JPH0358027B2 - - Google Patents
Info
- Publication number
- JPH0358027B2 JPH0358027B2 JP58103746A JP10374683A JPH0358027B2 JP H0358027 B2 JPH0358027 B2 JP H0358027B2 JP 58103746 A JP58103746 A JP 58103746A JP 10374683 A JP10374683 A JP 10374683A JP H0358027 B2 JPH0358027 B2 JP H0358027B2
- Authority
- JP
- Japan
- Prior art keywords
- reinforcement
- frame
- bars
- reinforcements
- stirrup
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Superconductors And Manufacturing Methods Therefor (AREA)
- Thin Film Transistor (AREA)
- Reinforcement Elements For Buildings (AREA)
Description
【発明の詳細な説明】
本発明は、はりの配筋工法に関するものであ
る。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a beam reinforcement construction method.
従来はりの配筋工法としては、一般に、第1図
イ〜オに図示する工法で施工されている。 Conventional beam reinforcement construction methods are generally constructed using the construction methods illustrated in FIG. 1A to 1E.
そこで、その概要を説明すると、はりの仮わく
1にスペーサ2を設置し、仮わく1の長手方向
に、かつそのスラブ床に数本の受け部材3を適宜
間隔で配置し、その受け部材3上に必要とする数
本の下主筋4、中吊主筋5、上主筋6を載置し、
これらを仮わく1に宙吊り状にする(同図イの状
態)。 Therefore, to explain the outline, spacers 2 are installed on the temporary frame 1 of the beam, several receiving members 3 are arranged at appropriate intervals in the longitudinal direction of the temporary frame 1 and on the slab floor, and the receiving members 3 Place the necessary lower main reinforcements 4, middle suspension main reinforcements 5, and upper main reinforcements 6 on top,
These are suspended on temporary frame 1 (state A in the same figure).
ついで、この宙吊り状の前記下、中吊、上主筋
4,5,6に、あばら筋7を複数本差し入れ、あ
ばら筋7をこれらの掛止する(同図ロの状態)。 Next, a plurality of stirrups 7 are inserted into the suspended lower, middle, and upper main reinforcements 4, 5, and 6, and the stirrups 7 are hooked thereto (the state shown in FIG. 3B).
そして、この例のように中吊主筋5を必要とす
るときは、下主筋4と中吊主筋5等とを区分け
し、その間に更に数本の受け部材8を挿入する
(同図ハの状態)。 When the main suspension reinforcements 5 are required as in this example, the lower main reinforcements 4 and the main suspension reinforcements 5, etc. are separated, and several more receiving members 8 are inserted between them (the state shown in Figure C). ).
この状態において、最初の受け部材3を引き抜
き下主筋4をあばら筋7の水平部に落し、これを
略均等に配置する(同図ニの状態)。 In this state, the first receiving member 3 is pulled out and the lower main reinforcing bars 4 are dropped onto the horizontal portions of the stirrups 7, and they are arranged approximately evenly (state D in the figure).
そして、このあばら筋7と下主筋4とを細い結
束鉄線で約束するのであるが、この場合は前述の
配置と同様に作業者が中吊、上主筋5,6をかき
わけ、上方より手を差し入れ、時には、腹ばいと
なり結束作業をなすのである(同図ホの状態)。 Then, the stirrups 7 and the lower main reinforcements 4 are connected with thin wire binding wires, but in this case, as in the arrangement described above, the worker lifts the middle, cuts through the upper main reinforcements 5 and 6, and inserts his hand from above. At times, they lie on their stomachs to perform the tying work (as shown in Figure 1).
つぎに中吊主筋5と上主筋6とを区分けし、そ
の間に更に別の数本の受け部材9を挿入する(同
図ヘの状態)と共に、中吊主筋5を支持する支持
筋10を前述と同様に中吊、上主筋5,6をかき
わけながら上方より手をもつて差し入れ、あばら
筋7に鉄線で結束する(同図トの状態)。 Next, the main suspension reinforcements 5 and the upper main reinforcements 6 are separated, and several other receiving members 9 are inserted between them (the state shown in the same figure), and the support bars 10 that support the main suspension reinforcements 5 are inserted as described above. In the same way as above, insert your hand from above while pushing aside the upper main reinforcements 5 and 6, and tie it to the stirrup 7 with iron wire (the state shown in Figure 3).
続いて、この支持筋10上に中吊主筋5を載置
する(同図チの状態)とともに、この中吊主筋5
と支持筋10とを、上主筋6をかきわけながら上
方より手を差し入れ、配置及び鉄線で結束する
(同図リの状態)。 Next, the main suspension reinforcement 5 is placed on the support bar 10 (the state shown in Figure 1), and the main reinforcement 5 is
and the support bars 10 are inserted from above while passing through the upper main bars 6, and are arranged and tied together with iron wire (the state shown in Fig. 1).
その後、あばら枠筋11を、あばら筋7の上端
折曲部に差し渡し鉄線で結束する(同図ヌの状
態)とともに、このあばら枠筋11に上主筋6を
配置し結束する(同図ルの状態)。 Thereafter, the stirrup bars 11 are tied together with iron wire across the bent portion of the upper end of the stirrup bars 7 (the state shown in Figure 1), and the upper main reinforcement 6 is placed on the stirrup bars 11 and tied together (the state shown in Figure 2). situation).
これによつて、はりの配筋は、原則として組み
立て完了である。 With this, the beam reinforcement is, in principle, completed.
そして、最後に、上主筋6を吊架している受け
部材9を引き抜き、組み立てられたはりの配筋
を、仮わく1内のスペーサ2上に落し込めば、は
りの配筋が終了するのである。このような従来の
工法では下記の様な欠点があつた。 Finally, by pulling out the receiving member 9 that suspends the upper main reinforcement 6 and dropping the assembled beam reinforcement onto the spacer 2 in the temporary frame 1, the beam reinforcement is completed. be. Such conventional construction methods had the following drawbacks.
(1) 上下主筋、必要により中吊主筋を配置後、あ
ばら筋を差し入れる方法であり、その差し入れ
が大変であるとともに、各種主筋に対してあば
ら筋を略均等間隔に配置することが困難である
こと。(1) This is a method of inserting stirrups after placing upper and lower main reinforcements and, if necessary, center suspension main reinforcements, which is difficult to insert and also makes it difficult to arrange stirrups at approximately equal intervals with respect to the various main reinforcements. Something.
(2) 上下主筋等を配設後、下主筋必要に応じて中
吊主筋、更に上主筋を整列配置し、結束するの
で、それぞれ上方に位置する主筋例えば上主筋
を配置、結束する時に、中吊主筋、上主筋が邪
魔となり、これらの作業が大変で、手間を要す
ると共に、作業性が悪いこと。(2) After arranging the upper and lower main reinforcements, the lower main reinforcement, if necessary, the middle suspension main reinforcements and then the upper main reinforcements are aligned and tied. The main suspension bars and top main bars get in the way, making these tasks difficult and time-consuming, and the workability is poor.
(3) とくに下主筋を配置、結束するときは、作業
者が腹ばいとなり作業しなければならないこと
が多く、ことにはりの有効せいが、高ければ高
いほど前述の作業の不可欠で、作業性が極度に
悪くなるものである。(3) In particular, when arranging and tying the lower main reinforcement, workers often have to work while lying on their stomachs, and the higher the effectiveness of the beam, the more essential the above-mentioned work becomes, and the easier the work becomes. It gets extremely bad.
(4) 受け部材を、各種主筋に区分けして挿入若し
くは引き抜かねばならず、大変に面倒であるこ
と。(4) The receiving member must be inserted or pulled out by dividing it into various main reinforcements, which is very troublesome.
(5) 前述の如く、作業性が悪いことによる工期の
長期化と、作業者の確保が必要となり、経済面
で問題があること。(5) As mentioned above, the construction period is prolonged due to poor workability, and it is necessary to secure workers, which poses economic problems.
従来の欠点を解消する方法の一例として、下記
のような技術文献が、挙げられる。 As an example of a method for solving the conventional drawbacks, the following technical literature can be cited.
即ち、特開昭58−13833号の梁巾の大きな地中
梁の組み工法がある。 That is, there is a construction method using underground beams with a large beam width, as disclosed in Japanese Patent Application Laid-Open No. 58-13833.
この発明は、梁の組み工法であつて、梁成腹筋
を備えた一方の側面相当部及び梁成腹筋を備えた
梁底相当部、並びに他方の側面下端相当部とを屈
曲形成した上面開放で、かつ他方の側面相当部を
欠く形態の籠状筋を設けること。 The present invention is a beam assembly method in which a portion corresponding to one side surface having a beam abdominal reinforcement, a portion corresponding to a beam bottom having a beam abdominal reinforcement, and a portion corresponding to the lower end of the other side surface are bent and the top surface is open. , and provide a cage-shaped strip that lacks a portion corresponding to the other side surface.
前記籠状筋の梁底相当部に、梁底腹筋を備えた
中子筋の梁成下端相当部を設けること。 A portion corresponding to the beam bottom end of a core reinforcement provided with a beam bottom abdominal muscle is provided in a portion corresponding to the beam bottom of the cage reinforcement.
前記中子筋の梁成下端相当部に梁成腹筋を備え
た中子筋相当部を設けること。 A portion corresponding to the core muscle including a beam abdominal muscle is provided at a portion corresponding to the lower end of the beam formation of the core muscle.
前記他方の側面下端相当部に、メツシユ化物を
組み付けて他方の側面相当部を、継手を取付けな
がら現場作業で、組み付ける現場組付け作業をす
ること、
前記梁成の一方又は他方の側面相当部(両側面
相当部とする。)を安定させるために巾止め筋を
配筋、結束する両側面相当部の安定作業をするこ
と、
前記両側面相当部の最上部に設けたかんざし筋
を介して、上部主筋を設けること、
前記上部主筋に、重畳するようにしてメツシユ
化物を設けたこと、
で構成されている。 On-site assembly work is carried out in which a mesh is assembled to the part corresponding to the lower end of the other side surface, and the part corresponding to the other side surface is assembled on-site while the joint is attached; To stabilize the parts corresponding to both sides, by arranging and tying the stop bars in order to stabilize the parts corresponding to both sides. The present invention is comprised of: providing an upper main reinforcement; and providing a mesh material so as to overlap the upper main reinforcement.
したがつて、この引例発明では、はりの枠筋を
構成するために、前述の如く、他方の側面下端相
当部に、メツシユ化物を組み付けて他方の側面相
当部を、継手を取付けながら現場作業で、組み付
ける現場組付け作業を要する。 Therefore, in this cited invention, in order to construct the frame reinforcement of the beam, as described above, a mesh material is assembled to the portion corresponding to the lower end of the other side surface, and the portion corresponding to the other side surface is assembled on-site while installing the joint. , requires on-site assembly work.
よつて、この発明は、枠筋構成に、余分の手間
を要することと、他方の側面相当部と、一方の側
面相当部との正確性の確保の困難性があり得るこ
とと、この正確性を確保しようとすると、かなり
の熟練が、要求される。 Therefore, the present invention requires extra effort in configuring the frame reinforcement, and it may be difficult to ensure accuracy between the other side surface portion and one side surface portion, and this accuracy In order to ensure this, considerable skill is required.
また前記両側面相当部を、安定させるために
は、前記他方の側面下端相当部に、メツシユ化物
を組み付けて他方の側面相当部を設けることが必
要となり、かなり繁雑かつ手間を要するものであ
る。 In addition, in order to stabilize the portions corresponding to both side surfaces, it is necessary to assemble a mesh material to the portion corresponding to the lower end of the other side surface to provide the portion corresponding to the other side surface, which is quite complicated and time-consuming.
上記に鑑み、本発明は、配筋作業の正確性、並
びに配筋の容易化、又はその結束作業の容易化を
達成すること。 In view of the above, it is an object of the present invention to achieve accuracy in reinforcement work, as well as ease of reinforcement work or easing of reinforcement work.
また、当初より一体構造の枠筋を有効利用し
て、巾止め筋等を必要としないはりの配筋工法を
提供し、配筋及び結束作業等の簡素化又はスピー
ド化に、大いに役立つこと、及び人員の削減をも
期待できること。 In addition, it provides a beam reinforcement construction method that makes effective use of integrally structured frame reinforcement from the beginning and does not require stop bars, etc., and is greatly useful for simplifying and speeding up reinforcement work, etc. Also, a reduction in the number of personnel can be expected.
等を目的として、創作されたものである。It was created for the purpose of
以下、本発明の一実施例を、図面を参照しなが
ら説明する。 An embodiment of the present invention will be described below with reference to the drawings.
先ず、側面視してほぼ倒コ字形をなす数本のあ
ばら筋21を適宜間隔で立設し、その両垂直部2
1′,21′にそれぞれ横筋22を配し、溶着若し
くは細い結束鉄線で結束し、第2図、第3図のよ
うな枠筋23を構成する。 First, several stirrups 21 that are approximately inverted U-shaped when viewed from the side are erected at appropriate intervals, and both vertical portions 2
Horizontal reinforcements 22 are arranged at 1' and 21', respectively, and are welded or bound with thin wire binding wires to form frame reinforcements 23 as shown in FIGS. 2 and 3.
通常、前記枠筋23は、工場生産される。 Usually, the frame reinforcement 23 is produced in a factory.
但し、この枠筋23の幅方向の大きさ又は長手
方向の長さは配設部位により区々となる。 However, the size in the width direction or the length in the longitudinal direction of the frame reinforcement 23 varies depending on the location where it is provided.
具体的には、例えば、前記幅方向の大きさと
は、短辺X方向に形成されるはりの仮わく24又
は24′の幅の大きさ(第4図で、図面上に於て、
上下方向の幅の大きさを云う。)、又は長辺Y方向
に形成されるはりの仮わく24″,24a″の幅の
大きさ(第4図で、図面上に於て、左右方向の幅
の大きさを云う。)となつている(但し、これは
一例であり、この例に限定されない。)。 Specifically, for example, the size in the width direction refers to the width of the temporary frame 24 or 24' of the beam formed in the short side X direction (in the drawing in FIG. 4).
Refers to the width in the vertical direction. ), or the width of the temporary frames 24'', 24a'' of the beam formed in the long side Y direction (in Fig. 4, this refers to the width in the left and right direction on the drawing). (However, this is just an example and is not limited to this example.)
また前記長手方向の長さとは、第4図のように
短辺X方向では、柱の仮わく44,44′と44,
44′との間に形成される長さ、即ちスパン間隔
100を云い、又第4図のように長辺Y方向で
は、柱の仮わく44と44′との間に形成される
長さ、即ちスパン間隔200を云いものとする
(但し、これは一例であり、この例に限定されな
い。)。 Furthermore, the length in the longitudinal direction means, in the short side X direction as shown in FIG.
44', that is, the span interval 100, and in the long side Y direction as shown in FIG. That is, the span interval is 200 (however, this is an example and is not limited to this example).
そして、第4図ように柱の仮わく44,44′
内には、前記枠筋23は配設されない。 Then, as shown in Figure 4, the temporary frames 44, 44' of the pillars are
The frame reinforcement 23 is not provided inside.
以上のようにスパン間隔100とほぼ同じ長さ
の枠筋23を、短辺X方向のはりの仮わく24,
24′に、同様にスパン間隔200とほぼ同じ長
さの枠筋23をはりの仮わく24″,24a″に、
それぞれ挿設することによつて、図示の全てのは
りの仮わく24,24′,24″,24a″内に、ス
ペーサ24aを介して枠筋23が配設される(第
5図Aの状態)。 As described above, frame reinforcements 23 with approximately the same length as the span interval 100 are placed in the temporary frame 24 of the beam in the short side X direction,
24', frame reinforcing bars 23 of approximately the same length as the span interval 200 are placed on the temporary frames 24'' and 24a'' of the beams.
By inserting the frame reinforcements 23 into the temporary frames 24, 24', 24'', and 24a'' of all the illustrated beams, the frame reinforcements 23 are installed via the spacers 24a (the state shown in FIG. 5A). ).
この状態に於いて、例えば短辺X方向の各はり
の仮わく24(24′も以下同様であり、代表し
て24で説明する。)に配設された枠筋23のあば
ら筋21の水平部21″に直交する方向いわゆる
仮わく24の長手方向に下主筋25を数本略均等
間隔に配設し(第5図Bの状態)、ついでこのあ
ばら筋21と下主筋25とを鉄線で結束する(第
5図Cの状態)。 In this state, for example, the horizontal position of the stirrup 21 of the frame reinforcement 23 arranged on the temporary frame 24 (24' is the same below, and will be described as 24 as a representative) of each beam in the short side X direction. Several lower main reinforcements 25 are arranged at approximately equal intervals in the longitudinal direction of the so-called temporary frame 24 in the direction perpendicular to the section 21'' (the state shown in FIG. 5B), and then the stirrups 21 and the lower main reinforcements 25 are connected with iron wire. Tie it up (state shown in Figure 5C).
その後長辺Y方向のはりの仮わく24″(24
a″も以下同様であり、代表して24″で説明す
る。)に配設された枠筋23のあばら筋21の水
平部21″に直交する方向いわゆる仮わく24″の
長手方向に下主筋125を数本略均等間隔に配設
すると共に、前記短辺X方向の各下主筋25の上
に重畳される。(第5図Dの状態参照)。 After that, the temporary beam frame 24'' (24
The same applies to a'', and 24'' will be explained as a representative. ), several lower main reinforcements 125 are arranged at approximately equal intervals in the longitudinal direction of the so-called temporary frame 24'' in a direction perpendicular to the horizontal portion 21'' of the stirrup 21 of the frame reinforcement 23 arranged in It is superimposed on each lower main reinforcement 25 in the direction. (See the state in Figure 5D).
ついでこのあばら筋21と下主筋125とを鉄
線で結束する(第5図Dの状態参照)。 Next, the stirrup 21 and the lower main reinforcement 125 are tied together with iron wire (see the state shown in FIG. 5D).
このようにして短辺X及び長辺Y方向の下主筋
25,125の配筋が終了したならば、各柱の仮
わく44,44′内で、前記両下主筋25,12
5が交錯する上に重畳するようにけい筋26を配
置し、柱の数本の主筋225にそれぞれ結束する
(最終的には、この第5図Dの状態となる)。 When the reinforcement of the lower main reinforcements 25, 125 in the short side X and long side Y directions is completed in this way, both the lower main reinforcements 25, 125 are
5 are intersected and overlapped, and each is tied to several main reinforcements 225 of the column (finally, the state shown in FIG. 5D is obtained).
続いて場合により、例えば短辺X方向のはりの
仮わく24,24′に配設したあばら筋21の両
垂直部21′,21′下方に支持筋27を差渡し、
その両垂直部21′,21′下方に支持筋27を差
渡し結束する(第5図Eの状態)。 Then, depending on the case, for example, the support bars 27 are passed below both vertical parts 21', 21' of the stirrups 21 arranged on the temporary frames 24, 24' of the beams in the short side X direction,
The support bars 27 are passed and tied below both vertical portions 21', 21' (state shown in FIG. 5E).
ついでこの支持筋27上にそれと直交する数本
の下側の中吊主筋28(以下単に中吊主筋28と
する。)を配置し(第5図Fの状態)、この支持筋
27と中吊主筋28とをを結束する。 Next, several lower main suspension reinforcements 28 (hereinafter simply referred to as main suspension reinforcements 28) are placed on this support bar 27 and perpendicular thereto (the state shown in Fig. 5F), and the support bars 27 and Bind the main reinforcement 28.
これにより、短辺X方向の支持筋27及び下側
の中吊主筋28の、配筋及び結束が終了する(第
5図Gの状態)。 This completes the reinforcement arrangement and bundling of the support bars 27 in the short side X direction and the lower suspension main bars 28 (state shown in FIG. 5G).
その後、長辺Y方向のはりの仮わく24″に配
設された枠筋23のあばら筋21の両垂直部12
1′に、既に結束されている支持筋127上に、
この支持筋127と直交する方向に、数本の下側
の中吊主筋128を配置し、その支持筋127に
下側の中吊主筋128を結束する。 After that, both vertical parts 12 of the stirrup 21 of the frame reinforcement 23 arranged on the temporary frame 24'' of the beam in the long side Y direction
1', on the support bars 127 that have already been tied,
Several lower main suspension bars 128 are arranged in a direction orthogonal to the support bars 127, and the lower main bars 128 are tied to the support bars 127.
また前記短辺X方向のあばら筋21の垂直部2
1′,21′と横筋22とは、数本の補助筋30を
結束する方式、又は長辺Y方向あばら筋21の垂
直部121′,121′と横筋22とに数本の補助
筋130を結束する方式も採用される。 Also, the vertical portion 2 of the stirrup 21 in the short side X direction
1', 21' and the horizontal reinforcements 22 can be constructed by bundling several auxiliary reinforcements 30, or by connecting several auxiliary reinforcements 130 to the vertical parts 121', 121' of the long side Y-direction stirrups 21 and the horizontal reinforcements 22. A binding method is also adopted.
このようにして、短辺X及び長辺Y方向の下側
の中吊主筋28,128の配筋が終了したなら
ば、各柱の仮わく44,44′内で、前記両中吊
主筋28,128が交錯する上に重畳するように
けい筋26′を配置し、柱の数本の主筋225に
それぞれ結束する(第5図Hの状態)。 In this way, when the reinforcement of the lower main suspension reinforcements 28, 128 in the short side , 128 are arranged so that they intersect and overlap each other, and are tied to several main reinforcements 225 of the column (the state shown in FIG. 5H).
その後、上側の中吊主筋32(以下単に中吊主
筋32とする。)を配筋する場合は、例えば、短
辺X方向のはりの仮わく24′上端部に、差渡し
た受け部材31上に短辺X側の中吊主筋32を数
本配置する(第5図Iの状態)。 After that, when arranging the upper main suspension reinforcement 32 (hereinafter simply referred to as the main suspension reinforcement 32), for example, place the support member 31 on the upper end of the temporary frame 24' of the beam in the short side X direction. Several main suspension reinforcements 32 are placed on the short side X side (the state shown in Fig. 5I).
ついで前記中吊主筋32に跨るようにして、支
持筋33をあばら筋21の両垂直部21′,2
1′上方に差渡し、この両垂直部21′,21′上
方に支持筋33を差渡し結束する(第5図Jの状
態参照)。 Next, the support bars 33 are attached to both vertical parts 21', 2 of the stirrup 21 so as to straddle the main suspension bars 32.
1' and above both vertical parts 21' and 21', support bars 33 are passed and tied (see the state shown in FIG. 5J).
ついで、この支持筋33下に、それと直交する
数本の中吊主筋32を配置し、この支持筋33と
中吊主筋32とを結束し、続いて受け部材31を
引き抜く(最終的には、第5図Jの状態)。 Next, several main suspension reinforcements 32 are placed below this support bar 33 and perpendicular thereto, and the support bars 33 and main suspension bars 32 are tied together, and then the receiving member 31 is pulled out (finally, Figure 5 J condition).
同様な操作を長辺Y側についてもなす(図示せ
ず)。 A similar operation is performed on the long side Y side (not shown).
その後、短辺X側の前記支持筋33上に上主筋
34を、数本配置し(第5図Kの状態)、これと
同様に長辺Y側の前記支持筋(図示せず)につい
ても、同様な操作をする。 After that, several upper main reinforcements 34 are arranged on the support reinforcements 33 on the short side , perform similar operations.
続いて、前記短辺X側の支持筋33又は長辺Y
側の支持筋(図示せず)の、それぞれに直交する
ように数本のあばら枠筋35を適宜間隔で配置
し、このあばら枠筋35を枠筋23の上端部に結
束する。 Next, the support bars 33 on the short side X side or the long side Y
Several stirrups 35 are arranged at appropriate intervals so as to be orthogonal to each of the side support bars (not shown), and the stirrups 35 are tied to the upper end of the frame reinforcement 23.
そうして、前記のようにして結束されたあばら
枠筋35の下方に、短辺X側又は長辺Y側のそれ
ぞれの上主筋34を、持ち上げながら添設かつ結
束することによつて、ここにはりの配筋が完了す
る(第5図Lの状態)。 Then, the upper main reinforcements 34 on the short side X side or the long side Y side are attached and tied together while lifting them below the stirrup reinforcements 35 that have been tied together as described above. The beam reinforcement is completed (state shown in Figure 5 L).
尚図示しないが中吊主筋32の配設しないとき
は、例えば短辺X側のはりの仮わく24,24′
に適宜間隔で受け部材(図示せず)を差渡し、こ
の受け部材(図示せず)に数本の上主筋34を配
筋する。 Although not shown, when the main suspension reinforcement 32 is not installed, for example, the temporary frames 24, 24' of the beam on the short side
A receiving member (not shown) is passed at appropriate intervals, and several upper main reinforcements 34 are arranged on this receiving member (not shown).
そして次に、同様な操作を介して長辺Y側に
も、数本の上主筋(図示せず)を配筋する。 Next, several upper main reinforcements (not shown) are arranged on the long side Y side through a similar operation.
その以後は、あばら枠筋35の配筋及び結束、
また上主筋34、上主筋(図示せず)の配設及び
結束更に受け部材(図示せず)の引き抜き等前述
の例と同様に操作する。 After that, the reinforcement and binding of the stirrup bars 35,
In addition, operations such as arranging and binding the upper main reinforcement 34 and the upper main reinforcement (not shown), and pulling out the receiving member (not shown) are performed in the same manner as in the above-mentioned example.
ここにはりの配筋が完了する。 The beam reinforcement is completed here.
その後は、従来と同様にはりの仮わく24,2
4′,24″,24a″、又は柱の仮わく44、4
4′内に、生コンクリートを流し込みの作業をす
る。 After that, the temporary frames 24 and 2 of the beams are used as before.
4', 24'', 24a'' or temporary frame of the column 44, 4
Pour fresh concrete into 4'.
本発明は、以上で詳述したように、工場で予め
製作された、上面開放のはりの枠筋を、それぞれ
はりの仮わく内で、かつスパン間に配設すること
と、及びその後下主筋、上主筋を配筋し、ついで
あばら筋筋を設ける構成である。 As described in detail above, the present invention involves arranging the frame reinforcements of the beams with open tops, which are manufactured in advance in a factory, within the temporary frames of the beams and between the spans, and then the lower main reinforcements. , the upper main reinforcement is arranged and then the stirrup reinforcement is provided.
したがつて、下記のような作用効果があります
ので、以下に、具体的に、列挙します。 Therefore, it has the following effects, which are specifically listed below.
本発明は、前記の如く、枠筋は、予め設計通
り構成されていることから、はりの仮わく内
に、あばら筋及び横筋を、設計通りに配筋でき
る。 In the present invention, as described above, since the frame reinforcement is configured in advance as designed, the stirrups and transverse reinforcement can be arranged in the temporary frame of the beam as designed.
前述の如く、あばら筋及び横筋を、設計通り
に配筋した後に、上下主筋又はあばら枠筋もま
た設計通りに配筋できる効果があり、配筋作業
の正確性、並びに配筋の容易化、又はその結束
作業の容易化が達成される。 As mentioned above, after the stirrups and transverse reinforcements have been arranged as designed, the upper and lower main reinforcements or stirrup bars can also be arranged as designed, which improves the accuracy of the reinforcement work and facilitates the reinforcement work. Alternatively, the bundling work can be facilitated.
また本発明では、あばら筋及び横筋、又は上
下主筋並びにあばら枠筋の設計通りに配筋でき
る、いわゆる配筋の精度の向上を介して、は
り、柱等の強度の向上が可能となる。 Further, according to the present invention, it is possible to improve the strength of beams, columns, etc. by improving the accuracy of so-called reinforcement arrangement, which allows the reinforcement to be arranged according to the design of stirrups and transverse reinforcements, or upper and lower main reinforcements, and stirrup reinforcements.
更に本発明では、枠筋が、当初より一体構造
であるので、この枠筋を安定させるための、巾
止め筋を設ける必要がなく、配筋及び結束作業
等の簡素化又はスピード化に、大いに役立つ処
である。 Furthermore, in the present invention, since the frame reinforcement has an integral structure from the beginning, there is no need to provide a stopper reinforcement to stabilize the frame reinforcement, which greatly simplifies and speeds up reinforcement work, etc. This is a useful place.
また人員の削減も期待できる。 We can also expect a reduction in personnel.
尚本発明では、巾止め筋(支持筋)を設けな
くても、枠筋は、その形状を維持しており、形
状維持のための特別な配慮を要さないことか
ら、前述の配筋の容易化、又はその結束作業の
容易化が達成される。 Furthermore, in the present invention, the frame reinforcement maintains its shape even without providing the width-stopping reinforcement (supporting reinforcement), and no special consideration is required to maintain the shape. Facilitation or facilitation of the bundling work is achieved.
第1図イ〜オは、従来の配筋工法の一例を示す
模式図である。第2図〜第5図は、本発明のはり
の配筋工法を示しており、先ず第2図は枠筋の正
面模式図、第3は同上平面模式図、第4図はりの
仮わく並びに柱の仮わく内を平面状に示し、各は
りの仮わく内に枠筋を挿設した状態の全体の平面
図、第5図A〜Lは配筋工法の一例を示す模式図
である。
21……あばら筋、22……横筋、23……枠
筋、24,24′,24″,24a″,44,44′
……仮わく、24a……スペーサ、25……下主
筋、26,26′……けい筋、27……支持筋、
28……中吊主筋、30……補助筋、31……受
け部材、32……中吊主筋、34……上主筋、3
5……あばら枠筋。
FIGS. 1A to 1E are schematic diagrams showing an example of a conventional reinforcement construction method. Figures 2 to 5 show the beam reinforcement construction method of the present invention. First, Figure 2 is a schematic front view of the frame reinforcement, Figure 3 is a schematic plan view of the same, and Figure 4 is the temporary frame of the beam and FIGS. 5A to 5L are schematic diagrams showing an example of the reinforcing construction method. 21... Stirrups, 22... Transverse bars, 23... Frame bars, 24, 24', 24'', 24a'', 44, 44'
... Temporary frame, 24a ... Spacer, 25 ... Lower main reinforcement, 26, 26' ... Tibial muscle, 27 ... Supporting reinforcement,
28... Main suspension reinforcement, 30... Auxiliary reinforcement, 31... Reception member, 32... Main suspension reinforcement, 34... Top main reinforcement, 3
5...Stirrel frame.
Claims (1)
コ字形をなすあばら筋に、数本の横筋を設けてな
る上面が開放された枠筋を、予め製作する枠筋構
成作業と、 この枠筋構成作業で既に構成された上面開放
で、かつ所定の長さを有する枠筋を、前記はりの
仮わく内のスパン間隔に、スペーサを介して挿設
する枠筋の挿設作業と、 ついで前記はりの仮わく内に挿設された枠筋の
あばら筋の水平部にそれと直交するように数本の
下主筋を配設し、この各下主筋とあばら筋とをそ
れぞれ結束する下主筋の配設及び結束作業と、 その後、前記はりの仮わく内に、挿設された下
主筋に間隔を於て重畳されるように、上主筋を受
け部材を介して配設する上主筋の配設作業と、 続いて前記各あばら筋の上端部で、かつ前記各
上主筋を跨設するようにあばら枠筋をそれぞれ配
設するとともに、このあばら枠筋と前記あばら筋
とを結束するあばら枠筋の配設及び結束作業と、 その後受け部材を抜き取るとともに、この上主
筋とあばら枠筋とをそれぞれ結束する上主筋の結
束作業と、 によつてはりの配筋を組み立てるようにしたこと
を特徴とするはりの配筋工法。[Scope of Claims] 1. A frame in which a frame reinforcement with an open upper surface is made in advance by providing several horizontal reinforcements in a large number of stirrups that are arranged at appropriate intervals and have an approximately inverted U-shape when viewed from the side. Reinforcement construction work, and frame reinforcement work in which frame reinforcements with open tops and predetermined lengths, which have already been constructed in this frame reinforcement construction work, are inserted at span intervals within the temporary frame of the beam through spacers. Next, several lower main reinforcements were placed perpendicular to the horizontal part of the frame reinforcement stirrups inserted into the temporary frame of the beam, and each lower main reinforcement and stirrup arranging and tying the lower main reinforcing bars to bind the beams, and then placing the upper main reinforcing bars in the temporary frame of the beam via receiving members so that they overlap the inserted lower main reins at intervals. Next, each stirrup reinforcement is placed at the upper end of each of the above-mentioned stirrup bars so as to straddle each of the above-mentioned upper main reinforcements, and this stirrup reinforcement and the above-mentioned stirrup reinforcement arranging and tying the stirrup bars to tie together the upper main bars and the stirrup bars, then removing the receiving member and tying the upper main bars to bind the upper main bars and the stirrup bars, respectively, and assembling the bar arrangement of the beam. A beam reinforcement construction method characterized by the following.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP10374683A JPS59228568A (en) | 1983-06-09 | 1983-06-09 | Wire arrangement of beam |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP10374683A JPS59228568A (en) | 1983-06-09 | 1983-06-09 | Wire arrangement of beam |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS59228568A JPS59228568A (en) | 1984-12-21 |
| JPH0358027B2 true JPH0358027B2 (en) | 1991-09-04 |
Family
ID=14362154
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP10374683A Granted JPS59228568A (en) | 1983-06-09 | 1983-06-09 | Wire arrangement of beam |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS59228568A (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS61146969A (en) * | 1984-12-17 | 1986-07-04 | 株式会社竹中工務店 | Assembling of reinforcement of beam |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS6019389B2 (en) * | 1980-11-12 | 1985-05-16 | 義美 溝口 | beam dropping device |
| JPS5813833A (en) * | 1981-07-20 | 1983-01-26 | Hiroshi Suwa | Assembling work for underground beam of large span |
-
1983
- 1983-06-09 JP JP10374683A patent/JPS59228568A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS59228568A (en) | 1984-12-21 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JPH06136857A (en) | Method of connecting precast concrete wall column and precast concrete wall | |
| JPH0358027B2 (en) | ||
| JPH0747544Y2 (en) | Shear reinforcement structure of reinforced concrete or steel reinforced concrete beams | |
| JP2542283B2 (en) | Joining Method of Beam Reinforcement in Wall-type Ramen Column | |
| JPS62305B2 (en) | ||
| JPH0452321Y2 (en) | ||
| JPH0738516Y2 (en) | Reinforcing bar for opening | |
| JP2651322B2 (en) | Construction method of wall type rigid frame structure | |
| KR102175474B1 (en) | Rebar assembly | |
| JPH07212B2 (en) | Method of assembling beam reinforcement and stirrups used for it | |
| JPH0732713Y2 (en) | Spacer for upper slab muscle | |
| JPH066552U (en) | Shear reinforcement with integrated accessory muscle | |
| JPH0437129Y2 (en) | ||
| JPS6039835B2 (en) | Reinforced steel construction method | |
| JP2542279B2 (en) | Joining method of main bar in wall type frame method | |
| JP2024011689A (en) | Void unit for concrete | |
| JPH11210228A (en) | Arrangement method of wall and floor slab | |
| JPH09151561A (en) | Beam reinforcement structure | |
| JPH056336Y2 (en) | ||
| JPH0558704U (en) | Precast reinforced concrete structure | |
| JPH0572506B2 (en) | ||
| JPH0216824B2 (en) | ||
| JPH06146301A (en) | Reinforcement unit for concrete foundation and connection method thereof | |
| JPH0231186B2 (en) | ||
| JPH0610511A (en) | Reinforcement method for columns and beams of buildings |