Deprecated: The each() function is deprecated. This message will be suppressed on further calls in /home/zhenxiangba/zhenxiangba.com/public_html/phproxy-improved-master/index.php on line 456
JPH0417262B2 - - Google Patents
[go: Go Back, main page]

JPH0417262B2 - - Google Patents

Info

Publication number
JPH0417262B2
JPH0417262B2 JP14136685A JP14136685A JPH0417262B2 JP H0417262 B2 JPH0417262 B2 JP H0417262B2 JP 14136685 A JP14136685 A JP 14136685A JP 14136685 A JP14136685 A JP 14136685A JP H0417262 B2 JPH0417262 B2 JP H0417262B2
Authority
JP
Japan
Prior art keywords
floor
center core
column
frame
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP14136685A
Other languages
Japanese (ja)
Other versions
JPS621954A (en
Inventor
Shigeru Hari
Masataka Fukushima
Yasushi Adachi
Kiichi Ono
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP14136685A priority Critical patent/JPS621954A/en
Publication of JPS621954A publication Critical patent/JPS621954A/en
Publication of JPH0417262B2 publication Critical patent/JPH0417262B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Casings For Electric Apparatus (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は建物の架構床部分をコンクリートス
ラブとした建物の架構施工法に関するもので、特
に高層建物あるいは超高層建物の施工に適する。
[Detailed Description of the Invention] [Industrial Application Field] The present invention relates to a method of constructing a building frame in which the frame floor portion of the building is a concrete slab, and is particularly suitable for constructing a high-rise building or a super high-rise building.

〔従来の技術およびその問題点〕[Conventional technology and its problems]

高層建物、超高層建物等においても、従来の鉄
骨主体の架構に対し、複合柱やアンボンドブレス
トレストコンクリートスラブ(以下、アンボンド
PCスラブという)を用いて、経済的な断面を有
する建物が設計されてきている。
Even in high-rise buildings and super high-rise buildings, composite columns and unbonded breastless concrete slabs (hereinafter referred to as unbonded) are used instead of conventional steel-based frames.
Buildings with economical cross-sections have been designed using PC slabs (called PC slabs).

しかし、下階より順次構築して行く方法では床
コンクリート打設のための型枠の組立、解体、移
動等に手間がかかり、また多くの仮設資材を必要
とするほか、工数も多いので、作業待ちの時間が
長くなる。
However, with the method of building the floors one by one starting from the lower floors, it takes time to assemble, dismantle, and move the formwork for pouring floor concrete, requires a lot of temporary materials, and requires a lot of man-hours. Waiting time becomes longer.

また、低層の建物でフラツトスラブ構造とする
場合は地上で数階分のスラブを形成し、リフトア
ツプする工法も知られているが、高層建物に適用
するのは困難である。
Furthermore, when constructing a flat slab structure for a low-rise building, a construction method is known in which several floors of slabs are formed above the ground and lifted up, but this method is difficult to apply to high-rise buildings.

この発明は上述のような問題点の解決を目的と
したものである。
This invention aims to solve the above-mentioned problems.

〔問題点を解決するための手段〕[Means for solving problems]

この発明の工法は床架構5の施工を上階から順
次下階へ向けて行なうものであり、まずセンター
コア1の構築を先行させ、続いてセンターコア1
外部の柱鉄骨2を所定高さまで立上げて行く。
The construction method of this invention is to construct the floor frame 5 sequentially from the upper floor to the lower floor, first constructing the center core 1, then constructing the center core 1.
The external column steel frame 2 is raised to a predetermined height.

センターコア1はエレベーター室や機械室等を
集中させた部分で、スライデイングフオーム工法
あるいはジヤンピングフオーム工法などで壁部分
のコンクリート工事を行なうことができる。また
柱鉄骨2については施工中、仮設の水平ブレース
3でセンターコア1と連結するなどして立上げて
行く。
The center core 1 is a part where the elevator room, machine room, etc. are concentrated, and the concrete work of the wall part can be performed using the sliding form method or the jumping form method. Also, during construction, the column steel frame 2 will be connected to the center core 1 with a temporary horizontal brace 3 and then erected.

次に立上げた柱鉄骨2の上部に、センターコア
1を取囲むようにして仮設ステージ4を組立て
る。仮設ステージ4は鉄骨フレーム4aと鉄骨フ
レーム4a上に設けた型枠4b等で構成し、セン
ターコア1および柱鉄骨2に沿つてスライドでき
るようにする。
Next, a temporary stage 4 is assembled on top of the erected steel column 2 so as to surround the center core 1. The temporary stage 4 is composed of a steel frame 4a, a formwork 4b provided on the steel frame 4a, etc., and is made to be able to slide along the center core 1 and the column steel frame 2.

次に、仮設ステージ4上に必要な配筋工事等を
行なつた後、床コンクリートを打設し、順次仮設
ステージ4を1階ずつ下げて下階の床コンクリー
トを打設して行く。なお、仮設ステージ4上に形
成されるスラブはフラツトスラブに限らず、梁付
スラブ等の場合もある。
Next, after performing necessary reinforcing work on the temporary stage 4, floor concrete is poured, and the temporary stage 4 is lowered one floor at a time, and floor concrete for the lower floors is poured. Note that the slab formed on the temporary stage 4 is not limited to a flat slab, but may also be a beamed slab or the like.

以上により、センターコア1と柱鉄骨2および
床架構5とからなる架構が形成され、また柱を鉄
骨鉄筋コンクリート柱等の複合柱とする場合は、
続いて柱鉄骨2周囲の配筋およびコンクリート工
事を行なう。
As described above, a frame consisting of the center core 1, column steel frame 2, and floor frame 5 is formed, and when the column is a composite column such as a steel reinforced concrete column,
Next, reinforcement and concrete work will be carried out around the steel column 2.

また、建物の階数が多い場合は、以上の作業を
二以上の高さで分けて行ない、センターコア1の
先行構築、柱鉄骨2の立上げ、仮設ステージ4に
よる上階から下階へ向けての床架構5の形成とい
つた作業を繰り返すことになる。
In addition, if the building has many floors, the above work is divided into two or more heights, and the center core 1 is constructed in advance, the column steel frame 2 is erected, and the temporary stage 4 is used to move from the upper floor to the lower floor. The process of forming the floor frame 5 will be repeated.

〔実施例〕〔Example〕

次に、図示した実施例について説明する。 Next, the illustrated embodiment will be described.

第5図は施工時における架構の平面図、第6図
は柱および床部分の構造を示す断面斜視図で、セ
ンターコア1は壁部分をスライデイングフオーム
あるいはジヤンピングフオーム工法で構築し、そ
のまわりに鉄骨鉄筋コンクリート製の複合柱で支
持されるアンボンドPCスラブの床架構5を形成
している。
Figure 5 is a plan view of the frame during construction, and Figure 6 is a cross-sectional perspective view showing the structure of the columns and floor. A floor frame 5 of unbonded PC slabs supported by composite columns made of steel-framed reinforced concrete is formed.

床架構5は床スラブ5a部分と梁5b部分とか
らなり、格子状鉄筋による床鉄筋11、懸垂線状
のアンボンドPCストランド12および梁鉄筋1
3を配してある。また柱については柱鉄骨2の周
囲に上下方向の主筋およびせん断補強筋としてフ
ーブ筋、スパイラル筋等の柱鉄筋10を配し、コ
ンクリート7を打設してある。
The floor frame 5 consists of a floor slab 5a portion and a beam 5b portion, and includes floor reinforcing bars 11 made of grid-like reinforcing bars, unbonded PC strands 12 in the form of catenary lines, and beam reinforcing bars 1.
3 is placed. Regarding the columns, column reinforcing bars 10 such as houb bars and spiral bars are arranged around the column steel frame 2 as vertical main bars and shear reinforcements, and concrete 7 is placed.

第2図〜第4図は仮設ステージ4の一例を示し
たもので、H形鋼等の鉄骨により、鉄骨フレーム
4aを組み、その上に型枠4bを設けたものであ
る。柱鉄骨2への固定は第3図および第4図に示
すように、各階位置に取り付けた接合プレートへ
のボルト接合によつて行なうことができる。ま
た、仮設ステージ4の型枠4bには柱位置にコン
クリート打設用の穴8を形成してあり、柱鉄骨2
と鉄筋コンクリートを組合わせた複合柱を形成で
きるようになつている。
FIGS. 2 to 4 show an example of the temporary stage 4, in which a steel frame 4a is constructed of steel frames such as H-shaped steel, and a formwork 4b is provided on top of the steel frame 4a. As shown in FIGS. 3 and 4, fixing to the column steel frame 2 can be performed by bolting to connection plates attached to each floor. In addition, holes 8 for pouring concrete are formed in the formwork 4b of the temporary stage 4 at the column positions, and the column steel frames 2
It is now possible to form composite columns by combining steel and reinforced concrete.

第7図〜第9図は他の実施例として、仮設ステ
ージ4の吊降しを柱鉄骨2の頂部に設置したセン
ターホールジヤツキ14で行なう場合を示したも
のである。この例では柱鉄骨2について1本あた
り4個のセンターホールジヤツキ14を用意し、
ワイヤーロープ15を介して仮設ステージ4の仮
設フレーム4aを吊支持している。
7 to 9 show, as another embodiment, a case in which the temporary stage 4 is suspended by a center hole jack 14 installed at the top of the column steel frame 2. In this example, four center hole jacks 14 are prepared for each column steel frame 2,
A temporary frame 4a of a temporary stage 4 is suspended and supported via a wire rope 15.

床コンクリートの施工に際しては柱鉄骨2にボ
ルト等で固定した受金具16上にジヤツキ17を
介して、仮設ステージ4を下から支持するように
なつている。仮設ステージ4の吊降し作業は受金
具16およびジヤツキ17を撤去し、センターホ
ールジヤツキ14の操作により、徐々に下げて行
き、下階位置の受金具16およびジヤツキ17上
に設置する。なお、図中18はワイヤーガイドで
ある。
When constructing the floor concrete, the temporary stage 4 is supported from below via jacks 17 on a receiving metal fitting 16 fixed to the column steel frame 2 with bolts or the like. To suspend the temporary stage 4, remove the bracket 16 and jack 17, gradually lower it by operating the center hole jack 14, and install it on the bracket 16 and jack 17 at the lower floor position. In addition, 18 in the figure is a wire guide.

また、仮設ステージ4はセンターコア1にも同
様に支持させることができ、センターコア1の壁
面に受金具取付用の埋込みボルトを用意して、柱
鉄骨2位置と同様に1または複数のセンターホー
ルジヤツキ14を用い、同時に吊降し作業を行な
う。
In addition, the temporary stage 4 can also be supported by the center core 1 in the same way, by preparing embedded bolts for mounting brackets on the wall of the center core 1, and installing one or more center holes in the same way as the column steel frame 2 position. Using the jack 14, the lifting work is carried out at the same time.

第1図a〜gは一例として、この発明を利用し
て地上48階の超高層ビルを構築する場合を示した
もので、次のような手順で作業を行なう。
FIGS. 1a to 1g show, as an example, the construction of a 48-story skyscraper using the present invention, and the work is carried out in the following steps.

スライデイングフオーム工法あるいはジヤン
ピングフオーム工法によりセンターコア1を所
定高さまで先行させて構築する(第1図a参
照)。
The center core 1 is built in advance to a predetermined height by the sliding form method or the jumping form method (see Fig. 1a).

柱鉄骨2を立上げ、仮設ステージ4を18階の
床位置に組立てる(第1図b参照)。柱鉄骨2
は仮設の水平ブレース3により、センターコア
1と連結しておき、まず18階部分について配筋
等行なつた後、床コンクリートを打設する。
The steel column 2 will be erected and the temporary stage 4 will be assembled on the 18th floor (see Figure 1b). Pillar steel frame 2
will be connected to the center core 1 by temporary horizontal braces 3, and after the reinforcing work will be done on the 18th floor, the floor concrete will be poured.

仮設ステージ4を1階分吊降し(第1図c参
照)、17階部分の床架構5を施工する。
The temporary stage 4 will be suspended one floor (see Figure 1c), and the floor frame 5 for the 17th floor will be constructed.

以下、同様の作業を4階まで繰返す(第1図
d参照)。なお、4階以下の低層部6について
は従来と同様下から建方を行ない、この部分の
作業を並行作業としている。また、この間セン
ターコア1をさらに上方へ構築して行く。
Thereafter, the same operation is repeated up to the fourth floor (see Figure 1 d). As for the low-rise part 6 of the fourth floor and below, erection is carried out from the bottom as in the past, and the work for this part is carried out in parallel. Also, during this time, the center core 1 is constructed further upward.

柱鉄骨2を上方へ立上げ、解体した仮設ステ
ージ4を32階の床位置に移動させ(第1図e参
照)、32階から19階まで順次、床架構5を施工
する。また、それと並行して、4階から上方へ
順次柱センターコアを打設して複合柱を形成さ
せるとともに、センターコア1の上方への構築
を完了させる。
The column steel frame 2 will be raised upward, the dismantled temporary stage 4 will be moved to the floor position on the 32nd floor (see Figure 1 e), and the floor frame 5 will be constructed sequentially from the 32nd floor to the 19th floor. In parallel with this, the column center cores are sequentially cast upward from the fourth floor to form a composite column, and the construction of the center core 1 upward is completed.

仮設ステージ4を屋根スラブ位置に移動させ
(第1図f参照)、順次33階まで床架構5を施工
する。また、同時に19階から柱コンクリートを
打設し、順次上方へ複合柱を形成させて行き、
下階からは上方へ向けてカーテンウオールの取
り付けを開始する。
The temporary stage 4 is moved to the roof slab position (see Figure 1 f), and the floor frame 5 is constructed sequentially up to the 33rd floor. At the same time, concrete pillars were poured starting from the 19th floor, and composite pillars were successively formed upwards.
Starting from the lower floor, we will begin installing the curtain wall upwards.

すべての架構作業を完了し(第1図g参照)、
カーテンウオールの作業を継続する。
Complete all structural work (see Figure 1g),
Continue curtain wall work.

以上の作業において、センターコア1の立上げ
の速度は1日に1階分、床架構5の施工は5日で
1階分、柱センターコアの施工が2日で1階分を
想定しており、床架構5の施工と、センターコア
1の上方階の施工、さらに床架構5の施工と下方
階の柱コンクリートの施工等を並行作業として行
なうことができる。
In the above work, it is assumed that the center core 1 will be built up one floor per day, the floor structure 5 will be built one floor in five days, and the pillar center core will be built one floor in two days. Therefore, the construction of the floor frame 5, the construction of the upper floor of the center core 1, the construction of the floor frame 5, the construction of column concrete on the lower floor, etc. can be performed in parallel.

〔発明の効果〕 上層階で組立てた仮設ステージを繰り返し使
用するので仮設資材が少なくて済み、経済的で
ある。
[Effects of the Invention] Since the temporary stages assembled on the upper floors are used repeatedly, less temporary materials are required, which is economical.

仮設ステージは解体せずに移動できるので作
業の手間が少なく、省力化が図れる。
Temporary stages can be moved without being dismantled, reducing the amount of work involved and saving labor.

コンクリートの硬化待ちの作業が少なくなる
ため、並行作業により大幅な工期短縮が図れ
る。
Since there is less work to do while waiting for the concrete to harden, parallel work can significantly shorten the construction period.

【図面の簡単な説明】[Brief explanation of drawings]

第1図a〜gはこの発明の一実施例における施
工手順を示す正面図、第2図は仮設ステージの鉄
骨フレームの底面図、第3図は第2図の−断
面図、第4図は第3図の−断面図、第5図は
施工途中における平面図、第6図は床および柱部
分の構造を示す断面斜視図、第7図は他の実施例
における要部の正面図、第8図は側面図、第9図
は平面図である。 1……センターコア、2……柱鉄骨、3……水
平ブレース、4……仮設ステージ、4a……鉄骨
フレーム、4b……型枠、5……床架構、5a…
…床スラブ、5b……梁、6……低層部、7……
柱コンクリート、8……柱コンクリート打設用の
穴、9……接合プレート、10……柱鉄筋、11
……床鉄筋、12……アンボンドPCストランド、
13……梁鉄筋、14……センターホールジヤツ
キ、15……ワイヤーロープ、16……受金具、
17……ジヤツキ、18……ワイヤーガイド。
Figures 1 a to g are front views showing the construction procedure in one embodiment of the present invention, Figure 2 is a bottom view of the steel frame of the temporary stage, Figure 3 is a cross-sectional view of Figure 2, and Figure 4 is a 3 is a sectional view, FIG. 5 is a plan view during construction, FIG. 6 is a sectional perspective view showing the structure of the floor and pillars, and FIG. 7 is a front view of main parts in another embodiment. 8 is a side view, and FIG. 9 is a plan view. 1... Center core, 2... Steel column, 3... Horizontal brace, 4... Temporary stage, 4a... Steel frame, 4b... Formwork, 5... Floor frame, 5a...
...Floor slab, 5b... Beam, 6... Low-rise section, 7...
Column concrete, 8... Hole for pouring column concrete, 9... Connection plate, 10... Column reinforcing bar, 11
...Floor reinforcing bar, 12...Unbonded PC strand,
13...Beam reinforcing bar, 14...Center hole jack, 15...Wire rope, 16...Bracket fitting,
17... Jackpot, 18... Wire guide.

Claims (1)

【特許請求の範囲】 1 センターコアの構築を先行させ、続いてセン
ターコア外部の柱鉄骨を所定高さまで立上げて行
き、該柱鉄骨に沿つてスライド可能な仮設ステー
ジを、立上げた前記柱鉄骨上部にセンターコアを
取囲むようにして組立て、該仮設ステージを1階
ずつ下げながら仮設ステージ上に順次下階の床コ
ンクリートを打設して行くことを特徴とする建物
の架構施工法。 2 柱鉄骨は仮設の水平ブレースでセンターコア
と連結しながら立上げる特許請求の範囲第1項記
載の建物の架構施工法。 3 仮設ステージは鉄骨フレームと該鉄骨フレー
ム上に設けた型枠とからなる特許請求の範囲第1
項または第2項記載の建物の架構施工法。
[Claims] 1. The center core is constructed first, and then the column steel frames outside the center core are erected to a predetermined height, and a temporary stage that is slidable along the column steel frames is installed on the erected pillars. A building frame construction method characterized by assembling the upper part of a steel frame to surround a center core, and successively pouring floor concrete for lower floors on the temporary stage while lowering the temporary stage one floor at a time. 2. The building frame construction method according to claim 1, in which the steel columns are erected while being connected to the center core using temporary horizontal braces. 3. The temporary stage consists of a steel frame and a formwork provided on the steel frame.
The method of constructing the structure of a building as described in paragraph 2 or paragraph 2.
JP14136685A 1985-06-27 1985-06-27 Construction of housing of building Granted JPS621954A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14136685A JPS621954A (en) 1985-06-27 1985-06-27 Construction of housing of building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14136685A JPS621954A (en) 1985-06-27 1985-06-27 Construction of housing of building

Publications (2)

Publication Number Publication Date
JPS621954A JPS621954A (en) 1987-01-07
JPH0417262B2 true JPH0417262B2 (en) 1992-03-25

Family

ID=15290311

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14136685A Granted JPS621954A (en) 1985-06-27 1985-06-27 Construction of housing of building

Country Status (1)

Country Link
JP (1) JPS621954A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2668237B2 (en) * 1988-04-14 1997-10-27 株式会社竹中工務店 Core leading construction method

Also Published As

Publication number Publication date
JPS621954A (en) 1987-01-07

Similar Documents

Publication Publication Date Title
JP3196043B2 (en) Construction method of stairs and staircase, construction method of stairs, and stair members
JPH05287901A (en) Construction of stairs
JP5003253B2 (en) RC beam construction method
JPH0657956A (en) Construction of concrete structure
JPH0417262B2 (en)
JP3241896B2 (en) Steel frame stair hang down method
US3435583A (en) Method of forming buildings
JPS61109827A (en) Construction of basement
JP3187618B2 (en) How to assemble beam reinforcement
JP3338240B2 (en) Construction method for reinforced concrete structures
JP7462475B2 (en) How to build a building
JP2696486B2 (en) Building construction method
JPH03197734A (en) Lift up method by replacement of scaffold body
JP3087196B2 (en) How to build stairs
JPH0437893B2 (en)
JPS63312437A (en) Construction of underground structure
JP3605661B2 (en) Construction method of concrete structure
JP2844096B2 (en) How to build stairs in buildings
JP2804219B2 (en) Reinforced steel pipe unit and building construction method using the same
JP3224152B2 (en) Construction method of cross beam in concrete building
JP2990216B2 (en) Construction method of reinforced concrete building
JPH083926A (en) Construction method of composite structure pier
JPH0827903A (en) All weather type building method
JP2026000775A (en) Construction method and stage structure
KR20250061106A (en) Construction Method and Apparatus for Elevator Mechanical Room Frames on the Roof Floor, such as Offices and Apartments, Using Steel Structures