JPH0410549B2 - - Google Patents
Info
- Publication number
- JPH0410549B2 JPH0410549B2 JP18819984A JP18819984A JPH0410549B2 JP H0410549 B2 JPH0410549 B2 JP H0410549B2 JP 18819984 A JP18819984 A JP 18819984A JP 18819984 A JP18819984 A JP 18819984A JP H0410549 B2 JPH0410549 B2 JP H0410549B2
- Authority
- JP
- Japan
- Prior art keywords
- support
- supports
- work
- scaffolds
- tie
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 239000000463 material Substances 0.000 claims description 25
- 238000010276 construction Methods 0.000 claims description 13
- 238000000034 method Methods 0.000 claims description 13
- 238000009415 formwork Methods 0.000 description 6
- 230000002787 reinforcement Effects 0.000 description 4
- 238000010586 diagram Methods 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 1
- 238000011900 installation process Methods 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Description
【発明の詳細な説明】
(産業上の利用分野)
本発明は、床板の型枠工事における施工法に関
する。DETAILED DESCRIPTION OF THE INVENTION (Industrial Application Field) The present invention relates to a construction method for forming floorboard formwork.
(従来の技術)
床板の施工工程は、型枠施工工程と配筋工程と
コンクリート打込工程とに大別できるが、従来よ
り型枠施工工程においては、床板下の作業空間を
広く取ることが課題であつた。そこで従来の施工
法を第6図に基づいて説明すると、支柱枠Kを組
立てた後、支柱枠の左右両側にかつ縦列方向に足
場15a…を2列毎に連続して配置して足場帯1
5を形成し、ついで足場帯の各足場の上端にパイ
プサポート16…を立設し、サポート上で床板
K1を受けると共に足場帯15,15間のパイプ
サポート間にはり17を架設し、はり上で床枠板
K1を受けるものである。足場帯15,15間の
空間が作業通路R1(点描図示部分)となる。また
他の従来例を第7図に基づいて説明する。まず支
柱枠Kの左右両側に足場18を対向して設置し、
各足場の縦列方向の足場間にわく組支柱を組立て
たステージ19を設設し、ステージの両側と足場
との間は作業通路R2となり得る空間をあけ、そ
して隣り合う足場の間、ステージの間に作業通路
となりうるだけの空間をあけてステージ20を設
置し、各ステージと足場18上に立設したサポー
トで床枠板K1を受ける。(Prior art) The floorboard construction process can be roughly divided into formwork construction process, reinforcing reinforcement process, and concrete pouring process. Conventionally, in the formwork construction process, it has been difficult to secure a wide working space under the floorboards. It was a challenge. Therefore, the conventional construction method will be explained based on FIG. 6. After assembling the support frame K, scaffolds 15a are successively arranged in every two rows on both the left and right sides of the support frame in the vertical direction.
5, then pipe supports 16 are erected at the upper end of each scaffold of the scaffold belt, and the floorboards are installed on the supports.
A beam 17 is installed between the pipe supports between the scaffolding strips 15 and 15 to receive K 1 , and the floor frame board is installed on the beam.
It is subject to K1 . The space between the scaffolding strips 15, 15 becomes a working path R 1 (portion shown in the dotted drawing). Another conventional example will be explained based on FIG. 7. First, scaffolds 18 are installed facing each other on both the left and right sides of the support frame K.
A stage 19 with frame supports assembled between each scaffold in the vertical direction is installed, a space is left between both sides of the stage and the scaffold, which can be used as a working path R 2 , and between the adjacent scaffolds, Stages 20 are installed with a space that can be used as a work passage between them, and the floor frame board K 1 is supported by supports erected on each stage and the scaffold 18.
(発明が解決しようとする問題点)
前者の施工法によると、床板下の作業空間も1
スパン内の床面積に占める割合が約56%であつて
空間効率の点で改善の余地があり、さらに作業通
路も相互に連らなることがなくそれぞれ独立して
おり、しかも第6図矢印方向に示すように2方向
に限られ、作業範囲が狭くなる課題があり、さら
に足場やパイプサポートの数量が多くなり、これ
が組立・解体の作業能率に影響を与えている。ま
た後者の施工法によると、各通路は第7図矢印に
示すように四方向に連らなりそれだけ作業範囲が
広くなるから作業がしやすくなるが、作業通路は
狭く、長物の材料の運搬には特に不便であり、作
業空間は52%と前者よりも小さくなつており、支
保工構成部材も多い。したがつていずれの施工法
においても、床板下の作業空間を広く取る点、支
保工構成部材を少なくする点で、なお改善すべき
課題がある。(Problem to be solved by the invention) According to the former construction method, the work space under the floorboards is
The ratio of the floor area within the span is approximately 56%, so there is room for improvement in terms of space efficiency.Furthermore, the work passages are not connected to each other but are independent, and moreover, they are located in the direction of the arrow in Figure 6. As shown in Figure 2, there is a problem that the work area is narrow because it is limited to two directions, and the number of scaffolds and pipe supports increases, which affects the efficiency of assembly and disassembly work. According to the latter construction method, the passages are connected in four directions as shown by the arrows in Figure 7, making the work easier as the work area becomes wider, but the work passages are narrow and difficult to transport long materials. The former is particularly inconvenient, as the work space is 52% smaller than the former, and there are more shoring components. Therefore, in either construction method, there are still issues to be improved in terms of increasing the working space under the floorboards and reducing the number of supporting components.
(問題点を解決するための手段)
本発明の施工法は、まず各柱の施工位置の両側
に足場2,2aをそれぞれ対向的に設置するもの
である。ついで足場2,2aの対向方向と直交す
る縦列方向において隣り合う足場の外側部間をつ
なぎ材3で連結する。この連結により、対となる
1組のつなぎ材3,3間には第1の作業通路Rが
形成される。連結作業の際、第1作業通路Rと交
差する第2の作業通路Raを確保するために、第
2作業通路に設定した部分に直交しかつ通行の妨
げとなる位置にくるつなぎ材は取り除いておく。
つなぎ材3による連結作業後に、つなぎ材に沿つ
てサポート5を所定間隔を置いて立設し、そして
各サポートを上記つなぎ材に連結すると共にこの
つなぎ材と直交する方向に隣り合うサポート間を
つなぎ材4でつなぐ。その後、上記縦列方向に並
んでいるサポート5上端に、上記作業通路R、
Raを利用して持ち込んだチヤンネル、I形鋼等
の大引材8を持ち上げて架設する。そして大引材
8間及び第1作業通路Rを挟んで位置する大引材
間に水平支保梁12を渡し、この梁上で床枠板
Kaを受けるのである。サポート5を立設する際、
サポートのうち第2作業通路Ra上に位置するサ
ポート5aは当初は設置することなく、スラブコ
ンクリートCを打設する前に立設して、打設前に
おける第2作業通路を確保しておく。(Means for Solving the Problems) In the construction method of the present invention, scaffolds 2 and 2a are first installed facing each other on both sides of the construction position of each pillar. Next, the outer parts of adjacent scaffolds in the column direction perpendicular to the direction in which the scaffolds 2 and 2a face each other are connected by a connecting material 3. Due to this connection, a first working path R is formed between the pair of connecting members 3, 3. During the connection work, in order to secure a second working path Ra that intersects with the first working path R, remove the connecting material that is perpendicular to the part set as the second working path and that is in a position that obstructs traffic. put.
After the connection work using the tie material 3, supports 5 are erected at predetermined intervals along the tie material, and each support is connected to the tie material, and adjacent supports in the direction perpendicular to the tie material are connected. Connect with material 4. Thereafter, the working path R,
Using Ra, lift the large lumber 8 such as channels and I-beams brought in and construct the structure. Then, a horizontal support beam 12 is passed between the large tension members 8 and between the large tension members located across the first working path R, and the floor frame board is placed on this beam.
We receive Ka. When setting up support 5,
Among the supports, the support 5a located on the second working path Ra is not initially installed, but is erected before pouring the slab concrete C to secure the second working path before pouring.
(実施例)
以下本発明の一実施例を図面に基づいて説明す
る。(Example) An example of the present invention will be described below based on the drawings.
まず、第1A図に示すように柱筋1を施工した
後に、柱筋の左右両側に対向的に足場2,2aを
組み、左右の対向方向と直交する方向すなわち縦
列方向の足場2と2、2aと2aの外側部間の上
下をつなぎ材である単管3でつなぐ。これによ
り、対となる1組の単管と隣り合う1組の単管と
の間に第1作業通路R(図面中、点描で示す部分)
が形成される。つなぎ作業に際して、第1作業通
路Rと直交する第2作業通路Ra(第1B図)を確
保するために、第2作業通路に当たる部分であつ
て通行の妨げとなる範囲内の下段の単管は取り除
いておく。 First, as shown in Fig. 1A, after constructing the column reinforcement 1, scaffolds 2 and 2a are set up oppositely on both the left and right sides of the column reinforcement. The upper and lower parts of the outer parts of 2a and 2a are connected with a single pipe 3, which is a connecting material. As a result, the first working passage R (portion shown in stippling in the drawing) is created between a pair of single pipes and an adjacent set of single pipes.
is formed. During the joint work, in order to secure a second working passage Ra (Fig. 1B) that is perpendicular to the first working passage R, the lower single pipe in the area that corresponds to the second working passage and is an obstruction to traffic is Remove it.
ついで、第1B図に示すように柱筋1の外周に
柱型枠Kを組み立てた後、各単管3,3の外側に
かつこの単管に沿つてサポート5を2400mmのピツ
チで左右のサポートが対となるように配置し、各
サポートを上下2段の単管3,3につなぎ、そし
て対となる左右のサポート間もその上下2個所を
つなぎ材である単管4…で連結する。サポート5
を立設する際、サポートのうち第2作業通路Ra
上に位置することゝなるサポート5aは、所定の
設置位置に立設することなく、この設置位置に最
も近い両側のサポートのいずれか一方のサポート
の近傍に立設しておき、通行の障害とならないよ
うにしておく。 Next, as shown in Figure 1B, after assembling the column formwork K around the outer periphery of the column reinforcement 1, supports 5 are installed on the outside of each single pipe 3 and along this single pipe at a pitch of 2400 mm on the left and right sides. are arranged in pairs, and each support is connected to the upper and lower two stages of single pipes 3, 3, and the pairs of left and right supports are also connected at their upper and lower two places with single pipes 4, which are connecting materials. support 5
When erecting the 2nd work passageway Ra of the support
The support 5a located above is not placed upright at a predetermined installation position, but is placed upright near one of the supports on both sides closest to this installation position, so as not to obstruct traffic. Make sure it doesn't happen.
各サポート5…は、第2,3図に示すように角
サポートであつて、上下両端にジヤツキホルダー
51,51aが取り付けてあり、下端部にサポー
トの高さ調整をするためのジヤツキ52が取り付
けてある。ジヤツキ52はハンドル53により動
作可能である。また第4図に示すようにサポート
5の上下2個所にホルダ6を介してクランプ7が
取り付けてあり、このクランプで足場2,2aを
つなぐ単管3を把持し、これにより各サポートは
立設状態が固定されている。単管3へのサポート
5の連結方法の他の例として、第5図に示すよう
にサポート5の上下2個所にボルト6を貫通させ
て、ボルト先端に取り付けたクランプ7aで単管
3を把持する方法もあるが、この方法を採用して
もよい。 Each support 5... is a corner support as shown in FIGS. 2 and 3, and has jack holders 51, 51a attached to both upper and lower ends, and a jack 52 for adjusting the height of the support at the lower end. It is installed. The jack 52 is operable by a handle 53. Furthermore, as shown in Fig. 4, clamps 7 are attached to the upper and lower parts of the support 5 via holders 6, and these clamps grip the single pipe 3 that connects the scaffolds 2 and 2a, thereby allowing each support to stand upright. The state is fixed. As another example of the method of connecting the support 5 to the single pipe 3, as shown in FIG. There is also a method to do this, but this method may also be used.
クランプ7aはナツト6bの締付けでサポート
5に固定される。 Clamp 7a is fixed to support 5 by tightening nut 6b.
左右方向の対となるサポートも同様の方法(ク
ランプ7又は7a)によつて単管4を介して相互
に連結している。 The left and right pairs of supports are also connected to each other via the single tube 4 by the same method (clamps 7 or 7a).
そして第1c図に示すようにサポート5を設置
固定した後、足場2と2、2aと2aとの間に足
場板P、Pを敷き込み、クレーン車Aを用いて作
業通路R,Ra上を所定位置まで移動させ、クレ
ーンAaによつてチヤンネル8を揚重し、縦列方
向に沿つて並ぶサポート5上にセツトする。 After installing and fixing the support 5 as shown in Fig. 1c, scaffold boards P and P are laid between the scaffolds 2 and 2 and 2a and 2a, and the crane truck A is used to move over the work paths R and Ra. The channel 8 is moved to a predetermined position, lifted by a crane Aa, and set on the supports 5 lined up along the column direction.
セツト方法について説明すると、第2,3図に
示すようにサポート5の上方に位置するジヤツキ
ホルダ51の一側部に、予め振止めアングルピー
ス9を載せてクランプ10のボルトを締付けて固
定しておいてから、チヤンネル8の下側フランジ
をジヤツキホルダ上の他側部に載せて、クランプ
10aでフランジをホルダ上に仮止めし、そして
チヤンネルの背面下部をアングルピースの垂直部
にボルト11で連結固定する。 To explain the setting method, as shown in Figs. 2 and 3, the steady angle piece 9 is placed on one side of the jack holder 51 located above the support 5, and the bolt of the clamp 10 is tightened to fix it. After that, place the lower flange of the channel 8 on the other side of the jack holder, temporarily fix the flange on the holder with the clamp 10a, and connect and fix the lower back of the channel to the vertical part of the angle piece with the bolt 11. .
その後、第1D図に示すように揚重車A1を利
用して通路R,Ra上を適宜位置まで移動させて
から、水平支保梁12を足場板Pの上方まで持ち
上げ、通路Rを挟んで隣り合うサポート5のチヤ
ンネル8,8間に架設する。梁12の支持方法
は、第2,3図に示すようにチヤンネル8の上部
フランジに予め取り付けてある溝形の支持枠81
内に梁の両端をセツトするものである。同様にし
て、対となるサポート5上のチヤンネル8,8間
にも梁12を架設する。 Thereafter, as shown in Fig. 1D, the lifting vehicle A1 is used to move the horizontal support beam 12 onto the aisles R and Ra to an appropriate position, and then lift the horizontal support beam 12 to the top of the scaffolding board P. It is constructed between channels 8, 8 of adjacent supports 5. The beam 12 is supported by a groove-shaped support frame 81 that is attached in advance to the upper flange of the channel 8, as shown in FIGS.
Both ends of the beam are set inside. Similarly, a beam 12 is also constructed between the channels 8 and 8 on the paired supports 5.
梁12を設置した後、第1E図に示すように梁
上に床枠板Kaを敷設する。そして第2作業通路
Ra上に設置すべきサポート5aを所定の位置に
戻す。 After installing the beam 12, the floor frame board Ka is laid on the beam as shown in FIG. 1E. And the second working passage
Return the support 5a to be installed on Ra to the predetermined position.
そして第1F図に示すように垂直ブレース13
及び上部つなぎ材14を入れてから、床枠板Ka
上にスラブコンクリートCを打設して、床板を施
工する。 and vertical brace 13 as shown in FIG. 1F.
After inserting the top connecting material 14, the floor frame board Ka
Place slab concrete C on top and construct the floorboards.
養生後は、再び第2作業通路Raを確保するた
めにサポート5aを取り除いておいてから、解体
作業に入る。作業中は、型枠運搬は作業車を使つ
て、通路R,Ra上を走行させる。 After curing, the support 5a is removed in order to secure the second working path Ra again, and then the dismantling work begins. During work, a work vehicle will be used to transport the formwork and will be driven along aisles R and Ra.
組立や解体時に作業車を使うか否かは床板の耐
力に左右され、その選択は任意である。施工する
にあたり、図示するように大引材にチヤンネル、
水平支保梁にトラス梁、サポートに角パイプ、つ
なぎ材として単管を用いれば支保工構成部材の重
量を軽量化することができる。因みに第1従来例
の重量を1とすると、第2従来例が約1.15である
のに対して上例では約0.78であつた。そして構成
部材数でも、従来例の約1/2ですんだ。さらに1
スパンの床面積に対する作業空間(通行可能床面
積)の比率も、上述した如く第1の従来例が56
%、第2従来例が52%であるのに対し、上例では
75%と高くなつた。さらに足場板を設置でき幅広
い足場板を敷設できるから作業が安全に行える。 Whether or not to use a work vehicle during assembly or disassembly depends on the strength of the floorboards, and the choice is arbitrary. When constructing, channel the main material as shown in the diagram.
The weight of the shoring components can be reduced by using truss beams for the horizontal support beams, square pipes for the supports, and single pipes for the connecting materials. Incidentally, assuming that the weight of the first conventional example is 1, the weight of the second conventional example is approximately 1.15, while that of the above example is approximately 0.78. The number of component parts is also approximately 1/2 that of the conventional model. 1 more
As mentioned above, the ratio of the working space (passable floor area) to the floor area of the span is 56 in the first conventional example.
%, while the second conventional example is 52%, the above example has
It rose to 75%. Furthermore, the work can be done safely because scaffolding boards can be installed and a wide range of scaffolding boards can be laid down.
また上例では、作業通路は第1作業通路Rと第
2作業通路Raとが交差する十字形に設定したが、
通路の設計計画によつては搬入口から目的地点ま
での過程で、例えば第2作業通路の一方を閉鎖し
たT字形になることがある。 Furthermore, in the above example, the working passage was set in the shape of a cross where the first working passage R and the second working passage Ra intersected.
Depending on the design plan of the passageway, the second work passageway may be shaped like a T, with one side closed, for example, in the process from the delivery entrance to the destination point.
(発明の効果)
以上説明したように本発明によれば、作業通路
を任意の方向に設定でき、作業空間を従来例に比
較して広く取ることができるから、組立、解体作
業が能率的かつ効率的に行え、型枠材の場内運搬
が容易となり、作業の安全性を確保でき、そして
支保工構成部材の数量を少なくできそれだけ作業
を迅速に行え、したがつて特に階高の高い建物、
フラツトスラブ等の現場作業時の荷重の大きい建
物に有効である。(Effects of the Invention) As explained above, according to the present invention, the work path can be set in any direction and the work space can be made wider than in the conventional example, making assembly and disassembly work efficient and efficient. It can be carried out efficiently, the formwork material can be easily transported within the site, work safety can be ensured, and the number of shoring components can be reduced, allowing the work to be carried out quickly.
Effective for buildings that are subject to heavy loads during on-site work, such as flat slab construction.
第1図乃至第1F図は施工工程を段階的に示す
図、第2図はチヤンネルの取付け状態を示す断面
図、第3図はチヤンネルの取付け状態を示す側面
図、第4図は縦列方向の単管を把持するクランプ
の取付け状態を示す斜視図、第5図は縦列方向の
単管を把持するクランプの他の実施例の取付け状
態を示す断面図、第6図及び第7図はそれぞれ従
来例の支保工の配置状態を示す説明図である。
2,2a……足場、3,4……つなぎ材、5,
5a……サポート、8……大引材、12……水平
支保梁、C……スラブコンクリート、R……第1
作業通路、Ra……第2作業通路。
Figures 1 to 1F are diagrams showing the construction process step by step, Figure 2 is a sectional view showing how the channels are installed, Figure 3 is a side view showing how the channels are installed, and Figure 4 is a vertical view of the installation process. FIG. 5 is a sectional view showing the mounting state of another embodiment of the clamp that grips single pipes in the column direction; FIGS. 6 and 7 are respectively conventional It is an explanatory view showing the arrangement state of the shoring of an example. 2, 2a...Scaffolding, 3,4...Tie material, 5,
5a...Support, 8...Large lumber, 12...Horizontal support beam, C...Slab concrete, R...1st
Work passage, Ra...Second work passage.
Claims (1)
対向的に配置し、 ついで足場の対向方向と直交する縦列方向にお
いて隣り合う足場外側部をつなぎ材で連結し、対
となる1組のつなぎ材と隣接するつなぎ材との間
に第1作業通路を形成し、このつなぎ材のうち、
第1作業通路に連らなる第2作業通路に設定した
部分に直交しかつ通行の妨げとなる位置にくるつ
なぎ材は取り除いておき、 つなぎ材によるつなぎ作業後、このつなぎ材に
沿つてサポートを所定間隔を置いて立設し、そし
て各サポートを上記つなぎ材に連結すると共にこ
のつなぎ材と直交する方向に隣り合うサポート間
をつなぎ材でつなぎ、 そして上記縦列方向に並ぶサポート上端に大引
材を架設し、 架設後、サポート間及び第1作業通路を挟んで
対向位置する大引材間に水平支保梁を渡して、こ
の梁上で床枠板を受けるものであつて、 上記サポートを立設する際、サポートのうち第
2作業通路上に位置するサポートは当初は設置す
ることなく、スラブコンクリート打設前に所定位
置に立設するものであることを特徴とする床板の
施工法。[Scope of Claims] 1. First, scaffolds are placed facing each other on both sides of the construction position of each pillar, and then the outer parts of the scaffolds that are adjacent in the column direction perpendicular to the facing direction of the scaffolds are connected with a connecting material, and the pairs are connected. A first working passage is formed between one set of binding materials and an adjacent binding material, and among these binding materials,
Remove the tie material that is perpendicular to the part set for the second work route that connects to the first work route and that is in a position that obstructs traffic.After the tie work with the tie material is completed, support should be placed along this tie material. Each support is erected at a predetermined interval, and each support is connected to the above-mentioned connecting material, and adjacent supports are connected in a direction perpendicular to this connecting material with a connecting material. After erection, a horizontal support beam is passed between the supports and between large timbers located opposite to each other across the first working passage, and the floor frame board is received on this beam, and the above support is erected. A method for constructing floorboards, characterized in that, when installing, among the supports, the supports located on the second working path are not initially installed, but are erected at predetermined positions before slab concrete is poured.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP18819984A JPS6168975A (en) | 1984-09-10 | 1984-09-10 | Construction of floor panel |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP18819984A JPS6168975A (en) | 1984-09-10 | 1984-09-10 | Construction of floor panel |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS6168975A JPS6168975A (en) | 1986-04-09 |
| JPH0410549B2 true JPH0410549B2 (en) | 1992-02-25 |
Family
ID=16219503
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP18819984A Granted JPS6168975A (en) | 1984-09-10 | 1984-09-10 | Construction of floor panel |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS6168975A (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP3746595B2 (en) * | 1997-07-07 | 2006-02-15 | 三井住友建設株式会社 | Floor construction method for freezer / refrigerated warehouse |
-
1984
- 1984-09-10 JP JP18819984A patent/JPS6168975A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS6168975A (en) | 1986-04-09 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP3569861B2 (en) | Construction method of stairs and staircase, staircase support device, and staircase structure | |
| US20050066609A1 (en) | Preassembled roof and floor deck panel system | |
| CA1151892A (en) | Prefabricated load bearing structure | |
| JPH0410549B2 (en) | ||
| KR102437398B1 (en) | Easy-to-install integrated slab euroform system | |
| JP7605601B2 (en) | Beam construction method and beam formwork support structure | |
| KR102289243B1 (en) | Underground Parking Lot Construction Method Using Pre-assembled bar column, U-shaped beam, Corrugated deck | |
| JPH0536042Y2 (en) | ||
| JPH07279418A (en) | Temporary structure | |
| JPH06341167A (en) | Working method for concrete structure | |
| JPH0681463A (en) | Building method for stair | |
| KR102910984B1 (en) | Construction method of doorway type cast-in-place beam support of civil building frame structure | |
| JP2611882B2 (en) | Construction method of stairs | |
| JP2817591B2 (en) | Construction method of steel reinforced concrete building | |
| RU2087650C1 (en) | House-building combine | |
| JP3944870B2 (en) | Method for constructing staircase with staircase and unit staircase used in this construction method | |
| JP3847029B2 (en) | Box-type building | |
| JPS6114302B2 (en) | ||
| JP2026003966A (en) | Steel frame construction method | |
| KR20260031837A (en) | High wall safety formwork system and its construction method | |
| JPS634146A (en) | Slab execution method | |
| JPH0528248Y2 (en) | ||
| JP3078198B2 (en) | Unit building with balconies | |
| CN118979624A (en) | A ribbed floor forming structure capable of being installed efficiently and a construction method thereof | |
| JPS61158537A (en) | Building of iron skeletal |