JPH0458527B2 - - Google Patents
Info
- Publication number
- JPH0458527B2 JPH0458527B2 JP17402284A JP17402284A JPH0458527B2 JP H0458527 B2 JPH0458527 B2 JP H0458527B2 JP 17402284 A JP17402284 A JP 17402284A JP 17402284 A JP17402284 A JP 17402284A JP H0458527 B2 JPH0458527 B2 JP H0458527B2
- Authority
- JP
- Japan
- Prior art keywords
- caisson
- casing
- pipe
- steel pipe
- air
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
- E02D23/02—Caissons able to be floated on water and to be lowered into water in situ
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
Description
【発明の詳細な説明】
[発明の技術分野]
本発明は、水中橋脚等の水中構造物を建設する
ための鋼管継足しケーソン基礎のケーシング管シ
ール工法及びその装置に関する。DETAILED DESCRIPTION OF THE INVENTION [Technical Field of the Invention] The present invention relates to a method and apparatus for sealing a casing pipe of a caisson foundation with a steel pipe connection for constructing an underwater structure such as an underwater bridge pier.
[従来技術]
従来のケーソン基礎には、あらじめ水底を所定
の基礎面まで掘削してからケーソンを据付ける方
式や、水底に沈設後ケーソン内側要部に杭を打ち
込み杭とケーソンを一体化する方式がある。これ
らのケーソンはケーソンを二重壁構造とすること
で浮遊させたり、ケーソン内側要部に配した杭の
底面を鋼板で仮蓋締することにより水密室を確保
し浮力を得ていた。またこれらのケーソンによれ
ば、地下連続壁を形成しなくとも必要な地盤反力
が得られていた。[Conventional technology] Conventional caisson foundations include a method in which the caisson is installed after excavating the water bottom to a specified foundation surface, or a method in which a pile is driven into the main inside part of the caisson after it has been sunk to the water bottom, and the pile and caisson are integrated. There is a method to do this. These caissons were made to float by making them double-walled, or by temporarily covering the bottoms of the piles placed inside the caissons with steel plates to ensure a watertight chamber and obtain buoyancy. Moreover, according to these caissons, the necessary ground reaction force was obtained without forming an underground continuous wall.
ところで、鋼管継足しケーソン基礎は大水深の
水域に大型の構造物基礎を建設するための工法
で、施工工程の概要は以下に示す通りである。 By the way, the steel pipe jointed caisson foundation is a construction method for constructing the foundation of a large structure in deep water, and the outline of the construction process is as shown below.
(1) ケーソン外周面に軸線を鉛直方向にした複数
のケーシング管を配置したケーソンをドツク等
で製作し、構造物基礎の建設地点まで運搬し、
所定の水底位置に沈設するか、所定の水面位置
に浮遊せしめた状態下で係留する。(1) A caisson with multiple casing pipes arranged on the outer circumferential surface of the caisson with the axes oriented vertically is manufactured using a dock, etc., and transported to the construction site of the structure's foundation.
It is moored either by sinking to a predetermined water bottom position or floating at a predetermined water surface position.
(2) 各ケーシング管の内側に鋼管杭を挿入し、鋼
管杭の下部を地中に埋設する。ついでケーシン
グ管内側と鋼管杭外側の間隙部に、モルタルを
充填して、ケーシング管と鋼管杭を固定する。(2) Insert a steel pipe pile inside each casing pipe, and bury the lower part of the steel pipe pile underground. Next, the gap between the inside of the casing pipe and the outside of the steel pipe pile is filled with mortar to fix the casing pipe and the steel pipe pile.
(3) 鋼管杭により囲つた部分の水底地盤を掘削
し、掘削した地中部分及びケーソンの内部に水
中コンクリートを打設し、大型の構造物基礎と
する。(3) Excavate the underwater ground in the area surrounded by steel pipe piles, and place underwater concrete in the excavated underground area and inside the caissons to serve as the foundation for a large structure.
しかしながら、上記のような施工工事を実施す
るに当つては以下に示すような問題があつた。 However, when carrying out the above construction work, there were problems as shown below.
(1) ケーソンは大寸法、大重量であり、ケーソン
をドツクより引き出すに当り、ケーソンの浮力
を利用する必要がある。このためケーソンを二
重壁構造として浮力室を得るとともに、ケーソ
ン外壁面に設けたケーシング管の下端を仮蓋締
して浮力を増す必要がある。しかしながらこの
仮蓋締をケーソン沈設後、簡単かつ確実に取り
外すことは容易ではない。(1) The caisson is large in size and heavy, and it is necessary to utilize the buoyancy of the caisson to pull it out of the dock. For this reason, it is necessary to make the caisson a double-walled structure to obtain a buoyancy chamber, and to increase the buoyancy by temporarily capping the lower end of the casing tube provided on the outer wall of the caisson. However, it is not easy to easily and reliably remove this temporary cover after the caisson has been sunk.
(2) ケーシング管内側と鋼管杭外側の間隙部に充
填するモルタルがケーシング管の下端より漏洩
して水域を汚染するのを防止し、また硬化した
モルタルの強度が低下したりしないようにシー
ルしなければならない。しかしながらシール部
は水底付近等の水中にありシール部の水深が大
きいと、ダイバーによる水中作業は困難をきわ
める。このためダイバー作業が不要なシール方
法が望まれていた。(2) The mortar filled in the gap between the inside of the casing pipe and the outside of the steel pipe pile will be sealed to prevent it from leaking from the bottom end of the casing pipe and contaminating the water area, and to prevent the strength of the hardened mortar from decreasing. There must be. However, the seal portion is underwater, such as near the bottom of the water, and if the seal portion is deep in water, underwater work by divers becomes extremely difficult. For this reason, a sealing method that does not require diver work has been desired.
(3) 地中に埋設した鋼管杭間には数10cmの継目間
隙を生ずる。鋼管杭にて囲つた部分の水底地盤
を掘削するとこの継目間隙部より外側の土砂が
掘削部へとくずれ落ちたり、鋼管杭埋込部の外
側の土砂が水流等により洗掘される。このため
地中にある鋼管杭が水中で露出した状態となり
杭上にあるケーソンを支持するに十分な支持力
が得られなくなるおそれがあつた。そこで、鋼
管杭間の鉛直継目をシールして地下連続壁を作
成する必要があつた。(3) A joint gap of several tens of centimeters is created between the steel pipe piles buried underground. When excavating the underwater ground in the area surrounded by steel pipe piles, the earth and sand outside the joint gap collapses into the excavated area, and the earth and sand outside the part where the steel pipe piles are embedded is scoured by water currents. As a result, the underground steel pipe piles were exposed in the water, and there was a risk that they would not be able to provide sufficient support to support the caissons on the piles. Therefore, it was necessary to create an underground continuous wall by sealing the vertical joints between the steel pipe piles.
従つて、洋上での鋼管継足しケーソン基礎を実
用化するためには、上記のようなケーソン各部の
シール方法を確立する必要がある。 Therefore, in order to put into practical use offshore caisson foundations with additional steel pipes, it is necessary to establish a method for sealing each part of the caisson as described above.
[発明の目的]
本発明は前述した問題のうち、特に鋼管継足し
ケーソン基礎のケーシング管における仮蓋締及び
充填したモルタルの漏洩の問題を解決するために
なされもので、鋼管継足しケーソン基礎を実用化
するための合理的なシール工法、及びシール装置
構造を提供することを目的とし、具体的には下記
事項を目的とする。[Object of the Invention] The present invention has been made to solve the above-mentioned problems, particularly the problems of temporary capping and leakage of filled mortar in the casing pipe of a caisson foundation with a steel pipe addition. The purpose is to provide a rational sealing method and sealing device structure for practical use, and specifically aims to achieve the following points.
(1) ケーシング管下端を一時的に仮蓋締してケー
シング管内を水密にするとともに、この仮蓋締
は水上からの操作で簡単に取り外せる。(1) Temporarily cap the lower end of the casing pipe to make the inside of the casing pipe watertight, and this temporary cap can be easily removed by operation from above the water.
(2) ケーシング管下端において、ケーシング管内
壁とケーシング管内に挿入した鋼管杭の外壁と
の間隙を潜水作業なしでシールし、間隙部に注
入する結合モルタルの漏洩を防止する。(2) At the lower end of the casing pipe, the gap between the inner wall of the casing pipe and the outer wall of the steel pipe pile inserted into the casing pipe is sealed without diving, and the bonding mortar injected into the gap is prevented from leaking.
[発明の概要]
本発明のシール工法は、ケーソンの外側面に添
つて複数の鋼管杭を地中に埋設して地下連続壁を
構築する鋼管継足しケーソン基礎工において、ケ
ーソン外周面に軸線を鉛直方向にした複数のケー
シング管を配列する工程と、給排気用ホース及び
引き抜き用ロープがケーシング管の上端に伸ばさ
れた弾性材料を主体とする気のう体をケーシング
管の下端に嵌め込み、流体注入管がケーソンの上
端に伸ばされた弾性材料を主体とする二重管シー
ル材を気のう体下部のケーシング管内周面に設け
る工程と、気のう体の内部に空気を充満して気の
う体をケーシング管の内周面に密着させる工程
と、ケーソン沈設後又は浮遊状態下で、気のう体
の空気を抜いて該気のう体をケーシング管より引
き抜き、該ケーシング管内に鋼管杭を挿入して該
鋼管杭の下部を地中に埋設する工程と、二重管シ
ール材の内部に流体を充満して二重管シール材を
膨脹させ間隙部を塞ぐ工程と、膨脹した二重管シ
ール材上部のケーシング管と鋼管杭との間隙部に
モルタルを充填して上記ケーシング管と鋼管杭を
結合する工程とを備えたものである。[Summary of the Invention] The seal construction method of the present invention is a method for attaching an axis to the outer circumferential surface of a caisson in steel pipe joint caisson foundation construction in which a plurality of steel pipe piles are buried underground along the outer surface of the caisson to construct an underground continuous wall. The process involves arranging multiple casing pipes in a vertical direction, and inserting an air bladder made of an elastic material into the lower end of the casing pipe, in which a supply/exhaust hose and a pull-out rope are stretched to the upper end of the casing pipe. The injection pipe is stretched to the upper end of the caisson, and a double-pipe sealing material mainly made of an elastic material is provided on the inner circumferential surface of the casing tube at the bottom of the air bladder, and the inside of the air bladder is filled with air. The process involves bringing the air sac into close contact with the inner peripheral surface of the casing pipe, and after the caisson is submerged or in a floating state, the air in the air sac is removed and the air sac is pulled out from the casing pipe, and the steel pipe is inserted into the casing pipe. A process of inserting a pile and burying the lower part of the steel pipe pile in the ground, a process of filling the inside of the double pipe sealing material with fluid and expanding the double pipe sealing material to close the gap, The method includes the step of filling the gap between the casing pipe and the steel pipe pile above the heavy pipe sealing material with mortar to join the casing pipe and the steel pipe pile.
また、本発明のシール装置構造は、ケーソンの
外周面に軸線を鉛直方向にして配列された複数の
ケーシング管下端に弾性材料を主体とする気のう
体が嵌め込まれ、該気のう体に給排気を行うホー
スと該気のう体をケーシング管から引き抜くロー
プとが該気のう体からケーシング管の上端に伸ば
され、気のう体の下側のケーシング管内周面に、
ケーシング管に挿入される鋼管杭を貫通させる弾
性材料を主体とする環状袋体の二重管シール材が
固定され、該二重管シール材に流体を充填する注
入管が該二重管シール材からケーソンの上端に伸
ばされてなる構造としたものである。 Further, in the sealing device structure of the present invention, an air bladder mainly made of an elastic material is fitted into the lower ends of a plurality of casing pipes arranged on the outer peripheral surface of the caisson with their axes in the vertical direction. A hose for air supply and exhaust and a rope for pulling out the air bladder from the casing tube are extended from the air bladder to the upper end of the casing tube, and are attached to the inner peripheral surface of the casing tube below the air bladder.
A double pipe sealing material of an annular bag mainly made of an elastic material is fixed to penetrate a steel pipe pile inserted into a casing pipe, and an injection pipe for filling the double pipe sealing material with fluid is fixed to the double pipe sealing material. The structure extends from the top to the top of the caisson.
[発明の実施例]
第1図は本発明の実施例におけるケーソンの浮
遊状態を示す斜視図である。1は水面、2は水面
1に浮遊するケーソンである。3はケーソン本体
で、二重側壁を有する直方体形状の鋼製型枠であ
る。ケーソン本体3の外周面には4で示すケーシ
ング管が軸線を鉛直方向にして並列に密接して多
数配置してある。5は円柱状の気のう体で、各ケ
ーシング管4の下端に嵌め込まれている。気のう
体5はゴム弾性材料を主体とし布や繊維コード等
の補強層を内蔵し、内部に空気を充満して気のう
体5の外周面をケーシング管4の内周面に密着さ
せている。また、6はゴム弾性材料を主体とする
ドーナツ状袋体のインフレート式二重管シール材
で、気のう体5の下部のケーシング管4の内周面
に固定されている。[Embodiment of the Invention] FIG. 1 is a perspective view showing a floating state of a caisson in an embodiment of the invention. 1 is a water surface, and 2 is a caisson floating on the water surface 1. 3 is the caisson body, which is a rectangular parallelepiped steel formwork with double side walls. On the outer circumferential surface of the caisson body 3, a large number of casing tubes indicated by 4 are arranged closely in parallel with each other with their axes in the vertical direction. Reference numeral 5 denotes a cylindrical air bladder, which is fitted into the lower end of each casing pipe 4. The air bladder 5 is mainly made of a rubber elastic material, has a reinforcing layer such as cloth or fiber cord, and is filled with air so that the outer circumferential surface of the air bladder 5 is brought into close contact with the inner circumferential surface of the casing pipe 4. ing. Further, numeral 6 denotes an inflatable double-tube sealing material having a donut-shaped bag mainly made of a rubber elastic material, and is fixed to the inner circumferential surface of the casing tube 4 at the lower part of the air sac 5.
第2図は第1図のA−A断面図で、気のう体5
と二重管シール材6の構成を示す。3aはケーソ
ン底板で、ケーソン本体3の二重側壁の下端がケ
ーソン底板3aにより連接し、二重側壁内を水密
にして浮力室を得ている。3bはこの浮力室の下
部に充填したコンクリートで、ケーソン2の重心
を低くし、浮遊時の浮体としてのケーソン2の安
定性を得るようにしている。5aは吊金具で気の
う体5の上部に設けられている。吊金具5aには
水面上にあるケーシング管4の上端より垂下した
5bで示すロープと、気のう体5内の給排気を行
なうための5cで示すホースが接続されている。
5dはストツパーであり、ケーシング管4の内周
面に添つて固定した、所定厚さを有する1枚また
は複数に分割した鋼板で、気のう体5の上面に下
端面を接している。6aはスペーサーで、スペー
サー6aの構造寸法はストツパー5dと同様であ
る。スペーサー6aは二重管シール材6の上部と
下部の2個所に設け、少なくとも二重管シール材
6の作動前のつぶれた時の厚さより大きな厚みを
有している。また、ストツパー5d及びスペーサ
ー6aをケーシング管4の内面に固定した部分の
内径は、第3図以降で説明する鋼管杭の外径より
大きくして、ケーシング管4内に鋼管杭を挿入し
た時、鋼管杭がストツパー5dやスペーサー6a
に引つかからない様にする。 Figure 2 is a sectional view taken along line A-A in Figure 1.
and shows the configuration of the double pipe sealing material 6. 3a is a caisson bottom plate, and the lower ends of the double side walls of the caisson body 3 are connected by the caisson bottom plate 3a, making the inside of the double side walls watertight to obtain a buoyancy chamber. 3b is concrete filled in the lower part of this buoyancy chamber, which lowers the center of gravity of the caisson 2 and stabilizes the caisson 2 as a floating body when floating. Reference numeral 5a denotes a hanging fixture, which is provided on the upper part of the air bladder 5. A rope 5b hanging down from the upper end of the casing pipe 4 above the water surface and a hose 5c for supplying and discharging air inside the air bladder 5 are connected to the hanging fitting 5a.
A stopper 5d is a steel plate divided into one or more parts having a predetermined thickness and fixed along the inner peripheral surface of the casing pipe 4, and its lower end surface is in contact with the upper surface of the air bladder 5. 6a is a spacer, and the structural dimensions of the spacer 6a are the same as those of the stopper 5d. The spacers 6a are provided at two locations, at the top and bottom of the double tube sealing material 6, and have a thickness that is at least greater than the thickness of the double tube sealing material 6 when it is collapsed before being activated. Furthermore, the inner diameter of the portion where the stopper 5d and the spacer 6a are fixed to the inner surface of the casing pipe 4 is made larger than the outer diameter of the steel pipe pile described in FIGS. 3 and after, so that when the steel pipe pile is inserted into the casing pipe 4, Steel pipe pile is stopper 5d and spacer 6a
Try not to get caught.
次に、上記ケーソン基礎の施工について説明す
る。例えば、造船所のドツクにおいてケーソン2
を建設してケーソン2を引き出す場合、ドツク内
注水に先だつて各ケーシング管4の下端に気のう
体5を装着充填してケーシング管4内を気密にし
ておけばケーシング管4内も浮力室として機能す
る。このためドツグ内注水を行なつてケーソン2
を水面に浮遊させてドツク外に引き出すことがで
きる。特にケーソン2が大寸法、大重量である場
合は、クレーンの吊能力以上の重量となり、ケー
ソン2の浮力を利用する必要がある。またケーソ
ン2の高さに比しドツク内の水深は浅いので、浮
力を利用する場合はケーソン2の底部で浮力室を
確保する必要がある。この要求を満たすのに、ケ
ーシング管4下端に機のう体5を嵌め込んだ後、
機のう体5に空気を供給してケーシング管4内周
面に密着させることは好都合に作用する。 Next, construction of the caisson foundation will be explained. For example, in a shipyard dock, caisson 2
When constructing a dock and pulling out the caisson 2, if the inside of the casing pipe 4 is made airtight by filling the lower end of each casing pipe 4 with an air bladder 5 before injecting water into the dock, the inside of the casing pipe 4 will also become a buoyancy chamber. functions as For this reason, water was injected into the dog and caisson 2 was installed.
can be floated on the water surface and pulled out of the dock. In particular, when the caisson 2 is large in size and heavy, the weight exceeds the lifting capacity of the crane, and it is necessary to utilize the buoyancy of the caisson 2. Furthermore, since the water depth inside the dock is shallow compared to the height of the caisson 2, it is necessary to secure a buoyancy chamber at the bottom of the caisson 2 when using buoyancy. To meet this requirement, after fitting the machine body 5 to the lower end of the casing pipe 4,
It is advantageous to supply air to the fuselage body 5 and bring it into close contact with the inner peripheral surface of the casing pipe 4.
ドツクより引き出されたケーソン2はタグボー
ト等にて建設地点まで浮遊曳航し、ケーソン2の
浮力室内に注水してケーソン2を水底に沈設す
る。ついで気のう体5内から空気を排出し、気の
う体5を水圧の作用でつぶしてからロープ5bを
巻き上げ、ケーシング管4より気のう体5を引き
抜く。ついでケーシング管4内に鋼管杭を順次建
て込み、杭打ちを行ない地下連続壁を形成する。
この場合、必ずしも上述のようにケーソン2を水
底に沈設させてからでなく、浮遊させた状態のま
まで、ケーシング管4内の気のう体5の撤去と鋼
管杭の打込みを杭毎に順次行なつていく方法もあ
る。 The caisson 2 pulled out from the dock is floated and towed to the construction site by a tug boat, water is poured into the buoyancy chamber of the caisson 2, and the caisson 2 is sunk to the bottom of the water. Then, the air is discharged from the inside of the air sac 5, the air sac 5 is crushed by the action of water pressure, and the rope 5b is wound up to pull out the air sac 5 from the casing pipe 4. Next, steel pipe piles are sequentially built into the casing pipe 4 and pile driving is performed to form an underground continuous wall.
In this case, the air bladder 5 inside the casing pipe 4 is removed and the steel pipe piles are driven one after another, not necessarily after the caisson 2 has been sunk to the bottom of the water as described above, but while it is still floating. There are ways to go about it.
気のう体5の代わりにゴム膜や鋼製蓋をケーシ
ング管4の下端に設けて仮蓋締しても、気のう体
5と同様な浮力室確保は可能である。しかしなが
らケーソン2の曳航後にこれを除去するとき潜水
作業を要するなど容易でなく、かつ確実に行なえ
る保証がない。これに対し、本実施例のように構
成した気のう体5を利用すれば、給排気用ホース
5cや引き抜き用ロープ5bの上端を水面上にま
で導いてあるので、その除去作業を全て水面上で
行なうことができることになる。 Even if a rubber membrane or a steel lid is provided at the lower end of the casing pipe 4 instead of the air bladder 5 and the lid is temporarily tightened, it is possible to secure the same buoyancy chamber as the air bladder 5. However, removing the caisson 2 after it has been towed is not easy as it requires diving, and there is no guarantee that it can be done reliably. On the other hand, if the air bladder 5 configured as in this embodiment is used, the upper ends of the supply/exhaust hose 5c and the pulling rope 5b are guided above the water surface, so all removal work is done on the water surface. This can be done above.
なお、この際気のう体5の下端にも上端に設け
たのと同様の吊金具とロープを設けておき、下側
のロープはケーシング管4外に引き出してから、
ケーシング管4の外面に添つてたくし上げ、水面
上でケーソン2に固定しておく。このようにする
ことにより、空気を排出し収縮した気のう体5が
ケーシング管4内を急速に浮上してくる危険性を
なくすことができ、気のう体5の回収作業の安全
確実性を増すことができる。 At this time, a hanging fitting and a rope similar to those provided at the upper end are provided at the lower end of the air bladder 5, and the lower rope is pulled out of the casing pipe 4, and then
It is rolled up along the outer surface of the casing pipe 4 and fixed to the caisson 2 above the water surface. By doing this, it is possible to eliminate the risk that the air sac 5 that has been deflated by expelling the air will rapidly float up inside the casing pipe 4, thereby increasing the safety and certainty of the recovery work of the air sac 5. can be increased.
第3図はケーソン2を沈設し気のう体5を除去
したケーシング管4内に8で示す鋼管杭を挿入
し、該鋼管杭を7で示す水底の地中に埋設した状
態を示す縦断面図である。なお、ケーシング管4
内に鋼管杭8を挿入して落し込む時には、ストツ
パ5dやスペーサー6aがケーシング管4と鋼管
杭8の偏心を少なくし、またスペーサー6aの間
に装着した流体注入前の二重管シール材6に鋼管
杭8が接触して二重管シール材6を損傷するのを
防止している。 Fig. 3 is a longitudinal section showing a state in which a steel pipe pile indicated by 8 is inserted into the casing pipe 4 from which the caisson 2 has been sunk and the air bladder 5 has been removed, and the steel pipe pile is buried underground at the bottom of the water, indicated by 7. It is a diagram. In addition, the casing pipe 4
When inserting and dropping the steel pipe pile 8 into the interior, the stopper 5d and spacer 6a reduce eccentricity between the casing pipe 4 and the steel pipe pile 8, and the double pipe sealing material 6 installed between the spacers 6a before fluid injection This prevents the steel pipe pile 8 from coming into contact with the double pipe sealing material 6 and damaging the double pipe sealing material 6.
第4図は第3図のB部拡大断面図で、二重管シ
ール材6の作動状態を示している。第4図中、6
cは二重管シール材6の内部に注入した空気、
水、モルタル等の流体で、二重管シール材6がこ
れらにより膨脹させられ、ケーシング管4の内面
と鋼管杭8の外面との間隙部をシールした状態を
示している。6bは鋼管、ゴムホース等の管で、
下端を二重管シール材6に接続し上端を水面上の
ケーソン2の上端に配管してある。6dはケーシ
ング管4の内面と鋼管杭8の外面との間隙部に注
入されたモルタルである。 FIG. 4 is an enlarged sectional view of section B in FIG. 3, showing the operating state of the double pipe sealing material 6. In Figure 4, 6
c is air injected into the inside of the double pipe sealing material 6;
The double pipe sealing material 6 is expanded with fluids such as water and mortar, and the gap between the inner surface of the casing pipe 4 and the outer surface of the steel pipe pile 8 is sealed. 6b is a pipe such as a steel pipe or a rubber hose,
The lower end is connected to a double pipe sealing material 6, and the upper end is piped to the upper end of the caisson 2 above the water surface. 6d is mortar injected into the gap between the inner surface of the casing pipe 4 and the outer surface of the steel pipe pile 8.
ここで、ケーソン2の沈設後の工程を詳細に説
明する。鋼管杭8の下部を地中に埋設した後、二
重管シール材6の内部に流体を注入し膨脹させて
間隙を塞ぐ。このシール作業は、本実施例のよう
に構成した二重管シール材6を利用することで、
水面上に配した注入管6bからモルタルを注入す
るだけで済み、水中作業を不要にしている。 Here, the steps after sinking the caisson 2 will be explained in detail. After the lower part of the steel pipe pile 8 is buried in the ground, fluid is injected into the double pipe sealing material 6 and expanded to close the gap. This sealing work can be done by using the double pipe sealing material 6 configured as in this embodiment.
It is sufficient to simply inject mortar from the injection pipe 6b placed above the water surface, eliminating the need for underwater work.
ついで二重管シール材6の上部の間隙部にモル
タル6dを注入して、ケーシング管4と鋼管杭8
を結合する。この際、二重管シール材6によつて
間隙部に注入したモルタル6dの漏洩が防止され
るので、モルタル6dの結合強度が充分に得られ
ると共に、モルタル6dの流失による水域汚染も
防止できる。 Next, mortar 6d is injected into the gap above the double pipe sealing material 6, and the casing pipe 4 and steel pipe pile 8 are
combine. At this time, since the double pipe sealing material 6 prevents the mortar 6d injected into the gap from leaking, sufficient bonding strength of the mortar 6d can be obtained, and water pollution due to the mortar 6d being washed away can be prevented.
以上の作業後は、鋼管杭8の鉛直継目を鋼管継
目シール材9を用いてシールし地下連続壁を構築
する。 After the above work, the vertical joints of the steel pipe piles 8 are sealed using the steel pipe joint sealing material 9 to construct an underground continuous wall.
[発明の効果]
以上説明したように、本発明は、洋上において
実績のなかつた鋼管継足しケーソン基礎の実用化
を図つたものであり、以下のような効果が得られ
る。[Effects of the Invention] As explained above, the present invention aims to put into practical use a caisson foundation with a steel pipe extension, which has not been used offshore, and provides the following effects.
(1) 本発明の工法によれば、気のう体に空気を満
たしてケーシング管内を水密にし浮力を利用し
てケーソンを浮上させることができ、大寸法、
大重量のケーソンをドツクより容易に引き出す
ことができる。そのうえ、気のう体はケーソン
を所定の位置に沈設後、水面上での操作で簡単
確実に除去できる。(1) According to the construction method of the present invention, it is possible to fill the air sac with air to make the inside of the casing pipe watertight, and to float the caisson using buoyancy.
A heavy caisson can be easily pulled out from the dock. Furthermore, air sacs can be easily and reliably removed by operating the caisson on the water's surface after the caisson has been sunk into place.
(2) 本発明の工法によれば、ケーシング管下端の
ケーシング管内面と鋼管杭外面との間隙部を、
水面上での操作でシールして、モルタルの漏洩
が防止できる。また、ダイバーの作業が不要な
ので大水深におけるシール作業も容易に行え
る。(2) According to the construction method of the present invention, the gap between the inner surface of the casing pipe and the outer surface of the steel pipe pile at the lower end of the casing pipe is
It seals when operated above the water surface to prevent mortar from leaking. In addition, sealing work at great depths can be easily performed as there is no need for divers to perform the work.
(3) 本発明の工法によれば、気のう体の給排気、
気のう体の除去、及び二重管シール材へのモル
タル注入を行う装置を全てケーソンの上部側に
配置することができ、これらの装置の準備、操
作及び撤去等、洋上での鋼管継足しケーソン基
礎の施工システムを効率的、経済的にする。(3) According to the construction method of the present invention, air bladder supply and exhaust,
The equipment for removing air capsules and injecting mortar into the double pipe sealing material can all be placed on the upper side of the caisson, and the preparation, operation, and removal of these equipment can be carried out during offshore steel pipe joining. To make the caisson foundation construction system efficient and economical.
(4) 本発明の装置構造によれば、ケーシング管の
仮蓋締とした気のう体の取り外し、及びケーシ
ング管下端のケーシング管内面と鋼管杭外面と
の間隙部のシール(二重管シール材への流体注
入)が、水面上での操作で行える。(4) According to the device structure of the present invention, it is possible to remove the air sac temporarily closed from the casing pipe, and seal the gap between the inner surface of the casing pipe and the outer surface of the steel pipe pile at the lower end of the casing pipe (double pipe seal). (injection of fluid into the material) can be performed by operating above the water surface.
第1図は本発明の実施例を示すケーソン浮遊状
態の斜視図、第2図は第1図のA−A断面図、第
3図はケーソン沈設状態の縦断面図、第4図は第
3図のB部拡大断面図である。
2……ケーソン、4……ケーシング管、5……
気のう体、6……二重管シール材、8……鋼管
杭。
Fig. 1 is a perspective view of the caisson in a floating state showing an embodiment of the present invention, Fig. 2 is a sectional view taken along the line A-A in Fig. 1, Fig. 3 is a longitudinal sectional view of the caisson in a submerged state, and Fig. 4 is a caisson in a suspended state. It is an enlarged cross-sectional view of part B in the figure. 2...Caisson, 4...Casing pipe, 5...
Air bladder, 6...double pipe sealing material, 8...steel pipe pile.
Claims (1)
中に埋設して地下連続壁を構築する鋼管継足しケ
ーソン基礎工において、 ケーソン外周面に軸線を鉛直方向にした複数の
ケーシング管を配列する工程と、 給排気用ホース及び引き抜き用ロープがケーシ
ング管の上端に伸ばされた弾性材料を主体とする
気のう体をケーシング管の下端に嵌め込み、流体
注入管がケーソンの上端に伸ばされた弾性材料を
主体とする二重管シール材を前記気のう体下部の
ケーシング管内周面に設ける工程と、 前記気のう体の内部に空気を充満して該気のう
体をケーシング管の内周面に密着させる工程と、 ケーソン沈設後又は浮遊状態下で、前記気のう
体の空気を抜いて該気のう体をケーシング管より
引き抜き、該ケーシング管内に鋼管杭を挿入して
該鋼管杭の下部を地中に埋設する工程と、 前記二重管シール材の内部に流体を充満して二
重管シール材を膨脹させ間隙部を塞ぐ工程と、 膨脹した二重管シール材上部のケーシング管と
鋼管杭との間隙部にモルタルを充填して上記ケー
シング管と鋼管杭を結合する工程とを、備えたこ
とを特徴とする鋼管継足しケーソン基礎のケーシ
ング管シール工法。 2 ケーソンの外周面に軸線を鉛直方向にして配
列された複数のケーシング管下端に弾性材料を主
体とする気のう体が嵌め込まれ、該気のう体に給
排気を行うホースと該気のう体をケーシング管か
ら引き抜くロープとが該気のう体からケーシング
管の上端に伸ばされ、 前記気のう体の下側のケーシング管内周面に、
ケーシング管に挿入される鋼管杭を貫通させる弾
性材料を主体とする環状袋体の二重管シール材が
固定され、該二重管シール材に流体を注入する注
入管が該二重管シール材からケーソンの上端に伸
ばされてなることを特徴とする鋼管継足しケーソ
ン基礎のケーシング管シール装置構造。[Scope of Claims] 1. In a steel pipe caisson foundation construction in which a plurality of steel pipe piles are buried in the ground along the outer surface of the caisson to construct an underground continuous wall, a plurality of steel pipe piles whose axes are perpendicular to the outer circumferential surface of the caisson are constructed. A process of arranging the casing pipes of a step of providing a double-pipe sealing material mainly made of an elastic material stretched at the upper end on the inner circumferential surface of the casing tube at the bottom of the air bladder; and filling the inside of the air bladder with air to close the air bladder. After the caisson is submerged or in a floating state, the air in the air sac is removed and the air sac is pulled out from the casing, and a steel pipe pile is inserted into the casing. burying the lower part of the steel pipe pile underground; a step of filling the inside of the double pipe sealing material with a fluid to expand the double pipe sealing material and closing the gap; A casing pipe seal for a caisson foundation with a steel pipe addition, comprising the step of filling the gap between the casing pipe and the steel pipe pile above the heavy pipe sealing material and joining the casing pipe and the steel pipe pile. Construction method. 2 An air bladder mainly made of an elastic material is fitted into the lower end of a plurality of casing pipes arranged on the outer peripheral surface of the caisson with their axes in the vertical direction, and a hose for supplying and exhausting air to the air bladder and a A rope for pulling out the air bladder from the casing tube is extended from the air bladder to the upper end of the casing tube, and a rope is attached to the inner circumferential surface of the casing tube below the air bladder.
A double pipe sealing material of an annular bag body mainly made of an elastic material is fixed to penetrate a steel pipe pile inserted into a casing pipe, and an injection pipe for injecting fluid into the double pipe sealing material is fixed to the double pipe sealing material. A casing pipe sealing device structure of a caisson foundation with a steel pipe connection, characterized by extending from the caisson to the upper end of the caisson.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP17402284A JPS6153919A (en) | 1984-08-23 | 1984-08-23 | Casing pipe sealing method for caisson foundation with steel pipe addition and its sealing device structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP17402284A JPS6153919A (en) | 1984-08-23 | 1984-08-23 | Casing pipe sealing method for caisson foundation with steel pipe addition and its sealing device structure |
Related Child Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP13784391A Division JPH0615773B2 (en) | 1991-06-10 | 1991-06-10 | Steel pipe extension caisson foundation sealing method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPS6153919A JPS6153919A (en) | 1986-03-18 |
| JPH0458527B2 true JPH0458527B2 (en) | 1992-09-17 |
Family
ID=15971269
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP17402284A Granted JPS6153919A (en) | 1984-08-23 | 1984-08-23 | Casing pipe sealing method for caisson foundation with steel pipe addition and its sealing device structure |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JPS6153919A (en) |
Families Citing this family (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102140801A (en) * | 2010-02-02 | 2011-08-03 | 中交二公局第五工程有限公司 | Cofferdam construction method in construction of deepwater pier bearing platform |
| CN104264687A (en) * | 2014-10-09 | 2015-01-07 | 张继红 | Shelling type recyclable soil retaining pile continuous wall and minimally invasive plug construction method thereof |
| CN111485549A (en) * | 2020-04-30 | 2020-08-04 | 广西路建工程集团有限公司 | Rotary drilling and buried drilling treatment method |
| JP7447328B1 (en) * | 2023-03-06 | 2024-03-11 | 日鉄エンジニアリング株式会社 | Construction method of steel pipe piles and steel pipe piles |
-
1984
- 1984-08-23 JP JP17402284A patent/JPS6153919A/en active Granted
Also Published As
| Publication number | Publication date |
|---|---|
| JPS6153919A (en) | 1986-03-18 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US3859806A (en) | Offshore platform | |
| US3314241A (en) | Method and apparatus for use in driving piles | |
| US1060271A (en) | Method of building subaqueous tunnels. | |
| US2612024A (en) | Submarine foundation and method of erecting | |
| GB1585170A (en) | Forming concrete structures for underwater pipelines | |
| JPH07216844A (en) | Underwater frame structure and its construction method | |
| CN116607556B (en) | Flexible anti-scouring method and protection system for offshore wind power foundation in operation and maintenance period | |
| US4081970A (en) | Underwater structure | |
| CN113737834A (en) | Recyclable negative pressure injection type open caisson structure and construction method | |
| US3457728A (en) | Replaceable pile sleeve insert | |
| CN109518674B (en) | Artificial island segment, assembled artificial island and construction method of assembled artificial island | |
| JPH0458527B2 (en) | ||
| US4038830A (en) | Modular geometric offshore structures system | |
| JPH06146305A (en) | Underwater foundation and installation method thereof | |
| US3091937A (en) | Underwater foundation structure and method therefor | |
| JPH09268562A (en) | Dry work method and work box used therefor | |
| JP3533525B2 (en) | Submarine tunnel construction method and box joining device | |
| CN110453704A (en) | A combined cofferdam structure and construction method for large-scale offshore anchorage construction | |
| JPH04339916A (en) | Sealing method for caisson foundations with steel pipe connections | |
| JP3799106B2 (en) | Final joint construction method for submerged boxes | |
| GB2057541A (en) | Building a shaft on a submerged tunnel | |
| JPH05125891A (en) | Large-diameter underground wall, construction method thereof, and pipe digging device | |
| JPS6352193B2 (en) | ||
| JP2599617B2 (en) | Underwater tunnel construction method | |
| JPH0377349B2 (en) |