JPH0415850B2 - - Google Patents
Info
- Publication number
- JPH0415850B2 JPH0415850B2 JP59033940A JP3394084A JPH0415850B2 JP H0415850 B2 JPH0415850 B2 JP H0415850B2 JP 59033940 A JP59033940 A JP 59033940A JP 3394084 A JP3394084 A JP 3394084A JP H0415850 B2 JPH0415850 B2 JP H0415850B2
- Authority
- JP
- Japan
- Prior art keywords
- drill body
- drill
- deviation
- current converter
- excavation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/13—Foundation slots or slits; Implements for making these slots or slits
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Description
【発明の詳細な説明】
この発明は、地下連続壁の掘削工事に用いられ
る掘削装置に関する。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to an excavator used for excavating an underground continuous wall.
近年、多くの土木工事、特に止水壁や、地下鉄
等の地下構造物の建造工事には地下連続壁工法、
すなわち、地中にある長さの溝を掘削し、ここに
鉄筋かごを建て込んだ後にコンクリートを打設し
て鉄筋コンクリート壁を施工する工事法が採用さ
れている。 In recent years, many civil engineering works, especially water-stop walls and construction of underground structures such as subways, are using the underground continuous wall construction method.
In other words, a construction method is used in which a long trench is excavated underground, a reinforcing cage is erected there, and then concrete is poured to construct a reinforced concrete wall.
ところで、上述した工事法における掘削作業に
おいては、掘削機の運転にかなりの熟練を必要と
し、ごく限られたオペレータが経験や勘を頼りに
運転を行なつているのが現状である。したがつ
て、人手不足からオペレータは高齢化して来てお
り、また、一方では経験や勘を頼りに運転を行な
つているために掘削溝の施工結果に個人差が生じ
るという問題がある。 Incidentally, in the excavation work according to the above-mentioned construction method, considerable skill is required to operate the excavator, and the current situation is that only a limited number of operators operate the excavator relying on their experience and intuition. Therefore, due to the lack of manpower, operators are getting older, and on the other hand, operators rely on experience and intuition, which causes individual differences in the results of excavated trench construction.
この発明は上記事情に鑑み、熟練したオペレー
タのみならず誰にでも容易に運転でき、しかも、
充分な掘削精度を確保することができる掘削装置
を提供するもので、掘削状況を検知する複数の検
知手段を有し、昇降装置により昇降可能に懸吊さ
れたドリル本体によつて掘削を行なうと共に、前
記ドリル本体に装備された偏位修正手段によつて
掘削偏位の修正を行なう掘削装置において、前記
検知手段は少なくとも、前記ドリル本体の深度を
検知する深度計、前記ドリル本体の鉛直方向に対
する傾きを検知する傾斜計、前記ドリル本体の備
えるドリルの電流値を検知するドリル電流変換
器、掘削孔より泥水を排出するポンプの電流値を
検知するポンプ電流変換器、および、掘削孔から
の排泥水量を検知する流量計を有して成り、さら
に、目標値の設定に用いられる設定手段と、前記
ドリル本体の昇降速度の制御を行なう速度コント
ローラと、前記偏位修正手段の制御を行なう偏位
コントローラと、少なくとも前記ドリル電流変換
器および前記ポンプ電流変換器による計測値と、
前記設定手段により設定された目標値とを比較
し、この比較結果に基づいて前記速度コントロー
ラを駆動制御すると共に、前記深度計および前記
傾斜計による計測値と、前記設定手段により設定
された目標値とを比較し、この比較結果に基づい
て前記偏位コントローラを駆動制御する制御手段
とを具備したことを特徴とする。 In view of the above circumstances, this invention can be easily operated not only by experienced operators but also by anyone.
The present invention provides a drilling equipment that can ensure sufficient drilling accuracy, has a plurality of detection means for detecting the drilling status, and excavates with a drill body that is suspended so that it can be raised and lowered by a lifting device. , in the drilling equipment in which the excavation deviation is corrected by a deviation correction means installed in the drill body, the detection means includes at least a depth gauge for detecting the depth of the drill body; An inclinometer that detects the inclination, a drill current converter that detects the current value of the drill provided in the drill body, a pump current converter that detects the current value of the pump that discharges muddy water from the drilling hole, and It has a flowmeter for detecting the amount of muddy water, and further includes a setting means used for setting a target value, a speed controller for controlling the lifting speed of the drill body, and a biasing device for controlling the deflection correcting means. a controller, and measured values from at least the drill current converter and the pump current converter;
The target value set by the setting means is compared, and the speed controller is driven and controlled based on the comparison result, and the measured values by the depth meter and the inclinometer are compared with the target value set by the setting means. The present invention is characterized by comprising a control means for comparing the values and driving and controlling the deflection controller based on the comparison result.
以下、図面を参照し、この発明の一実施例につ
いて説明する。 Hereinafter, one embodiment of the present invention will be described with reference to the drawings.
第1図は、この発明の一実施例による掘削装置
における掘削機の構成を示す正面図であり、図に
おいて1は車輪2によつてレール上を走行する専
用やぐらである。この専用やぐら1の下部支持台
1a上には油圧モータによつて駆動されるウイン
チ3が固定されており、このウインチ3によつ
て、吊ワイヤーロープ4を巻上げ、もしくは巻下
げることにより、吊ワイヤーロープ4に懸吊され
たドリル本体5の昇降が行なわれる。この場合、
吊ワイヤーロープ4は専用やぐら1の上部支持台
1b上の滑車6を通過して垂直下方に伸び、そし
て、ドリル本体5の上部に位置する動滑車7にお
いて折り返した後に、上部支持台1bまで上昇
し、上部支持台1b上の滑車8を通過して再度下
向きに伸びた後、その端部が下部支持台1a上に
固定された張力計9に取付けられている。そし
て、この張力計9によつて、吊ワイヤーロープ4
の張力、すなわち吊ワイヤーロープ4に懸吊され
たドリル本体5の荷重が計測される。また、1
0,11は二方向傾斜計(以下単に傾斜計と称
す)であり、上部支持台1b上の両端部に各々取
付けられている。これら傾斜計10,11の各々
には測定用ワイヤ12,13が、取付けられてお
り、これら2本の測定用ワイヤ12,13がドリ
ル本体5の両側部に取付けられた一対の滑車1
4,15と、専用やぐら1の上部支持台1b上に
取付けられた一対の滑車16,17と、下部支持
台1a上に取付けられた一対の巻取りローラ1
8,19とによつて対称に張設されている。そし
て、ドリル本体5が紙面に垂直な方向(以下Y方
向という)および紙面の左右方向(以下X方向と
いう)に偏位した場合に、測定用ワイヤ12,1
3が傾斜し、これに伴い傾斜計10,11が傾斜
する。そして、この傾斜計10,11の傾斜に基
づいて、測定用ワイヤ12,13の各々のX方向
およびY方向の傾斜角度が計測される。また専用
やぐら1の上部支持台1bには、一方の測定用ワ
イヤ13の移動によつて作動する深度計20が取
付けられており、この深度計20によつてドリル
本体5の掘削距離が計測される。なお、深度計2
0としては例えばロータリエンコーダが用いられ
る。 FIG. 1 is a front view showing the configuration of an excavator in an excavator according to an embodiment of the present invention, and in the figure, reference numeral 1 denotes a dedicated tower that runs on rails with wheels 2. A winch 3 driven by a hydraulic motor is fixed on the lower support base 1a of this exclusive tower 1, and by winding up or lowering the hanging wire rope 4, the winch 3 The drill body 5 suspended from the rope 4 is raised and lowered. in this case,
The hanging wire rope 4 passes through a pulley 6 on the upper support stand 1b of the special tower 1 and extends vertically downward, and after turning back at the movable pulley 7 located at the upper part of the drill body 5, rises to the upper support stand 1b. After passing through the pulley 8 on the upper support stand 1b and extending downward again, its end is attached to a tension gauge 9 fixed on the lower support stand 1a. Then, using this tension meter 9, the hanging wire rope 4
The tension, that is, the load of the drill body 5 suspended on the hanging wire rope 4 is measured. Also, 1
0 and 11 are two-way inclinometers (hereinafter simply referred to as inclinometers), which are respectively attached to both ends of the upper support base 1b. Measuring wires 12 and 13 are attached to each of these inclinometers 10 and 11, and these two measuring wires 12 and 13 connect to a pair of pulleys 1 attached to both sides of the drill body 5.
4, 15, a pair of pulleys 16, 17 mounted on the upper support stand 1b of the dedicated tower 1, and a pair of winding rollers 1 mounted on the lower support stand 1a.
8 and 19 symmetrically. When the drill body 5 is displaced in the direction perpendicular to the plane of the paper (hereinafter referred to as the Y direction) and in the left-right direction of the plane of the paper (hereinafter referred to as the X direction), the measurement wires 12, 1
3 is tilted, and the inclinometers 10 and 11 are accordingly tilted. Then, based on the inclinations of the inclinometers 10 and 11, the inclination angles of the measurement wires 12 and 13 in the X direction and the Y direction are measured. Furthermore, a depth gauge 20 that is activated by the movement of one measuring wire 13 is attached to the upper support stand 1b of the dedicated tower 1, and the excavation distance of the drill body 5 is measured by this depth gauge 20. Ru. In addition, depth meter 2
For example, a rotary encoder is used as the zero.
一方、ドリル本体5において21,21…は、
回転することにより地盤を掘削するドリルビツト
であり、ドリル本体5の内部に取付けられた水中
モータ(図示せず)によつて回転駆動される。ま
た22,22…は偏位修正板であり、ドリル本体
5の前面および後面に各々4枚ずつ、計8枚が取
付けられている。この偏位修正板22,22…
は、ドリル本体5の内部に取付けられた油圧ポン
プ(図示せず)により駆動されて、ドリル本体5
の前面および後面から垂直に突出するようになつ
ている。この場合、8枚の偏位修正板22,22
…は各々、別個に駆動することが可能である。ま
た、ドリル本体5の底面の中央にはリバース吸込
み口(図示せず)が開口しており、このリバース
吸込み口は、ドリル本体5の中央を貫通し、専用
やぐら1に達する配管23、および配管23の上
端部に接続されたホース24を介して排水ポンプ
25の吸込み口と連通している。そして、この排
水ポンプ25により、掘削孔上部から、掘削時に
おいて常時給水される水を、掘削した土砂と共
に、リバース吸込み口から吸上げ、配管23とホ
ース24とを介して地上に排出するようになつて
いる。この場合、配管23はドリル本体5の掘削
深度に応じて、自在に継ぎ足すことが可能であ
る。また、26は流量計であり、この流量計26
によつて排水ポンプ25により排水される泥水の
流量が計測される。 On the other hand, in the drill body 5, 21, 21...
This is a drill bit that excavates the ground by rotating, and is rotationally driven by an underwater motor (not shown) installed inside the drill body 5. Further, 22, 22, . . . are deviation correction plates, and a total of eight plates, four plates each, are attached to the front and rear surfaces of the drill body 5. These deviation correction plates 22, 22...
is driven by a hydraulic pump (not shown) installed inside the drill body 5.
It is designed to protrude vertically from the front and rear surfaces of the In this case, eight deviation correction plates 22, 22
... can be driven separately. Further, a reverse suction port (not shown) is opened at the center of the bottom of the drill body 5, and this reverse suction port is connected to a pipe 23 that passes through the center of the drill body 5 and reaches the dedicated tower 1, and a pipe. It communicates with the suction port of a drainage pump 25 via a hose 24 connected to the upper end of the drain pump 23 . The drainage pump 25 sucks up the water that is constantly supplied during excavation from the upper part of the excavation hole together with the excavated soil from the reverse suction port and discharges it to the ground via the piping 23 and hose 24. It's summery. In this case, the piping 23 can be freely added according to the excavation depth of the drill body 5. Further, 26 is a flowmeter, and this flowmeter 26
The flow rate of muddy water drained by the drain pump 25 is measured.
次に、第2図を用いて、第1図に示す掘削機を
コントロールする制御部の構成について説明す
る。 Next, the configuration of a control section that controls the excavator shown in FIG. 1 will be explained using FIG. 2.
第2図において、20,10,11,26,9
は、各々第1図に示す深時計、傾斜計、流量計、
張力計である。30はドリル本体5に取付けられ
た水中モータの電流値(ドリル電流値)の計測を
行なうドリル電流変換器であり、31は排水ポン
プ25の駆動に用いられるモータの電流値(ポン
プ電流値)の計測を行なうポンプ電流変換器であ
る。また、32は複数のポテンシヨメータよりな
るパラメータ設定器である。そして、これら深度
計20、傾斜計10,11、ドリル電流変換器3
0、流量計26、ポンプ電流変換器31、および
張力計9による各計測値、並びにパラメータ設定
器32によつて設定された値は、インターフエイ
スユニツト(以下I/Fと称す)34によつて
A/D(アナログ/デイジタル)変換された後に、
コンピユータ33に入力される。また、35はウ
インチの巻上げ/巻下げの速度制御を行なう速度
コントローラであり、手動によつて、あるいはコ
ンピユータ33よりI/F34を介して出力され
る制御信号によつて駆動される。36は掘削時に
おいて各偏位修正板22,22…の突出、もしく
は引き込みの制御を行う偏位コントローラであ
り、速度コントローラ35と同様に、手動によつ
て、あるいはコンピユータ33よりI/F34を
介して出力される制御信号によつて駆動される。
また、37は、モード選択スイツチであり、オペ
レータが、このモード選択スイツチ37を操作す
ることによつて、掘削装置の動作における4つの
モードのうちの1つが、任意に選択できるように
なつている。ここで、掘削装置の動作における4
つのモードと、各モードにおける処理内容は次の
通りである。 In Figure 2, 20, 10, 11, 26, 9
are a depth clock, an inclinometer, a flow meter, respectively shown in Fig. 1,
It is a tension meter. 30 is a drill current converter that measures the current value of the underwater motor (drill current value) attached to the drill body 5, and 31 is a drill current converter that measures the current value of the motor used to drive the drainage pump 25 (pump current value). This is a pump current converter that performs measurements. Further, 32 is a parameter setting device consisting of a plurality of potentiometers. These depth gauges 20, inclinometers 10 and 11, and drill current converter 3
0, the measured values by the flowmeter 26, the pump current converter 31, and the tension meter 9, as well as the values set by the parameter setting device 32, are processed by the interface unit (hereinafter referred to as I/F) 34. After A/D (analog/digital) conversion,
It is input to the computer 33. A speed controller 35 controls the speed of hoisting/lowering the winch, and is driven manually or by a control signal outputted from the computer 33 via the I/F 34. 36 is a deviation controller that controls the protrusion or retraction of each deviation correction plate 22, 22, etc. during excavation, and like the speed controller 35, it can be controlled manually or from the computer 33 via I/F 34. It is driven by a control signal output from the
Further, 37 is a mode selection switch, and by operating this mode selection switch 37, the operator can arbitrarily select one of four modes of operation of the drilling equipment. . Here, 4 in the operation of the drilling rig
The two modes and the processing contents in each mode are as follows.
モード0:手動運転
偏位量算出
表示・記録処理
モード1:偏位量算出
表示・記録処理
ウインチ巻下げ速度制御
自動緊急処理
自動定深度処理
モード2:偏位量算出
表示・記録処理
偏位修正制御
自動緊急処理
自動定深度処理
モード3:偏位量算出
表示・記録処理
ウインチ巻下げ速度制御
偏位修正制御
自動緊急処理
自動定深度処理
そして、速度コントローラ35、偏位コントロ
ーラ36、モード切換スイツチ37および、コン
ピユータ33の指示により鳴動するブザー(図示
せず)によつて操作卓が構成される。また、この
操作卓の近傍には排水ポンプ駆動用モータ、水中
モータ等の始動もしくは停止を行なう手動スイツ
チが設けられている。Mode 0: Manual operation Deflection amount calculation display/recording processing Mode 1: Deflection amount calculation display/recording processing Winch lowering speed control Automatic emergency processing Automatic constant depth processing Mode 2: Deflection amount calculation display/recording processing Deviation correction Control automatic emergency processing automatic constant depth processing mode 3: deviation amount calculation display/record processing winch lowering speed control deviation correction control automatic emergency processing automatic constant depth processing And speed controller 35, deviation controller 36, mode changeover switch 37 A console is constituted by a buzzer (not shown) that sounds in response to an instruction from the computer 33. Further, a manual switch for starting or stopping the drain pump driving motor, submersible motor, etc. is provided near the console.
次に、38はキーボードであり、コンピユータ
33に対する指示の入力、あるいは掘削作業前に
おける各種目標値の設定に用いられる。また39
はフロツピーデイスク、40はCRT(ブラウン管
表示装置)、41はプリンタである。 Next, 38 is a keyboard, which is used to input instructions to the computer 33 or to set various target values before excavation work. Also 39
is a floppy disk, 40 is a CRT (cathode ray tube display), and 41 is a printer.
以上の構成を有する掘削装置の動作について説
明する。まず、オペレータはキーボード38を用
いて各種目標値の設定を行う。この場合設定され
る目標値には、目標深度、X方向およびY方向の
偏位許容範囲等、予め工事仕様により決定されて
いるものの他、ポンプ電流値、ドリル電流値等の
ように過去のデータ、もしくは地盤の調査結果か
ら決定されるものがある。また、オペレータは、
パラメータ設定器32によつて、排水流量の最低
限界値等の設定を行う。次に、全ての項目につい
て設定が終了したならば、オペレータは操作卓の
近傍に設けられたスイツチを操作して、給水を開
始すると共に、排水ポンプ駆動用モータおよび水
中モータを始動させる。次に、モード選択スイツ
チ37によつて動作モードを選択する。いま、例
えばモード3が選択されたとすると、このスイツ
チ情報がI/F34を介してコンピユータ33に
入力される。コンピユータ33は、入力されたス
イツチ情報に基づいてモード3が選択されたこと
を検知し、速度コントローラ35に対し、ウイン
チ3の巻下げ指示を出力する。これにより、ドリ
ル本体5が降下を始め、ドリルビツト21,21
…が地盤に達すると、ドリル本体5の自重によ
り、掘削が開始される。以後、コンピユータ33
にはI/F34を介して深度計20、傾斜計1
0,11、ドリル電流変換器30等の各検知手段
の検知結果が入力される。そして、コンピユータ
33は、入力された各検知結果に基づいて次の各
処理を行う。 The operation of the excavation rig having the above configuration will be explained. First, the operator uses the keyboard 38 to set various target values. In this case, the target values set include those determined in advance according to the construction specifications, such as the target depth and allowable deviation range in the X and Y directions, as well as past data such as pump current values and drill current values. Alternatively, it may be determined based on the results of a ground survey. In addition, the operator
The parameter setter 32 is used to set the minimum limit value of the drainage flow rate, etc. Next, when the settings for all items are completed, the operator operates a switch provided near the console to start water supply and also start the drain pump drive motor and submersible motor. Next, the mode selection switch 37 selects an operation mode. For example, if mode 3 is selected, this switch information is input to the computer 33 via the I/F 34. The computer 33 detects that mode 3 has been selected based on the input switch information, and outputs an instruction to lower the winch 3 to the speed controller 35. As a result, the drill body 5 begins to descend, and the drill bits 21, 21
When the drill body 5 reaches the ground, excavation is started due to the weight of the drill body 5. From then on, computer 33
Depth meter 20, inclinometer 1 via I/F 34
The detection results of each detection means such as 0, 11, drill current converter 30, etc. are input. Then, the computer 33 performs the following processes based on each input detection result.
(1) 偏位量算出
例えば第3図に示すように測定用ワイヤ1
2,13がY方向に角度θだけ傾斜した場合を
仮定する。lRおよびh1を大、各々深度計20に
よつて計測された掘削距離、および地表から傾
斜計10,11までの高さとすると、掘削深度
h2は、
h2=lRCOSθ ……(1)
また、Y方向の偏位量lyは、
ly=Htanθ=(h1+lRCOSθ)tanθ ……(2)
となる。(1) Calculation of deviation amount For example, as shown in Figure 3, measurement wire 1
2 and 13 are tilted by an angle θ in the Y direction. l If R and h 1 are large, the excavation distance measured by the depth gauge 20, and the height from the ground surface to the inclinometers 10 and 11, then the excavation depth is
h 2 is expressed as: h 2 =l R COSθ (1) Also, the amount of deviation in the Y direction, ly , is as follows: ly = Htanθ = (h 1 +l R COSθ) tanθ (2).
しかして、コンピユータ33は、深度計20
および傾斜計10,11による計測値と、上記
(1)、(2)式とによりドリル本体5の掘削深度、X
方向の偏位量、およびY方向の偏位量を算出す
る。 Therefore, the computer 33
and the measured values by the inclinometers 10 and 11, and the above
Based on equations (1) and (2), the drilling depth of the drill body 5,
The amount of deviation in the direction and the amount of deviation in the Y direction are calculated.
ところで、ドリル本体5の傾斜角度θは、地
上部に設置した専用やぐら1に取り付けた傾斜
計10,11により、計測ワイヤ12,13を
介して計測される。傾斜計10,11をこのよ
うな構成とすることにより下記の如き利点があ
る。この傾斜計10,11はドリル本体5の傾
斜状態を検出するのみならず、掘削進路の正否
をも直接に指標するものとなるのである。すな
わち、傾斜計10,11はドリル本体5とは別
に地上部に設置してあるので、例えドリル本体
5が鉛直方向を向いている場合でもその掘削進
路が所定の進路からずれていればワイヤ12,
13は傾き、ドリル本体5が正規掘削ラインよ
り偏位していることが直接的に検知されるので
ある。このことはすなわち、上記傾斜計10,
11によるときには、ドリル本体5を単に該傾
斜計10,11が傾斜しないように方向を制御
するのみで、ドリル本体5を正規状態に制御す
ることができ、複雑な換算計算を必要とせず、
誤差の少ない確実な方向制御を簡単に行なえる
ことを意味する。 Incidentally, the inclination angle θ of the drill body 5 is measured via measurement wires 12 and 13 by inclinometers 10 and 11 attached to a dedicated tower 1 installed above ground. By configuring the inclinometers 10 and 11 in this manner, there are the following advantages. The inclinometers 10 and 11 not only detect the inclination state of the drill body 5, but also directly indicate whether the excavation course is correct or not. That is, since the inclinometers 10 and 11 are installed on the ground separately from the drill body 5, even if the drill body 5 is oriented vertically, if the excavation path deviates from the predetermined path, the wire 12 ,
13 is tilted, and it is directly detected that the drill body 5 is deviated from the normal drilling line. This means that the inclinometer 10,
11, the drill body 5 can be controlled to a normal state by simply controlling the direction of the drill body 5 so that the inclinometers 10 and 11 do not tilt, and no complicated conversion calculation is required.
This means that reliable direction control with few errors can be easily performed.
(2) 表示・記録処理
コンピユータ33は、I/F34を介して入
力される各検知手段の検知結果、並びに前述し
た式(1)、(2)により算出されたドリル本体5の掘
削深度、およびX方向・Y方向の偏位量の変化
の状態を逐次CRT40に数値表示すると共に、
これら検知結果等に予めキーボード38によつ
て設定された一定深度毎に、プリンタ41より
印字出力する。また、コンピユータ33は、
CRT40に表示される前記検知結果等を、一
定時間毎にフロツピイーデイスク39に記録す
る。そして、このフロツピーデイスク39に記
録されたデータは、掘削工事の詳細なデータを
記録したものとして保管されると共に、今後、
類似した工事を行う場合の参考資料となる。(2) Display/record processing The computer 33 receives the detection results of each detection means input via the I/F 34, the excavation depth of the drill body 5 calculated by the above-mentioned formulas (1) and (2), and The status of changes in the amount of deviation in the X and Y directions is displayed numerically on the CRT 40, and
These detection results and the like are printed out from the printer 41 at each constant depth set in advance using the keyboard 38. Further, the computer 33
The detection results displayed on the CRT 40 are recorded on the floppy disk 39 at regular intervals. The data recorded on this floppy disk 39 will be stored as a record of detailed data of the excavation work, and will be used in the future.
This will serve as reference material when carrying out similar construction work.
(3) ウインチ巻下げ速度制御
コンピユータ33は、予めキーボード38に
より設定された、ドリル電流およびポンプ電流
の目標値と、ドリル電流変換器30およびポン
プ電流変換器31による計測値とを比較し、こ
の比較結果に基づいてウインチ3の巻下げ速度
の制御を行う。すなわち、ドリル電流変換器3
0による計測値が、予め設定された目標値より
大きい場合であれば、予測した以上の負荷がド
リルビツト21,21…に作用していることに
なる。したがつて、この場合、コンピユータ3
3は速度コントローラ35に対して、巻下げ速
度の低下指示を出力する。これにより、ウイン
チ3の巻下げ速度が低下し、ドリルビツト2
1,21…に作用する負荷が軽減される。逆
に、ドリル電流変換器30による計測値が、目
標値より小さい場合であれば、コンピユータ3
3は運転効率を上げるために速度コントローラ
35に対して、巻下げ速度の増加指示を出力す
る。これにより、ウインチ3の巻下げ速度が増
加する。(3) Winch lowering speed control The computer 33 compares the target values of the drill current and pump current set in advance using the keyboard 38 with the measured values by the drill current converter 30 and the pump current converter 31. The lowering speed of the winch 3 is controlled based on the comparison result. That is, drill current converter 3
If the measured value of 0 is larger than the preset target value, it means that a load greater than predicted is acting on the drill bits 21, 21, . . . . Therefore, in this case, computer 3
3 outputs an instruction to the speed controller 35 to lower the lowering speed. As a result, the lowering speed of the winch 3 decreases, and the drill bit 2
The load acting on 1, 21, . . . is reduced. Conversely, if the measured value by the drill current converter 30 is smaller than the target value, the computer 3
3 outputs an instruction to increase the lowering speed to the speed controller 35 in order to increase operating efficiency. This increases the lowering speed of the winch 3.
一方、ポンプ電流変換器31により計測値
が、予め設定された目標値より大きい場合であ
れば、掘削土砂の量が排水ポンプ25の処理能
力を上回つていることになり、排水ポンプ25
が閉塞を起こす虞れがある。したがつて、この
場合コンピユータ33は速度コントローラ35
に対して、巻上げ速度の低下指示を出力する。
これにより、ウインチ3の巻下げ速度が低下
し、掘削土砂の量が減少する。逆に、ポンプ電
流変換器31による計測値が目標値より小さい
場合であれば、運転効率を上げるために、コン
ピユータ33は速度コントローラ35に対し
て、巻下げ速度の増加指示を出力する。 On the other hand, if the value measured by the pump current converter 31 is larger than the preset target value, it means that the amount of excavated soil exceeds the processing capacity of the drainage pump 25, and the drainage pump 25
may cause blockage. Therefore, in this case, the computer 33 controls the speed controller 35.
outputs an instruction to reduce the hoisting speed.
As a result, the lowering speed of the winch 3 is reduced, and the amount of excavated earth and sand is reduced. Conversely, if the measured value by the pump current converter 31 is smaller than the target value, the computer 33 outputs an instruction to increase the lowering speed to the speed controller 35 in order to increase operating efficiency.
以上述べたようにして、ウインチ3の巻下げ
速度の制御が行なわれる。ところで、地盤によ
つてはドリル電流変換器30による計測値に基
づく判断と、ポンプ電流変換器31による計測
値に基づく判断に矛盾を生じる場合がある。例
えば、ドリルビツト21,21…に作用してい
る負荷が高いにもかかわらず、排水量が多い場
合、すなわちドリル本体5が非常に硬い地盤に
達した場合には、ドリル電流変換器30による
計測値と、その目標値との比較結果によればウ
インチ3の巻下げ速度を低下させなければなら
ないが、ポンプ電流変換器31による計測値
と、その目標値との比較結果によればウインチ
3の巻下げ速度を増加させなければならない。
また、ドリルビツト21,21…が極端に軟い
地盤に達した場合においても、前述した判断に
矛盾を生じる場合がある。すなわち、掘削土砂
が多く、一方ドリルビツト21,21…に作用
する負荷が軽い場合である。コンピユータ33
は、上述したような判断の矛盾が生じた場合に
は、ドリルビツト21,21…が極端に摩耗し
たりモーターの焼損を招かないように、また、
排水ポンプ25が閉塞を起こさないように、予
めキーボード38より設定された目標値を、掘
削状況に合わせて最適な目標値に変更する。 As described above, the lowering speed of the winch 3 is controlled. However, depending on the ground, there may be a conflict between the judgment based on the measured value by the drill current converter 30 and the judgment based on the measured value by the pump current converter 31. For example, if the load acting on the drill bits 21, 21, . According to the comparison result with the target value, the lowering speed of the winch 3 must be reduced; Speed must be increased.
Further, even if the drill bits 21, 21, . . . reach extremely soft ground, there may be a contradiction in the above-mentioned judgment. That is, there is a large amount of excavated earth and sand, but the load acting on the drill bits 21, 21, . . . is light. computer 33
In the event of a discrepancy in judgment as described above, the drill bits 21, 21, etc. should be checked to prevent excessive wear and damage to the motor.
In order to prevent the drainage pump 25 from clogging, the target value set in advance from the keyboard 38 is changed to an optimal target value according to the excavation situation.
(4) 偏位修正制御
ドリル本体5のY方向の偏位が検出された場
合、コンピユータ33は、偏位した側の偏位修
正板22,22…を突出させるように、偏位コ
ントローラ36に対し制御指示を出力する。こ
れにより、指示された偏位修正板22,22…
が突出し、これら突出した偏位修正板22,2
2…が掘削壁を強く押圧することにより、ドリ
ル本体5の掘削方向が変更される。(4) Deflection correction control When a deviation of the drill body 5 in the Y direction is detected, the computer 33 controls the deviation controller 36 to project the deviation correction plates 22, 22, etc. on the side where the deviation occurred. Outputs control instructions. As a result, the instructed deviation correction plates 22, 22...
protrudes, and these protruding deviation correction plates 22, 2
2 strongly presses the excavation wall, thereby changing the excavation direction of the drill body 5.
なお、ドリル本体5は、X方向の偏位に対し
て、偏位修正手段を有していない。したがつ
て、X方向の偏位に対しては、偏位の修正を行
なうことができないが、連続壁の施工において
X方向の偏位は、それが顕著でない限り問題と
なることはない。 Note that the drill body 5 does not have a deviation correcting means for deviation in the X direction. Therefore, deviations in the X direction cannot be corrected, but deviations in the X direction do not pose a problem in the construction of continuous walls unless they are significant.
(5) 自動緊急処理
この処理は、排水ポンプ25が閉塞を起こし
た場合、すなわち、流量計25による計測値
が、パラメータ設定器32に設定されている排
水量の最低限界値以下になつた場合、およびド
リル本体5のX方向およびY方向の各々の偏位
量が、予めキーボード38より設定されたX方
向およびY方向の偏位許容範囲を超えた場合に
おける、コンピユータ33の処理である。この
場合、コンピユータ33は、まず、ウインチ3
の巻下げ停止指示を速度コントローラ35に対
し出力すると共に、偏位コントローラ36に対
し、全ての偏位修正板21,21…の引き込み
指示を出力する。これにより、ドリル本体5の
降下が停止すると共に、突出している偏位修正
板21が引き込まれる。次いで、コンピユータ
33は、速度コントローラ35に対し、ウイン
チ3の巻上げ指示を出力する。これにより、ド
リル本体5が上昇を始める。そして、コンピユ
ータ33は、予めキーボード38より設定され
た距離だけドリル本体5が上昇したならば、そ
の時点で速度コントローラ35に対し、ウイン
チ3の巻上げ停止指示を出力する。そして、ド
リル本体5が停止した後、予めキーボード38
により設定された一定時間経過後に、流量計2
6により計測計、もしくはドリル本体5の偏位
量が運転可能な状態に復帰しているか否かを検
出する。すなわち、コンピユータ33は、ドリ
ル本体5が上昇したことによつて、流量計26
による計測値がパラメータ設定器32に設定さ
れている排水量の最低限界値以上になつたか否
か、もしくは、ドリル本体5のX方向およびY
方向の偏位が、予め設定された偏位許容範囲内
に収まつたか否かを検出し、これらの条件が満
たされている場合には、速度コントローラ35
に対し、ウインチ3の巻下げ指示を出力する。
これにより、ドリル本体5が停止している位置
から、再度、掘削が開始される。しかしなが
ら、前述した条件が満たされていない場合に
は、コンピユータ33は、操作卓上のブザーを
鳴動させた後、動作モードをモード0に切換え
る。これにより、速度コントローラ35および
偏位コントローラ36はその後手動運転される
ことになる。(5) Automatic emergency processing This processing is performed when the drainage pump 25 becomes clogged, that is, when the measured value by the flowmeter 25 falls below the minimum limit value of the drainage volume set in the parameter setting device 32. This is a process performed by the computer 33 when the amount of deviation of the drill body 5 in the X direction and the Y direction exceeds the allowable deviation range in the X direction and the Y direction set in advance from the keyboard 38. In this case, the computer 33 first
A lowering stop instruction is output to the speed controller 35, and an instruction to pull in all the deflection correction plates 21, 21, . . . is output to the deflection controller 36. As a result, the descent of the drill body 5 is stopped, and the protruding deviation correction plate 21 is retracted. Next, the computer 33 outputs an instruction to hoist the winch 3 to the speed controller 35. As a result, the drill body 5 begins to rise. Then, when the drill body 5 rises by a distance preset from the keyboard 38, the computer 33 outputs an instruction to the speed controller 35 to stop hoisting the winch 3 at that point. After the drill body 5 has stopped, the keyboard 38 is
After a certain period of time set by
6, it is detected whether the measuring meter or the amount of deviation of the drill body 5 has returned to the operable state. That is, the computer 33 detects that the flowmeter 26 is
whether the measured value exceeds the minimum limit value of the displacement set in the parameter setting device 32, or whether the measured value by
It is detected whether the deviation in the direction falls within a preset allowable deviation range, and if these conditions are met, the speed controller 35
In response, an instruction to lower the winch 3 is output.
As a result, excavation is started again from the position where the drill body 5 is stopped. However, if the above-mentioned conditions are not met, the computer 33 switches the operation mode to mode 0 after sounding the buzzer on the console. As a result, the speed controller 35 and the deflection controller 36 are then manually operated.
(6) 自動定深度処理
この処理は、ドリル本体が、配管23の継ぎ
足しを必要とする深度に達した場合、もしくは
ドリル本体5が、予めキーボード38によつて
設定された最終目標深度に達した場合におけ
る、コンピユータ33の処理である。この場合
コンピユータ33は、まず、速度コントローラ
35に対して、ウインチ3の巻下げ停止指示を
出力すると共に、偏位コントローラ36に対
し、全ての偏位修正板21,21…の引き込み
指示を出力する。これにより、ドリル本体5の
降下が停止すると共に、突出している偏位修正
板21が引き込まれる。次いで、コンピユータ
33は操作卓上のブザーを鳴動させた後に、動
作モードをモード0に切換える。その後、掘削
機の停止を確認したオペレータは、操作卓の近
傍に設けられたスイツチを操作して、排水ポン
プの駆動用モータおよび水中モータを停止させ
た後に、掘削機が最終目標深度に達したのであ
れば、速度コントローラ35の手動操作して、
ウインチ3を巻上げる。また、配管23の継ぎ
足し深度に達したのであれば、配管23の継ぎ
足し作業を行う。そして配管23の継ぎ足し作
業が終了したならば、オペレータは、排水ポン
プの駆動用モータおよび水中モータを始動させ
た後に、モード選択スイツチを操作して、モー
ド3を選択する。以下、掘削が続行される。(6) Automatic fixed depth processing This processing is performed when the drill body reaches a depth that requires the addition of piping 23, or when the drill body 5 reaches the final target depth set in advance using the keyboard 38. This is the processing of the computer 33 in this case. In this case, the computer 33 first outputs an instruction to the speed controller 35 to stop lowering the winch 3, and also outputs an instruction to the deviation controller 36 to pull in all the deviation correction plates 21, 21... . As a result, the descent of the drill body 5 is stopped, and the protruding deviation correction plate 21 is retracted. Next, the computer 33 switches the operation mode to mode 0 after sounding the buzzer on the operation desk. After confirming that the excavator has stopped, the operator operates a switch located near the control console to stop the drainage pump drive motor and submersible motor, and then confirms that the excavator has reached the final target depth. If so, manually operate the speed controller 35,
Hoist winch 3. Further, if the depth for adding the pipe 23 has been reached, the work for adding the pipe 23 is performed. When the work of adding the pipe 23 is completed, the operator starts the drive motor of the drainage pump and the submersible motor, and then operates the mode selection switch to select mode 3. Excavation continues below.
以上が、コンピユータ33が行う各処理の動作
内容である。 The above is the operation content of each process performed by the computer 33.
ところで、地盤によつては、そこが以前に全く
掘削経験のない場所であり、かつ、地盤につい
て、事前に充分な調査等を行なうことができない
場合がある。このような場合には、掘削前に、キ
ーボード38より必要な目標値(例えば、ドリル
電流値)等の全てを設定できないので、モード3
によつて運転することは不可能となる。したがつ
て、このような場合においては、熟練したオペレ
ータによる試し掘りが行なわれる。試し掘りは、
オペレータが自らの判断により、設定することが
できない目標値に応じて、モード0〜モード2を
選択することによつて開始される。そして、オプ
レータは、CRT40に表示された、各検知結果
等に基づいて速度コントローラ35、もしくは偏
位コントローラ36、もしくはこれらコントロー
ラ双方の操作を行い、掘削を行う。そして、オペ
レータが、掘削機の動作が安定したと思われる時
点、すなわち、オペレータがドリル本体5の偏位
量を、予め設定された偏位許容範囲内に収めるこ
とができる最適な掘削速度が得られたと判断した
時点で、オペレータは、モード選択スイツチ37
を操作して、モード3を選択する。モード選択ス
イツチ37が操作されると、スイツチ情報がI/
F34を介してコンピユータ33に入力される。
コンピユータ33は、入力されたスイツチ情報に
基づいてモード3が選択されたことを検知する
と、未設定の目標値について、例えば、ドリル電
流の目標値が、未設定であつたとすると、モード
選択スイツチ37が操作された時点における、ド
リル電流変換器30による計測値を、本来ならば
予めキーボード38により設定される目標値とす
る。これにより、以後、モード3によつて掘削を
続行することが可能となる。なお、この場合、オ
ペレータが最適な掘削速度を得ることができたと
判断した時点で、モード3の選択を行なつたが、
最適な掘削速度が得られなくても、オペレータ
が、最適な掘削速度を把握できたならば、一度掘
削機を停止させた後に、キーボード38より新た
めて、未設定の目標値を設定してもよい。 By the way, depending on the ground, there may be cases where there is no previous experience of excavation, and it may not be possible to conduct a sufficient investigation of the ground in advance. In such a case, it is not possible to set all necessary target values (for example, drill current value) using the keyboard 38 before drilling, so mode 3 is selected.
This makes it impossible to drive. Therefore, in such cases, trial digging is performed by a skilled operator. Trial digging is
The process is started when the operator selects Mode 0 to Mode 2 according to a target value that cannot be set based on his/her own judgment. Then, the operator operates the speed controller 35, the deflection controller 36, or both of these controllers based on the detection results displayed on the CRT 40 to perform excavation. Then, the operator determines the optimum excavation speed at which the operation of the excavator seems to be stable, that is, the optimum excavation speed at which the operator can keep the amount of deviation of the drill body 5 within the preset allowable deviation range. When the operator determines that the mode selection switch 37
Operate to select mode 3. When the mode selection switch 37 is operated, the switch information is
It is input to the computer 33 via F34.
When the computer 33 detects that mode 3 has been selected based on the input switch information, the computer 33 selects the mode selection switch 37 for an unset target value, for example, if the target value of the drill current has not been set. The value measured by the drill current converter 30 at the time when is operated is set as the target value that would normally be set in advance using the keyboard 38. This makes it possible to continue excavation in mode 3 from now on. In this case, mode 3 was selected when the operator determined that the optimum excavation speed could be obtained.
Even if the optimum excavation speed cannot be obtained, if the operator can grasp the optimum excavation speed, once the excavator has stopped, the operator can set the unset target value again using the keyboard 38. Good too.
以上説明したようにこの発明によれば、掘削機
を、掘削状況の変化に応じて自動的に制御するこ
とができ、したがつて、熟練したオペレータのみ
ならず誰にでも容易に運転できると共に、オペレ
ータの負担を軽減させることができる。また、こ
の発明によれば、高い掘削精度を確保することが
できる効果が得られる。例えば、深度100mまで
掘削して1/1000以上の精度を確保することが可能
となる。また特に、制御手段は、速度コントロー
ラを駆動制御するにあたり、少なくともドリル電
流およびポンプ電流の双方の計測値を比較データ
として制御するものであるから、排水ポンプの閉
塞やドリル用のモーターの焼損等を防止つつ、掘
削地盤の状況に応じて最適な掘削を効率的に実施
することができる、といつた優れた効果を奏す
る。 As explained above, according to the present invention, the excavator can be automatically controlled according to changes in excavation conditions, and therefore can be easily operated by not only skilled operators but also anyone. The burden on the operator can be reduced. Further, according to the present invention, it is possible to obtain the effect of ensuring high excavation accuracy. For example, it will be possible to excavate to a depth of 100m and ensure accuracy of 1/1000 or more. In particular, since the control means uses at least the measured values of both the drill current and the pump current as comparison data when driving and controlling the speed controller, it is possible to prevent blockage of the drainage pump, burnout of the drill motor, etc. This has excellent effects such as being able to efficiently carry out optimal excavation depending on the excavated ground conditions while preventing the excavation.
さらに、特許請求の範囲第2項に記載した構成
とすれば、傾斜計がドリル本体の掘削進路の正否
を直接に指標するものとなるので、この傾斜計が
傾斜しないようにドリル本体の方向を制御するの
みでドリル本体を正規状態に制御することがで
き、複雑な換算計算を排除し、誤差の少ない確実
な方向制御を簡単に行なえる、といつた利点があ
る。 Furthermore, with the configuration described in claim 2, the inclinometer directly indicates whether the drilling path of the drill body is correct or not. It has the advantage of being able to control the drill body to its normal state just by controlling it, eliminating complicated conversion calculations, and easily performing reliable direction control with few errors.
第1図は、この発明の一実施例による掘削装置
における掘削機の構成を示す正面図、第2図は、
第1図に示す掘削機を制御する制御部の構成を示
すブロツク図、第3図は、ドリル本体5の掘削深
度および偏位量を求める処理を説明するための説
明図である。
3……ウインチ(昇降装置)、9……張力計
(検知手段)、10,11……二方向傾斜計(検知
手段)、12,13……測定用ワイヤ(ワイヤ)、
20……深度計(検知手段)、22……偏位修正
板(偏位修正手段)、26……流量計(検知手
段)、30……ドリル電流変換器(検知手段)、3
1……ポンプ電流交換器(検知手段)、32……
パラメータ設定器(設定手段)、33……コンピ
ユータ(制御手段)、35……速度コントローラ、
36……偏位コントローラ。
FIG. 1 is a front view showing the configuration of an excavator in an excavator according to an embodiment of the present invention, and FIG.
A block diagram showing the configuration of a control section that controls the excavator shown in FIG. 1, and FIG. 3 are explanatory diagrams for explaining the process of determining the excavation depth and deviation amount of the drill body 5. 3...Winch (lifting device), 9...Tension meter (detection means), 10, 11...Two-way inclinometer (detection means), 12, 13...Measurement wire (wire),
20...depth meter (detection means), 22...deviation correction plate (deviation correction means), 26...flow meter (detection means), 30...drill current converter (detection means), 3
1... Pump current exchanger (detection means), 32...
Parameter setting device (setting means), 33... Computer (control means), 35... Speed controller,
36...Deflection controller.
Claims (1)
昇降装置により昇降可能に懸吊されたドリル本体
によつて掘削を行なうと共に、前記ドリル本体に
装備された偏位修正手段によつて掘削偏位の修正
を行なう掘削装置において、 前記検知手段は少なくとも、前記ドリル本体の
深度を検知する深度計、前記ドリル本体の鉛直方
向に対する傾きを検知する傾斜計、前記ドリル本
体の備えるドリルの電流値を検知するドリル電流
変換器、掘削孔より泥水を排出するポンプの電流
値を検知するポンプ電流変換器、および、掘削孔
からの排泥水量を検知する流量計を有して成り、
さらに、 (a) 目標値の設定に用いられる設定手段と、 (b) 前記ドリル本体の昇降速度の制御を行なう速
度コントローラと、 (c) 前記偏位修正手段の制御を行なう偏位コント
ローラと、 (d) 少なくとも前記ドリル電流変換器および前記
ポンプ電流変換器による計測値と、前記設定手
段により設定された目標値とを比較し、この結
果に基づいて前記速度コントローラを駆動制御
すると共に、前記深度計および前記傾斜計によ
る計測値と、前記設定手段により設定された目
標値とを比較し、この結果に基づいて前記偏位
コントローラを駆動制御する制御手段と、 を具備したことを特徴とする掘削装置。 2 前記傾斜計は地上部に設置されてワイヤを介
して前記ドリル本体と接続されており、ドリル本
体の傾きを前記ワイヤの傾きにより検知する構成
のものである特許請求の範囲第1項記載の掘削装
置。[Claims] 1. Having a plurality of detection means for detecting excavation conditions,
In a drilling device that performs drilling with a drill body suspended movably up and down by a lifting device, and corrects the excavation deviation by a deviation correction means installed in the drill body, the detection means includes at least one of the following: , a depth meter that detects the depth of the drill body, an inclinometer that detects the inclination of the drill body with respect to the vertical direction, a drill current converter that detects the current value of the drill provided in the drill body, and a drain current converter that discharges muddy water from the drill hole. It consists of a pump current converter that detects the current value of the pump, and a flowmeter that detects the amount of mud water discharged from the borehole,
Further, (a) a setting device used to set a target value, (b) a speed controller that controls the vertical speed of the drill body, and (c) a deviation controller that controls the deviation correction device. (d) Compare the measured values by at least the drill current converter and the pump current converter with the target value set by the setting means, drive and control the speed controller based on this result, and and control means for comparing the measured value by the inclination meter and the inclinometer with the target value set by the setting means, and driving and controlling the deflection controller based on the result. Device. 2. The inclinometer according to claim 1, wherein the inclinometer is installed on the ground and connected to the drill body via a wire, and the inclination of the drill body is detected by the inclination of the wire. drilling rig.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP3394084A JPS60181420A (en) | 1984-02-24 | 1984-02-24 | drilling rig |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP3394084A JPS60181420A (en) | 1984-02-24 | 1984-02-24 | drilling rig |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS60181420A JPS60181420A (en) | 1985-09-17 |
| JPH0415850B2 true JPH0415850B2 (en) | 1992-03-19 |
Family
ID=12400500
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP3394084A Granted JPS60181420A (en) | 1984-02-24 | 1984-02-24 | drilling rig |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS60181420A (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP5616244B2 (en) * | 2011-01-21 | 2014-10-29 | 西松建設株式会社 | Foundation judgment method by underground drilling data analysis |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS51148905A (en) * | 1975-06-16 | 1976-12-21 | Takenaka Komuten Co | Method of controlling excavation of ditch and hole for continuous wall and foundation pile |
| JPS58218518A (en) * | 1982-06-11 | 1983-12-19 | Mitsui Constr Co Ltd | Excavator for underground wall face |
-
1984
- 1984-02-24 JP JP3394084A patent/JPS60181420A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS60181420A (en) | 1985-09-17 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| EP0201503B1 (en) | Casting of structural walls | |
| CN114108624A (en) | Two-adjustment one-control type perpendicularity control construction method for one-column one-pile steel pipe column | |
| CN110528550A (en) | The hard soil layer in caisson cutting edge position is broken and slag cleaning device and its construction method | |
| CN112411530A (en) | A construction method for verticality control of casing occlusal piles in reclamation strata | |
| CN115387328B (en) | Beach cast-in-place pile construction method based on ultra-long spiral drilling machine | |
| USRE34576E (en) | Casting of structural walls | |
| CN114837213A (en) | Tower crane foundation structure and construction method thereof | |
| JP2717874B2 (en) | Open caisson construction method and device | |
| CN114508098A (en) | Pile foundation construction method | |
| JP4558456B2 (en) | Caisson structure | |
| CN110670585A (en) | Pile extension construction method | |
| JPH06108456A (en) | Position measuring device for excavator for underground wall construction method | |
| JPH0415850B2 (en) | ||
| CN114775586A (en) | A kind of foundation pit reverse method rotary excavation and bottom expansion, full rotation positioning construction method | |
| CN117107748B (en) | Hole forming construction method for mechanical dry operation of anchor piles in sandstone areas | |
| CN118704505A (en) | A large caisson sinking construction method without drainage | |
| JPH0565658B2 (en) | ||
| CN110984862A (en) | Hole guiding device for geological static pressure pile in rich thick sand layer and construction method | |
| JP2006124942A (en) | Excavating equipment for caisson | |
| JP6846812B2 (en) | How to excavate a direct foundation board of an underground structure | |
| JP4111690B2 (en) | Boom work vehicle | |
| CN112726565A (en) | Construction method for rotary digging pile penetrating through construction waste | |
| JP7830936B2 (en) | Excavator | |
| JPS63255488A (en) | drilling rig | |
| JP2640419B2 (en) | Pile head processing equipment |