JPH0348972B2 - - Google Patents
[go: Go Back, main page]

JPH0348972B2 - - Google Patents

Info

Publication number
JPH0348972B2
JPH0348972B2 JP18919083A JP18919083A JPH0348972B2 JP H0348972 B2 JPH0348972 B2 JP H0348972B2 JP 18919083 A JP18919083 A JP 18919083A JP 18919083 A JP18919083 A JP 18919083A JP H0348972 B2 JPH0348972 B2 JP H0348972B2
Authority
JP
Japan
Prior art keywords
formwork
holes
anchor bolts
frame
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP18919083A
Other languages
Japanese (ja)
Other versions
JPS6080641A (en
Inventor
Chomi Iyogi
Takemasa Sugyama
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Takenaka Komuten Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Takenaka Komuten Co Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP18919083A priority Critical patent/JPS6080641A/en
Publication of JPS6080641A publication Critical patent/JPS6080641A/en
Publication of JPH0348972B2 publication Critical patent/JPH0348972B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Description

【発明の詳細な説明】 この発明は石張材固定用アンカーボルトの埋設
方法に関し、特にアンカーボルトの埋設精度が改
良できる方法に関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for burying anchor bolts for fixing stone cladding, and particularly to a method that can improve the burying accuracy of anchor bolts.

従来から建築構造物の外壁として、コンクリー
ト製躯体の外面に平板状の石材を張り付けること
が行なわれており、躯体に石材を仮止めしてこれ
らの間にモルタルを流し込んで固定する湿式工法
は、耐震性およびモルタル中の石灰分がメジに滲
み出る白華現象さらには施工性が悪いという問題
があつたため近年コンクリート躯体内にアンカー
ボルトを埋設し、ネジの刻設された頭部を躯体面
から突出させ、L字金具等を用いて石材を躯体面
に取付けるいわゆる乾式石張工法が開発された。
Traditionally, flat stones have been attached to the outside of a concrete frame as the exterior walls of architectural structures, and wet construction methods involve temporarily fixing the stones to the frame and pouring mortar between them. In recent years, anchor bolts have been buried within the concrete structure, and the engraved heads of the screws have been placed on the surface of the structure, as there have been problems with earthquake resistance, efflorescence, where the lime content in the mortar oozes out, and poor workability. A so-called dry stone cladding method has been developed in which the stones are attached to the building frame using L-shaped fittings and the like.

この乾式石張工法においては、躯体内に埋設す
るアンカーボルトの据付精度が重要なポイントと
なる。
In this dry masonry construction method, the installation accuracy of the anchor bolts buried within the building frame is an important point.

すなわち、アンカーボルト相互間の位置、水平
度、躯体からの突出量が精度よく施工されない
と、これを修正しなければならないため施工能率
が低下するだけでなく取付強度も問題となる。特
に石材の自重を負担するアンカーボルトの垂直方
向の間隔および水平度はより高精度が要求され
る。
In other words, if the position, levelness, and amount of protrusion from the structure between the anchor bolts are not performed with high precision, this will have to be corrected, which will not only reduce construction efficiency but also pose a problem in installation strength. In particular, higher precision is required for the vertical spacing and horizontality of anchor bolts that bear the weight of the stone.

ところで、従来行なわれていたアンカーボルト
の埋設方法は、コンクリート打設用の型枠に予め
透孔を穿設しておき、これを建込んだ後コンクリ
ートを打設し、打設コンクリートが適度に硬化し
た状態で前記透孔内にアンカーボルトを1本ずつ
押し込んでで行なつていた。
By the way, the conventional method of burying anchor bolts is to drill through holes in advance in the formwork for concrete pouring, and then pour concrete after the holes are erected. This was done by pushing the anchor bolts one by one into the through holes in the hardened state.

しかし、この方法では、非能率的であるととも
に、躯体形成用の打設コンクリートが完全に硬化
した後ではアンカーボルトの据付けができず、一
方、余り硬化しない状態で据付けるとアンカーボ
ルト自重でズリ下がつて水平度が保てなくなる。
However, this method is inefficient, and the anchor bolts cannot be installed after the poured concrete for forming the frame has completely hardened. On the other hand, if the anchor bolts are installed before the concrete has hardened, the anchor bolts will shift due to their own weight. It will drop and you will not be able to maintain levelness.

従つて、アンカーボルトを透孔内に挿通して据
付けるタイミングの判断が極めて難しく、その上
打設コンクリートへの据付けは、人手で行なわれ
るためバラツキがあつて、所望する精度内に埋設
することが困難であつた。
Therefore, it is extremely difficult to judge the timing to insert the anchor bolt into the hole and install it.Furthermore, the installation into the poured concrete is done manually, so there are variations, and it is difficult to bury the anchor bolt within the desired precision. was difficult.

このため埋設されたアンカーボルトの上下、左
右の傾きを修正しなければならず施工状態が低下
し、工期の短縮、コストダウンをする上で障害と
なつていた。
For this reason, the vertical and horizontal inclinations of the buried anchor bolts had to be corrected, which deteriorated the construction condition and became an obstacle to shortening the construction period and reducing costs.

この発明は上述した従来の問題点に鑑みてなさ
れたものであつて、その目的とするところは、石
材固定用のアンカーボルトを高精度の下に埋設で
きる石張材固定用アンカーボルトの埋設方法を提
供するところにある。
This invention has been made in view of the above-mentioned conventional problems, and its purpose is to provide a method for burying anchor bolts for fixing stone cladding, which can bury anchor bolts for fixing stone materials with high precision. It's there to do.

上記目的を達成するためこの発明は、石張材固
定用アンカーボルトをコンクリート躯体内に埋設
する方法において、躯体を形成するための型枠に
予め所定間隔を置いて透孔を穿設するとともに、
この型枠に前記透孔と位置対応する個所に挿通孔
を穿設したフレーム材を固着し、この挿通孔およ
び前記透孔内に前記アンカーボルトの頭部を挿入
して螺着した後、前記型枠を建込みコンクリート
を打設し、コンクリートの硬化後に前記アンカー
ボルトの螺着を解除した後、型枠を撤去し前記ア
ンカーボルトを躯体内に埋設してなることを特徴
とする。
In order to achieve the above object, the present invention provides a method for embedding anchor bolts for fixing masonry materials in a concrete structure, in which through-holes are drilled at predetermined intervals in a formwork for forming the structure, and
A frame material having an insertion hole formed in a position corresponding to the through hole is fixed to this formwork, and the head of the anchor bolt is inserted and screwed into the insertion hole and the through hole, and then the The method is characterized in that a formwork is set, concrete is poured, and after the concrete has hardened, the anchor bolts are unscrewed, the formwork is removed, and the anchor bolts are buried in the building frame.

以下、この発明の好適な実施例について添付図
面に基づいて詳細に説明する。
Hereinafter, preferred embodiments of the present invention will be described in detail based on the accompanying drawings.

第1図から第4図はこの発明に係るる石張材固
定用アンカーボルトの埋設方法の一実施例を示す
ものである。
1 to 4 show an embodiment of a method for embedding an anchor bolt for fixing stone cladding according to the present invention.

第1図はコンクリートを打設して躯体20を形
成するために建込む型枠22を配置した状態を示
すものである。
FIG. 1 shows a state in which formwork 22 is placed to be erected to form a frame 20 by pouring concrete.

この型枠22は平板細長に形成されるととも
に、その軸心には長手方向に沿つて一対のフレー
ム材24,26が、型枠22を挟み込むようにし
て両側面から取り付けられ、複数の固定用ボルト
ナツト28,28…で固着されている。
This formwork 22 is formed into an elongated flat plate, and a pair of frame members 24 and 26 are attached to the axis of the formwork along the longitudinal direction from both sides so as to sandwich the formwork 22. It is fixed with bolt nuts 28, 28...

上記型枠22には、鉛直方向に所定の間隔を置
いて透孔30,30…が穿設されており、その径
は後述するアンカーボルトの直径よりも若干大き
く、その鉛直方向の間隔は躯体20に張付けられ
る石材との関係で設定されている。
In the formwork 22, through holes 30, 30... are bored at a predetermined interval in the vertical direction, the diameter of which is slightly larger than the diameter of an anchor bolt, which will be described later, and the interval in the vertical direction is It is set in relation to the stone material attached to 20.

上記フレーム材24,26のうち、型枠22の
外側面に位置するフレーム材24は、一側部およ
び上下端が開口した断面形状をコ字形となつてお
り、内側のフレーム材26は一側部が開口した皿
状に形成され、それぞれの開口部が対向するよう
に配置されるとともに、それぞれのフレーム材2
4,26には上記型枠22に穿設した透孔30と
位置対応する個所に挿通孔32,34が形成され
ている。上記挿通孔32,34のうち内側のフレ
ーム材26のものは、外方(形成される躯体20
側)に向かつてその径を拡大するようにテーパー
状に形成されている。
Of the frame materials 24 and 26, the frame material 24 located on the outer surface of the formwork 22 has a U-shaped cross section with one side and upper and lower ends open, and the inner frame material 26 has one side open. The frame members 2 are formed into a dish shape with openings, and are arranged so that the respective openings face each other.
4 and 26 have insertion holes 32 and 34 formed in positions corresponding to the through holes 30 drilled in the formwork 22, respectively. Of the insertion holes 32 and 34, those of the inner frame material 26 are inserted into the outer (frame 20 to be formed)
It is tapered so that its diameter increases toward the side.

一方、石張材固定用アンカーボルト36は、第
2図に示すように一端部が略L字形に折曲されて
おり、他端側の頭部36aにはネジが周設されて
いる。
On the other hand, as shown in FIG. 2, the anchor bolt 36 for fixing stone cladding has one end bent into a substantially L-shape, and a screw is provided around the head 36a at the other end.

このアンカーボルト36のL字折曲部36bお
よび中央部36cの略2/3の長さが躯体20内に
埋設され、中央部36cの略1/3の長さを躯体2
0外に突出するが、この突出量に相当する個所に
傘状のストツパー38が固着されており、このス
トツパー38は上記挿通孔34に嵌合する傾斜部
38aと、これに連続して形成されたフランジ部
38bとで構成されている。
Approximately 2/3 of the length of the L-shaped bent portion 36b and central portion 36c of this anchor bolt 36 is buried in the body 20, and approximately 1/3 of the length of the central portion 36c is buried within the body 20.
An umbrella-shaped stopper 38 is fixed at a location corresponding to the amount of this projection, and this stopper 38 is formed continuously with the sloped portion 38a that fits into the insertion hole 34. flange portion 38b.

上記アンカーボルト36は、内側のフレーム材
26側からその頭部36aを、挿通孔34、透孔
30、挿通孔32と挿通させてナツト40を頭部
36aに螺着することで型枠22に固定される。
The anchor bolt 36 is attached to the formwork 22 by inserting its head 36a through the insertion hole 34, the through hole 30, and the insertion hole 32 from the inner frame material 26 side, and screwing the nut 40 into the head 36a. Fixed.

このようにしてアンカーボルト36が固定され
た型枠22は、第1図に示すように横方向に所要
の数連結して建込まれ、コンクリートを打設し、
硬化に上記ナツト40の螺着を解除して型枠22
を撤去すれば、アンカーボルト36は躯体20内
に埋設される。
The formwork 22 to which the anchor bolts 36 are fixed in this way is erected by connecting the required number of forms horizontally as shown in FIG. 1, and concrete is poured.
After curing, the nut 40 is unscrewed and the formwork 22 is removed.
When removed, the anchor bolts 36 are buried within the frame 20.

この場合、上記内側のフレーム材26と型枠2
2との間隔部は、フレーム材26が皿状に形成さ
れ、且つその挿通孔34がストツパー38の傾斜
部38aおよびフランジ部38bとで閉塞されて
いるため、打設されたコンクリートが外部に漏出
するのを防止するとともに、コンクリートの硬化
後離型を容易にする。
In this case, the inner frame material 26 and the formwork 2
2, the frame material 26 is formed into a dish shape, and its insertion hole 34 is closed by the inclined part 38a and flange part 38b of the stopper 38, so that the poured concrete does not leak to the outside. This prevents the concrete from curing and makes it easier to release the concrete after it hardens.

さて、上述した構成からなる石張材固定用アン
カーボルトの埋設方法にあつては、アンカーボル
ト36の埋設は、型枠22にフレーム材24,2
6を固着し、これにアンカーボルト36を螺着す
ることで行なわれるため作業が簡単となるだけで
なく、アンカーボルト36は透孔30、挿通孔3
2,34に挿通され、しかもストツパー38と躯
体20側のフレーム材26の挿通孔34を嵌合さ
せ、さらにその頭部36aをナツト40で締付け
型枠22、フレーム材24,26と強固に結合さ
せて埋設されるため、この種の工法で特に重要な
アンカーボルトの鉛直方向の位置間隔、垂直度、
突出量を高い精度下に確実に施工できる。
Now, in the method of burying the anchor bolts for fixing masonry materials having the above-mentioned configuration, the anchor bolts 36 are buried in the frame members 24 and 24 in the formwork 22.
6 and then screw the anchor bolt 36 onto it, which not only simplifies the work, but also allows the anchor bolt 36 to fit through the through hole 30 and the insertion hole 3.
2, 34, and the stopper 38 is fitted with the insertion hole 34 of the frame material 26 on the frame 20 side, and the head 36a is further tightened with a nut 40 to firmly connect it to the formwork 22 and the frame materials 24, 26. Since the anchor bolts are buried vertically, the vertical spacing, perpendicularity, and
The amount of protrusion can be reliably constructed with high precision.

また、躯体20形成後に撤去されたフレーム材
24,26が固着された型枠22は、これを外す
ことなく再びアンカーボルト36を装着して他の
場所に建込むことができる便利さもある。
Furthermore, the formwork 22 to which the frame members 24 and 26 that have been removed after the formation of the frame 20 are fixed can be conveniently reinstalled with anchor bolts 36 and erected at another location without having to be removed.

なお、上記実施例では、フレーム材24,26
を型枠22の両側面に固着した場合を例示した
が、これを外側のフレーム材24のみとし、型枠
22の透孔30をストツパー38と嵌合する形状
としても上述した作用効果を奏することができ
る。
In addition, in the above embodiment, the frame materials 24, 26
Although the case where the frame material 22 is fixed to both sides of the formwork 22 has been illustrated, the above-mentioned effects can also be achieved even if the frame material 24 is used only as the outer frame material and the through hole 30 of the formwork 22 is shaped to fit with the stopper 38. I can do it.

また、上記アンカーボルト36は略L字形に限
られるものではなく、直線あるいはクランク形等
各種の形状が使用できるとともに、例えば躯体2
0側の配筋が埋設の障害となる場合には、その配
筋を迂回するような形状に屈曲させるることも可
能である。
Further, the anchor bolt 36 is not limited to a substantially L-shape, and can have various shapes such as a straight line or a crank shape.
If the reinforcement on the 0 side becomes an obstacle to embedding, it is also possible to bend the reinforcement into a shape that bypasses the reinforcement.

さらに、型枠22の幅長によつては、上記フレ
ーム材24,26を水平方向に所定間隔を置いて
平行して複数固着できることはいうまでもない。
Furthermore, depending on the width of the formwork 22, it goes without saying that a plurality of the frame members 24, 26 can be fixed in parallel at a predetermined interval in the horizontal direction.

以上、実施例で詳細に説明したように、この発
明に係る石張材固定用アンカーボルトの埋設方法
にあつては、アンカーボルトをフレーム材とナツ
トとを用いて型枠に装着して埋設するため、取扱
が簡単となるだけでなく、アンカーボルトの突出
量、垂直度等を高精度下に埋設することができ
る。
As described above in detail in the embodiments, in the method of burying an anchor bolt for fixing stone cladding according to the present invention, the anchor bolt is mounted and buried in a formwork using a frame material and a nut. Not only is it easy to handle, but the protrusion and verticality of the anchor bolt can be buried with high precision.

【図面の簡単な説明】[Brief explanation of drawings]

第1図から第4図はこの発明の一実施例を示す
もので、第1図は型枠を建込んだ状態の正面図、
第2図は第1図の−線に沿つた要部断面図、
第3図は第2図の−線断面図、第4図は第2
図の−線断面図である。 20……躯体、22……型枠、24……フレー
ム材、26……フレーム材、28……固定用ボル
トナツト、30……透孔、32……挿通孔、34
……挿通孔、36……アンカーボルト、36a…
…頭部、36b……折曲部、36c……中央部、
38……ストツパー、40……ナツト。
Figures 1 to 4 show an embodiment of the present invention; Figure 1 is a front view of the formwork with the formwork erected;
Figure 2 is a sectional view of the main part along the - line in Figure 1;
Figure 3 is a - line sectional view of Figure 2, Figure 4 is a cross-sectional view of Figure 2.
It is a sectional view taken along the - line in the figure. 20...framework, 22...formwork, 24...frame material, 26...frame material, 28...fixing bolt nut, 30...through hole, 32...insertion hole, 34
...Insertion hole, 36...Anchor bolt, 36a...
...Head part, 36b...Bending part, 36c...Central part,
38...Stopper, 40...Natsuto.

Claims (1)

【特許請求の範囲】[Claims] 1 石張材固定用アンカーボルトをコンクリート
躯体内に埋設する方法において、該躯体を形成す
るための型枠に予め所定間隔を置いて透孔を穿設
するとともに、該型枠に該透孔と位置対応する個
所に挿通孔を穿設したフレーム材を固着し、該挿
通孔および該透孔内に該アンカーボルトの頭部を
挿通して螺着した後、該型枠を建込みコンクリー
トを打設し、該コンクリートの硬化後に該アンカ
ーボルトの螺着を解除した後、該型枠を撤去し該
アンカーボルトを該躯体内に埋設してなることを
特徴とする石張材固定用アンカーボルトの埋設方
法。
1. In a method of embedding anchor bolts for fixing masonry materials in a concrete structure, holes are drilled in advance at predetermined intervals in the formwork for forming the structure, and holes are made in the formwork to correspond to the positions of the holes. After fixing the frame material with insertion holes drilled in the places to be used, and inserting and screwing the heads of the anchor bolts into the insertion holes and the through holes, set the formwork and pour concrete. A method for burying an anchor bolt for fixing stone cladding, comprising: releasing the screwing of the anchor bolt after the concrete hardens, removing the formwork, and burying the anchor bolt in the building frame.
JP18919083A 1983-10-12 1983-10-12 Embedding of anchor bolt for anchoring stone lined material Granted JPS6080641A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP18919083A JPS6080641A (en) 1983-10-12 1983-10-12 Embedding of anchor bolt for anchoring stone lined material

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP18919083A JPS6080641A (en) 1983-10-12 1983-10-12 Embedding of anchor bolt for anchoring stone lined material

Publications (2)

Publication Number Publication Date
JPS6080641A JPS6080641A (en) 1985-05-08
JPH0348972B2 true JPH0348972B2 (en) 1991-07-26

Family

ID=16237013

Family Applications (1)

Application Number Title Priority Date Filing Date
JP18919083A Granted JPS6080641A (en) 1983-10-12 1983-10-12 Embedding of anchor bolt for anchoring stone lined material

Country Status (1)

Country Link
JP (1) JPS6080641A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2137760C1 (en) * 1993-08-26 1999-09-20 Яманоути Фармасьютикал Ко., Лтд. Benzazepine derivative, pharmaceutical composition, derivative of difluorobenzazepine and derivative of (substituted) amino-benzoyldifluorobenzazepine

Also Published As

Publication number Publication date
JPS6080641A (en) 1985-05-08

Similar Documents

Publication Publication Date Title
US7908804B2 (en) Structural lintel assembly and building construction method using the same
CN110528950B (en) An assembled concealed corbel beam-column joint connection device
EP3861179B1 (en) Precast concrete panel joining system, method of making a panel joint, panel joint obtained by the method
AU2020101961B4 (en) Construction of a building using precast panels
JPH0348972B2 (en)
CN220620732U (en) A grouting sleeve used for positioning steel bars in prefabricated building construction
JPH0138947B2 (en)
JP5378137B2 (en) Reinforcement structure for existing fabric foundation and foundation
CN114232989A (en) Floor slab edge reverse ridge template and erecting method thereof
JP7792083B2 (en) Unit structure and unit structure construction method
KR100338653B1 (en) Construction method or device for construction of concrete
JPS639733Y2 (en)
CN219508852U (en) Closed prefabricated cover plate of basement outer wall post-pouring strip
CN222557939U (en) A heat-proof bridge connection structure for pipes buried in floor slabs and steel bars
JPS6347206Y2 (en)
JPH0529203Y2 (en)
JPH10140828A (en) Enrooting metal fitting for concrete form and method for enrooting concrete form by using the same
JPH0115761Y2 (en)
JPH0233551Y2 (en)
JP3027589U (en) Wooden building connection foundation block
JP2000110173A (en) Foundation construction method and foundation structure
JPH0546572Y2 (en)
CN120844706A (en) Adjustable wall connection assembly and construction method for prefabricated buildings
JPS5925059B2 (en) Temporary fixing method for brick panel erection
CN121066287A (en) Metal reinforcing frame decoration masonry partition wall structure and construction method