JPH0359203B2 - - Google Patents
Info
- Publication number
- JPH0359203B2 JPH0359203B2 JP60017603A JP1760385A JPH0359203B2 JP H0359203 B2 JPH0359203 B2 JP H0359203B2 JP 60017603 A JP60017603 A JP 60017603A JP 1760385 A JP1760385 A JP 1760385A JP H0359203 B2 JPH0359203 B2 JP H0359203B2
- Authority
- JP
- Japan
- Prior art keywords
- steel material
- tension
- slab
- floor slab
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Bridges Or Land Bridges (AREA)
- Working Measures On Existing Buildindgs (AREA)
Description
【発明の詳細な説明】
〔産業上の利用分野〕
この発明は床版の敷設工法に関するものであ
る。[Detailed Description of the Invention] [Industrial Application Field] This invention relates to a method for laying floor slabs.
橋梁の床版補修工事等において、プレキヤスト
コンクリート製の床版に打換えることがある。す
なわち既設の床版を打ち壊して新たに方形状の床
版を複数枚連続して敷設するものである。
In bridge deck repair work, etc., deck slabs may be replaced with precast concrete slabs. In other words, the existing floor slab is demolished and a plurality of new rectangular floor slabs are successively laid.
このような工事においては交通の規制を最小限
にするために、工事はほぼ夜間に限られる。従つ
て打ち換え部分を複数に分け、各部分を一夜ごと
に工事を行うようにし、敷設した複数枚の床版ご
とに挿通させたPC鋼材を緊張して仮連結してお
く。次の日前夜に敷設した床版に新たな床版を継
ぎ足し、PC鋼材を床版内に挿通し、前夜に敷設
した床版のPC鋼材にカツプラー等の連結具によ
つて連結し、緊張するという作業を繰り返し、全
体の打ち換えを完了する。 In order to minimize traffic restrictions, construction work is generally limited to nighttime hours. Therefore, the parts to be replaced were divided into multiple parts, each part being worked on overnight, and the prestressed steel members inserted through each of the multiple floor slabs laid were temporarily connected with tension. Add a new slab to the slab that was laid the night before the next day, insert the prestressing steel into the slab, connect it to the prestressing steel of the slab that was laid the night before with a coupling device such as a coupler, and tighten it. Repeat this process to complete the entire replacement.
以上のような工法において問題となるのは以下
の点である。
The problems with the above construction methods are as follows.
まず床版の支持体(主桁等)の不陸、あるいは
床版の寸法精度の誤差により、緊張済みのPC鋼
材の軸心と新たに配置するPC鋼材の軸心が一致
せず、緊張したままでは鋼材同士の接続が困難で
ある。 First, due to unevenness of the deck support (main girder, etc.) or an error in the dimensional accuracy of the deck, the axis of the prestressed prestressing steel material and the newly placed prestressing steel material do not match, resulting in tension. If left as is, it will be difficult to connect steel materials.
また床版接続部の目違いによるPC鋼材軸心の
スズには、偏心だけではなく、軸心同士の角度の
ズレを伴うことが多く、緊張したままでは鋼材同
士の接続は極めて困難である。 Furthermore, the tin of the PC steel shafts due to misalignment of the floor slab connections is often accompanied by not only eccentricity, but also angular deviation between the shaft centers, and it is extremely difficult to connect the steel materials together under tension.
更に既設の緊張鋼材に新たに鋼材を接続し、緊
張力を導入すると既設の緊張鋼材の接続端の定着
具(アンカープレート)は不要となるにもかかわ
らず、緊張したままで接続すると他に転用できな
いという問題がある。ことに鋼材の軸心同士の角
度のズレを伴うときは、既設の緊張鋼材の定着具
を抜き取つてから鋼材を接続する必要がある。 Furthermore, if a new steel member is connected to an existing tension steel member and tension is introduced, the anchor plate at the connection end of the existing tension steel member is no longer required, but if it is connected with tension, it may be used for other purposes. The problem is that it can't be done. In particular, when there is an angular misalignment between the axes of the steel materials, it is necessary to remove the existing tension steel fixtures before connecting the steel materials.
この発明は、平行な二側面に両端が開口する道
路進行方向に貫通したPC鋼材挿通孔を有する方
形パネル状の床版を、既設の床版を撤去した位置
に複数枚載置して、各床版のPC鋼材挿通孔にPC
鋼材を挿通、緊張して仮連結し、該床版に連続し
て床版を設置する際にPC鋼材の緊張を一旦解除
して、連結具により既設のPC鋼材に新たにPC鋼
材を連結して新たな床版に挿通し、再び緊張して
全体を一体化させることにより上記の問題点を解
消するものである。
In this invention, a plurality of rectangular panel-shaped floor slabs each having a prestressed steel insertion hole penetrating in the direction of road travel and open at both ends on two parallel sides are placed in a position where the existing floor slab has been removed. PC in the PC steel material insertion hole of the floor slab
Insert the steel material and temporarily connect it by tensioning it, and when installing the deck slab continuously on the slab, the tension in the prestressing steel material is temporarily released, and the new prestressing steel material is connected to the existing prestressing steel material using a connecting tool. The above problem is solved by inserting it into a new floor slab and tensioning it again to integrate the whole.
以下図に示す一実施例に基づき、この発明を施
工順序ごとに説明する。
The present invention will be explained below for each construction order based on an embodiment shown in the drawings.
実施例は橋梁の床版打ち換え工事におけるもの
である。 The example is a bridge deck replacement work.
〔イ〕 床版
図において1はプレキヤストコンクリート製
の方形パネル状の床版である。床版1には平行
な二側面に開口し、道路進行方向に貫通する
PC鋼材挿通孔2が複数形成されている。[B] Floor slab In the figure, 1 is a rectangular panel-shaped floor slab made of precast concrete. Floor slab 1 has openings on two parallel sides and penetrates in the direction of road travel.
A plurality of PC steel material insertion holes 2 are formed.
〔ロ〕 既設床版撤去(第3図)
既設の床版3を撤去する。工事中の交通を確
保するために図において右半分のみを撤去し、
左半分はそのままにして走行可能としておく。
中央部に道路進行方向に仮高欄4を設置する。[B] Removal of existing floor slab (Figure 3) Remove existing floor slab 3. In order to secure traffic during construction, only the right half of the diagram was removed.
Leave the left half intact so it can be driven.
A temporary railing 4 will be installed in the center in the direction of road travel.
〔ハ〕 補助桁設置(第4図)
床版3を撤去した位置に平行に補助桁5,5
を設置する。[C] Auxiliary girder installation (Fig. 4) Auxiliary girders 5, 5 are installed parallel to the position where the floor slab 3 was removed.
Set up.
〔ニ〕 床版設置(第5図)
既設の床版3を撤去した位置に新たに床版1
を設置する。床版1は夜間に複数枚を道路進行
方向に連続して設置する。複数枚の床版1の
PC鋼材挿通孔2にPC鋼材6を挿通して緊張
し、定着して仮連結しておく。[D] Floor slab installation (Figure 5) New floor slab 1 will be installed at the location where the existing floor slab 3 was removed.
Set up. A plurality of floor slabs 1 are installed successively in the direction of road travel at night. Multiple floor slabs 1
A prestressed steel material 6 is inserted into the prestressed steel material insertion hole 2, tensioned, fixed, and temporarily connected.
〔ホ〕 床版の連結(第6a図〜第6c図)
前日に設置した床版1に連続して新たに床版
1を連結する。連結する際に、PC鋼材6を新
たに設置した床版1のPC鋼材挿通孔2に挿通
して前日定着したPC鋼材6にカツプラー等の
連結具7によつて新たにPC鋼材6を連結して
緊張し、床版1全体を一体に連結する。この作
業を繰り返して全長に床版1を設置するもので
ある。[E] Connection of floor slabs (Figures 6a to 6c) A new floor slab 1 is connected continuously to the floor slab 1 installed the previous day. When connecting, insert the prestressed steel material 6 into the prestressed steel material insertion hole 2 of the newly installed floor slab 1 and connect the new prestressed steel material 6 to the prestressed steel material 6 that was fixed on the previous day using a coupling tool 7 such as a coupler. Then, the entire floor slab 1 is connected together. This work is repeated to install the floor slab 1 along the entire length.
図においては最初に設置した床版1の端部に
ジヤツキ8を設置してPC鋼材6を緊張する場
合を示す。 The figure shows the case where a jack 8 is installed at the end of the first installed floor slab 1 to tension the PC steel material 6.
PC鋼材6,6同士を連結する際に、既設の
PC鋼材6の緊張を一旦解除する。緊張が解除
された状態であればPC鋼材6,6の軸心がズ
レていたり、角度がずれていても容易に連結具
7によつて連結が可能となる。また一旦緊張を
解除すれば、支圧板等の定着具9を取り外すこ
とができる。 When connecting PC steel materials 6 and 6, the existing
Temporarily release the tension on the PC steel material 6. If the tension is released, even if the axes of the PC steel materials 6, 6 are misaligned or the angles are misaligned, the connection can be easily made using the coupling tool 7. Further, once the tension is released, the fixing device 9 such as a bearing plate can be removed.
〔ヘ〕 他の連結方法(第7a図〜第7f図)
その他端部にジヤツキ8を載置できないとき
は、図に示すように床版1のいずれか一枚の上
面に凹部10を設け、PC鋼材挿通孔2を凹部
10の相対向する両内側面に開口して、PC鋼
材6の端部を各々突出させ、該端部を把持して
緊張することが可能である。以下緊張順序を説
明する。[F] Other connection methods (Figures 7a to 7f) If the jack 8 cannot be placed on the other end, a recess 10 is provided on the top surface of one of the floor slabs 1 as shown in the figure, It is possible to open the PC steel material insertion hole 2 on both opposing inner surfaces of the recess 10 so that the ends of the PC steel material 6 protrude, and to grip and tighten the ends. The tension order will be explained below.
前日に設置した複数の床版1,…のPC鋼材
挿通孔2に挿通されたPC鋼材6の一方の端部
は後方の床版1の端部に連結具7により連結さ
れ、他方の端部は凹部10を設けた前方の床版
1の凹部の内側面に定着具9により定着され前
記複数の床版1,…が仮連結されている。 One end of the PC steel material 6 inserted into the PC steel material insertion hole 2 of the plurality of floor slabs 1, ... installed on the previous day is connected to the end of the rear floor slab 1 by a connector 7, and the other end is connected to the end of the rear floor slab 1. is fixed by a fixing device 9 to the inner surface of the recess of the front floor slab 1 provided with the recess 10, and the plurality of floor slabs 1, . . . are temporarily connected.
定着具9を取外し鋼材の緊張を解くと共に、
取外されて凹部10内に突出しているPC鋼材
6の端部に新たにカツプラ等の連結具7の一方
の側を取付ける。 Remove the fixing tool 9 and release the tension on the steel material, and
One side of a coupling tool 7 such as a coupler is newly attached to the end of the removed PC steel material 6 protruding into the recess 10.
新たに設置した複数の床版1,…のPC鋼材
挿通孔2に挿通したPC鋼材6の前方端部を定
着具9により前方の床版1の端部に定着し、後
方端部を凹部を設けた床版1の凹部10内へ突
出させ、凹部10内にジヤツキ8を設置して、
前記鋼材6の後方端部をジヤツキ8の前方に設
けたチヤツクの挿通孔に通して把む。(第7a
図)
ジヤツキ8により前日に挿通したPC鋼材と
新たに挿通したPC鋼材6を緊張させ前記チヤ
ツクに把まれたPC鋼材6の端部を連結具7に
取付け、(第7b図)前日に設置した床版1,
…および新たに設置した床版1,…をPC鋼材
により一体化し、板材26を凹部10に載置す
れば車輌の通行も可能となる。(第7c図)
緊張を一旦解除して定着具9を取外す。(第
7d図)
PC鋼材6の端部に更にPC鋼材6を連結して
連続して敷設した床版1内に挿通する。(第7
e図)
ジヤツキ8によつてPC鋼材6を緊張して床
版1全体を一体に連結する。(第7f図)
ジヤツキ8としては例えば第8図に示すよう
な双胴式のジヤツキ8が使用できる。該ジヤツ
キ8は、2本のシリンダ11,11の両端間
が、中間にU字状の切欠き12が形成された支
圧部13,13によつて連結され、シリンダ1
1,11間にくさび押圧シリンダ14が取付け
られている。くさび押圧シリンダ14のロツド
先端には押圧部15が固定されている。 The front end of the prestressed steel material 6 inserted into the prestressing steel material insertion hole 2 of the newly installed plurality of floor slabs 1,... is fixed to the end of the front floor slab 1 by the fixing device 9, and the rear end is inserted into the recessed part. Protrude into the recess 10 of the provided floor slab 1, install the jack 8 in the recess 10,
The rear end of the steel material 6 is passed through the insertion hole of the chuck provided in front of the jack 8 and grasped. (Chapter 7a
Figure) Using the jack 8, tension the PC steel material 6 inserted the previous day and the newly inserted PC steel material 6, and attach the end of the PC steel material 6 gripped by the chuck to the connector 7, which was installed the previous day (Figure 7b). Floor slab 1,
... and the newly installed floor slabs 1, ... are integrated with prestressed steel and the plate material 26 is placed in the recess 10, allowing vehicles to pass through. (Fig. 7c) Once the tension is released, the fixing tool 9 is removed. (Fig. 7d) The PC steel material 6 is further connected to the end of the PC steel material 6 and inserted into the continuously laid floor slab 1. (7th
Fig. e) The PC steel material 6 is tensioned by the jacks 8 to connect the entire deck 1 together. (Fig. 7f) As the jack 8, for example, a twin-barrel jack 8 as shown in Fig. 8 can be used. The jack 8 has two cylinders 11, 11 whose ends are connected by bearing pressure parts 13, 13 in which a U-shaped notch 12 is formed in the middle.
A wedge pressing cylinder 14 is installed between 1 and 11. A pressing portion 15 is fixed to the rod tip of the wedge pressing cylinder 14.
以上のような構成のジヤツキ8の使用方法に
つき説明する。 A method of using the jack 8 having the above structure will be explained.
第8図に示すジヤツキ8の一方の支圧部13
の切欠き12にPC鋼材6aを挿通してその先
端を連結具7の一方のくさび17で把かみ、連
結具7の後端を支圧部13の内側に当接させ
る。他方の支圧部13の切欠き12にチヤツク
16(第9図参照)の保持筒16aを挿通して
取付け、チヤツク16にPC鋼材6bを挿通し
て把かむ。 One bearing pressure part 13 of the jack 8 shown in FIG.
The prestressing steel material 6a is inserted into the notch 12, and its tip is gripped by one wedge 17 of the connector 7, and the rear end of the connector 7 is brought into contact with the inside of the bearing pressure part 13. The holding cylinder 16a of the chuck 16 (see FIG. 9) is inserted into the notch 12 of the other bearing pressure part 13 and attached, and the PC steel material 6b is inserted into the chuck 16 and gripped.
油圧をシリンダ11内へ送り込み両方の支圧
部13を近接させてPC鋼材6a,6bを緊張
し、PC鋼材6b先端をくさび18に挿通しく
さび押圧シリンダ14の押圧部15によりくさ
び18を押圧してPC鋼材6bを把かみ、PC鋼
材6a,6bを連結具7で連結する。(第9図
〜第11図)シリンダ11内の油圧を開放して
チヤツク16を取り外し、ついでジヤツキ8を
取り外す。 Hydraulic pressure is sent into the cylinder 11 to bring both bearing pressure parts 13 close together to tension the PC steel members 6a and 6b, and the tip of the PC steel member 6b is inserted into the wedge 18 and the wedge 18 is pressed by the pressing part 15 of the wedge pressing cylinder 14. grasp the prestressed steel material 6b, and connect the prestressed steel materials 6a and 6b with the connector 7. (FIGS. 9 to 11) Release the hydraulic pressure in the cylinder 11, remove the chuck 16, and then remove the jack 8.
〔ト〕 その他のジヤツキ
第12図および第13図に示すのは、方形状
の摺動部28に摺動自在にラム19を設け、ラ
ム19と摺動部28下面にフオーク20を各々
突設する。ラム19をシリンダ21によつて摺
動させて、フオーク20,20に把持したPC
鋼材6a,6bを緊張する。緊張した後、別途
用意した連結具7によつてPC鋼材6a,6b
を連結する。[G] Other jacks As shown in FIGS. 12 and 13, a ram 19 is slidably provided on the rectangular sliding portion 28, and forks 20 are protruded from the ram 19 and the lower surface of the sliding portion 28, respectively. do. The ram 19 is slid by the cylinder 21 and the PC is gripped by forks 20, 20.
Tension the steel members 6a and 6b. After applying tension, connect the PC steel materials 6a and 6b using the separately prepared connecting tool 7.
Concatenate.
第14図および第15図に示すのは単胴のシ
リンダ22のケーシングとロツド先端に鉤状の
係止部23,23を設け、係止部23,23に
よつてPC鋼材6a,6bをくさびによつて定
着した連結具7,7を引張る。所定の力で緊張
した後、ボルト24を連結具7,7に掛け渡し
てナツト25により定着する。その後ジヤツキ
8を外せばよい。 14 and 15 show that hook-shaped locking parts 23, 23 are provided on the casing and rod tip of a single-body cylinder 22, and the PC steel materials 6a, 6b are wedged by the locking parts 23, 23. Pull the connectors 7, 7 fixed by the . After being tensioned with a predetermined force, the bolt 24 is passed over the coupling tools 7, 7 and fixed with a nut 25. After that, just remove the jack 8.
その他第16図に示すように双胴のシリンダ
21,21間にPC鋼材6,6の端部を位置さ
せ、筒状の円筒形スリーブ本体7aと、本体に
螺着できる蓋体7bとからなる連結具7の本体
7aの底部につかみ金具27を固定し、蓋体7
bの底部につかみ金具27を回動自在に挿入し
シリンダ21,21を作動させPC鋼材端部を
互いに引き寄せ鋼材を緊張すると共に本体7a
に蓋体7bを螺着してPC鋼材同士を連結具7
により連結してもよい。 In addition, as shown in FIG. 16, the ends of the PC steel materials 6, 6 are positioned between the twin cylinders 21, 21, and the sleeve body 7a has a cylindrical shape, and the lid body 7b can be screwed onto the body. The grip 27 is fixed to the bottom of the main body 7a of the connector 7, and the lid 7
The grip fitting 27 is rotatably inserted into the bottom of the main body 7a, and the cylinders 21 and 21 are actuated to draw the ends of the PC steel materials together, tensioning the steel materials, and tightening the steel materials.
Screw the lid 7b onto the connecting tool 7 to connect the PC steel materials to each other.
They may be connected by
この発明は以上のような構成を有し、PC鋼材
を連結する際に、一旦PC鋼材の緊張を解除して
連結するため、PC鋼材の軸心の偏心によるズレ
や角度のズレがあつてもPC鋼材同士をなじませ
ることができ、容易に連結することができる。ま
た緊張を解除した際に支圧板等の定着具を取り外
して転用することができる。
This invention has the above-mentioned configuration, and when connecting prestressing steel materials, the tension of the prestressing steel materials is first released and then the tension is released, so even if there is a deviation or angular misalignment due to eccentricity of the axis of the prestressing steel materials. PC steel materials can be blended together and easily connected. Further, when the tension is released, the fixing device such as the bearing plate can be removed and used for other purposes.
第1図は橋梁の側面図、第2図はその平面図、
第3図〜第5図は施工順序の縦断面図、第6a図
〜第6c図は床版の連結作業順序の説明図、第7
a図〜第7f図はその他の床版の連結作業順序の
説明図、第8図はジヤツキの斜視図、第9図〜第
11図はジヤツキによる緊張作業順序を示す一部
切欠き平面図、第12図は他のジヤツキの平面
図、第13図はその側面図、第14図はその他の
ジヤツキの一部切欠き平面図、第15図はその側
面図、第16図はその他のジヤツキの横断面図で
ある。
1……床版、2……PC鋼材挿通孔、3……既
設床版、4……仮高欄、5……補助桁、6……
PC鋼材、7……連結具、8……ジヤツキ、9…
…定着具、10……凹部。
Figure 1 is a side view of the bridge, Figure 2 is its plan view,
Figures 3 to 5 are longitudinal cross-sectional views of the construction sequence, Figures 6a to 6c are explanatory diagrams of the order of connecting floor slabs, and Figure 7
Figures a to 7f are explanatory diagrams of the order of connecting work for other floor slabs, Figure 8 is a perspective view of the jack, and Figures 9 to 11 are partially cutaway plan views showing the order of tension work by the jack. Fig. 12 is a plan view of another jack, Fig. 13 is a side view thereof, Fig. 14 is a partially cutaway plan view of another jack, Fig. 15 is a side view thereof, and Fig. 16 is a side view of another jack. FIG. 1... Floor slab, 2... PC steel material insertion hole, 3... Existing floor slab, 4... Temporary railing, 5... Auxiliary girder, 6...
PC steel material, 7... Connector, 8... Jacket, 9...
... Fixing tool, 10 ... recess.
Claims (1)
に貫通したPC鋼材挿通孔を有する方形パネル状
の床版を、既設の床版を撤去した位置に複数枚載
置して各床版のPC鋼材挿通孔にPC鋼材を挿通、
緊張して仮連結し、該床版に連続して床版を設置
する際にPC鋼材の緊張を一旦解除して、連結具
により既設のPC鋼材に新たにPC鋼材を連結して
新たな床版に挿通し、再び緊張して全体を一体化
させることを特徴とする床版の敷設工法。1 A plurality of rectangular panel-shaped floor slabs with prestressed steel insertion holes penetrating in the direction of road travel with openings at both ends on two parallel sides are placed in the position where the existing floor slabs have been removed, and the PC of each slab is installed. Insert the PC steel material into the steel material insertion hole,
Temporarily connect the prestressed steel materials under tension, and when installing the slabs consecutively to the slab, the tension in the prestressed steel materials is temporarily released, and a new prestressed steel material is connected to the existing prestressed steel materials using a connecting tool to create a new floor. A method of laying floor slabs, which is characterized by inserting the slab and tensioning it again to unify the whole.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP60017603A JPS61176705A (en) | 1985-01-31 | 1985-01-31 | Laying of floor panel |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP60017603A JPS61176705A (en) | 1985-01-31 | 1985-01-31 | Laying of floor panel |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS61176705A JPS61176705A (en) | 1986-08-08 |
| JPH0359203B2 true JPH0359203B2 (en) | 1991-09-09 |
Family
ID=11948454
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP60017603A Granted JPS61176705A (en) | 1985-01-31 | 1985-01-31 | Laying of floor panel |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS61176705A (en) |
Families Citing this family (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP6799998B2 (en) * | 2016-11-07 | 2020-12-16 | 三井住友建設株式会社 | Repair method of floor slab and intermediate fixing tool |
| JP6808585B2 (en) * | 2017-07-05 | 2021-01-06 | 鹿島建設株式会社 | Construction method of concrete floor slab |
| JP7656478B2 (en) * | 2021-04-19 | 2025-04-03 | オリエンタル白石株式会社 | How to replace precast PC floor slabs |
| JP7656477B2 (en) * | 2021-04-19 | 2025-04-03 | オリエンタル白石株式会社 | Tensioning method for precast PC members |
| JP7656476B2 (en) * | 2021-04-19 | 2025-04-03 | オリエンタル白石株式会社 | Precast PC floor slab joining method |
| JP7833978B2 (en) * | 2022-06-24 | 2026-03-23 | 三井住友建設株式会社 | Method for erecting corrugated steel web bridges |
-
1985
- 1985-01-31 JP JP60017603A patent/JPS61176705A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS61176705A (en) | 1986-08-08 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US5594977A (en) | Smooth rod-gripping apparatus | |
| WO2011159049A2 (en) | Rebar coupler using an oblong rotating wedge | |
| US4900193A (en) | Concrete structural member splicing device | |
| JPH0359203B2 (en) | ||
| JP7217673B2 (en) | Concrete floor slab, method for forming concrete floor slab, and method for repairing concrete floor slab | |
| US4605340A (en) | Pile splice | |
| JPH0782709A (en) | Reinforcement method for concrete structure using hollow PC steel rod | |
| CN216712586U (en) | Rail cementing insulation joint clamping plate detacher | |
| JP2907740B2 (en) | Bevel prestressed box culvert and method of introducing prestress into bevel box culvert | |
| JP2005090124A (en) | Connecting structure for precast floor slab | |
| JP2913461B2 (en) | Concrete member connection structure | |
| JP2001349001A (en) | PC steel wire connector | |
| JP2916453B1 (en) | Member connection device | |
| JP2698907B2 (en) | Foundation structure for building | |
| JPH09221915A (en) | Prestress introducing unit | |
| JPH06322722A (en) | Delivery construction method of stressed-ribbon bridge and pc floor slab unit used therefor | |
| JPS6366966B2 (en) | ||
| JP2000320023A (en) | Connection structure of concrete product | |
| JPH082164Y2 (en) | Bridge slab repair structure | |
| JP7246292B2 (en) | Concrete floor slab and method for forming concrete floor slab | |
| JPH0439906Y2 (en) | ||
| JPH0649675Y2 (en) | Tunnel lining structure | |
| JP3075557B2 (en) | Concrete block connection method | |
| JPS603187Y2 (en) | Fastening device for blocks for waterway construction | |
| JPH0555643B2 (en) |