioned upper steel pipe pile 11 and lower steel pipe pile 12, a tip steel pipe pile 26 is attached.
In this example, which is for a large depth of 100 m, the entire inside of the long erected pile 27 is filled with concrete, and reinforcing bars may be inserted as appropriate, but reinforcing bars may be inserted in places where there is little need for reinforcing bars. You are also free to omit it.

本発明では、2本の径の相違する鋼管杭を縦設
し縦杭した場合、即ち、第3図の下部鋼管杭12
を最終杭と言い、第7図のように3本の径の相違
する鋼管杭を継杭した場合には先端鋼管杭26を
最終杭という。
In the present invention, when two steel pipe piles with different diameters are installed vertically, that is, the lower steel pipe pile 12 in FIG.
is called the final pile, and when three steel pipe piles with different diameters are connected as shown in FIG. 7, the tip steel pipe pile 26 is called the final pile.

また、本発明は管径を異にする鋼管杭を逐次内
挿しつつ縦設するので、最初に沈設する鋼管杭が
最大径鋼管杭となり、後述のように最初に角鋼管
矢板を沈設する場合は該角鋼管矢板が最大径鋼管
杭となる。もつとも、同径の鋼管杭を連結する場
合は、それらを総称して最大径鋼管杭という。こ
の場合、管径は角鋼管矢板の短辺の長さをいう。
In addition, since the present invention vertically installs steel pipe piles with different diameters by sequentially inserting them, the first steel pipe pile to be sunk becomes the largest diameter steel pipe pile. The square steel pipe sheet pile becomes the maximum diameter steel pipe pile. However, when steel pipe piles of the same diameter are connected, they are collectively referred to as the maximum diameter steel pipe pile. In this case, the pipe diameter refers to the length of the short side of the square steel pipe sheet pile.

次に、継杭手段の詳細についてさらに説明す
る。
Next, details of the joint pile means will be further explained.

第8図は、第7図の継部23の周辺部Aの部分
拡大断面図であつて、上部鋼管杭11が充分な深
度に達するまでに沈設されていた場合、下部鋼管
杭12は鉛直荷重のみを負担すれば良く、継部2
3において剛性の高い継杭手段を講ずる必要は薄
いので、第8図に示すように上部鋼管杭11と下
部鋼管杭12が適宜間隔、たとえば、500〜1000
mm程度重なり合うようにし、コンクリート充填に
よつて接合すれば、強度的に充分目的を達成する
ことが可能である。
FIG. 8 is a partially enlarged cross-sectional view of the peripheral area A of the joint 23 in FIG. You only need to pay for the joint part 2.
3, there is little need to provide a highly rigid connecting pile means, so the upper steel pipe pile 11 and the lower steel pipe pile 12 are spaced appropriately, for example, 500 to 1000, as shown in FIG.
If they are overlapped by about 1/2 mm and joined by concrete filling, it is possible to achieve the purpose sufficiently in terms of strength.

本発明において、継部とは鋼管杭の上、下端に
ついて前述のように重なり合う部分を継部とい
い、継杭とは該継部を利用して上、下鋼管杭を接
合することをいう。
In the present invention, the joint section refers to the overlapping portion of the upper and lower ends of the steel pipe pile as described above, and the joint pile refers to the joining of the upper and lower steel pipe piles using the joint section.

而して、継部23の接合強度を高めたい場合
は、第9図の概略断面図に示すように、上部鋼管
杭11の内側下端や下部鋼管杭12の内側上端に
適宜寸法のジベル28a,28bを溶着するか、
あるいは、第10図の部分切欠斜視図に示すよう
に環状棒鋼29a,29bを溶着するほか、第1
1図の部分断面図に示すように螺旋状突起30を
備えた鋼管杭31を採用する。
If it is desired to increase the joint strength of the joint 23, as shown in the schematic cross-sectional view of FIG. Weld 28b or
Alternatively, in addition to welding the annular steel bars 29a and 29b as shown in the partially cutaway perspective view of FIG.
As shown in the partial sectional view of FIG. 1, a steel pipe pile 31 provided with a spiral protrusion 30 is employed.

本発明では、前記ジベル28a,28bや環状
棒鋼29a,29bおよび螺旋状突起30のよう
に、形状寸法の異なる鋼管杭の間の荷重伝達をコ
ンクリートを介して行うにあたり、鋼管杭とコン
クリートの間の付着せん断強度を高める部材を突
起と総称する。
In the present invention, when carrying out load transmission between steel pipe piles with different shapes and dimensions, such as the dowels 28a and 28b, the annular steel bars 29a and 29b, and the spiral protrusion 30, through concrete, the Members that increase adhesive shear strength are collectively referred to as protrusions.

該突起を設ける場合は、次段の鋼管杭の挿入や
アースオーガ、あるいは、根固めロツドの内挿に
支障を生じさせないような形状、寸法のものを採
用することが望ましい。
When providing such protrusions, it is desirable to adopt a shape and size that does not cause any hindrance to the insertion of the next stage steel pipe pile, earth auger, or foot protection rod.

また、前記結合にあたつて継部の部分充填を行
う際は、第9図に示すように閉塞板32を用いる
が、その係止手段は第5図の例と同様である。
Further, when partially filling the joint portion during the connection, a closing plate 32 is used as shown in FIG. 9, and its locking means are the same as in the example shown in FIG. 5.

次に、本発明の方法を大型化学装置の基礎築造
に利用した例について説明する。
Next, an example in which the method of the present invention is utilized for constructing the foundation of a large-scale chemical device will be described.

第12図は該基礎の構造を示す概略斜視図で、
化学装置33(説明の都合上1部分のみを図示す
る)は補強支持脚34a〜34cを備えた基礎コ
ンクリート版35上に固定され、該基礎コンクリ
ート版35は継手を有する角鋼管矢板36(説明
の都合上1部材のみに符号を付す)を連結してな
る井筒パネル37によつて支持されている。
FIG. 12 is a schematic perspective view showing the structure of the foundation,
The chemical equipment 33 (only one part is shown for the sake of explanation) is fixed on a basic concrete slab 35 with reinforcing support legs 34a to 34c, which has square steel pipe sheet piles 36 with joints (in the explanation). For convenience, only one member is designated by a reference numeral).

また、前記角鋼管矢板36には下部鋼管杭38
が前述の中堀圧入によつて全体の半数分だけ縦設
されており(第19図参照)、その先端には球根
19が構築され、鉛直荷重を支えている。
In addition, a lower steel pipe pile 38 is attached to the square steel pipe sheet pile 36.
is vertically installed by half of the total length by the above-mentioned hollow press-fit (see Fig. 19), and a bulb 19 is constructed at its tip to support the vertical load.

この実施例では、井筒パネル37の長さを30.5
m(地上部4.5m、地下部26m)とし、下部鋼管
杭38の長さを30mとし、それぞれを1m程度重
なり合うようにした。
In this embodiment, the length of the Izutsu panel 37 is 30.5
m (4.5 m above ground, 26 m underground), and the length of the lower steel pipe piles 38 was 30 m, with each pile overlapping about 1 m.

また、井筒パネル37の直径を略12.6mとし、
上部鋼管杭として角鋼管矢板は外径800mm、板厚
12mmのものを採用し、下部鋼管杭38には外径
700mm、板厚12mmのものを採用した。
In addition, the diameter of the well panel 37 is approximately 12.6 m,
The square steel pipe sheet pile used as the upper steel pipe pile has an outer diameter of 800 mm and a plate thickness.
The lower steel pipe pile 38 has an outer diameter of 12 mm.
A 700mm and 12mm plate thickness was used.

前述の井筒パネル37の長さを30.5mとするた
め、単位角鋼管矢板として15mと15.5mのものを
溶接手段によつて連結し、前述の第2図a〜cに
示した手段と略同一の手段で沈設した。
In order to set the length of the above-mentioned well panel 37 to 30.5 m, unit square steel pipe sheet piles of 15 m and 15.5 m were connected by welding means, which is approximately the same as the means shown in Fig. 2 a to c above. It was deposited by means of

その状況を第13図〜第15図に示す。第13
図は角鋼管矢板36a,36bを溶接連結し、ア
ースオーガ8を用いて中堀圧入している状況を示
し、第14図は角鋼管矢板36a,36bを所定
深さに沈設した状況を、第15図は鋼管杭38a
を角鋼管矢板36a,36bに内挿し、支持管1
3を利用して中堀圧入した状況を示すものであつ
て、前記角鋼管矢板としては第16図、第17
図、第18図の概略平面図に示す角鋼管矢板36
c,36b,36eを適宜単独、もしくは、組合
せて用いる。
The situation is shown in FIGS. 13 to 15. 13th
The figure shows a situation in which square steel pipe sheet piles 36a and 36b are welded together and press-fitted into a hollow using an earth auger 8. The figure shows steel pipe pile 38a
is inserted into the square steel pipe sheet piles 36a and 36b, and the support pipe 1
16 and 17 are used as the square steel pipe sheet piles.
, the square steel pipe sheet pile 36 shown in the schematic plan view of FIG.
c, 36b, and 36e are used alone or in combination as appropriate.

第19図は、1実施例にかかる井筒パネル37
aの部分平面図で、角鋼管矢板36eの内側に鋼
管杭38bを1つおきに挿入したもので、所望の
井筒の曲率に容易に適合させることが可能である
と共に、水平荷重に対する強度が高く、建造物に
対する安定した支持力を期待することが出来る。
FIG. 19 shows the well panel 37 according to one embodiment.
In the partial plan view of a, steel pipe piles 38b are inserted every other square steel pipe pile 36e inside the square steel pipe sheet pile 36e, and it can be easily adapted to the desired curvature of the well, and has high strength against horizontal loads. , stable supporting capacity for buildings can be expected.

(発明の効果) 本発明の方法は、掘削量が少ないので長尺建込
杭を短期間に、かつ使用するコンクリートが少な
く、鋼管同志の溶接が少ないので経済的に構築で
きるため、大形構造物の基礎や土留を構成するに
あたり、経済的効果が極めて大きく、また土木力
学的な強度の点についても、従来法に比して何等
の遜色も無いので、その効果は極めて大である。
(Effects of the Invention) The method of the present invention requires only a small amount of excavation, so long piles can be constructed in a short period of time, less concrete is used, and there is less welding between steel pipes, so it can be constructed economically. When constructing foundations and earth retaining structures, the economic effect is extremely large, and in terms of civil engineering strength, there is no inferiority to conventional methods, so the effect is extremely large.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明にかかる鋼管杭の中堀圧入途中
の工程を示す概略部分断面図、第2図a,b,c
は同じく中堀圧入の工程順別の状況を示す概略部
分断面図、第3図乃至第6図は本発明にかかる先
端根固めおよび継杭手順を示す概略部分断面図、
第7図は長尺建込杭の概略部分断面図、第8図は
継部およびその周辺部の部分拡大断面図、第9図
は継部に突起を設けた部分拡大断面図、第10図
は環状棒鋼からなる突起を設けた継部部分切欠斜
視図、第11図は螺旋状突起を備えた鋼管杭の部
分断面図、第12図は化学装置の基礎構造の概略
斜視図、第13図〜第15図は井筒パネルの構築
手順を示す説明図、第16図〜第18図は角鋼管
矢板の平面図、第19図は井筒パネルの部分平面
図、第20図は従来の長尺建込杭の沈設状況説明
図である。 1……筒状ケーシング、2a,2b……小径下
杭、3……水中堀削装置、4……押圧装置、5
a,5b……大径上杭、6……段付杭、7……建
込作業車、8……アースオーガ、9……アースオ
ーガ駆動装置、10……押圧装置、11……上部
鋼管杭、12……下部鋼管杭、13……支持管、
14……リーダ、15……長尺建込杭、16……
根固めロツド、17……先端刃先部、18……先
端空腔、19……球根、20……閉塞板、21…
…鉄筋篭、22a,22b……鉄線、23……継
部、24a,24b……止金具、25……部分充
填、26……先端鋼管杭、27……長尺建込杭、
28a,28b……ジベル、29a,29b……
環状棒鋼、30……螺旋状突起、31……鋼管
杭、32……閉塞板、33……化学装置、34a
〜34c……補強支持脚、35……基礎コンクリ
ート版、36,36a〜36e……角鋼管矢板、
37,37a……井筒パネル、38,38a,3
8b……下部角鋼管杭。
Fig. 1 is a schematic partial cross-sectional view showing the process of press-fitting a steel pipe pile according to the present invention, Fig. 2 a, b, c
3 to 6 are schematic partial sectional views illustrating the procedure of the tip cementing and connecting pile according to the present invention,
Figure 7 is a schematic partial cross-sectional view of a long built-in pile, Figure 8 is a partial enlarged cross-sectional view of the joint and its surrounding area, Figure 9 is a partial enlarged cross-sectional view of the joint with a protrusion, and Figure 10. 11 is a partial cross-sectional view of a steel pipe pile with a spiral projection; FIG. 12 is a schematic perspective view of the basic structure of a chemical equipment; FIG. 13 - Figure 15 is an explanatory diagram showing the construction procedure of Izutsu panels, Figures 16 to 18 are plan views of square steel pipe sheet piles, Figure 19 is a partial plan view of Izutsu panels, and Figure 20 is a conventional long construction. It is an explanatory diagram of the setting situation of pile piles. 1... Cylindrical casing, 2a, 2b... Small diameter lower pile, 3... Underwater excavation device, 4... Pressing device, 5
a, 5b...Large diameter upper pile, 6...Stepped pile, 7...Erection work vehicle, 8...Earth auger, 9...Earth auger drive device, 10...Press device, 11...Upper steel pipe Pile, 12... lower steel pipe pile, 13... support pipe,
14... Leader, 15... Long erected pile, 16...
Root hardening rod, 17... Tip cutting edge, 18... Tip cavity, 19... Bulb, 20... Obstruction plate, 21...
... Rebar basket, 22a, 22b ... iron wire, 23 ... joint, 24a, 24b ... fastener, 25 ... partial filling, 26 ... tip steel pipe pile, 27 ... long erected pile,
28a, 28b... Jibel, 29a, 29b...
Annular steel bar, 30...Spiral projection, 31...Steel pipe pile, 32...Closure plate, 33...Chemical device, 34a
~34c...Reinforcement support leg, 35...Foundation concrete plate, 36, 36a-36e...Square steel pipe sheet pile,
37, 37a...Izutsu panel, 38, 38a, 3
8b...Lower square steel pipe pile.

Claims (1)

【特許請求の範囲】 1 管径を異にする複数の鋼管杭を用いて建込杭
を構築するに際し、あらかじめ各鋼管杭の継部内
周面に突起を配設しておき、地盤を掘削しながら
前記鋼管杭を径の大きいものから順次内挿しなが
ら圧入してお互の継部が重なるように建込み、最
終鋼管杭を所定建込深度に建込んだ後に、前記鋼
管杭内部にコンクリートを充填することを特徴と
する建込杭の継杭構築方法。 2 下方の継部からその下部に閉塞板を配置し、
前記継部にコンクリートを充填し、順次上方の継
部にコンクリートを充填することを特徴とする特
許請求の範囲第1項記載の建込杭の継杭構築方
法。 3 鋼管杭内全部にコンクリートを充填すること
を特徴とする特許請求の範囲第1項記載の建込杭
の継杭構築方法。 4 鋼管杭の最上部に鋼管矢板を用いることを特
徴とする特許請求の範囲第2項または第3項記載
の建込杭の継杭構築方法。
[Scope of Claims] 1. When constructing a built-in pile using a plurality of steel pipe piles with different pipe diameters, a protrusion is placed in advance on the inner peripheral surface of the joint of each steel pipe pile, and the ground is excavated. Then, the steel pipe piles are inserted and press-fitted in order from the largest diameter, so that their joints overlap, and after the final steel pipe pile is erected to a predetermined depth, concrete is poured inside the steel pipe pile. A method for constructing a joint pile for an erected pile, which is characterized by filling the pile. 2 Place a blocking plate below the lower joint,
2. The method of constructing a joint pile for an erected pile according to claim 1, characterized in that the joint portion is filled with concrete, and the upper joint portions are sequentially filled with concrete. 3. A method for constructing a joint pile for an erected pile according to claim 1, characterized in that the entire inside of the steel pipe pile is filled with concrete. 4. A method for constructing a joint pile for an erected pile according to claim 2 or 3, characterized in that a steel pipe sheet pile is used at the top of the steel pipe pile.
JP30069186A 1986-12-17 1986-12-17 Joint pile construction of erected pile Granted JPS63156113A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP30069186A JPS63156113A (en) 1986-12-17 1986-12-17 Joint pile construction of erected pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP30069186A JPS63156113A (en) 1986-12-17 1986-12-17 Joint pile construction of erected pile

Publications (2)

Publication Number Publication Date
JPS63156113A JPS63156113A (en) 1988-06-29
JPH0340765B2 true JPH0340765B2 (en) 1991-06-20

Family

ID=17887916

Family Applications (1)

Application Number Title Priority Date Filing Date
JP30069186A Granted JPS63156113A (en) 1986-12-17 1986-12-17 Joint pile construction of erected pile

Country Status (1)

Country Link
JP (1) JPS63156113A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101775802B (en) * 2010-03-03 2012-02-22 长沙理工大学 Intermediate pile foundation suitable for karst area

Also Published As

Publication number Publication date
JPS63156113A (en) 1988-06-29

Similar Documents

Publication Publication Date Title
JP2011157812A (en) Retaining wall and construction method therefor
JP2007205161A (en) Retaining wall and its construction method
JP4812324B2 (en) Retaining wall and its construction method
JP2000352296A (en) Method o constructing passage just under underground structure
JP2003027462A (en) Construction method of underground continuous wall, and construction method of underground structure
JPH0340765B2 (en)
JPH04119837U (en) Underground structures to prevent liquefaction
JP5169638B2 (en) Construction method of underground structure
JP7275844B2 (en) WALL-LIKE STRUCTURE AND METHOD OF CONSTRUCTING WALL-LIKE STRUCTURE
JP2000355941A (en) Building and its construction method
JP7830792B2 (en) Buildings and their construction methods
JPH07279172A (en) Method for setting tie rod anchor in deep layer ground
JPH10131176A (en) Reinforcing method of existing pile by force-fit of outer winding steel pipe
JP3082054B2 (en) Large-scale, deep steel continuous basement wall and method of constructing the same
JP7640439B2 (en) Connection method between the support pile and the tendon and retaining structure
JPS6128774B2 (en)
JPH0559215B2 (en)
KR101150795B1 (en) The deepened sheet plate and the method of installation of the same
JPS58199925A (en) Construction of underground wall and underground foundation pile with brace
KR20200005837A (en) Underground vertical structure construction method using top-down method and segments used in the same
JPH0672517B2 (en) How to build a shaft
JPH07324329A (en) Construction method of water blocking wall with steel tube columns
JPH10152853A (en) Construction method of underground structure and structural member used therefor
JP3082053B2 (en) Large-scale, deep steel continuous basement wall and method of constructing the same
JP2555796B2 (en) Underground construction method using hollow PC columns

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees