Prior art keywords
concrete
hole
frame
connection port
outlet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP61011978A
Other languages
Japanese (ja)
Other versions
JPS62171407A (en
Inventor
Haruo Hirayama
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hirayama Manufacturing Corp
Original Assignee
Hirayama Manufacturing Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hirayama Manufacturing Corp filed Critical Hirayama Manufacturing Corp
Priority to JP61011978A priority Critical patent/JPS62171407A/en
Publication of JPS62171407A publication Critical patent/JPS62171407A/en
Publication of JPH0357689B2 publication Critical patent/JPH0357689B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Connection Or Junction Boxes (AREA)

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は、アウトレツトボツクスの上にコンセ
ントを有するコンセント支持体を接続してなるフ
ロアコンセントを、コンクリート床形成における
コンクリート流し込み時に埋め込む方法に関す
る。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a method for embedding a floor outlet, which is formed by connecting an outlet support having an outlet on an outlet box, during concrete pouring in forming a concrete floor.

(従来の技術) 従来、この種の埋め込み方法として、まずコン
クリートを流し込む前に床形成用枠板上に架台を
仮止めし、該架台上にアウトレツトボツクスをネ
ジにより固定し、次に枠板上に生コンクリート流
し込み、上記アウトレツトボツクスをコンクリー
ト内に埋没させ、次にコンクリート硬化後上記ア
ウトレツトボツクスの接続口の上にあるコンクリ
ートを削り取つて該接続口を露出させる穴をあけ
ると共に、該穴の内周面に生コンクリートを補充
しつつコテ塗りにより次のコンセント支持体の挿
入保持に適合する均整な穴に補修し、次に上記補
修穴からコンセント支持体を挿入してアウトレツ
トボツクスに接続する方法が一般に行われてい
る。しかし、この従来方法では、上記穴の補修を
手作業のコテ塗りで行うため、作業に手数がかか
るばかりでなく、所期の適正な穴に形成すること
が容易でない等の欠点があつた。
(Prior art) Conventionally, as this type of embedding method, first, before pouring concrete, a pedestal is temporarily fixed on a frame plate for floor formation, an outlet box is fixed on the pedestal with screws, and then an outlet box is fixed on the frame plate. Pour fresh concrete over the outlet box, bury the outlet box in the concrete, and then, after the concrete has hardened, scrape off the concrete above the outlet box connection port to make a hole to expose the connection port. While replenishing the inner surface of the hole with ready-mixed concrete, use a trowel to repair the hole to create a symmetrical hole suitable for inserting and holding the next outlet support, then insert the outlet support through the repaired hole and place it in the outlet box. A commonly used method is to connect. However, in this conventional method, the hole is repaired by hand painting with a trowel, which not only requires a lot of work but also has drawbacks such as difficulty in forming the desired hole properly.

(発明が解決しようとする問題点) 本発明は、従来の欠点を除くことを課題とす
る。
(Problems to be Solved by the Invention) An object of the present invention is to eliminate the conventional drawbacks.

(問題点を解決するための手段) 上記課題を解決するため、本発明の構成は、 床形成用枠板上に架台を仮止めし、該架台上に
アウトレツトボツクスを固定することと、 上記枠板上に生コンクリートを、上記アウトレ
ツトボツクスを埋没させる所定床面の高さまで流
し込むことと、 上記コンクリートの硬化後上記アウトレツトボ
ツクスのコンセント支持体との接続口の上面にあ
るコンクリートを除去して該接続口を露出させる
穴をあけることと、 コンセント支持体の外径より若干外径の大きい
両端開口の補修用枠筒を上記穴内において上記接
続口に開口端をあてて起立させると共に、該枠筒
の外周に生コンクリートを補充して上記穴を均整
穴に補修することと、 上記補充コンクリートの硬化後上記枠筒を抜き
取り、その後の均整穴内にコンセント支持体を挿
入して上記アウトレツトボツクスの接続口に接続
することと、 から成る。以下図面を参照して本発明方法の実施
例を説明する。
(Means for Solving the Problems) In order to solve the above-mentioned problems, the configuration of the present invention includes: temporarily fixing a pedestal on a frame plate for floor formation, and fixing an outlet box on the pedestal; Pour fresh concrete onto the frame board to the height of a predetermined floor surface in which the outlet box will be buried, and after the concrete has hardened, remove the concrete on the top surface of the connection port of the outlet box with the outlet support. making a hole to expose the connection port, and standing a repair frame with open ends at both ends, which has an outer diameter slightly larger than the outer diameter of the outlet support, in the hole and placing the open end against the connection port; Replenishing the outer periphery of the frame tube with fresh concrete to repair the hole into a symmetrical hole; After the supplementary concrete has hardened, the frame tube is removed, and an outlet support is inserted into the symmetrical hole, thereby forming the outlet box. It consists of: connecting to the connection port of; Embodiments of the method of the present invention will be described below with reference to the drawings.

まず、第1図示のようにコンクリート床の下面
を形成すべき木製枠板1の所定位置上面に、門形
の架台2を釘3…により仮止めし、この架台2の
水平上板上にフロアコンセントのうちのアウトレ
ツトボツクス4をのせ、その内側からネジ5,5
を該アウトレツトボツクス2底板を貫通して架台
2上板に螺着してアウトレツトボツクス4を架台
2上に固定する。上記アウトレツトボツクス4は
上面を開口した皿状のもので、その開口部にフロ
アベース6を有し、該フロアベース6の上面を接
続口として開口すると共にその開口部内周面に水
平調整リングを支持すべき溝を形成してある。
First, as shown in the first diagram, a gate-shaped pedestal 2 is temporarily fixed to the upper surface of a wooden frame board 1 at a predetermined position on which the lower surface of the concrete floor is to be formed, with nails 3. Place the outlet box 4 of the outlet and tighten the screws 5 and 5 from the inside.
The outlet box 4 is fixed on the pedestal 2 by passing through the bottom plate of the outlet box 2 and screwing onto the top plate of the pedestal 2. The outlet box 4 is dish-shaped with an open top, and has a floor base 6 in the opening.The top of the floor base 6 is opened as a connection port, and a horizontal adjustment ring is provided on the inner peripheral surface of the opening. A groove is formed for support.

次に、第2図示のように上記フロアベース6の
開口上面に適宜の蓋板7をのせて該開口を覆い、
ついで生コンクリート8を枠板1上に上記フロア
ベース6を埋没させる所定床面の高さまで流し込
む。
Next, as shown in the second figure, a suitable cover plate 7 is placed on the upper surface of the opening of the floor base 6 to cover the opening,
Next, fresh concrete 8 is poured onto the frame board 1 to a predetermined floor height in which the floor base 6 is buried.

上記コンクリート8の硬化後、第3図示のよう
にフロアベース6の開口上面の上にあるコンクリ
ートをたがね等を用いて削り取り、該フロアベー
ス6の蓋板7つき接続口を露出させる穴9をあ
け、ついで蓋板7を取り外す。この場合上記穴9
は通常荒いすり鉢状となる。
After the concrete 8 has hardened, as shown in the third figure, the concrete above the opening of the floor base 6 is scraped off using a chisel or the like, and a hole 9 is used to expose the connection port with the cover plate 7 of the floor base 6. , and then remove the cover plate 7. In this case, the hole 9
Usually has a rough mortar shape.

次に、第4図示のように上記穴9内におけるフ
ロアベース6の接続口端面に両端開口の補修用枠
筒10をその開口端をあてて起立させ、ついで上
記枠筒10の外周面と上記穴9内面との間に生コ
ンクリート11を補充し、その上面を上記コンク
リート8上面と一致させて上記穴9を補修する。
上記補修用枠筒10は、コンセント支持体の外
径、本例ではコンセント支持体の水平調整リング
の外径よりも若干外径の大きい円筒体で、その下
端に、第7,8図示のように開口上端12に嵌合
できる径で適宜先細りに傾斜する錐筒状態手13
を同心的に突設してあり、このような構造の枠筒
10を複数個準備しておき、床コンクリートの厚
さに応じて第7図鎖線で示すように複数個の枠筒
10…を順次開口上端12に継手13を嵌合して
継ぎ足して使用する。なお、本例の枠筒10は、
水平調整リングの外形に応じて筒外周面に母線方
向の突条を隆出している。又枠筒10は成形後の
抜き取りを容易にするため下方へ若干先細りに形
成しておくのもよい。
Next, as shown in FIG. 4, the repair frame 10 with its open ends placed on the end surface of the connection port of the floor base 6 in the hole 9 is erected, and then the outer circumferential surface of the frame 10 and the Fresh concrete 11 is replenished between the inner surface of the hole 9 and the hole 9 is repaired by aligning its upper surface with the upper surface of the concrete 8.
The repair frame cylinder 10 is a cylindrical body whose outer diameter is slightly larger than the outer diameter of the outlet support, in this example, the outer diameter of the horizontal adjustment ring of the outlet support, and has a cylindrical body with an outer diameter slightly larger than the outer diameter of the horizontal adjustment ring of the outlet support in this example. A conical cylinder 13 having a diameter that can fit into the upper end 12 of the opening is tapered as appropriate.
A plurality of frame tubes 10 having such a structure are prepared, and a plurality of frame tubes 10 are arranged concentrically and projectingly as shown by the chain lines in FIG. 7 according to the thickness of the floor concrete. The joints 13 are successively fitted into the upper end 12 of the opening and used as additional parts. Note that the frame cylinder 10 of this example is
A protrusion in the generatrix direction is protruded on the outer peripheral surface of the cylinder according to the outer shape of the horizontal adjustment ring. Further, the frame tube 10 may be formed to be slightly tapered downward in order to facilitate removal after molding.

上記補充コンクリート11の硬化後枠筒10を
上方へ抜き取ると、第5図示のようにフロアベー
ス6の接続口を露出させる均整な穴14が形成さ
れる。
When the frame tube 10 is pulled upward after the supplementary concrete 11 has hardened, a symmetrical hole 14 is formed which exposes the connection port of the floor base 6, as shown in FIG.

コンセント支持体15は、本例では外周面にオ
ネジを有する外筒16の上端にフランジ状のフロ
アプレート17を突設すると共に、外筒16内
に、上記フロアプレート17面から上方に進退自
在の内筒を挿入し、該内筒の側面にコンセントを
取付け、さらに上記外筒16に水平調整リングを
螺合したものである。まず、水平調整リングを外
筒16から分離し、これを上記均整穴14からフ
ロアベース6の溝内に嵌合し、ついでコンセント
支持体15の外筒16を第6図示のように均整穴
14から上記水平調整リングに螺合し、そのフロ
アプレート17をコンクリート11の上面に当接
する。
In this example, the outlet support 15 has a flange-shaped floor plate 17 protruding from the upper end of an outer cylinder 16 which has a male screw on its outer circumferential surface, and a floor plate 17 that is movable upwardly and retractably from the surface of the floor plate 17 inside the outer cylinder 16. An inner cylinder is inserted, an outlet is attached to the side surface of the inner cylinder, and a horizontal adjustment ring is screwed onto the outer cylinder 16. First, the horizontal adjustment ring is separated from the outer tube 16 and fitted into the groove of the floor base 6 through the alignment hole 14, and then the outer tube 16 of the outlet support 15 is inserted into the alignment hole 14 as shown in the sixth figure. The floor plate 17 is screwed onto the horizontal adjustment ring, and the floor plate 17 is brought into contact with the upper surface of the concrete 11.

(発明の効果) 本発明のフロアコンセントのコンクリート床へ
の埋め込み方法によれば、補修用枠筒を使用する
ことによりコンセント支持体の挿入保持に適合す
る均整穴を容易かつ確実に形成することができ、
それによりフロアコンセントの埋め込み作業の能
率向上を実現できるのである。
(Effects of the Invention) According to the method of embedding a floor outlet in a concrete floor of the present invention, by using a repair frame cylinder, it is possible to easily and reliably form a symmetrical hole suitable for inserting and holding an outlet support. I can do it,
This makes it possible to improve the efficiency of embedding floor outlets.

【図面の簡単な説明】[Brief explanation of drawings]

図面は本発明の実施例を示し、第1図はアウト
レツトボツクスを固定した工程の略線正面図、第
2図はコンクリート流し込み工程の同上図、第3
図はコンクリート除去工程の同上図、第4図は補
修用枠筒を用いた穴補修工程の同上図、第5図は
補修用枠筒抜き取り後の同上図、第6図はコンセ
ント支持体接続工程の同上図、第7図は補修用枠
筒の縦断正面図、第8図は同上底面図である。 1……枠体、2……架台、4……アウトレツト
ボツクス、8……生コンクリート、9……穴、1
0……補修用枠筒、11……補充生コンクリー
ト、14……均整穴。
The drawings show an embodiment of the present invention, and FIG. 1 is a schematic front view of the process in which the outlet box is fixed, FIG. 2 is the same view of the concrete pouring process, and FIG.
Figure 4 is the same diagram as above of the concrete removal process, Figure 4 is the same diagram as above of the hole repair process using a repair frame, Figure 5 is the same diagram as above after the repair frame is removed, and Figure 6 is the process of connecting the outlet support. FIG. 7 is a longitudinal sectional front view of the repair frame, and FIG. 8 is a top and bottom view of the same. 1... Frame, 2... Frame, 4... Outlet box, 8... Fresh concrete, 9... Hole, 1
0... Frame tube for repair, 11... Replenishment fresh concrete, 14... Balanced hole.

Claims (1)

【特許請求の範囲】 1 コンクリート床形成用枠板上に架台を仮止め
し、該架台上にアウトレツトボツクスを固定する
ことと、 上記枠板上に生コンクリートを、上記アウトレ
ツトボツクスを埋没させる所定床面の高さまで流
し込むことと、 上記コンクリートの硬化後上記アウトレツトボ
ツクスのコンセント支持体との接続口の上面にあ
るコンクリートを除去して該接続口を露出させる
穴をあけることと、 コンセント支持体の外径より若干外径の大きい
両端開口の補修用枠筒を上記穴内において上記接
続口に開口端をあてて起立させると共に、該枠筒
の外周に生コンクリートを補充して上記穴を均整
穴に補修することと、 上記補充コンクリートの硬化後上記枠筒を抜き
取り、その後の均整穴内にコンセント支持体を挿
入して上記アウトレツトボツクスの接続口に接続
することと、 からなるフロアコンセントのコンクリート床への
埋め込み方法。
[Scope of Claims] 1. Temporarily fixing a pedestal on a concrete floor forming frame plate and fixing an outlet box on the pedestal; burying ready-mixed concrete on the frame plate and burying the outlet box. pouring the concrete to a predetermined floor height; after the concrete has hardened, remove the concrete on the top surface of the connection port of the outlet box with the outlet support to make a hole to expose the connection port; and making a hole to expose the connection port; A repair frame with an outer diameter slightly larger than the outer diameter of the body and open at both ends is erected in the hole by placing the open ends against the connection port, and the hole is balanced by replenishing the outer periphery of the frame with ready-mixed concrete. Repairing the hole; After the supplementary concrete has hardened, the frame tube is removed, and an outlet support is then inserted into the sized hole and connected to the connection port of the outlet box. How to embed it in the floor.
JP61011978A 1986-01-24 1986-01-24 Method of burying floor plug socket in concrete floor Granted JPS62171407A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP61011978A JPS62171407A (en) 1986-01-24 1986-01-24 Method of burying floor plug socket in concrete floor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP61011978A JPS62171407A (en) 1986-01-24 1986-01-24 Method of burying floor plug socket in concrete floor

Publications (2)

Publication Number Publication Date
JPS62171407A JPS62171407A (en) 1987-07-28
JPH0357689B2 true JPH0357689B2 (en) 1991-09-03

Family

ID=11792690

Family Applications (1)

Application Number Title Priority Date Filing Date
JP61011978A Granted JPS62171407A (en) 1986-01-24 1986-01-24 Method of burying floor plug socket in concrete floor

Country Status (1)

Country Link
JP (1) JPS62171407A (en)

Also Published As

Publication number Publication date
JPS62171407A (en) 1987-07-28

Similar Documents

Publication Publication Date Title
JPH0813608A (en) Construction method and guide formwork for thin precast concrete columns
JPH0357689B2 (en)
AU706617B2 (en) Sanitary ware and method of installation
JPH0539150Y2 (en)
JPH09296611A (en) Support-fixing device for safety fence to be installed during construction of concrete structure
JPS5856288Y2 (en) Pedestal for embedded metal fittings
JPH0450325Y2 (en)
JPS5920489Y2 (en) Anchor bolt mounting structure
JPS5922181Y2 (en) Formwork separator mounting bracket
JP3033479U (en) Fixture for draining pipe construction with nail holes in the reinforcing ribs
JPH09310491A (en) Sleeve hole former for concrete slab
JPS6127422Y2 (en)
JPS6323518Y2 (en)
JPH0535188Y2 (en)
JPH0433283Y2 (en)
JPS6032292Y2 (en) formwork equipment
JP2002127119A (en) Tool for temporarily fastening sleeve to form
JPS6022180Y2 (en) Concrete temporary frame tightening fittings
JPH0126827Y2 (en)
JPH0133898Y2 (en)
JPH0725389Y2 (en) Formwork for manhole
JPH0441710Y2 (en)
JPS6212739Y2 (en)
JPS6129888Y2 (en)
JPH0114210Y2 (en)