JPH0341640B2 - - Google Patents
[go: Go Back, main page]

JPH0341640B2 - - Google Patents

Info

Publication number
JPH0341640B2
JPH0341640B2 JP58121438A JP12143883A JPH0341640B2 JP H0341640 B2 JPH0341640 B2 JP H0341640B2 JP 58121438 A JP58121438 A JP 58121438A JP 12143883 A JP12143883 A JP 12143883A JP H0341640 B2 JPH0341640 B2 JP H0341640B2
Authority
JP
Japan
Prior art keywords
segment
shield machine
tunnel
platform frame
invert
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP58121438A
Other languages
Japanese (ja)
Other versions
JPS6013199A (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP12143883A priority Critical patent/JPS6013199A/en
Publication of JPS6013199A publication Critical patent/JPS6013199A/en
Publication of JPH0341640B2 publication Critical patent/JPH0341640B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は、インバートセグメントを用いたト
ンネル掘進方法に関するものであり、特に、シー
ルドマシンによつて円形に掘進されるトンネルの
掘進方法に関するものである。
[Detailed Description of the Invention] [Field of Industrial Application] The present invention relates to a method for excavating a tunnel using an invert segment, and in particular to a method for excavating a tunnel excavated in a circular manner by a shield machine. be.

〔従来の技術〕[Conventional technology]

従来のシールド工法は、シールドマシンの推進
に伴つて、該シールドマシンの直後に油圧パワー
ユニツト、油タンク、電気の動力盤並びに制御盤
及びずり搬送ベルトコンベア等を装備した後続台
車を掘進とともに移行させて、該シールドマシン
の推進、ずりの搬出、セグメントの搬入及び組立
等の作業を連続的に行つている。
In the conventional shield construction method, as the shield machine advances, a subsequent truck equipped with a hydraulic power unit, oil tank, electric power panel, control panel, shear belt conveyor, etc. is moved immediately after the shield machine as it excavates. Operations such as propelling the shield machine, transporting shear, transporting and assembling segments are carried out continuously.

又、その後方においては、ずり車、セグメント
運搬台車等を往動、復動させ、ずりの搬出及びセ
グメントの搬入等の作業が行われている。
Further, behind it, a shear wheel, a segment transport cart, etc. are moved forward and backward, and work such as carrying out shears and carrying in segments is performed.

更に、その後方に於ては、前記のずり車或はセ
グメント運搬台車等を後方へ、又、後方から前方
へ運行させるために、本線レールを設けて、該本
線レールに前記台車を走行させ、外部へずりを搬
出したり或は外部よりセグメント等の資材の搬入
を為している。
Further, at the rear thereof, in order to run the above-mentioned shear car or segment transport trolley, etc. to the rear and from the rear to the front, a main line rail is provided, and the above-mentioned trolley is run on the main line rail, Shears are transported to the outside, or materials such as segments are brought in from the outside.

然るに、前記後続台車とかずり車或はセグメン
ト運搬台車等はトンネル内で順次組立てられるセ
グメントの底面にレールを敷設して、該レール上
を走行するようにしなければならないが、環状に
組立てられるセグメントの底面、にレールを敷設
するには、セグメントの円弧状の底面に先ず、渡
し材即ちレール受梁を渡し、これに歩廊板の敷設
とレールの取付けを為す等の極めて面倒な作業が
行われねばならない。
However, the following truck, pulley truck, segment transport truck, etc. must run on the rails by laying rails on the bottom of the segments that are assembled one after another in the tunnel. In order to lay the rails on the bottom surface, extremely tedious work must be carried out, such as first passing a rail support beam over the arc-shaped bottom surface of the segment, then laying the walkway board and attaching the rail to this. No.

そこで、シールドマシンを用いてトンネルを掘
進するとき、トンネル孔の底部中央部位にインバ
ートセグメントを配設し、これを中心としてセグ
メントを組立てゆくと共に、該インバートセグメ
ントの上面中央部位に枕木と一体に形成されたレ
ールが取付けられ、更に、前後方向の組付けを助
成するために、前後方向に相互に突部と凹部とを
設け、そして、之等の突部と凹部とを嵌合させて
トンネル軸方向の組付け及びレール布施を簡素化
している技術が実開昭51−102235号公報に開示さ
れている。
Therefore, when excavating a tunnel using a shield machine, an invert segment is placed at the center of the bottom of the tunnel hole, and the segments are assembled around this, and the invert segment is formed integrally with the sleeper at the center of the top surface. In addition, in order to assist the assembly in the front and back direction, protrusions and recesses are mutually provided in the front and rear directions, and these protrusions and recesses are fitted to form the tunnel shaft. A technique that simplifies directional assembly and rail installation is disclosed in Japanese Utility Model Application Publication No. 51-102235.

又、レールを敷設したプラツトホーム枠がトン
ネル軸方向へ移行可能に構成された移動式路床装
置も特公昭42−17126号公報に記載されている。
Further, a mobile roadbed device in which a platform frame on which rails are laid can be moved in the axial direction of the tunnel is also described in Japanese Patent Publication No. 17126/1983.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

上記従来型で、シールドマシンを用いて円形状
のトンネルを掘進するとき、該シールドマシンを
作動させるための油圧パワーユニツト、油タン
ク、電気の動力盤、制御盤或はずり搬送ベルトコ
ンベア等を装備した後続台車を移行せしめ乍ら、
該シールドマシンを連続的に作動せしめ、そし
て、掘削したずりを後方へ搬送し、更に、後方か
らセグメント等の資材の供給のための搬送作業を
同時に行うことはできない。
When using the above conventional type to excavate a circular tunnel using a shield machine, it is equipped with a hydraulic power unit, an oil tank, an electric power panel, a control panel, or a shear conveyor belt to operate the shield machine. While the following truck was moved,
It is not possible to operate the shield machine continuously, transport the excavated shear to the rear, and carry out transport work for supplying materials such as segments from the rear at the same time.

依つて、シールドマシンを連続的に作動させ乍
らずりを後方へ搬送し、後方からセグメント等の
供給が同時にできるるようにしてシールドマシン
によるトンネル掘進作業効率の向上を計るために
解決せらるべき技術的課題が生じてくるのであ
り、本発明は該課題を解決することを目的とす
る。
Therefore, it is necessary to solve this problem in order to improve the efficiency of tunnel excavation work using the shield machine by continuously operating the shield machine to transport the debris to the rear and simultaneously supplying segments etc. from the rear. A technical problem arises, and the present invention aims to solve this problem.

〔課題を解決するための手段〕[Means to solve the problem]

この発明は上記目的を達成せんとして提案せら
れたものであり、シールドマシンにてトンネルを
順次掘削するに当つて、該シールドマシンのテー
ル部近傍の中央下部に、インバートセグメントを
敷設し、該インバートセグメントは前記シールド
マシンの掘進に伴つて順次敷設組立てられると共
に、該インバートセグメントを中心としてセグメ
ントを組立て、且つ、該インバートセグメントの
中央上面には本線レールが取付けられ、更に、該
トンネル低部にはトンネル軸方向へ移動可能に設
けられたプラツトホーム枠を配設して、該プラツ
トホーム枠にレールを敷設して台車等を往復動で
きるようにしたシールドマシンを用いたトンネル
掘進工法に於て、前記インバートセグメントの前
記本線レールの左右両側部を上方へ突起せしめて
その上面を軌道面に形成し、該双方の軌道面に跨
つて油圧パワーユニツト、油タンク、電気動力盤
並びに制御盤、ずり搬送ベルトコンベア等を装備
した後続台車を移行せしめ、且つ、該後続台車は
前記双方の軌道面より上方へ立設して門型状に構
成され、その上部左右両端部に転倒防止用のロー
ラを取付けて該ローラをセグメントの内側面に沿
つて転動せしめ、更に、その後方に、前記プラツ
トホーム枠を前記インバートセグメントの左右の
軌道面に摺動可能に跨設して該プラツトホーム枠
の左右に平行してレールを敷設し、各レールにず
り車、セグメント、運搬台車等を往動或は復動せ
しめて、該シールドマシンによる掘進と、ずり並
びにセグメント等の搬送を可能ならしめたことを
特徴とするインバートセグメントを用いたトンネ
ル掘進方法を提供せんとするものである。
This invention was proposed to achieve the above object, and when tunnels are sequentially excavated by a shield machine, an invert segment is laid at the lower center near the tail of the shield machine, and the invert segment is The segments are sequentially laid and assembled as the shield machine excavates, and the segments are assembled around the invert segment, and a main rail is attached to the center upper surface of the invert segment, and a main rail is attached to the lower part of the tunnel. In a tunnel excavation method using a shield machine in which a platform frame that is movable in the direction of the tunnel axis is disposed and rails are laid on the platform frame so that a cart or the like can be moved back and forth, the above-mentioned invert The left and right sides of the main rail of the segment are projected upward to form a raceway surface on the upper surface, and a hydraulic power unit, an oil tank, an electric power panel, a control panel, and a shear belt conveyor are installed across both raceway surfaces. etc., and the following bogie is constructed in a gate shape by standing above both track surfaces, and rollers for preventing falling are attached to both left and right ends of the upper part of the bogie. A roller is caused to roll along the inner surface of the segment, and further behind the platform frame, the platform frame is slidably straddled over the left and right track surfaces of the invert segment, and rails are installed parallel to the left and right sides of the platform frame. An invert segment characterized in that a shear wheel, segment, transport cart, etc. are moved forward or backward on each rail to enable excavation by the shield machine and transportation of shears, segments, etc. This paper aims to provide a tunnel excavation method using.

〔作用〕[Effect]

インバートセグメントの中央部に設けられてい
る本線レールの両外面を上方に突起せしめ、その
上面を軌道面としたため、この軌道面はシールド
マシンにて掘削された円形状のトンネルであるに
も拘らず、その横巾が広くなり、依つて、前記本
線レールとは別個に該軌道面上に後続台車並びに
左右両側に夫々レールを敷設したプラツトホーム
枠を移行自在に配設するとき、該プラツトホーム
枠に敷設されたレール上を運行するずり車等も大
きな容量のものを使用でき、作業性も向上する。
更に、シールドマシンの稼働に必要な油圧パワー
ユニツト、油タンク、電気動力盤並びに制御盤、
ずり搬送ベルトコンベア等は該後続台車に配備し
てシールドマシンによる掘削推進を可能にし、更
に、セグメントの組立てのためのセグメントその
他の資材の搬入は前記プラツトホーム枠に取付け
たレール上を台車を走行させることにより可能と
なる。而も、前記後続台車は門型状に形成され、
且つ、その上部両端部にはローラが取付けられて
セグメントの内側面に沿つて転動するので、該後
続台車は転倒することはなく、その移行動作も円
滑となる。
Both outer surfaces of the main rail provided at the center of the invert segment are projected upward, and the upper surface is used as the raceway surface, even though this raceway surface is a circular tunnel excavated by a shield machine. , the width becomes wider, and therefore, when a platform frame with a trailing bogie and rails laid on the track surface separately from the main line rail and rails on both left and right sides is installed in a movable manner, the platform frame Large-capacity shear cars and the like can be used to operate on the built-in rails, improving work efficiency.
Furthermore, the hydraulic power unit, oil tank, electric power panel and control panel necessary for the operation of the shield machine,
A shear conveyor belt conveyor, etc. is installed on the following truck to enable excavation propulsion by the shield machine, and the truck is run on rails attached to the platform frame to carry in segments and other materials for segment assembly. This makes it possible. Moreover, the following truck is formed in a gate shape,
In addition, since rollers are attached to both upper ends of the segment and roll along the inner surface of the segment, the following truck will not fall over and its transition operation will be smooth.

斯くして、シールドマシンによるトンネル掘進
作業と同時に、ずり排出及びセグメントその他の
資材の運搬台車の運行が行われるので、セグメン
トの組立作業も前記シールドマシンの稼働と共に
行うことができるようになり、シールドマシンに
よるトンネル掘進作業が極めて効率的に行われる
のである。
In this way, the shear removal and transportation of segments and other materials are carried out at the same time as the tunnel excavation work by the shield machine, so that the segment assembly work can be carried out at the same time as the shield machine is operated. Tunnel excavation work by machines is carried out extremely efficiently.

〔実施例〕〔Example〕

以下、本発明の一実施例を別紙添付図面に従つ
て説明する。尚、説明の都合上、従来公知に属す
る構成も同時に説明する。
An embodiment of the present invention will be described below with reference to the accompanying drawings. For convenience of explanation, conventionally known configurations will also be explained at the same time.

1は掘進されたトンネル孔に順次組立てられた
セグメント、2は後続台車、3はプラツトホーム
枠、3′はプラツトホーム枠3群の後部のプラツ
トホーム枠、4は本線レールを示す。
Reference numeral 1 indicates the segments assembled in the excavated tunnel hole, 2 the following bogie, 3 the platform frame, 3' the platform frame at the rear of the group of 3 platform frames, and 4 the main rail.

前記各部の詳細を次に説明する。 The details of each part will be explained next.

環状に組立てられるセグメント1の内環体の中
央下部に於ては、第4図乃至第6図で示されるよ
うに、インバートセグメント5を用いる。インバ
ートセグメント5の中央には、導流溝17を備
え、導流溝17を挟んでその両側に本線レールの
レール取付面6,6を形成し、レール取付面6,
6の外側にこれより稍高く軌道面7,7を形成す
る。
At the lower center of the inner ring body of the segment 1 assembled into an annular shape, an inverted segment 5 is used as shown in FIGS. 4 to 6. A guide groove 17 is provided at the center of the invert segment 5, and rail mounting surfaces 6, 6 for the main rail are formed on both sides of the guide groove 17.
Raceway surfaces 7, 7 are formed on the outside of 6 to be slightly higher than this.

セグメント1はインバートセグメント5を中心
として、その左右に順次環状に組立てられる。
The segments 1 are sequentially assembled into a ring on the left and right sides of the invert segment 5.

第3図に於て、後続台車2は油圧パワーユニツ
トa、油タンクb、電気の動力盤、制御盤c、ず
り搬送ベルト15等を装備したものでトンネル掘
進に当つてテール部で、トンネル掘削、ずり搬
送、セグメント組立等の作業を為すについて最も
重要な装置である。
In Fig. 3, the following bogie 2 is equipped with a hydraulic power unit a, an oil tank b, an electric power panel, a control panel c, a shear conveyor belt 15, and the like. This is the most important equipment for tasks such as shear conveyance, segment assembly, etc.

この後続台車2はインバートセグメント5の左
右の軌道面7,7上を移行するが、これには第4
図で示すように台足8を設けて軌道面7,7を摺
動するようにしてもよいが、この台足8,8の代
りに車輪を設けるようにしてもよい。
This following bogie 2 moves on the left and right track surfaces 7, 7 of the inverted segment 5, but there is a fourth
As shown in the figure, a pedestal 8 may be provided to slide on the raceway surfaces 7, 7, but wheels may be provided in place of the pedestals 8, 8.

同図に於て、9,9は後続台車2の上方左右に
設けたローラであつて、このローラ9,9は後続
台車2の転倒を防ぎ常に安定的に軌道面7,7上
を摺動できるようにし、作業を円滑且つ安全に行
うことを可能にする。
In the figure, reference numerals 9, 9 are rollers provided on the upper left and right sides of the trailing truck 2, and these rollers 9, 9 prevent the trailing truck 2 from overturning and always slide stably on the track surfaces 7, 7. This enables the work to be carried out smoothly and safely.

プラツトホーム枠3は、後続台車2の後方に於
て、多数並設させるものであり、このプラツトホ
ーム枠3にはトンネル軸線方向の左右に於て夫々
レール10,10を敷設し、その上をずり車とか
セグメント等の資材を運ぶトロを運行させる。
A large number of platform frames 3 are arranged in parallel at the rear of the following bogie 2. Rails 10, 10 are laid on the platform frame 3 on the left and right sides of the tunnel axis, and a shear wheel is mounted on the platform frames 3. Toro is operated to transport materials such as segments.

11はプラツトホーム枠3の中央に立設せる
柱、12は柱11の上部に設けた桁材でその両端
に設けたローラ13,13は組立てられたセグメ
ント1内面を転動する。
Reference numeral 11 denotes a column erected at the center of the platform frame 3, 12 a beam member provided on the upper part of the column 11, and rollers 13, 13 provided at both ends thereof roll on the inner surface of the assembled segment 1.

プラツトホーム枠3の下面には台足14,14
を設け、この台足14,14はインバートセグメ
ント5の軌道面7,7上を摺動する。
On the underside of the platform frame 3 are pedestals 14, 14.
are provided, and the pedestals 14, 14 slide on the raceway surfaces 7, 7 of the invert segment 5.

プラツトホーム枠3の上方の桁材12上には掘
進機で掘削されたずりを搬送し、これを下方に移
行してきたずり車に投入するための搬送ベルト1
6を設置する。搬送ベルト16は後続台車2の搬
送ベルト15に連繋したものである。
On the girder 12 above the platform frame 3 is a conveyor belt 1 for conveying the shear excavated by the excavator and feeding it into the shear wheel moving downward.
Install 6. The conveyor belt 16 is connected to the conveyor belt 15 of the following truck 2.

3′はプラツトホーム枠3群の後方に並列した
プラツトホーム枠で、このプラツトホーム枠3′
には前記のような支柱11、桁材12等を設け
ず、トンネル軸線方向の左右2列にレール10′,
10′を取付ける。プラツトホーム枠3′の下面に
も台足14′,14′を取付けインバートセグメン
ト5の軌道面7,7上を摺動する。
3' is a platform frame parallel to the rear of the 3rd group of platform frames, and this platform frame 3'
The above-mentioned pillars 11, girders 12, etc. are not provided in the tunnel, and rails 10', rails 10',
Install 10'. Pedestals 14', 14' are also attached to the lower surface of the platform frame 3' and slide on the raceway surfaces 7, 7 of the invert segment 5.

本線レール4はインバートセグメント5中央の
レール取付面6,6に取付けられていて、この本
線レール4は前記のプラツトホーム枠3′群に取
付けた左右のレール10′,10′と夫々連結す
る。
The main rail 4 is attached to rail mounting surfaces 6, 6 at the center of the invert segment 5, and the main rail 4 is connected to left and right rails 10', 10' attached to the platform frames 3', respectively.

本発明に於ては掘削施工事には、テール部に於
てその工事に最も活躍する後続台車2は、インバ
ートセグメント5上の軌道面7,7上を移動する
ようにしたので、別に同車移行のためのレールを
特別に設ける必要はない。
In the present invention, during excavation work, the trailing bogie 2, which is most active in the work at the tail section, moves on the track surfaces 7, 7 on the invert segment 5, so that the same car is not required. There is no need to provide special rails for transition.

このことは組立てたセグメントに、レール取付
けのために渡し材を設けるとか歩廊板を設けるよ
うな必要が全くないということであり、又、トン
ネル掘進に伴つて後続台車レール2を前方に移し
換えるというような煩雑な手数が全く不必要とな
ることである。又、後続台車2に続いて設けられ
るずり搬送のためのずり車とか、セグメント1そ
の他の資材の搬入のための運搬台車は、インバー
トセグメント5の軌道面7,7上を摺動する各プ
ラツトホーム枠3,3′上にレール10,10、
10′,10′を取付けてその上を走行させるよう
にしたことにより、これにも矢張り渡し材とか歩
廊板等を必要とせず、簡単にこれが取付けられ、
又、その取外し移動等の手間が全くかからなく、
誰プラツトホーム枠3,3′を掘進に伴つて順次
前方に摺動させて行くだけで済むので、その作業
が単純化されて能率的に行うことができる。
This means that there is no need to provide a bridge or walkway board for rail attachment to the assembled segment, and there is no need to move the trailing bogie rail 2 forward as the tunnel is excavated. Such complicated steps are completely unnecessary. In addition, a shear wheel for shear conveyance provided following the succeeding truck 2 and a transport truck for carrying in the segment 1 and other materials are attached to each platform frame sliding on the track surfaces 7, 7 of the invert segment 5. Rails 10, 10 on 3, 3',
By attaching 10' and 10' and allowing the vehicle to run on top of them, there is no need for arrow struts or walkway boards, etc., and this can be easily installed.
In addition, it does not take any effort to remove and move.
Since it is only necessary to sequentially slide the platform frames 3, 3' forward as the excavation progresses, the work is simplified and can be carried out efficiently.

そして、プラツトホーム枠3,3′上に取付け
たレール10,10、10′,10′は、それだ
け、そのレベルを高くすることができるので、坑
内を広く使用することができることになり、従つ
て、ずり車等は大きな容量のものを使用でき、作
業性が向上し、安全面でも有利であると共に、そ
れだけ車両編成が短くなり、同プラツトホーム枠
3,3′の仮掘進距離が短くなる。そして、これ
までのように渡し材の上にレールを敷設するのに
較べ軌道が安定するので、車両の走行速度を早く
することができる。
Since the rails 10, 10, 10', 10' installed on the platform frames 3, 3' can be raised accordingly, the underground area can be used more widely. A large-capacity shear wheel or the like can be used, which improves work efficiency and is advantageous in terms of safety. In addition, the vehicle formation is shortened accordingly, and the temporary excavation distance of the platform frames 3, 3' is shortened. In addition, since the track is more stable than the conventional method of laying rails on the crossing material, the running speed of the vehicle can be increased.

更に、本線レール4は取付金具をもつて直接イ
ンバートセグメント5のレール取付面6,6に取
付ければよいので短時間にこれを行うことができ
その作業も簡単になる。
Furthermore, since the main rail 4 can be directly attached to the rail attachment surfaces 6, 6 of the invert segment 5 using attachment fittings, this can be done in a short time and the work is simple.

そして掘削搬出作業中、掘削土砂が坑内に落ち
こぼれても、これはインバートセグメント5の導
流溝17に収集され、これを排除清掃することも
容易であるので、絶えず行われる坑内清掃時間を
短縮することができる。
Even if excavated soil falls into the mine during excavation and unloading work, it will be collected in the flow guide groove 17 of the invert segment 5, and it can be easily removed and cleaned, thereby reducing the time required for constantly cleaning the mine. be able to.

〔発明の効果〕 インバートセグメントに設けた本線レールの両
外側部を上方へ突起せしめて、その上面を軌道面
としたため、円形のトンネルであるにも拘らず、
トンネル底部が広く使用されることができて作業
性が向上する。更に、該インバートセグメントの
該軌道面上に後続台車を運行させるのであるか
ら、シールドマシンによるトンネル掘進工事に於
て、最も活躍する後続台車を運行させるための特
別のレールを必要とせず、且つ、該後続台車は門
型状であるため、その下部に於ける各種の作業に
支障を来さず、更に、上部両端部にローラを設け
てセグメントの内側面に沿つて転動可能に形成さ
れているため、該後続台車が転倒することもな
く、シールドマシンの掘削施工の安全性が確保さ
れる。更に、該後続台車の後方にはプラツトホー
ム枠が該軌道面に摺動自在に配設されているの
で、該プラツトホーム枠の摺動も円滑となり、且
つ、該プラツトホーム枠は前述せる如く、円形の
トンネルの底部にあつても広く形成されることが
可能であるため、左右両側に夫々ずり出し、又は
セグメント搬送等の台車を走行させるレールを
夫々備えることが可能となり、且つ、該台車も容
量の大なるものを運行させることができるので、
シールドマシンの稼働能率が大となる。
[Effect of the invention] Both outer sides of the main line rail provided in the invert segment were made to protrude upward, and the upper surface was used as the raceway surface, so even though it was a circular tunnel,
The tunnel bottom can be used widely, improving work efficiency. Furthermore, since the trailing bogie is run on the track surface of the invert segment, there is no need for a special rail for running the trailing bogie, which is most useful in tunnel excavation work using a shield machine, and Since the following trolley is gate-shaped, it does not interfere with various operations at the lower part, and furthermore, rollers are provided at both ends of the upper part so that it can roll along the inner surface of the segment. Therefore, the following truck does not fall over, and the safety of excavation work by the shield machine is ensured. Furthermore, since the platform frame is disposed at the rear of the following bogie so as to be able to slide freely on the track surface, the platform frame can slide smoothly, and as mentioned above, the platform frame is connected to the circular tunnel. Since it can be formed wide even at the bottom of the container, it is possible to provide rails on both the left and right sides for running trolleys such as sliding or segment transportation, and the trolleys also have a large capacity. Because it is possible to operate
The operating efficiency of the shield machine increases.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図はトンネル掘進施工中のトンネルの横断
平面図で同図イはその左半部、同図ロはその右半
部、第2図は同じく縦断側面図で同図イは左半
部、同図ロはその右半部、第3図はテール部の拡
大縦断側面図、第4図はそのA−A線断面を示す
ものであるがその1実施例図である。第5図は第
2図B−B線断面図、第6図は同じくC−C線断
面図である。 1……セグメント、2……後続台車、3,3′
……プラツトホーム枠、4……本線レール、5…
…インバートセグメント、6……レール取付面、
7……軌道面、10,10′……レール。
Figure 1 is a cross-sectional plan view of a tunnel during tunnel excavation construction. Figure A is the left half of the tunnel, B is the right half of the tunnel, Figure 2 is a vertical side view of the tunnel, and A is the left half of the tunnel. FIG. 3 is an enlarged longitudinal cross-sectional side view of the tail portion, and FIG. 4 is a cross-sectional view taken along the line A--A of one embodiment. FIG. 5 is a cross-sectional view taken along the line B--B in FIG. 2, and FIG. 6 is a cross-sectional view taken along the line C--C in FIG. 1...Segment, 2...Following truck, 3, 3'
...Platform frame, 4... Main line rail, 5...
...Invert segment, 6...Rail mounting surface,
7...Race surface, 10,10'...Rail.

Claims (1)

【特許請求の範囲】[Claims] 1 シールドマシンにてトンネルを順次掘削する
に当つて、該シールドマシンのテール部近傍の中
央下部に、インバートセグメントを敷設し、該イ
ンバートセグメントは前記シールドマシンの掘進
に伴つて順次敷設組立てられると共に、該インバ
ートセグメントを中心としてセグメントを組立
て、且つ、該インバートセグメントの中央上面に
は本線レールが取付けられ、更に、該トンネル低
部にはトンネル軸方向へ移動可能に設けられたプ
ラツトホーム枠を配設して、該プラツトホーム枠
にレールを敷設して台車等を往復動できるように
したシールドマシンを用いたトンネル掘進工法に
於て、前記インバートセグメントの前記本線レー
ルの左右両側部を上方へ突起せしめてその上面を
軌道面に形成し、該双方の軌道面に跨つて油圧パ
ワーユニツト、油タンク、電気動力盤並びに制御
盤、ずり搬送ベルトコンベア等を装備した後続台
車を移行せしめ、且つ、該後続台車は前記双方の
軌道面より上方へ立設して門型状に構成され、そ
の上部左右両端部に転倒防止用のローラを取付け
て該ローラをセグメントの内側面に沿つて転動せ
しめ、更に、その後方に、前記プラツトホーム枠
を前記インバートセグメントの左右の軌道面に摺
動可能に跨設して該プラツトホーム枠の左右に平
行してレールを敷設し、各レールにずり車、セグ
メント、運搬台車等を往動或は復動せしめて、該
シールドマシンによる掘進と、ずり並びにセグメ
ント等の搬送を可能ならしめたことを特徴とする
インバートセグメントを用いたトンネル掘進方
法。
1. When sequentially excavating a tunnel with a shield machine, an invert segment is laid at the lower center near the tail of the shield machine, and the invert segment is sequentially laid and assembled as the shield machine excavates, Segments are assembled around the invert segment, a main rail is attached to the upper center surface of the invert segment, and a platform frame movable in the tunnel axis direction is provided at the bottom of the tunnel. In a tunnel excavation method using a shield machine in which rails are laid on the platform frame and a bogie etc. can be moved back and forth, the left and right sides of the main rail of the invert segment are made to protrude upward. The upper surface is formed as a raceway surface, and a subsequent bogie equipped with a hydraulic power unit, an oil tank, an electric power panel, a control panel, a shear belt conveyor, etc. is moved across both track surfaces, and the following bogie is It is constructed in a gate shape by standing above both raceway surfaces, and rollers for preventing falling are attached to both left and right ends of the upper part, and the rollers are caused to roll along the inner surface of the segment. On the other hand, the platform frame is slidably straddled over the left and right track surfaces of the invert segment, rails are laid parallel to the left and right sides of the platform frame, and a shear wheel, segment, transport cart, etc. are installed on each rail. 1. A method for tunnel excavation using an invert segment, characterized in that the shield machine can be moved forward or backward to enable excavation by the shield machine and transport of shears, segments, etc.
JP12143883A 1983-07-04 1983-07-04 Tunnel drilling method using invert segment Granted JPS6013199A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12143883A JPS6013199A (en) 1983-07-04 1983-07-04 Tunnel drilling method using invert segment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12143883A JPS6013199A (en) 1983-07-04 1983-07-04 Tunnel drilling method using invert segment

Publications (2)

Publication Number Publication Date
JPS6013199A JPS6013199A (en) 1985-01-23
JPH0341640B2 true JPH0341640B2 (en) 1991-06-24

Family

ID=14811136

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12143883A Granted JPS6013199A (en) 1983-07-04 1983-07-04 Tunnel drilling method using invert segment

Country Status (1)

Country Link
JP (1) JPS6013199A (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2936241B2 (en) * 1991-10-29 1999-08-23 日工株式会社 Mud treatment method for shield machine
JP6920173B2 (en) * 2017-11-02 2021-08-18 株式会社東宏 Belt conveyor support device

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5220504A (en) * 1975-08-06 1977-02-16 Koichi Uemura Method of causing automatic advancement of operation truck for laying rails
JPS51102235U (en) * 1976-02-19 1976-08-17

Also Published As

Publication number Publication date
JPS6013199A (en) 1985-01-23

Similar Documents

Publication Publication Date Title
US3206824A (en) Apparatus for forming a tunnel
JP5793062B2 (en) Tunnel construction apparatus and tunnel construction method
JPH0341640B2 (en)
JPH04333800A (en) Lining material carrying device
CN118774945B (en) A synchronous construction system and construction platform for a connecting passage
JP2018053456A (en) Segment stock and automatic transfer device
JP4723469B2 (en) Underground work equipment behind the shield machine
CN216714385U (en) Trolley for tunnel construction
JP2873818B1 (en) Continuous belt conveyor support mechanism in tunnel excavation
JP3689165B2 (en) Material and material transport structure for uplift excavation
JP3731723B2 (en) Underground transport system and loading / unloading method
JPH03151497A (en) Segment transfer device used in shield method
JPH0246559Y2 (en)
JP3051568B2 (en) Traveling equipment for subsequent equipment of a tunnel excavator
JP7231151B2 (en) material transportation system
CN109488322B (en) Tunnel inverted arch rapid excavation construction equipment and construction method thereof
JP2698946B2 (en) How to transport segments and excavated soil in shield construction
JP3305376B2 (en) Trailing bogies and equipment of shield machine
JPH0246558Y2 (en)
JPH0259278B2 (en)
CN223707717U (en) Tunnel trolley and tunnel trolley group
CN213264343U (en) Self-balancing transshipment bridge conveyor
JPH06270793A (en) Construction method using single-rail transporter
JPS6344884B2 (en)
JP3138762B2 (en) Transport cart and transport method