Info
- Publication number
- JPH0433926B2 JPH0433926B2 JP58228558A JP22855883A JPH0433926B2 JP H0433926 B2 JPH0433926 B2 JP H0433926B2 JP 58228558 A JP58228558 A JP 58228558A JP 22855883 A JP22855883 A JP 22855883A JP H0433926 B2 JPH0433926 B2 JP H0433926B2
- Authority
- JP
- Japan
- Prior art keywords
- pipe
- tube
- ground
- grout
- sewing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/12—Consolidating by placing solidifying or pore-filling substances in the soil
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Structural Engineering (AREA)
- Agronomy & Crop Science (AREA)
- Environmental & Geological Engineering (AREA)
- Soil Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Description
【発明の詳細な説明】
本発明は地盤改良型縫地工法に関するものであ
る。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a ground improvement type sewing method.
トンネルおよび地下構造物を構築する場合、掘
削により地山の緩みや地表面の変形を抑止する為
に次の各工法などが採用されている。 When constructing tunnels and underground structures, the following construction methods are used to prevent loosening of the ground and deformation of the ground surface due to excavation.
<イ> パイプルーフ工法
トンネルの掘削に先立ち、掘削断面外周に沿つ
てパイプ(鋼管)を挿入し、トンネル形状に合せ
たルーフを形成し、トンネル掘削に伴いこのルー
フを支保工で直接支承して、掘削による地表面の
変形を抑止する工法。<B> Pipe roof construction method Prior to tunnel excavation, a pipe (steel pipe) is inserted along the outer circumference of the excavation cross section to form a roof that matches the tunnel shape, and as the tunnel is excavated, this roof is directly supported by shoring. , a construction method that prevents deformation of the ground surface due to excavation.
<ロ> 薬液注入工法
薬液等を地盤に注入し、地盤の透水性を減少さ
せたり、地盤の強度を増加させる工法。<B> Chemical injection method A method of injecting chemical solutions into the ground to reduce the permeability of the ground or increase its strength.
<ハ> 凍結工法
凍結固化予定地盤にあらかじめ凍結管を一定間
隔で打込み、凍結機で冷凍したプラインを凍結管
内に循環させるか、あるいは、液体窒素ボンベか
らガスを凍結管に放出するかして地盤を凍結固化
する工法。<C> Freezing method: Freezing pipes are driven into the ground to be frozen and solidified in advance at regular intervals, and frozen plines are circulated through the freezing pipes using a freezing machine, or gas is released into the freezing pipes from a liquid nitrogen cylinder to freeze the ground. A method of freezing and solidifying.
以上の各工法は施工上、次のような問題を抱え
ている。 Each of the above construction methods has the following problems in construction.
<イ> 軟弱地盤の場合には各工法の単一採用だ
けでは不十分であるため、実際には複数の工法
を併用している。<B> In the case of soft ground, it is insufficient to use a single construction method, so in reality, multiple construction methods are used in combination.
その際各工法ごとの作業を独立して行うので
作業効率が低く、コスト高となる。 At this time, work for each construction method is performed independently, resulting in low work efficiency and high costs.
<ロ> 単一工法だけを採用する場合、地山崩壊
の危険性を重視し、過剰設計となりやすい。<B> When only a single construction method is adopted, emphasis is placed on the risk of ground collapse, which tends to lead to over-design.
本発明はこの様な問題を解決するためになされ
たもので、作業性、経済性および安全性に優れ
た、地盤改良型縫地工法を提供する事を目的とす
る。 The present invention was made to solve such problems, and an object of the present invention is to provide a ground improvement type sewing method that is excellent in workability, economy, and safety.
次に図面に基ずきながら本発明の一実施例につ
いて説明するが、まず本工法に使用する縫地材に
ついて説明する。 Next, an embodiment of the present invention will be described based on the drawings, but first a description will be given of the sewing material used in this construction method.
[イ] 縫地材
縫地材1は縫地管2と内挿管4およびグラウト
管3で構成する。[A] Sewing material The sewing material 1 is composed of a sewing material tube 2, an inner tube 4, and a grout tube 3.
[ロ] 縫地管
縫地管2は第1図に示すように鋼製、塩化ビニ
ール等からなる中空管である。[B] Sewn pipe The sewn pipe 2 is a hollow pipe made of steel, vinyl chloride, etc., as shown in FIG.
縫地管2は後述するように地山に貫入して地山
に縫い合わせるだけでなく、逆流を防止したグラ
ウト注入を目的とする長尺の管である。 As will be described later, the sewing pipe 2 is a long pipe whose purpose is not only to penetrate the ground and stitch it to the ground, but also to inject grout while preventing backflow.
グラウト剤の逆流を防止するには例えば、第7
図に示すように縫地管2の周面に放出孔22を複
数円周方向に開設し、そして放出孔22を同心の
凹溝24を凹設し、この凹溝24内の底部にゴム
やウレタン等の円盤の中心に切り込みを入れて形
成したゴム弁25をねじ止め、あるいは接着剤等
を使つて固定する。 To prevent backflow of grouting agent, for example,
As shown in the figure, a plurality of discharge holes 22 are opened in the circumferential direction on the circumferential surface of the sewing pipe 2, and a concave groove 24 concentric with the discharge holes 22 is provided. A rubber valve 25 formed by making a cut in the center of a disk made of urethane or the like is fixed by screwing or using adhesive or the like.
このゴム弁25は放出孔22から圧力が作用す
ると切り込みの入つた円盤を噴射方向に押しやつ
て開孔状態を形成するが、逆に外部から円盤に圧
力が作用すると、円盤が放出孔22を閉塞するよ
う構成する。 When pressure is applied from the discharge hole 22, this rubber valve 25 pushes the disc with the notch in the injection direction to form an open hole.On the other hand, when pressure is applied to the disc from the outside, the disc pushes the discharge hole 22. Configure to block.
本実施例のように、各放出孔22毎に凹溝24
を凹設し、この凹溝24内に弁を設置したので、
縫地管2の強度を十分に確保できる。 As in this embodiment, each discharge hole 22 has a concave groove 24.
Since the groove 24 is recessed and the valve is installed inside the groove 24,
Sufficient strength of the sewing pipe 2 can be ensured.
[ハ] 内挿管
内挿管4は後述するグラウト管3の外径より僅
かに内径の大きな管であり、内部にグラウト管3
を収納する。[C] Internal tube The internal tube 4 has an inner diameter slightly larger than the outer diameter of the grout tube 3, which will be described later, and has the grout tube 3 inside.
to store.
すなわち、内挿管4の先端は、グラウト管3の
ストツパー32に係止するパツキン5に当接し、
および内挿管4の中間にはもう一つのパツキン5
が介在する。 That is, the tip of the inner tube 4 comes into contact with the gasket 5 that locks on the stopper 32 of the grout tube 3,
and another gasket 5 in the middle of the internal tube 4.
intervenes.
パツキン5間に位置する内挿管4の周面には、
注入孔41を開孔する。 On the circumferential surface of the internal intubation tube 4 located between the seals 5,
The injection hole 41 is opened.
[ロ] グラウト管
グラウト管3は内挿管4内にスライド自在に位
置して、内挿管4と共に前記縫地管2内に進退自
在に内挿して、縫地管2内の希望する箇所だけに
単数以上の薬液等を一度に注入することを目的と
した注入管である。[B] Grout tube The grout tube 3 is slidably positioned in the inner tube 4, and is inserted into the sewing tube 2 together with the inner tube 4 so as to move forward and backward, so that it can be inserted only at a desired location inside the sewing tube 2. This is an injection tube intended for injecting one or more medicinal solutions at once.
グラウト管3の先端は閉塞し、かつこの先端に
は内周面より突出したストツパー32を形成す
る。 The tip of the grout tube 3 is closed, and a stopper 32 is formed at the tip to protrude from the inner peripheral surface.
グラウト管3の周面には円周方向に噴射孔31
群を開孔し、さらに、噴射孔31の両側にはゴム
等の弾力性素材をリング状に形成したパツキン5
を装着する。 Injection holes 31 are arranged in the circumferential direction on the circumferential surface of the grout pipe 3.
In addition, on both sides of the injection hole 31, there is a gasket 5 made of a ring-shaped elastic material such as rubber.
Attach.
グラウト管3および内挿管4は両者が組合つて
希望する放出孔22からのみ薬液等を注入する事
を目的とする。 The purpose of the grout tube 3 and the inner tube 4 is to inject the chemical liquid etc. only from the desired discharge hole 22 when both are combined.
従つてグラウト管3と内挿管4を相互移動させ
るとパツキン5は圧縮されて膨脹し、また圧縮力
を解除してやると元の形状に復元する。 Therefore, when the grout tube 3 and the inner tube 4 are moved relative to each other, the packing 5 is compressed and expanded, and when the compressive force is released, it returns to its original shape.
その結果、パツキン5が膨脹すると縫地管2の
内壁が相当な圧力で押付けられてグラウト管3と
内挿管4の間の空間43が遮断される。 As a result, when the packing 5 expands, the inner wall of the sewing tube 2 is pressed with considerable pressure, thereby blocking the space 43 between the grout tube 3 and the inner tube 4.
また、複数の薬液を混合して放出したいときは
グラウト管3内を例えばB液専用通路として使用
できるほかに、内挿管4の基端にスイベル等を装
着し、空間43を例えばA液専用通路として利用
できる訳であるが、パツキン5が膨脹するとこの
空間43が途中で遮断されて、A液の供給が不能
となる。 In addition, when it is desired to mix and release a plurality of chemical solutions, the inside of the grout tube 3 can be used as a passage exclusively for liquid B, for example, and a swivel or the like can be attached to the proximal end of the inner tube 4, so that the space 43 can be used as a passage exclusively for liquid A. However, when the gasket 5 expands, this space 43 is cut off midway, making it impossible to supply liquid A.
そこで、空間43が遮断される直前のグラウト
管3の周面に連絡孔34を開設し、そしてグラウ
ト管3内に設けた逆止弁33位置から、噴射孔3
1までの間を連絡するゴム等の弾性材からなるゴ
ム管6を内壁に密着させて配置する。 Therefore, a communication hole 34 is opened on the circumferential surface of the grout pipe 3 immediately before the space 43 is blocked, and the injection hole 3 is opened from the position of the check valve 33 provided in the grout pipe 3.
A rubber tube 6 made of an elastic material such as rubber is placed in close contact with the inner wall.
その結果パツキン5が膨脹しても、A液は空間
43から連絡孔34を経てゴム管6を押しやつて
グラウト管3の内壁面との間に独立した通路を形
成しながら移動して、噴射孔31の直前でB液と
合流する。 As a result, even if the packing 5 expands, the liquid A moves from the space 43 through the communication hole 34, pushes the rubber tube 6, forms an independent passage between it and the inner wall surface of the grout tube 3, and is injected. It merges with the B liquid just before the hole 31.
従つて、両液A,Bを注入孔41で噴射する直
前に合流して噴射できるので、瞬結材を他の薬液
等と併用しても管内で固化する心配がまつたくな
い。 Therefore, since both liquids A and B can be combined and injected immediately before being injected at the injection hole 41, there is no need to worry about solidification in the pipe even if the instant setting material is used together with other chemical liquids.
次にトンネル工事に利用した場合の施工方法に
ついて説明する。 Next, we will explain the construction method when used for tunnel construction.
[イ] 縫地管の設置
トンネル開削方向に傾けて公知の穿孔装置で穿
孔し、この孔内に前記縫地管2を設置する。[B] Installation of the sewn pipe A hole is bored with a known drilling device at an angle in the tunnel excavation direction, and the sewn pipe 2 is installed in this hole.
縫地管2を地中に配置するには、次の二つの方
法が考えられる。 The following two methods can be considered for arranging the sewing pipe 2 underground.
その一つは縫地管2をアウターケーシングとし
て利用し、先端にインナービツトを有するインナ
ーロツドと共に穿孔を行つた後、縫地管2内から
インナーロツドを引き抜いて縫地管2を地中に残
存する方法である。 One method is to use the sewn pipe 2 as an outer casing, perform drilling together with an inner rod having an inner bit at the tip, and then pull out the inner rod from inside the sewn pipe 2, leaving the sewn pipe 2 underground. It is.
もう一つは、既存のアウターケーシングとイン
ナーロツドで穿孔を行ない、アウターケーシング
内からインナーロツドを抜いて縫地管2を入れ替
えた後、地中からアウターケーシングを抜取る方
法も考えられる。 Another method is to make a hole in the existing outer casing and inner rod, remove the inner rod from the outer casing, replace the sewing pipe 2, and then remove the outer casing from underground.
なお、縫地管2を鋼管と塩化ビニールパイプを
組合せて形成することも可能である。 Note that it is also possible to form the sewn pipe 2 by combining a steel pipe and a vinyl chloride pipe.
この場合、トンネル断面内に塩化ビニールパイ
プからなる縫地管2を配置すると掘削時の縫地管
2の端部破壊が容易となる。 In this case, if the seam pipe 2 made of vinyl chloride pipe is arranged within the cross section of the tunnel, the ends of the seam pipe 2 can be easily destroyed during excavation.
[ロ] 薬液注入(低圧グラウト)
公知の方法で縫地管2の先端を閉塞した状態で
地中に配置したら縫地管2の基端側にパツカーを
配置し、縫地管2内には内挿管4を装備したグラ
ウト管3を挿入する。[B] Chemical injection (low-pressure grouting) Once the tip of the sewing pipe 2 is closed and placed in the ground using a known method, a packer is placed on the proximal end of the sewing pipe 2, and a grout is placed inside the sewing pipe 2. A grouting tube 3 equipped with an internal tube 4 is inserted.
次に縫地管2内でグラウト管3とこのグラウト
管3を収納する内挿管4を相互移動してパツキン
5を膨脹させた後、グラウト管3および内挿管4
の基端から公知のグラウト剤をそれぞれ低圧で充
填すると、グラウト剤が逆流を防止しながら放出
孔22から削孔内に充填される。 Next, the grout tube 3 and the inner tube 4 that accommodates the grout tube 3 are mutually moved within the sewing tube 2 to inflate the packing 5, and then the grout tube 3 and the inner tube 4 are moved.
When a known grouting agent is filled at low pressure from the base end of each hole, the grouting agent is filled into the drilled hole from the discharge hole 22 while preventing backflow.
一度噴出したグラウト剤はゴム弁25が装着し
てあるので管内に逆流する心配がまつたく無い。 Since the rubber valve 25 is attached, there is no worry that the grout once spouted will flow back into the pipe.
グラウト剤を低圧で充填するのは、縫地管2と
地山間に一様なグラウト層を形成して適度な密着
を図り、グラウト剤の必要以上な充填を阻止する
ためである。 The reason why the grouting agent is filled at low pressure is to form a uniform grout layer between the sewn fabric pipe 2 and the ground to achieve appropriate adhesion and to prevent unnecessary filling of the grouting agent.
[ハ] 部分充填(高圧グラウト)
縫地管2の貫入する地盤の一部に地下水層やク
ラツク等が存在する場合にはこれらの箇所を地盤
改良する必要がある。[C] Partial filling (high-pressure grouting) If there are groundwater aquifers, cracks, etc. in the part of the ground that the seamed pipe 2 penetrates, it is necessary to improve the ground at these locations.
そのため、穿孔の際排土より地質を判断してク
ラツクや地下水層等の発生位置を把握しておき、
この情報をもとにこれらの地域に集中して薬液を
充填して地盤改良を行う。 Therefore, when drilling, it is necessary to judge the geology from the soil removed and understand the location of cracks and underground water layers.
Based on this information, we concentrate on these areas and fill them with chemicals to improve the ground.
これらの地域に薬液を充填するには、高圧で圧
送して、低圧で充填したグラウト層を突破して積
極的にクラツク発生箇所や地下水層等に浸透させ
る。 To fill these areas with chemical solution, it is pumped under high pressure, breaks through the grout layer filled at low pressure, and actively penetrates into crack occurrence areas and underground water layers.
この際、地山と縫地管2の間にグラウト剤が全
域に渡つて充填してあるので、薬液が不必要な程
広域に浸透することはない。 At this time, since the grouting agent is filled over the entire area between the ground and the sewn fabric pipe 2, the chemical solution does not unnecessarily permeate over a wide area.
従つてある特定位置の注入孔41群に接近する
箇所のみ薬液が集中して放出される。 Therefore, the chemical solution is concentrated and discharged only at a location close to the group of injection holes 41 at a certain specific position.
その結果、薬液はクラツク発生箇所や地下水層
内に進入して段階的(部分的)な地盤の改良が可
能になる。 As a result, the chemical liquid enters the crack occurrence area and the underground water layer, making it possible to improve the ground in stages (partially).
[ニ] 掘進
所定のグラウト注入を終了したら、グラウト管
3および内挿管4を抜取り、縫地管2内にモルタ
ル等を充填した後、縫地管2の埋設された状態で
トンネル開削方向に掘削する。[d] Excavation After completing the specified grout injection, the grout pipe 3 and the inner tube 4 are removed, and after filling the seam pipe 2 with mortar etc., excavate in the tunnel excavation direction with the seam pipe 2 buried. do.
掘削断面内に位置する縫地管2の基端側は掘削
の進行に伴つて順次切断されて行くが、他はその
まま地中に残存する。 The proximal end side of the seamed pipe 2 located within the excavation cross section is sequentially cut as the excavation progresses, but the rest remains underground as is.
その結果、トンネル周囲の地山は縫地管2によ
つて各層を貫通して縫い合わされ、同時に地下水
層やクラツク等が存在する場合には適切に地盤改
良が施されて安定した状態を維持できる。 As a result, the ground around the tunnel is sewn together through each layer by the sewing pipe 2, and at the same time, if there is an underground water layer or crack, the ground can be appropriately improved and a stable state can be maintained. .
[ホ] その他の実施例
第8図のように凹溝24内の底面に設置するゴ
ムやウレタン等からなる円盤の盤面に円周方向の
スリツト27を開設したスリツトゴム弁26を採
用する事も考えられる。[E] Other Embodiments It is also possible to consider adopting a slit rubber valve 26 in which a slit 27 in the circumferential direction is formed on the surface of a disk made of rubber, urethane, etc., which is installed on the bottom surface of the groove 24, as shown in FIG. It will be done.
スリツト27は放出孔22を避けた位置に開設
し、グラウト時は円盤と凹溝24の底面間に通路
を形成するが、スリツト27に外圧が作用して
も、凹溝24の底面で通路を遮断できる位置に形
成する。 The slit 27 is opened at a position that avoids the discharge hole 22 and forms a passage between the disk and the bottom of the groove 24 during grouting, but even if external pressure acts on the slit 27, the bottom of the groove 24 will not open the passage. Form in a position where it can be blocked.
また、縫地管2の周面の放出孔22を被覆でき
るようなリング状の弾性材からなるゴム環(図示
せず)を環装してなる逆止弁を採用する事も考え
られる。 It is also conceivable to adopt a check valve formed by enclosing a rubber ring (not shown) made of a ring-shaped elastic material and capable of covering the discharge hole 22 on the circumferential surface of the sewing pipe 2.
本発明は以上説明したようになるから次のよう
な効果を期待することができる。 Since the present invention is as explained above, the following effects can be expected.
<イ> 従来、軟弱地盤が存在する場合には複数
の工法が併用されていたが、本発明は縫地管を
グラウト注入管として利用する事により、ロツ
クボルト的効果と地盤改良による両効果を期待
することができる。<B> Conventionally, multiple construction methods were used in combination when soft ground existed, but the present invention uses a sewn ground pipe as a grout injection pipe, and is expected to have both a lock bolt effect and a ground improvement effect. can do.
従つて大幅な作業の効率化とコストの低減を
図る事ができる。 Therefore, it is possible to significantly improve work efficiency and reduce costs.
<ロ> 地層に応じて段階的な薬液の注入が可能
である。<B> It is possible to inject chemicals in stages according to the strata.
そのため、高価な薬液を必要量以上に注入す
る事を防止でき、経済的であるだけでなく、良
好な地盤の改良効果を得る事ができる。 Therefore, it is possible to prevent the injection of expensive chemicals in excess of the required amount, which is not only economical but also provides a good ground improvement effect.
<ハ> 単数以上の薬液等を同時に噴出できるの
で、従来まで併用が困難とされていた瞬結剤の
使用が可能となる。<C> Since more than one chemical solution can be ejected at the same time, it becomes possible to use a supersetting agent, which was previously considered difficult to use together.
<ニ> 放出孔が逆流防止機能を具備しているた
め、管体の挿入時においては土砂の流入を阻止
でき、また薬液注入時においては薬液の逆流を
効果的に防止できる。<D> Since the discharge hole has a backflow prevention function, it is possible to prevent the inflow of earth and sand when the tube is inserted, and it is also possible to effectively prevent the backflow of the chemical solution when the chemical solution is injected.
第1図:縫地材の一実施例の説明図、第2図:
縫地材の断面図、第3,4図:施工方法の説明
図、第5図:第4図における−の断面図、第
6図:第4図における−の断面図、第7図:
縫地管の放出孔付近の断面図、第8図:その他の
実施例の説明図。
1……縫地材、2……縫地管、3……グラウト
管、4……内挿管、5……パツキン、25……ゴ
ム弁。
Figure 1: An explanatory diagram of one embodiment of the sewing material, Figure 2:
Cross-sectional view of the sewing material, Figures 3 and 4: Explanatory diagram of the construction method, Figure 5: Cross-sectional view of - in Figure 4, Figure 6: Cross-sectional view of - in Figure 4, Figure 7:
A sectional view of the vicinity of the discharge hole of the sewing pipe, FIG. 8: An explanatory diagram of another embodiment. 1... Sewing material, 2... Sewing pipe, 3... Grout pipe, 4... Internal intubation tube, 5... Packing, 25... Rubber valve.
Claims (1)
孔を管体の長手方向に沿つて設けた縫地管を使用
し、 開削予定地盤に前記縫地管を複数本断面方向に
傾けて貫入し、 縫地管の任意位置の放出孔から逆流を防止した
状態で薬液を噴出させて周囲の地山を固化する、 地盤改良型縫地工法。[Claims] 1. Using a seamed pipe in which a plurality of discharge holes with a backflow prevention function are provided along the longitudinal direction of the pipe body on the circumferential surface of the pipe body, a plurality of the seamed pipes are installed in the ground to be excavated. This is a soil improvement type seaming construction method in which the material is penetrated at an angle in the direction of the main cross section, and the chemical liquid is ejected from the discharge holes at arbitrary positions in the seamed pipe to prevent backflow and solidify the surrounding ground.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP22855883A JPS60123616A (en) | 1983-12-05 | 1983-12-05 | Ground improving type palissage method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP22855883A JPS60123616A (en) | 1983-12-05 | 1983-12-05 | Ground improving type palissage method |
Related Child Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2655085A Division JPS60215916A (en) | 1985-02-15 | 1985-02-15 | Injection pipe for ground improvement |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS60123616A JPS60123616A (en) | 1985-07-02 |
| JPH0433926B2 true JPH0433926B2 (en) | 1992-06-04 |
Family
ID=16878253
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP22855883A Granted JPS60123616A (en) | 1983-12-05 | 1983-12-05 | Ground improving type palissage method |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS60123616A (en) |
Families Citing this family (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR2704899B1 (en) * | 1993-05-07 | 1995-07-07 | Sol Cie | METHOD AND DEVICE FOR INJECTING PRODUCTS INTO THE SOIL. |
| JP4878294B2 (en) * | 2007-01-22 | 2012-02-15 | 東急建設株式会社 | Ground improvement method and equipment |
| JP5026829B2 (en) * | 2007-03-20 | 2012-09-19 | 株式会社大林組 | Seismic reinforcement facilities and methods for seismic reinforcement of masonry walls |
| JP4942211B2 (en) * | 2008-01-21 | 2012-05-30 | 鹿島建設株式会社 | Ground reinforcement method |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPS5110812U (en) * | 1974-07-10 | 1976-01-27 | ||
| JPS5927830B2 (en) * | 1976-11-19 | 1984-07-09 | 日本鉱機株式会社 | Tunnel excavation method in soft ground |
-
1983
- 1983-12-05 JP JP22855883A patent/JPS60123616A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS60123616A (en) | 1985-07-02 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN107605498B (en) | Construction method of horizontal grouting reinforcement structure at the end of shield tunnel in water-rich sandy pebble stratum | |
| JP2004027813A (en) | Packer for pressure type soil nailing and method of soil nailing using it | |
| KR20000071412A (en) | The device and the method for pouring ground | |
| JP2785907B2 (en) | Packer and soil compaction method using it | |
| JPH0433926B2 (en) | ||
| JP4679966B2 (en) | Boring hole closing method and equipment | |
| JPH0370048B2 (en) | ||
| JP3987234B2 (en) | Ground mountain tip receiving reinforcement method | |
| JP3015858B2 (en) | Construction structure of landslide prevention pile and its construction method. | |
| CN118481666A (en) | Water stop ring shield segment with embedded pocket and water stop ring construction method | |
| JPH03132592A (en) | Foundation improvement for driving tunnel | |
| JP2002047881A (en) | Pipeline construction method | |
| JP3467221B2 (en) | Ground reinforcement method | |
| JP3675705B2 (en) | Ground reinforcement method | |
| KR102853477B1 (en) | Direct-boring hole grouting method using a rapid-hardening grouting simultaneous pressurized injection device | |
| JP2005314940A (en) | Chemical grouting device | |
| JPH0313689A (en) | Construction method for tunnel | |
| JPH0776819A (en) | Improving method for ground of tunnel excavation part and peripheral part thereof | |
| JPH074600U (en) | Injection fixing type support member | |
| JP3524493B2 (en) | Ground reinforcement method | |
| CN222936716U (en) | Underground working face drilling water outlet grouting plugging device | |
| JP2002256790A (en) | Method and device for filling drilled hole based on grout material injection via down-the-hole drill | |
| JPH0459409B2 (en) | ||
| JP2865907B2 (en) | Hardener injection method and hardener injection device | |
| JP2566521B2 (en) | Tunnel excavation and surrounding ground improvement method |